a new approach

17

Upload: ezra

Post on 10-Jan-2016

24 views

Category:

Documents


1 download

DESCRIPTION

A NEW APPROACH. WHAT CAUSED THE MAINE DOT TO CONSIDER CBE?. LACK OF COMPETITION VOLITILE MATERIAL COST LACK OF FUNDING CONTRACTOR TAKING ADVANTAGE OF LUMP SUM ITEMS AND ERRORS IN PLANS INCREASE IN NUMBER AND COST OF CONTRACT MODIFICATIONS. WHY SHOULD MAINE DOT USE CBE. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: A NEW APPROACH
Page 2: A NEW APPROACH
Page 3: A NEW APPROACH

LACK OF COMPETITIONLACK OF COMPETITION

VOLITILE MATERIAL COSTVOLITILE MATERIAL COST

LACK OF FUNDINGLACK OF FUNDING

CONTRACTOR TAKING ADVANTAGE OF LUMP SUM CONTRACTOR TAKING ADVANTAGE OF LUMP SUM ITEMS AND ERRORS IN PLANSITEMS AND ERRORS IN PLANS

INCREASE IN NUMBER AND COST OF CONTRACT INCREASE IN NUMBER AND COST OF CONTRACT MODIFICATIONSMODIFICATIONS

Page 4: A NEW APPROACH
Page 5: A NEW APPROACH
Page 6: A NEW APPROACH
Page 7: A NEW APPROACH

Reviewing the plans for constructibility will create Reviewing the plans for constructibility will create better plans and will result in better prices.better plans and will result in better prices.Increase Credibility of the DepartmentIncrease Credibility of the DepartmentReview and Verify bid Quantities and SpecificationsReview and Verify bid Quantities and SpecificationsMarket AnalysisMarket AnalysisMaterial Cost AnalysisMaterial Cost AnalysisReview Contract Documents from Consultant Design Review Contract Documents from Consultant Design FirmsFirmsAssist in the defense of claimsAssist in the defense of claimsAbility to question contractors bidding practicesAbility to question contractors bidding practicesTrain MDOT designers and construction personnelTrain MDOT designers and construction personnelAssist Residents in validating contract modificationsAssist Residents in validating contract modifications

Page 8: A NEW APPROACH
Page 9: A NEW APPROACH

Eliminate Existing 600

mm CMP

Page 10: A NEW APPROACH
Page 11: A NEW APPROACH

Cost Estimate Report

The additional estimated cost of using PGAB 58-34 in lieu of the traditional PGAB 64-28 for a MDOT project located in Jackman and Long Pond TWP, Maine.

February 2006

Page 12: A NEW APPROACH

AN EXAMPLE OF A SUBTLE UNBALANCE BID;A $10 MARK-UP COST $30,000THE 3,000 HRS OVER-RUNS 37% TO 4,167 HRSTHE $30,000 INVESTMENT RESULT IN A $41,670 RETURN

Page 13: A NEW APPROACH
Page 14: A NEW APPROACH
Page 15: A NEW APPROACH
Page 16: A NEW APPROACH

206.061 Structural Exc-Below Grade;

5,850 cy @ $8/cy = $46,800

Page 17: A NEW APPROACH