a b c d e f 1 rfp/2014/647 rfp/2014/647 msrp finance ... · 1 2 3 4 a b c d e f rfp/2014/647...
TRANSCRIPT
1
2
3
4
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
3 General General Terms of Reference 6.3.5.1 Resume of
proposed personnel. As signature is
required then it is expected to have
scanned pages as appendixes ?
Yes, scanned and attached, to be submitted along with technical
proposal.
4 General General Terms of Reference Annex B Appendix I -
Technical Response Format. 6.Technical
Response to RFP. "the submitted
technical response must stricly adhere to
the rules and format"… It does mean
answers should follow the tables
structure provided in the same
document (like 6.3.4 overal approach an
implemetation plan in a table of 5 cells)
or it is enough to follow the format in
terms of item content without the tavbe
stucture for the responce ?
It is enough to follow the format in terms of item content and
sequence without the table stucture for the response.
Page 1 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
5
6
7
8
5 General General Terms of Reference: page 3 6.3.4 (for all
lots) application specific approach and
implementation plan. Is it required to
respond points 1 to 7 for each module?
Meaning 29 assesments, approaches,
scope of tasks and implementation
plans? What is the content of the
answers expected at this level?
A vendor bidding for Lot 1 should submit a consolidated overall
master project plan.
In addition, for each application in the list, bidder must respond to
points 1 to 7, with a maximum possible application-specific
approach and implementation plans per Lot as follows:
Lot 1 - 25
Lot 2 - 2
Lot 3 - 2
Note that a separate technical response must be submitted per Lot.
Refer to Annex B - Appendix I, para 1.
"Vendors are expected to write full answers for each requirement
... Additional references may be attached as necessary, however
unnecessarily lengthy documents are discouraged."
6 General General Terms of Reference 6.4.1. Is there an
specific calculation formula used to
measure the technical criteria? % Weight
of Project Approach compared , %
Proposed Personnel , Understanding,
Company qualifications, etc
Yes, weighted scoring methodology will be used for each of the
criteria mentioned in Cover letter 2.5.2
7 General General Please let us know if there are any major
inflight project that may impact the
upgrade timelines
On depencies, see:
7 83
Please refer to paragragh "Dependency" of section Statement of
purpose of the TOR (Annex B Section 1, para 5)
8 General General Please provide high level phase-wise
time line for HCM 8.9 to 9.2 upgrade See also: 8 9 30 83
114 115
Tentative Go-live by Q1 2016
Page 2 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
9
10
11
12
13
9 General General Please let us know when is HCM9.2
upgrade is expected to go-live
See also: 8 9 30 83
114 115
Refer to Q&A: 8
10 General General In reference to "Annex B - Terms of
Reference" Section 4- RFP mentions 12
month of Implementation + 3 month of
prod support + 3 month of
implementation of new features, IT also
mentions that beyond first three month
of support, some support would be
required for year end activities. Going by
the constraint of going live maximum by
Jun-2016, 3 month warranty support
would end in Sep-16. Please let us know
if you foresee support required beyond
Sep-2016 till Jan-2017?
Yes, if the proposed Go-live period goes beyond Sep 2016. Bidder
may submit change order rates schedule that could be used for
additional post implementation support, as needed.
UNHCR has established a 12-month implementation (construction
to go-live) window
followed by a post go-live support for the three (3) months
immediately following go-live
and an additional three (3) months to be used within one year
following the roll-out for
other key processing milestones such as year-end support.
11 General General Please let us know if you are open for
any other solution option for Lot1?
See also: 11 131
Yes, provided that the vendor could demonstrate that the
alternative approach is better.
Also see QA131
12 General General Please confirm if you intend to convert
all crystal reports to XML publisher or
continue using crystal reports.
See also: 12 87 128
Yes. Refer to Work Package 07e deliverables.
13 General General During your assessment have you
prepared any list of customization which
will be potentially be removed in 9.2
upgrade OR do you want vendor to
indicate that as part of RFP response
Prelimiray assessment has been conducted, it however needs
further detailed analysis during the Implementation and Build
phase (i.e. this RFP)
Page 3 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
14
15
16
17
14 General General In reference to "Annex B - Appendix I -
Technical Response Format" Section
6.3.4 -'For all lots, for each application' -
Request you to please share the
expectation from subsection '3 scope of
task' and how it is different from '2
Assessment of need'
Refer to: Technical Response, section 6.3.4, approach and
implementation plan.
Assessment of needs : here you describe your understanding of the
requirements, including the nature of activities required in order to
deliver the solution.
Scope of the tasks: Describe in detail the scope of task for meeting
the needs
15 General General In reference to "Annex B - Appendix I -
Technical Response Format" Section
6.3.6 - Please let us know if we can have
a 3 separate stand alone documents for
each lot explaining our response for each
work package. These will be supplement
documents of 3 main technical responses
Yes. You should submit three (3) documents in this case, one per
lot.
Refer to Annex B - Appendix I, para 1.
"A separate technical response must be submitted for each Lot."
16 General General In reference to "Annex B - Appendix I -
Technical Response Format" Section
6.3.5.2 - Please let us know what is the
expectation from subsection 2- Profile
See also: 16 17
For each project role (examples: Project Manager, Functional
Consultant, Developer, Sr. Developer, Technical Architect),
subsection 2 will be repeated/appended to include all proposed
personnel for the project.
17 General General In reference to "Annex B - Appendix I -
Technical Response Format" Section
6.3.5.2 - We understand for each project
role (e.g. Project Manager, Functional
Consultant, Developer, Sr. Developer)
subsection 2 will be repeated
See also: 16 17
For each project role (examples: Project Manager, Functional
Consultant, Developer, Sr. Developer, Technical Architect),
subsection 2 will be repeated/appended to include all proposed
personnel for the project.
Page 4 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
18
19
20
18 General General In reference to "Annex B - Appendix I -
Technical Response Format" Section
6.3.4 - 'For Lot1 (Summary)' subsection 3
'Implementation Plan'. RFP states "This
should incorporate work and deliverables
from Lot 2 and Lot 3". We undestand this
will include standalone Implementation
plan for each lots in respective Technical
response document. example:- Lot 1
response will have implementation plan
for Lot 1 only, Lot 2 response document
will have implementaion plan for Lot2
only and Lot 3 response will have
implementation plan for Lot 3 only.
Please confirm
As specificed in the ToR, bidder for Lot1 (Prime Vendor) is
responsible for coordination activities within its lot as well as with
other Lots for interdependent activities. As part of the
engagement, the Prime Vendor must ensure the integration of all
activities, incorporate/consolidate the implementation plan for all
three (3) lots into a master project plan.
As such, in addition to stand-alone implementation plans for each
application in Lot 1, the bidder for Lot1 must include a higher-level
implementation plan.
See work packages.
19 General General We do not see the break up of estimation
required for Tech Architecture in "Annex
C - RFP 2014-647 Financial Offer
Form.xlsx" . Please let us know how do
you want the break up of efforts for tech
architecture implemementation - This
cannot be divided over lots as this will be
a seperate effort for all lots
UNHCR has a hosting service provider with whom the project
should collaborate to ensure proper hardware sizing and setup.
The system integrator for each lot will be responsible for ensuring
proper installation/setup/technical architecture, providing
guidance is necessary, and will be responsible for the maintenance
during the period of the engagement.
20 General General The RFP cover letter states UNHCR is
exempt from all direct taxes and customs
duties. Please confirm if vendors and its
consultants deputed Onsite (under work
visa) for UNHCR engagements are also
exepmted to pay Income Tax in
Switzerland
The tax exemption relates to UNHCR payments to the supplier. For
further inquiries please consult the Swiss authorities.
Page 5 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
21
22
23
24
25
26
21 General General The RFP cover letter states same price for
3 years, can we provide three different
prices covering each of the year
Financial offers are required by deliverables and the offers should
remain valid for the duration of the project.
22 General General The RFP cover letter states other UN
agencies can leverage the prices of
successful bidder from UNHCR
agreement, can the same be applied in
the reverse context, wherein UNHCR
leverages existing contract of the bidder
with other UN agencies
Generally speaking yes, however it is subject to the agreement
between the other UN agency and the vendor.
23 General General The RFP cover letter mentions sharing of
CV of core staff. Please clarify which
resources to be considered as core staff
for which CV need to be provided
CVs of all proposed personnel
24 General General TOR states contract will be awarded to
single or JV or Consortium vendor for
each Lots singlely or completely. In
relation to this, can a bidder provide
multiple responses - Single and under JV
/ Consortium and still be eligible for
consideration under each lot category
singlely as well as under JV / Consortium
No. Only one response (per lot) is needed, even if bidding as part of
consortium. The responses will be evaluated per lot (as a single lot
bid) in any case.
See Annex B - Appendix I -Technical_Response_Format, section
6.4.1
25 General General In case a bidder bids for one or two lots
singlely, then is it mandatory to have
prior relationship with successful primary
vendor
No.
26 General General For the consultants to be deputed onsite,
can you confirm what kind of visa / work
permit and support will be provided by
UNHCR
UNHCR will provide a Letter of Attestation for the issuance of the
visa. Further requirements need to be settled by the vendor.
Page 6 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
27
28
29
30
31
27 General General Is it mandatory to have French speaking
consultants
Working language is English, knowledge of French an asset
28 General General Supplier Registeration - RFP Letter
Section 2.5.1 - Submission of Documents
for supplier registeration should be done
along with final submission or can be
done earlier to it.
Please provide them together with your submission, as stated in
the Cover Letter.
29 General General Financial - RFP Letter section 2.5.2 - Can
you share the current UN exchange rate
for USD & Euro conversion, for our
understanding and evaluation
Please follow the link for the current conversion rate:
http://treasury.un.org/operationalrates/Default.aspx
30 General General TOR - Section 1 - The upgrade of
Peoplesoft HCM (from 8.9 to 9.2)
understand is a spearate project. Please
confirm the planned date of go live for
same.
Please let know if this is undertaken by
UNHCR internal team or alternate
vendor, ensuring we can prepare
cooridnation plan accordingly. See also: 8 9 30 83
114 115
Tentative Go-live by Q1 2016. It's undertaken by UNHCR staff with
the assistance of a consultancy firm.
Coordination work must be discussed/cleared via the UNHCR HCM
project team.
31 General General TOR - Section 1 Lots - Please confirm the
bolt-ons elements to replace Peoplesoft
EPM.
The RFP currently states Bolt-on
applications to be developed
supplementing certain functionality of PS
EPM, please let know depending upon
feasibility can one or all of these bolt-on
can be implemented in Hyperion
Planning Lot-2
Refer to Annex B - Appendix II - Application Overview - Lot1 - Bolt-
on…
Page 7 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
32
33
34
32 General General Section 2.1 - mentions that this upgrade
project will address existing deficiences
and will facilitate compliance with UN
financial regulations and rules. Are there
any specific compliance scenarios as per
IPSAS that need to be covered.Request
you to please provide update on the
deficiences / changes expected
Refer to Annex B - Appendix II, challenges and pain points.
33 General General Section 2.1 - mentions introduction of
operational and business efficiencies
including the automation or elimination
of a number of manual activities
currently required to comply with IPSAS.
Also, there is mention of centralization
(regionalization) of some functions. It
would if you can give some examples
relating to the same
Examples of challenges include: dual accrual and (modified) cash
basis recording, capturing of ancillary costs/systematic inclusion of
transport costs for asset and inventory purchases, centralization of
payment approval at the regional level, decentralization of
payments at country level, implementation of workflow approval
framework across the MSRP applications suite.
For more information, refer to Annex B - Appendix II, challenges
and pain points.
34 General General Section 2.3 - mentions expectation of
improved donor reporting. Please specify
if this reporting is expected from PS or
Hyperion
While most of the reporting for donors is anticipated to come from
PeopleSoft, reports may have to be generated from both systems
depending on the needs.
This is covered in Work-packages 02 and 07 e) of Lot1 and Lot2.
Page 8 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
35
36
37
35 General General Section 3.1 - It is mentioned that for each
of the 3 requirements in scope of this
RFP, Fit-Gap and Keep Drop Analysis has
been prepared. It would help if the same
can be provided.
See also: 35 37
Preliminary Fit-Gap and Keep-drop analyses have been performed
and documented. This will be shared with selected bidder(s)
during the due diligence process. Further detailed analysis to be
performed in the RFP Work-package 02 (including but not limited
to their review, revalidation, revision, finetuning, completion).
36 General General Section 3.3 - Is it safe to assume for Lot 2
implementation the primary work
location will be Geneva, with no
expected travel to Budapest.
If travel to Budapest (for coordination
with technical team) needs to be
considered, please let know expected
ratio of working between Geneva and
Budapest. Also, is it safe to assume that
this travel if required would be billed /
As part of its proposed implementation plan, bidder must submit
the expected ratio of working / coordinating with UNHCR technical
team in Budapest and include this in the proposal (technical and
financial).
It is irrelevant to provide the details of UN travel rules at this point
in time.
37 General General Please share Fit-Gap/Keep-Drop analysis,
traceability matrix or any other relevant
documents that are available, that were
prepared as part of the recently
concluded concenptual design phase.
See also: 35 37 See response to question: 35
Page 9 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
38
39
40
41
42
43
38 General General Please suggest level of documentation
(business requirement documents,
functional, tech specs etc) available for
the current MSRP system.
For the current MSRP system, the level of document varies but, in
general, existing customizations (particularly those updated or
applied in recent years) have sufficient related
documentation/information.
Following the Conceptual design phase, AS-IS business processes
are also well documented along with the desired TO-BE state.
Detailed business requiremetns, functional, tech specs to be
prepared in the next phase of the project.
39 General General Please indicate the daily volume of
common transactions/day (Requisitions,
POs, Vouchers, Journals, etc). Also,
please indicate the no. of users in the
system.
Refer to attached document on Users and Volume of Common
Transaction.
40 General WP06 What is the current/expected Single Sign-
On setup?
Currently, portal is used as a gateway to all applications (HR, EP,
TM and FS), and the same is expected at the minimum. In addition,
UNHCR has recently implemented active directory and so
integration to active directory needs to be assessed as part of the
project.
41 General WP06 What is the current production database
size?
For current architecture, see Annex B - Appendix III, Technical
Architecture as well as attached documents on RFP 647 - QandA.
42 General WP06 Is RAC implemented on Oracle DB? If yes,
would there be a DB/cluster upgrade as
part of this project?
No. RAC is not implemented.
43 General General Section 4 - states the additional support
of 3 months to be used within one year
following the roll-out for other key
processing milestones. It would help if
you can provide scenarios (roll-outs) with
tentative time-plan on when this support
As part of its proposed overall project implementation plan, it is for
the Bidder to propose rollout tentative time-plan. Support from off-
shore needs to be discussed with/agreed by UNHCR with clear SLA.
Page 10 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
44
45
46
44 General General In case of post go-live support, can we
assume this will be pre-dominantly being
provided from off-shore during UNHCR
Geneva normal working hours. Please
specify for each lot activity
As part of its proposed overall project implementation plan, it is for
the Bidder to propose rollout tentative time-plan. Support from off-
shore needs to be discussed with/agreed by UNHCR with clear SLA.
45 General General Annexure B-5 > Section 2-Methodology
indicates five main phases (Assessment,
Upgrade, Development & Test, UAT, Go
Live & Support) whereas the work
package definitions indicate 10
processes, please let know the
adaptations (when to be used) of the two
and if there is any correlation
"Annexure B-5 > Section 2" methodology refers specifically to the
PeopleSoft upgrade exercise itself. (It does not discuss other
important activities such as project management, change
management, etc...)
The work packages cover all the activities under OUM Oracle
Phases and Implement Focus Areas. Please refer to Oracle project
methodology for more explanations.
46 General General How many resources of UNHCR will be
part of the project? What is the
distribution of roles between them? How
will the allocation of these resources
happen (full time / part time)?
At present, UNHCR's core project team is composed of 3 FTE's: a
project manager, a business coordinator, a senior business analyst.
The extended project team includes process/subject matter experts
and business analysts in the functional areas with varying degrees
of involvement.
The bidder is expected to propose the overall project structure and
staffing, including UNHCR roles and responsibilities.
Refer to 6.3.5.3. Expected UNHCR roles and staff levels of Technical
Response.
Page 11 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
47
48
49
50
47 General General Could you please provide editable
versions (excel sheet) of customizations
tables as mentioned in Annex B-
Appendix III-1-Customization review.pdf,
specially table-Annexure 1-
Customization overview-page no 57
& Object-wise Module-level
customization inventory for major
modules- page no 59
No.
48 General WP03 Do you have a dedicated communication
team? If yes, what are their capabilities
and would they be able to support the
project?
Currently, the project team is covering all communication related
to the project itself. UNHCR intends to strengthen with bidder's
personnel.
See work package 3
49 General WP03 What are the communication channels
and mechanisms that UNHCR wants to
utilize during the upgrade program:
email, newsletters, information sessions,
webcasts, videos, self-running product
demonstrations?
Communication mechanisms will vary according to purpose and
audience.
See attached documents:
RFP QandA - Communication
RFP QandA - Change Management
50 General WP03 Does "Change Planning and Execution"
scope include business process redesign
activities or is it restricted to analyzing
the delta between AS IS and TO BE
processes and develop a plan on what
the impact is for users +
recommendations for communication &
training?
Both.
See attached document: RFP QandA - Change Management
Page 12 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
51
52
53
51 General WP03 Does "Change Planning and Execution"
includes organization restructuring
activities, where (Oracle) vendor needs
to present recommendations on how to
change the organization structure, or is it
restricted to recommendations and
execution activities in the areas of
communication and training on how to
support the organization through the
business and IT transition?
Yes.
See attached document: RFP QandA - Change Management
52 General WP04 Do you have particular additional
language requirements besides English?
See also: 52 104
137 158 242 488
507 5265 537 557
577
If refering to consultants, no, but fluency in another UN language
(eg French) is helpful;
If refering to training, main training is in English with some French;
If referring to working system language (setup), no; However, some
reports/descriptions are in French, Spanish;
53 General WP04 Do they have an internal training team
that will work together with the (Oracle)
vendor consultants in a blended team
during the development and delivery of
the training. If yes, how big is their
training team.
See also: 53, 59, 60 Yes but with limited capacity, UNHCR intends to strengthen with
bidder's personnel.
UNHCR will use internal resources to build training capabilities and
capacity for post implementation; however, we anticipate that the
Prime Vendor will be involved in both train-the-trainer and end-
user training delivery. UNHCR team members will also be used to
provide end-user training.
See attached document: RFP QandA - Training
Page 13 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
54
55
56
57
58
59
60
54 General WP04 What are the different job roles that will
be affected by this initiative and that
require end user training?
To be determined.
See attached documents:
RFP QandA - Change Management;
RFP QandA - Training
55 General WP04 What are the number of users per job
role and how is their geographical
spread?
See attached documents:
RFP QandA - Training
RFP 647 - QandA - Users and Volume of Common Transactions
56 General WP04 Beside full training on newly
implemented modules, is it required
delta training on upgraded modules?
Yes.
See attached document: RFP QandA - Training
57 General WP04 Do you have a Learning Management
System? Or how do you currently
host/distribute the training materials and
eLearning?
See attached document: RFP QandA - Training
58 General WP04 What are the training team's skill set /
capabilities: Buy training from supplier
and/or develop your own training
material?
See ToR, section 3.3, Work Package 04.
Also see attached document: RFP QandA - Training
59 General WP04 Do you have your own trainers? See also: 53, 59, 60 See response to question 53.
60 General WP04 If you have your own training team, is it
planned to work in collaboration with
Oracle's team? If yes, how much of their
time will be provided?
See also: 53, 59, 60 See response to question 53.
Page 14 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
61
62
63
64
61 General WP04 Section 3.3 - As part of the end user
training work package, it is expected that
all end users will be required to be
effectively trained. Request you to share
the no. of users expected to be trained
across each lot
To be determined.
See attached document: RFP QandA - Training
62 General WP04 Section 3.3 - Additionally for training,
please let know if this needs to be
conducted for all users at Geneva / each
individual location / online training.
Request you to share the method to be
adapted across each lot
Please refer to Key activities of WP-04.
Also see attached document: RFP QandA - Training
63 General WP05 Section 3.3 - As part of the knowledge
transfer work package, please let know
the users (including no. of) for whom this
needs to be accomplished across each
lot.
Also, is it safe to assume that this will be
undertaken at one location for each lot.
No, do not assume that this will be undertaken at one location.
Most likely, Knowledge transfer activities will be conducted in
Geneva, Budapest, and possibly UNHCR service centers responsible
for production support, depending on the Lot/Applications.
The (business) users to be trained include functional experts in
their respective areas of responsibility. For example, procurement
related to PMCS functional expert, Accounting/Financial to AFS
functional expert etc...
64 General WP06 Section 3.3 - As part of system
configuration and setup, is it safe to
assume that native security would be
defined for each application.
Also, there is mentioned of agreed
benchmarks for security, request to
specify these benchmarks for
understanding of expectations
Yes, security should be defined for each application. Benchmark for
security would be the current system. Security should be at the
mimimum as good as the current system if not better.
Page 15 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
65
66
67
68
69
70
71
72
65 General WP06 Section 3.3 - As part of the approval
workflows, please let know the no. of
levels of approval is expected to be
defined
In principle 1 to 2 levels but it will depend on the business process
area.
For example, for supply chain processes, normally one level, with
potential prior technical clearance on some cases/process flows.
In any new processes where plan to use workflow it is still to
decide the level of approvals.
66 General WP08 Please specify if UNHCR is using any
specific testing tool or alternately any
core process that needs to be followed
Please refer to WP08: For PeopleSoft, functional test cases should
be developed as part of the
implementation of PeopleSoft Test Framework (PTF).
The System Integrator will use and provide, if necessary, the tools
and agreed procedures to manage the testing activities.
67 Lot1-Expenses WP02 What is the payment method that is
going to be used for expense payments?
At the very least, the same payment methods already in use for
paycycles, both electronic and manual methods.
68 Lot1-Billing WP02 Are invoices others than CD (which is
interfaced from bolt-on) are manually
entered in Billing?
Some invoices will be entered manually, but not all. There will
potentially be 3rd party interfaces from systems other than the
Contributions Management bolt-on, for example generation of
invoices from an Excel upload.
69 Lot1-Billing WP02 Is there a plan to use AM-BI interface? Yes, the use of AM-BI interface is in the plan.
70 General WP06 Is the application accessible from outside
network? In that case what is the
existing/expected setup?
Yes, the application should be available over the internet.
71 Lot1-App.Upgrd WP06 Is there any specific requirement of latest
patch level that need to be applied on
9.2?
This is dependent on the latest available PUM image during the
test moves and code catch-up schedule.
72 General WP06 Is the database Unicode/Non-Unicode? Unicode
Page 16 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
73
74
75
76
77
78
79
80
73 Lot1-App.Upgrd WP09 Is there any limitation on application
down time during go-live?
Minumum disruption. Only in the events of force-majeur
74 Lot1-App.Upgrd WP06 Is there any limitation in the number of
upgrade passes (w.r.t space
considerations)?
In principle, no limitation but dependent on the availability of
resource. Bidder to propose optimum plan with minumum
disruption.
75 Lot1-Billing WP02 Are invoices other than CD are interfaced
or entered in AR?
Yes. Refer to Annex B - Appendix II - Billing which discusses invoices
for various income related activities.
76 Lot1-Proj.Costing WP03 Integration is required between
PeopleSoft Expenses and designated
UNHCR Travel Agency for ticket
reconciliation. Is it for reconciliation only
or are you planning to integrate with the
travel partner to leverage the reservation
to create Expense Reports?
To be determined/elaborated. Detailed requirements gathering
and analysis is part of the engagement.
77 Lot1-Expenses WP03 A high-level Fit–Gap document is
available as part of the assessment
report for this module. Where can we
find those documents?
See response to question: 35
78 Lot1-Expenses WP03 Could you please provide example of HR
Travel?
HR Travel would include travels for: initial appointment,
reassignment, home leave, family visit, educated grant
travel/reverse education grant travel, separation, reassignment
combined with home leave
79 Lot1-Billing WP03 Could you please explain the acronyms
MIP, LOP?
MIP - Medical Insurance Plan
LOP - ?
80 Lot1-Accounts PayableWP02 Could you please explain the acronyms
AFS, DESS and DFAM?
AFS - Accounts and Financial Service
DESS - Division for Emergencies, Supply and Security
DFAM - Division of Financial and Administrative Management;
Page 17 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
81
82
83
84
85
81 Lot1-Accounts PayableWP06 How do you calculate the payroll for the
employees depuded to a local field
office?
Payroll is calculated in the HR system, which is outside of scope of
PeopleSoft FSCM.
The actual formula is irrelevant for this engagement.
82 Lot1-Cash ManagementWP02 In the cash flow overview section, what is
the Implementation Partner reporting?
For information on Implementing Partners, please refer to:
Annex_B_-_Appendix_II_-_Application_Overview_-_Lot1_-_Bolt-
on_-_Partnership_Management.pdf
83 Lot 1 In General Can UNHCR provide us with the timeline
for its PeopleSoft HCM upgrade, for all
the phases? This will help to understand
alignment of new module
implementations like Expenses with the
HCM project.
Please comment if any other inflight
projects that will have a dependency or
affect the Finance upgrade timelines
See also: 8 9 30 83
114 115;
On depencies, see:
7 83
HCM Timeline: See response to Q8
Depencies: See response to Q7
84 Lot 1 In General Section 4 of Annex B Terms of Reference
indicates that UNHCR has described the
timeline as twelve months. Please
confirm if the vendor can propose an
alternative timeline to align well with the
RFP requirements.
Yes.
85 Lot 1 In General Please describe if UNHCR has a
prescribed minimum time window for
user acceptance testing
Bidder should include/propose in the overall implementation plan.
Constraints include the year-end closure Dec-Apr time period,
which should be avoided, as key SME's and business owners will
have limited availability.
Page 18 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
86
87
88
86 Lot 1 In General Please clarify if UNHCR has a preference
for and also licenses for specific testing
tools like HP QTP for Functional testing
and Loadrunner for Performance testing.
Please refer to WP08: For PeopleSoft, functional test cases should
be developed as part of the
implementation of PeopleSoft Test Framework (PTF).
The System Integrator will use and provide, if necessary, the tools
and agreed procedures to manage the testing activities.
87 Lot 1 In General Annex B Reporting Deliverables mentions
conversion of all reports to standard
tools (e.g. Crystal Reports to XML
Publisher). We understand that there are
over 150 Crystal reports in the current
PeopleSoft system. Please describe if it is
necessary to convert all these Crystal
reports to XML Publisher even if current
Crystal reports meet the functional
requirements.
Alternatively, please comment if an
analysis been done on how many Crystal
reports necessarily need to move to XML
Publisher
See also: 12 87 128
Yes, Crystal Report conversion to XML Publisher in in scope.
At this point, UNHCR has not established the number of Crystal
reports that have to be converted, but it is reasonable to assume
that at least 100 reports are impacted.
88 Lot 1 In General For all the new modules that are being
proposed to be implemented, please
comment if detailed approved
requirements and fit gap documents can
be shared to facilitate near accurate
estimates.
See response to question: 35
Page 19 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
89
90
91
92
93
89 Lot 1 In General Has UNHCR finalized integration
requirements with external travel
agencies and credit card vendors for
specific requirements like secure file
transfer, file encryption, infrastructure
etc.
No.
90 Lot 1 In General Please comment on the UNHCR
commitment on providing Subject Matter
Expertise for UNHCR requirements for
the upgrade and implementation.
UNHCR is committed.
91 Lot 1 In General Please clarify if Organization Change
Management is in scope for the vendor
See attached document: RFP QandA - Change Management
92 Lot 1 In General For all the new modules that are being
proposed to be implemented, please
comment if detailed approved
requirements and fit gap documents can
be shared in order to propose an
accurate estimate for implementation
See response to question: 35
93 Lot1-App.Upgrd General Please confirm whether environment
consolidation (merger of PeopleSoft
Financials 8.4 and Treasury Management
Systems 9.0) is within the scope of this
RFP?
Yes. This is a KEY deliverable.
Page 20 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
94
95
96
97
98
99
100
94 Lot1-App.Upgrd General RFP mentions the project duration for a
year. Are there any blackout periods
when UNHCR will not be able to Go Live
for business or strategic reasons?
Year-end closure period is considered a go-live 'blackout period' for
Lot1, upgrade and consolidation into PeopleSoft 9.2.
95 Lot1-App.Upgrd General Does UNHCR expect the upgrade and
implementation of new modules to go in
parallel or sequential?
The timing of the implementation of new PeopleSoft modules vis-à-
vis the upgrade depends on a number of factors, including the
criticality of the module. Definitely some new modules will go
parallel, some later in sequential.
96 Lot1-App.Upgrd General What is the strength of the current
PeopleSoft team?
a) Management Resources
b) Functional Resources
c) Techno-Functional Resource
d) Technical Resource
Vendor should assume, in general, that UNHCR resources have
strong knowledge in their areas of responsibility, but limited
capacity.
97 Lot1-App.Upgrd General What’s the actual size of current
PeopleSoft Production Database?
For current architecture, see Annex B - Appendix III, Technical
Architecture.
98 Lot1-App.Upgrd General Do we have any change control
mechanism in place?
For changes to the project, see work package 1.
99 Lot1-App.Upgrd General Do you have any restriction of sharing
copy of production data with offshore?
No copy of production data will be shared.
100 Lot1-App.Upgrd General Is the upgrade planned to be a “a near
Vanilla” Upgrade?
See also: 100 101 Mixed, in the sense that the idea is to maximize vanilla
functionality, minimize intrusive customizations.
UNHCR recognises the value of PeopleTools as a development
environment and expect to use it for non-intrusive bolt-on
modules within the PeopleSoft application.
Page 21 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
101
102
103
104
105
106
101 Lot1-App.Upgrd General If the answer to the above question is
“No”, then please specify the additional
functionalities for each implemented
module that you plan to implement in
the target version (apart from the
current customizations)?
See also: 100 101
Most of the additional functionalities are mentioned in the
appendix II documents.
102 Lot1-App.Upgrd General With respect to implementation of
additional functionalities, have you
completed the scoping and estimation of
effort? Please provide details.
No.
103 Lot1-App.Upgrd General Is Database Installation and Maintenance
part of scope for the upgrade
Database installation is handled by our service provider hosting the
environments. The System Integrator will be responsible for
ensuring proper installation/setup, providing guidance is
necessary, and will be responsible for the maintenance during the
period of the engagement in collaboration with the hosting service
provider.
104 Lot1-App.Upgrd General Is current Environment Multi lingual? If
yes, let us know languages implemented.
See also: 52 104
137 158 242 488
507 5265 537 557
577
No.
105 Lot1-App.Upgrd General Do we need to consider addressing key
challenges listed for each of the existing
modules as part of the upgrade scope?
Or this would be taken up post Upgrade
as Phase 2?
In principle, yes, the key challenges should be addressed.
106 Lot1-App.Upgrd General What is the duration (in weeks) you are
considering for the user acceptance
testing phase? Or you expect Oracle to
provide you with duration based on best
practices
For vendor to propose its approach/best practice and agree with
UNHCR
Page 22 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
107
108
109
110
111
112
113
114
115
116
107 Lot1-App.Upgrd General What is the duration (in weeks) you are
considering for the parallel testing
phase? Or you expect Oracle to provide
you with duration based on best
practices
For vendor to propose its approach/best practice and agree with
UNHCR
108 Lot1-App.Upgrd General Are you looking for Performance testing
phase in upgrade project?
Yes, please refer to WP08
109 Lot1-App.Upgrd General Do we have any tools like Load Runner
for performing the Performance Testing?
UNHCR does not have any tools for performance testing.
110 Lot1-App.Upgrd General Is there any documentation on test case
plans available?
No. If any, it would be minimal.
111 Lot1-App.Upgrd General Can you provide offshore access to
specific instances (DEV, TEST, TRN etc.)
on your servers?
Access to UNHCR servers will only be granted to official project
staff accepted by UNHCR.
112 Lot1-App.Upgrd General Can you provide copies of your non-
production instances to our offshore
facilities after sanitizing the instances of
any real data (i.e. after masking the real
data)?
No copy of non-production instances will be shared.
113 Lot1-App.Upgrd General How many months of support do you
require after the upgrade go-live?
See also: 113, 543,
563, 583
Refer to Terms of reference 4. Timeline and Constraints
114 Lot1-App.Upgrd General Are there any dependencies between the
upgrade project and any other initiatives
within the organization? See also: 8 9 30 83
114 115
Refer to Terms of Reference - Statement of purpose - Dependency
115 Lot1-App.Upgrd General When is the Go Live planned for HR
Upgrade which is currently in flight?
See also: 8 9 30 83
114 115
See response to question: 8
116 Lot1-App.Upgrd General When are you planning to start the
project?
Refer to Terms of reference 4. Timeline and Constraints
Page 23 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
117
118
119
120
121
122
117 Lot1-App.Upgrd General Do we have Data Archival in place for
existing PeopleSoft System? Is upgrade of
Archived data in scope or out of scope as
part of this upgrade?
No data archiving in place for existing PeopleSoft
118 Lot1-App.Upgrd General Is expectation for training is only to Train
the Trainer or end users as well. If end
users, how many user training sessions
are required to be conducted and what is
the total no of end users
See response to question: 53
119 Lot1-App.Upgrd General Can we assume that Train the trainer
Manuals would be used to train or do
you have any specific requirement on
user manuals.
To be determined.
See attached document: RFP QandA - Training
120 Lot1-App.Upgrd General Can we assume Application Knowledge
Transfer would be only on new
functionalities and can we covered
during SIT and UAT Phase
To be determined. In principle, application KT should cover new
and changed functionalities as a priority, but also provide a
refresher on other functionality in the target versions.
The timing of the knowledge transfer must be determined during
the planning stages of the engagement.
121 Lot1-App.Upgrd General How many resources would be part of KT
sessions from current IT Team
Approximately, 4 resources.
122 Lot1-App.Upgrd General Do you have any additional requirement
of documentation which need to be
handed over as part of KT sessions?
See Work Package 5.
Page 24 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
123
124
125
123 Lot1-App.Upgrd General What is expected from Oracle for non-
Oracle Bolt-ons applications?
Within this engagement, the vendor is expected to perform the
activities and deliver the outputs covered under the work
packages, including rollout and the provision of post-
implementation support.
Particularly for bolt-ons (and other customizations), UNHCR
expects high quality build, development and documentation.
124 Lot1-App.Upgrd General UNHCR has mentioned "Chartfields
rationalization" as one of the key
priorties, could you please describe this
requirement in detail? Do you expect us
to explore and identify any additional
Chartfields requirements?(Annexure B-
Appendix I-Terms of Reference(TOR),
Section 2.3-Key Priorties, Page no 6)
This is Key Priority (KP1) which is adressed by uNHCR relevant
business owners, internally.
125 Lot1-App.Upgrd General UNHCR has mentioned "Single travel
system" as one of the key priorties, could
you please describe this requirement in
detail? Which travel management system
are you currently using?(Annexure B-
Appendix I-Terms of Reference(TOR),
Section 2.3-Key Priorties, Page no 6)
The management of travel is currently a manual process , outside
of MSRP across UNHCR HQs and and UNHCR field operations.
Page 25 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
126
127
126 Lot1-App.Upgrd General Terms of Reference mentions that
vendors would be responsible for
finalization of requirements, developing
the strategy for reviewing
customizations, ensuring the traceability
of decisions and migrate those deemed
usable. In this case is the requirments
gathering also in scope of this RFP or
would the requirements be provided by
UNHCR? (Annexure B-Appendix I-Terms
of Reference(TOR), Section 3.2.2-Build
and Implementation Phase-
Customizations overview)
Requirements gathering is also in scope.
127 Lot1-App.Upgrd General As per the scope, PeopleSoft EPM 8.9 will
be decommissioned and its current
functionalities will be distributed across
Hyperion and PeopleSoft Financials 9.2
as bolt on. During the conceptual design
phase, is any decision made on what
functionalities will be in PeopleSoft as
bolt-ons vs what will be in Hyperion. If
yes please provide details.(Annexure B-
Appendix I-Terms of Reference(TOR)
The decision was made. Full details are in Annex B, Appendix II.
Please refer to the document for Contributions Management in
particular.
Page 26 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
128
129
130
128 Lot1-App.Upgrd General We are assuming that all Crystal reports
currently in use need to be converted to
XML Publisher. Please confirm.
(Annexure B-Appendix I-Terms of
Reference(TOR), Section 3.2.3-Build
and Implementation Phase-Customized
reports and queries)See also: 12 87 128
See response to question: 12 and 87
129 Lot1-App.Upgrd General For potential implementation of
additional PeopleSoft Modules of Real-
estate Management and Project Costing,
is any preparation done at UNHCR
level. If yes please provide details along
with expectations from vendor? (Annexure B-Appendix I-Terms of
Reference(TOR), Section 3.2.1-Build
and Implementation Phase-
Applications overview)
See also: 129 141
As per shared documentation, only a feasibility study to determine
that the modules are capable of handling the UNHCR required
functionality has been undertaken. No formal fit-gap session
undertaken.
130 Lot1-App.Upgrd General We are assuming that all interfaces
mentioned in Annex B-Appendix III-1-
customized interfaces.pdf are related to
PeopleSoft FSCM only. Please confirm.
Also if possible, could you please provide
a diagrammatic representation
/architecture of all interfaces?
In the current environment, the customized interfaces may be
related to FSCM v8.4 (Fin/SCM), Peoplesoft EPM v8.9
(Budget/Income) or FSCM v9.0 (Treasury). It is expected that as
part of this engagement, activities will be carried out in order to
identify all possible integration to other applications/systems.
The current system landscape is illustrated in Annex B, Appendix IIII
under section 1.3.1. heading Current System Landscape.
Page 27 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
131
132
131 Lot1-App.Upgrd WP02 If the answer to the above question is
‘Yes’ then what would be preferred
approach for environment
consolidation?
• Upgrade and then consolidate
• Consolidate and then Upgrade
See also: 11 131
UNHCR prefers upgrading FSCM to 9.2 and consolidating TMS
directly into 9.2.
See:
ToR - Appendix_IIII_-_5_-
_Methodology_and_Options_for_Upgrade
Also see QA11
132 Lot1-App.Upgrd WP02 Detailed Budgeting :
• How many reports needs to be
developed in Financial Reports?
• How many reports from PeopleSoft
queries and as well as from GFI and GFX
is expected?
• How many web Forms needs to be
developed in Hyperion Planning?
• How many users are planning to use
the system? This is required for load
balancing
• How many years of History needs to be
stored in the System? This is required for
planning historical data migration
• Is the historical data available in
systems or excel?
• What kind of security level is expected
in the Hyperion Planning Web Forms?
• Are they planning to host detailed
budgeting and position budgeting on the
same environment?
See also: 132 305
Some details may only be elaborated during the engagement (eg.
number of web forms, number years of history, security levels,
etc).
Approximately 10 NVision existing detailed budgeting reports exist
in the current EPM system but it is expected to have more in
Hyperion. (See also Annex B - Appendix II - Application Overview -
Lot1 - Bolt-on - Partnership Management, "Challenges section".
Current EPM Queries are provided in Annex IV section 2.
Currently EPM has approximately 2500 individual users. The
number of Hyperion users will have to be determined.
Page 28 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
133
134
133 Lot1-App.Upgrd WP02 We understand that As-is assessment, fit
gap and drop keep analysis, to be
process flows and functional design for
all existing PeopleSoft applications have
already been completed and we are only
expected to do a revalidation of the
same along with build and
implementation, Testing and
deployment. Please confirm.(Annexure
B-Appendix I-Terms of
Reference(TOR), Section 3.2.1-Build
and Implementation Phase-
Applications overview)
See Work Packages, particularly work packages 2.
134 Lot1-App.Upgrd WP02 We understand that As-is assessment, fit-
gap and drop-keep analysis, to-be
process flows and functional design for
all new required and potential
PeopleSoft applications and bolt-ons are
in scope along with build and
implementation, testing and
deployment. Please confirm.(Annexure
B-Appendix I-Terms of
Reference(TOR), Section 3.2.1-Build
and Implementation Phase-
Applications overview)
Yes. (For potential new applications, build and Implementation,
testing and deployment activities will depend on clearance/final
business decisions.)
Page 29 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
135
136
137
138
135 Lot1-App.Upgrd WP03 We Understand that UNHCR is willing to
accomplish Oracle PeopleSoft business
process improvements to be aligned with
delivered/standard functionalities of
Oracle/PeopleSoft and wants planning
and execution of change management
plan. Are you also expecting vendors to
do financial process analysis and
redesigning? Are you willing to align your
financial business processes with
Industry best practices? (Annexure B-
Appendix I-Terms of Reference(TOR)
Section 3.3)
To be determined.
Before making this decision, UNHCR will work with the System
Integrator to discuss other options such as available work-around
or process re-design. Acceptable solutions will be determined by
UNHCR in conjunction with the System Integrator and may be any
of the options described under 2.2 Guiding principles of the TOR.
136 Lot1-App.Upgrd WP04 Do you have UPK training modules for
the existing PeopleSoft modules, that can
be used as a starting point?
There are some, but may be outdated.
Also see attached document: RFP QandA - Training
137 Lot1-App.Upgrd WP04 Does UNHCR expect vendor to provide
training content/documentation in
different languages? Also does UNHCR
expect vendor to provide training in its
own toolset or would UNHCR provide
their toolset? (Annexure B-Appendix I-
Terms of Reference(TOR) Section 3.3)
See also: 52 104
137 158 242 488
507 5265 537 557
577
All materials/documentation in English (UNHCR will take care of
the translation/production of material in different languagues (to
check with GLC).
For additional information on training, see attached document: RFP
QandA - Training
138 Lot1-App.Upgrd WP04 As user Training is in scope, please
confirm number of users of Financial
management system that need to be
trained. (Annexure B-Appendix I-
Terms of Reference(TOR) Section 3.3)
To be determined.
See attached document: RFP QandA - Training
Page 30 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
139
140
141
139 Lot1-App.Upgrd WP06 UNHCR mentions that System Integrator
must develop backup and recovery plan
as well as disaster recovery strategy.
Please provide inputs on whether it is
needed to be done for all production and
non-production environments during
implementation? Also during the post go
live support is the system integrator
expected to execute the disaster
recovery test as well (Annexure B-
Appendix I-Terms of Reference(TOR)
Section 3.3)
Backup recovery and disaster recovery strategies apply to the
production environment acceptable to UNHCR.
The system integrator is expected to actively participate and
support the disaster recovery test in collaboration with UNHCR and
the hosting service provider as part of the post go live support.
140 Lot1-App.Upgrd WP06 On Security: Is Single Sign-on existing
between current MSRP systems of
PeopleSoft HR and PeopleSoft Financials?
If not is the vendor supposed to
implement it? What will be the role of
vendor who currently does PeopleSoft
HR Upgrade in this activity. (Annexure B-
Appendix I-Terms of Reference(TOR)
Section 3.3)
Yes, through portal
141 Lot1-App.Upgrd WP08 For potential implementation of
additional PeopleSoft Modules of Real-
estate Management and Project Costing,
is any preparation done at UNHCR
level. If yes please provide details along
with expectations from vendor?
(Annexure B-Appendix I-Terms of
Referen
See also: 129 141
See answer to question: 129
Page 31 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
142
143
144
142 Lot1-App.Upgrd WP08 Does UNHCR use any tool (like HP Quality
Center) during the testing phase to
maintain test scripts, test data and defect
tracking. If yes please provide details. (Annexure B-Appendix I-Terms of
Reference(TOR) Section 3.3)
No, UNHCR currently does not use any tool for test scripts, test
data and defect tracking specifically for PeopleSoft related testing,
however SpiraTeam has been used in other projects.
Please refer to WP08: For PeopleSoft, functional test cases should
be developed as part of the
implementation of PeopleSoft Test Framework (PTF).
The System Integrator will use and provide, if necessary, the tools
and agreed procedures to manage the testing activities.
143 Lot1-App.Upgrd WP08 Please confirm if UNHCR is also looking
for GL parallel test. If yes, please state
preferred duration of GL parallel runs. (Annexure B-Appendix I-Terms of
Reference(TOR) Section 3.3)
Ambiguous question.
144 Lot1-App.Upgrd WP08
Can you provide the names of key
processes that qualify for performance
testing during the performance testing
phase? (Annexure B-Appendix I-Terms
of Reference(TOR) Section 3.3)
To be determined. Performance testing will be performed across
applications to measure response time with a single user or with
multiple users using the system, e.g. procurement to pay
processes, reports (nVisions), transactions against Essbase, queries,
etc
Page 32 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
145
146
147
148
145 Lot1-Billing General Will this be a Vanilla Implementation? This will be assessed in this RFP (see WP02).
In principle, UNHCR would like a (close to) vanilla implementation
but recognizes that standard functionility may not meet all of its
needs. (Refer to ToR, section 2.2 - Guiding Principles.)
Example: The invoice created for CDs is likely to be complex and
necessitate detailed formatting. As a bespoke invoice is a standard
requirement, the implementation still falls into the category of a
vanilla implementation.
146 Lot1-Billing WP02 Please let us know how many Billing
systems do you have? Do you want to
convert data or integrate them to new
system?
Currently, UNHCR does not have a Billing system per-se. Billing
occurs outside of PeopleSoft with manual documents. No data
conversion is anticipated.
147 Lot1-Billing WP02 Please confirm if UNHCR creates AP
vouchers from Billing (e.g. RMA)?
Currently, UNHCR does not have a Billing system. In the PS9.2
implementation, UNHCR might use this functionality. (To be
decided.)
148 Lot1-Billing WP02 Please confirm if UNHCR generates
interunit Invoices
Currently, UNHCR does not have a Billing system. In the PS9.2
implementation, UNHCR might use this functionality. (To be
decided.)
Page 33 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
149
150
151
152
153
154
149 Lot1-Billing WP02 Please let us know how many Invoice
formats will UNHCR organization will be
requiring?
The final number of invoice formats will determined during the
engagement.
System integrator must consider that at least the following may be
required: One for CDs (with complex formatting), one for staff
(reimburseable loans, etc), one for third-parties (sub lease, etc),
and one for the PI shop (with a nice presentation that includes links
to further information, etc). The invoice for CDs will need to
duplicated so as to allow for English, French and Spanish versions.
150 Lot1-Billing WP02 Please let us know what would be the
intended Process Flow:
1. Billing > Accounts Receivable > General
Ledger
2. Billing > General Ledger (for Revenue
Tracking) and AR > GL (for Payments).
The intended Process Flow is 1. Billing > AR > GL
151 Lot1-Billing WP02 Please confirm the Assumption: Invoices
will be generated on the basis of Billing
Identifiers (Charge Codes).
To be determined during this engagement.
152 Lot1-Billing WP02 Please confirm the Assumption: There
would be multiple Invoice Templates for
various Invoicing Activities. See also: 149, 152,
440
Correct. See answer to questions 149 and 440 for more detail.
153 Lot1-Billing WP02 Please let us know the Invoices raised are
subjected to VAT/Service Tax, or, as a UN
Agency, UNHCR follows its own Taxing
Method or None.
UNHCR is not subject to VAT.
154 Lot1-Billing WP02 Please let us know if there will be a
specific Numbering Sequence for
different types of Invoices.
To be determined during this engagement.
Page 34 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
155
156
157
158
159
160
161
155 Lot1-Billing WP07 Please list the integration point to Billing
(e.g. Order Management, 3rd party etc.)
The Contributions Management bolt-on will function as a 3rd party
integration to BI. Another 3rd party systems could be for MIP.
UNHCR are not planning to implement Order Management.
156 Lot1-Expenses General Will this be a Vanilla Implementation? Very likely, some customizations will be required. However, the
objective of the project is to maximize the use of standard
functionalities...
Refer to:
ToR, 2.2, Guiding Principles.
Annex_B_-_Appendix_II_-_Application_Overview_-_Lot1_-_FS_-
_Expense.pdf
157 Lot1-Expenses General Among the listed functionnalities, what
are those which aleady exist in the
current version ?
PeopleSoft Expense module is not currently in use.
Annex_B_-_Appendix_II_-_Application_Overview_-_Lot1_-_FS_-
_Expense.pdf
158 Lot1-Expenses General Notifications will be in english only or will
depend on the preferred languages ?
See also: 52 104
137 158 242 488
507 5265 537 557
577
Notifications will be in English only
159 Lot1-Expenses General Are there reports to automatically
generate and attach to notifications ?
To be determined.
160 Lot1-Expenses WP02 Please let us know the relationship of
existing Expenses business process with
PeopleSoft GL Business Unit (For Ex: one
to many / Many to One)
UNHCR is currently using only one GL Business Unit, with
subsystems having multiple Business Units. Expenses are likely to
follow the same model.
161 Lot1-Expenses WP02 Please let us know what pare payment
methods used (Credit Card / Bank
transfer/ Salary)
To be elaborated during engagement (requirement gathering
activity).
Page 35 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
162
163
164
165
166
167
168
169
162 Lot1-Expenses WP02 Please let us know how may expenses
type required to be configured
To be elaborated during engagement (requirement gathering
activity).
163 Lot1-Expenses WP02 Does any expenses type require
questionaries’ to be answered by user?
OR do you need them to be configured
that way.
To be elaborated during engagement (requirement gathering
activity).
164 Lot1-Expenses WP02 Please let us know if barcode is to be
printed on expense sheet
To be elaborated during engagement (requirement gathering
activity).
165 Lot1-Expenses WP02 Please confirm if you need details
tracking for following expenses type?
Meals & Lodging
Hotel
Transportation
Personal Vehicle Mileage
Anything else
To be elaborated during engagement (requirement gathering
activity).
166 Lot1-Expenses WP02 Please confirm if UNHCR requires
visibility into Ongoing Activities,
Requirement such as
Budget vs. Actual
Projected Expense
Expenses In Progress
To be elaborated during engagement (requirement gathering
activity).
167 Lot1-Expenses WP02 Please confirm if use of pre-trip travel
authorization Required (Yes/No)
In the organization, a travel authorization is required before any
trip. To be elaborated during engagement (requirement gathering
activity).
168 Lot1-Expenses WP02 Please confirm if use of Credit Card
Charges Import Required (Yes/No)
To be elaborated during engagement (requirement gathering
activity).
169 Lot1-Expenses WP02 Please confirm if use of Imaging Solution
Required (Yes/No)
To be elaborated during engagement (requirement gathering
activity).
Page 36 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
170
170 Lot1-GRC General We see lots of controls defined in
“Annexure A – GRC” for all streams like
Finance, Supply chain - Have you done
the control assessment of these earlier
and has it been accepted by UNHCR that
it will go in GRC System? We see these
listed to be more of Operational Reports
than controls. Most of them can be
handled directly in PeopleSoft Systems
and Operational Reports.
Only controls related to high risk access
conflicts to be monitored should be in
AACG
Transactions - Related to Master Data,
Threshold Values, Configurations,
Different states, Due dates etc that
required continuous monitoring should
be built in TCG and not General
Operational Reports.
Refer to the TOR Annex_B and appendix II_Application_GRC .The
prioritisation of the controls to go in GRC has not yet been done.
Re. Annex B and AppendixII-GRC, the system integrator will
revalidate the list of controls that will go in GRC - out of the overall
listed controls. Bidder to propose/advise based on their experience
/ expertise.
Page 37 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
171
172
173
171 Lot1-GRC General The output from GRC application is a
report that can be assessed by Risk Team
or Business Process owners. They can do
it only if they know PeopleSoft
Application and GRC Control Definitions
(I mean technically). Does UNNHCR have
this kind of a skill set across all countries?
Then the Business owners need to take
action / Remediation activity in
PeopleSoft Application for the changes,
and then test them. It is a mix of IT teams
and Business Leads to act on GRC
application.
GRC is new module. At this point in time, UNHCR does not have
technical GRC skills. Re. WP02 and Annexure 1- GRC.
Bidder to propose/advise based on their experience / expertise.
172 Lot1-GRC General I see that you have mentioned about US
and Country teams - Are these teams just
analyzing the GRC reports or they will
work in GRC application individually to
create controls. As a best practice in GRC,
is to manage the application centrally like
a shared service and requests - to create
new model, enhance the existing control
can come from Global US or Country
teams.
In adherence with best practice for GRC - UNHCR envisages to
manage the GRC application centrally (creation of new models
enhancement of controls etc.). However, as per annex B_Appendix
II, the system integrator will assist in defining the role of UNHCR
country offices in the implementation of GRC. Bidder to
propose/advise based on their experience / expertise
173 Lot1-GRC General How many members will be actively
working in GRC system after
implementation - We need to know this
to design the GRC user roles using Fusion
Security Model
This will be determined with the assistance of System ingrators
(Annex B_ Appendix II_ GRC ).
Page 38 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
174
175
176
177
178
174 Lot1-GRC General If you have already done an Inception
Phase, it will great if you can share that -
so that we don’t need to factor that in
our estimates and add more value to
UNHCR.
This is expected from System integrators. The most detailed
information is avaialble in Annex B_ Appendix II_GRC. TOR,
Annex_B, WP02 forseees that System integrator will revalidate the
conclusions and reocmmendation of concpetual design; prepare
final detailed business requirements documents,; functional
configuration and setup documentation etc.
175 Lot1-GRC WP02 In relation to Oracle GRC we would like
to know current pain points to Roles &
Security in supply chain area?
See response to question: 170
176 Lot1-GRC WP02 In relation to Oracle GRC we would like
to know the current requirements of
tracking in Supply chain area? For
example PO Lines, bank account
numbers etc
Key GRC challenges for Supply chain area are listed in Annex B_
Appendix II_ GRC .
177 Lot1-GRC WP02 We understand that your current
PeopleSoft system is having number of
controls in place. Are you looking at
additional controls (Access/Transaction)
in Supply chain area on top of existing
controls?
Yes, additional controls (Access / Transaction (GRC))shall be on top
of improved control in 9.2. FSCM applications, in upgraded system.
178 Lot1-GRC Have the list of Models and Controls
from a SoD Perspective been already
frozen? From a scope point of view is the
list of Models AnnexB-Appendix II
Application Overview - Lot1 - GRC final?
No - the list of Models and Controls from SOD perspective has not
been finalised. The list of models in Annex B - Appendix 2 - GRC is
not final. The Access Controls described are posssible controls that
could be configured in GRC. But those controls (that will go in GRC)
need to reviewed, refined, priotised and validated, with the System
integrator, as per Annex B_ Appendix II_ GRC.
Page 39 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
179
180
181
182
183
184
179 Lot1-GRC Similarly, have the list of Models and
Controls from a Transactions Control
Perspective been already frozen? From a
scope point of view is the list of Models
AnnexB-Appendix II Application
Overview - Lot1 - GRC final?
Re. response to question 178. Similarly the list of Transactions are
not final. They need ot be refined and valiaded with System
integrator.
180 Lot1-GRC Who will own the GRC Project
BRM/IT/Functional champions?
Currently, the Office of the Controller.
181 Lot1-GRC Is Advisory services on Hardware sizing in
scope for this RFP?
To some extent, yes. UNHCR has a hosting service provider with
whom the project should collaborate to ensure proper hardware
sizing and setup.
Refer to work package 6.
182 Lot1-GRC Is Installation of required GRC Modules in
scope for this RFP?
Yes. One instance of GRC has been installed at UNHCR hosting
service provider. Installation of additional instances (e.g Dev, Test,
Prod) will be required and will be performed in coordination with
UNHCR IT team and UNHCR service provider.
183 Lot1-GRC Is Integration of GRC Modules to
PeopleSoft in scope for this RFP?
Definitely yes.
184 Lot1-GRC Is Oracle AACG going to be used to clean
up Segregation of duties conflicts Inter
and Intra role conflicts before Go live?
Preferably but not mandatory.
Role conflicts to be resolved before go-live, however Internal
controls monitoring (continuous transaction monitoring &
continuous control monitoring) is an on-going activity.
Page 40 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
185
186
187
188
189
190
191
185 Lot1-GRC Is remediation of Segregation of duties
violations in scope for this RFP?
Yes. Please refer to Annex B. Appendix II - GRC.
The annex includes list of Access Controls that could be configured
in GRC. This list of Access Controls will refined and validated during
the engagement. Including based on best practices, remediation of
detected conflicts will be proposed during the build and
implementation phase, and is in scope.
186 Lot1-GRC How many countries rollout is in scope? GRC will be centrally managed. In the long term, dashboard will be
available to country office management (120+)
187 Lot1-GRC Will Business want us to builid custom
objects for TCG in case the objects do not
exist or will this be done as a custom
report in Peoplesoft?
Yes.Detailed requirements will be assessd during the Build and
Implementation phase (this RFP)
188 Lot1-GRC Can we have the approximate number of
current users and roles?
None as it's a new application. This will be determined with the
assistance of System ingrators (Annex B_ Appendix II_ GRC ).
189 Lot1-GRC Is there a plan to use implement Oracle
identity manager for user provisioning?
There is a tentative plan to implement an Identity Management
system for user provisioning but that's not yet definite
190 Lot1-GRC What are your highest priority areas that
you are looking to address with the
implementation of the GRC modules
Implementation of GRC is meant to prevent fraud and errors, as a
priority (re. TOR, para 2.3 key priority # 9).
191 Lot1-GRC How many key controls are tested and
monitored on an ongoing basis and how
many controls are planned to be
implemented as part of GRC
Implementation
See Annex B. Appendix II - GRC - the list and number of controls to
be configued in GRC will be refined, validated and worked out with
System integrator .
See also answer to questions: 178, 179
Page 41 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
192
193
194
195
196
197
198
192 Lot1-GRC Are there any key risk areas (buisness
process / modules) which management is
looking at for some extra emphasis at the
time of building the controls for ACG and
TCG ?
Refer to Annex B - Appendix II - GRC - the areas looked at for
building GRC controls are Supply chain, Core finance, Treasury.
193 Lot1-GRC Whether there is Risk and Control Matrix
document available or the same need to
be prepated from the scratch ?
No, here is no Risk and Control Matrix document available. This
needs to be prepared.
194 Lot1-GRC Whether any instances of fraud or
unauthorized access to systems /
transactions have been encountered in
the existing legacy systems ?
See also: 194 195 Relevant details to be discussed during the engagement.
195 Lot1-GRC Are there any findings by the statutory /
internal audit teams with respect to
unauthorized access / SOD conflicts ? If
yes please share the audit report ?
See also: 194 195 Relevant information will be provided during construction.
196 Lot1-GRC At how many locations the PeopleSoft /
GRC is planned to be implemented ? How
many users would be using the
PeopleSoft / GRC ? Are we looking at any
timelines for implementation of GRC ?
For timelines, see Annex B Appendix III, Methodology and Options
for Upgrade; also see Annex B_TOR - para 4. timelines and
constraints.
GRC is currently planned to be managed centrally. The number of
users will be proposed by System Integrator.
197 Lot1-Proj.Costing General Will this be a Vanilla Implementation? This will be assessed in this RFP WP02.
In principle, as much as possible, as long as main functionality
requirements are supported, yes.
198 Lot1-Proj.Costing General Is Project budgeting in Project Costing be
implemented?
See answer to question: 199
Page 42 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
199
200
201
202
203
204
199 Lot1-Proj.Costing WP02 Request you to please confirm if projects
need to be created for Capital Projects
only, and not for other types of Assets
(like Software). If yes, then will these
other types of Assets continue to be
Captured/Capitalized as per the current
UNHCR System (interfaced from
Procurement System).
At the very least, the current planned implementation is related to
fixed assets, as a cost collector for construction and
improvement/operating costs of existing fixed assets.
As a new application, any additional requirement (opportunities)
will be identified/elaborated during the engagement as part of the
scoping and comprehensive assessment.
200 Lot1-Proj.Costing WP02 Request you to please provide more
elaboration for the nature/relevance of
capturing Serially Tracked Items as Assets
(with example).
STIs are mainly IT equipments.
201 Lot1-Proj.Costing WP02 Please let us know if Capital Projects
Budgeting be driven (initiated) from
Project Costing Module, or continue to
be created as per the current UNHCR
System.
See answer to question: 199
202 Lot1-Proj.Costing WP02 Apart from Capital Projects, please let us
know what other type of Projects might
be intended to be tracked under Project
Costing Module.
See answer to question: 199
203 Lot1-Real State General How this module will interact with other
modules (GL, AM, etc.) ?
Detailed to be determined/elaborated as part of this engagement.
As per shared documentation, only a feasibility study to determine
that the module is capable of handling the UNHCR required
functionality has been undertaken. No formal fit-gap session
undertaken.
204 Lot1-Real State General What are the expected functionalities ? See answer to question: 203
Page 43 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
205
206
207
208
209
210
211
212
205 Lot1-Real State WP02 Please let us know what is the current
process of Capturing Capital Lease Assets
in the UNHCR System (Initial recordation,
Lease payments, Depreciation).
See answer to question: 203
206 Lot1-Real State WP02 Please confirm if UNHCR deals with
Leases as both Lessee and Lessor.
Both.
207 Lot1-Real State WP02 Please let us know, what are the Terms
on which UNHCR Asset is transferred to
Implementation Partner under Right of
Use Agreement.
In general, UNHCR 'borrows' the asset to the IP at a no cost to
UNHCR (all operational costs with the IP), and the asset is subject
to normal depreciation in the UNHCR Asset module (relevant
chapter 8 part to be shared?). Only 'events' normally undertaken
beside depreciation is annual physical verification.
208 Lot1-Real State WP02 Please confirm if UNHCR needs the
functionality of creating Lease Rent
Escalations.
See answer to question: 203
209 Lot1-Real State WP07 Are there data conversions to do from
other applications ?
To be determined, although none known at this point.
210 Lot1-Real State WP07 Are there interfaces with other
applications to realize ?
Yes, at the very least, other PeopleSoft applications, such as AP,
AM, Billing, Project Costing.
211 Lot1-SRM General Has UNHCR already procured licenses
related to modules like Expense,
eSupplier, Strategic Sourcing? If not
when UNHCR is expected to make a final
decision with respect to procurement of
licenses?
Yes for Expenses, eSupplier and Strategic Sourcing.
212 Lot1-SRM General Whether SRM Suite be opened for
Vendors over internet?
Yes with proper authentication measures, e.g for supplier self
registration, self-services (PO acknowledgement, advance
shipment notification, Bid responses, etc)
Page 44 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
213
214
215
216
213 Lot1-SRM General Can we consider Implementation of SRM
Suite as Vanilla Implementation?
To be assessed during WP02 of this RFP.
In principle, UNHCR would prefer to have vanilla implementation,
however, some minor customization might be necessary.
214 Lot1-SRM WP02 In relation to Strategic Sourcing has
UNHCR performed high level fit-gap
analysis for Strategic Sourcing module
like Expense module? If so can results of
Fit-Gap analysis be provided to
understand potential gaps that have
been identified and also to accurately
estimate efforts for its implementation?
To date, UNHCR has completed a high-level discussions/feasibility
study to determine that the modules are capable of handling the
UNHCR required functionality. No formal fit-gap session
undertaken.
(Note: The statement "… for Strategic Sourcing module like
Expense module..." is not very clear)
215 Lot2-Hyperion General Do you anticipate to implement the
automated tool for metadata
synchronization (like accounts,
departments etc.) for Hyperion Planning
with source systems like PeopleSoft
FSCM? If yes, do you have licenses for
the tool?
PeopleSoft FSCM remains the system of record for all chartfields
from which metadata for Hyperion shall be synchronized. (Please
note that Hyperion DRM is not in scope.)
216 Lot2-Hyperion General Terms Of reference.pdf-Page9-Though
implementation of Hyperion is clearly
mentioned in LOT1, on this page it says
"Review 7 implementation of solution
replacing EPM; this seems like a
contradiction?
Revalidation of solutions (including those that replace EPM) is part
of this engagement. Refer to "Work-package 02 - Business process
analysis and detailed design".
It is mentioned specifically for EPM purely to emphasize that the
analysis still should be done even though EPM will be
decommissioned.
Page 45 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
217
218
219
220
217 Lot2-Hyperion General Terms Of reference.pdf-Page10-There
should a be a detailed review of existing
reports- obsolete, enhanced replaced- is
this required as a separate task or can I
include it in requirement gathering phase
altogether?
Financial reports to be developed in HFR, WebAnalysis and
SmartView shall be identified during the detailed analysis and
design phases of the project.
218 Lot2-Hyperion General Terms Of reference.pdf-Page10-UNHCR
prefers a single go-live date for
PSFT9.2,GRC & Hyperion- then what is
the difference between LOT1 & LOT2?
It is a UNHCR internal decision to have a single go-live for PSFT9.2
(and GRC) and Hyperion, since Hyperion replaces EPM.
Difference between lots: The lots are divided into groups of
applications. Lot 1 covers PeopleSoft (and GRC), Lot 2 covers
Hyperion. Refer to ToR, p3, Requirement Groupings (Lots)
219 Lot2-Hyperion General Terms Of reference.pdf-Page11-says
preferred model is Onsite but mixed can
also be considered; Are we thinking for
giving Mixed mode implementation? If
yes then our best practice (40% Onsite,
60% offshore model)?
See also: 219, 549 As clearly described in the 3.3 Statement of Work of the TOR (para
3.)
"… should the proposed delivery model include work conducted
offshore, the System Integrator must include the approach in the
proposal..."
220 Lot2-Hyperion General Terms Of reference.pdf-Page11-Work will
be in two locations- Budapest & Geneva;
does it mean that these have separate
setup? Or is it one integrated system
accessed from different location, Are
rollouts out of scope?
One setup, one integrated system globally. Work location defined
based on duty station core business user groups.
For in-scope activities, see work packages.
Page 46 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
221
222
223
224
225
221 Lot2-Hyperion General Terms Of reference.pdf-Page13-Business
Process revalidation only? Pls confirm
that the detailed requirement gathering
has already been done? This page also
says that Detailed Business
Requirements document is a deliverable.
So what does it mean
The high level business requirements already captured should be
updated, refined and completed as per the Terms of Rerefence
document, Workpackage 2. The detailed requirements gathering
and analysis is in scope of this project.
222 Lot2-Hyperion General Terms Of reference.pdf-Page16- End
User Training; typically for Hyperion
since it’s a small module, we provide 1
week of "Train the trainer" trg for Key
Users & 1 week for Admin Users. Will
that be sufficient in this case. Pls specify;
We will have a custom built curriculum
for the training depending upon the
implementation of Hyperion at UNHCR. I
am assuming thats is the Ask, Pls confirm
This should be answered/assessed as part of WP04.
For additional information on training, see attached document: RFP
QandA - Training
223 Lot2-Hyperion General Terms Of reference.pdf-Page18-Says Non
production instances as Dev,SIT & Uat
therefore there are a total of 4 instances
, pls confirm
For Hyperion, the appropriate number of instances has to be
determined as part of this engagement. Using the currently ERP
application as baseline: DEV, TST (SIT), UAT and PRD, with
additional support and training environments.
224 Lot2-Hyperion General Terms Of reference.pdf-Page19-Talks
about Disaster Recovery- is there a
separate DR instance requirement
See answer to question: 139
225 Lot2-Hyperion General Terms Of reference.pdf-Page19-DBA
activities are required from SI's end?
Yes.
Page 47 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
226
227
228
229
230
226 Lot2-Hyperion General Terms Of reference.pdf-Page20-Talks
about PeopleSoft HCM(Personnel &
Payroll) & FOCUS as the external
systems? Are these the only two systems
or are there any other. Pls specify
Foreseen systems to interact with Hyperion:
- PeopleSoft FSCM
- PeopleSoft HCM
- Focus
(See systems interactions diagram in Annex B - Appendix II -
Application Overview - Lot2 - Hyperion - Position Budgeting, page
5).
227 Lot2-Hyperion General Terms Of reference.pdf-Page22-Test
Scripts have to be prepared by SI? This is
typically done by the customer & forms
basis of acceptance during Uat
For UAT, test cases, scenario and related test data for will be
provided by UNHCR. The technical work required to create the test
scripts enabling the test execution remains the responsibility of the
System Integrator.
For unit testing and SIT, testing is the responsibility of the system
integrator with quality and testing procedure compliance checks by
UNHCR.
228 Lot2-Hyperion General Terms Of reference.pdf-Page22-What is
configuration Testing?
In the context of Hyperion, this is anticipated to be a test that the
recommended Hyperion configuration will work with
interdependent (hardware, software, network/web setup)
components.
229 Lot2-Hyperion General Terms Of reference.pdf-Page22-IS
volume/stress testing required?
Yes
230 Lot2-Hyperion General Terms Of reference.pdf-Page24-3 months
of Post go live Support+ additional 3
months of extended support is required,
is the extended support optional
currently or has to be estimated right
away?
Yes extended support should be estimated as part of the overall
project implementation plan
Page 48 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
231
232
233
231 Lot2-Hyperion General Annex B - Appendix IIII - 1 -
Customization Review-Page 56-Says
"Existing EPM Customizations for
Planning and Budgeting needs to be
dropped.". Since we are always
reemploying Hyperion, all the
customizations will have to be recreated.
Does this mean that they don’t want any
of the old customizations?
Hyperion has different architecture and capabilities compared to
EPM. In that sense there are no EPM customizations to be ported
to Hyperion to deliver the functionality required for UNHCR.
232 Lot2-Hyperion General Annex B - Appendix IIII - 2 -Customized
reports and queries-There are about 21
existing reports mentioned in the list; is
this the final requirement for the Pracle
Hyperion as well or we can expect more
reports?
Reports relate to Income recording are not in scope for Hyperion.
At least 9 NVision reports for detailed budgeting in the current
EPM system are in scope. UNHCR will take advantage of Hyperion
reporting capabilities, and expects to have additional reports in
Hyperion. (See also Annex B - Appendix II - Application Overview -
Lot1 - Bolt-on - Partnership Management, "Challenges section").
233 Lot2-Hyperion General Annex B - Appendix IIII - 4 Technical
Architecture-page2-The technical
Architecture document talks about a
number of instances Dev,Test,Training,
Production,Pod Support, DR. Pls can you
confirm the number of the instances &
the names. As a Best practice for
Hyperion we have Dev->Test-
>Production environment
See response to question: 223
Page 49 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
234
235
236
234 Lot2-Hyperion General Annex B - Appendix IIII - 4 Technical
Architecture-page3-Do you want High
Availability on Production & DR for
Hyperion as well? Pls confirm
Definitely, high availability of Hyperion in Production.
The availability in non-production enviromnment will be discussed
during the engagement, but would normally follow best practice.
235 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 9-What does this line mean "There
should not be any developments
required in Focus for Hyperion
Planning"?
It is not expected that the replacement of EPM by Hyperion would
require changes in other systems such as Focus.
("Focus" is the name of the RBM planning and budgeting tool of
UNHCR, see systems interactions diagram in Annex B - Appendix II -
Application Overview - Lot2 - Hyperion - Position Budgeting, page 5
)
236 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 10-Says "PeopleSoft HRMS 8.9 will
be upgraded to 9.2 (out of the scope of
this project).Approved positions will be
exported from period and created in
HRMS 9.2 during planning." From
Hyperion Perspective can we assume
that our source will be HRMS 9.2 which
would have been upgraded by UNHCR
separately or shall we assume that it
would be 8.9?Pls confirm
Currently, HRMS is anticipated to go-live before the applications in
this project.
Refer to Q&A: 8
Page 50 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
237
238
237 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 10-"Reporting from Global Focus
Insight will continue. UNHCR can
leverage multidimensional reporting
features of Hyperion planning
Budgeting". What does this mean? If If
GFI is going to continue, will it be the
main reporting tool? Or Are we
considering HFR as the main reporting
tool?
GFI is a UNHCR BI tool is meant for monitoring operational
information, it has access to a limited set of financial data.
HFR is meant for financial analysis only with a broader scope of
financial data.
238 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 9-PeopleSoft FSCM will be
upgraded to 9.2. Posting of
Comprehensive and position budgets will
happen the
same way from Hyperion . Can you
elaborate on the role of FSCM in the
Future State post Hyperion
Implementation?
Please see Annex B - Appendix II - Application Overview - Lot1 - FS -
General Ledger (page 7 "Standard budget maintenance").
Page 51 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
239
240
241
239 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 10-"Reporting from Global Focus
Insight will continue. UNHCR can
leverage multidimensional reporting
features of Hyperion planning
Budgeting".
From the list of Budgeting and Planning
reports, which reports will be generated
from existing reporting tool in future.
Also, is there any list of reports required
from Hyperion available at this stage
?(Using Smart view, Web Analysis and
Hyperion Financial Reports)
How and when do you distribute reports
within the organization ?
See response to question: 232
240 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
How and when do you distribute reports
within the organization ? Is there any
requirements for reporting books?
There are currently various models for distributing reports through
the organization (peridic and ad -hoc, self service, through
subscription, etc.) which will be elaborated during the engagement.
The various possibilities offered by Hyperion for reports
distribution and report books shall be evaluated against the
business requirements during the analysis phase, as specified in
the Workpackage 2 of the Terms of Reference.
241 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
What are the requirements for Historical
reporting ?
Hystorical data shall be accessible readily from Hyperion reporting
mechanisms.
Page 52 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
242
243
244
245
246
247
248
249
250
242 Lot2-Hyperion General
Lot2 - Hyperion - Detailed BudgetingIs
there any requirement of Multi language
interface/ reports?
See also: 52 104
137 158 242 488
507 5265 537 557
577
Working language is English. However, for a few reports,
translations may be required for additional languages, likely to be
French and/or Spanish.
243 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 10-No of Hierarchies required ?
See "Hyperion Planning High level design" section of Annex B -
Appendix II - Application Overview - Lot2 - Hyperion - Detailed
Budgeting.
244 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-No.
of Accouunts / Roll up structures? To be determined/elaborated. Detailed requirements gathering
and analysis is part of the engagement.
245 Lot2-Hyperion General Lot2 - Hyperion - Detailed Budgeting-
Page 8-Other than 5 Key challenges for
Budgeting mentioned on Page 8, are
there any pain points ?If so, can you
elaborate?
Please see also Key challenges for "Position management section"
of Annex B - Appendix II - Application Overview - Lot2 - Hyperion -
Position Budgeting. Detailed analysis and design will allow
identifying additional issues and challenges.
246 Lot2-Hyperion General How do you maintain the security and
workflow management ?
To be determined/elaborated during the engagement.
247 Lot2-Hyperion General What is the user base? Is that centralized
?
See response to question: 299
248 Lot2-Hyperion General No. of groups required for the system? See response to question: 299
249 Lot2-Hyperion General Can you elaborate on the Historical data
migration requirements for Hyperion
?How many years of data is required to
be migrated from PSFT EPM to Oracle
Hyperion?
To be determined. For reference, oldest models are from 2006.
250 Lot2-Hyperion General Will Actuals (Expenses) comparison with
Budget be done in Hyperion ? If Yes, then
what will be the source system for
Actuals data?How is the comparison with
Actuals being done today? What will be
the process to be adopted for future ?
Ability to check the budget vs. existing commitments is required.
Therefore, Commitment Control expenditures and closed period
data shall be imported and closed period data shall be imported as
well (Donor Report ledger).
Page 53 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
251
252
253
254
255
256
257
258
251 Lot2-Hyperion General What will be the source system for
Actuals data?
PeopleSoft
252 Lot2-Hyperion General What are the audit trail requirements? The capability to track for each budget submission is required (i.e.
when it took place, who submitted it, who approved, whether
target validation was executed and whether it failed or pass)
253 Lot2-Hyperion General Is Hyperion Public Sector Planning in
scope ?
No.
254 Lot2-Hyperion General Do we have to implement Hyperion
Planning with CAPEX & Workforce
modules?
No.
255 Lot2-Hyperion General Would there be a need for Manual
Adjustments to be done ?
Yes, but only for the information captured/entered/owned in
Hyperion (i.e.: information owned by other systems shall cannot be
altered by the users in Hyperion)
256 Lot2-Hyperion General Reimplementation of Hyperion & data
migration is the scope for Hyperion. Pls
can you elaborate on Data migration
requirement?
Yes, data migration is in scope. Detailed requirements will be
determined as part of the engagement.
257 Lot2-Hyperion General The RFP says that the inception &
conception phases have been
over.However, the two documents
provided for Hyperion are at very high
level. Pls can you provide all the detailed
documents on Hyperion, it will help us to
estimate better
Most activities were conducted to determine high-level functional
fit/gap and keep/drop. Further detailed analysis to be performed in
the RFP Work-package 02, particularly for any new application
implementation or functionality development.
On detailed documentation, see answer to question 35.
258 Lot2-Hyperion General Given that Salary and Grade is taken from
PSoft HRMS System and Salary ID is defined in
EPM, how does salaried establish a link
between the salary cost and position.
Please see, Annex B - Appendix II - Application Overview - Lot2 -
Hyperion - Position Budgeting "Calculation of estimated staff cost"
section for the calculation of the position cost associated to each
EPM Job code.
Page 54 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
259
260
261
262
263
264
259 Lot2-Hyperion General How are all position parameters consolidated
at the EPM Job Code ? How is the EPM Job
Code defined? Can a scenario with example
be provided ?
Please see, Annex B - Appendix II - Application Overview - Lot2 -
Hyperion - Position Budgeting "Calculation of estimated staff cost"
section.
260 Lot2-Hyperion General Given that the frozen FOCUS position plan
consists of location, grade, cost, EPM JC, HR
JC, goal and eff..dates. Can an example
depicting this information be provided
explaining how the goals are used in position
planning ?
The Goal is currently used on the Positions themselves to carry the
information determining whether it relates to programme,
management or support function (in this particular case, the Goal
does not relate to RBM, but the chartfield is reused for this specific
purpose).
261 Lot2-Hyperion General Given that FOCUS maintains only one account
code (699999) per position.
How can the position budget be summarized
at cost center and account level ?
The breakdown by detailed account codes is maintained in EPM.
262 Lot2-Hyperion General Given that during implementation, the 'OL'
position changes (i.e. Add/Change/Delete) are
directly done in PSoft HRMS, without the
intervention of PSoft EPM.
How is the position information related
sanctivity maintained in PSoft EPM w.r.t to
these changes ?
EPM is used during the planning phase to calculate the cost of
Positions of a particular grade and a particular location. The
position requirements are determined in Focus using this
information. Following decisions of a review process, approved
Positions are transferred from Focus, to EPM, to HRMS.
During implementation phase, cost by grade and location
maintained in EPM does not change (unless exceptions). The
source reference for the Positions themselves remains HRMS.
263 Lot2-Hyperion General What does "desgin revalidation" indicate ?
How and when is it expected ? Is it expected
to be part of the RFP?
Who would be responsible for conducting the
design revalidation ?
The high level business requirements already captured should be
updated, refined and completed as per the Terms of Rerefence
document, Workpackage 2. The detailed requirements gathering
and analysis is in scope of this project.
264 Lot2-Hyperion General What does the second phase of MSRP
Upgrade project indicate ? when is it
scheduled ?
If referring to general MSRP Upgrade Project phasing, first phase
refers to the "Conceptual Design", second phase is the "Build and
Construct" covered by this RFP.
Page 55 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
265
266
267
268
269
265 Lot2-Hyperion General As part of the "Design Revalidation" can the
existing design/dimension structure/model be
changed, modified or deleted.
Yes, adjustments can be made as part of the design revalidation as
long as justified and aligned with the business requirements.
266 Lot2-Hyperion General Is there a spcific reason for having a separate
application for position planning as the same
information would be used for computing the
"STAFF" cost?
Secondly, any specific reason for storing
position information in two different cubes in
the POSBUD application
Recommendations shall be reviewed during the design
revalidation.
Refer to Work Package 2 of the Terms of Reference.
267 Lot2-Hyperion General Though it mentions a biennial cycle, the
references indicate an annual cycle for
budgeting as the planning cycle involves a
comprehensive operational plan for
subsequent year which then is detailed to be
implemented again in the subsequent year.
What would be horizon for actual budget
preparation - annual or biennium ? If
biennium, then how and when is the second
year of biennium planned and detailed ?
2016-2017 biennium example:
- In 2015: UNHCR plan activities for 2016 and for 2017.
- In 2016: UNHCR implements 2016 activities and re -plan 2017
activities with more details and more accuracy.
- In 2017: UNHCR reports on 2016 activities and implements 2017
activities.
268 Lot2-Hyperion General Is spending authority the same as budgeting
ceilings ? what is the granularity for it ?The budget ceiling, also refered as Budget Target, is the total OL
budget approved for a given UNHCR Operation for a given year.
The spending authority represents the available budget balance to
spend for a given UNHCR Operation in the current year. The
spending authority is defined per budget year, Cost Center, Pillar,
budget category and implementer type (Direct implementation or
through partnership)
269 Lot2-Hyperion General Supplementary Budgets. Do they need to be
tracked as separate budgets or an increase to
the existing budgets for each pillar ?
Additional resources approved resulting from Supplementary
Budget requests shall be tracked in Hyperion Planning.
Page 56 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
270
271
272
273
274
275
270 Lot2-Hyperion General Understanding:
A comprehensive budget consists of three
categories, namely 'Operational
Budget'(OPS),'Administrative Budget'(ABOD)
and 'Staff Costs'(STAFF).
These categories in turn are categorised as -
Funded Budget (OL) and Unfunded Budget
(AOL)
Is the above understanding correct ?
These are 2 different characteristics of the budget. The budget is
broken down in 3 categories (OPS, Staff and ABOD), and comprises
a funded (OL) and un-funder (AOL) component.
271 Lot2-Hyperion General Given the RBM hierarchy and budgeting
cycles, is PPG and Pillar at the same level ?
Can a scenario explaining the process defining
a RBM hierarchy and budget by Pillar be
provided ?
No, PPG and Pillar are 2 different dimensions with no parent-child
relation.
See also answer to question 272.
272 Lot2-Hyperion General How do the 4 budget pillars assimilate with
the RBM Hierarchy?Pillars are an orthogonal dimension to RBM hierachy. In other
words, any RBM element of an Operation's plan can be linked to
any of the 4 Pillars.
273 Lot2-Hyperion General How do "cost center" and "outputs" relate in
terms of the budget preparation as the
Budgets are entered at 'Output' level and roll-
up the RBM hierarchy.
Cost Center is an orthogonal dimension to RBM hierachy and
therefore Outputs. In other words, any Output element of an
Operation's plan can be linked to any Cost Center.
274 Lot2-Hyperion General Where is the implementer code used in the
budget preparation/RBM hierarchy ?Each OPS budget line is qualified with an implementer code. The
implementer code determines whether the item/service supported
by the budget line is delivered by UNHCR directly or through a
partner.
275 Lot2-Hyperion General Considering that a 'situation' and an
'operation' are the same, in The given
example, between codes 1115 and 4115, 1 &
4 reperesent the pillar - Please clarify what do
the remaining 3 digits indicate ?
Situation and Operation are different. A Situation refers to a
specific operational crisis or emergency, often of a regional nature,
encompassing multiple countries and therefore multiple UNHCR
Operations.
The last 3 digits are used for distinguishing and tracking specific
Situation by Pillar across UNHCR Operations.
Page 57 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
276
277
278
279
280
281
282
276 Lot2-Hyperion General What are the contents of FOCUS ? Does it
consists of RBM/Narratives and budgeting.
Given the implementation of Hyperion
Planning, would FOCUS still continue to hold
the RBM hierarchy narratives ?
Focus remains the primary tool fo UNHCR end users to enter
planning and budgeting information (RBM plan structure
definition, narratives, indicators, budgets).
277 Lot2-Hyperion General What is the time horizon of budget
preparation?
When is the approved budget exported from
FOCUS and imported into EPM and what
level?
The planning and budgeting cycle is outline in Annex B - Appendix II
- Application Overview - Lot2 - Hyperion - Detailed Budgeting,
"budgeting cycle" section.
See also answer to question 472.
278 Lot2-Hyperion General What is the difference between approved
budget, budget targets/ceiling and summary
budget ?
See answer to question 268.
279 Lot2-Hyperion General Given that Budget Target Validation of only
the 'OL' component is carried out for OPS and
ABOD, is there similar validation for 'AOL' ?
Currently, no.
280 Lot2-Hyperion General Please clarify if our understanding is correct -
There is no incremental update if OPS or
ABOD budgets fails target validation and the
entire budget load fails
Correct.
281 Lot2-Hyperion General Staff Budgets dont undergo Budget Target
Validation ?No. Only approved staff positions can be exported from Focus to
Hyperion by the Operations. As the related staff costs have been
approved upfront, there is no need to undergo budget target
validation for staff costs.
282 Lot2-Hyperion General Given that the budget in FOCUS is entered
and maintained multiple currencies, in what
currency is the operational budget computed
where multiple currency are involved during
the implementation
USD
Page 58 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
283
284
285
286
287
288
289
283 Lot2-Hyperion General HQ entering budgeting Targets? Arent the
budget targets being entered in FOCUS,
exported and imported in EPM? How are they
different from the approved budget for OL.
See 268 for budget targets definition. The details budgets are
entered in Focus by the Operations then exported to EPM when
they undergo budget target validation against the budget targets.
Budget targets reflect the approved budgets at a more granular
level.
284 Lot2-Hyperion General What are commited amounts? Where are
they entered ? and at what level is the
comparison carried out ?
Commited amounts refer to encumbrances and pre encumbrances
in this context.
285 Lot2-Hyperion General How and Why are multiple versions of
approved budgets possible and and what
purpose do they serve ?
Within a budget year, the approved budget of the operations can
be increased to allow them to address unforeseen operational
emergencies. It is important to be able to keep track of these
changes during the year.
Details/Justification on this requirement will be provided as part of
the engagement.
286 Lot2-Hyperion General How and Why are multiple versions of target
validated budgets possible and and what
purpose do they serve ?
See answer to question 285
287 Lot2-Hyperion General If multiple version of target-validated budget
exist, which version is exported and imported
into Psoft Financials FOBS Ledger ?
The current/most recent version is exported and imported in FSCM
FOBS ledger.
288 Lot2-Hyperion General What are the existing reports from Global
Focus Insight? Once hyperion planning is
implemented, what are report expectations
from it ?
See response to question: 237
289 Lot2-Hyperion General what does the statement "The budget targets
are defined at the beginning of the
implementation and reflect the approved
initial OL." inidicate ?
See answer to question 268.
Page 59 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
290
291
292
293
290 Lot2-Hyperion General Given that the Custom Dimension "Pillar
Situation" is used to represent the
Operational event alongwith the "Entity"
Dimension, is the RBM hierarchy/Budget
pertaining to an operation entered "per
country" as depicted by the "Entity"
dimension?
See answer to question 326.
291 Lot2-Hyperion General How and where is the Site Code dimension
used ?The Site code is mainly used for planning and budgeting where it
represent either a physical geographical location (a camp, a village
or a region) or a mean to track specific projects or activities.
292 Lot2-Hyperion General Is there a spcific reason for having a separate
application for position planning as the same
information would be used for computing the
"STAFF" cost?
Secondly, any specific reason for storing
position information in two different cubes in
the POSBUD application ? Can it be
remodeled ?
See response to question: 266
293 Lot2-Hyperion General Query: The high level diagram, as well as Step
1 and Step 3 mention the FDMEE for
transferring information between different
systems while use of ODI is retricted to Step
2. Is there a specific reason behind use of
using 2 different integration tools ? Can this
model be adjusted to use only FDMEE/ODI as
integrator?
To be validated during the engagement.
Page 60 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
294
295
296
294 Lot2-Hyperion General The technical architecture details
application stack consists of four layers -
Production, Training, Non-Production
and DR. Additionally under non-
production stack, six environments have
been detailed. Please let know if
installation and support for all these 9-10
environments need to be planned.
Yes.
Please also see response to question: 103
295 Lot2-Hyperion General The technical architecture details the
server details / sizing for various
environments. Please let know if the
same is final or does the bidder needs to
plan for services related to updating the
same considering the final application
landscape and process confirmed as part
of the implementation
Technical architure (future) - to be determined.
UNHCR has a hosting service provider with whom the project
should collaborate to ensure proper hardware sizing and setup.
See Work Package 6.
296 Lot2-Hyperion General As per Annexure B-5, UNHCR has
proposed for two options, does that
mean that bidders have to submit
proposal for both options in each Lot
because efforts & commericals can be
different in both the options
For Hyperion, only one proposal is required focusing on how
Hyperion (development and implementation) should fit in the
overall project delivery.
Page 61 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
297
298
299
300
301
297 Lot2-Hyperion General a) We assume that UNHCR has procured
the licences for Hyperion Planning,
Hyperion Web Analysis and Hyperion
Financial Reporting. Please confirm
along with version details.
b) Also, please confirm what additional
Hyperion and other technology tools /
licenses have been procured by UNHCR ?
Provide details.
The following apps have been purchased: Hyperion Planning Plus,
Hyperion Financial Data Quality Management, Enterprise Edition,
Hyperion Financial Data Quality Management, Enterprise Edition,
Adapter Suite.
For additional information, refer to the attached document on
target application verions
298 Lot2-Hyperion General Do you budget in more than one
currency ? If so, please define the
currencies used for data entry as well as
those currencies used for reporting.
Yes, detailed budgets
299 Lot2-Hyperion General What is the expected number of users /
concurrent Users for Hyperion Planning ?
Refer to attached document on Users and Volume of Common
Transaction for best available information.
300 Lot2-Hyperion General Does UNHCR have any timelines which
they have set for the implementation of
Hyperion Planning ?
See also: 300 462
Hyperion must go-live at the same time as PeopleSoft 9.2 (core
FSCM applications).
See:
ToR - 3.2.6 - Methodology and Options for Upgrade
ToR - Appendix_IIII_-_5_-
_Methodology_and_Options_for_Upgrade
301 Lot2-Hyperion General Do you have uptime requirements that
require failover, redundancy, and
disaster recovery?
Yes, up all the time.
Page 62 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
302
303
304
302 Lot2-Hyperion WP02 Regarding revenue allocation and
earmarking tracking, can you please
elaborate on the different scenarios for
‘What-If’ analysis?
While the scenarios need to be determined/elaborated they are
likely to include exchange rate fluctuation and the impact of
approving or denying certain programmes. Detailed requirements
gathering and analysis is part of the engagement.
303 Lot2-Hyperion WP02 Can you please share the excel which is
currently used for revenue allocation
and earmarking tracking? If UNHCR
wants to automate the functionality,
then we would need to understand the
current manual process
UNHCR do not currently have a well-functioning tracking solution.
Proposals should be provided following detailed requirements
gathering and analysis. An example of a spreadsheet that is
currently used for earmarking tracking is attached to illustrate the
current manual processes. The example contains fake data.
304 Lot2-Hyperion WP02 Does UNHCR have a specific Data
Integration tool for Hyperion
Implementation? Please clarify whether
tools like ODI or Informatica can be used
for System Integration?
UNHCR has acquired FDMEE/FDQM. The system integrator should
advise of the best data integration tool to use, preferably using the
above or any other tool delivered with Hyperion/PeopleSoft/Oracle
for which it already has license.
Page 63 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
305
306
307
305 Lot2-Hyperion WP02 Position Budgeting Module :
• How many reports needs to be
developed in Financial Reports?
• Extracting data from Source Systems is
it in the Scope of the System? Or will it
be provided by the Team? For Example:
Extraction of Active Positions from HRMS
is it under the Scope Lot 2 Hyperion
Project?
• How many users are planning to use
the system? This is required for load
balancing
• Installation of Hyperion Planning
System - Is it under the scope?
• What kind of security level is expected
in the Hyperion Planning Web Forms?
• How many web Forms needs to be
developed in Hyperion Planning?
See also: 132 305
Some details may only be elaborated during the engagement (eg.
number of web forms, number years of history, security levels,
etc).
Less 10 reports existing positon management reports exist in the
current EPM system but it is expected to have more in Hyperion.
Current EPM Queries are provided in Annex IV section 2.
Interfaces with HRMS are in place to access position data. Review
and analysis of these interfaces, extraction of Position data is in
scope.
Currently EPM has approximately 2500 individual users. The
number of Hyperion users will have to be determined.
306 Lot2-Hyperion WP02 Please share details of current gaps /
pain areas if any on the compliance with
UN System Accounting standards that
requires to be addressed through this
project
Please refer to Annex B - Appendix II.
307 Lot2-Hyperion WP02 Please share details of current gaps /
pain areas if any on the compliance with
International Public Accounting
standards that requires to be addressed
through this project
Please refer to Annex B - Appendix II.
Page 64 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
308
309
310
311
308 Lot2-Hyperion WP02 Please share details of proposed
Hyperion Planning and HFR user base
and their locations
HFR reports should be accessible to all UNHCR users which can be
located in any of the HQ and 126 UNHCR Operations. (Some with
limited internet connectivity)
309 Lot2-Hyperion WP02 In Annex – B – Appendix II – Application
Overview – Lot 2 – Reporting will be met
through
Hyperion Cubes – Are the cubes referred
here are a) Est_Pos b) Est_Pln and c)
Pos_Pln
more details be provided on this
Current design recommendations will be reviewed and finalized
during the detailed analysis and design phase of the project, which
is in scope of this RFP.
310 Lot2-Hyperion WP02 In Annex – B – Terms of Reference –
Sec.2 Project Overview – 2.1 – Business
Drivers & Expected Benefits - Reporting
& Management Oversight – Can more
details in terms of the list of reports and
years of data be provided on Improve
system performance through Data clean
up.
Taking advantage of Hyperion reporting capabilities, it is expected
to have more reports in Hyperion than listed in Annex B - Appendix
II - hyperion planning documents
311 Lot2-Hyperion WP02 In Annex B - Terms of Reference - Sec 1 -
Additional Activities in scope (The use of
ETL and other integration tools) Is
UNHCR planning to use other ETL and
Integration tools other than FDQMEE ? If
yes, what are they and for what purpose
of they will be used in this project?
To be validated during the engagement.
Page 65 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
312
313
314
315
316
317
318
312 Lot2-Hyperion WP02 In Annex B - Terms of Reference - Sec 1 -
Additional Activities in scope (Essbase
installation) - Please confirm if Essbase
installation is the database of planning
application or additional cubes? Request
you to please elaborated on this
Essbase is expected to be the database of Hyperion Planning
Applications. The system integrator is expected to either install and
configure Essbase themselves or write the document explaining
how to install and configure Essbase as required by the project to
be carried out by the hosting service provider.
313 Lot2-Hyperion WP02 How many years of historical data
(Actual) needs to be loaded and
managed in the system
To be determined. For reference, oldest models are from 2006.
314 Lot2-Hyperion WP02 What is the budgeting approach – top
down or bottom-up?
The budget captured by the Operations is realized at Output level,
bottom -up approach.
315 Lot2-Hyperion WP02 We assume that the reports mentioned
in this section are the only reports for
Hyperion Planning. Please confirm and
let us know if there are any additional
number of reports.
See answer to question 431.
316 Lot2-Hyperion WP06 Please share details of proposed
hardware for implementation of
Hyperion Planning and Hyperion
Financial Reporting
The system integrator is expected to come up with a
recommendation.
317 Lot2-Hyperion WP06 Please share details on version of FDMEE
,Hyperion Planning and Hyperion
Financial Reporting that needs to be
implemented in this project
Refer to attached document on target application version.
318 Lot2-Hyperion WP07 What is the current process through
which Meta data is managed across
applications (Focus , PeopleSoft , Oracle
GRC) and the plan for management on
implementation of Hyperion Planning
Currently, data is transferred mainly using database links, XML files
and messaging (integration broker).
Page 66 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
319
320
321
322
323
324
325
319 Lot2-Hyperion WP07 Please share Details of reports that needs
to be achieved through HFR , Web
analysis and Smart view. Can a sample of
these can be provided to understand
complexity
See answer to question 431.
320 Lot2-Hyperion WP07 As mentioned in "Annex B - Appendix IIII -
4 - Technical Architecture" - Section
1..3.4 and section 1.4.1, please share
"Annexure - A"
Please see attached files for "RFP 647 - QandA 320 ...".
321 Lot2-Hyperion Planning How many number of users will be
accessing the Planning and Budgeting
system.If possible please provide
approximate spread by Geography
See answer to question: 308
322 Lot2-Hyperion Planning What is the number of concurrent users
accessing the Planning and Budgeting
system
See answer to question: 308
323 Lot2-Hyperion Planning What is the frequency of budgeting
(Monthly, quarterly, half yearly etc..)?
See answer to question 472.
324 Lot2-Hyperion Planning Is there a situation where your
transactions happen in more than one
currency and does UNHCR expect
planning and budgeting tool to handle
Multi currency and currency
translations?
Yes, UNHCR Operation may operate in USD in combination of one
or several other currencies. Hyperion should be able to handle this.
325 Lot2-Hyperion Planning Which master data tool does UNHCR use
currently to manage dimensions and
hirarchies. Is Hyperion DRM in scope for
this implementation?
Currently Hyperion is not implemented. Hyperion DRM is not in
scope. PeopleSoft FSCM remains the system of record for all
chartfields (presumably main dimensions for Hyperion)
Page 67 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
326
327
328
329
330
331
332
326 Lot2-Hyperion Planning Will there be any changes to existing
People Soft EPM dimensions when
implemented in Hyperion Planning
Mapping of existing dimensions to Hyperion planning will be
reviewed and finalized during the detailed analysis and design
phase of the project, which is in scope of this RFP.
327 Lot2-Hyperion Planning Please provide the number of business
entities which are required to be covered
under the Planning and Budgeting
process.Also provide the base members
in account and cost center dimension
Question is not clear. Most likely this question will be answered
during the engagement.
328 Lot2-Hyperion Planning What are the requirements for
availability of Historical Plan and actuals
data in Hyperion Planning application?
Question is not clear. Most likely this question will be answered
during the engagement.
329 Lot2-Hyperion Planning Does UNHCR have ODI or FDMEE in
current landscape which can be
leveraged for data and metadata loads to
Hyperion Planning (BUDPLAN)
application? If not which ETL tool
licenses have been purchased for
Hyperion Planning
Refer to attached document on target application version.
330 Lot2-Hyperion Planning What is the ETL tool that UNHCR is
planning to use?
See response to question: 329
331 Lot2-Hyperion Planning What is the complexity of allocations
(Simple, Medium, Complex) to be
automated/defined in Hyperion
Planning? What is the approximate no. of
allocation rules that is required to be
allocated?
Question is not clear. Most likely this question will be answered
during the engagement. For best estimates, please refer to the
attached Annex B - Appendix II for business requirements.
332 Lot2-Hyperion Planning Is there any Driver based Planning in
scope?
Page 68 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
333
334
335
336
337
333 Lot2-Hyperion Planning Can you please share the approximate
number of business/validation rules (like
allocations, currency conversion etc)
associated with the planning process and
their complexities
Please see Annex B - Appendix II.
334 Lot2-Hyperion Planning The document says that "for position
budgeting system the replacement of
PeopleSoft EPM by Hyperion Planning
will have to be revalidated against the
business
requirements during the second phase of
the MSRP upgrade project". So do we
have to provide estimates for
implementation of Position Budgeting in
Hyperion Planning as part of estimates
for "Lot 2"
Yes
335 Lot2-Hyperion Planning How many reports are to be developed in
Hyperion Financial Reports/ Web
Analysis?
See response to question: 232
336 Lot2-Hyperion Planning Is DR for Hyperion Planning in scope? Please refer to Work Package 6.
"The System Integrator must develop a back-up and recovery plan
as well as a disaster recovery strategy which is appropriate for the
new technical architecture to ensure high availability of the
system."* CB: Carlo - to answer
337 Lot2-Hyperion Planning Is Hardware installation and setup for
Hyperion also in scope for the vendor
Please refer to Work Package 6.
UNHCR has a hosting service provider with whom the project
should collaborate to ensure proper hardware sizing and setup.
Page 69 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
338
339
340
341
342
343
344
338 Lot2-Hyperion Planning Please confirm whether the servers for
all the required environments for
Hyperion Planning would be physical or
virtual?
The system integrator is expected to come up with a
recommendation. Preference is for a full virtual solution.
339 Lot3-Demantra General We understand that implementation of
demantra and SNO will be done from the
ground up (no prior existence). Please
confirm.
Yes, implementation will be done from the ground up.
340 Lot3-Demantra General Has UNHCR decided the 'Versions' of the
Planning applications? If yes please let us
know details
Best available information is in the attached document on target
application version
341 Lot3-Demantra General Please list down the actual names of the
Modules to be implemented under
Planning section (Demantra, SNO)
Relevant modules/functionality in Demantra and SNO addressing
the high-level requirements provided in the document. (System
integrator to advise.)
Refer also to the attached list of target applications and their
versions.
342 Lot3-Demantra General Scope: Please provide us the scope in
terms of a) Geographies/Countries and b)
Languages
See also: 52 104
137 158 242 488
507 5265 537 557
577
Supply:
a) worldwide (90-120 countries)
b) English
343 Lot3-Demantra General Has UNHCR been using any other
applications for Planning in the 'As-is'
World? Please provide details
For supply planning, planning has been done mainy in Excel.
344 Lot3-Demantra General In both options of the program as
mentioned in Appendix 3,
implementation of Planning applications
is indicated after the core PS and
Treasury work is completed. Please
confirm if this understanding of ours is
correct.
Refer to timeline and constraints, as well as Annex B-AppendixIII-
Methodology and Options. In both options, the schedule of
activities should be adapted to the timeline and constraints of the
project.
Page 70 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
345
346
347
348
349
350
351
345 Lot3-Demantra General Infra and Sizing: has UNHCR already done
any kind of Infrastructure or
Environment Sizing for the Planning
applications? If yes please share details
No, please submit proposal for technical architecture requirements
/ sizing
346 Lot3-Demantra General Apart from PS are there any other ERP
applications from which data needs to be
pulled into Demantra? If so please share
the ERP application details.
Data will be pulled from PeopleSoft and possibly Excel
347 Lot3-Demantra WP02 Has UNHCR performed high level fit-gap
analysis/ requirement gathering for
Demantra and SNO?
As per shared documentation, only a feasibility study to determine
that the modules are capable of handling the UNHCR required
functionality has been undertaken. No formal fit-gap session
undertaken.
348 Lot3-Demantra WP02 Please let us know what is Demantra
Version and What are Demantra
Modules in Scope for this
implementation?
Refer to attached QandA - Technical - Target Application Versions.
349 Lot3-Demantra WP02 Please share the number of items,
customer and approximate sales history
count (Volume)?
There is no 'traditional' sales activity.
350 Lot3-Demantra WP02 Please elaborate about UNHCR RBM
(Result Based Management)Framework
In a nutshell RBM is UNHCR's management strategy which also
includes managing the resources of the organization along a
Results Framework (RF). It guides the assessment, planning,
allocation of resources, implementation and reporting. The RF also
guides the budgeting structure, annual plans and budgets. In the
first phase implementing Demantra, the supply chain planning will
not be directly linked to the budgetting process to take place in
Hyperion (or similar).
351 Lot3-Demantra WP02 Please let us know if UNHCE gets any
Forecast from outside entities like
Customers and Suppliers?
UNHCR receives demand planning from internal customers
(country operations) and captures production capacity and availble
stocks (external suppliers)
Page 71 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
352
353
354
355
356
357
352 Lot3-Demantra WP02 Please let us know what is your planning
horizon (how far in the future do you
look?)
One year in advance
353 Lot3-Demantra WP02 Please let us know do you have Configure
to Order (CTO) scenario?
No, UNHCR does not have any CTO.
354 Lot3-Demantra WP02 Please let us know which are the key
functional areas (ex: Production
Planning, Finance, Customer Service, etc)
that currently use the output of the
forecast/demand plan?
Inventory managmeent, Procurement and Country Operations are
using the output of the forecast/demand plan.
355 Lot3-Demantra WP02 Please let us know if we are using
constraint planning or unconstrained
planning? If constraints planning then
can you pls. share the different
constraints used by the current planning
application?
Constraints (limitations) could be related capacity of production,
capacity on flows (e.g. capacity and frequence of lines, closure due
to raining season and delays in customs formalities) and maximum
storage capacity in warehouses in the chain etc.
356 Lot3-Demantra WP02 What is that you want to forecast?
- Number of beneficiaries in each cach
camp or quantity at item x location
(camp?) x time bucket?
UNHCR would like to be able to forecast need for Core Relief Items,
based on number of beneficiaries and distribution key, other items
based on real detected/determined needs, OK
357 Lot3-Demantra WP02 What is the source data you want to be
considered for generating the forecast?
- Purchase Order history (If yes, purchase
order at what level of item x location)?
- Material Stock Request (MSR) history
(This is supported through standard
integration between demantra and
PeopleSoft)?
- Actual consumption at the camps?
- Actual material received at camps?
All mentioned. As per shared documentation, only a feasibility
studie to determine that the modules are capable of handling the
UNHCR required functionality has been undertaken. No formal fit-
gap session undertaken.
Page 72 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
358
359
360
361
362
363
364
365
366
358 Lot3-Demantra WP02 We understand that planning horizon is
current year + next year. What is the
minimum time bucket required for
forecasting / supply planning. Is it
weekly, monthly ?
The different iterations of the planning will have different time
horizons, the anticipation is that the plan with have monthly
buckets as the lowest level.
359 Lot3-Demantra WP02 What is the location level at which you
want to generate, view and measure
forecast? Is it at camp level or country
level or any other location level?
UNCHR wants to generate, view and measure forecast at camp
(local locations), country, stockpile and warehouse level.
360 Lot3-Demantra WP02 What is the approximate number of
users expected to use demantra?
See also: 360 369
370 389
Supply would expect in the range of 150 users.
361 Lot3-Demantra WP02 Do you expect any third part (example:
NGOs) to view demantra data or input
any type of data?
No, only UNHCR.
362 Lot3-Demantra WP02 Do you have a requirement to handle
multiple currencies in demantra?
Yes.
363 Lot3-Demantra WP02 What is the primary unit of
measurement?
Whatever is assigned to the given item in the PS item master.
364 Lot3-Demantra WP02 Do you have a requirement for unit
conversions?
No.
365 Lot3-Demantra WP02 What are the KPIs for demand planning? Currently, no KPIs are developed for demand planning apart from
timely submission of complete plans. Tbd as a part of the design
and implementation.
366 Lot3-Demantra WP02 Provide some simulation scenario
examples for demand planning.
The following elements to be considered in the demand planning:
no. of beneficiries, forecasted beneficiaries, the needs/
requirement of commodities, stocks, stocks in pipeline, stock
reserved as safety stocks, distribution plan, elements considered as
risk with time zone, sourcing options and capcity of each option
(availability and delivery lead time)
Page 73 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
367
368
369
370
371
372
373
374
367 Lot3-Demantra WP02 High Level Design: To what extent have
the High Level design for Demantra and
SNO applications been done? Have any
recommendations on Phasing, solution
approach been made?
No high level design, only a feasibility studie to determine that the
modules are capable of handling the UNHCR required functionality
has been undertaken.
368 Lot3-Demantra WP02 Has the solution design for Demantra &
SNO completed? If so, share please share
the design.
No solution design, only a feasibility studie to determine that the
modules are capable of handling the UNHCR required functionality
has been undertaken.
369 Lot3-Demantra WP04 Please let us know how many end users
will be accessing Demantra? Please
provide a approximate break-up by User
Group.(Ex. Demand Planner, Demand
Manager, Customer Planner etc).
See also: 360 369
370 389
Supply would expect in the range of 150 users. Break-up has not
been defined yet.
370 Lot3-Demantra WP04 Please let us know how many
geographies are in Scope; users from
which locations will access Demantra?
See also: 360 369
370 389
Global use, equal to current use of PS.
371 Lot3-Demantra WP05 Please let us know how is the interaction
between the users and the IT team taking
place right now, if there is a need for an
access/change in forecast?
Interaction is done through DESS Business Support Section. This
section validates the user requirements and create the change
request to IT team. Further tests are coordinated.
372 Lot3-Demantra WP06 Please let us know what is the time
bucket for the forecasting process (ex:
monthly, weekly, etc)?
The different iterations of the planning will have different time
horizons, the anticipation is that the plan with have monthly
buckets as the lowest level.
373 Lot3-Demantra WP06 Please let us know if you measure
forecast accuracy today? If yes what is
the accuracy level of your forecast
today?
We do not currently measure forecast accuracy. Would be a part of
the implementation.
374 Lot3-Demantra WP06 Please let us know what is your current
Product Structure?
Global use, equal to current use of PS.
Page 74 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
375
376
377
378
379
380
381
382
375 Lot3-Demantra WP06 Please let us know what is your current
Location (Customer) Structure?
Global use, equal to current use of PS.
376 Lot3-Demantra WP06 Please let us know how often you want
the forecast to be published?
Minimum on Monthly basis
377 Lot3-Demantra WP06 Please let us know how are the New
Products introduced right now?
New items will be registered in the PS item master.
378 Lot3-Demantra WP06 Please let us know if you have different
forecasting cycles based on the life of the
product for example short life and long
life products?
No
379 Lot3-Demantra WP06 Please let us know if you generate
forecast by units, revenue or both?
Forecasts would be based on unit demand, potentially translated
to cash flow forecast based on determined lead time per item.
380 Lot3-Demantra WP06 Please let us know if you handle
seasonality, Trend etc today? Do you use
any Causal Factors?
Yes, UNHCR handles seasonality today, but the planning and
management is very basic.
381 Lot3-Demantra WP06 Please let us know at what level do you
review the forecast? List a few key things
which you do today to generate or
manipulate the forecast number?
UNHCR reviews the submission of the country operation plan
twice in one year. at the beginning of the planning cycle followed
by another review at the end of the planning year. at this stage
UNHCR is using excel to come up with different analysis (Charts).
However, during the implementaion year further review will be
carried out on quartely/monthly basis to review the progress of the
implementation.
382 Lot3-Demantra WP06 Please let us know what is the period for
which you maintain the back-dated
forecast? i.e. for how many weeks do you
maintain the previous weeks forecast?
UNHCR is not using previous periods demand to adjust future
period demand in the same plan. UNHCR would like to keep
historic plans to be able to compare.
Page 75 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
383
384
385
386
387
388
389
390
391
383 Lot3-Demantra WP06 Please let us know if any kind of forecast
override happens? If so at which level?
Whether it is at item/org level or at a
higher level.
At item level.
See also answer to question: 382.
384 Lot3-Demantra WP06 Please let us know how often is the S&OP
(Sales and Operation Planning) meeting
occurs?
Quarterly reviews, but no formal S&OP as in the commercial
business.
385 Lot3-Demantra WP06 Please let us know how is the final Plan
getting approved? Is this through the
tool and fed back to the other systems?
The plan will be approved in the tool, on direct (integration) feed
back to other systems as PS Purchasing.
386 Lot3-Demantra WP06 Scope: Please provide us the scope in
terms of a) No of Products/SKUs,
Locations/DCs, Replenishment Centres
and b) no of planners/users
Potentially, the number of SKUs will be as per PS item master,
locations are equal to number of high level warehouse locations,
and expect number of users to be in the range of 150.
387 Lot3-Demantra WP06 Do we need to build integration from
Demantra (final consensus forecast) to
any other applications?
Supply: Most probably not, but to be determined at requirement
gathering stage.
388 Lot3-Demantra WP06 Integration between Demantra and SNO
would be standard (out-of-box) or any
would any custom integration be
required?
Standard integration expected.
389 Lot3-Demantra WP06 How many estimated users will be
handling Demantra/SNO?
See also: 360 369
370 389
UNHCR (Supply) would expect in the range of 150 users.
390 Lot3-Demantra WP07 Please let us know what level of
forecasting information is required from
Demantra to the source system for
inventory replenishment/Detailed
planning (outbound)?
UNHCR will most probably not require outbound integration from
Demantra.
391 Lot3-Demantra WP07 Please let us know what level of
forecasting information is required from
Demantra to Hyperion?
At the current stage no integration from Demantra to Hyperion is
planned.
Page 76 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
392
393
394
395
392 Lot3-Demantra WP07 Please let us know if Demantra will get all
the necessary information to generate
the forecast from People soft or any
other third party systems involved
(inbound)?
Demantra (central planning user) will generate global/regional
forecast based on local plans entered in country operations.
Certain data import from PS foreseen, detailed developed process
and design to determine.
393 Lot3-Demantra WP08 How many test cycles are in scope for
Demantra/SNO implementation?
System integrator should propose according to best practices.
394 Lot3-Demantra WP10 Demantra Managed Support:
a. Demantra plan processing/interfaces
would be run only once a month. Do you
need support only for that specific
week/period?
b. If yes, would you need 8*5 coverage
during that week or 24*7 as you cannot
proceed with further activities till these
activities are completed ?
c. Does the managed support include
execution of all the Demantra/SNO
activities during the monthly cycle OR is
support required for issues faced during
the monthly cycle?
d. Post go-live, creation of any new
worksheets/series/integration is part of
the managed support scope. Please
confirm
For questions a, b, c, bidder is expected to propose their approach.
For question d, UNHCR expects the delivery of work packages.
395 Lot3-Demantra Please explain what is the current
planning tool that is used at UNHCR
Currently Excel sheet is used for planning.
Page 77 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
396
397
398
396 Lot3-Demantra We understand that Demantra can only
facilitate demand forecasting and SOP.
Planning cannot be done with Demantra
and SNO.
Since the RFP does not indicate a proper
planning tool, please comment if the
vendor is expected to propose an
optimum tool
Vendor is not expected to propose optimum tool. Demantra and
SNO are expected to facilitate planning.
397 Lot3-Demantra Please explain, what is the UNHCR
Results Based Management framework
RBM is UNHCR's management strategy which includes managing
the resources of the organization along a Results Framework (RF).
It guides the assessment, planning, allocation of resources,
implementation and reporting. The RF also guides the budgeting
structure, annual plans and budgets. In the first phase
implementing Demantra, the supply chain planning will not be
directly linked to the budgetting process to take place in Hyperion
(or similar).
398 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
it is mentioned that "Reduce manual
inputs to the planning process through
one consolidated database".
Demand can be changed but not supply.
Planning recommendations can be
brought in Demantra but supplies cannot
be overridden. Actual changes have to be
done in Source. All forecast streams have
to be changed in demantra. Supply
simulations can be done. But actual
changes need to be done in Source
n/a. Not a question.
Page 78 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
399
400
401
399 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
it is mentioned that "Manage, analyze
and compare country-/region-/season-
specific risk scenarios to support
procurement and inventory decisions."
Please provide examples about such
scenarios.
UNHCR plans to 'include' use of additional contingency plans
(during the standard planning cycle +) for countries where an
emergency is possible, and use the supply requirements from
selected contingency plan(s) to simulate the impact on current
flows and stock, to validate if changes to infrastucture and sourcing
plan(s) has to be made. Demantra will not be used as a 'operational
planning' tool as suggested in the question.
400 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
it is mentioned that "Introduce scenario
and simulation planning: improve agility
and reaction time to planned and
unplanned events"
We understand that this is more of a
Rapid Planning functionality. This is not
supported in Demantra. Please kindly
comment.
UNHCR plans to 'include' use of additional contingency plans
(during the standard planning cycle +) for countries where an
emergency is possible, and use the supply requirements from
selected contingency plan(s) to simulate the impact on current
flows and stock, to validate if changes to infrastucture and sourcing
plan(s) has to be made. Demantra will not be used as a 'operational
planning' tool as suggested in the question.
401 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
"Strengthen the bottom-up approach
through the planning cycle" is
mentioned.
Please elaborate what is meant by a
Bottom up approach
The central planning and forecasting will be based on country
developed plans and contingency plans.
Page 79 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
402
403
404
405
402 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
"Support a multiple reiterations
approach, allowing for increasing the
level of detail as information is known
and implementation gets closer." is
mentioned.
Please kindly provide more details about
this requirement.
At the first iteration of planning at the budget proposal stage
supply needs could be annual. At the next iteration during the
detailed budget validation, the requirement could be quarterly
supply forecast. And at the final iteration linked to detailed
operational planning the requirement could be monthly supply
forecast.
403 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
"Manage final automatic approval
process for the planning cycle, monitor
exceptions and adjustment." is
mentioned.
Please kindly describe the planning tool
that will be used.
The following elements to be considered in the demand planning:
no. of beneficiries, forecasted beneficiaries, the needs/
requirement of commodities, stocks, stocks in pipeline, stock
reserved as safety stocks, distribution plan, elements considered as
risk with time zone, sourcing options and capcity of each option
(availability and delivery lead time)
404 Lot3-Demantra Please explain what is the current
forecasting process
Currently forecasting is done in Excel. The following elements to be
considered in the demand planning: no. of beneficiries, forecasted
beneficiaries, the needs/ requirement of commodities, stocks,
stocks in pipeline, stock reserved as safety stocks, distribution plan,
elements considered as risk with time zone, sourcing options and
capcity of each option (availability and delivery lead time)
405 Lot3-Demantra Please explain what is the Frequency of
forecasting
We request operations to submit their forecast one year in
advance followed by another review of the same forecast in 8
month time. Later, the review will be on monthly/ quartely basis .
Page 80 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
406
407
408
409
410
411
412
406 Lot3-Demantra Please explain what is the Frequency of
Plan run
We request operations to submit their forecast one year in
advance followed by another review of the same forecast in 8
month time. Later, the review will be on monthly/ quartely basis .
407 Lot3-Demantra Under High level business requirements
in "Annex B - Appendix II - Application
Overview - Lot3 - Demantra & SNO.pdf",
"Ability to analyze market trends for
certain core items (availability, price)" is
mentioned.
Please kindly provide more examples on
the requirement and about market
trends
E.g analyse seasonal price fluctuations, quantity shortages, the root
cause of such fluctuations, capacity of suppliers.
408 Lot3-SNO WP02 Request you to please list out the
different constraints involved (ex: Supply
constraints, Mfg constraints, etc.)?
Mainly the warehouse network (locations), number of available
routings in the network, seasonal contraints per routing (e.g.
closed due to rainy season), dynamic constraints (security situation
blocking use of corridor).
409 Lot3-SNO WP02 Request you to please list out what are
the different costs involved (ex: Fixed
cost, Transportation, etc.)?
Item Price, Transportation costs, Inspection costs, Customs costs,
installation costs (for ceratin items), are the most typical costs.
410 Lot3-SNO WP02 What is the number of camps and
warehouses considered for planning?
UNCHR has approximately 200 warehouses.
411 Lot3-SNO WP02 What are the KPIs for supply planning? No KPIs are developed for demand planning apart from timely
submission of complete plans. Tbd as a part of the design and
implementation.
412 Lot3-SNO WP02 Provide some simulation scenario
examples for supply planning.
Analyse cost vs. on time-delivery to delvier the items to different
warehouses from different suppliers (via different transportation
routes, hubs). By inclussion of contingency (emergency) plans,
validate ability of the current structure and goods flow to manage
the additional demand.
Page 81 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
413
414
415
416
417
418
419
413 Lot3-SNO WP02 Do you have supply network and
geographical (latitude, longitude
position) location of camps in your
current system. This is required for
calculating distances in SNO.
We have, but currently not entered into PS per inventory location.
414 Lot3-SNO WP02 Do you have transportation cost and
capacity data available in your current
system?
For international procurements UNCHR has the transportation
cost. Capacity data is not available.
415 Lot3-SNO WP02 Do you have storage cost data available
in the current system?
No, UNCHR does not have storage cost data in the PS system.
416 Lot1 Planning What is the level of detail required for
the different areas of the process (e.g.
person level headcount planning,
product level planning, etc)
Ambiguous question. Budgeting (and related planning/forecasting)
is not done on PeopleSoft FSCM (Lot1).
417 Lot1 Planning How stable is your data model? (does the
information planned change every year?)
The data model, i.e. metadata dimensions, are stable. Frequent
changes happen during the year on the metadata itself (e.g.:
creation of a new Cost Center, a new PPG etc.)
418 Lot1 Planning What is the level of data security
requirements for the budgeting process,
especially for the position budgeting.
There is no data sensitivity per -se for the information managed
under Hyperion.
419 Lot1 Planning - ProcessHow is your current planning process
documented? Are objectives, scope,
expected accuracy, time horizon, extent
of scenario analysis, potential issues and
review procedures documented?
The internal procedures for Operations planning processes are well
documented.
Page 82 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
420
421
422
423
424
420 Lot1 Planning - ProcessWhat tools/techniques Are used for
budget preparation? Will the new tool be
used for driver based forecasting
calculation models (for detailed
budgeting) or just for data entry,
versioning, comparisons and workflow
purposes?
The budget is prepared and captured in "Focus", please see Annex
B - Appendix II - Application Overview - Lot2 - Hyperion - Detailed
Budgeting, "Budgeting systems" section.
421 Lot1 Planning - Processis a formal budget procedure and
detailed timetable issued that states all
tasks, roles and responsibilities across
the organisation to prepare all aspects of
the budget from beginning to publication
and reporting?
The internal procedures for Operations planning, internal and
external reporting processes are well documented.
422 Lot1 Planning - PeopleAre there dedicated resources and a
department responsible for performing
budgeting, planning and forecasting?
Have these people been trained on the
processes and the systems? Who else
understand the day to day activities?
Ambiguous question. Budgeting (and related planning/forecasting)
is not done on PeopleSoft FSCM (Lot1).
423 Lot1 Planning - PeopleHave dedicated staff and management
members been trained on How to
prepare and perform planning, budgeting
and forecasting using the automated
tools?
Ambiguous question. Budgeting (and related planning/forecasting)
is not done on PeopleSoft FSCM (Lot1).
424 Lot1 Planning - PeopleHow effective is the communication
across the business units during the
budget process? Do you know How other
departments use the output of your
plans?
Effective, yes.
Page 83 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
425
426
427
428
429
430
431
432
425 Lot1 Planning - PeopleWhat kind of skills Do you think your
team should develop in order to be more
effective in their current role for
budgeting process?
End user training is described in Workpackage 4 of the Terms of
Reference document.
See also attached document RFP QandA - Training
426 Lot1 Planning - TechnologyWhat is the level of automation in the
data integration and reporting processes
Average to low. It is expected that the manual processes currently
in place, in particular in the areas of analysis and reporting, will be
supported and automated to the extent possible.
427 Lot1 Planning - TechnologyHow many period of historical data will
be loaded and maintained in the
application
To be determined. For reference, oldest models are from 2006.
428 Lot1 Planning - TechnologyWhat will be number of users ? See response to question: 299
429 Lot1 Planning - TechnologyIs there any performance benchmark to
run business rules?
The bechmark should be defined and finalized as part of the
project
430 Lot1 Planning - TechnologyIs there need for what if scenario
analysis?
Possibility to offer What if analysis should be reviewed in light of
the business requirements analysis.
431 Lot1 Planning - TechnologyHow many reports need to be developed
in HFR / Smartview ? Can we assume
them to be the one in Annexure 2 of
Annex B
Currently there are 9 NVision reports for detailed budgeting in the
PeopleSoft EPM system. However, taking advantage of Hyperion
reporting capabilities, UNHCR expects to have more reports in
Hyperion. (See also Annex B - Appendix II - Application Overview -
Lot1 - Bolt-on - Partnership Management, "Challenges section").
432 Lot1 Planning - TechnologyIs there a possibility of dimenison
hierarchies being changed during the
budget cycle ? Like new Implementor
code being generated between V1 and
V2?
Yes, see also 417.
In addition and although fairly rare, movement of a dimension
member from on hierarchy branch to another could happen during
the year (e.g.: A specific Cost Center is moved from one Operation
to another)
Page 84 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
433
434
435
436
433 Lot1 Planning - TechnologyFor the purpose of Position Budgeting ,
can we assume a particular staff will be
tagged to a particular job code
throughout budget cycle?
Please note that for planning and budgeting, staff information is
less relevant than the position it is assigned to.
Each position has a cost which is used for planning and budgeting.
Due to operational needs, position's information, e.g.: grade or
title, may change in the course of the budget year.
Details will be discussed during the engagement.
434 Lot1 Planning - TechnologyIs there a need for allocating HQ costs? Ambiguous question.
If referring to actuals, yes. See application overview.
If referring to detailed budgeting, Focus is currently the source of
information.
If referring to the "allocation" functionality of Hyperion, it will be
used as appropriate.
435 Lot1 Planning - TechnologyCan we assume entity as lowest level of
data submission?
No, budget submitted and exported to FSCM have more detailed
information such as Account and Output codes. Please see Annex B
- Appendix II - Application Overview - Lot2 - Hyperion - Detailed
Budgeting, "Chartfields (dimensions)" section for more details.
436 Lot3-Demantra Is there historical data in a current
system or will this need to be developed
once Demantra has been implemented?
If it is in a current system integration will
need be to be considered however if
there is no historical data it will take time
to build up the relevant historical data to
draw upon.
If the historical data refers to previous purchasing, issues from
warehouse, etc, UNHCR has the data. Concerning planning
accuracy, no systemised historical data is available. OK
Page 85 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
437
438
439
437 Lot3-Demantra Demantra and Strategic Network
optimiser are both strategic planning
tools but there is a requirement of a
operational supply and demand tool.
what will be the Operational planning
tool as there is no mention of this?
Field will use output from the strategic planning tool to support
their planning, no operational tool planned.
438 Lot1-GRC What is your current staff level, do you
have developpers that you plan to
leverage?
No. For the implementation, the system integrator will provide the
development effort to put GRC into operation.
UNHCR will use internal resources to build knowledge and capacity
for post implementation; however, we anticipate that the Prime
Vendor will be involved in both train-the-trainer and transfer
knowledge to UNHCR.
439 Lot1-GRC It appears that that FIT gap has already
completed, so you have already reviewed
the new 9.2 functionality and
determined what they want to
implement ?
Refer to Annex B_TOR Work Package 2 - Business process analysis
and detailed design will be revalidated with System integrator
including detailed business requirements documents and revised
fit/gap and keep /drop analysis (see deliverable).
Page 86 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
440
441
442
443
444
440 Lot1-GRC Billing - What countries, lamguage and
currencies do you plan to invoice in ?
Countries: "Invoices" for may be sent to any country.
Languages: At least English, French and Spanish
Currency: Can be any
441 Lot1-GRC Billing - What taxes (Sales, VAT) will need
to be calculated on an invoice?
There is currently no requirement to calculate any Sales tax or VAT.
442 Lot1-GRC Project Costing: Project Security - Is it in
scope or out of Scope.
To be determined/elaborated. Detailed requirements gathering
and analysis is part of the engagement.
443 Lot1-GRC Billing: Whether invoices to be generated
for Field specific units or for a single unit
globally?
Requirements vary depending on the type of invoice. In general,
invoices for billing can be created in any of the Business Unit (that
represent mainly countries where UNHCR operates)
This will be determined as part of WP02.
444 Lot1-GRC Billing: What are the Tax Calculation
requirements on Customer invoices.
Currently, UNHCR does not have any Tax calculation requirement.
Page 87 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
445
446
447
448
449
450
451
452
453
445 Lot1-GRC Billing: What are the Revenue budgeting
requirement on customer invoices.
UNHCR does not use Revenue budgeting at the moment and no
plan to use it.
However, UNHCR would like to setup commitment control for
certain revenue to increase Spending Authority.
446 Lot1-GRC Expenses: Approval process requirement
for Cash Advances and Claim Settlements
- Is it in scope or out of Scope.
To be elaborated during engagement (requirement gathering
activity).
447 Lot1-GRC Expenses: Expense Receipt Verification
and audit requirements- Is it in scope or
out of Scope.
To be elaborated during engagement (requirement gathering
activity).
448 Lot1-GRC What PeopleSoft instance is the HRMS
system on?
Currently, 8.9, but upgrade to 9.2 is in progress.
449 Lot1-GRC On average, number of users utilizing the
system?
For best available information, see attached RFP 647 - QandA -
Users and Volume of Common Transactions.
450 Lot1-GRC Appears VAT is currently calculated and
stored outside of PeopleSoft, are there
any requirements / needs / desires to
calculate within any PeopleSoft modules
(e.g. Billing, Purchasing, Payables...)
AR is not applicable, and VATs on AP process may be subject to
payment but reimbursable from the tax authority.
451 Lot1-GRC Purchasing / eProcurment: Current
number of requesters and buyers? What
language are purchase orders created in?
See also: 52 104
137 158 242 488
507 5265 537 557
577
For best available information, see attached RFP 647 - QandA -
Users and Volume of Common Transactions.
452 Lot1-GRC Purchasing: Volume of requisitions and
purchase orders created on a monthly
basis?
For best available information, see attached RFP 647 - QandA -
Users and Volume of Common Transactions.
453 Lot1-GRC Payables: Volume of vouchers created on
a monthly basis?
For best available information, see attached RFP 647 - QandA -
Users and Volume of Common Transactions.
Page 88 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
454
455
456
457
458
459
460
461
454 Lot1-GRC Payables / Receivables: How many
different banks are currently utilized for
payments and deposits?
Field accounts approximately 350 bank accounts, 300 petty cash
accounts, 30 operational cash accounts.
HQ accounts approximately operational platform approx 20
accounts, FX and investment accounts approx 15.
455 Lot1-GRC Expenses: Volume of expense reports
created on a monthly basis?
n/a. Expenses is currently not in use.
456 Lot1-GRC Expenses: Are expenses payments
expected to be paid via PeopleSoft
Payroll or Payables?
To be elaborated during engagement (requirement gathering
activity).
457 Lot1-GRC Expenses: Are any corporate cards
utilized that will need to be feed into
PeopleSoft?
To be elaborated during engagement (requirement gathering
activity).
458 Lot1-GRC Expenses: Number of employees and
contractors projected to utilize the
Expense system?
UNHCR has 8000+ staff globally, most of whom are potential users
of the Expense system.
459 Lot1-GRC Billing: Will billing be centralized to a
team or rolled out to the field to enter
bills and generate invoices?
Billing will be rolled out to the field.
Voluntary contribution activities will be centralized but field will
generate the invoices for other types of billing activities (eg.
Guesthouse sales).
460 Lot1-GRC General Ledger: In what capacity is
PeopleSoft nVision utilized for reporting?
nVision is used for both statutory requirements (Trial Balance,
Balance Sheet, P&L) and also operational budget-expenditure
monitoring/control.
nVisions mainly based on GL, Budget ledger and KK tables.
461 Lot1-GRC General Ledger: Are nVision reports ran
online or only from the client nVision
instance?
Both
Page 89 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
462
463
464
465
466
467
468
462 Lot2-Hyperion General Hyperion Planning will be implemented
after Peoplesoft Upgrade is completed.
Please confirm if this understanding is
correct.
See also: 300 462
The same go-live date for PeopleSoft and Hyperion Planning
463 Lot2-Hyperion General Will Hyperion Plannning also be used for
Financial Planning to do financial
budgeting or it's limited to only
Manpower and position budgeting?
Scope of Hyperion Planning is described in Annex B - Appendix II -
Application Overview - Lot2 - Hyperion - Detailed Budgeting and
Annex B - Appendix II - Application Overview - Lot2 - Hyperion -
Position Budgeting.
464 Lot2-Hyperion General How many entities / branches are there? In 2014, UNHCR had 126 Operations.
465 Lot2-Hyperion General Is there any difference in the calculation
logics across entities based on country
specific legal elements to be considered
for paytoll cost, if yes, please elaborate.
To be detailed during the engagement.
466 Lot2-Hyperion General Do you have provisions of
monthly/quarterly forecasting or
budgeting process revisions? Or will
Hyperion Planning be used only for
Annual Budgeting purposes?
The annual budget cycle and revisions is described in Annex B -
Appendix II - Application Overview - Lot2 - Hyperion - Detailed
Budgeting, "Budgeting cycle" section
467 Lot2-Hyperion General What exact information makes a
position. Is it a combination of Salary
scale, grade and step?
Please see attached Annex B - Appendix II for overview. Detailed
requirements will be elaborated during the engagement.
468 Lot2-Hyperion General As mentioned survey salary is defined in
USD, so for every entity this gets
converted further using exchange rate. Is
this assumption correct?
No, position costs for planning and budgeting purposes are
handled in USD only.
Page 90 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
469
470
471
472
469 Lot2-Hyperion General How does the cost account breakdown
for position cost happpen - allocation /
simple calculation ?
This is the result of a calculation. For the purpose of estimation,
assume that the calculation is medium to high in complexity.
470 Lot2-Hyperion General All FDMEE interface will be developed
using flat file as extract from the source
system. Is this assumption correct?
The final solution needs to be determined on a case by case basis.
471 Lot2-Hyperion General We assume that UNCHR IT team will
provide the data extracts from FOCUS /
PeopleSoft as per the format provided by
Hyperion team during implementation. Is
this assumption correct?
In principle, the data extracts from FOCUS will not change. Any
data extract requirement must be discussed and agreed with the
UNHCR IT Team.
For PeopleSoft, ETL activities will need to be discussed between
System Integrator (SI) for Lot 1 and SI for Lot 2. FDQM/FDMEE is
expected to address most of the integration requirements.
472 Lot2-Hyperion General What is the frequency for the data loads? The details will be determined/elaborated during the engagement.
From Focus to Hyperion, one could expect 10 submissions per day,
noting that there are some periods where it can peak to >50 per
day.
From Hyperion to FSCM: This is a nightly automated process
described in Annex B - Appendix II - Application Overview - Lot2 -
Hyperion - Detailed Budgeting, "Target Validation in PeopleSoft
EPM" section.
Page 91 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
473
474
475
476
473 Lot2-Hyperion General What is the expected number of reports.
Please share break with split of
complexity by - simple/ medium/
complex
Generic definition of report
- Simple : Data retrieval in grid. No FR
calculations, no complex formating
- Medium : simple FR calculations,
custom headings
- Complex: Conditional fomratting,
complex formulaes, multiple grids
Financial reports to be developed in HFR, WebAnalysis and
SmartView shall be identified during the detailed analysis and
design phases of the project.
474 Lot2-Hyperion General Can you please elaborate the number of
users and security setup requirements?
Please refer to the attached QandA - Users and Volume of
Common Transactions
475 Lot1 - GRC Hardware Vendor (Sun, HP, Oracle etc) Currently, GRC is not installed in UNHCR. UNHCR has a hosting
service provider with whom the project should collaborate to
ensure proper hardware sizing and setup.
Please refer to Annex B - Appendix III on Technical Overview and
Work Packages.
Additional information to answer technical questions have also
been attached. See attached:
Technical - MSRP Systems at ICC
Technical - System Topology - AS IS
Technical - Current MSRP Versions
Technical - Target Application Versions
476 Lot1 - GRC Operating System Version and Release
(32/64 bit)
See response to question: 475
Page 92 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
477 Lot1 - GRC Provide details of hardware clustering (if
any)
See response to question: 475
478 Lot1 - GRC Is there any virtual environment No.
Please also see response to question: 475
479 Lot1 - GRC Is Load-Balancer being used ? Please
confirm.
Yes.
Please also see response to question: 475
480 Lot1 - GRC Oracle DB Version to be installed See attached Target Application Versions
481 Lot1 - GRC Is Database clustered (RAC)? See response to question: 475
482 Lot1 - GRC Total Database Users Refer to attached document on Users and Volume of Common
Transaction.
483 Lot1 - GRC Avg and Max Concurrent Users of
Database #
Refer to attached document on Users and Volume of Common
Transaction.
484 Lot1 - GRC Number of DR sites One anticipated.
485 Lot1 - GRC If application layer to be in cluster
mention the environment details. (e.g)
UAT,PROD
Yes.
Please also see response to question: 475
486 Lot1 - GRC Total number of instance and names To be determined.
Also see response to question 475
487 Lot1 - GRC Data guard required ? If yes active/active
or active/passive?
To be determined.
Also see response to question 475
488 Lot1 - GRC Specify the list of languages used in the
current Application instance, other than
English (US)
See also: 52 104
137 158 242 488
507 5265 537 557
577
Currently, only English is anticipated.
489 Lot1 - GRC Specify the list of third party
applications? Please provide the
integration architecture diagram if
available.
Integration with PeopleSoft is the the key requirement, possibly
along with Hyperion, Demantra/SNO. Other 3rd party applications
to be determined during the engagement.
490 Lot1 - GRC Application version details See attached Target Application Versions
491 Lot1 - GRC Application is Clustered ? See response to question: 475
Page 93 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
492
493
494
495
496
497
498
499
500
492 Lot1 - GRC Customization details ? "Customization" in the context of GRC has to be determined.
GRC is new module. At this point in time, UNHCR has the output of
the scoping sessions conducted during the conceptual design
phase. Refer to Annex B - Appendix II - GRC.
493 Lot1 - GRC Integration details Main integration requirement is with PeopleSoft.
494 Lot2 - Hyperion Hardware Vendor (Sun, HP, Oracle etc) Currently, Hyperion is not installed in UNHCR. UNHCR has a hosting
service provider with whom the project should collaborate to
ensure proper hardware sizing and setup.
Please refer to Annex B - Appendix III on Technical Overview and
Work Packages.
Additional information to answer technical questions have also
been attached. See attached:
Technical - MSRP Systems at ICC
Technical - System Topology - AS IS
Technical - Current MSRP Versions
Technical - Target Application Versions
495 Lot2 - Hyperion Operating System Version and Release
(32/64 bit)
See response to question: 494
496 Lot2 - Hyperion Provide details of hardware clustering (if
any)
See response to question: 494
497 Lot2 - Hyperion Is there any virtual environment See response to question: 494
498 Lot2 - Hyperion Is Load-Balancer being used ? Please
confirm.
See response to question: 494
499 Lot2 - Hyperion Oracle DB Version to be installed See attached Target Application Versions
500 Lot2 - Hyperion Is Database clustered (RAC)? See response to question: 494
Page 94 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
501
502
503
504
505
506
507
508
509
510
511
512
501 Lot2 - Hyperion Total Database Users To be determined.
Refer to attached document on Users and Volume of Common
Transaction.
502 Lot2 - Hyperion Avg and Max Concurrent Users of
Database #
To be determined.
Refer to attached document on Users and Volume of Common
Transaction.
503 Lot2 - Hyperion Number of DR sites One anticipated.
504 Lot2 - Hyperion If application layer to be in cluster
mention the environment details. (e.g)
UAT,PROD
See response to question: 494
505 Lot2 - Hyperion Total number of instance and names See response to question: 494
506 Lot2 - Hyperion Data guard required ? If yes active/active
or active/passive?
See response to question: 494
507 Lot2 - Hyperion Specify the list of languages used in the
current Application instance, other than
English (US)
See also: 52 104
137 158 242 488
507 5265 537 557
577
English.
508 Lot2 - Hyperion Specify the list of third party
applications? Please provide the
integration architecture diagram if
available.
High level integration diagram is presented in Annex B - Appendix II
- Application Overview - Lot2 - Hyperion - Detailed Budgeting,
"Budgetting systems" section where essentially EPM will be
replaced by Hyperion.
509 Lot2 - Hyperion Application version details See attached Target Application Versions
510 Lot2 - Hyperion Application is Clustered ? See response to question: 494
511 Lot2 - Hyperion Customization details ? "Customization" in the context of Hyperion has to be determined.
Hyperion Planning is new to UNHCR. At this point in time, UNHCR
has outputs of the scoping sessions conducted during the
conceptual design phase.
Refer to Annex B - Appendix II.
512 Lot2 - Hyperion Integration details See response to question: 494 and 508
Page 95 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
513
514
515
516
517
518
519
520
521
522
513 Lot3 - Demantra Hardware Vendor (Sun, HP, Oracle etc) Currently, Demantra is not installed in UNHCR. UNHCR has a
hosting service provider with whom the project should collaborate
to ensure proper hardware sizing and setup.
Please refer to Annex B - Appendix III on Technical Overview and
the Work Packages.
Additional information to answer technical questions have also
been attached. See attached:
Technical - MSRP Systems at ICC
Technical - System Topology - AS IS
Technical - Current MSRP Versions
Technical - Target Application Versions
514 Lot3 - Demantra Operating System Version and Release
(32/64 bit)
See response to question: 513
515 Lot3 - Demantra Provide details of hardware clustering (if
any)
See response to question: 513
516 Lot3 - Demantra Is there any virtual environment See response to question: 513
517 Lot3 - Demantra Is Load-Balancer being used ? Please
confirm.
See response to question: 513
518 Lot3 - Demantra Oracle DB Version to be installed See attached Target Application Versions
519 Lot3 - Demantra Is Database clustered (RAC)? See response to question: 513
520 Lot3 - Demantra Total Database Users To be determined.
Refer to attached document on Users and Volume of Common
Transaction.
521 Lot3 - Demantra Avg and Max Concurrent Users of
Database #
To be determined.
Refer to attached document on Users and Volume of Common
Transaction.
522 Lot3 - Demantra Number of DR sites One anticipated.
Page 96 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
523 Lot3 - Demantra If application layer to be in cluster
mention the environment details. (e.g)
UAT,PROD
To be determined.
See response to question: 513
524 Lot3 - Demantra Total number of instance and names To be determined.
See response to question: 513
525 Lot3 - Demantra Data guard required ? If yes active/active
or active/passive?
To be determined.
See response to question: 513
526 Lot3 - Demantra Specify the list of languages used in the
current Application instance, other than
English (US)
See also: 52 104
137 158 242 488
507 5265 537 557
577
n/a.
See response to question: 513
527 Lot3 - Demantra Specify the list of third party
applications? Please provide the
integration architecture diagram if
available.
PeopleSoft and possibly Excel. No other 3rd party applications that
needs to relate to Demantra are deployed (only PS).
528 Lot3 - Demantra Application version details Refer to attached: RFP QandA - Target application versions.
529 Lot3 - Demantra Application is Clustered ? See response to question: 513
530 Lot3 - Demantra Customization details ? Preferably vanilla implementation.
531 Lot3 - Demantra Integration details To be determined during this engagement.
532 Financials /Management RDBMS release to be installed See response to question: 513
533 Financials /Management PSFT Tools Version to be installed Please see attached: RFP 647 - QandA - Target Application
Versions.docx
534 Financials /Management Application Server Version To be
Installed
Please see attached: RFP 647 - QandA - Target Application
Versions.docx
535 Financials /Management Applications Modules to be installed Please see attached: RFP 647 - QandA - Target Application
Versions.docx
536 Financials /Management Character Set to be installed Unicode
537 Financials /Management Languages to be installed See also: 52 104
137 158 242 488
507 5265 537 557
577
English
Page 97 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
538
539
540
541
542
543
544
545
546
547
548
549
538 Financials /Management Number of instances to be installed
including name of instances
See Annex B - Appendix III - 4: Technical Architecture and Annex B -
Appendix III - 5: Methodology and Options.
539 Financials /Management Mention the names of instances required
to be in RAC. (e.g UAT,PROD)
See response to question 42
540 Financials /Management Should the install has any custom
database configured, If yes, Please
provide all the details of the same
Question is not clear.
541 Financials /Management Number of users accessing each
Environment
For best available information, see attached RFP 647 - QandA -
Users and Volume of Common Transactions.
542 Financials /Management Total Project duration See also: 84, 542,
562, 582
See ToR, section 4, timeline and constraints.
Also see answer to question: 84
543 Financials /Management Support duration for SIT,UAT,PROD etc See also: 113, 543,
563, 583
3 months after go-live; 3 months to be used within one year for key
processing milestones.
See ToR, section 4, timeline and constraints.
544 Financials /Management FP or T&M? Fixed Price. See Technical Response and Financial Offer forms.
545 Financials /Management Do you need fallback to be
implemented? If Y, Does fallback have to
be Active-Active or Active-Passive
Yes. Active-active
546 Financials /Management datagaurd to be implemented ? See response to question 487
547 Financials /Management Number of DR sites Currently, UNHCR has 1 DR site for all applications.
548 Financials /Management If application layer to be in cluster
mention the environment details. (e.g)
UAT,PROD
See response to question 42
549 Financials /Management Implementation approach ? (Offshore or
Onsite or Offshore&Onsite)
See answer to question: 219
Page 98 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
550
551
552
553
554
555
556
557
558
559
560
561
550 Financials /Management Please mentione Intergration
requirement with other product
Examples include homegrown Fleetwave, EFT payfiles (banking),
PeopleSoft HR, Hyperion (future), Demantra/SNO (future)
For additional information, refer to Annex B - Appendix III
551 Financials /Management Is Load-Balancer being used ? Please
confirm.
Yes, load balancers are used in all the current production
environment.
552 EPM RDBMS release to be installed n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
553 EPM PSFT Tools Version to be installed n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
554 EPM Application Server Version To be
Installed
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
555 EPM Applications Modules to be installed n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
556 EPM Character Set to be installed n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
557 EPM Languages to be installed See also: 52 104
137 158 242 488
507 5265 537 557
577
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
558 EPM Number of instances to be installed
including name of instances
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
559 EPM Mention the names of instances required
to be in RAC. (e.g UAT,PROD)
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
560 EPM Should the install has any custom
database configured, If yes, Please
provide all the details of the same
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
561 EPM Number of users accessing each
Environment
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
Page 99 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
562
563
564
565
566
567
568
569
570
571
562 EPM Total Project duration See also: 84, 542,
562, 582
See ToR, section 4, timeline and constraints.
Also refer to QA: 84
563 EPM Support duration for SIT,UAT,PROD etc See also: 113, 543,
563, 583
3 months after go-live; 3 months to be used within one year for key
processing milestones.
See ToR, section 4, timeline and constraints.
564 EPM FP or T&M? n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
565 EPM Do you need fallback to be
implemented? If Y, Does fallback have to
be Active-Active or Active-Passive
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
566 EPM datagaurd to be implemented ? n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
567 EPM Number of DR sites n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
568 EPM If application layer to be in cluster
mention the environment details. (e.g)
UAT,PROD
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
569 EPM Implementation approach ? (Offshore or
Onsite or Offshore&Onsite)
Refer to 3.3 Statement of Work - Primary location of the Terms of
Reference
570 EPM Please mentione Intergration
requirement with other product
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
571 EPM Is Load-Balancer being used ? Please
confirm.
n/a. EPM to be replaced by Hyperion or bolt-on PeopleSoft
functionality.
Page 100 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
572
573
574
575
576
577
578
579
572 SCM Treasury RDBMS release to be installed Treasury will be consolidated into the FSCM Instance 9.2. See
response to similar questions for FSCM: 532 to 551.
UNHCR has a hosting service provider with whom the project
should collaborate to ensure proper hardware sizing and setup.
Please refer to Annex B - Appendix III on Technical Overview and
the Work Packages.
Additional information to answer technical questions have also
been attached. See attached:
Technical - MSRP Systems at ICC
Technical - System Topology - AS IS
Technical - Current MSRP Versions
Technical - Target Application Versions
573 SCM Treasury PSFT Tools Version to be installed See response to question 572.
574 SCM Treasury Application Server Version To be
Installed
See response to question 572.
575 SCM Treasury Applications Modules to be installed Please see attached: RFP 647 - QandA - Target Application
Versions.docx
576 SCM Treasury Character Set to be installed See response to question 572.
577 SCM Treasury Languages to be installed See also: 52 104
137 158 242 488
507 5265 537 557
577
English
578 SCM Treasury Number of instances to be installed
including name of instances
See response to question 572.
579 SCM Treasury Mention the names of instances required
to be in RAC. (e.g UAT,PROD)
See response to question 572.
Page 101 of 102
1
2
A B C D E F
RFP/2014/647 RFP/2014/647 MSRP Finance Upgrade
Question
Number
Lot - Section Work Pkg Question Related Questions Answer
580
581
582
583
584
585
586
587
588
589
590
591
580 SCM Treasury Should the install has any custom
database configured, If yes, Please
provide all the details of the same
See response to question 572.
581 SCM Treasury Number of users accessing each
Environment
See response to question 572.
582 SCM Treasury Total Project duration See also: 84, 542,
562, 582
See ToR, section 4, timeline and constraints.
Also refer to QA: 84
583 SCM Treasury Support duration for SIT,UAT,PROD etc See also: 113, 543,
563, 583
3 months after go-live; 3 months to be used within one year for key
processing milestones.
See ToR, section 4, timeline and constraints.
584 SCM Treasury FP or T&M? Fixed Price. See Technical Response and Financial Offer forms.
585 SCM Treasury Do you need fallback to be
implemented? If Y, Does fallback have to
be Active-Active or Active-Passive
See response to question 572.
586 SCM Treasury datagaurd to be implemented ? See response to question 572.
587 SCM Treasury Number of DR sites One anticipated.
588 SCM Treasury If application layer to be in cluster
mention the environment details. (e.g)
UAT,PROD
See response to question 572.
589 SCM Treasury Implementation approach ? (Offshore or
Onsite or Offshore&Onsite)
Refer to 3.3 Statement of Work - Primary location of the Terms of
Reference
590 SCM Treasury Please mentione Intergration
requirement with other product
See response to question 572.
591 SCM Treasury Is Load-Balancer being used ? Please
confirm.
See response to question 572.
Page 102 of 102
Build and Implementation phase of the MSRP Upgrade Project
1
RFP 647 - Question and Answer
Additional Information
Extract of Change Management Strategy
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
2
This is an extract of the overall change management strategy to support the upgrade project. The strategy must be reviewed, revalidated and revised during the build and implementation phase.
Organizational Change Management encompasses all activities aimed at helping it understand and
successfully adopt new technologies. A comprehensive and structured approach is critical to the
success of any program that will bring about significant change.
In the context of MSRP Upgrade project, Change Management is a systematic set of proactive steps
To ensure continued sponsorship and business engagement by the key stakeholders
For a smooth and controlled system transition with minimal disruption
To prepare UNHCR staff, at the HQ and field, for the new (updated) system
To ensure policies, procedures/guidelines and system instructions are aligned
To contribute in the management of e project risks and helping the business achieve its defined objectives for the project
People
Business Process Technology Objectives
& Guiding
Principles
UNHCR CHANGE MANAGEMENT
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
3
Change management activities go hand-in-hand with the upgrade project which UNHCR has divided into two main stages: 1, the conceptual design, completed, and; 2, the actual upgrade and implementation, this RFP
1.1 Change Assessment (Stage 1 – Conceptual Design)
During this stage the groundwork for the MSRP Upgrade Change Management activities is done,
changes in MSRP system are assessed, organizational characteristics are reviewed, and impacts to
existing procedures and UNHCR staff functions are identified to the extent possible.
1.2 Change Assessment (Stage 2)
The assessment of changes continues into the actual upgrade phase of the project to determine and will cover these
two main activities.
Finalize Open Requirements with Business & Vendor
During conceptual upgrade stage, some of the requirements are listed in Fit Gap for which decisions were yet to be taken by business. Taking a Go - No Go decision would help in preparing for subsequent steps in Change Management and would give a realistic view of quantum of change in system & business process and its impact on UNHCR staff.
Revisit Policy & Business Process Change
Based on finalized requirements and decisions, on which of the new modules would be part of the upgraded MSRP, assessment needs to be done on the impacted changes in Policies, Procedures and System.
1.3 Change Planning & Execution
Up until this point, the Change Assessment which was defined as two stage activities, focused on laying the groundwork for change management activities and assess impact based on decision to be taken by business on the open requirements.
After assessment, the actual change management activities need to be planned and executed. This section lists the plan, its approach and implementation details
Prepare the Change Management Charter Form core change agent team Perform stakeholder (impacted parties) analysis Prepare the communication strategy Prepare training strategy Plan sponsor involvement
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
4
Assess people change and end-user impact Form readiness assessment group Prepare transition Plan Assess organizational readiness Revisit all inputs and dependencies of change management
Prepare MSRP Upgrade Change Management Charter
UNHCR would create a Change Management Charter to set the direction with following objectives
It would set the stage for successful implementation of the project.
Aligning with project objectives and guiding principles define critical success factors for CM efforts.
Put in words the sponsor’s vision of change by providing overview on project objectives, rationale and expected state in future.
Bring clarity on the roadmap to stakeholders and staff with Executive Direction and Commitment to support upgrade.
It also helps in cascading information faster and alignment of objectives and vision.
Reaffirmation/Formation of Core Change Management Team for MSRP Upgrade
UNHCR to create a Core Change Management Team for MSRP Upgrade that would be aligned to the
Signed and Approved Project Management Charter (Project Structure and Organization) whose
responsibility would involve:
Being key drivers of change.
Coordinate & manage overall change management activities.
Alleviate the concerns of UNHCR Stakeholders and End User groups to ensure that additional difficulties with perceptions about the project do not arise.
This group can facilitate a review of the impact that change may have on employee skills and assigned duties in order to develop a plan to address for workforce changes.
(Continue to) Perform Stakeholders Analysis
(Those affected by changes in business process and technology by MSRP Upgrade Project)
Direct
Senior Management
HQ Staff/Regional Office/Field Staff
External
Donors/Implementing Partners
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
5
Indirect
HR, GLC, Support, Project Management/Audit & External Bodies
Assess the key stakeholders and super users readiness by asking questions regarding the change, its impact etc.
Stakeholder assessment helps to determine the best feedback channels for each identified
stakeholder group. It is important to understand the major questions and concerns that these
groups may have, so that adequate attention can be paid to correcting misunderstandings, filling in
the gaps, undoing rumors, etc. If UNHCR understands, what the potential barriers to acceptance are,
it will be better prepared to take proactive action to eliminate them.
Determine the most effective way to reach the stakeholder groups (e.g., individual or group interviews, surveys, web site with user response capability, etc.).
Recognize serious concerns or misunderstandings and be prepared to respond to them promptly. Help concerned stakeholders to see why the project is in their best interest.
Be persistent and creative in approach to those influential individuals who demonstrate continued resistance. Make every effort to make them aware of how the project works in their favor. Turn them into allies.
Plan to make management commitment to the project visible throughout the organization.
Prepare/Revise the Communication Strategy
As part of Change Management, the communication strategy and plan need to be aligned. Existing plan needs to be revalidated with respect to the results of change management assessments and the most suitable option s need to be taken forward.
Prepare/Update Training Strategy
Current training plan/strategy has served as a guide for the training needs of project team and Subject Matter Experts for engagement in upgrade project related activities.
This plan needs to be updated to include training plan for the implementation, as per the outcomes of change management assessments and planning and the most suitable options need to be taken forward.
Plan Continued Sponsor Involvement
As sponsors are actively involved in the upgrade project, this is a reassessment of providing visibility to
end users and staff distributed globally, on how sponsors are actively involved and it leads to faster Buy
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
6
in. It could lead to updated plan for different modes of actively involving sponsors in driving the message
and communicating with end users across organization.
Assess/Re-Assess People Change and End User Impact
Awareness Level on Upgrade
Identify lack of information & resistance
Guard against complacency
Identify key sponsors from UNHCR who act as positive influence driving this change.
Form Readiness Assessment Group
Drill further to form this group which would be an extended arm of Core Change management team that
would lead in implementation and spread message across staff. This could align with the ‘Field
Reference Group’ which is planned by UNHCR. Specific focus to impacted UNHCR regional & field office
staff and communicate to encourage ownership and nurture acceptance of the new business processes
and system. Have different forums in which the user community can interact with change agents,
readiness assessment groups and sponsors to discuss project issues and potential user impacts. These
meetings can be:
Customized for Specific User Groups.
Specific plans for business process/workflows identified for improvement.
Focus group for IPSAS and compliance adherence changes.
Identify training needs Change in Roles and Responsibilities, job profile.
Interaction workshops.
Address particular concerns the users may have.
Provide timely and accurate information about upcoming events.
Ensure the consistency of information passed onto the user community.
Ensure project buy-in by the users.
Follow up
Provide potential users with a way to provide feedback, ask questions, etc.
Recommendation is through the intranet portal as it would provide real time visibility to common issues and solutions
Prepare Transition Plan
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
7
Develop a transition plan for people who are part of updated business process which needs change in roles and responsibilities as well as still set of impacted staff
Assess Organizational Readiness
Risk parameters assessment
Functional Impact & Business Process Change Listing
Sponsor Buy In & Involvement Plan
Policy & Procedure Update plan
Revisit all inputs and dependencies of Change Management
Use learnings from similar past project in UNHCR
Form Change group
Address Staff and UNHCR organization issues specific to upgrade
Finalize open requirements to be implemented along with business
Propose updated organization structure based on Roles and Responsibilities, Job description
Update Policy and Procedures
Implement Communication Mechanism & Plan
Prepare training content
At the end of Planning & Execution Stage, the key expectations are:
Visibility of all changes which are going to take place in the system
Identification of stakeholders and audience
Impact on Policy, Procedure, Technology & People
Formation of Core Change Agent Group
Skill Gap Analysis and Transition requirements
Organizational Readiness Assessment
Communication Plan aligned with its strategy
Focused training plan as per training strategy
Master tracker sheet aligned with upgrade lifecycle and milestones
Based on the functional and business impact plan for:
Regular Communication - Aligned with Communication Strategy
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
8
Focused Trainings – Aligned with Training Strategy
Prepare Roles & Responsibilities Matrix
Preparing roles and responsibilities of all involved users would give ownership clarity and identify gaps if any for
Sponsor/Stakeholder
Change Agent Team
Project Management Office
Business Users
GLC
Vendor
Support teams
1.4 Change Monitoring & Verification
For all the planned activities under Change management and its Execution, it is important to monitor
and assess if the project is on track to meet the desired objectives set out with respect to change
management.
A master tracking sheet would be an overall plan on a single page which would give an overview of group of change management activities. It would help tracking the progress in a single page or a sheet and dependencies if any to be shared with sponsors and help in monitoring the progress with respect to planned milestones.
Activities include but are not limited to:
Forming the Change Control Board
Publishing results of planned measurement
Evaluation and tracking of regulatory compliance requirements
Planning for testing groups and covering
Review of transition plans
Assessment of readiness for change
Analysis of support logs and system behavior
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy
9
Monitoring & Verification stage expectations are
Regular communication, tracking & review
Training outcome and feedback assessment
Skill Set Transition
Align with other related strategies for collaboration (User Acceptance testing)
Evaluate system performance and user tickets from support team
Lessons learned
Closure and Archival
Review, identify and address weakness in the processes
Review, identify and address gaps in the training material or skill enhancement needs of the users
Build and Implementation phase of the MSRP Upgrade Project
1
RFP 647 - Question and Answer
Additional Information
Extract of Change Management Strategy
on Communication
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy on Communication
2
This is an extract of the change management strategy to support the upgrade project.
The communication strategy is developed to ensure sharing timely information about the project to all
stakeholders and to receive quality feedback from them, which is equally important. This would be
aligned with project communication plan.
Different Modes/Medium
Location Based Meetings – All Staff
Newsletters, Targeted Emails and Broadcasts
Intranet, Online tutorials, Content & Repository, and other web-based webcasts, videos, self-running demons
Survey
Online Training
User Groups
Workshops, Certifications
A communication plan must be developed and/or revised to identify various audiences within this
project and specify who will get what information at what time, in what format and through what
means of delivery. In addition, the project team will track and record lessons learned throughout this
project, so that the experience gained can be leveraged in the future.
In general, the approach would include:
The use brochures, fliers, white papers or other means of communication to inform those who will be affected of the benefits of the new system. Specifically, fliers can provide all end-users the opportunity to understand the new system and become aware of the benefits it provides.
Creation intranet web site for upgrade project and ensure that all relevant parties are aware of :
Project Status, Progress and Performance
Interactive Question and Answer Communication
Frequently Asked Questions (FAQ)
Relevant Project Documents
Glossary of Terms (for each key Module)
Newsletter
Tutorials
Training Schedule
Emails and newsletters as way of communication
Build the effective communication channel after go live
Use other media (see list above of different communication modes/medium) to transmit relevant information to reach the target audience
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy on Communication
3
Based on the group of stakeholders/staff categorized as per location (HQ, Region & Field) and functional roles or departments the communication would be different. It is recommended that a dedicated landing page in intranet portal be the primary source of communication in UNHCR. This would help in transmitting consistent messages for all staff and different sections and FAQs could help clarify doubts and provide updates in consistent manner. Any good communication plan would need a proper tracker to monitor the progress as well as effectiveness of communication done. Based on feedback and inputs received, further follow up actions needed could be tracked to closure.
Operating
System
Linux -5
Oracle
Corp
Linux -5
Oracle
Corp
Linux -5
Oracle
Corp
Linux -5
Oracle
Corp
Linux -5
Oracle
Corp
2008 SP1 2003
11gR1 (10.3.1) 2008 SP1 2003
EPM 8.9 8.50.09 11.2.0.3 MP4 10gR3 11gR1 (10.3.1)
HRMS
(HR/Payroll)8.9 8.50.09 11.2.0.3 MP3 10gR3
2003
FSCM (TMS) 9 8.50.09 11.2.0.3 10gR3 11gR1 (10.3.1) 2008 SP1 2003
2008 SP1 2003
FSCM
(Fin/SCM)8.4 8.50.09 11.2.0.3 10gR3 11gR1 (10.3.1) 2008 SP1
WebserverCrystal
ReportsMS Office
Portal 8.9 8.50.09 11.2.0.3 10gR3 11gR1 (10.3.1)
Application App Version PT VersionOracle
VersionMP Tuxedo Cobol
Server Express 5.0
wp4
Server Express 5.0
wp4
Server Express 5.0
wp4
Server Express 5.0
wp4
Server Express 5.0
wp4
The International Computing Centre (ICC) provides a managed hosting service for UNHCR’s MSRP systems which are based on PeopleSoft applications. A managed hosting service includes the following principal activities: • Hosting the hardware on which the applications reside, including networking • Managing the application environment
MSRP
RAFS
(Fin/SCM)
UNHCR Web site
(Internet)UNHCR-Net
(Intranet)
RATM
(Treasury)
RAPA
(Portal)
RAEP
(Budget/
Income)
RAHR
(HRMS/GP)
Database
Link/
Integration
Broker
RAFC
(Focus)
SMS Reporting (Cognos)
GF-I/GF-X (SharePoint)
Database Link
Database Link
Medgate
GroupWise
User List
(CSV File)
Data File
(CSV)
Data File
(CSV)
Data Export
(CSV File)
Various HR
Data
(CSV File)
Office Wings
EFT Files
LMS
(Cornerstone)
L and C Data
(CSV)
Bank
Statement
(CSV File)
Exchange
Rates
(RTF)
File Export
Process
File Export
Process
File Import
Process
File Import
Process
File Import
Process
File Import
Process
Database Link
Database Link
UNJSPF
Database
Data File
(CSV)
MSRP Upgrade Project (SahFire) - Target Application Versions
Application App Version Comment
PeopleSoft FSCM
General Ledger Commitment Control Accounts Payable Accounts Receivable Purchasing Asset Management Inventory Banking Cash/Deal/Risk Management Billing Expenses SRM (eSupplier, eProcurement,
Strategic Sourcing) Real-Estate Management Project Costing
9.2 Latest available image as at last upgrade pass
Governance, Risk and Compliance
Access Controls Governor Transaction Controls Governor
Including: Transaction Controls Governor
Connector to PeopleSoft Enterprise for TCG
To be determined. In principle, most recent supported version available that is compatible with the target PeopleSoft FSCM version/image.
Hyperion Hyperion Planning Plus
Including: FDMEE FDMEE Adapter Suite
To be determined. In principle, most recent supported version available that is compatible with the target PeopleSoft FSCM version/image.
Demantra
Demand Management
To be determined. In principle, most recent supported version available.
SNO Strategic Network Optimization
To be determined. In principle, most recent supported version available.
PeopleSoft HRMS 9.2 Upgrade project in progress.
PTools 8.54 (to be confirmed)
In principle, most recent supported version available
that is compatible with the target PeopleSoft FSCM version/image. Please note that the final PeopleTools version is to be decided in coordination with the PeopleSoft HRMS upgrade project. The PeopleTools version should be the same for all PeopleSoft environments in UNHCR.
Oracle Database 11g or higher Although not required, UNHCR prefer to have the database versions of all PeopleSoft applications to be the same. In making the final decision for the database version, the PeopleSoft HRMS upgrade project should be taken into consideration.
The above should respond to multiple technical questions on: PeopleSoft, GRC, Hyperion,
Demantra/SNO.
1Gb/s
10Gb/s
SAN
RPS
Firewall
Firewall
Production
RPS
DP03
HP DL380
8 cores 48Gb
FS
DP02
HP DL380
8 cores 48Gb
HR, T
M
DP01
HP DL380
8 cores 48Gb
PA, E
P
remo
HP DL370
8 cores 12Gb
12Tb
DR Network
UNHCR HQ
Internet
AP03
HP DL380
8 cores 96Gb
All a
pps
WP01
HP DL360
4 cores 16Gb
All a
pps
AP02
HP DL380
8 cores 96Gb
All a
pps
AP01
HP DL380
8 cores 96Gb
All a
pps
WP02
HP DL360
4 cores 16Gb
All a
pps
1Gb/s
10Gb/s
Non-Production
WN01
HP DL360
4 cores 16Gb
PA, F
S
DN02
HP DL380
8 cores 48Gb
HR, T
M, E
P
AN02
HP DL380
8 cores 96Gb
HR, T
M, E
P
AN01
HP DL380
8 cores 96Gb
PA, F
S
WN02
HP DL360
4 cores 16Gb
HR, T
M, E
P
DN01
HP DL380
8 cores 48Gb
PA, F
S
remo
HP DL370
8 cores 12Gb
12Tb
SAN
UNHCR HQ
Firewall
1Gb/s
Training / D
R
10Gb/s
WT01
HP DL360
4 cores 16Gb
All a
pps
DT02
HP DL380
8 cores 64Gb
HR, T
M, E
P
AT02
HP DL380
8 cores 96Gb
All a
pps
AT01
HP DL380
8 cores 96Gb
All a
pps
WT02
HP DL360
4 cores 16Gb
All a
pps
DT01
HP DL380
8 cores 64Gb
PA, F
S
SAN
RPS
Internet
UNHCR HQ
Production
Network
Fire
wall
Fire
wall
vire
n
HP DL370
8 cores 12Gb
12Tb
Training / D
RNon-Production
Production
Servers
Database
Application / W
eb
Windows
Key:
NFS / B
ackup
DT02: p
icao
DT01: camu
DN02: p
au
DN01: patmore
DP03: satomi
DP01: sourwood
DP02: syrin
ga
AN01: abuta
AN02: avenca
AT02: w
hitespire
AT01: w
hiteash
AP03: amur
AP01: a
jos
AP02: a
cai
WT02: lo
mbardy
WT01: lo
dgepole
WN02: liv
eoak
WN01: le
yland
WP02: re
dmaple
WP01: ra
intre
e
viren
remo
Build and Implementation phase of the MSRP Upgrade Project
1
RFP 647 - Question and Answer
Additional Information
Extract of Change Management Strategy
on Training
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy on Training
2
This is an extract of the training strategy to support the actual upgrade project.
UNHCR has a Global Learning Center (GLC) with the goal of providing all staff who carry out UNHCR work with opportunities to learn new skills, acquire knowledge to improve their performance and better manage their individual career paths. GLC is responsible for coordinating internal learning activities agency-wide, ensuring that learning design, delivery, and evaluations have the highest substantive and methodological integrity, and that our learning activities closely reflect institutional priorities.
Global Learning Center (GLC) has a ‘Learn and Connect’ portal for UNHCR. The "Learn & Connect"
Learning Management System, with an ever-growing catalogue of courses, offers a selection of learning
opportunities – both online and in more traditional workshop formats.
GLC, the upgrade vendor, the project team and the business SME’s need to partner in developing appropriate training material catering to staff needs, as well as in delivering end-user and train-the-trainers courses .
Target Trainees
UNHCR has operations in 100+ countries with some 8,000+ staff . Of these, staff members in positions with administrative, financial, budgeting, donor relationship, managerial and supply management functions are impacted by the project and therefore form the cohort for trainings planned as part of its implementation. UNHCR resources will be impacted in different ways and therefore will need to be provided with a mix of training materials as appropriate. The assessment of training requirements will be continued during build and implementation phase.
Prepare Consolidated List of Trainings required
Inputs should be taken from
Skill Gap analysis & Training Needs Assessment
Business process changes or workflows
New modules
User Needs
Lessons learned
Organizational experience with different training methods and their effectiveness
Develop Curriculum and Content
Prepare focused training programs & tailored curriculum (topics covered, reference and other training
materials used) and content (specific information to be delivered) for each group. The training to be
provided in settings appropriate to the content and group responsibilities (e.g., Field Staff in Regional or
identified hubs; HQ & GSC Staff in a training rooms).
Build and Implementation phase of the MSRP Upgrade Project
Additional Information – Extract of Change Management Strategy on Training
3
PeopleSoft UPKs for targeted training
UPK (User Productivity Kit) is interactive learning environment that portrays a simulated PeopleSoft
environment. User learns by performing the task themselves and the UPK provides instructions as one
progresses.
It is similar to working on the real system with the added feature of being guided through the tasks with
the choice of being able to see the task being performed or performing the task as instructed. A table of
contents is used to display all the available training topics.
Other modes of training
Conference room pilot (CRP)/Live Training
People books
Oracle University
External Trainer (Upgrade vendor)
Serious attention to be paid to methods of delivery and as a result while most employees will receive
classroom presentations; certain groups will receive hands on training.
In addition, relevant CBTs, presentations will be made available on the project web site as a means of distributing key information about the project to all stakeholders. The following list could be used as a guide in development of this training program:
It is important to understand the training needs of each stakeholder group, develop targeted training
activities, and deliver content with the appropriate method. A good training plan will serve as an
effective road map for training activities.
Training is essential to the success of this project. Each stakeholder group in the project may have
unique training needs, this need to be captured for the groups relevant to MSRP upgrade project, their
specific training needs and information about the training materials and facilities that will be used. It
will form basis for the training plan.
GLC Portal could be used effectively for training content accessibility. One of the possibilities could be to
have a consolidated section for MSRP upgrade related training content which could be categorized
based on business groups, key modules or process flows.
RFP 647: Information on Users and Volume of Common Transactions
Questions to be answered:
Please indicate the daily volume of common transactions/day (Requisitions, POs, Vouchers, Journals,
etc). Also, please indicate the no. of users in the system.
Generally there are more transactions per day during the first quarter and last quarter of the
fiscal year. In a normal day the approximate average transactions per day are as follows:
Requisitions: 60 (maximum in one day is 1,075)
Purchase Orders : 75 (maximum in one day is 743)
Vouchers: 985 (maximum in one day is 6,472)
Journals: 350 (maximum in one day is 4,697)
The above figures include all transactions regardless of status (Open, Approved, Cancelled,
or Closed).
1) Following is the count of common transactions
a. Requisitions (by Year)
Year Number of transactions
2004 1,713
2005 3,432
2006 5,505
2007 14,940
2008 19,523
2009 20,895
2010 21,835
2011 23,703
2012 19,734
2013 22,890
2014 24,749
2015 1,061
b. Purchase Orders (by Year)
Year Number of transactions
2004 2,375
2005 4,261
2006 6,169
2007 14,650
2008 19,628
2009 21,963
2010 22,912
2011 25,639
2012 22,429
2013 25,674
2014 28,135
2015 732
c. Vouchers (by Year)
Year Number of transactions
2004 9,629
2005 40,600
2006 91,031
2007 204,795
2008 267,773
2009 282,706
2010 286,038
2011 301,986
2012 323,425
2013 344,405
2014 359,969
2015 7,581
d. Journals (by Ledger)
Ledger Count in Journals
BUDGET 35,839
CBL 865
COMMIT 165
COMMIT_DTL 162
DONOR_RPT 1,432
FOBS 18,728
HCR 1,720,952
OBL_PLAN 3,594
PREUNOG 2,524
2) Setup/Master data
a. Vendors: 144,335
b. Items: 7,152
c. Banks: 374
d. Bank Accounts: 981
What are the number of users per job role and how is their geographical spread?
The function is decentralized with the HQ having a monitoring and policing function.
Currently UNHCR has approximately 397 office locations spread across 253 countries and
250 warehouses. The system integrator is expected to carry out assessment activities that
will clearly identify roles and users in different locations based on the business
requirements.
How many number of users will be accessing the Planning and Budgeting system. If possible please
provide approximate spread by Geography
What is the expected number of users / concurrent Users for Hyperion Planning ?
Currently there are 2,012 users in EPM. The system integrator is expected to carry out
assessment activities that will clearly identify roles and users in different locations based on
the business requirements.
Number of Users: MSRP, GRC, Hyperion, Demantra/SNO
Note: GRC, Hyperion, Demantra/SNO is currently not implemented and therefore information
on the number of users for these applications is not available. As mentioned previously, the
system integrator is expected to carry out assessment activities that will facilitate sizing.
Current environment
MSRP Approximate number of users per environment:
DEV 20 users
TST 20 Users
UAT 60 Users
SUP 60 Users
PRD 4050 users
TRN 20 users + size of a training class
No. of concurrent users for the production environment:
In PIA:
FS/SCM: 1,429
TM: 110
EPM: 171
Concurrent named database users should not exceed 15.
Anticipated in the Upgraded Version
MSRP: Similar to the current environment (for applications already in use)
GRC: To be determined as GRC is currently not in use. However, the initial
implementation is anticipated to be "centralized".
Hyperion: To be determined as Hyperion is currently not in use. In principle, at least
one per field office/operation would require access, as well as at least one per HQ
division. Most or all of the budgeting section in HQ would need access.
Demantra/SNO: To be determined as neither Demantra nor SNO is currently in use.
*** FAKE DATA FOR THE PURPOSES OF ILLUSTRATION ***
OPS ABOD STAFF TOTAL
OP APPROVED 100,000,000 10,000,000 20,000,000 130,000,000
OPS ABOD STAFF TOTAL
OL APPROVED 50,000,000 5,000,000 10,000,000 65,000,000
UNEARMARKED 20,000,000
TOTAL UNEARMARKED 20,000,000
EARMARKED - DADAAB 10,000,000
EARMARKED - KAKUMA 5,000,000
EARMARKED - NAIROBI 5,000,000
TOTAL EARMARKED 20,000,000
TOTAL Contributions recorded 40,000,000 62%
OPS ABOD STAFF TOTAL
OP APPROVED 20,000,000 1,000,000 1,000,000 22,000,000
OPS ABOD STAFF TOTAL
OL APPROVED 10,000,000 500,000 500,000 11,000,000
TOTAL (with 7%) #REF! #REF!
TOTAL (excl. 7%) #REF! #REF!
OPS ABOD STAFF TOTAL
OP APPROVED 120,000,000 11,000,000 21,000,000 152,000,000
OPS ABOD STAFF TOTAL
OL APPROVED 60,000,000 5,500,000 10,500,000 76,000,000
TOTAL (excluding 7%) #REF! #REF!
2014 KENYA OPERATION
BUDGET - FUNDING - EXPENDITURES as of 30.06.14
(in USD)
FUNDING - CONTRIBUTIONS (recorded)
55,000,000
REGULAR EXCOM BUDGET (AB)
GRAND TOTAL BUDGET - AB + SB
65,500,000
FUNDING - CONTRIBUTIONS (recorded + firm projections) + carry-over
110,000,000
21,000,000
131,000,000
SB BUDGET - South Sudan Situation - (Kakuma)
10,500,000
FUNDING - CONTRIBUTIONS (recorded)
H:\RFP\RFP 647 Finance MSRP upgrade\Questions and Answers\Answers\RFP 647 - QandA\RFP 647 - QandA 303 - ExampleTrackingSpreadsheet
23/01/2015
*** FAKE DATA FOR THE PURPOSES OF ILLUSTRATION ***
Country/Donors CD Amount
EU 40037 100,000
JPN 40033 5,000,000
USA 40079 10,000,000
PSFR:
France 45022 50,000
Germany 45053 45,000
Australia 45055 40,000
TOTAL 15,235,000
Unearmarked contributions at the country level
*** FAKE DATA FOR THE PURPOSES OF ILLUSTRATION ***
BUDGET MSRP (03/04/14)
Objectives EPM CURRENT
BUDGET (OL)
CD 33005
(RPP2)
CD 33032
(IFS) CD 40004 TOTAL
Budgetary space
available (EPM
budget)
Expenditures as
of 01.04.14
(MSRP)
Impl.rateImpl.rate
vs income
1. Favourable Protection Environment 1,000,000
110 - International and regional instruments acceded to -
111 - Law and policy developed 25,000 25,000 0%
112 - Administrative institutions and practice developed or strengthened 500,000 - 500,000 #DIV/0!
113 - Access to legal assistance and legal remedies improved 500,000 - 500,000 0%
114 - Access to the territory improved - #DIV/0!
115 - Public attitude towards persons of concern improved 50,000 50,000 0%
2. Fair Protection Processes and Documentation 1,500,000
210 - Receptions conditions improved 50,000 - 50,000 0%
212 - Quality of registration and profiling improved or maintained 500,000 - 500,000 0% #DIV/0!
213 - Access to and quality of status determination procedures improved 250,000 - 250,000 0%
214 - Level of individual documentation increased 50,000 50,000 0%
215 - Civil registration and civil status documentation strengthened 5,000 - 5,000
3. Security from Violence and Exploitation 500,000
310 - Protection from Crime - 9,194 9,194 (9,194) -
312 - Risk of SGBV is reduced and quality of response improved 50,000 - 50,000 0%
313 - Risks related to detention reduced and freeedom of movement increased 50,000 - 50,000
314 - Protection of children 400,000 - 400,000 0% #DIV/0!
4. Basic Needs and essential services 1,500,000
410 - Health 1,000,000 700,000 700,000 300,000 0% 0%
411 - Population has optimal access to reproductive health and HIV services 50,000 - 50,000 0%
413 - Food Security -
415 - Population lives in satisfactory conditions of sanitations and hygiene - -
418 - Population has sufficient basic and domestic items -
419 - Services for persons with specific needs strengthened 150,000 - 150,000 0%
420 - Education 300,000 100,000 100,000 200,000 0% 0%
5. Community Empowerment and Self Reliance 400,000
510 - Community mobilization strengthened and expanded 50,000 - 50,000 0%
513 - Self reliance and livelihoods improved 350,000 - 350,000 0% #DIV/0!
6. Durable Solutions 150,000
611 - Potential for voluntary return realized - - #DIV/0!
612 - Reintegration -
614 - Potential for resettlement realized 100,000 - 100,000 0%
615 - Reduction of statelessness is achieved 50,000 50,000
7. Leadership, Coordination and Partnerships 30,000
710 - Coordination and partnerships strengthened 15,000 - 15,000 0%
711 - Camp management and coordination refined and improved -
713 - Donor relations and resource mobilization strengthened 15,000 - 15,000 0%
8. Logistics and Operations Support 600,000
810 - Logistics and supply chain 400,000 - 400,000 0%
811 - Operations Management 200,000 - 200,000 0%
TOTAL OPS 5,680,000 - - 100,000 9,194 700,000 - - - - 809,194 14% 4,275,806 - 0%
X.21
- 0%
ABOD 2,134,040 - 2,134,040
STAFF 9,377,506 188,760 188,760 9,188,746
GRAND TOTAL 17,191,546 - - 288,760 9,194 700,000 - - - - 997,954 6% 16,193,592
EARMARKED CONTRIBUTIONS
2014 NAIROBI PILLAR 1 BUDGET WITH EARMARKED CONTRIBUTIONS
in USD
H:\RFP\RFP 647 Finance MSRP upgrade\Questions and Answers\Answers\RFP 647 - QandA\RFP 647 - QandA 303 - ExampleTrackingSpreadsheet2
23/01/2015
BUDGET MSRP (03/04/14)
Objectives EPM CURRENT
BUDGET (OL)
CD 99005
(RPP2)
EC -
CD 11032
(IFS)
CD 33094 CD 88004 CD 22065 CD 77018 CD 99887 TOTAL
Budgetary space
available (EPM
budget)
Expenditures as of
01.04.14 (MSRP)
Impl.rate
vs. OL
Impl.rate vs
income
1. Favourable Protection Environment 500,000
112 - Administrative institutions and practice developed 250,000 250,000
113 - Access to legal assistance and legal remedies improved 200,000 100,000 100,000 100,000 0% 0%
114 - Access to the territory improved and risk of refoulement reduced 50,000 - 50,000 0%
2. Fair Protection Processes and Documentation 750,000
210 - Reception conditions improved - - #DIV/0!
212 - Quality of registration and profiling improved 400,000 - 400,000 0% #DIV/0!
213 - Access to and quality of status determination improved 300,000 - 300,000 0%
214 - Level of individual documentation increased 50,000 - 50,000 0%
215 - Civil registration and civil status documentation strengthened - - #DIV/0!
3. Security from Violence and Exploitation 2,500,000
310 - Protection from crime strengthened 1,500,000 100,000 100,000 1,400,000 0% 0%
312 - Risk of SGBV is reduced 500,000 - 500,000 0%
313 - Risks related to detention reduced & freedom of movement increased 100,000 - 100,000 0%
314 - Protection of children 400,000 20,000 20,000 380,000 0% 0%
4. Basic Needs and essential services 25,000,000
410 - Health 6,000,000 4,000,000 4,000,000 2,000,000 0% 0%
411 - Reproductive health and HIV services 1,000,000 - 1,000,000 0% #DIV/0!
412 - Nutrition 2,000,000 2,000,000 2,000,000 - 0% 0%
413 - Food Security 1,500 - 1,500 0%
414 - Water 2,000,000 - 2,000,000 0% #DIV/0!
415 - Population lives in satisfactory sanitary conditions 2,000,000 1,500,000 1,500,000 500,000 0% 0%
416 - Shelter and Infrastructure 1,500,000 1,500,000 1,500,000 - 0% 0%
417 - Population has sufficient access to energy 1,000,000 500,000 500,000 500,000 0% 0%
418 - Population has sufficient basic & domestic items 4,000,000 1,500,000 1,500,000 2,500,000 0% 0%
419 - Services for persons with specific needs strengthened 150,000 - 150,000 0% #DIV/0!
420 - Education 5,348,500 100,000 2,000,000 250,000 500,000 2,850,000 2,498,500 0% 0%
5. Community Empowerment and Self Reliance 2,500,000
510 - Community mobilizations strengthened and expanded 400,000 - 400,000 0% #DIV/0!
511 - Peaceful co-existence with local communities promoted 500,000 500,000 500,000 - 0% 0%
512 - Natural resources and environment better protected 200,000 - 200,000 0%
513 - Self-reliance and livelihoods improved 1,400,000 750,000 750,000 650,000 0% 0%
6. Durable Solutions 500,000
610 - Comprehensive Solutions strategy developed strengthened & updated - - -
611 - Potential for foluntary return realized 200,000 200,000 0%
614 - Potential for resettlement realized 300,000 - 300,000 0%
7. Leadership, Coordination and Partnerships 500,000
710 - Coordination and partnerships strengthened -
711 - Camp management and coordination refined and improved 500,000 - 500,000 0% #DIV/0!
712 - Emergency Management strengthened - #DIV/0!
713 - Donor relations and resource mobilizatio strengthened 40,000 40,000 (40,000) #DIV/0! 0%
8. Logistics and Operations Support 5,000,000
810 - Logistic and supply chain 2,000,000 - 2,000,000 0% #DIV/0!
811 - Operations management 3,000,000 - 3,000,000 0%
TOTAL OPS 37,250,000 - 1,010,000 100,000 7,500,000 1,000,000 5,000,000 - - 250,000 500,000 - - - 15,360,000 21,890,000 - 0%
(40,000) X.21
Unearmarked@Da
daab level5,000,000 5,000,000
7% 200,000 7,000 207,000
20,360,000 #DIV/0! - 0%
ABOD 4,718,590 2,357 2,357
STAFF 11,397,752 424,314 1,438,291 383,027 2,245,632
GRAND TOTAL 53,366,342 - 1,636,671 107,000 13,938,291 1,000,000 5,383,027 - - 250,000 500,000 - - - 22,814,990
EARMARKED CONTRIBUTIONS (RECORDED + FIRM PROJECTIONS)
2014 DADAAB/ALINJUGUR BUDGET WITH EARMARKED CONTRIBUTIONS
*** FAKE DATA FOR THE PURPOSES OF ILLUSTRATION ***
H:\RFP\RFP 647 Finance MSRP upgrade\Questions and Answers\Answers\RFP 647 - QandA\RFP 647 - QandA 303 - ExampleTrackingSpreadsheet2
23/01/2015
Software
Component Type Component Name Version Remarks
Database
Oracle Database 11gR2 11.2.0.3 UTF-8 Characterset
Browser
Firefox , Internet Explorer 24
Interet Explorer 9.x,8.x
Languages
Oracle Tier 1 Chinese (Simplified/Traditional), Japanese, French, German,
Korean, Portuguese (Brazilian), Spanish, Danish, Italian, Dutch
Application Server and Middleware for
GRC Core
Oracle WebLogic Server 12.1.2
Oracle Application Development
Runtime (ADR) 12.1.2
Oracle Repository Creation Utility 12.1.2
Application Server and Middleware for
GRC Intelligence (Embedded)
Oracle WebLogic Server 10.3.6 with Oracle JDK 1.7
Oracle Application Development
Runtime (ADR) 11.1.1.7
Oracle Repository Creation Utility 11.1.1.7
Additional Middleware (Standalone)
Oracle Business Intelligence 11.1.1.7
Standalone OBIEE Instance will be used for Customization and New Dashboard
and Reports development. Not required for Proof of Concept
Oracle WebLogic Server 10.3.6 with Oracle JDK 1.7
Oracle Application Development
Runtime (ADR) 11.1.1.7
Oracle Repository Creation Utility 11.1.1.7
Operating Systems
Windows Operating System Server 200x
Linux x86‐64(Preferred) Oracle Linux 6
Red Hat Enterprise Linux 6
Virtualization forApplication Server
Hardware Oracle VM Server 3.2.6
Oracle GRC 8.6.4 Certification Matrix
Architecture Server Tiers
Locate GRC application and database servers in same machine to
eliminate I/O (network) boundary constraints that can cause
performance issues
Network
When using AACG or TCG, locate GRC application and database
servers in same network segment as monitored business
application databases
Sizes
Bus and Infrastructure 64bit,Processor Speed 2.4Ghz+,
Application Server CPU 16 cores (GRC) + 16 Core for (GRCI) Production environment sizing
16 core for DB + 8 Cores for Apps Tier Non Production environment
Application Server Memory 64G (32+32) Production environment sizing
40G (24+16) Non Production environment
Application Server Storage 500G
Database Server SGA 15G (GRC + GRCI) Production environment sizing
10G (GRC + GRCI) Non Production environment sizing
Database Server Storage 1TB Use RAID 5 , No RAID 1+0 or 0+1 required
1TB Use RAID 5 , No RAID 1+0 or 0+1 required
AACG
Oracle PeopleSoft Enterprise FSCM
& HCM 9.2 (PT8.53),9.1 (PT8.53/50),9.0 (PT8.49/48),8.9 (PT8.49/48) AACG PEA: PSFT application server running in
Oracle Linux 4 or 5, Red Hat Enterprise Linux 4 or
5, or MS Windows Server 2003; and running on
x86 32‐bit.
Oracle PeopleSoft Enterprise HCM 9.2
PSFT application server running in WebLogic
10.x or 9.2. PSFT using Oracle database or MS
SQL Server 2008
TCG Oracle PeopleSoft Enterprise FSCM 9.2,9.1 PSFT running in Linux x86‐64. PSFT using Oracle
database 11gR1
Oracle Hyperion Planning Plus - Version 11.1.2.3
SoftwareComponent Type Component Name Version Remarks
Database
Oracle Database 11gR2 11.x
Browser Firefox , Internet Explorer
Internet Explorer 7.x
Internet Explorer 8.x
Internet Explorer 9.x
Firefox 17.x ESR
Windows Server 2008 with SP2+
Windows Server 2008 R2 (all SP levels included)
Windows Server 2003 with SP2/R2+, SP3+
Languages
English (US)
Application Server and Middleware
Oracle WebLogic Server
Oracle WebLogic Server 11gR1 (10.3.5 and 10.3.6)
(bundled with Hyperion Planning Plus)
Oracle Application Development 10.3.6 with Oracle JDK 1.7
Runtime (ADR)
Oracle Repository Creation Utility
Web Server Oracle Apache server Oracle Apache server(bundled with Hyperion Planning Plus)
Additional Middleware FD(Q)M 11.1.2.X
Operating Systems Windows Server 200X
Windows Server 2008 with SP2+ OR
Windows Server 2008 R2 (all SP levels included) OR
Windows Server 2003 with SP2/R2+, SP3+
Enterprise Linux
Solaris
HardwareArchitecture Server Tiers Production Environment(Only One) Hyperion Planning Plus Application with FDM (integrator)
Prod Instance - Install Oracle epm components by Tier (Web Tier in Server#1 Virtual OS (Distributed env))
Prod Instance - Install Oracle epm components by Tier (Service Tier in Server#2 Virtual OS (Distributed env))
Prod Instance - Install Oracle epm components by Tier (Apache Server in Server#3 Physical OS (Distributed env))
Prod Instance - Install Oracle epm components by Tier (Essbase component in Server#4 Physical OS (Distributed env))
Production Instance - ORACLE RDBMS - database in Server #3 (Distributed env)-Virtual OS
Non Production ( 3-4 environments)
Server Tiers Non-Prod Instance - Install Oracle epm components by Tier (Web Tier in Server#1 Virtual OS (Distributed env))
Non-Prod Instance - Install Oracle epm components by Tier (Service Tier in Server#2 Virtual OS (Distributed env))
Non-Prod Instance - Install Oracle epm components by Tier (Apache Server in Server#3 Physical OS (Distributed env))
Non-Prod Instance - Install Oracle epm components by Tier (Essbase component in Server#4 Physical OS (Distributed env))
Non-Production Instance - ORACLE RDBMS - database in Server #3 (Distributed env)-Virtual OS
Network
Sizes ProductionBus and Infrastructure NA
Application Server CPU 8 core Duo Production environment sizing only
Application Server Memory -RAM 24GB Virtual Memory Only
Web Server Memory (Apache)-RAM 16GB Physical Memory
Application Server Storage NA
Database Server SGA-RAM 32GB Virtual Memory Only
SAN Storage 800GB
Non-Production
Bus and Infrastructure NA
Application Server CPU 8 core Duo Non Production environment sizing only
Application Server Memory -RAM 32GB Virtual Memory Only
Web Server Memory (Apache)-RAM 16GB Physical Memory
Application Server Storage NA
Database Server SGA-RAM 32GB Virtual Memory Only
SAN Storage 2 TB
QandA 320: Please interpret with the attached document on UNHCR Target Versions.
PeopleSoft PeopleTools 8.53 with Oracle Database 10.2.0.5.0
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 10.2.0.5.0 64-bit Supported
IBM AIX on POWER Systems (64-bit) 6.1 10.2.0.5.0 64-bit Supported
IBM: Linux on System z Red Hat Enterprise 5 10.2.0.5.0 64-bit Supported
IBM: Linux on System z SLES 11 10.2.0.5.0 64-bit Supported
Linux x86-64 Oracle Linux 5 10.2.0.5.0 64-bit Supported
Linux x86-64 Red Hat Enterprise 5 10.2.0.5.0 64-bit Supported
Linux x86-64 SLES 11 10.2.0.5.0 64-bit Supported
Microsoft Windows x64 (64-bit) 2008 10.2.0.5.0 64-bit Supported
Oracle Solaris on SPARC (64-bit) 10 10.2.0.5.0 64-bit Supported
Oracle Solaris on x86-64 (64-bit) 10 10.2.0.5.0 64-bit Supported
PeopleSoft PeopleTools 8.53 with Oracle Database 11.1.0.7.0
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 11.1.0.7.0 64-bit Supported
IBM AIX on POWER Systems (64-bit) 6.1 11.1.0.7.0 64-bit Supported
Linux x86-64 Oracle Linux 5 11.1.0.7.0 64-bit Supported
Linux x86-64 Red Hat Enterprise Linux 5 11.1.0.7.0 64-bit Supported
Linux x86-64 SLES 11 11.1.0.7.0 64-bit Supported
Microsoft Windows x64 (64-bit) 2008 11.1.0.7.0 64-bit Supported
Oracle Solaris on SPARC (64-bit) 10 11.1.0.7.0 64-bit Supported
PeopleSoft PeopleTools 8.53 with Oracle Database 11.2.0.3.0
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 11.2.0.2.0 64-bit (min) Supported
IBM AIX on POWER Systems (64-bit) 6.1 11.2.0.2.0 64-bit (min) Supported
IBM AIX on POWER Systems (64-bit) 7.1 11.2.0.2.0 64-bit (min) Supported
IBM: Linux on System z Red Hat Enterprise Linux 5 11.2.0.2.0 64-bit (min) Supported
IBM: Linux on System z SLES 11 11.2.0.2.0 64-bit (min) Supported
Linux x86-64 Oracle Linux 5 11.2.0.2.0 64-bit (min) Supported
Linux x86-64 Oracle Linux 6 11.2.0.2.0 64-bit (min) Planned
Linux x86-64 Red Hat Enterprise Linux 5 11.2.0.2.0 64-bit (min) Supported
Linux x86-64 Red Hat Enterprise Linux 6
Linux x86-64 SLES 11 11.2.0.2.0 64-bit (min) Supported
Microsoft Windows x64 (64-bit) 2008 11.2.0.2.0 64-bit (min) Supported
Microsoft Windows x64 (64-bit) 2008 R2 11.2.0.2.0 64-bit (min) Supported
Oracle Solaris on SPARC (64-bit) 10 11.2.0.2.0 64-bit (min) Supported
Oracle Solaris on SPARC (64-bit) 11 11.2.0.3.0 64-bit (min) Planned
Oracle Solaris on x86-64 (64-bit) 10 11.2.0.2.0 64-bit (min) Supported
Oracle Solaris on x86-64 (64-bit) 11 11.2.0.3.0 64-bit (min) Planned
Compatibility with Tuxedo
PeopleSoft PeopleTools 8.53 with Oracle Tuxedo 11.1.1.30
Platform Version Supported Version Support Status
Linux x86-64 SLES 11 Tuxedo 11gR1 (11.1.1.30) Supported
Linux x86-64 Red Hat Enterprise 6 Tuxedo 11gR1 (11.1.1.30) Supported
Linux x86-64 Oracle Linux 6 Tuxedo 11gR1 (11.1.1.30) Supported
Linux x86-64 Oracle Linux 6 Tuxedo 11gR1 (11.1.1.30) Supported
PeopleSoft PeopleTools 8.53 with Oracle Tuxedo 11.1.1.20
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 Tuxedo 11gR1 (11.1.1.20) Supported
IBM AIX on POWER Systems (64-bit) 6.1 Tuxedo 11gR1 (11.1.1.20)
Supported
IBM AIX on POWER Systems (64-bit) 7.1 Tuxedo 11gR1 (11.1.1.20)
Supported
Oracle Solaris on SPARC (64-bit) 11 Tuxedo 11gR1 (11.1.1.20) Supported
Oracle Solaris on SPARC (64-bit) 10 Tuxedo 11gR1 (11.1.1.20) Supported
Linux x86-64 Red Hat Enterprise 6 Tuxedo 11gR1 (11.1.1.20) Supported
Linux x86-64 Red Hat Enterprise 5 Tuxedo 11gR1 (11.1.1.20) Supported
Microsoft Windows x64 (64-bit) 2008 Tuxedo 11gR1 (11.1.1.20) Supported
Microsoft Windows x64 (64-bit) 2008 R2 Tuxedo 11gR1 (11.1.1.20) Supported
Compatibility with IBM WebSphere
PeopleSoft PeopleTools 8.53 with IBM WebSphere Application Server 8.5
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 8.5.0.1 64Bit Supported
IBM AIX on POWER Systems(64-bit) 6.1 8.5.0.1 64Bit Supported
IBM AIX on POWER Systems(64-bit) 7.1 8.5.0.1 64Bit Supported
Linux x86-64 Oracle Linux 6 8.5.0.1 64Bit Supported
Linux x86-64 Oracle Linux 5 8.5.0.1 64Bit Supported
Linux x86-64 Red Hat Enterprise Linux 6 8.5.0.1 64Bit Supported
Linux x86-64 Red Hat Enterprise Linux 5 8.5.0.1 64Bit Supported
Linux x86-64 SLES-11 8.5.0.1 64Bit Supported
Microsoft Windows x64(64-bit)2008 8.5.0.1 64Bit Supported
Microsoft Windows x64(64-bit)2008 R2 8.5.0.1 64Bit Supported
Oracle Solaris on SPARC(64-bit) 10 8.5.0.1 64Bit Supported
Oracle Solaris on x86-64 (64-bit) 10 8.5.0.1 64Bit Supported
Compatibility with Weblogic Server
PeopleSoft PeopleTools 8.53 with Oracle WebLogic Server 10.3.6.0.0
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
IBM AIX on POWER Systems (64-bit) 6.1 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
IBM AIX on POWER Systems (64-bit) 7.1 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Linux x86-64 SLES 11 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Linux x86-64 Red Hat Enterprise 6 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Linux x86-64 Red Hat Enterprise 5 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Linux x86-64 Oracle Linux 6 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Linux x86-64 Oracle Linux 5 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Microsoft Windows x64 (64-bit) 2008 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Microsoft Windows x64 (64-bit) 2008 R2 Oracle Weblogic Server 10.3.6 64-bit 10.3.6(minimum) Supported
Oracle Solaris on SPARC (64-bit) 11 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Oracle Solaris on SPARC (64-bit) 10 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Oracle Solaris on x86-64 (64-bit) 11 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Oracle Solaris on x86-64 (64-bit) 10 Oracle Weblogic Server 10.3.6 64-bit 10.3.6 (minimum) Supported
Compatibility with Crystal Reports 2008
PeopleSoft PeopleTools 8.53 with Crystal Reports 2008
Platform Version Supported Version Support Status
Microsoft Windows (32-bit) 7 Crystal Reports 2008 SP3 Supported
Microsoft Windows x64 (64-bit) 2008 Crystal Reports 2008 SP3 Supported
Microsoft Windows x64 (64-bit) 2008 R2 Crystal Reports 2008 SP3 Supported
Microsoft Windows x64 (64-bit) 7 Crystal Reports 2008 SP3 Supported
PeopleSoft PeopleTools 8.53 with Crystal Reports 2011
Platform Version Supported Version Support Status
Microsoft Windows (32-bit) 7 Crystal Reports 2008 SP3 Supported
Microsoft Windows x64 (64-bit) 2008 Crystal Reports 2008 SP3 Supported
Microsoft Windows x64 (64-bit) 2008 R2 Crystal Reports 2008 SP3 Supported
Microsoft Windows x64 (64-bit) 7 Crystal Reports 2008 SP3 Supported
Compatibility with Verity 6.5.1
PeopleSoft PeopleTools 8.53 with Verity Development Kit 6.5.1
Platform Version Supported Version
Support Status Verity 6.5.1 support
Deployment options for 6.5.1
Search Server Supported
HP-UX Itanium 11.31 Verity 6.5.1 Supported 64-bit Type-1 & Type-3 Yes
IBM AIX on POWER Systems (64-bit) 6.1
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
IBM AIX on POWER Systems (64-bit) 7.1
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Linux x86-64 Oracle Enterprise Linux 5
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Linux x86-64 Red Hat Enterprise Linux 6
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Linux x86-64 Red Hat Enterprise Linux 5
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Linux x86-64 SLES-11
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Linux x86-64 Oracle Linux 6
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Linux x86-64 Oracle
Linux 5 Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Microsoft Windows x64 (64-bit) 2008
Verity 6.5.1 Supported 32-bit Type-1 & Type-3 Yes
Microsoft Windows x64 (64-bit) 2008 R2
Verity 6.5.1 Supported 32-bit Type-1 & Type-3 Yes
Oracle Solaris on SPARC (64-bit) 11
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Oracle Solaris on SPARC (64-bit) 10
Verity 6.5.1 Supported 32-bit Type-2 & Type-3 Yes
Oracle Solaris on x86-64 (64-bit) 11
Verity 6.5.1 Not Supported (Need to Setup
32-bit Type-3 No
Type-3 for the Search)
Oracle Solaris on x86-64 (64-bit) 10
Verity 6.5.1
Not Supported (Need to Setup Type-3 for the Search)
32-bit Type-3 No
Compatibility with Microfocus COBOL NetExpress 5.1
PeopleSoft PeopleTools 8.53 with Microfocus COBOL NetExpress 5.1
Platform Version Supported Version Support Status
Microsoft Windows x64 (64-bit) 2008 Micro Focus Net Express 5.1 32-bitWrap Pack 4 (minimum)
Supported
Microsoft Windows x64 (64-bit) 2008 R2
Micro Focus Net Express 5.1 32-bitWrap Pack 4 (minimum)
Supported
Compatibility with Microfocus COBOL Server Express 5.1
PeopleSoft PeopleTools 8.53 with Microfocus COBOL Server Express 5.1
Platform Version Supported Version Support Status
HP-UX Itanium 11.31 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
IBM AIX on POWER Systems (64-bit) 6.1 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
IBM AIX on POWER Systems (64-bit) 7.1 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
IBM: Linux on System z: Red Hat Enterprise Linux 5
Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
IBM: Linux on System z: SLES 11 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum) Supported
Linux x86-64 SLES 11 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
Linux x86-64 Red Hat Enterprise 6 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
Linux x86-64 Red Hat Enterprise 5 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
Linux x86-64 Oracle Enterprise Linux 6 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum) Supported
Linux x86-64 Oracle Enterprise Linux 5 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum) Supported
Linux x86-64 Oracle Enterprise Linux 5 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum) Supported
Oracle Solaris on SPARC (64-bit) 11 Micro Focus Server Express 5.1 64-bitWrap Pack 4 Supported
(minimum)
Oracle Solaris on x86-64 (64-bit) 11 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
Oracle Solaris on x86-64 (64-bit) 10 Micro Focus Server Express 5.1 64-bitWrap Pack 4 (minimum)
Supported
Compatibility with IBM COBOL for AIX 4.1
PeopleSoft PeopleTools 8.53 with IBM COBOL for AIX 4.1
Platform Version Supported Versions Support Status
IBM AIX on POWER Systems (64-bit) 6.1 IBM COBOL for AIX 4.1.1.1 Supported
IBM AIX on POWER Systems (64-bit) 7.1 IBM COBOL for AIX 4.1.1.1 Supported
Compatibility with IBM COBOL for Windows 7.6
PeopleSoft PeopleTools 8.53 with IBM COBOL for Windows 7.6
Platform Version Supported Version Support Status
Microsoft Windows x64 (64-bit) 2008 IBM COBOL for Windows 7.6 Supported
Microsoft Windows x64 (64-bit) 2008 R2 IBM COBOL for Windows 7.6 Supported
Compatibility with IBM COBOL for z/os
PeopleSoft PeopleTools 8.53 with IBM Enterprise COBOL for z/OS 4.2
Platform Version Supported Version Support Status
IBM z/OS on System z 1.13 IBM Enterprise COBOL for z/OS 4.2 Supported
IBM z/OS on System z 1.12 IBM Enterprise COBOL for z/OS 4.2 Supported
PeopleSoft PeopleTools 8.53 with IBM Enterprise COBOL for z/OS 4.1
Platform Version Supported Version Support Status
IBM z/OS on System z 1.13 IBM Enterprise COBOL for z/OS 4.1 Supported
IBM z/OS on System z 1.12 IBM Enterprise COBOL for z/OS 4.1 Supported
PeopleSoft PeopleTools 8.53 with IBM Enterprise COBOL for z/OS 3.4
Platform Version Supported Version Support Status
IBM z/OS on System z 1.13 IBM Enterprise COBOL for z/OS 3.4 Supported
IBM z/OS on System z 1.12 IBM Enterprise COBOL for z/OS 3.4 Supported
Compatibility with Operating System
Operating System Versions Supported Status
Apple Mac OS X(Intel)32 bit 1 versions(10.5) Supported
Apple Mac OS X(Intel)64 bit 2 version(10.7, 10.6) Supported
Apple iOS 1 versions(5) Supported
IBM: linux on system z 2 Version(Red Hat Linux 5,SLES 11)
Supported
HP-UX itanium 1 version(11.31) Supported
IBM AIX on POWER System(64 bit)
2 Version(7.1,6.1) Supported
IBM z/OS on System z 2 Version(1.13,1.12) Supported
IBM Linux on System z 2 Version(IBM: Linux on System z
SLES 11, Linux on System z Red Hat
Enterprise Linux 5)
Supported
Linux x86-64 5 Versions(Linux x86-64 SLES 11,
Linux x86-64 Red Hat Enterprise Linux 6, Linux x86-64 Red Hat
Enterprise Linux 5, Linux x86-64 Oracle Linux 6, Linux x86-64 Oracle
Linux 5)
Supported
Microsoft Windows(32-bit) 1 versions(Microsoft Windows (32-
bit) 7)
Supported
Microsoft Windows(64-bit) 5 Versions(2008 R2, 2008, 2012(planned), 7, 8(planned))
Supported
Oracle Solaris on SPARC(64-bit) 2 versions(11,10) Supported
Oracle Solaris on x86-64(64-bit) 2 versions(11,10) Supported
Compatibility with Application ,Browsers & clients
Browser Versions Support Status
Firefox 1 Releases(17) Supported
Google Chrome 2 Releases(Google Chrome 24,
Google Chrome 19)
Supported
IBM DB2 Client 2 Releases(9.7,9.5) Supported
IBM DB2 Connect 2 Releases(9.7,9.5) Supported
IBM Informix Client SDK 2 releases(3.70.3.50) Supported
Internet Explorer 2 Releases(10,9) Supported
Microsoft SQL Server Client 2 Release(2012, 2008) Supported
Oracle Database Client 3 Releases(11.2.0.3.0, 11.1.0.7.0, 10.2.0.5.0)
Supported
Safari 2 Releases(6, 5) Supported
Sysbase Open client 2 Release(15.7, 15.5) Supported
Microsoft Word 2 Releases(2010,2007) Supported
Microsoft Excel 2 Releases(2010,2007) Supported
Compatibility with Databases
Product Version Support Status
IBM DB2 for Linux Unix and
Windows
2 Releases(9.7, 9.5) Supported
IBM DB2 for z/OS 2 Releases(10.1, 9.1) Supported
IBM Informix 2 Releases(11.7,11.5) Supported
Microsoft SQL Server 2 Release(2012, 2008) Supported
Oracle Database 3Releases(11.2.0.3,11.1.0.7,10.2.5) Supported
Oracle Real Application
Clusters
3Releases(11.2.0.3,11.1.0.7,10.2.5) Supported
Oracle Secure Enterprise 1 Release(11.1.2.2.0) Supported
Sysbase Adaptive Server 2 Release(15.7, 15.5) Supported
Process Scheduler Server Hardware Requirements
• Sufficient disk space to accommodate the operating system:
• Intel (Windows)
• Intel (Linux)
• Z/series (Linux)
• HP (HP-UX PA-RISC)
• HP (HP-UXItanium)
• IBM (AIX)
• Sun (Solaris)
• z/OS
• Backup device
• Video controller and display.
• Appropriate network interface card and cabling to connect to network.
Process Scheduler Server Software Requirements
• RDBMS connectivity software
• Operating system
• Supported SQL query tool
• Any required network connectivity software
• PS/nVision for PeopleSoft People Tools 8.51 requires Microsoft Open XML SDK 2.0 to generate
reports on Process Scheduler
Application Server Hardware Requirements
• Recommend two processors minimum; at least four processors for production.
• Memory requirement is 512 MB (minimum) per server for roughly up to 25 users. After that add 1.5
MB per user for each user beyond 25 users. 1,000 users require roughly 2.0 GB of memory.
• Recommend fastest or near fastest processors available.
• Sufficient disk space to accommodate:
• Oracle Tuxedo (235 MB).
• Micro Focus Net Express COBOL Compiler (270 MB).
• Database connectivity package varies per platform; check with vendor.
• PeopleSoft application server files and code (2.5 GB).
• Network interface card.
Application Server Software Requirements
• Oracle Tuxedo
• Database connectivity package.
• PeopleSoft application server files and code.
• Any required application server patches.
• FTP capability. (The delivery mechanism for PeopleSoft “patches” and other PeopleSoft maintenance
files is through an FTP server.)