a method to increase the integration capacity of dg on weak distribution network
DESCRIPTION
A method to increase the integration capacity of DG on weak distribution network. Sami Repo Tampere University of Technology FINLAND. Problem of weak distribution network. Weak medium voltage (MV) network length of 20 kV feeders may be 100 km demand in sparsely populated areas is very low - PowerPoint PPT PresentationTRANSCRIPT
1Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
A method to increase the integration capacity of DG on
weak distribution network
Sami Repo
Tampere University of Technology
FINLAND
2Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Problem of weak distribution network
• Weak medium voltage (MV) network– length of 20 kV feeders may be 100 km– demand in sparsely populated areas is very low
=> impedance of feeders may be remarkably high
• Integration of DG is limited by voltage rise– problems may occur during low demand periods– acute in coastal and skerries areas due to wind
power installations
3Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Proposed method to increase the integration capacity of DG units
1. Meshed operation of distribution network– MV networks are constructed meshed for reasons
of reliability, but operated radially
2. Control of DG unit active and reactive power– based on terminal voltage at the case studied – consumption of reactive power is used to limit the
voltage rise problem when necessary– the production of active power must also be
limited, if this is not enough
4Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Meshed operation of MV network
• will divide power flows to the feeders more evenly than radial operation
• losses will be minimised
• voltage rise due to DG can be limited
• may allow more enhanced control and operation principles than today
• should be taken into account in most potential areas of DG in long-term planning studies
5Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Protection of meshed MV network
• When a fault occurs the task is to indicate and locate the faulty ring (see session 3 paper 25)
• Ring is opened using fast switch-disconnectors
• Conventional feeder protection may operate
• The amount of load interrupted due to the fault is the same as in a radially operated network
• Extra delay must be allowed for in the protection
7Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Study case data
Wind power units:• connected 22 km away
from HV/MV substation
• 4*750 kW• frequency converters• power factor control
between 0.92 - 1.00 ind. or cap.
Network data:• Upper limit of MV
voltage is 21 kV• Maximum production
capacity is 1.1 MW
Loads:• real hourly load curves
and customer data (annual energy and customer type)
8Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Network transfer capability
Load ofKasnäsfeeder [kW]
Maximumproduction [kW]
Radial Ring
Reactive power ofgenerator [kVar]
Radial Ring
364 1120 1900 -480 -810
572 1300 2100 -553 -895
825 1550 2500 -660 -1065
1174 2000 2900 -852 -1150
9Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Energy production capability- initial data
0 5 10 150
100
200
300
400
500
Wind speed [m/s]
Fre
quen
cy
0 500 1000 1500 2000 2500 30000
200
400
600
800
1000
Power output [kW]
Fre
quen
cy
0 1000 2000 3000 4000 5000 6000 7000 8000300
400
500
600
700
800
900
1000
1100
1200
Time [h]
Load
[kW
]
Load duration curve 1Load duration curve 2Load duration curve 3
Minimum load = 364 kW
Maximum load = 1174 kW
10Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Energy production capability- test results
1528 1556 1591
56
2
58
5
61
4
36
,6
47
,8
60
,8
0
200
400
600
800
1000
1200
1400
1600
1 2 3
Load duration curves
Ele
ctri
city
no
t p
rod
uce
d [
MW
h]
3 MW
2.25 MW
1.5 MW
321
356
389
11,5 22,9
34,2
0 0 00
50
100
150
200
250
300
350
400
1 2 3
Load duration curves
Ele
ctric
ity n
ot p
rodu
ced
[MW
h]
3 MW
2.25 MW
1.5 MW
Radial Ring
11Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Conclusions
• Integration capacity of DG on weak MV network may be increased by proposed method– no centralised control system or operator
interaction is needed to operate the network
– it may be concluded by DG unit terminal voltage
• Requirements of the method are possibility– to operate network as a ring with fast switch-
disconnector
– to control active and reactive power of DG unit
12Sami Repo Finland Session 4 – Block 4
Barcelona 12-15 May 2003
Practical issues
• Possibility to control the integration capacity should be considered in interconnection contract
• Proposed method is quite different from the "minimum load maximum production" planning principle because the integration capacity is flexible and dependent on network conditions
• Further research is needed to clarify impacts on power quality and to extend studies to more complex systems