a preliminary look at peak loads and resources for 2007 and policy issues to consider
DESCRIPTION
Energy Action Plan. A Preliminary look at Peak Loads and Resources for 2007 and Policy Issues to Consider. David Ashuckian, P.E., Manager Electricity Analysis Office Joint Meeting December 11, 2006. Topics of this presentation. Review of 2006 weather adjusted demand. - PowerPoint PPT PresentationTRANSCRIPT
A Preliminary look at Peak Loads and Resources for 2007 and Policy Issues to Consider
David Ashuckian, P.E., ManagerElectricity Analysis Office
Joint MeetingDecember 11, 2006
Energy Action Plan
Energy Commission 2December 11, 2006
Topics of this presentation
Review of 2006 weather adjusted demand.
Preliminary look at Probability of meeting reserve margins in 2007.
Policy issues regarding the use of Demand Response and Interruptibles.
Review of CA ISO Emergencies called over the last 5 years and possible options for reducing frequency.
Energy Commission 3December 11, 2006
2006 Weather Adjusted Actual Loads
2006 ISO summer daily peak tracking
25,000
30,000
35,000
40,000
45,000
50,000
55,000
6/15
6/17
6/19
6/21
6/23
6/25
6/27
6/29 7/
17/
37/
57/
77/
97/
117/
137/
157/
177/
197/
217/
237/
257/
277/
297/
31 8/2
8/4
8/6
8/8
8/10
8/12
8/14
8/16
8/18
8/20
8/22
8/24
8/26
8/28
8/30 9/
19/
39/
59/
79/
99/
119/
139/
15
MW
2006 actual
2006estimated
Estimate based on 2005 weather-load relationship,2006 observed weather and 2005 IEPR growth rate
Energy Commission 4December 11, 2006
2007 Preliminary Outlook - Statewide
2007 Summer Monthly Outlook California Statewide
Resource Adequacy Planning Conventions June July August September
1 Existing Generation1 57,897 57,897 57,897 57,8972 Retirements (Known) 0 0 0 03 High Probability CA Additions 0 0 0 0
4 Net Interchange 2 13,118 13,118 13,118 13,1185 Total Net Generation (MW) 71,015 71,015 71,015 71,015
6 1-in-2 Summer Temperature Demand (Average)3 57,125 59,726 60,350 59,4197 Demand Response (DR) 524 524 524 5248 Interruptible/Curtailable Programs 1,603 1,603 1,603 1,603
9 Planning Reserve428.0% 22.5% 21.2% 23.1%
Expected Operating ConditionsTotal Net Generation (MW) 71,015 71,015 71,015 71,015
10 Outages (Average forced + planned) -2,695 -2,695 -2,695 -2,695
11 Zonal Transmission Limitation5 -150 -150 -150 -150
12 Expected Operating Generation with Outages/Limitations6 68,170 68,170 68,170 68,170
13 Expected Operating Reserve Margin (1-in-2)724.5% 17.7% 16.2% 18.5%
Adverse Conditions14 High Zonal Transmission Limitation -250 -250 -250 -25015 High Forced Outages (1 STD above average) -1,160 -1,160 -1,160 -1,16016 1-in-10 Summer Temperature Demand 60,573 63,330 63,992 63,005
17 Adverse Scenario Reserve Margin7 12.8% 6.7% 5.3% 7.4%
18 Adverse Scenario Reserve Margin w/DR and Interruptibles8 17.2% 10.9% 9.4% 11.6%19 Resources needed to meet 7.0% Reserve (W/DR & Interruptibles) 0 0 0 020 Surplus Resources Above 7.0% Reserve (W/DR & Interruptibles) 4,923 1,972 1,264 2,320
21 Existing Aging Generation Without Capacity Contracts9-2,070 -2,070 -2,070 -2,070
Energy Commission 5December 11, 2006
2007 Preliminary Outlook - Probability of meeting reserve margins for CA ISO Control area
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0%5%10%15%20%25%30%35%
Operating Reserve Margin
Cu
mu
lati
ve
Pro
ba
bil
ity
Existing plus proposed additional peakers, demand response, and interruptible load
Existing resources, demand response, and interruptible load
Sta
ge
3
Sta
ge
2
Sta
ge
1
Energy Commission 6December 11, 2006
2007 Preliminary Outlook - Probability of meeting reserve margins for CA ISO Control area
60%
70%
80%
90%
100%
0%1%2%3%4%5%6%7%8%9%10%
Operating Reserve Margin
Cu
mu
lati
ve
Pro
ba
bilit
y
Existing plus proposed additional peakers, demand response, and interruptible load
Existing resources, demand response, and interruptible load
80.5% (1-in-5)
Stage 1Demand
ResponseStage 2
Interruptibles
Stage 3Firm LoadShedding
84.1% (1-in-6)
94.7% (1-in-19)
90.2% (1-in-10)
99.7% (1-in-333)
98.7% (1-in-77)
Energy Commission 7December 11, 2006
2007 Preliminary Outlook - Probability of meeting reserve margins for SP 26
40%
50%
60%
70%
80%
90%
100%
0%1%2%3%4%5%6%7%8%9%10%
Operating Reserve Margin
Cu
mu
lati
ve
Pro
ba
bil
ity
Existing plus proposed additional peakers, demand response, and interruptible load
Existing resources, demand response, and interruptible load
52.7% (1-in-2.1)
Stage 1Demand
ResponseStage 2
Interruptibles
Stage 3Firm LoadShedding
59.5% (1-in-2.5)
78.2% (1-in-5)
62.6% (1-in-2.7)
99% (1-in-100)
93.3% (1-in-15)
Energy Commission 8December 11, 2006
Policy Issues that have surfaced
Generators have complained that Demand Response is not being called often enough.
Program operators concerned that excessive use of DR and Interruptibles will result in customers dropping out of program.
Energy Commission 9December 11, 2006
Summary of CA ISO load Curtailments over the Last 5 years
Total number of Firm Load curtailments that have occurred over last 5 years: 2 (two) March 8, 2004 August 25, 2005
Total number of Non-Firm (interruptible) load curtailments that have occurred over the last 5 years: 11 (eleven) 2002 (3) - June 18 (SP 26), July 10, September 3. 2003 (0) - 2004 (4) - March 8 (SP26), May 3 (SP26), July 20 (SP26),
September 14 (Humboldt). 2005 (3) - July 21 (SP26), July 22 (SP26), August 25 (SP26). 2006 (1) - July 24.
Energy Commission 10December 11, 2006
0
1
2
3
4
5
2002 2003 2004 2005 2006
Nu
mb
er o
f Eve
nts
Total Events MOW greater than Curtailment Forecast Deviation greater than Curtailment
Summary of CA ISO load Curtailments over the Last 5 years
Energy Commission 11December 11, 2006
Policy issues to consider:
How can we tell when the number of load curtailments is excessive?
Because DR and Interruptibles do not reduce the probability of emergencies being called, Is the CA ISO getting a bad rap? Is the public being alerted when there may not be a true emergency?
What are some possible options to address these issues?
Energy Commission 12December 11, 2006
Possible option to reduce number of emergencies: Add More Generation
Increase Resource Adequacy requirements. Change Planning criteria from 1-in-2 to 1-in-10.
Pros: - Provides more generation. - Increases reserve levels at all times.
Cons: - Additional cost (at all times). - Resources not likely to be used frequently. - Likely to have only minimal effect on reducing the
number of emergencies as most emergencies declared with additional generation available.
Energy Commission 13December 11, 2006
Possible option to reduce number of emergencies: Add More DR and Interruptibles
Direct LSE’s to expand DR and increase number of Interruptible customers.
Pros: - Provides greater reserve margins once emergency is called.
- Reduces need for additional generation resources. Cons: - Additional cost (at all times).
- Likely to have minimal effect on reducing the number of emergencies as resources are called
after an emergency is declared.
Energy Commission 14December 11, 2006
Possible option to reduce number of emergencies: Change tariffs
Change DR and/or Interruptible tariffs to allow use before emergency is declared.
Pros: - Reduces probability of emergencies being called. - Better Alignment of these resources with Loading Order. - Public is altered less, only for true emergencies and may be more apt to respond.
Cons: - May increase the frequency of use of these resources.
- May reduce customer participation.
Energy Commission 15December 11, 2006
Questions that might provide additional insight:
How many hours have interruptibles been called over the last 5 years?
How many times has an individual customer been interrupted over the last 5 years?
How have customers’ interruption histories compared with their agreements?
Staff efforts are ongoing to gather additional information and data.