a report on fewa watershed siltation dams problems and
TRANSCRIPT
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS
AND MITIGATION MEASURES
(KHAHARE DAM, HARPAN DAM, BETINI DAM AND LAURUK DAM)
Study Team Signature
Coordinator Dr. Bishnu Raj Baral, Member, Policy and Planning Commission, Gandaki Province
Member Dr. Anup Gurung, Chief Executive Officer, Lake Conservation and Development Authority, Gandaki Province
Member Er. Sharada Mohan Kafle, Chief Engineer, Pokhara Metropolitan City
Member (Expert)
Er. Mani Raj Dahal, MSc. Hydraulics & River Basin Development (Expert River Hydraulics/Hydropower Components Design); Chief Engineer, Clean Energy Consultants, Kathmandu
Member (Expert)
Mr. Ghan Bdr. Shrestha, MSc. Eng. Geology (Expert Geologist/Watershed Sediment); Geologist, Clean Energy Consultants, Kathmandu
Member Secretary
Mr. Krishna Ghimire; Chief, Soil Conservation and Watershed Management Office, Tanahu, Gandaki Province
Submitted to:
Province Government
Ministry of Industry, Tourism, Forest and Environment Gandaki Province, Pokhara, Nepal
October 2020
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
2
This page has been left blank intentionally
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
3
कामयकायी सायाॊश
पेवातार ऩोखया भहानगयऩालरकाको दक्षऺण-ऩक्षिभी ऺेत्रभा अवक्षथथत नेऩारकै दोस्रो ठूरो तार हो। पेवाताररे जराधाय ऺेत्रवाट आउने ऩानी शदु्धीकयण, ऩनुबययण तथा बण्डायण गनय, काफयन य ववववध ऩौविक ऩदाथयहरूको प्रशोधन गनय, तार ऺेत्रभा यहेका फोटलफरुवा य जनावयहरूराई वासथथान/ऩौविक ऩदाथय उऩरब्ध गयाउने जथता ऩमायवयणीम सेवाहरु प्रदान गनय भहत्त्वऩूणय बलूभका खेरेको हदुा मस ऺेत्रराई अन्तयाविम भहत्वको याभसय ऺेत्र घोषणा गरयएको छ।पेवाताररे लसॊचाई, जरववद्यतु ्य ऩमयटन ववकासभा ऩलन मोगदान ऩरु् माएको छ। ववक्रभ सॊवत २०2९ सारभा तारको दक्षऺण-ऩूवॉ बागभा लनभायण गरयएको फाॉधरे ३२० हेक्टय जलभनभा लसॊचाई गनय य ५०० वकरोवाट ववद्यतु उत्ऩादन गनय भद्दत गयेको छ। त्मथतै, पेवाताररे राखौ आन्तरयक य अन्तयायविम ऩमयटकहरू आकवषयत गयी आम य योजगायीका अवसयहरू लसजयना गनय तथा सभग्रभा ऩोखयाराई नेऩारकै एक गलतशीर य जीवन्त ऩमयटकीम शहयको रुऩभा नेऩार य ववश्व बरय थथावऩत गयाउन उल्रेखनीम बलूभका खेरेको छ।
थथानीम अथयतन्त्रभा ठूरो मोगदान ऩमुायउदै आएको पेवातार ऺेत्रभा ववगत केही दशकदेक्षख बने तारको ददगो व्मवथथाऩनका सन्दबयभा ववलबन्न सभथमाहरु देखा ऩयेका छन।्जथतै, शहयी ऺेत्रफाट ववना प्रशोधन तारभा ऩगु्ने ढरको ऩानी तथा पोहोय तथा वषायतभा भूर सडक हदैु तारभा ऩगु्न ेऩानीरे तार प्रदषुण फढाएको छ।त्मथतै, जराधाय ऺेत्रभा अव्मवक्षथथत रुऩभा गरयने खेलत प्रणारी य सडक लनभायणका कायण बूऺ म हनुे तथा ऩवहयो जाने य ठुरो भात्राभा गेग्रान तथा वारवुा उत्ऩादन बई पेवातार ऩरुयएय तार ऺेत्र ववथतायै खकु्षचचदै गईयहेको छ। नेऩार सयकायरे सन ् २००२ भा वपलनश इन्टयनेशनर डेवरऩभेन्ट एजेन्सी (FINIDA) को सहकामयभा गयेको अध्ममनरे वावषयक १,४२,००० भेविक टन भाटो तारभा ऩगु्ने गयेको जनाएको छ। पेवातारको प्रभखु खोरा हऩयन य सहामक खोराहरु जथतै: खहये, फेलतनी य रौरुक भध्मे खहये खोरारे सफैबन्दा फढी गेग्रान तथा वारवुा ल्माउन ेगदयछ बन ेत्मसऩलछ हऩयन, रौरुक, फेलतनी खोरारे ल्माउन ेगदयछन।् हऩयन खोरारे वगाएय ल्माएको गेग्रान तथा वारवुा/भाटो तारको भखुभा थपु्रन ेय हऩयन खोरारे धाय ऩरयवतयन गने लनमलभत रुऩभा हनुे गदयछ। खोरारे धाय ऩरयवतयन गयेको सभम य तारको फाॉध नवनेको वेराभा तार ऺेत्र उल्रेख्म अलतक्रलभत बएको ऩाईन्छ।ववक्रभ सॊवत २०१३ भा २२,००० योऩनी ऺेत्रपरभा पैलरएको तार ऺेत्र ववक्रभ सॊवत २०64 भा आईऩगु्दा ८,२५६ योऩनीभा खचुचेको ववगतका प्रलतवेदनहरुरे उल्रेख गयेका छन।्मवह गलतभा तार ऺेत्र ऩरुयदै जान े तथा जग्गा अलतक्रभण फढ्दै जान ेहो बने १०० फषयभा तार ऩूणयरुऩभै रोऩ हनु ्सक्न ेववगतका अध्ममनहरुरे उल्रेख गयेका छन।् तसथय, नेऩार सयकाय, प्रदेश सयकाय य ऩोखया भहानगयऩालरकारे पेवातार ऺेत्रको ददगो ववकास य सॊयऺण गने कामयराई उच्च प्राथलभकता ददएका छन।्
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
4
पेवातार सॊयऺण सचवक्षन्ध सवोच्च अदारतको ववक्रभ सचवत २०७६ को पैसराराई भध्मनजय गदै तारभा आउन े गेग्रान तथा वारवुा/भाटोराई तारभा आउन ु ऩूवय नै जचभा गरय तार ऩरुयनवाट जोगाउन ेउद्देश्मरे आलथयक वषय २०७६/०७७ भा ऩोखया भहानगयऩालरका य प्रदेश सयकायको सॊमकु्त रगानीभा चायवटा लसल्टेसन ् फाॉधहरू (खहये, हऩयन, रौरुक य फेलतनी) को लनभायण कामय सचऩन्न बएको लथमो। मद्यवऩ, २०७७ को फषायतको सभमभा खहये य हऩयन खोराभा लनलभयत फाॉधभा उल्रेख्म ऺलत ऩगु्मो य फाॉध वरयऩरयको ऺेत्रभा वाढी ऩथमो। जसरे गदाय, फाॉधको क्षथथयता य ददगोऩन सचफन्धभा प्रश्नहरु उठे। मस अध्ममनको भखु्म उद्देश्म फाॉधभा देक्षखएका सभथमाराई ऩवहचान गने, सचफद्ध जोक्षखभहरूराई कभ गनयका रालग ववकल्ऩ खोज गने य रागत तथा आचदानी आकरन गरय सयकायराई भागयलनदेशन गनुय यहेको छ। मो अध्ममन प्रलतवेदन थथरगत अवरोकन य उऩरब्ध बएका सूचना तथा तथमाॊकहरुको ववश्लषेणको आधायभा तमाय गरयएको छ। प्रलतवेदनभा फाॉधको सॊचारनभा आउन सक्ने जोक्षखभहरु न्मूनीकयण गनय सहमोगी हनुे सॊयचनाहरुको प्रायक्षचबक लडजाईन य रागत अनभुान सभेवटएको छ। त्मथतै, थवुप्रएका गेग्रान तथा वारवुाको आमतन आकरन गरय त्मसभापय त हनु सक्न ेआचदानी य भनुापा सवहतको प्रायक्षचबक आलथयक ववश्लषेण सभेत सभेवटएको छ। मस अध्ममनको भखु्म लनष्कषय तथा सझुाफहरु लनचन अनसुायका छन:्
1= खहये य हऩयन खोराभा ढुॊगाको ऩखायर (Stone Masonry) फाट लनभायण गरयएका फाॉधका सॊयचनाहरु उच्च जोक्षखभभा यहेको य आउन ेवषायतभा थऩ बत्कन सक्ने जोक्षखभ यहेको हदुा वषायत शरुु हनु ुऩवुय नै भभयतसचबाय तथा ऩनु्थथाऩना य सदुृढीकयण गनुयऩने देक्षखन्छ।
2= फेलतनी य रौरुक खोराभा लनलभयत वाधभा २०७७ को वषायतको लसजनभा खासै सभथमा नदेक्षखएको हदुा अवथथा हेरयकन आगाभी वषयहरुभा भभयत सचबाय तथा ऩनु्थथाऩना य सदुृढीकयण गनय सवकन्छ। मद्यवऩ, फेलतनी य रौरुक दवैु वाधको वकनायभा वाढी लनमन्त्रण गनयका लनक्षचत लनलभयत ऩखायरहरुको उचाई मसै वषय फढाउन ुऩने देक्षखन्छ।
3= खहये य हऩयन खोरा फाॉध बक्षत्कन ेसक्न ेजोक्षखभ न्मूनीकयण गनय फाॉधको दवैु लतयको थरोऩभा कॊ वक्रट ज्माकेवटङ्, थरोऩको अन्त्म लतयको बागभा कॊ वक्रटको ऩखायर (कट आप वार), ४.५ लभटयको उचाईवाट खसेको ऩानीको फहाफराई लनथतेज ऩानय फाॉधको तल्रो कट अप वारऩलछ कॊ वक्रटको ऩोखयी (क्षथटलरॊग वेलसन) लनभायण गनुयऩने देक्षखन्छ। त्मथतै, खहये वाधको दवैु वकनायभा लनभायण गरयएको फाढी लनमन्त्रण गने ऩखायरको उचाई फढाउन ुऩने देक्षखन्छ बन ेहऩयन खोरा फाॉधको दामा वकनायभा लनलभयत फाढी लनमन्त्रण गने ऩखायरको उचाई फढाउन ु ऩने देक्षखन्छ।
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
5
4= आकक्षथभक रुऩभा आउन सक्न ेफाढीराई लनमलभत रुऩभा फाॉधको तल्रो बबूागभा प्रवाह गनय तथा गेग्रन लनकाल्न ेसभमभा फाॉधभा जभेको ऩानीराई तकायएय गेग्रान तथा वारवुा लनकाल्न सक्षजरो फनाउन फाॉधको कुनै एक खण्डभा थरइुस गेट लनभायण गनुयऩने देक्षखन्छ।
5= खोरारे ल्माउन े गेग्रान तथा वारवुाको तरुनाभा लथग्राउन े बाग न्मून यहेको छ। मसथय, वषायतको सभमभा गेग्रान तथा वारवुाको लनमलभत उत्खनन नगयेको खण्डभा एक फाढीभा आउन ेगेग्रान तथा वारवुारे ऩलन फाॉधको भालथल्रो बाग ऩयैु बयाउन ेय फाॉधको दईु वकनायावाट ऩानी वावहय प्रवाह बई नोक्सान गयाउने जोक्षखभ देक्षखन्छ। मसथय, फाढी य वेड रेवेर अनगुभन गरय गेग्रान तथा वारवुा उत्खननको कामय लनमलभत गनुयऩने देक्षखन्छ।
6= चायवटै फाॉधका सॊयचनाहरुको भभयत सचबाय तथा ऩनु्थथाऩना य सदुृढीकयणको प्रायक्षचबक रागत सऩुरयवेऺण रागत सवहत करयफ ३६ कयोड ८४ राख अनभुान गरयएको छ। सो भध्मे खहये फाॉधका रालग करयफ १७ कयोड ८८ राख, हऩयन फाॉधका रालग करयफ ८ कयोड ३५ राख, रौरुक फाॉधका रालग करयफ ३ कयोड ६७ राख य फेलतनी फाॉधका रालग करयफ ३ कयोड ५६ राख राग्न ेआकरन गरयएको छ। मस वहसाफरे मसै वषय भभयत सचबाय तथा ऩनु्थथाऩना, य सदुृढीकयण गनय सझुाईएका खहये य हऩयन फाॉधको रालग करयफ २६ कयोड २३ राख राग्न ेअनभुान गरयएको छ।
7= एक ऩटक चाय वटै फाॉध ऺेत्र बरयएको खण्डभा करयफ २ राख ६५ हजाय घन लभटय लगटी, फारवुा तथा अरु रयफय फेड साभग्री थवुप्रने प्रायक्षचबक आकरन गरयएको छ। लफवक्र हनु सक्न ेलगटी य फारवुा भापय त करयफ २० कयोड ७१ राख आचदानी हनुे देक्षखन्छ। कुर आचदानी भध्मे ५० प्रलतशत गेग्रान तथा वारवुा उत्खनन, प्रशोधन तथा भभयत सचबायभा खचय राग्न सक्न ेआकरनको आधायभा करयफ १० कयोड ३३ राख खदु भनुापा हनुे देक्षखन्छ।
8= फाॉधको भभयत सचबाय तथा ऩनु्थथाऩना य सदुृढीकयणको रालग अनभुान गरयएको रागत य ढुॊगा लगट्टी वारवुा भापय त प्राप्त हनुे आचदानी सभेतराई भध्मनजय गरय ववश्लषेण गदाय आलथयक तथा ववक्षिम ऩरयसूचक याम्रो (Project IRR = 16%; Project B/C Ratio = 1.35; Simple Payback= 4.94 Years; Return on Investment = 23%; Investors B/C Ratio = 2.80) देक्षखन्छ। मसथय, मस आमोजनाभा फैंकको रगानी ऩलन आकषयण हनु सक्न ेसाथै थव-रगानी (Equity Investment) ऩलन चाडै उठ्ने देक्षखन्छ।
9= फाॉधको भभयत सचबाय तथा ऩनु्थथाऩना य सदुृढीकयण तथा ढुॊगा, लगट्टी य वारवुा व्मवथथाऩनको रालग ऩवहरो ववकल्ऩको रुऩभा ऩोखया भहानगयऩालरका य प्रदेश सयकायरे सॊमकु्त रुऩभा रगानी गयेको खण्डभा तारको सॊयऺण य ववकासको रालग आवश्मक ऩने उल्रेख्म स्रोत त्मवहफाट
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
6
जटुाउन सवकन े देक्षखन्छ।दोस्रो ववकल्ऩको रुऩभा लनक्षज ऺेत्रराई फाॉधको भभयत सचबाय तथा ऩनु्थथाऩना, ऩनु:लनभायण य सदुृढीकयणका साथ् साथै ढुॊगा, लगट्टी य वारवुा व्मवथथाऩनको ऩलन क्षजचभा ददन ेगरय अगालड फढ्न सवकन्छ।
10= मस प्रायक्षचबक अध्ममनभा प्रथताव गरयएको सॊयचना, रागत य आचदानी ववना ववथततृ टोऩोग्रावपक सवे, साभान्म थथरगत अवरोकन य उऩरब्ध सूचना तथा तथमाॊकको आधायभा गरयएको हदुा फाॉधको भभयत सचबाय तथा ऩनु्थथाऩना, ऩनु:लनभायण य सदुृढीकयणको कामय शरुु गनुय ऩूवय ववथततृ सवे गरय प्रथताववत सॊयचनाहरुको वपल्डभा रेआउट गरय प्रभाणीकयण गने तथा लडजाईन, रागत तथा आचदानी ऩनुयारोकन गनुयऩने हनु्छ। त्मथतै, लनभायण अवलधबय ववऻ तथा राब ग्रावह टोलर भापय त लनमलभत सऩुरयवेऺण गरय गणुथतय लनमभन गनुयऩने देक्षखन्छ।
11= लनभायण गरयएका फाॉधरे ढुॊगा, लगट्टी तथा वारवुा लथग्राउन भद्दत गदयछ बने अलधकाॊश लसल्ट तथा भाटो फगेय हऩयन खोरा हदैु पेवातार गएय लथलग्रन्छ। मसथय, तारभा ऩगु्न ेलसल्ट तथा भाटोको आमतन ववथततृभा आकरन गरय त्मसको व्मवथथाऩनभा ध्मान ददनऩुने आवश्मकता यहेको देक्षखन्छ।
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
7
Executive Summary
Fewa Lake located in the south-western part of the Pokhara Metropolitan City is the second largest
lake of Nepal. The lake has been declared as a Ramsar area of international importance as the lake
area has played an important role in purifying, recharging and storing water; processing carbon and
various nutrients; providing habitat/nutrients to the plants and animals, and providing ecosystem
services as a whole. Fewa Lake has also contributed to irrigation, hydropower, and tourism sector.
The dam, built in the south-eastern part of the lake in Bikram Samvat 2029 BS, has helped to irrigate
320 hectares of land and generate 500 kilowatts of electricity. Similarly, Fewa Lake has played a
significant role in attracting millions of domestic and international tourists, to create income and
employment opportunities, and to establish Pokhara as a dynamic and vibrant touristic city in Nepal
and around the world.
Over the past few decades, the Fewa Lake region, which has been a major contributor to the local
economy, has faced various problems in terms of sustainable management of the lake. The
unorganized farming system and road construction in its catchment have led to erosion and
landslides and production of a significant amount of sediment. The shrinkage of the lake area is
often attributed to the heavy sedimentation production in the catchment. A study conducted by the
Government of Nepal in 2002, in collaboration with the Finnish International Development Agency
(FINIDA), stated that 142,000 metric tons of sediment reaches the lake annually. Among the major
tributaries of Fewa Lake (Khahare, Harpan, Betini, and Lauruk), Khahare brings the highest amount
of sediment which is then followed by Harpan, Lauruk, and Betini. Sediment brought by the Harpan
accumulates at the mouth of the lake and the Harpan River changes its course regularly. In the past,
the lake area encroached significantly when the river changed its course and before the construction
of Fewa dam. Past studies have shown shrinkage of lake area from 22,000 ropani in Bikram Samvat
2013 to 8,256 ropani by Bikram Samvat 2064. The past studies have also pointed out that the lake
could disappear completely in 100 years if this trend continues. The Government of Nepal, the
Province Government, and the Pokhara Metropolitan City have, therefore, given high priority to the
sustainable development and conservation of the Fewa Lake area.
Considering the Supreme Court's decision of Bikram Samvat 2076 regarding the conservation of
Fewa Lake, Pokhara Metropolitan City and the Province government jointly constructed four siltation
dams (Khare, Harpan, Lauruk, and Betini) in 2076/077 in order to help reduce lake sedimentation.
However, during the rainy season of 2077, the dam on the Khahare and Harpan were severely
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
8
damaged and the areas around the dam were flooded. As a result, questions were raised about the
stability and sustainability of the dam. The main objective of this study was to identify the problems
in dams, to suggest alternatives measures that help to reduce the associated risks, to determine
preliminary design and estimate for the suggested measures, and to provide suggestions to the
government. This study report has been prepared based on field observation and analysis of
available information and data. The report includes preliminary design and cost estimates of
structures that will help to minimize the risks involved in the operation of the dam. Similarly, a
preliminary economic/financial analysis has been carried out by approximating the volume of sand
and gravel and the possible income and profit through it. The main conclusion and suggestions of
this study are as follows.
1. The stone masonry dam structures of Harpan Khola and Khahare Khola are at high risks and
may collapse during the next rainy seasons, so maintenance, rehabilitation, and
reinforcement should be done before the onset of the monsoons.
2. The dams built on the Betini and Lauruk have not seen much of a problem in the 2077 rainy
season, so maintenance, rehabilitation, and reinforcement of those dams can be executed
in the following years. However, the walls along both Betini and Lauruk dams should be
heightened to prevent flood overtopping.
3. In order to reduce the risk of breakage of Khahare and Harpan dams, concrete jacketing on
slopes in both sides of the dam, construction of the concrete wall (cut off the wall) at the
end of the slope and, provisioning of stilling basins to dissipate energy of overflowing water
from 4.5 m height dam are highly recommended. Similarly, the height of the flood control
wall constructed on both sides of Khahare dam should be increased while the flood control
wall height on the right bank of Harpan dam should be increased.
4. Sluice gates should be constructed in one sections of the dam to facilitate draining of water
during sediment mining works and to release floods during emergency.
5. The siltation area is very small as compared to the volume of sand and gravel that the
stream brings. Therefore, if regular excavation of sediment is not done during the rainy
season, there is a risk of the complete filling even during one flood period and flood
overtopping from flood control walls. It is therefore necessary to regularly monitor flood
and bed levels, and carry mining works.
6. The initial investment for the maintenance, rehabilitation and strengthening along with
primary supervision of the structures of all the four dams is estimated at around NRs. 368.4
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
9
million. Out of this, it is estimated that it will cost around NRs 178.8 million for Khahare
Dam, Rs 83.5 million for Harpan Dam, Rs 36.7 million for Lauruk Dam, and Rs 35.60 million
for Betini Dam. For the Khahare and Harpan dams alone, NRs. 262.3 million will be required
for the maintenance, rehabilitation and strengthening.
7. Once the four dams are filled, about 265,000 cubic meters of gravel, sand, and other river
bed material will accumulate. It is approximated that the deposited material could generate
around NRs. 207.1 million of gross revenue through the sale of the deposited gravel and
sand. The net benefit that could be obtained through the sale of deposited material (while
assuming 50 percent of the gross income be spent on the excavation of material, processing
them, and maintenance) is estimated to be around 103.3 million.
8. The economic and financial analysis considering the estimated cost for maintenance,
rehabilitation and strengthening of the dam and the potential revenue generation through
the sale of deposited material indicators reveals very good economic and financial
indicators (Project IRR = 16%; Project B/C Ratio = 1.35; Simple Payback= 4.94 Years; Return
on Investment = 23%; Investors B/C Ratio = 2.80). These economic and financial indicators
clearly imply that investment of bank could also be attracted and quick return on equity
investment is also possible.
9. If the Pokhara Metropolitan City and the province government jointly invest in the
maintenance, rehabilitation, strengthening of dams and management of deposited
material, significant resources required for the conservation and development of the Fewa
Lake could be generated from it. As a second alternative, the private sector can be
entrusted with the maintenance and rehabilitation, and strengthening of the dam as well as
the management of deposited material.
10. The proposed mitigation measures, cost and profit from this study are based on site
observation without any detail topographic survey and, available primary and secondary
reports and data. Therefore, before the construction, it should follow the detailed survey,
layout of proposed structures on the field, and updating of construction cost, income and
profit. Similarly, the quality construction work should be monitored closely through regular
supervision of experts and beneficiary stakeholders during the construction period.
11. The siltation dams help to retain gravel-sand categories sediment while still allowing silt
and mud to flow into Fewa Lake through Harpan Khola. It is therefore strongly
recommended to assess the volume of silt and mud reaching the lake in detail and pay
attention to its long-term management.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
10
Table of Contents
कामयकायी सायाॊश ............................................................................................................................ 3
Executive Summary ...................................................................................................................... 7
List of Tables .............................................................................................................................. 12
List of Figures ............................................................................................................................. 13
Chapter 1: Introduction .............................................................................................................. 15
1.1 Background ........................................................................................................................... 15
1.2 Objectives and Scope of Work .............................................................................................. 16
1.3 Methodology ......................................................................................................................... 17
1.4 Structure of the Report ......................................................................................................... 18
Chapter 2: Status Review and Mitigation Measures .................................................................... 19
2.1 Introduction .......................................................................................................................... 19
2.2 Geology of Fewa Lake Watershed ........................................................................................ 20
2.3 Mass movements and erosions ............................................................................................ 21
2.4 River Geomorphology ........................................................................................................... 22
Braided Channel ............................................................................................................ 22 2.4.1
Meandering Channels ................................................................................................... 23 2.4.2
Mouth/Delta formation ................................................................................................ 23 2.4.3
2.5 Khahare Khola Siltation Dam ................................................................................................ 24
Salient Feature .............................................................................................................. 24 2.5.1
Problem and Mitigation Measures ............................................................................... 26 2.5.2
Properties of Deposited Material ................................................................................. 32 2.5.3
2.6 Harpan Khola Siltation Dam .................................................................................................. 33
Salient Features ............................................................................................................. 33 2.6.1
Problem and Mitigation Measures ............................................................................... 34 2.6.2
Properties of Deposited Material ................................................................................. 41 2.6.3
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
11
2.7 Lauruk Khola Siltation Dam ................................................................................................... 42
Salient Features ............................................................................................................. 42 2.7.1
Problems and Mitigation Measures .............................................................................. 42 2.7.2
Properties of Deposited Material ................................................................................. 45 2.7.3
2.8 Betini Siltation Dam .............................................................................................................. 46
Salient Features ............................................................................................................. 46 2.8.1
Problems and Mitigation Measures .............................................................................. 46 2.8.2
Properties of Deposited Material ................................................................................. 49 2.8.3
Chapter 3: Typical Design and Estimate of Risk Mitigation Facilities ............................................. 51
3.1 Design Parameters ................................................................................................................ 51
3.2 Retrofitting Option for Khahare Siltation Dam ..................................................................... 51
3.3 Retrofitting Option for Harpan Khola Dam ........................................................................... 55
3.4 Lauruk Dam ........................................................................................................................... 57
3.5 Betini Dam ............................................................................................................................. 59
3.6 Summary Cost for Retrofitting Option .................................................................................. 61
Chapter 4: Management, Operation and Maintenance Plan ........................................................ 63
4.1 Revenue potential from construction material .................................................................... 63
4.2 Sample financial analysis ...................................................................................................... 64
4.3 Finding and Remarks ............................................................................................................. 67
Chapter 5: Conclusion and Recommendations ............................................................................ 69
5.1 Conclusion ............................................................................................................................. 69
5.2 Recommendations ................................................................................................................ 70
Annexes..................................................................................................................................... 71
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
12
List of Tables
Table 2-1: Catchment Area, 100 Years Flood, Siltation dam width, specific discharge and sediment
load at the siltation dam. ..................................................................................................................... 19
Table 2-2: Technical problem with the planning, design, construction and operation of Khahare
Siltation Dam (Khahare dam). ............................................................................................................. 26
Table 2-3: Lithology and usefulness of deposited material in Khahare siltation dam....................... 32
Table 2-4: Technical concerns on planning, design, construction, operational issues and mitigation
measures (Harpan dam) ....................................................................................................................... 34
Table 2-5: Lithology and usefulness of deposited material in Harpan siltation dam. ....................... 41
Table 2-6: Technical concerns on planning, design, construction, operational issues and mitigation
measures (Lauruk dam)........................................................................................................................ 43
Table 2-7: Lithology and usefulness of deposited material in Lauruk siltation dam. ........................ 45
Table 2-8: Technical concerns on planning, design, construction, operational issues and mitigation
measures (Betini dam). ........................................................................................................................ 46
Table 2-9: Lithology and usefulness of deposited material in Lauruk siltation dam. ........................ 49
Table 3-1: Technical design parameters for the assessment of dam planning and design ............... 51
Table 3-2: Different components of retrofitting option for Khahare siltation dam. ......................... 53
Table 3-3: Different components of retrofitting option for Khahare siltation dam. ......................... 56
Table 3-4: Different components of retrofitting option for Lauruk siltation dam. ............................ 58
Table 3-5: Different components of retrofitting option for Betini siltation dam. ............................. 60
Table 3-6: Summary cost estimate of the suggested retrofitting option for four siltation dam. ...... 61
Table 4-1: Sediment load in Khahare, Harpan, Lauruk and Betini (GoN/UNDP report based data). 63
Table 4-2: Deposited approximate volume of sediment load in 2020 monsoon season. ................. 63
Table 4-3: Revenue generation from deposited sediment during 2020 monsoon season. ............... 64
Table 4-4: Financial parameter for analysis ........................................................................................ 65
Table 4-5: Projected Cash Flow Analysis for Economic model ........................................................... 65
Table 4-6: Investor CASH FLOWS Statement for Financial Model ...................................................... 66
Table 4-7: Financial analysis results..................................................................................................... 67
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
13
List of Figures
Figure 2-1: Location of 4 dams U/S of Fewa Lake in its catchments for sedimentation control. ...... 19
Figure 2-2: Engineering geological map of Pokhara Area. .................................................................. 20
Figure 2-3: Active landslides distributions Khahare Khola sub-watershed ........................................ 21
Figure 2-4: Brained channels at the lower reaches ............................................................................. 22
Figure 2-5: Meandering channels of the Harpan khola ...................................................................... 23
Figure 2-6: Mouth or Delta of the Fewa lake ...................................................................................... 24
Figure 2-7: Location of Khahare Dam and river training works. ......................................................... 25
Figure 2-8: A typical section of existing Khahare siltation dam. ........................................................ 25
Figure 2-9: Khahare Siltation Dam on August 2020 ............................................................................ 30
Figure 2-10: Khahare Siltation Dam on September 18, 2020.............................................................. 30
Figure 2-11: Breech of right embankment after filling the dam and changed river course .............. 31
Figure 2-12: The most suitable location for construction of siltation dam (1 km upstream of present
dam location). ...................................................................................................................................... 31
Figure 2-13: A typical section of existing Harpan siltation dam. ........................................................ 33
Figure 2-14: Harpan Dam on Aug 2020 ................................................................................................ 37
Figure 2-15: Harpan dam having proximity to good access road at pre-inspection visit Aug 2020 .. 37
Figure 2-16: Overtopping from left side flood wall near dam due to skewed planform. .................. 38
Figure 2-17: Damaging pattern on the D/S glacis and even some part is taken away at middle...... 38
Figure 2-18: Bank cutting beyond left flood wall by overtopping the wall ........................................ 39
Figure 2-19: Site visit team for assessment of siltation dams on Harpan Dam left bank .................. 39
Figure 2-20: Scouring of toe of dam. ................................................................................................... 40
Figure 2-21: Scouring of toe of flood wall and channel degradation downstream. .......................... 40
Figure 2-22: Lauruk Khola Siltation dam which relatively in better condition as compared to the
Khahare and Harpan dam. ................................................................................................................... 44
Figure 2-23: Catchment and location of Lauruk dam. ......................................................................... 44
Figure 2-24: Relatively better condition of the dam but the river gradient is still high .................... 47
Figure 2-25: The chance of overtopping from just u/s of the dam (View from Upstream) ............... 48
Figure 2-26: Fully deposited dam and overtopping from left bank (View from D/S) ........................ 48
Figure 2-27: U/s reach of the dam showing flood control gabion walls on both bank and road,
houses at the left bank. ....................................................................................................................... 49
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
14
Figure 3-1: Khahare Dam layout and its components/Facilities ......................................................... 52
Figure 3-2: Typical section of Khahare dam (existing situation-top) and (suggested retrofitting
option-bottom) ..................................................................................................................................... 53
Figure 3-3: Under sluice plan and section proposed at the dam edge for water level control. ........ 54
Figure 3-4: Harpan Dam layout and its components/Facilities (retrofitting option) ......................... 55
Figure 3-5: Typical section of Harpan dam (suggested retrofitting option). ...................................... 56
Figure 3-6: Lauruk Dam layout and its components/Facilities (retrofitting option) .......................... 57
Figure 3-7: Typical section of Lauruk dam (suggested retrofitting option). ....................................... 58
Figure 3-8: Betini Dam layout and its components/Facilities (retrofitting option) ........................... 59
Figure 3-9: Typical section of Betini dam (suggested retrofitting option). ........................................ 60
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
15
1. Chapter 1: Introduction
1.1 Background
The Fewa Lake, second largest Lake of Nepal, is located in the south-western region of Pokhara
Metropolitan City in Gandaki province. The lake has been declared as Ramsar site -- as its wetlands
help in water purification, water storage, processing of carbon and other nutrients, support
hundreds of plants and animals, and provide ecosystem services as a whole. It has contributed in
irrigation, hydropower and tourism development. The dam constructed in the south eastern part of
the lake in 2029 BS has helped to irrigate 320 hectares of land and to produce 500 kilowatts of
electricity. The lake has also helped to establish Pokhara as one of the most vibrant tourism cities of
Nepal by attracting thousands of domestic and international tourists and, thereby, creating income
and employment opportunities.
While the Fewa Lake has significantly contributed to the local economy, some management and
conservation issues has also arisen since the last few decades. Direct feeding of municipal sewerage
and storm water into the lake has degraded the lake water quality. The soil erosion and landslides
caused by the haphazard construction of roads together with the imprudent land use in its
catchment has accelerated lake sedimentation and loss of lake water surface area. A study
conducted by Nepal Government in collaboration with the Finnish International Development
Agency (FINNIDA) in 1992 has estimated 142,000 metric tons of sediment deposition every year. The
major tributaries of the Fewa Lake are Harphan Khola, Khahare Khola, Betini Khola and Lauruk Khola.
The Khahare Khola is the main tributary carrying highest sediment which is then followed by Harpan,
Lauruk, Betini. The Harpan Khola reaches just after the Harpan-Betini confluence has a typical
meandering morphology (cut off generation and shifting of its channel regularly). In this reach, the
Harpan Khola flows in single meander channel and piles sediment at the mouth of the lake delta. The
cut off generation process in meandering channel and the deposition process at the delta play a
major role in shifting the Harpan Khola and formation of the dry abandoned aggraded area near the
lake delta. In the past, some of the abounded channel area has been encroached and registered by
the public leading to significant loss of the Fewa Lake area. Noticeably, the 22,000 ropani of the lake
area in 2013 BS has gradually shrunk to 8,256 ropani in 2064 BS. It has been projected that if the
trend of lake sedimentation and land encroachment continues, the lake may be completely
disappeared in the next 100 years (Study Report on investigation of encroached land on Fewa Lake,
2069 BS).
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
16
In the fiscal year 2076/077, the Pokhara Metropolitan City and the Province government jointly
constructed four stone masonry siltation dams (Khahare Khola, Harpan Khola, Lauruk Khola, and
Bitini Khola) to retain sediment and help reduction of lake sedimentation. During the 2077 monsoon,
however, the downstream slope of the stone masonry wall on Khahare and Harpan Khola were
severely damaged, raising question about the stability of the dam and its long-term functioning. The
Minister for Industry, Tourism, Forest and Environment and the Mayor of the Pokhara Metropolitan
City, therefore, jointly formed a study team composed of six members in 2077/05/21 BS to identify
problems and suggest the mitigation measures to reduce the associated risks. The composition of
the study team was as follows:
Composition of Study Team
Coordinator Dr. Bishnu Raj Baral, Member, Policy and Planning Commission, Gandaki Province
Member Dr. Anup Gurung, Chief Executive Officer, Lake Conservation and Development Authority, Gandaki Province
Member Er. Sharada Mohan Kafle, Chief Engineer, Pokhara Metropolitan City Office
Member
(Expert)
Er. Mani Raj Dahal, MSc. Hydraulics & River Basin Development (Expert River Hydraulics/Hydropower Components Design); Chief Engineer, Clean Energy Consultants, Kathmandu
Member
(Expert)
Mr. Ghan Bdr. Shrestha, MSc. Eng. Geology (Expert Geologist/Watershed Sediment); Geologist, Clean Energy Consultants, Kathmandu
Member Secretary Mr. Krishna Ghimire Chief, Soil Conservation and Watershed Management Office, Tanahu, Gandaki Province
1.2 Objectives and Scope of Work
The main objective of the study was to identify problems of siltation dams and suggest alternative
solutions in the prevention of further damages. The specific objectives of the study were:
1. To review design and identify technical and managerial problems associated with the
siltation dams.
2. To suggest alternative solution to minimize further damaging of siltation dams and suggest
effective operation strategies.
3. To carry preliminary design and prepare drawing and cost estimate for the suggested
mitigation measures.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
17
In order to achieve the main and specific objectives, the scopes of work for the study were as follow:
Review previous study reports and construction details of the siltation dam.
Carry field visit of four siltation dams and identify their status.
Identify technical problems in design and construction of dams.
Find the management problems associated with the siltation dam.
Suggest mitigation measures and classify short-term, mid-term and long-term plan to reduce
lake sedimentation.
Design, prepare drawing, and estimate cost for the mitigation measures.
Prepare a report and present the main content of the report to related stakeholders.
Prepare the final report incorporating suggestions from stakeholders.
1.3 Methodology
The following works were carried out to produce the study report:
The problems in the siltation dam and methodology for this study were discussed among the
team members.
Historical studies and available documents were reviewed.
Site visit of four siltation dam was carried out by the study team together with the minister
for Industry, Tourism, Forest and Environment.
Preliminary findings of field observation were presented to stakeholders (Chief Minister,
Minister, Mayor and Government Officials).
The root cause of the problem was identified and previous design was reviewed.
Technical problems associated to design of the siltation dams and their operations were
identified.
Necessary repair and corrective measures for effective and safe operation of siltation dam
were identified.
Alternative solutions to manage sediment trapped by the dams were discussed.
Hydraulic and structural design of the suggested alternative solution was carried out.
Typical drawing was prepared for the suggested design.
Quantity calculation and cost estimate was carried out based on the current district rate.
Economic and financial analysis of the sediment management project was carried out by
approximating market value of sediment and the cost of the suggested retrofitting
measures.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
18
Report writing was carried by incorporating all above works to produce the final report.
1.4 Structure of the Report
The content of the study report has been structured in six chapters as follow:
Chapter 1: Introduction
Chapter 2: Status Review and Mitigation Measures
Chapter 3: Typical Design and Estimate of Risk Mitigation Facilities
Chapter 4: Management, Operation and Maintenance Plan
Chapter 5: Conclusion and Recommendations
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
19
2. Chapter 2: Status Review and Mitigation Measures
2.1 Introduction
The major tributaries of feeding discharge and sediment into the Fewa Lake are Harphan Khola,
Khahare Khola, Betini Khola and Lauruk Khola. The catchment areas at Harpan, Khahare, Betini and
Lauruk siltation dam are 35.7 sq km, 25.3 sq km, 7.1 sq km, and 4.5 sq km, respectively (Figure 2-1).
Figure 2-1: Location of 4 dams U/S of Fewa Lake in its catchments for sedimentation control.
The 100 years flood at the Khahare, Harphan, Lauruk and Betini dam have been estimated at 66
m3/s, 87 m3/s, 17 m3/s and 24 m3/s, respectively. The Khahare Khola brings highest volume of
sediment which is then followed by Harpan Khola, Betini and Lauruk (Table 2-1).
Table 2-1: Catchment Area, 100 Years Flood, Siltation dam width, specific discharge and sediment
load at the siltation dam.
SN Dam
Catchment Area
(Sq. Km)
Flood
Q100 yr
(m3/s)
Dam
Width
(m)
Discharge per meter
(m2/s)
Sediment Estimated *
(Metric Ton)
1 Khahare 25.3 66 100 0.66 238000
2 Harpan 35.7 87 90 0.97 143000
3 Lauruk 4.5 17 40 0.43 Small
4 Betini 7.1 24 40 0.60 Negligible
Note: * the sediment data presented here are based on rough approximation. No detail analysis has been carried out.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
20
2.2 Geology of Fewa Lake Watershed
The Pokhara has Quaternary deposits around the valley (Yamanaka, et. al., 1982). The area
comprises of Kuncha Formation and Fogfog Quartzite of the Lesser Himalayan Rock Sequences and
over lined by the Quaternary deposits of Residual Soils, Colluvial Soils, and Alluvial Fan Deposits
(Engineering and Environmental Geological map of Pokhara, scale 1:50 000, DMG, GON, 1998).
Figure 2-2: Engineering geological map of Pokhara Area.
The followings are formation around Pokhara Valley and at the catchment of Fewa Lake
Residual soils (srs): The residual soils (Loamy to sandy gravel) are distributed on the hill slopes of
Fewa Lake watershed. The thickness of the soils varies between 1 to 5 m deep on average.
Colluvial soils (sco): The colluvial inhomogeneous deposits (silt and sand with boulders on top) are
found at the lower reaches of the watersheds at foot slopes. The thickness of the soil is greater than
1 m.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
21
Nonactive (nf) alluvial fan: These types of the deposits are poorly sorted gravels, sandy, gravel, sand
and silt, fine material towards margin and the thickness generally increases towards centre of the
fan.
Fogfog Quartzite: It consists of fine-grained, massive, quartzite, but bedded in upper part,
intercalated of green phyllite and basic rocks at places. Mostly the sub-watershed of the Harpan
Khola covered with white, massive, bedded, quartzite, as results the 90% of boulders observed at
Ghatichina area are Quartzites.
Kuncha Formation: The formations composed of gritty phyllites, and quartzite, interbed and are very
soft rock mass as well as moderately to deeply weathered and thick colluvium deposits. Mostly the
sub-watersheds of the Khahare, Betini and Lauruk cover with sort rock mass and forming deep soil
profiles.
2.3 Mass movements and erosions
The slope of the Fewa Lake watershed is unstable. There are numbers of old slides and intensive,
gully erosions problems. Some old landsides are still active and some are dormant types. Few slides
are very large in size. The mechanisms of the failures are translations, spreads/creeps, complex, and
channelized flow. The wetness of the failed material is moist to very wet and the rate of the
movements is slow to rapid.
Figure 2-3: Active landslides distributions Khahare Khola sub-watershed
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
22
There are 32 active landslides in Khahare sub-watershed. The largest active landslide in Khahare sub-
watershed is about 0.12 km2 areas. These slope instabilities, landslides, gully erosions, and channel
flows contributes to production of huge amount of the sediments.
2.4 River Geomorphology
The upper reaches of the watersheds have dendric and sub parallel drainage patterns. The stream
channel continuously shape and reform their channels through erosion of the channel boundary:
bed and banks and reworking of sediments.
Braided Channel 2.4.1
After the sloped hill, the Harpan Khola, Khahare, Betini and Lauruk enter into the gentle wider plain
where the river channels become braided (see at Ghatchhina, Bhadure, Bhidabari up to Pame area
for braided reach). The braided reach are capable of transporting sediment across wide range of
flows which leading to high rate of bed turnover and production of temporally diverse mosaic of bars
and channels. The braided reach has ready source of easily available aggregate that is economically
prized.
Figure 2-4: Brained channels at the lower reaches
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
23
Meandering Channels 2.4.2
After the braided reach, the Harpan Khola morphology resembles meandering morphology (see the
reach downstream of Pame area). Meandering streams develop in relatively flat areas, such as a
floodplain, and where sediment consists primarily of fine sands, silts, and clay.
Figure 2-5: Meandering channels of the Harpan khola
Mouth/Delta formation 2.4.3
At the lake mouth/delta, the Harpan Khola Plunge into the lake. Fine sand and silts are deposited at
the mouth whereas the suspended sediments are deposited into the lake.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
24
Figure 2-6: Mouth or Delta of the Fewa lake
2.5 Khahare Khola Siltation Dam
Salient Feature 2.5.1
The Khahare khola reach near the dam area has 2 % longitudinal slope. The width of Khahare Khola
varies from 80 m to 316 m. The overall morphology of the reach resembles with the braided
morphology (Multichannel River). The salient features of the dam and flood protection structure on
the Khahare Khola are as follows:
• Planform: U shape
• Flow length : 100 m
• Left flood wall length : 100 m
• Right wing wall length: 100 m
• Top width of dam : 0.5 m
• Bottom width of dam: 7 m
• Height of dam : 4-4.5 m
• Downstream gabion apron width : 10 m (to protect d/s erosion)
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
25
• Upstream right embankment: 300 m (starting the dam section to upstream)
The location of Khahare siltation dam and other structure has been shown in Figure 2-7.
Figure 2-7: Location of Khahare Dam and river training works.
A typical longitudinal section of the siltation dam constructed on the Khahare Khola has been shown
in Figure 2-8. The dam composed of a simple stone masonry trapezoidal wall together with a gabion
launching apron at the downstream. The height of the dam at the right corner is 4 m which gradually
increases to 4.5 m at the left corner.
Figure 2-8: A typical section of existing Khahare siltation dam.
Siltation Dam
Right flood wall
Right flood Wall
Left flood Wall
Stone Masonry Wall
Gabion Launching Apron
u/s
d/s
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
26
Problem and Mitigation Measures 2.5.2
The problems associated to the Khahare siltation dam were overtopping of right embankment and
river course change, scouring of dam toe, scouring of downstream slope of the dam, complete filling
of the dam/no sediment mining. Overtopping of the right embankment can be attributed to the
inappropriate location of the siltation dam, unfavorable geological and topographic condition and
excessive sediment retention/river bed aggradation. Scouring of dam toe can be attributed to
inappropriate design of dam structure without the provision of cut off and energy dissipation
structure that are requisite in dam construction (cf. most of the dam constructed in run river
hydropower projects consider low height (1-2 m) weir structure with provision of cut off and energy
dissipation structure). The scouring of the downstream slope of the dam can be attributed to the
excessive slope of the dam and uneven dam height (4 m at the right side and 4.5 m at the left side).
Due to the uneven dam height, most of flood discharges were concentrated to the right corner of
the dam. The high slope of the downstream face, without having hard stone/concrete lining, could
not resist the force of high current leading to stability problems and erosion. The dam was filled by
2-3 floods of the season but sediment mining was not carried out which led to excessive bed level
aggradation and overtopping.
The issues wise analysis of problems and their mitigation measures has been summarized in the
Table 2-2. The pictures taken during different site visit have been shown in the Figure 2-9, 2-10,2-11
and 2-12 to provide insights about the site condition.
Table 2-2: Technical problem with the planning, design, construction and operation of Khahare Siltation Dam (Khahare dam).
Technical
Concern
Provided Feature/
Present Situation
Operational /Safety
Issues
Precautions/Mitigation
Measures
1. Location
of
siltation
dam
The siltation dam was
constructed at the
left side of the flood
plain restricting the
river into narrow
width.
The flood level
analysis considering
the construction of
the siltation dam and
other river training
embankment were
There is possibility of
river course change
as the river can
overflow and scour
right embankment
due to rapid bed
aggradation
upstream.
The geological and
topographic
condition around the
dam is such that the
Construct higher and
stronger embankment
on right bank of the
dam with cutoff
If possible relocate the
dam on better location
i.e 1 km upstream of
current location having
rocky right bank and
favourable geological
and topographic
condition
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
27
Technical
Concern
Provided Feature/
Present Situation
Operational /Safety
Issues
Precautions/Mitigation
Measures
not carried out. flood has tendency to
directly hit the right
embankment
2. Retention
of
sediment
without
removal
plan
No road access for
gravel mining and
transporting vehicle
into the dam
Upstream deposit
area.
No provision of
emergency flood
regulating gates.
No provision for
draining water from
dam which may be
required while
mining the deposit.
No plan for
monitoring of flood,
sediment and bed
level.
Without the event
based sediment
removal plan the
siltation dam could
not function
properly.
If sediment is not
removed regularly,
there is always
tendency of sudden
deposition,
overtopping and
flooding the
surrounding lands.
Construct a ramp to
U/S of the dam to
facilitate mining from
inside and transport.
Construct a sluice gate
at the dam edge to
regulate flood in the
case of emergency and
to drain the water
while mining gravel.
3. Retention
volume
There are numbers of
active slides in the
catchment and can
deliver more than
expected sediment
episodically.
The dam could be
filled even by a flood
event leading to
overflow from the
embankment and
flooding in the
surrounding land.
Construct series of
check dams just
upstream of the dam
to retain most of the
course gravel and use
the dam for retaining
finer material.
4. Design of
main dam
The dam consists of
stone masonry wall
having high slope
(1.2:1) at d/s as well
as u/s glacis.
The dam height is
uneven (4 m at the
right side and 4.5
meter at the left
side).
Uneven dam height
hinders uniform
distribution of flow
over weir
concentrating
discharge on the
right corner of the
dam.
High downstream
slope of the dam
produces high
current on the wall
Flatten D/S slope of
the dam as much as
possible and install
energy dissipating
structure.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
28
Technical
Concern
Provided Feature/
Present Situation
Operational /Safety
Issues
Precautions/Mitigation
Measures
which the stone
masonry could not
resist.
Downstream slope
erosion and tow
erosion not avoidable
at the current
situation due to high
current.
5. Dam body
material
selection
and safety
The dam was
constructed using
stone masonry and
plum concrete
Erosion of
downstream face of
the dam is
unavoidable at the
current situation as
the stone masonry
wall is not enough to
resist the eroding
force of water
flowing through the
high slope
Concrete jacketing
could improve stability
and hard and dressed
stone Lining could help
controlling of surface
erosion
6. Absence
of U/S
and D/S
Cutoff
The 4-4.5 m height
stone masonry dam
has been built
without any cut-offs
Due to the absence
cut-offs there is
possibility of piping
and increase seepage
from base
Extend the concrete
jacket deeper to U/S
and D/S cutoff.
7. Energy
dissipatio
n
structure
missing at
the d/s
Most of the gabion
blocks laid at the
base were damaged
There was no energy
dissipation structure
at the d/s
The gabion laid at the
D/S bottom is not
competent to resist
scouring and to
dissipate energy
Construct a stilling
basin with depressed
flood and plunge in the
pool for energy
dissipation for dam
overflow discharge.
8. Flood wall
(embank
ment
wall) on
right bank
Earthen, stone
masonry and gabion
structure is reported
at the right
embankment
The coverage length
and type of structure
is not suitable for
protection
Construct
concrete/stone
masonry wall having
cut off at the bottom
considering 100 years
flood and 2 m free
board.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
29
Technical
Concern
Provided Feature/
Present Situation
Operational /Safety
Issues
Precautions/Mitigation
Measures
9. Flood
Regulatio
n
There is no any
provision of
emergency sluice
gate for the case of
emergency flood
regulation and
draining of water
while mining
There will be
problem on mining
material having high
water level for
control during
removal of material
One side can have
sluice gate which will
reduce water level u/s
making the channel
water level down so
that the mining shall
be possible; the sluice
gate could also be
used to regulate
emergency flood.
10. Additional
boulder/
debris
retention
check
dam
No any check dams
just upstream of the
dam that could have
retained sediment
The present dam
area may not be
sufficient enough to
trap the sediment
load
Construction of series
of temporary check
dams just upstream of
the dam can help
retaining sediment
load before entering
into the dam (course
gravel could be
retained by the check
dam and the main dam
could be used for fine-
course gravel
trapping).
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
30
Figure 2-9: Khahare Siltation Dam on August 2020
Figure 2-10: Khahare Siltation Dam on September 18, 2020
Concentration of discharge on the right corner of the dam due to uneven construction of the dam height
Overtopping location
Damaged downstream slope of the siltation dam
(middle of dam to right corner)
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
31
Figure 2-11: Breech of right embankment after filling the dam and changed river course
Figure 2-12: The most suitable location for construction of siltation dam (1 km upstream of present
dam location).
Upstream of the dam completely filled with sediment
Changed River Course
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
32
Properties of Deposited Material 2.5.3
The field observations suggest that the material deposited in Khahare siltation dam are very good to
use as constructions aggregates. The lithology and usefulness of deposited material in Khahare
siltation dam has been summarized in the Table 2-3.
Table 2-3: Lithology and usefulness of deposited material in Khahare siltation dam
Locations/sites Lithologies Usefulness
Khahare Khola 60 to 70% of gravels, pebbles, cobbles are glassy, smooth, and, rough, flat and platy, composed of Phyllites, Schists, and Meta-Sandstone
30 to 40% of mostly gravels and pebble and cobbles are of equidimensional, elongate, glassy, smooth, and rough, subangular to sub rounded, white, light green, F-C-G, are composed of Quartzite
60 to 70% of sands and gravels
20 to 30% of clay to silt
<10% of boulders
30% to 40% volume of the materials are Good to Excellent for crashing stones, and useful for constructions aggregates, and remaining are useful for filling only
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
33
2.6 Harpan Khola Siltation Dam
Salient Features 2.6.1
The Harpan Khola reach near the dam area has 2.3 % longitudinal slope. The width of Harpan Khola
varies from 35 m to 110 m. The overall morphology of the reach resembles with the single thread
channel morphology having point bar. The salient features of the dam and flood protection structure
on the Harpan Khola are as follows:
• Planform: U shape
• Flow length: 100 m
• Left wing wall length: 100 m
• Right wing wall length: 100 m
• Top width of dam: 0.5 m
• Bottom width of dam: 9 m
• Height of dam: 4 m
• Downstream gabion apron width: 10 m (to protect d/s erosion)
• Left embankment: 100 m
A typical longitudinal section of the siltation dam constructed on the Harpan Khola has been shown
in Figure 2-13. The dam composed of a simple stone masonry trapezoidal wall together with a
gabion launching apron at the downstream. The height of the dam is 4 m.
Figure 2-13: A typical section of existing Harpan siltation dam.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
34
Problem and Mitigation Measures 2.6.2
The major problems associated to the Harpan siltation dam were overtopping of the left flood wall,
scouring of dam toe, scouring of downstream slope of the dam, scouring at the bottom of flood wall
and no sediment removal. Overtopping at the left embankment can be attributed to the curved
nature of the flood wall near the dam axis/wrong orientation of flood wall in comparison to the dam
axis. Scouring of dam toe can be attributed to inappropriate design of dam structure without the
provision of cut off and energy dissipation structure that are requisite in dam construction (cf. most
of the dam constructed in run river hydropower projects consider low height (1-2 m) weir structure
with provision of cut off and energy dissipation structure). The scouring of the downstream slope of
the dam can be attributed to the excessive slope of the dam. The high slope of the downstream face,
without having hard stone/concrete lining, could not resist the force of high current leading to
stability problems and erosion. The dam was completely filled during one monsoon but sediment
mining was not carried out which led to excessive bed level aggradation and overtopping from the
left flood wall.
The issues wise analysis of problems and their mitigation measures has been summarized in the
Table 2-4. The pictures taken during different site visit have been shown in the Figure 2-14 to 2-21 to
provide insights about the site condition.
Table 2-4: Technical concerns on planning, design, construction, operational issues and mitigation measures (Harpan dam)
Technical
Concern
Provided Feature/
Present Situation
Operational/Safety Issues Precautions/Mitigation
Measures
1. Plan
shape of
the flood
wall
The flood wall has not
been positioned at 90-
degree angle with dam
axis especially at the
end of left bank, wall is
rotated.
The height of the left
flood wall is not enough
to control high flood
discharge.
The curved wing wall
(oblique with the dam
axis) have tendency to
push water to left
corner and erode.
River is overtopping
the embankment wall
due to less freeboard
problem and curved
geometry of the wall.
Needs to remove
ome part and need
to make Straight for
the curve part of
the left flood wall
and increase height
of the left flood wall
+1m considering
100 years flood
along with enough
free board.
Or regularly
monitor flood level
and maintain
minimum 1 meter
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
35
Technical
Concern
Provided Feature/
Present Situation
Operational/Safety Issues Precautions/Mitigation
Measures
free board.
2. Retention
of
sediment
without
removal
plan
No access of gravel
mining and transporting
vehicle into the dam.
No provision of
emergency flood
regulating gates.
No provision for
draining water from
dam which may be
required while mining
the gravel.
No plan for monitoring
of flood, sediment and
bed level.
Without the event-
based or continuous
sediment removal
plan the siltation dam
could not function
properly.
If sediment is not
removed regularly,
there is always
tendency of sudden
deposition,
overtopping and
flooding the
surrounding lands.
Construct a ramp to
U/S of the dam to
facilitate mining
and transport.
Construct a sluice
gate at the dam to
regulate flood in
the case of
emergency and to
drain the water
while mining
deposited material.
3. Design of
main
dam
The dam consists of
stone masonry wall
having high slope (1.2:1)
at d/s as well as u/s
glacis.
High downstream
slope of the dam
produces high current
on the wall which the
stone masonry could
not resist.
Downstream slope
erosion and tow
erosion not avoidable
at the current
situation due to high
current.
Flatten D/S slope of
the dam.
4. Flood
Wall
The bottom of the left
flood wall just
downstream of the dam
axis has experienced
scouring.
Flood has overtopped at
left flood wall
Due to absence of cut
off at the bottom of
flood wall there is
tendency of failure of
wall (left and right
wall downstream of
the dam) at any time.
At the present
situation, there is
possibility of
overtopping of left
flood wall.
Correct alignment
and Provide cut off
at the bottom of
flood wall especially
at the flood wall d/s
of the dam
Heighten the flood
wall or maintain at
least 1 meter of
free board.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
36
Technical
Concern
Provided Feature/
Present Situation
Operational/Safety Issues Precautions/Mitigation
Measures
5. Dam
body
material
selection
and
safety
The dam was
constructed using stone
masonry
Erosion of
downstream face of
the dam is
unavoidable at the
current situation as
the stone masonry
wall is not enough to
resist the eroding
force of water flowing
through the high
provided slope
Concrete jacketing
could improve
stability and hard
stone pitching could
help controlling its
surface erosion
6. Absence
of U/S
and D/S
Cutoff
The 4 m height stone
masonry dam has been
built without any cut-
offs at the bottom
Due to the absence of
cut-offs there is
possibility of piping
and seepage from the
base
Extend the concrete
jacket deeper to
U/S and D/S cut-off.
7. Energy
dissipatio
n
structure
missing
at the d/s
There was no energy
dissipation structure at
the d/s
Due to lack of energy
dissipating structure
and absence of
sediment flow, the
channel downstream of
the dam seems to be
degrading.
The gabion laid at the
d/s floor is not
competent to resist
scouring and to
dissipate energy
Construct a stilling
basin with
depressed flood
and plunge in the
pool for energy
dissipation.
8. Flood
Regulatio
n
There is no any
provision of emergency
gate for the case of
emergency flood
regulation and draining
of water while mining
There will be problem
on mining material
and water level
control during
material removal time
One side can have
sluice gate which
will reduce water
level u/s making the
channel water level
down so that the
mining shall be
possible; the sluice
gate could also be
used to regulate
emergency flood.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
37
Figure 2-14: Harpan Dam on Aug 2020
Figure 2-15: Harpan dam having proximity to good access road at pre-inspection visit Aug 2020
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
38
Figure 2-16: Overtopping from left side flood wall near dam due to skewed planform.
Figure 2-17: Damaging pattern on the D/S glacis and even some part is taken away at middle
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
39
Figure 2-18: Bank cutting beyond left flood wall by overtopping the wall
Figure 2-19: Site visit team for assessment of siltation dams on Harpan Dam left bank
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
40
Figure 2-20: Scouring of toe of dam.
Figure 2-21: Scouring of toe of flood wall and channel degradation downstream.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
41
Properties of Deposited Material 2.6.3
The field observations suggest that the material deposited in Harpan siltation dam are excellent to
use as construction material. The lithology and usefulness of deposited material in Harpan siltation
dam has been summarized in the Table 2-5.
Table 2-5: Lithology and usefulness of deposited material in Harpan siltation dam.
Locations/sites Lithologies Usefulness
Harpan Khola 70 to 80% of mostly boulders and gravels, pebbles and cobbles of equidimensional, glassy, smooth, and rough, sub-angular to sub-rounded, White, Light Green, F-C-G, are composed of Quartzite
20 to 30% of gravels, pebbles and cobbles are glassy, smooth, and, rough, flat and platy, composed of Phyllites, Schists, Meta-Sandstone
Boulder dominates with and cobble, (>70%) gravel and very few portions of silt and sand
80% to 90% volume of the materials are Good to Excellent for crashing stones, and useful for constructions aggregates
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
42
2.7 Lauruk Khola Siltation Dam
Salient Features 2.7.1
The Lauruk khola reach near the dam area has 7.7 % longitudinal slope. The width of Lauruk Khola
varies from 30 m to 35 m. The overall morphology of the reach resembles with the braided
morphology. The salient features of the dam and flood protection structure on the Lauruk Khola are
as follows:
• Shape of Dam: U shaped
• Flow Length : 40 m, Total Height: 3 m ie 0.5m Bottom, Transition : 2m, Top : 0.5m
• Left wing length :66m
• Right wing Length: 66m
• Top width :0.5m
• Bottom Width: 6.7m on Flow Path, Left and Right wing width : 7m
Low discharge per meter dam length
Upstream settling zone partially occupied
Relative clean water flow
Less siltation/less severe flood
No any scouring detected on lunching apron
Source of material from soft rock so less erosion on dam d/s face
Problems and Mitigation Measures 2.7.2
The Lauruk siltation dam has not serious problems as compared to Khahare and Harpan Dam. The
major problems and their mitigation measures in Lauruk dam have been summarized in Table 2-6.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
43
The pictures taken during site visit have been shown in the Figure 2-22 and 2-23 to provide insights
about the site condition.
Table 2-6: Technical concerns on planning, design, construction, operational issues and mitigation
measures (Lauruk dam).
Particular Concern
Provided Feature/ Present Situation
Operational/Safety Issues
Precautions/ Mitigation Measures
1. Approaching River section is in High gradient or Slope
The River slope is high at the location of dam surrounding by Paddy Field and small height of flood wall
There can be overtopping also from the sides during high flash flood by excessive bed load
There is requirement increasing height of the left flood wall
2. D/S Face of erosion of Stone Masonry dam
The Dam is created by Stone Masonry wall with high down side slope
Face Erosion shall be high making dam in danger
Concrete jacketing with D/S cut-off be helpful
3. D/S Apron Stability
There is gabion Crates filled and paced at the toe of the dam for energy dissipation
The gabion life is very short, and can erode easily from toe of the dam having common material
There can be precast Concrete slab or additional slab at the base
4. Removal Facility
There is no access ramp to go vehicle U/S of dam for removing the deposit
There will be difficult to remove material trapped u/s of dam
There can be Access Road as Ramp down into the storage area
5. Further D/S Glacis of the dam erosion and slope stability
There is free flowing channel d/s with high gradient which can cause more erosion due to storage of sediment u/s of dam
The aggradation of immediate Downstream of the dam can cause dam instability
D/S can have another Check Dam or Cut off together with boulder lining
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
44
Figure 2-22: Lauruk Khola Siltation dam which relatively in better condition as compared to the
Khahare and Harpan dam.
Figure 2-23: Catchment and location of Lauruk dam.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
45
Properties of Deposited Material 2.7.3
The field observations suggest that the material deposited in Lauruk siltation dam are not good for
construction purpose. Instead, the material can be used for filling purpose. The lithology and
usefulness of deposited material in Khahare siltation dam has been summarized in the Table 2-7.
Table 2-7: Lithology and usefulness of deposited material in Lauruk siltation dam.
Locations/sites Lithologies Usefulness
Lauruk Khola 80 to 90% of gravels, pebbles, cobbles are glassy, smooth, and, rough, flat and platy, composed of Phyllites and Schists
5 to 10% of mostly gravels and pebble and cobbles are of equidimensional, elongate, glassy, smooth, and rough, subangular to sub rounded, are composed of Quartzite
Bulk volume of the materials is very poor to poor quality, so that the materials are useful for filling only.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
46
2.8 Betini Siltation Dam
Salient Features 2.8.1
The Betini khola reach near the dam area has 5.35 % longitudinal slope. The width of Betini Khola
varies from 25 m to 115 m. The overall morphology of the reach resembles with the braided
morphology. The salient features of the dam and flood protection structure on the Betini Khola are
as follows:
• Shape of Dam: U shaped
• Flow Length : 40m, Total Height: 3m ie 0.5m Bottom, Transition : 2m, Top : 0.5m
• Left wing length :66m
• Right wing Length: 66m
• Top width :0.5m
• Bottom Width: 6.7m on Flow Path, Left and Right wing width : 7m
• Downstream gabion stilling basin width 6m: Height 0.6 m
• Low flood discharge per meter of dam as compared to others
• No any structural damage yet on apron
• Absence of any scouring as well as damage on apron
Problems and Mitigation Measures 2.8.2
The Betini siltation dam has not serious problems as compared to Khahare and Harpan Dam. The
major problems and their mitigation measures in Betini dam have been summarized in Table 2-8.
The pictures taken during site visit have been shown in Figure 2-24 to 2-27 to provide insights about
the site condition.
Table 2-8: Technical concerns on planning, design, construction, operational issues and mitigation measures (Betini dam).
Particular Concern
Provided Feature/ Present Situation
Operational/Safety Issues Precautions/Mitigation Measures
1. River is in high gradient
The river slope is high at the location of dam, one side is valley other side is housing area
There can be overtopping also from left side during high flash flood if bed load is not removed on regular basis
There is requirement of D/s Protection and also increasing height of the flood wall U/S of the dam on left side
2. D/S Face of dam erosion
The dam is created by stone masonry wall on high slope like
There can be d/s face damage similar to others in the coming
Planning of concrete jacketing and heightening of
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
47
Particular Concern
Provided Feature/ Present Situation
Operational/Safety Issues Precautions/Mitigation Measures
others dam
years the left flood wall considering the instantaneous flood is recommended
3. D/S Apron Stability
There is gabion boxes filled at the toe of the dam for energy dissipation p/ protection
There is tendency of removal of gabion boxes in few leading to downstream toe erosion and dam safety
There can be precast concrete slab or additional slab at the base
4. Removal Facility
There is no access into the U/S are of dam
There will be difficult to remove material trapped u/s taking vehicle down inside he deposited area
There can be Access Road and Ramp going down to the dam
5. D/S river slope stability
There is free flowing channel d/s and can cause more erosion due to storage of sediment u/s of dam
The aggradation of immediate Downstream of the dam can cause dam instability
D/S can have more cutoff followed by boulder lining
Figure 2-24: Relatively better condition of the dam but the river gradient is still high
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
48
Figure 2-25: The chance of overtopping from just u/s of the dam (View from Upstream)
Figure 2-26: Fully deposited dam and overtopping from left bank (View from D/S)
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
49
Figure 2-27: U/s reach of the dam showing flood control gabion walls on both bank and road, houses at the left bank.
Properties of Deposited Material 2.8.3
The field observations suggest that the material deposited in Betini siltation dam are not good for
construction purpose. Instead, the material can be used for filling purpose. The lithology and
usefulness of deposited material in Betini siltation dam has been discussed in Table 2-9.
Table 2-9: Lithology and usefulness of deposited material in Lauruk siltation dam.
Locations/sites Lithologies Usefulness
Betini Khola 70 to 80% of gravels, pebbles, cobbles, boulders are glassy, smooth, and, rough, flat and platy, composed of Phyllites and Schists
20% to 30% of mostly gravels and pebble and cobbles are of equidimensional, elongate, glassy, smooth, and rough, subangular to sub rounded, are composed of Quartzite
About 20 to 25% of the material can use for crasher stone after sieving, and remaining usable for the filling only
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
50
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
51
3. Chapter 3: Typical Design and Estimate of Risk
Mitigation Facilities
3.1 Design Parameters
Previous study considered simple regression technique to calculate design discharge over the dam
for design of the spillway length. In this study, the Hydest 2004 method was used to calculate 100-
year return period flood and instantaneous flood. As there is trend of concentrated rainfall and
severe flash floods, the instantaneous flood is recommended for design of the dam facilities. The
100-year return period flood, instantaneous flood, width of the dam, head over crest on the dam,
specific discharge per m length of dam have been listed in Table 3-1 for design reference.
Table 3-1: Technical design parameters for the assessment of dam planning and design
SN
Siltation Dam
Catchment
Area
(km2)
Q100yr
Return period flood (m3/s)
Instantaneous flood (m3/s)
Width
(m)
Head over crest (m)
Flood wall
(m)
Specific Discharge (m2/s)
Estimated Sediment Load (m3/yr)
1 Khahare 25.3 66 212 100 1.26 2.3 2.12 238000
2 Harpan 35.7 91 281 90 0.77 1.8 1.01 100000
3 Lauruk 4.5 17 61 40 0.43 1.4 0.43 42332
4 Betini 7.1 24 85 40 0.54 1.5 0.60 66791
3.2 Retrofitting Option for Khahare Siltation Dam
There will be concrete jacketing over the current stone masonry dam surface to retrofit main body
of the dam. Additionally, there will be stone lining panel, on both u/s and d/s slope supported by
holding keys. The concrete jacket will be extended to u/s and d/s cut off. There will be concrete
stilling basin downstream of the dam in order to dissipate spilling energy and to avoid downstream
bed degradation. The stilling basin will have stone lining (or Concrete Precast Blocks) for extra safety.
There is a challenge of construction of cutoff maintaining the profile extending the jacket and to
safeguard machinery while digging below foundation. Hence, excavation of cutoff need to be in
offset and support wall is needed inside part which can act as formwork. Also, for the purpose of
reducing water level during removing of deposited sediment out of dam, a small sluice gate will also
be provided. The gate can be used to lower water level during sediment removal time and
emergency flood. A ramp like structure should is also provided to provide access of
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
52
instrument/vehicle to the dam during maintenance and sediment mining time. The planform and a
typical longitudinal section of the retrofitting design have been shown in Figure 3-1, 3-2, and 3-3
respectively. The detail of the retrofitting option has been summarized in Table 3-2.
.
Figure 3-1: Khahare Dam layout and its components/Facilities
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
53
Figure 3-2: Typical section of Khahare dam (existing situation-top) and (suggested retrofitting
option-bottom)
Table 3-2: Different components of retrofitting option for Khahare siltation dam.
SN Retrofitting Component Details about the components Remarks
1 Concrete Jacketing 60 cm on top and 90 cm in bottom d/s face in total
30 cm on top and 60 cm in bottom Concrete d/s face
2 Hard Stone Lining 30 cm stone lining on all surface with 40cm key concrete and panels width 2m each
3 U/S and D/S cutoff 2m deep cutoff 30 to 60cm thick
4 D/S Stilling Basin 10 m width 0.7 to 1.2m deep sloping bottom type stilling basin
5 D/s Cutoff of Stilling basin
After Basin further 1.75m deep cutoff
6 Boulder Riprap D/s for extra safety 1.2m dia boulder riprap
7 U/S Geotextile Blanket U/s face Boulder Lining with Geotextile base and Red Clay filled carpeting for seepage/piping control
8 Sluice Gate on Left bank 3x2m size 1 sluice gate for level regulation
9 Divider and Parapet of sluice blocks
Lifting mechanism of Gate and access platform
10 Access Road and Ramp Track inside basin for Truck access to remove deposit
There will be requirement of access Road and Sloping ramp at least 4 m wide at 10% Slope to take truck down to the basin for removal of the debris.
11. Flood Wall and river Training works right bank
There is massive River Training Works including Scour Protection cutoff and Stone Masonry Base and back side support dike
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
54
Figure 3-3: Under sluice plan and section proposed at the dam edge for water level control.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
55
3.3 Retrofitting Option for Harpan Khola Dam
Most of the problems in Harpan Khola siltation dam are similar to problems in Khahare dam. The
suggested component for retrofitting are construction of concrete jacketing, cut off, stilling basin
and heightening of the left flood wall. There is also requirement of re-alignment of left side flood
wall just after dam and extension of the flood protection d/s further till river has bend. There is also
requirement of heightening of the side flood channel especially on left bank of the river u/s of the
dam. The planform and a typical longitudinal section of retrofitting design have been shown in
Figure 3-4 and 3-5, respectively. The detail of the retrofitting option has been summarized in Table
3-3.
Figure 3-4: Harpan Dam layout and its components/Facilities (retrofitting option)
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
56
Figure 3-5: Typical section of Harpan dam (suggested retrofitting option).
Table 3-3: Different components of retrofitting option for Khahare siltation dam.
SN Retrofitting Component Details about the components Rem
1 Concrete Jacketing 60 cm on top and 90 cm in bottom d/s face in total
30 cm on top and 60 cm in bottom Concrete d/s face
2 Hard Stone Lining 30 cm stone lining on all surface with 40cm key concrete and panels width 2m each
3 U/S and D/S cutoff 2m deep cutoff 30 to 60cm thick
4 D/S Stilling Basin 10 m width 0.7 to 1.2m deep sloping bottom type stilling basin
5 D/s Cutoff of Stilling basin
After Basin further 1.75m deep cutoff
6 Boulder Riprap D/s for extra safety 1.2m dia boulder riprap
7 U/S Geotextile Blanket U/s face Boulder Lining with Geotextile base and Red Clay filled carpeting for seepage/piping control
8 Sluice Gate on Left bank
3x2m size 1 sluice gate for level regulation
9 Divider and Parapet of sluice blocks
Lifting mechanism of Gate and acces plateform
10 Acces Road and Ramp Track inside basin for Truck acces to remove
There will be requirement of access Road and Sloping Ramp at least 4m wide at 10% Slope to take truck down
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
57
SN Retrofitting Component Details about the components Rem
depoit to the basin from Highway side on right bank.
11 Flood Wall Heightening The left bank u/s flood wall needs heightening for the safety on the flooding left bank settlement and paddy field.
12 Relocation of D/S flood wall
The Flood wall constructed in oblique to the dam axis needs to be relocated, straight on the alignment of the river
13 Extension of Flood wall D/S on left bank
There is requirement of extending the Flood wall on the left bank further downstream up to the river bend position.
3.4 Lauruk Dam
The field observation suggests that the Lauruk dam is operating well and there are not serious
issues. However, the stone masonry dam and downstream protection structures are not enough for
longevity of the dam. The heightening of left flood wall is therefore strongly suggested in order to
avoid overtopping. The planform and a typical longitudinal section of the retrofitting design have
been shown in Figure 3-6 and 3-7 respectively. The detail of the retrofitting option has been
summarized in Table 3-4.
Figure 3-6: Lauruk Dam layout and its components/Facilities (retrofitting option)
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
58
Figure 3-7: Typical section of Lauruk dam (suggested retrofitting option).
Table 3-4: Different components of retrofitting option for Lauruk siltation dam.
SN Project Component Details Proposed for development Rem
1 Concrete Jacketing 60 cm on top and 90 cm in bottom d/s face in total
30 cm on top and 60 cm in bottom Concrete d/s face
2 Hard Stone Lining 30 cm stone lining on all surface with 40cm key concrete and panels width 2m each
3 U/S and D/S cutoff 2m deep cutoff 30 to 60cm thick
4 D/S Apron 6 m width 0.6 deep Apron with Stone Lining
5 D/s Cutoff of Apron After Basin further 1.75m deep cutoff
6 Boulder Riprap D/s for extra safety 1.2m dia boulder riprap
7 U/S Geotextile Blanket U/s face Boulder Lining with Geotextile base and Red Clay filled carpeting for seepage/piping control
8 Sluice Gate on Left bank 1.2x1.2m size 1 sluice gate for level regulation
9 Divider and Parapet of sluice blocks
Lifting mechanism of Gate and acces plateform
10 Acces Road and Ramp Track inside basin for Truck acces to remove depoit
There will be requirement of access Road and Sloping Ramp at least 4m wide at 10% Slope to take truck down to the basin from left bank.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
59
SN Project Component Details Proposed for development Rem
11 Flood Wall Heightening The left bank as well as right flood wall needs heightening for the safety on the flooding paddy field both side in the area.
3.5 Betini Dam
The field observation suggests that the Betini dam is operating well and there are not serious issues.
However, the stone masonry dam and downstream protection structures are not enough for
longevity of the dam. The heightening of flood wall is suggested in order to avoid overtopping. The
planform and a typical longitudinal section of the retrofitting design have been shown in Figure 3-8
and 3-9 respectively. The detail of the retrofitting option has been summarized in Table 3-5.
Figure 3-8: Betini Dam layout and its components/Facilities (retrofitting option)
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
60
Figure 3-9: Typical section of Betini dam (suggested retrofitting option).
Table 3-5: Different components of retrofitting option for Betini siltation dam.
SN Project Component Details Proposed for development Remarks
1 Concrete Jacketing 60 cm on top and 90 cm in bottom d/s face in total
30 cm on top and 60 cm in bottom Concrete d/s face
2 Hard Stone Lining 30 cm stone lining on all surface with 40cm key concrete and panels width 2m each
3 U/S and D/S cutoff 2m deep cutoff 30 to 60cm thick
4 D/S Apron 6 m width 0.6 deep Apron with Stone Lining
5 D/s Cutoff of Apron After Basin further 1.75m deep cutoff
6 Boulder Riprap D/s for extra safety 1.2m dia boulder riprap
7 U/S Geotextile Blanket
U/s face Boulder Lining with Geotextile base and Red Clay filled carpeting for seepage/piping control
8 Sluice Gate on Left bank
1.2x1.2m size 1 sluice gate for level regulation
9 Divider and Parapet of sluice blocks
Lifting mechanism of Gate and access platform
10 Access Road and Ramp Track inside basin for Truck access to remove deposit
There will be requirement of access Road and Sloping Ramp at least 4m wide at 10% Slope to take truck down to the basin from left bank.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
61
SN Project Component Details Proposed for development Remarks
11 Flood Wall Heightening
The left bank flood wall needs heightening for the safety on the flooding area on that side already overtopping.
3.6 Summary Cost for Retrofitting Option
The bill of quantify was calculated using typical section and profile of the suggested retrofitting
option. The district rate provided by the Pokhara Metropolitan City office was used for item cost
estimation. The summary of cost for the suggested retrofitting option has been presented in Table 3-
6. The detail Bill of Quantify (BoQ) and Rate Analysis has been presented in Annex 02 and 03
respectively. The grand total cost for retrofitting Khahare, Harpan, Lauruk and Betini siltation dam is
calculated at NRs 368,484,000. The cost for each dam has been shown in Table 3-6.
Table 3-6: Summary cost estimate of the suggested retrofitting option for four siltation dam.
S.N.
Descriptions Amount
(NRs)
Misc and
Contingency 10%
Base Cost (NRs)
VAT 13%
Total Cost With
VAT(NRs)
A Engineering, Supervision, Management of Retrofitting works
LS @ 10% of the Cost
27,108
2,711
29,819
3,877
33,696
Sub-Total of A
27,108
2,711
29,819
3,877
33,696
B BETINI Siltation Dam
B1
General Items (Insurance, Mobilization, Camping, Power etc.)
2,045
-
2,045
266
2,311
B2
Betini Dam Strengthening/Retrofitting
19,370
1,937
21,307
2,770
24,077
B3
Betini Undersluice
7,458
746
8,204
1,066
9,270
Sub-Total of B
28,873
2,683
31,556
4,102
35,658
C Harpan Siltation Dam
C 1
General Items (Insurance, Mobilization, Camping, Power etc.)
4,792
-
4,792
623
5,415
C 2
Harpan Dam Repair/Retrofitting
52,700
5,270
57,970
7,536
65,506
C 3
Harpan Undersluice and Approach
10,168
1,017
11,185
1,454
12,639
Sub-Total of C
67,660
6,287
73,946
9,613
83,559
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
62
S.N.
Descriptions Amount
(NRs)
Misc and
Contingency 10%
Base Cost (NRs)
VAT 13%
Total Cost With
VAT(NRs)
D Lauruk Siltation Dam
D 1
General Items (Insurance, Mobilization, Camping, Power etc.)
2,109
-
2,109
274
2,383
D 2
Lauruk Dam Strengthening/Retrofitting
20,895
2,089
22,984
2,988
25,972
D 3
Lauruk Undersluice
6,768
677
7,445
968
8,413
Sub-Total of D
29,771
2,766
32,538
4,230
36,768
E KHAHARE Siltation Dam
E 1
General Items (Insurance, Mobilization, Camping, Power etc.)
10,254
-
10,254
1,333
11,587
E 2
Khahare Dam and River Training works
126,041
12,604
138,645
18,024
156,669
E 3
Khahare Undersluice
8,485
848
9,333
1,213
10,547
Sub-Total of E
144,780
13,453
158,233
20,570
178,803
Grand Total Cost
298,193
27,899
326,092
42,392
368,484
Note: The cost presented here was based on the Google map based information and field observations. Indeed, no detail topographic survey was carried out. It is therefore suggested to take this cost as preliminary which needs further verification while preparing detail project report. During detail study, it is strongly recommended to carry detail topographic survey, to update design as per the topography, to carry field verification by laying out every in the field and estimate final cost.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
63
4. Chapter 4: Management, Operation and Maintenance
Plan
4.1 Revenue potential from construction material
The study report "Development of Ecosystem based Sediment Control Techniques & Design of
Siltation Dam to Protect Fewa Lake" by GoN/UNDP, 2015 estimated the sediment load in Khahare,
Harpan, Lauruk and Betini by using Mayer-Peter and Muller Formula (Table 4-1).
Table 4-1: Sediment load in Khahare, Harpan, Lauruk and Betini (GoN/UNDP report based data).
SN
Dam
Location
Catchment
Area (km2)
Q100yr
Flood (m3/s)
Instantaneous
flood (m3/s)
Sediment
Load (m3/yr)
Remarks
1 Khahare 25.3 66 212 149,145
2 Harpan 35.7 91 281 86,522
3 Lauruk 4.5 17 61 26,528
4 Betini 7.1 24 85 41,855
GD. Total
304,050
Field observation suggested that the sediment deposited in Khahare and Harpan dam are of
commercial quality for production of aggregate, chips and sand. However, sediment deposited in
Lauruk and Betini dam is from different geological settings so that they can only be used as filler,
sub-base coarse or low grade concrete. All dams have been filled completely. The volume of
sediment filled at the dam in one season has been approximated in the Table 4-2.
Table 4-2: Deposited approximate volume of sediment load in 2020 monsoon season.
SN Dam Observation Filling
Dimension u/s of dam
Remarks
Location By Filled Volume (m3)
1 Khahare 135000 100*300*4.5
2 Harpan 90,000 100*200*4.5
3 Lauruk 24000 60*100*4
4 Betini 16,000 40*100*4
Grand Total 265,000
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
64
The value of sediment deposited in the dam was calculated by considering current district rate
(Table 4.3). Once four dams are filled, about 265,000 m3 sediment could be accumulated. However,
deposited material on Harpan and Khahare dam can only be used as construction material which
estimates to be 225,000 m3. The material from Lauruk and Betini has to be dumped safe on some
area or road pavements/embankments. The saleable volume of gravel and sand from Khahare and
Harpan could generate NRs. 207,187,500 gross revenue. The net revenue after deducting processing
cost (50 % of gross revenue for processing) could be approximated at NRs. 103,593,750.
Table 4-3: Revenue generation from deposited sediment during 2020 monsoon season.
Dam
Dam U/S deposit sediment
(m3)
Sand recove
ry %
Sand Volume
(m3)
Sand
Rate (NRs/
m3)
Aggregate recovery
% Aggrade (m3)
Rate (NRs/m)
Total Gross sales (NRs)
Rem
Khahare 135000 15% 20250 2100 35% 47250 1850 129937500
50% Recover
Harpan 90,000 10% 9000 2100 30% 27000 1850 68850000
40% Recover
Lauruk 24000 10% 2400 2100 30% 7200
No sell 5040000
Dumping
Betini 16,000 10% 1600 2100 30% 4800
No sell 3360000
Dumping
Total 265,000
33250 sales 86250
207187500
Gross income deducting processing cost @ 50%
103379400
Note: the sales volume calculation is done with assumed recovery rates of the deposited material.
This is consideration with one time fill only and processing/screening material removal after summer,
more revenue is also possible if more extraction I needed.
4.2 Sample financial analysis
The cost of the Repair/Protection works is estimated about 368 million whereas gross revenue is
estimated about NRs. 103 Million. The cost of construction is financed 70% from Bank @ 12%, and
construction major in first year with 60% draw down, 30% 2nd year and 10% third year for
maintenance and miscellaneous cost (Table 4-4).
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
65
Table 4-4: Financial parameter for analysis
Base Cost 2020 price level 368484 NRs, 000
Scenario what happens after FINANCING WITH BANK Before Banking
After Banking
Total Cost 368484 100%
Total Cost 427617 100.0%
Pure Cash Loan 240183 65.18%
Total Loan 299311 70.0%
Equity 128301 33.18%
Equity 128307 30.0%
Interest Rate 12.0%
Interest Calculation
Time (year) Interest Tot Interest
First year drawdown 60% 2.5 43233 43233
Second year drawdown 30% 1.5 12970 56203
Third year drawdown
10% 0.5 1441 57644
Total Interest 57644 57644
Loan Arrangement Fee 0.50%(Theki) 1489 0.50%
Total Interest to be capitalized 59133 NRs 16%
Cost including IDC 427617 ie Gross Revenue each year
103594 NRs
A Simple financial model based on Simple cash flow is prepared to evaluate the internal rate of
return and Return on Investment of the project based on cost/benefit projection.
Table 4-5: Projected Cash Flow Analysis for Economic model
Year Revenue O/M Royalty Profit before Tax Tax Cash flows
1
(256,570)
2 (128,285)
3 (42,762)
Cash Flow
1 103,594 10,359 5,179.69 73,801 14,760 73,295
2 106,702 10,670 5,335.08 54,989 10,998 79,698
3 109,809 10,990 5,490.47 57,919 11,584 81,745
4 112,917 11,320 5,645.86 60,757 12,151 83,800
5 116,025 11,660 5,801.25 63,528 12,706 85,859
6 119,133 12,009 5,956.64 66,247 13,249 87,917
7 122,241 12,370 6,112.03 68,925 13,785 89,974
8 125,348 12,741 6,267.42 71,571 14,314 92,026
9 125,348 13,123 6,267.42 71,239 14,248 91,710
10 125,348 13,517 6,267.42 70,883 14,177 91,388
11 125,348 13,922 6,267.42 70,508 14,102 91,057
12 125,348 14,340 6,267.42 70,114 14,023 90,718
13 125,348 14,770 6,267.42 69,704 13,941 90,370
14 125,348 15,213 6,267.42 69,277 13,855 90,013
15 125,348 15,669 6,267.42 68,835 13,767 89,645
16 125,348 16,140 6,267.42 68,377 13,675 89,266
17 125,348 16,624 6,267.42 67,902 13,580 88,877
18 125,348 17,122 6,267.42 67,413 13,483 88,476
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
66
Year Revenue O/M Royalty Profit before Tax Tax Cash flows
19 125,348 17,636 6,267.42 66,907 13,381 88,063
20 125,348 18,165 6,267.42 66,385 13,277 87,639
21 125,348 18,710 6,267.42 65,846 13,169 87,202
22 125,348 19,271 6,267.42 65,291 13,058 86,751
23 125,348 19,850 6,267.42 64,718 12,944 86,288
24 125,348 20,445 6,267.42 64,127 12,825 85,810
25 125,348 21,058 6,267.42 63,519 12,704 85,319
26 125,348 21,690 6,267.42 62,891 12,578 84,813
27 125,348 22,341 6,267.42 62,244 12,449 84,291
28 125,348 23,011 6,267.42 61,578 12,316 83,754
29 125,348 23,702 6,267.42 60,891 12,178 83,201
30 125,348 24,413 6,267.42 60,183 12,037 82,632
The cash Flow Statement for calculation of Rate of Return is also presented paying back loan and
interest of the bank (Table 4-6).
Table 4-6: Investor CASH FLOWS Statement for Financial Model
Year
Depreciation
Unpaid Loan Interest
Principle
Before Tax Tax
Cash flows After Tax
Gross Return
1 188832 to Bank (76,984)
2 273851 (38,492)
3 299311
(12,831)
Cash Flow
1 14,254 299,311 35,917
12,402
48,320
37,884 7,577 32158
2 14,254 286,908 34,429
13,891
48,320
42,013 8,403 33974
3 14,254 273,017 32,762
15,558
48,320
46,313 9,263 35746
4 14,254 257,460 30,895
17,425
48,320
50,802 10,160 37471
5 14,254 240,035 28,804
19,516
48,320
55,506 11,101 39143
6 14,254 220,520 26,462
21,857
48,320
60,451 12,090 40757
7 14,254 198,662 23,839
24,480
48,320
65,666 13,133 42306
8 14,254 174,182 20,902
27,418
48,320
71,185 14,237 43784
9 14,254 146,764 17,612
30,708
48,320
74,092 14,818 42820
10 14,254 116,056 13,927
34,393
48,320
77,384 15,477 41768
11 14,254 81,663 9,800
38,520
48,320
81,105 16,221 40618
12 14,254 43,143 5,177
43,143
48,320
85,310 17,062 39359
13 14,254 0 90,057 18,011 86300
14 14,254 89,614 17,923 85945
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
67
Year
Depreciation
Unpaid Loan Interest
Principle
Before Tax Tax
Cash flows After Tax
Gross Return
15 14,254 89,158 17,832 85580
16 14,254 88,688 17,738 85204
17 14,254 88,203 17,641 84817
18 14,254 87,705 17,541 84418
19 14,254 87,191 17,438 84007
20 14,254 86,662 17,332 83583
21 14,254 86,117 17,223 83147
22 14,254 85,556 17,111 82698
23 14,254 84,977 16,995 82236
24 14,254 84,382 16,876 81759
25 14,254 83,769 16,754 81269
26 14,254 83,137 16,627 80763
27 14,254 82,486 16,497 80243
28 14,254 81,816 16,363 79707
29 14,254 81,126 16,225 79154
30 14,254 80,415 16,083 78586
4.3 Finding and Remarks
The financial analysis revealed IRR of more than 16%, BC Ratio of 1.35 times and Return on
Investment of 23% from this venture (Table 4-7).
Table 4-7: Financial analysis results
Results
NPV 127487 NRs
Project IRR 16%
Project B/C Ratio 1.35
Simple Payback 4.93 Years
Equity Holders NPV 170278
Return on Investment 23%
Investors B/C Ratio 2.80
The following conclusion could be drawn from the preliminary financial analysis:
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
68
1. The cost and benefit analysis shows that the Dam Repair project seems to be a bankable
project based on nominal revenue from the sales of construction material.
2. The rate of return is remarkable and private sector can also be attracted on this project.
3. The investment is possible on 70: debt 30% Equity ratio and loan from commercial bank is
also possible.
4. The loan can be paid with interest and principal within 12 years.
5. The return on investment shall be more than 20%.
6. The repair works can be implemented immediately making suitable policy framework for the
repair and collection of revenue from the sales of retained volume.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
69
5. Chapter 5: Conclusion and Recommendations
5.1 Conclusion
Watersheds of Harpan Khola consist of the hard and good rock quality whereas the other
sub watersheds have soft rock mass.
Active landslides, soil erosion, channel flows and new haphazardly constructed rural roads
are main geohazard of the Fewa Lake watersheds contributing to sediment production and
lake sedimentation.
The Khahare and Harpan dam have severe stability problem because of D/S face erosion of
the dam and they can fail completely at any time. The Lauruk and Betini dams have not
severe stability problem for now but they are also susceptible to failure in the long-term.
The simple stone masonry dam without having concrete jacket, cut off both upstream and
downstream toe of dam, and stilling basin is not enough to resist the sediment and
discharge load. It is therefore, recommended to retrofit these dams sequentially.
In the first phase, it is recommended retrofitting Khahare and Harpan dam. For both dam, it
is imperative to provide concrete jacket with stone lining, cut off, and stilling basin. It is also
recommended heightening flood walls considering the instantaneous flash flood.
It is recommended to observe functioning of Lauruk and Betini dam in the coming flood
season and carry necessary retrofitting. However, heightening of left flood wall in Lauruk
and Betini is immediately necessary as the stream is overtopping the flood wall already.
Once four dams are filled, about 265,000 m3 sediment could be accumulated. However,
deposited material on Harpan and Khahare dam can only be used as construction material
which estimates to be 225,000 m3; rest (material from Lauruk and Betini) has to be dumped
safe on some area or road pavements/embankments.
There is no use of the dam if the removal/withdrawal of the material is not done regularly
by monitoring flood and bed level. No more investment is suggested without having proper
sediment removal mechanism. There is requirement of truck access to dam u/s, ramp, and
side sluice gate to facilitate sediment removal works.
The preliminary cost of repair/rehabilitation, retrofitting and strengthening the dam and
river training works is estimated at NRs 368 million including supervision cost.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
70
The net revenue from the sales of aggregate and sand from the dam deposit could be in the
order of 103 million (One time filling of dam). The Khahare dam could be filled more than
one time in a year generating more aggregate and revenue.
Preliminary financial analysis based on the retrofitting cost and the market values of the
deposited material suggest that the project is bankable and attractive (IRR = 16%, BC Ratio =
1.35 and Return on Equity =23%).
5.2 Recommendations
Before implementing the dam retrofitting option suggested in this study, it is strongly
recommended to carry detail study. The main activities during the detail study could be:
detail topographic survey, updating of retrofitting option suggested in this study based on
the topographic map, field verification, and final quantity and cost estimation.
It is recommended to estimate of revenue from the deposited material before bidding the
sediment mining project. In order to determine the revenue more accurately, it is
recommended to carry sediment sampling/sieve analysis, development of gradation curve,
quantification of saleable and non-saleable material and determine their market value.
As a first option, it recommended running the sediment mining project by province
government and the Pokhara Metropolitan city. The revenue generated from the sediment
mining project could be used for conservation and development of Fewa Lake and its
catchment. As the project is bankable and attractive, private sector could also be invited to
do this business through BOOT model.
The siltation dam is not the final solution to get rid of lake sedimentation. The siltation dam
is applicable to retail most of the coarse-gravel sediment and small proportion of sand-silt-
clay. Most of the supply based materials (sand-clay) are still transported to the lake. It
therefore recommended determining effectiveness of the siltation dam reducing lake
sedimentation by carrying detail catchment scale analysis.
The scope of catchment scale study could be: watershed landslides hazard mapping,
quantification of sediment production, analysis of human intervention such as cropping
pattern, construction activities and their contribution to sediment production.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
71
Annexes
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
72
Annex 01: Quantity Calculation and BoQ Estimate of the Repair works
FEWA WATERSHED SILTATION DAM Total Repair/Retrofitting Cost
in '000
Annex: 01
S.No
. Descriptions
Amount (NRs)
Misc and
Contingency 10%
Base Cost (NRs)
VAT 13%
Total Cost With VAT
(NRs)
Remarks
A Engineering, Supervision, Management of Retrofitting works
LS @ 10% of the Cost
27,108
2,711
29,819
3,877
33,696
Sub-Total of A
27,108
2,711
29,819
3,877
33,696
B Betini Siltation Dam
B1 General Items (Insurance, Mobilization, Camping, Power etc.)
2,045
-
2,045
266
2,311
B2 Betini Dam Strengthening/Retrofitting
19,370
1,937
21,307
2,770
24,077
B3 Betini Undersluice
7,458
746
8,204
1,066
9,270
Sub-Total of B
28,873
2,683
31,556
4,102
35,658
C Harpan Siltation Dam
C 1
General Items (Insurance, Mobilization, Camping, Power etc.)
4,792
-
4,792
623
5,415
C 2
Harpan Dam Repair/Retrofitting
52,700
5,270
57,970
7,536
65,506
C 3
Harpan Undersluice and Approach
10,168
1,017
11,185
1,454
12,639
Sub-Total of C
67,660
6,287
73,946
9,613
83,559
D Lauruk Siltation Dam
D 1
General Items (Insurance, Mobilization, Camping, Power etc.)
2,109
-
2,109
274
2,383
D 2
Lauruk Dam Strengthening/Retrofitting
20,895
2,089
22,984
2,988
25,972
D 3
Lauruk Undersluice
6,768
677
7,445
968
8,413
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
73
Sub-Total of D
29,771
2,766
32,538
4,230
36,768
E Khahare Siltation Dam
E 1 General Items (Insurance, Mobilization, Camping, Power etc.)
10,254
-
10,254
1,333
11,587
E 2 Khahare Dam and River Training works
126,041
12,604
138,645
18,024
156,669
E 3 Khahare Undersluice
8,485
848
9,333
1,213
10,547
Sub-Total of E
144,780
13,453
158,233
20,570
178,803
Grand Total Cost 298,193
27,899
326,092
42,392
368,484
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
74
Annex: 02
FEWA LAKE WATERSHED SILTATION DAM
Bill of Quantity of Repair/Retrofitting works
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
A: GENERAL ITEMS
1
Insurance of Contractor's Resources (Personnel, labours, Equipment's Third Party etc.) all as per Contract Conditions except Contractor's All Risk (CAR)
LS 1.0 5,000,000.00 5000000.00
2 Mobilization and Demobilization
LS 1.0 700,000.00 700000.00
3 Contractor, Site Facilities including Labour Camp
LS 1.0 3,000,000.00 3000000.00
4 Provision for Standby Power Supply
LS 1.0 3,000,000.00 3000000.00
5
Established the material testing lab, Lab test in or off sore the project
LS 1.0 1,000,000.00 1000000.00
6 River Diversion and Dewatering
LS 1.0 5,000,000.00 5000000.00
7 Construction Power and Lighting for Works
LS 1.0 1,000,000.00 1000000.00
8
Progress Report, Construction Drawings and As Built Drawings
LS 1.0 500,000.00 500000.00
- Total 19,200,000.00 For all
B. Betini Siltation Dam B1. Dam Repair/Retrofitting
1 Site Clearance m2 0.00 83.00 -
2
Excavation of Earth soil (Including Boulder <3.0m
3
Volume) by equipment
m3 2417.63 116.00 280,445.52
3
Earth Work in excavation in boulder mix soil including disposal up to 10m lead and
m3 284.43 142.00 40,388.71
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
75
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
1.5m lift
4
Earth Work in excavation in hard rock without blasting including disposal up to 10m lead and 1.5m lift
m3 142.21 1,290.00 183,455.74
5
E/W in Backfilling by Ordinary Soil in 15cm thick layer and compaction with sprinkling of water, haulage distance 10m.
m3 284.43 120.00 34,131.30
6 Dry Stone Soling m3 26.33 1,988.28 52,349.76
7
Laying 30cm thick Filter material inclusive haulage up to 10 m and lift up to 1.5m
m2 1363.80 1,360.95 1,856,060.20
8 Boulder Riprap (upto 1.0m Dia. Boulder)
m3 891.00 1,650.00 1,470,150.00
9 Boulder Riprap (upto 1.2m Dia. Boulder)
m3 567.36 2,210.00 1,253,865.60
10 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 99.05 4,354.70 431,335.74
11
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 13.16 12,070.00 158,896.72
12
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 71.57 12,704.29 909,259.25
13
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including up to 30m
m3 306.61 17,101.67 5,243,619.50
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
76
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
lead.
14
Providing and Placing M35/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 58.79 19,271.82 1,132,996.31
15
Providing, fixing and removing formworks for Concreting Works.
m2 1232.51 887.09 1,093,345.39
16 Reinforcement works for RCC Concrete.
MT 26.22 117,702.20 3,085,981.15
17
Random Rubble Masonry in 1:4 Cement and sand mortar
m3 139.62 10,368.88 1,447,702.33
18 300mm PCV Water Stop
m 191.45 1,673.65 320,420.29
19 25mm thick Expansion Joint Board
m2 95.73 2,525.05 241,710.41
20 Joint Sealant m2 95.73 1,403.05 134,306.96
Sub Total
19,370,420.87
B 2. Undersluice
1 Dry Stone Solling m3 8.24 1,988.28 16,382.51
2 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 8.59 4,354.70 37,398.57
3
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 4.12 12,070.00 49,725.68
4
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including up to 30m lead.
m3 31.11 12,704.29 395,287.62
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
77
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
5
Providing and Placing M20/40 Cement Concrete machines mixed for the wall, column, beam etc., including up to 30m lead.
m3 11.31 16,070.85 181,833.65
6
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 184.91 17,101.67 3,162,219.05
7
Providing, fixing and removing formworks for Concreting Works.
m2 326.30 887.09 289,456.13
8 Reinforcement works for RCC Concrete.
MT 13.64 117,702.20 1,605,477.23
9 Stone Masonry Work in 1:4 Cement mortar
m3 4.86 10,368.88 50,423.84
10 300mm PVC Water Stop
m 15.00 1,673.65 25,104.75
11 25mm thick Expansion Joint Board
m2 7.50 2,525.05 18,937.88
12 Joint Sealant m2 7.50 1,403.05 10,522.88
13 Sluice Gate MT 7.00 145,000.00 1,015,000.00
14 Gate Lifting Mechanism
LS 2.00 300,000.00 600,000.00
Sub Total 7,457,769.78
Total 26,828,190.65
C. Harpan Siltation Dam C1. Dam Repair/Retrofitting
1 Site Clearance m2 0.00 83.00 -
2
Excavation of Earth soil (Including Boulder <3.0m
3
Volume) by equipment
m3 6578.81 116.00 763,142.43
3
Earth Work in excavation in boulder mix soil including disposal up to 10m lead and 1.5m lift
m3 773.98 142.00 109,904.89
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
78
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
4
Earth Work in excavation in hard rock without blasting including disposal up to 10m lead and 1.5m lift
m3 386.99 1,290.00 499,215.89
5
E/W in Backfilling by Ordinary Soil in 15cm thick layer and compaction with sprinkling of water, haulage distance 10m.
m3 773.98 120.00 92,877.38
6 Dry Stone Soling m3 68.89 1,988.28 136,966.07
7
Laying 30cm thick Filter material inclusive haulage up to 10 m and lift up to 1.5m
m2 3025.90 1,360.95 4,118,091.04
8 Boulder Riprap (upto 1.0m Dia. Boulder)
m3 1955.80 1,650.00 3,227,070.00
9 Boulder Riprap (upto 1.2m Dia. Boulder)
m3 1284.12 2,210.00 2,837,905.20
10 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 504.85 4,354.70 2,198,464.17
11
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 34.44 12,070.00 415,731.84
12
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 235.57 12,704.29 2,992,803.06
13
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 997.80 17,101.67 17,064,128.08
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
79
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
14
Providing and Placing M35/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 131.42 19,271.82 2,532,628.43
15
Providing, fixing and removing formworks for Concreting Works.
m2 2067.91 887.09 1,834,425.04
16 Reinforcement works for RCC Concrete.
MT 81.89 117,702.20 9,638,364.21
17
Random Rubble Masonry in 1:4 Cement and sand mortar
m3 291.46 10,368.88 3,022,078.61
18 300mm PCV Water Stop
m 334.25 1,673.65 559,417.51
19 25mm thick Expansion Joint Board
m2 167.13 2,525.05 421,998.98
20 Joint Sealant m2 167.13 1,403.05 234,484.73
Sub Total
52,699,697.56
C 2. Undersluice
1 Dry Stone Solling m3 10.03 1,988.28 19,941.93
2 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 14.56 4,354.70 63,414.66
3
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 5.01 12,070.00 60,529.54
4
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 43.16 12,704.29 548,375.82
5
Providing and Placing M20/40 Cement Concrete machines mixed for
m3 13.76 16,070.85 221,207.24
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
80
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
the wall, column, beam etc., including up to 30m lead.
6
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including upto 30m lead.
m3 262.14 17,101.67 4,483,038.02
7
Providing, fixing and removing formworks for Concreting Works.
m2 409.22 887.09 363,013.03
8 Reinforcement works for RCC Concrete.
MT 19.14 117,702.20 2,253,311.03
9 Stone Masonry Work in 1:4 Cement mortar
m3 4.86 10,368.88 50,423.84
10 300mm PVC Water Stop
m 15.00 1,673.65 25,104.75
11 25mm thick Expansion Joint Board
m2 7.50 2,525.05 18,937.88
12 Joint Sealant m2 7.50 1,403.05 10,522.88
13 Sluice Gates MT 10.00 145,000.00 1,450,000.00
14 Gate Lifting Mechanism
LS 2.00 300,000.00 600,000.00
Sub Total
10,167,820.60
Total
62,867,518.16
D. Lauruk Siltation Dam D1. Dam Repair/Retrofitting
1 Site Clearance m2 0.00 83.00 -
2
Excavation of Earth soil (Including Boulder <3.0m
3
Volume) by equipment
m3 2601.38 116.00 301,760.17
3
Earth Work in excavation in boulder mix soil including disposal up to 10m lead and 1.5m lift
m3 306.04 142.00 43,458.36
4
Earth Work in excavation in hard rock without blasting including
m3 153.02 1,290.00 197,398.90
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
81
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
disposal up to 10m lead and 1.5m lift
5
E/W in Backfilling by Ordinary Soil in 15 cm thick layer and compaction with sprinkling of water, haulage distance 10m.
m3 306.04 120.00 36,725.38
6 Dry Stone Soling m3 20.08 1,988.28 39,927.69
7
Laying 30cm thick Filter material inclusive haulage up to 10 m and lift up to 1.5m
m2 1436.78 1,360.95 1,955,384.33
8 Boulder Riprap (up to 1.0m Dia. Boulder)
m3 848.78 1,650.00 1,400,489.64
9 Boulder Riprap (up to 1.2m Dia. Boulder)
m3 705.60 2,210.00 1,559,376.00
10 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 144.77 4,354.70 630,427.23
11
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including up to 30m lead.
m3 10.04 12,070.00 121,192.15
12
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 67.61 12,704.29 858,936.58
13
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 390.98 17,101.67 6,686,348.31
14
Providing and Placing M35/20 Cement Concrete machine mixed for
m3 50.85 19,271.82 980,051.75
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
82
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
Super Structure, including up to 30m lead.
15
Providing, fixing and removing formworks for Concreting Works.
m2 816.56 887.09 724,359.75
16 Reinforcement works for RCC Concrete.
MT 30.57 117,702.20 3,597,735.88
17
Random Rubble Masonry in 1:4 Cement and sand mortar
m3 125.66 10,368.88 1,302,932.09
18 300mm PCV Water Stop
m 126.00 1,673.65 210,879.90
19 25mm thick Expansion Joint Board
m2 63.00 2,525.05 159,078.15
20 Joint Sealant m2 63.00 1,403.05 88,392.15
Sub Total
20,894,854.41
D 2. Undersluice
1 Dry Stone Solling m3 7.48 1,988.28 14,879.97
2 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 6.57 4,354.70 28,598.60
3
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 3.74 12,070.00 45,165.03
4
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 28.87 12,704.29 366,806.56
5
Providing and Placing M20/40 Cement Concrete machines mixed for the wall, column, and beam etc., including up to 30 m lead.
m3 12.11 16,070.85 194,690.33
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
83
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
6
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including upto 30m lead.
m3 160.00 17,101.67 2,736,283.19
7
Providing, fixing and removing formworks for Concreting Works.
m2 272.94 887.09 242,120.36
8 Reinforcement works for RCC Concrete.
MT 12.06 117,702.20 1,419,404.55
9 Stone Masonry Work in 1:4 Cement mortar
m3 4.86 10,368.88 50,423.84
10 300mm PVC Water Stop
m 15.00 1,673.65 25,104.75
11 25mm thick Expansion Joint Board
m2 7.50 2,525.05 18,937.88
12 Joint Sealant m2 7.50 1,403.05 10,522.88
13 Sluice Gate MT 7.00 145,000.00 1,015,000.00
14 Gate Lifting Mechanism
LS 2.00 300,000.00 600,000.00
Sub Total 6,767,937.93
Total
27,662,792.34
E. Khahare Siltation Dam E 1. Dam Repair/Retrofitting
1 Site Clearance m2 0.00 83.00 -
2
Excavation of Earth soil (Including Boulder <3.0m
3
Volume) by equipment
m3 10036.80 116.00 1,164,269.22
3
Earth Work in excavation in boulder mix soil including disposal up to 10m lead and 1.5m lift
m3 1180.80 142.00 167,673.66
4
Earth Work in excavation in hard rock without blasting including disposal up to 10m lead and 1.5m lift
m3 590.40 1,290.00 761,616.27
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
84
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
5
E/W in Backfilling by Ordinary Soil in 15cm thick layer and compaction with sprinkling of water, haulage distance 10m.
m3 1180.80 120.00 141,696.05
6 Dry Stone Soling m3 129.04 1,988.28 256,569.12
7
Laying 30cm thick Filter material inclusive haulage up to 10 m and lift up to 1.5m
m2 5150.00 1,360.95 7,008,879.63
8 Boulder Riprap (upto 1.0m Dia. Boulder)
m3 2500.00 1,650.00 4,125,000.00
9 Boulder Riprap (upto 1.2m Dia. Boulder)
m3 3180.00 2,210.00 7,027,800.00
10 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 215.10 4,354.70 936,695.22
11
Providing and Placing M10/40 Cement Concrete machine mixed for the foundation, footing etc., including upto 30m lead.
m3 64.52 12,070.00 778,761.83
12
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 1071.25 12,704.29 13,609,468.25
13
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 2140.99 17,101.67 36,614,483.87
14
Providing and Placing M35/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 174.22 19,271.82 3,357,575.72
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
85
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
15
Providing, fixing and removing formworks for Concreting Works.
m2 4680.96 887.09 4,152,435.50
16 Reinforcement works for RCC Concrete.
MT 203.19 117,702.20 23,915,634.59
17
Random Rubble Masonry in 1:4 Cement and sand mortar
m3 2012.06 10,368.88 20,862,797.08
18 300mm PCV Water Stop
m 318.75 1,673.65 533,475.94
19 25mm thick Expansion Joint Board
m2 159.38 2,525.05 402,429.84
20 Joint Sealant m2 159.38 1,403.05 223,611.09
Sub Total 126,040,872.89
E 2. Undersluice
1 Dry Stone Solling m3 4.92 1,988.28 9,791.27
2 30 cm thick. Hard Stone Lining with M25/20 Concrete
m2 11.16 4,354.70 48,594.49
3
Providing and Placing M10/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 2.46 12,070.00 29,719.36
4
Providing and Placing M15/40 Cement Concrete machines mixed for the foundation, footing etc., including upto 30m lead.
m3 20.93 12,704.29 265,962.46
5
Providing and Placing M20/40 Cement Concrete machines mixed for the wall, column, beam etc., including up to 30m lead.
m3 12.56 16,070.85 201,922.21
6
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure,
m3 216.12 17,101.67 3,695,959.55
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
86
S.N. Description of Items Unit Quantity Unit Rate (NRs.) Amount (NRs) Rem
including upto 30m lead.
7
Providing, fixing and removing formworks for Concreting Works.
m2 350.97 887.09 311,340.45
8 Reinforcement works for RCC Concrete.
MT 14.98 117,702.20 1,762,822.97
9 Stone Masonry Work in 1:4 Cement mortar
m3 5.23 10,368.88 54,265.51
10 300mm PVC Water Stop
m 15.00 1,673.65 25,104.75
11 25mm thick Expansion Joint Board
m2 7.50 2,525.05 18,937.88
12 Joint Sealant m2 7.50 1,403.05 10,522.88
13 Sluice Gate MT 10.00 145,000.00 1,450,000.00
14 Gate Lifting Mechanism
LS 2.00 300,000.00 600,000.00
Sub Total 8,484,943.78
Total 134,525,816.67
Note: The cost in this table is without considering miscellaneous cost and VAT.
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
87
Annex:03
FEWA WATERSHED SILTATION DAM Items Rate Summary
Item No. Description of Items Unit Rate (NRs) Remarks
1 Site Clearance/Earthwork
1.1 Site Clearance m2 83.00
1.2
Earthwork Excavation in common materials (Including Boulder <1.5m3
Volume) by equipment m
3 116.00
1.4
Earth Work in excavation in boulder mix soil including disposal up to 10m lead and 1.5m lift
m3 142.00
1.4A
Earth Work in excavation in boulder mix soil including disposal up to 30m lead and 1.5m lift manually
m3 210.00
1.5
Earth Work in excavation in hard rock without blasting including disposal up to 10m lead and 1.5m lift
m3 1,290.00
1.8
E/W in Backfilling by Ordinary Soil in 15cm thick layer and compaction with sprinkling of water, haulage distance 10m.
m3 120.00
1.9
E/W in Backfilling by River Gravel with compaction with sprinkling of water, haulage distance 10m.
m3 240.00
1.10 Impervious Clay (Red Soil) Material Filling m3 1,349.85
2 Soling/filter/Lining Works
2.1 Dry Stone Soling m3 1,988.28
2.2
Laying 30cm thick Graded Filter material inclusive haulage up to 10 m and lift up to 1.5m
m2 1,360.95
2.3
Laying 50cm thick Inverted Filter material inclusive haulage up to 10 m and lift up to 1.5m
m2 1,595.11
2.4 Boulder Riprap (up to 1.2m Dia. Boulder) m3 1,650.00
2.5 Boulder Riprap (up to 1.5m Dia. Boulder) m3 2,210.00
2.6 River Gravel Packing m3 2,581.82
2.7 30 cm thick. Hard Stone Lining M25/20 Cement Concrete m2 4,354.70
2.8
Laying of 50mm thick layer of slate of size 300mm x 300mm and pointing the joints by 1:3 c/m
m2 1,280.00
3 Concrete/Formworks/Reinforcement Works
3.1
Providing and Placing M10/40 Cement Concrete machine mixed for the foundation, footing etc., including up to 30m lead.
m3 12,070.00
3.2
Providing and Placing M15/40 Cement Concrete machine mixed for the foundation, footing etc., including up to 30m lead.
m3 12,704.29
3.3
Providing and Placing M20/40 Cement Concrete machine mixed for the wall etc., including up to 30m lead.
m3 16,070.85
3.4
Providing and Placing M20/20 Cement Concrete machine mixed for the wall, column, beam etc., including up to 30m lead.
m3 16,268.73
3.5
Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 17,101.67
35A
Providing and Placing M30/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 17,743.22
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
88
Item No. Description of Items Unit Rate (NRs) Remarks
35B
Providing and Placing M35/20 Cement Concrete machine mixed for Super Structure, including up to 30m lead.
m3 19,271.82
3.6
Providing and Placing Plum M15/40 Cement Concrete machine mixed for the foundation, footing etc., including up to 30m lead.
m3 10,921.13
3.7
25mm Cement Concrete Flooring in M20/20 cement sand mortar with 20mm gauge stone
m2 522.19
3.8 Providing, fixing and removing formworks for Concreting Works. m2 887.09
3.9 Providing, fixing and removing formworks for Column, height up to 9m
m2 1,328.03
3.10 Reinforcement works for RCC Concrete. MT 117,702.20
4 Masonry Works
4.1 Dry Stone Masonry Work up to 0-5m ht. m3 4,339.23
4.2
Providing and Laying Random Rubble Masonry in mud mortar, lead 30m masoned height 0-5m
m3 4,428.99
4.3
Providing and Laying Random Rubble Masonry in 1:4 Cement and sand mortar
m3 10,368.88
4.4 Providing and Laying Random Rubble Masonry in 1:6 Cement and sand mortar
m3 9,615.38
4.5 Gabion Works m3 4,059.79
4.6 Brick Work in foundation in 1:4 cement and sand mortar m3 16,551.70
4.7 Block Masonry Work in Superstructure in 1:4 cement and sand mortar m3 19,808.25
5 Plastering/Pointing Works
5.1 12mm thick Cement Plaster in 1:4 cement and sand mortar m2 390.45
5.2 20mm thick Cement Plaster in 1:4 cement and sand mortar m2 624.71
5.3 Cement Pointing Work in 1:3 Cement mortar in Stone Masonry Wall m2 290.93
5.4 3mm thick neat cement punning m2 34.73
6 Wood/Glass Works
6.1 Wood works in Chaukhat of Door/Window. m3 254,267.28
6.2 1.5" thick Saalwood Door Shutter. m2 11,745.44
6.3 Glass Shutter for Windows. m2 7,854.45
6.4 False Ceiling with 3 mm plywood m2 4,622.63
7 Painting Works
7.1 Two Coat Water Proof Cement Painting on plastered surface. m2 123.76
7.2
One Coat Enamel Painting over One Coat Priming on Door and Windows.
m2 177.57
8 Roofing Work
8.1 CGI Sheet Roofing works with supply of Materials complete. m2 1,214.58
8.2 Making CGI Sheet ridge including supply of material, fixation etc. m2 880.28
8.3 Steel pipe truss for CGI sheet roofing Kg 246.63
9 Road Works
9.1 Subgrade Construction and preparation of Formation in cutting (Excluding Rock Excavation) including disposal of material upto 10m
m3 122.93
9.2
Subgrade Construction and preparation of Formation in Rock cutting with regulation course of natural materials
m3 1,411.53
9.3
Providing, Laying, Spreading, watering, levelling and Compaction of crusher run material as sub-base course grading SB1 lead upto 10m
m3 2,281.27
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
89
Item No. Description of Items Unit Rate (NRs) Remarks
9.4
Providing, Laying, Spreading, watering, levelling and Compaction of crusher run material as base course lead upto 10m
m3 2,649.83
9.5
Providing and Placing of 1.60m dia. RCC Pipes with or without collars, jointed with cement mortar in the proportion of 1:2 lead upto 100m
rm 28,712.68
9.6
Providing and Placing of 0.60m dia. RCC Pipes with or without collars, jointed with cement mortar in the proportion of 1:2 lead upto 100m
rm 10,766.79
9.7
Providing and Placing of 0.45m dia. RCC Pipes with or without collars, jointed with cement mortar in the proportion of 1:2 lead upto 100m
rm 9,310.98
9.8
Providing and Placing of 0.30m dia. RCC Pipes with or without collars, jointed with cement mortar in the proportion of 1:2 lead upto 100m
rm 8,188.39
9.9
Providing, jointing and laying 110mm dia. HDP Pipes with or without collar etc. complete in place for Weep Hole and Sub Surface
rm 735.94
9.10 Providing, jointing and laying 160mm dia. HDP Pipes with or without collar etc. complete in place for Sub Surface
rm 1,648.34
10 Miscellaneous Items
10.1 300 mm PVC Water Stopper rm 1,673.65
10.2 25mm thick Expansion Joint Board (Saltax Board) m2 2,525.05
10.3 Joint Sealant m 1,403.05
10.4 Barbed Wire Fencing with Wooden Post m 1,629.29
10.5 Barbed Wire Fencing with Angle Iron Post m 1,187.67
10.6 Providing and Laying and fixing of Geo-textile (Filter Fabrics), lead 30m m2 148.62
10.7 Flat iron grill in windows with red oxide paint Kg 143.00
10.8 Glazed tile in kitchen and bathroom in 1:4 Cement Sand m2 2,759.34
A REPORT ON FEWA WATERSHED SILTATION DAMS PROBLEMS AND MITIGATION MEASURES 2020
90
Annex 04: Sample Design Drawings for Repair/Retrofitting