a conceptual framework of project risk management

Upload: swati-oza

Post on 08-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    1/16

    A CONCEPTUAL FRAMEWORK

    OF

    PROJECT RISK MANAGEMENT

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    2/16

    SYNOPSIS:

    INTRODUCTION TO PROJECT RISKMANAGEMENT.

    OBJECTIVE OF PROJECT RISK MANAGEMENT.

    NEED FOR RISK ANALYSIS.

    10 GOLDEN RULES OF PROJECT RISKMANAGEMENT

    ELEMENTS OF RISK MANAGEMENT.

    RISK MANAGEMENT PLAN.

    THE RISK MANAGEMENT PROCESS.

    CLASSIC MISTAKES OCCUR IN SOFTWAREPROJECT DEVELOPMENT.

    CONCLUSION.

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    3/16

    INTRODUCTION :

    What is a Project?A project is a temporary endeavor undertaken to produce a

    unique product or service

    What is a Risk?

    A risk is any anticipated unfavorable event that can occurwhile a project is ongoing.

    What is a Project Risk Management?

    It is an art and science of identifying ,analysing andresponding to risk throughout the project and in the bestinterest of meeting project objective

    Temporary Characteristics ofProjects

    Unique

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    4/16

    OBJECTIVE OF PROJECT RISK MANAGEMENT:

    The broad objectives of the project risk managementprocess are :

    Survival of the organization.

    Efficiency in operations.

    Uninterrupted operations.Continued growth .

    Enhance the capability of the organization.

    Extend the organizations overall risk management

    processes to projects, and apply them in a consistent way.

    Enhance the management of projects across the

    organization and obtain better project outcomes, in all

    respect.

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    5/16

    NEED FOR PROJECT RISK MANAGEMENT

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    6/16

    10 GOLDEN RULES OF PROJECT

    RISK MANAGEMENT

    1. Make Risk Management Part of Your Project

    2. Identify Risks Early in Your Project

    3. Communicate About Risks

    4. Consider Both Threats and Opportunities5. Clarify Ownership Issues

    6. Priorities Risks

    7. Analyze Risks

    8. Plan and Implement Risk Responses

    9. Register Project Risks

    10. Track Risks and Associated Tasks

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    7/16

    ELEMENTS OF RISK MANAGEMENT

    The job of Project Risk management is to identify,

    address and eliminate sources of risk before they

    become threats to completion of a project.Different elements of risk management are:

    Crisis management.

    Fix on failure .

    Risk mitigation.

    Prevention.

    Elimination of root causes.

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    8/16

    RISK MANAGEMENT PLAN:

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    9/16

    RISK IDENTIFICATION: Identify all the possible riskevents that could affect the project.

    RISK ASSESSEMENT: Assess each risk in terms of probability,impact severity and controllability.

    For risk assessment, each risk should first be rated in two ways:1.The likelihood of a risk coming true (r).2. Severity of damage caused due to the risk becoming true (s).Based on these two factors, the priority of each risk can be

    computed as :p = r * s

    3 MAIN CATEGORIES OF

    RISK

    PROJECTRISK

    TECHNICALRISK

    BUSINESSRISK

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    10/16

    RISK DEVELOPMENT: Develop a strategy and/or

    contingency for responding to each risk.

    RISK CONTAINMENT: This involve monitor and control

    risks dynamically. Different risks require different

    containment procedures.3 MAIN STRAYEGY USED FOR

    RISK CONTAINMENT

    Avoid the risk Transfer the risk Risk reduction

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    11/16

    PROJECT RISK MANAGEMENT

    PROCESSES

    It help project teams make informed decisionsregarding alternative approaches to achievingtheir objectives and the relative risk involved ineach project.

    Risk management encourages the project team totake appropriate measures to:Minimize adverse impacts to project scope, cost,

    and schedule.Maximize opportunities to improve the projects

    objectives with lower cost, shorter schedules, andhigher quality.

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    12/16

    PROJECT RISK MANAGEMENT

    PROCESSES

    Fig.: The Project Risk Management Process

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    13/16

    CLASSIC MISTAKES OCCUR IN

    SOFTWARE PROJECT DEVELOPMENT:

    What is classic mistake?

    Some ineffective practices chosen by many people who

    produce predictable and unpredictable bad results, during

    and at the end of the project are known are classicmistakes.

    The main effect of these mistakes is, you wont get rapid

    development.

    Once if these mistakes are analyzed, it can be used with

    project planning and risk management which will

    definitely help the development speed of project.

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    14/16

    Classic mistakes have been divided along the development dimensions

    of people, process, product and technology.

    PEOPLE RELATED

    MISTAKES

    PROCESSED

    ORIENTED

    MISTAKES

    PRODUCT

    RELATED

    MISTAKES

    TECHNOLOGY

    RELATED

    MISTAKES

    y Undermined

    motivation

    y Weak personnel

    y Uncontrolled

    problem employees

    y Heroics

    y Noisy, crowded

    offices

    y Friction between

    developers and

    customers

    y Unrealistic

    expectations

    y Lack of user-input

    y Wishful thinking.

    y Overly optimistic

    schedules

    y Insufficient risk

    management

    y Contractor failure

    y Insufficient

    planning

    y Wasted time

    during the fuzzy

    front end

    y Shortchanged

    upstream activities

    y Inadequate design

    y Requirement

    gold-plating

    y Feature creep

    y Developer gold

    platting

    y Push-me, pull-

    me negotiation

    y Research

    oriented

    development

    y Silver bullet

    syndrome

    y Overestimated

    savings from new

    tools or method

    y Switching tools in

    the middle of the

    project

    y Lack of automated

    source-code control

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    15/16

    CONCLUSION:

    As the problem and risk faced by each project are unique, soit is not possible to prescribe a standard format.

    A good project risk management within an organization hasthe following characteristics:

    (a) Project risk management activities commence at theinitiation of the project, risk management plans are developedand risk management continues throughout the project lifecycle.

    (b) Project risk management is not a discrete stand-alone

    process, but is integrated with other project managementfunctions.(c) The implementation of project risk management is the

    responsibility of all project stakeholders and they participateactively in the process.

  • 8/6/2019 A Conceptual Framework of Project Risk Management

    16/16

    THANK YOU