› ... › docs › 160929defencensprequirements1.pdf · national sub-meter program...

28
Version 1.0 (October 2016) NATIONAL SUB-METER PROGRAM REQUIREMENTS REVISION V1.0 OCTOBER 2016

Upload: others

Post on 27-Feb-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

Version 1.0 (October 2016)

NATIONAL SUB-METER PROGRAM REQUIREMENTS

REVISION V1.0 OCTOBER 2016

Page 2: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 1

DEFINITIONS

District Metered Area (DMA)

A small metered area within a supply and distribution system that is specifically defined, for example by the closure of valves. The quantity of water entering and leaving the area can be metered permanently. Also referred to as a Demand Management Area.

Estate Maintenance and Operational Services (EMOS)

Defence Contractor responsible for the maintenance of the estate, including the location, maintenance and operation of Defence meters and metering systems.

Gate meter Defence owned meter immediately downstream of the utility meter measuring the site’s resource consumption.

Metering System Refers to a resource monitoring system at the facility/building level (e.g. Building Management System (BMS)) or precinct/site/regional level system (e.g. Regional Utility Management System (RUMS)).

New Build Activities that involve the installation and connection of new meters and/or metering system hardware/software (e.g. BMS) during the construction of new facilities, infrastructure or equipment.

National Sub-meter Program (NSP)

Defence’s metering, monitoring and management program in response to the Commonwealth Government’s Energy Efficiency in Government Operations (EEGO) policy. The collected data is organised within Defence’s Resource Management System (RDMS).

NSP Program Manager Person responsible for managing the NSP, reporting against Program KPIs, and ensuring the installed meters and metering systems are connected to the RDMS.

Parent and child meters

Sub-meters where the parent meter is upstream of the child meter and measures the child meter’s consumption in addition to other streams. It is important to understand the relationship between meters to avoid double counting. This information is collected through the Meter Hierarchy Template.

Project Delivery Service (PDS)

Defence Contractor responsible for managing the tendering and installation of meters and metering systems under Defence’s Estate Works Program.

Program Sponsor Defence authority responsible for overseeing the NSP such that the program objectives are realised. The sponsor is the Directorate of Energy Efficiency, Environmental Resource Management and Sustainability (DEEERMS).

Resource Data Management System (RDMS)

A network of meters measuring Defence’s electricity, water and gas consumption and transmitting this data to a central data repository allowing users to report, analyse, investigate and action resource opportunities.

Refurbishment Activities that involve the installation and connection of new meters and/or metering system hardware/software (e.g. Building Management System) during the repair or replacement of existing facilities, infrastructure, systems and equipment.

Retrofit Activities that involve the installation, reconfiguration and/or connection of meter and/or metering system hardware/software to existing facilities or infrastructure. In the NSP context, retrofit installations are those that occur outside of the delivery of new or refurbished capital works.

Service Provider Responsible for planning and designing the installation and connection of meters and metering systems in accordance with the NSP requirements.

Sub-meter

Meter that measures a particular building/end use downstream of the utility gate meter and provides better granularity of resource usage. The majority of sub-meters connected to the NSP are measuring facility/building level resource consumption. There are some instances where sub-facility/building data is being captured under the NSP, primarily for the separation of ‘Light and Power’ and ‘Central Plant’ end uses in offices (Table 3-3).

Utility meter Meter that the utility reads to determine Defence’s utility charges often measured at the gate.

Page 3: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 2

DOCUMENT STATUS

Version No.

Issue Date Amendment Details Amended by

1 October 2016 Issued for Use This document supersedes relevant sections of the ‘Electrical Sub-metering Manual for New Construction’ and the ‘Electrical Sub-metering Manual for Retrofits’.

PB (DEEERMS)

DOCUMENT NAVIGATION

Section Key Purpose Target Audience

SECTION 1 – PROGRAM OVERVIEW

Defines the National Sub-meter Program drivers, objectives, targets and KPIs.

Program Sponsor NSP Program Manager

SECTION 2 – PROGRAM IMPLEMENTATION

Outlines the functions and respective requirements to be met by the NSP Program Manager to achieve the NSP objectives.

Program Sponsor NSP Program Manager

SECTION 3 –PLANNING AND DESIGN

States the design requirements for the planning, installation and connection of meters and metering systems to the RDMS.

Program Sponsor NSP Program Manager Service Providers (e.g. EMOS, PDS and Construction Contractors and Design Consultants)

Page 4: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 3

TABLE OF CONTENTS

1. SECTION 1 ...................................................................................................................................... 4 1 PROGRAM OVERVIEW .............................................................................................................. 4 1.1 DOCUMENT PURPOSE ....................................................................................................................... 4 1.2 ASSOCIATED DOCUMENTS ............................................................................................................... 4 1.3 PROGRAM DRIVERS .......................................................................................................................... 4 1.3.1 GOVERNMENT POLICY.................................................................................................................. 4 1.4 DEFENCE POLICY AND STRATEGY ................................................................................................... 4 1.5 NATIONAL SUB-METER PROGRAM OBJECTIVES .............................................................................. 5 1.6 TARGETS .......................................................................................................................................... 5 1.7 MEASURING PROGRAM PERFORMANCE ........................................................................................... 5 1.8 PROGRAM SPONSOR ......................................................................................................................... 6 2. SECTION 2 ...................................................................................................................................... 7 2 PROGRAM IMPLEMENTATION ............................................................................................... 7 2.1 NSP PROGRAM MANAGER ............................................................................................................... 7 2.2 SOFTWARE PLATFORM ..................................................................................................................... 7 2.3 DATA ACQUISITION .......................................................................................................................... 7 2.4 GOVERNANCE .................................................................................................................................. 7 2.5 IMPLEMENTATION FUNCTIONS ......................................................................................................... 8 3. SECTION 3 .................................................................................................................................... 10 3 PLANNING AND DESIGN .......................................................................................................... 10 3.1 PRECEDENCE .................................................................................................................................. 10 3.2 REQUIREMENTS .............................................................................................................................. 10 3.3 PROGRAM EXEMPTION ................................................................................................................... 10 3.4 METERING POINTS ......................................................................................................................... 11 3.5 BUILDING MANAGEMENT SYSTEMS (BMS) .................................................................................. 14 3.6 METERING THRESHOLDS................................................................................................................ 14 3.7 SUB-METER CHARACTERISATION ................................................................................................... 17

Page 5: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 4

1. SECTION 1

1 PROGRAM OVERVIEW

1.1 Document Purpose The purpose of this document is to define the National Sub-meter Program (NSP) such that Defence can:

• make the purpose for the NSP clear to relevant stakeholders • detail the performance requirements against set key performance indicators (KPIs) and their

corresponding targets • apply consistent decision making when making investment decisions and prioritising program

investment • detail metering requirements to stakeholders.

1.2 Associated Documents This document should be read in conjunction with Defence’s Smart Infrastructure Manual: Design and Construction. An overall document matrix outlining how these documents fit into the NSP document suite is explained further on the Defence Estate Quality Management System (DEQMS).

1.3 Program Drivers 1.3.1 Government Policy The Government’s Energy Efficiency in Government Operations (EEGO) policy requires Defence to develop and implement a comprehensive energy management strategy that includes a metering, monitoring and management program. The NSP is designed to meet these EEGO requirements and define end use categories in accordance with EEGO (refer Table 3-6). The data captured under the NSP is organised within Defence’s Resource Management System (RDMS).

1.4 Defence Policy and Strategy The NSP is driven through Defence resource management policy and strategy, namely:

• Defence Estate Energy Policy (2014) • Defence Estate Water Policy (2014) • Defence Estate Energy Strategy (2014-2019) • Defence Estate Water Strategy (2014-2019)

A primary objective defined in both policies is: ‘Measuring and Monitoring – ensure infrastructure and processes are in place to be able to measure and manage Defences energy and water consumption and energy generation effectively.’

Page 6: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 5

1.5 National Sub-meter Program Objectives The objectives of the NSP are to:

1. capture resource consumption data nationally in a centrally available location accessible by users of the estate

2. undertake analysis and reporting to identify resource inefficiency and opportunities for improvement

3. reduce utility costs through improved efficiency and cost recovery, where appropriate 4. action identified opportunities and link to Defence funding streams 5. measure and verify action outcomes 6. comply with regulatory and Ministerial obligations and 7. build corporate knowledge to inform:

a. estate strategic planning and investment activities b. operational performance specific to facility types and c. programs targeting user behaviour on the estate.

1.6 Targets The NSP aims to achieve the resource coverage targets outlined in Table 1-1.

Table 1-1: Coverage targets

Resource Coverage Strategic Driver Details for sub-metering installs

Electricity Minimum 80% of energy consumption by NSP end use categories1

EEGO Policy Estate Energy Strategy

1. New builds to have building/facility level sub-meters or metering systems connected to the RDMS

2. Retrofit to have a Return on investment emphasis only

3. Both subject to threshold requirements in Section 3.

Water Minimum 80% of water consumption

Estate Water Strategy

Gas2 Minimum 80% of energy consumption

Estate Energy Strategy

1.7 Measuring Program Performance Program performance is measured against the key performance metrics and targets outlined in Table 1-2.

Table 1-2: Program KPIs and targets

KPI Description Electricity Target Water Target Gas Target Report

% Coverage

% of the estate’s electricity, water or gas consumption metered by Facility Type and/or end use in the case of water and gas

80% coverage by end of FY 2017-2018

80% coverage by end of FY 2018-2019

80% coverage by end of FY 2019-2020

Monthly

Utility consumption savings

Savings realised. Cumulative achieved savings (kWh, MJ, kL) commencing baseline year FY 2014/15

21.7M kWh +/- 4.3M kWh by FY 2019-2020

177,400 kL +/- 35,500 kL by FY 2020-2021

9.5M MJ +/- 1.9M MJ by FY 2021-2022

Monthly

1 EEGO defined end use categories include: office – tenant light & power, office – central services, climate controlled stores, laboratories, and computer centres. Other end-use categories have been further defined and are included in Table 3-6. 2 Gas refers to natural gas distributed in a pipeline to Defence sites.

Page 7: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 6

KPI Description Electricity Target Water Target Gas Target Report

Gross Value

Gross savings realised. Cumulative achieved savings ($) commencing baseline year FY 2014/15

$3.25M +/- 0.65M by FY 2019-2020

$550K +/- $110K by FY 2020-2021

$200K +/- $40K by FY 2021-2022 Monthly

Gross Value as a percentage of utility expenditure

Gross savings realised. (Cumulative achieved savings ($) / Utility Spend Baseline Year FY 2014/15 ($))

2-3% savings of total baseline electricity spend by end of FY 2019-2020

2-3% savings of total baseline water spend by end of FY 2020-2021

2-3% savings of total baseline gas spend by end of FY 2021-2022

Monthly

Net Value

Net savings realised after investment. Cumulative achieved savings ($) – Ongoing Program Costs ($), commencing baseline year FY 2014/15.

$975K +/- $325K by FY 2019-2020

$165K +/- $55K by FY 2020-2021

$60K +/- $20K by FY 2021-2022 Monthly

Net Value as a percentage of utility expenditure

Net savings realised after investment. (Cumulative achieved savings ($) – Ongoing Program Costs ($) / Utility Spend Baseline Year FY2014/15 ($))

0.5-1% savings of total baseline electricity spend by end of FY 2019-2020

0.5-1% savings of total baseline water spend by end of FY 2020-2021

0.5-1% savings of total baseline gas spend by end of FY 2021-2022

Monthly

Achieved Gross Savings as a proportion of Total Identified Savings in the RDMS

Cumulative gross savings achieved ($) / Cumulative total identified savings ($) in the RDMS

50% conversion of identified savings to actual savings ongoing from FY 2017-2018

50% conversion of identified savings to actual savings ongoing from FY 2018-2019

50% conversion of identified savings to actual savings ongoing from FY 2019-2020

Monthly

It is acknowledged that changes to utility prices or the utility tariff structure will impact the ability to achieve KPIs in the above table and ultimately the types of savings that can be identified and realised through the NSP. The Program Sponsor will factor these changes into the reporting of KPIs each year.

1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency, Environmental Resource Management and Sustainability (DEEERMS) on behalf of the Technical Authority, Assistant Secretary Environment and Engineering (ASEE). Thresholds and targets set in this document will be reviewed and updated to reflect changes in meter and utility market charges. The most current version will be available from the DEQMS website and shall be referred to when developing contractual documentation. Enquiries may be directed to:

Director Energy Efficiency, Environmental Resource Management and Sustainability

Tel: (02) 6266 8045

Email: [email protected]

Page 8: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 7

2. SECTION 2

2 PROGRAM IMPLEMENTATION Defence has identified four functions to achieve the National Sub-meter Program objectives defined in Section 1.5. These are:

1. NSP Program Manager 2. Software Platform 3. Data Acquisition 4. Governance.

The four functions are described below.

2.1 NSP Program Manager The NSP is overseen by the NSP Program Manager. The NSP Program Manager reports directly to the Program Sponsor. The NSP Program Manager is required for the ongoing development, implementation, and integration of the NSP into Defence’s day-to-day business. The NSP Program Manager drives the program such that a secure, useful and reliable NSP will meet the overall program objectives. The requirements of this role are defined in Section 2.5.

2.2 Software Platform The NSP Program Manager is responsible for the ongoing operation and maintenance of the software platform. The NSP is supported by a web-based software platform, compliant with Defence security requirements and receives data from NSP metering points across the estate. The data is stored and managed within the software platform in accordance with quality management and assurance processes outlined in the relevant program protocols. The software platform has the functionality to allow users to undertake data analysis and automated reporting to help meet users’ resource reporting requirements. The software platform, analysis and reporting functionality requirements are described in more detail in Section 2.5.

2.3 Data Acquisition The NSP Program Manager is responsible for the regular and secure acquisition of NSP Data, specifically that:

• Data is transferred from each installed NSP meter and NSP measurement device (e.g. individual electricity, water or gas meter or BMS) to the software platform on a regular basis (typically daily).

• Any data transfer that contains identifiable information is secure (i.e. an intercepted file should not allow the physical location to be matched to the metered data).

• The transfer has quality control protocols in place to ensure the completeness of the received information (i.e. no missing data).

Acquisition data requirements are described in more detail in Section 2.5.

2.4 Governance Governance of the NSP is the responsibility of the Program Sponsor on behalf of the Assistant Secretary Environment & Engineering (ASEE): Progress of the NSP is measured using the KPIs outlined in Table 1-2 and reported annually to ASEE. Program Governance requirements are outlined in Section 2.5.

Page 9: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 8

2.5 Implementation Functions Table 2-1 defines the requirements identified under each implementation function.

Table 2-1: Implementation function – requirements Function Requirements

NSP

Pro

gram

Man

ager

Man

agem

ent R

espo

nsib

ility

1. Meters and metering equipment installed and commissioned is monitored to ensure that it is correctly connected to the RDMS, in a timely manner and in accordance with relevant specifications and NSP processes. Any potential problems are highlighted and reported to the relevant party such that the issues are addressed promptly.

2. Meter fleet and metering equipment connected to the RDMS is tracked and fixes for any faulty meters are recommended to the Program Sponsor for action, such that RDMS performance is maximised.

3. Quality, security controls and procedures are in place and proactively implemented to ensure the integrity and quality of the RDMS and associated program processes is maximised.

4. Automation and thresholds built into the RDMS continue to be developed and maintained such that they remain accurate, current, meet the functionality required by users, and contribute to the achievement of the NSP objectives and KPIs.

5. Facility-specific estimated resource intensity targets and associated facility information captured in the Smart Infrastructure Metering Strategy are entered into the RDMS.

6. Registers (e.g. SIM Card, user and meter registers) and associated program documentation are accurate and up to date.

7. Meter, data and associated agreements with third parties are managed on behalf of Defence to ensure the outcomes provide value for money and any potential problems are quickly brought to the Program Sponsor’s attention.

8. Processes, procedures and guidance are documented and implemented that cover: a) installation, connection, data transfer, and commissioning of meters b) tracking of hardware, user access, SIM cards and other relevant project components c) data management d) data interrogation, maintenance and cleansing e) data analysis including use of tools and queries f) anomaly identification and g) report development and generation in accordance with reporting requirements.

9. Consistent, relevant and timely communications is provided to RDMS users and stakeholders covering both program level and system level information.

10. Training activities, training materials and guidance is provided to RDMS users that is current, relevant and useful such that it meets users’ needs.

11. Training and support is provided to RDMS users such that nationally consistent processes and procedures are followed.

12. Training is provided to users to increase their energy and water data management and analytical skills to proactively action, rectify and reduce utility costs.

13. Technical support is provided centrally to users for all NSP related queries and all queries are dealt with promptly and effectively.

14. Technical and strategic advice is provided to Defence Managers, RDMS users and Defence Contractors that is relevant, timely and proactive to assist: a) achievement of the objectives and intent of the program b) installation & commissioning oversight and guidance c) meter fault rectification and repairs d) procurement of hardware e) data extraction f) data interpretation g) reporting h) meter performance i) feasibility studies and business case development j) policy development and k) scoping of future meter rollout.

15. NSP KPIs are reported in accordance with Table 1-2.

Page 10: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 9

Softw

are

Plat

form

Sof

twar

e

1. The software allows users to easily access, view, analyse and report using collected metered data corresponding to their work function.

2. The software safely and securely stores historic metering data. 3. The software enables the storage of other data against each meter such that users can compare

resource consumption and other relevant analysis between facilities (e.g. BOM data, floor area m2, utility cost).

4. The software stores and tracks progress of identified resource saving opportunities in the form of Sustainability Action Plans (SAPs).

Ana

lysi

s fu

nctio

nalit

y

5. The software platform meets the following analysis requirements: a) Targets set during design and construction are compared against the actual energy and water

intensity of newly constructed Defence infrastructure in an automated and systematic way. b) Facility performance is tracked and compared against facility specific performance targets

and appropriate industry benchmarks, normalised by climatic zones and seasonal variation. c) Anomalies are identified where a facility may be under-performing (e.g. outside expected

ranges in peak demand or base load over a month) based on pre-determined thresholds built into the RDMS.

d) Trends in consumption are identified and interrogated at levels as required by the user (e.g. meter, precinct, site or estate wide).

e) Cost implications of resource consumption and resulting savings from addressing inefficiencies.

f) Resource inefficiencies are identified.

Rep

ortin

g &

Dis

play

func

tiona

lity

6. The software platform meets the following reporting requirements: a) Reports are produced that require minimal user input. b) Reports are produced that align with the user’s reporting requirements (e.g. ad-hoc or

standard automated reports, format and audience appropriate) and cover the following resource management aspects, as defined by Defence needs:

i. Resource consumption trends and profiles ii. Opportunities in the form of SAPs iii. Regulatory and Defence policy compliance iv. Facility performance against design targets and benchmarks v. Anomalies (e.g. unexpected deviations from predetermined tolerances in power

factor correction, peak demand, consumption, base load fall or facility specific targets and benchmarks)

vi. Financial savings including identified and realised vii. Meter fleet status viii. Ecologically Sustainable Development (ESD) Program and other resource

investment outcomes (e.g. realised payback).

Dat

a A

cqui

sitio

n 1. The data is transferred remotely from the meters or metering systems to the software platform in a timely, secure and quality controlled manner.

2. The data transfer networks (e.g. Virtual Private Network) and the protocols governing them are defined, maintained and communicated to the relevant contractors.

3. Issues with data acquisition and transfer are identified in a timely manner and reported to the appropriate entity (i.e. Program Sponsor or system manufacturer) for remedy.

4. The efficiency of data acquisition is periodically reviewed to demonstrate that value for money is maximised.

Gov

erna

nce 1. NSP Program Manager reports monthly to the Program Sponsor

2. A progress meeting is held quarterly between the Program Sponsor and the NSP Program Manager.

3. Progress of the NSP KPIs (Table 1-2) are reported annually to the Technical Authority.

Page 11: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 10

3. SECTION 3

3 PLANNING AND DESIGN

3.1 Precedence There are multiple electricity, water and gas meters across the Defence estate. Meters and metering systems connected to Defence’s RDMS are for the purpose of national energy management and associated reporting. The remainder of the meter fleet has been installed in response to other requirements, external to the sub-meter program. These requirements are contained in the following:

• Section J Energy Efficiency of the National Construction Code (NCC) Volume One – Building Code of Australia (BCA)

• Defence Manual of Infrastructure Engineering – Electrical (MIEE).

The NSP requirements do not supersede these other metering requirements.

3.2 Requirements Service Providers responsible for planning and design activities shall ensure the following is undertaken:

• The planning and design of NSP electricity, water, and gas meters and metering systems is in accordance with the requirements outlined in Sections 3.3 to 3.6.

• Any new meter allocations are to be designed and installed in accordance with Defence’s Physical Security Zones (PSZ) methodology. Building users must be informed that the meters are wireless and these meters conform to the overall building classification. Details of the PSZ methodology is available via the DRN intranet here.

• The decision to connect a BMS to the RDMS is at the discretion of the NSP Program Manager in accordance with Section 3.5 and the BMS-RDMS Connection Protocol.

• Any new or replacement meters or BMS meet the relevant hardware and data protocol specifications available on the NSP page through DEQMS.

• For New Builds or Refurbishments the Service Provider submits to DEEERMS a final Metering Strategy and Metering Hierarchy Template at design completion. Both are available on DEQMS.

• For retrofitting meters to existing facilities, Service Providers submit a New Meter Form and Meter Hierarchy Template in accordance with the meter installation guideline (available from DEQMS) for any new meters or replacement meters being connected to the RDMS.

• New or replacement meters are added to Defence's estate information system to ensure maintenance of the meter hardware can be performed.

3.3 Program Exemption Where the NSP requirements cannot be met due to technical feasibility (e.g. prohibitive for safety or for security reasons) and/or not cost effective for Defence, then an exemption shall be sought with appropriate justification and supporting evidence (e.g. cost estimate to install the meter). Written Defence acknowledgement shall be obtained by the Service Provider at the initial design stages via [email protected]. Post-construction requests for exemptions are not acceptable.

Page 12: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 11

3.4 Metering Points Connect a meter (or metering system) to the RDMS where the following scenarios apply:

Table 3-1: Metering point scenarios Resource

Scenario Utility Meter or Gate Meter Meter at facility/building level or sub-

building level Meter in the reticulation network Metering resource generation/alternative supply

Elec

tric

ity

New

Bui

ld

Where the site’s total consumption >100,000 kWh p.a.

Where Building/Load Type requirements are triggered in Table 3-3 do one of: • Connect via a new BMS head-end

(refer to Section 3.5) OR • Utilise a new meter being installed to

meet other requirements (e.g. Section J BCA) OR

• Provide a new meter.

Where new substations are installed in accordance with the MIEE.

Where a new (whether as part of new build/refurbishment/or works to existing facilities/buildings): • wind or solar generation3 system

is rated at >10 and >20 kW4 respectively .

• diesel generation system is rated at >200 kW and the energy generation requirement is estimated to be >100,000 kWh p.a.

Ref

urbi

shm

ent

Where the Building/Load Type requirements are triggered in Table 3-3 and either the works: • have been classed as significant5, in

accordance with Defence’s BEPM OR

• involve the replacement of an existing BMS, switchroom or sub-station for facilities/end uses.

Ret

rofit

6

Where an existing compliant utility gate meter total consumption >100,000 kWh p.a. OR Where a new effective gate meter has to be installed the threshold increases to >200,000 kWh p.a.

Where a facility’s total annual consumption >200,000 kWh p.a. Where this facility/building is ‘Mixed Use’ also meter for any individual area or category of consumption that is >200,000 kWh p.a., where circuitry allows.

Where there are existing meters in the electricity reticulation network connect to the RDMS where the downstream energy consumption is >100,000 kWh p.a.

Intentionally left blank.

3 Other generation systems will be revisited for inclusion in the future. 4 Under the Renewable Energy Target (RET) scheme generation systems have different capacity thresholds above which these systems are eligible for the creation of Large Generation Certificates (LGC) and must be metered to do so. Where LGCs will be created then metering in accordance with the relevant kW capacity threshold under the RET scheme takes precedence. 5 Significant refurbishments are those that can change the total building and services regulated annual energy consumption by more than 10%. The 10% limit applies to those staged refurbishments that occur over a 3 year period with no less than a 3 year period between one set of refurbishments and the next set. Refer to Defence’s BEPM for further detail. 6 Where the cost to connect to the RDMS becomes prohibitive or technically not feasible (e.g. safety or security reasons) then the facility shall be included under the targeted monitoring program in preference to the installation of direct connect or closed Current Transformer (CT).

Page 13: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 12

Resource

Scenario Utility Meter or Gate Meter Meter at facility/building level or sub-

building level Meter in the reticulation network Metering resource generation/alternative supply

Wat

er

New

Bui

ld Where the site’s total

consumption >5,000 kL p.a. Where Building/Load Type requirements are triggered in Table 3-4 do one of: • Connect via a new BMS head-end

(refer to Section 3.5) OR • Provide a new meter.

When works are being undertaken on site to replace or construct new water reticulation where Building/Load Type requirements are triggered in Table 3-4 (i.e. irrigation schemes, specific District Metered Area (DMA).

Where infrastructure/buildings use >5,000 kL p.a. alternative water sources.

Ref

urbi

shm

ent

Where Building/Load Type requirements are triggered in Table 3-4 and either the works: • include changes to the

facility/building’s hydraulic services that allow for meter installation OR

• involve the replacement of an existing BMS (refer to Section 3.5).

Ret

rofit

7

Where the site’s total annual consumption >5,000 kL p.a. OR Where a new effective gate meter has to be installed the threshold increases to >12,000 kL p.a.

Where a facility’s total annual consumption >12,000 kL p.a.

Where there are existing meters in the water reticulation network connect to the RDMS where the downstream water consumption is >5,000 kL p.a.

Intentionally left blank.

Gas

New

Bui

ld

Where the site’s total consumption >700 GJ p.a.

Where Building/Load Type requirements are triggered in Table 3-5 do one of: • Connect via a new BMS head-end

(refer Section 3.5) OR • Utilise a new meter being installed to

meet other requirements (e.g. Section J BCA) OR

• Provide a new meter.

When works are being undertaken to replace or construct new gas reticulation servicing Building/Load Type requirements are triggered in Table 3-5.

Intentionally left blank.

Ref

urbi

shm

ent

Where the Building/Load Type requirements are triggered in Table 3-5 and either the works: • have been classed as significant8, in

accordance with Defence’s BEPM OR

• involve the replacement of an existing BMS (refer to Section 3.5).

Intentionally left blank.

7 Where the cost to connect to the RDMS becomes prohibitive or it is technically not feasible (e.g. safety or for security reasons) then the facility is included under a targeted monitoring program in preference to the installation of new meters. 8 Significant refurbishments are those that can change the total building and services regulated annual energy consumption by more than 10%. The 10% limit applies to those staged refurbishments that occur over a 3 year period with no less than a 3 year period between one set of refurbishments and the next set. Refer to Defence’s BEPM for further detail.

Page 14: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 13

Resource

Scenario Utility Meter or Gate Meter Meter at facility/building level or sub-

building level Meter in the reticulation network Metering resource generation/alternative supply

Ret

rofit

9

Where the site’s total annual consumption >700 GJ p.a. OR Where a new effective gate meter has to be installed the threshold increases to >1,800 GJ p.a.

Where a facility’s total annual consumption >1,800 GJ p.a.

Intentionally left blank

9 Where the cost to connect to the RDMS becomes prohibitive or is technically not feasible (e.g. safety or for security reasons) then the facility is included under a targeted monitoring program in preference to the installation of new meters.

Page 15: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 14

3.5 Building Management Systems (BMS) A BMS or the metering system head end shall be connected to the RDMS where the scenarios in Table 3-2 apply and as agreed with the NSP Program Manager in accordance with the BMS-RDMS Connection Protocol.

Table 3-2: BMS Scenarios

Resource Scenario BMS (e.g. building level) or Precinct/site level system head unit (e.g. site resource management system)

Elec

tric

ity /

Wat

er /

Gas

New Build Where the system covers facilities that trigger the Building/Load Type requirements in Table 3-3, Table 3-4 and Table 3-5 and provides resource data at the facility/building level. Refurbishment

Retrofit

Where the existing system meets each of the following: • covers facilities that trigger requirements in Table 3-3, Table 3-4 and

Table 3-5 • provides resource data at the facility/building level • allows connection to the RDMS that is cost-effective and technically

feasible (e.g. not prohibitive for safety or for security reasons).

3.6 Metering Thresholds The specific building/load type requirements and thresholds for electricity, water and gas meters are summarised in Tables 3-3 to 3-5.

Table 3-3: Electricity meter thresholds

Building/load type NSP metering requirement

New buildings / refurbishments

Office buildings <2,000m2 area AND with estimated electricity consumption >100,000 kWh p.a.

One NSP meter to cover whole building electricity consumption (note office buildings come under the Facility Group ‘Administration’ as per Table 3-6).

New buildings / refurbishments

Office buildings >2,000m2 area

NSP meters to cover each of the following:

a. Office Light and Power (L&P) (lighting and general power outlet (GPO) power for tenant use).

b. Central Plant (central mechanical plant including chillers, fans, pumps, electric heating and any central packaged HVAC units) and base building services such as common area lighting.

The number of meters should be minimised while covering these categories. Virtual meters can only be used where a BMS is able to calculate and produce an output file for the virtual meter that can be exported to the RDMS (as per the BMS-RDMS Connection Protocol).

Where a NABERS rating is required provide all necessary metering and sub-metering in accordance with ‘NABERS Energy and Water for offices: Rules for collecting and using data’ to allow for the collection of data to obtain or verify a NABERS rating.

Page 16: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 15

New buildings / refurbishments

Non-office buildings with estimated electricity consumption >100,000 kWh p.a.

One NSP meter to cover the whole building’s electricity consumption and NSP meters to cover each of the following high priority end uses:

a. L&P where estimated electricity consumption >100,000 kWh p.a.

b. Central Plant where estimated electricity consumption >100,000 kWh p.a.

The number of meters should be minimised while covering these categories, e.g. if building electricity usage is only Central Plant and L&P (and both > 100,000 kWh p.a.) a whole building meter is not required. Alternatively, a virtual meter may be provided as per the requirement outlined for ‘office buildings > 2,000m2’.

For mixed use buildings, provide a separate meter for each individual area, special load or category of consumption (e.g. workshop) where estimated electricity consumption > 100,000 kWh p.a. If more than 80% of the estimated electrical consumption can be attributed to a single category assign the building to this category.

New buildings / refurbishments

Non-office buildings with estimated maximum demand >100 kW

One NSP meter to cover the whole building’s electricity consumption.

If more than 80% of the estimated electrical consumption can be attributed to a single category assign the building to this category.

New buildings / refurbishments

Special cases

There may be special cases on new infrastructure or major refurbishment projects where additional NSP meters may be required, outside the conditions listed above. These will generally include buildings that exhibit large, short duration loads (kW/kVA demand) that have a significant impact on a sites power and energy (kWh) usage profile. Examples include priority operational loads such as ship degaussing, the provision of meters for on billing of third party electricity use and sites where load and consumption are needed to monitored closely for operational purposes (e.g. demand at site needs to be rationed throughout the day, load shedding).

If there is a likelihood that any buildings will be used by third parties these buildings shall be metered separately for the purpose of cost recovery by Defence.

In these cases NSP meters may also be specified by the Program Sponsor or Defence Representative (e.g. NSP Program Manager).

Retrofit

Group of similar non-office existing buildings with estimated aggregate electricity consumption >200,000 kWh

One NSP meter to cover an aggregated group of the same type of buildings with similar consumption profiles, where circuitry allows.

If there are any loads that will distort the typical profile then these buildings shall be metered separately, subject to the thresholds above.

If there is a likelihood that any buildings will be used by third parties these buildings shall be metered separately for the purpose of cost recovery by Defence.

Building categories under the NSP are detailed in Table 3-6.

Page 17: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 16

The specific building/load type requirements and thresholds for water meters are summarised in Table 3-4 .

Table 3-4: Water meter thresholds

Building/load type NSP water metering requirement

New buildings / refurbishments

Buildings with estimated water consumption >5,000 kL p.a.

One NSP meter to cover the infrastructure’s total water consumption and NSP meters to cover each of the following high priority end uses where estimated water consumption >5,000 kL p.a.:

a. Amenities water consumption (toilets, showers, basins).

b. HVAC water consumption (e.g. cooling towers).

c. Irrigation water consumption.

d. Process water consumption (e.g. operational equipment or use, wash points).

The number of meters should be minimised while covering these categories. If remaining building/area water consumption does not exceed 5,000 kL p.a. then no other NSP metering is required.

New buildings / refurbishments

Water reticulation

The layout of new water reticulation shall be separated into distinct water supply areas (District Metering Area (DMA)) with the entrance and outlet (if applicable) metered to facilitate leak detection. The layout of the water reticulation network shall be designed to minimise the number of meters while maximising coverage and leak detection capability.

New buildings / refurbishments

Water reticulation for irrigation

NSP meters shall be provided where the downstream estimated water consumption for irrigation >5,000 kL p.a. This threshold shall be used for each DMA within the irrigation network.

The layout of the water reticulation network shall be designed to minimise the number of meters while maximising coverage and leak detection capability.

The specific building/load type requirements and thresholds for gas meters are summarised in Table 3-5. Meters must have the capability and connectivity via a modem or other communication device to the RDMS.

Table 3-5: Gas meter thresholds

Building/load type NSP gas metering requirement

New buildings / refurbishments

Buildings with estimated gas consumption >700 GJ p.a.

One NSP meter to cover infrastructure’s total gas consumption and NSP meters to cover each of the following high priority end uses with estimated gas consumption >700 GJ p.a.:

a. Water or air heating (swimming pools, DHW boilers, HVAC heating boilers, steam generation).

b. Different sections of a mixed facility e.g. workshop and office that meet the threshold where they have different gas consuming equipment.

c. Cogeneration.

The number of meters should be minimised while covering these categories. If remaining building/area gas consumption does not exceed 700 GJ p.a then no other NSP metering is required.

Page 18: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 17

3.7 Sub-meter characterisation Each sub-meter installed as part of the NSP must be characterised according to the categories listed in Table 3-6. The Facility Group category is the high level category that Defence uses to report under Commonwealth EEGO requirements. Underneath each Facility Group there is a variety of Facility Type categories which will be used for internal Defence energy management activities, these are less formal and new options can be added as the program continues to evolve.

Page 19: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 18

Table 3-6: NSP Facility Groups and Types

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

Accommodation Barracks / Shared Accommodation / Single Live In Accommodation, Detached Houses, Apartments, Amenities

B.1a.01

B.1a.02

Building BCA 1a House

Defence House

DHA

B.1b.01

B.1b.05

B.1b.06

Building BCA 1b Residential Accommodation

L5 Living In Accommodation (LIA)

Off Base Accommodation

L4 Living In Accommodation (LIA)

B.2.01

B.2.05

B.2.06

Building BCA 2 Unit Accommodation

L5 Living In Accommodation (LIA)

Off Base Accommodation

L4 Living In Accommodation (LIA)

B.3.01

B.3.02

B.3.03

B.3.04

Building BCA 3 Residential Accommodation

Detention Centre

L1 Living In Accommodation (LIA)

L3 Living In Accommodation (LIA)

Training/Transit

10 For general operation and maintenance of the estate, Defence uses the Estate Register Information Model (ERIM) to classify Defence buildings, infrastructure, infrastructure systems, equipment, equipment systems and spaces on the Defence estate through a system of Estate Classes This includes the classification of buildings and spaces as per the National Construction Code (NCC/BCA) for engineering design purposes (Estate Class 2 in ERIM).

Page 20: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 19

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

B.3.05

Accommodation

L2 Living In Accommodation (LIA)

B.10a.01 Building BCA 10a Non-Habitable Ablution

S.05

S.06

S.22

S.43

Space Bathroom

Bedroom

Dining Areas

Laundry

-

-

-

-

Administration Offices, Non-Base Offices, Data Centres, Other (to be confirmed with DEEERMS as required)

B.5.01

B.5.02

B.5.03

B.5.04

B.5.05

Building BCA 5 Working Accommodation Office

Office Accommodation

Recruitment Centre

Consulting Medical/Dental service

Police

Air Traffic Control

S.39

S.52

S.54

S.64

S.76

Space ICT Equipment Room

Meeting Room

Office

Resource Room

Waiting Room

-

-

-

-

-

Page 21: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 20

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

Communications Communications B.10a.19 Building BCA 10a Non-Habitable Communication

S.39 Space ICT Equipment Room -

Education and Training Classrooms, Museums, Lecture Theatres, On-Base Child Care Facilities, On-Base Schools, Training Grounds

B.9b.05

B.9b.15

B.9b.03

B.9b.09

B.9b.10

B.9b.01

B.9b.04

Building BCA 9b Hall or Assembly Educational

Training

Child Care Centre

Library

Museum

Assembly Hall

Conference

S.02

S.14

S.44

S.73

S.59

Space Auditorium

Computer Training

Library

Training / Classroom

Plant

-

-

-

-

-

Health Medical Centres, Hospitals, Other (to be confirmed with DEEERMS if required)

B.9a.01

B.9a.02

Building

BCA 9a Healthcare

Health Care

Hospital

S.58

S.21

Space Pharmacy

Dental Treatment Room

-

-

Page 22: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 21

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

S.51

S.53

S.55

S.61

S.76

S.77

Medical Treatment Room

Nurses Station

Operating Theatre

Radiology

Waiting Room

Ward

-

-

-

-

-

-

Laboratories Laboratories S.41

S.50

Space

Space

Laboratory

Medical Laboratory

-

-

Mess Mess Halls, Kitchens, Cafeterias

B.6.10 Building BCA 6 Retail Building Mess

S.04

S.22

S.40

Space Bar Areas

Dining Areas

Kitchen

-

-

-

Page 23: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 22

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

Mixed11

Other Substations, Car Parks, Central Plant, Pump Stations, Other loads12

S.34 Space Garage -

Recreation Exterior, Gyms, Ovals, Sports Centres, Pools, Other

B.9b.06

B.9b.07

B.9b.08

B.9b.11

Building BCA 9b Hall or Assembly Gymnasium

Indoor Pool

Indoor Sport

Pavilion or Grandstand

S.09

S.36

S.63

S.65

S.67

S.71

Space Change Room

Gymnasium

Recreation

Sauna

Sport Court

Swimming Pool Area

-

-

-

-

-

-

11 Substations, distribution pillars, facilities or buildings where 80% or more of the electricity consumption or peak estimated electrical load cannot be assigned to a single Facility Group 12 All other facilities or infrastructure not covered in the other Facility Groups listed.

Page 24: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 23

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

Retail Bank

Food

Post Office

Service Station

Shop

Shopping Centre

Butcher

B.6.01

B.6.03

B.6.06

B.6.07

B.6.08

B.6.09

Building BCA 6 Retail Building Bank

Food

Post Office

Service Station

Shop

Shopping Centre

S.03

S.24

S.31

S.35

S.60

Space Bank

Dry Cleaning

Food

General Shop

Post Office

-

-

-

-

-

Page 25: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 24

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

Special Loads Defence Operational loads (e.g. ship plug-in, fuel pumping, other)

Warehouse and Storage

General Stores, Climate Controlled, Garages, Warehouses, Other

B.7a.03

B.7a.04

B.7a.05

B.7a.06

B.7a.08

B.7a.09

B.7a.10

Building BCA 7a Vehicle Shelter

Bike

Car

Coach

Machinery

Armoured Vehicle

Truck

Fire Station

B.7b.01

B.7b.02

B.7b.03

B.7b.04

B.7b.05

B.7b.06

B.7b.07

B.7b.08

B.7b.09

B.7b.10

Building BCA 7b Warehouse and Storage

AFFF Store

Battery Store

Chemical Store

Explosive Ordnance Store

Hazardous Materials Store

Store

Warehouse

POL Store

Aircraft

Artillery

Page 26: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 25

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

B.7b.11

B.7b.12

B.7b.13

B.7b.14

B.7b.15

Marine

Armoury

Plant & Equipment

Communication

Computer

B.10a.02

B.10a.06

B.10a.08

B.10a.09

B.10a.10

B.10a.11

B.10a.12

B.10a.13

B.10a.14

Building BCA 10a Non-Habitable

Animal Shelter

Shed

AFFF Store

Battery Store

Chemical Store

Explosive Ordnance Store

Hazardous Materials Store

Store

POL Store

S.01

S.11

S.69

Space

Armoury

Chemical Store

Store

-

-

-

Page 27: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 26

Facility Group Facility Types

Estate Register Information Model (ERIM)10

EC-Id Estate Class 1 Estate Class 2 (NCC/BCA) Estate Class 3

Workshops Workshops, Hangars, Maintenance Facilities

B.8.02

B.8.09

B.8.10

B.8.11

B.8.17

B.8.20

Building

BCA 8 Working Accommodation Non-Office

Aircraft Workshop

Laboratory

Laundry/ Dry Cleaning

Meteorological Station

Workshop or Factory

Mechanic

B.10b.01 Building BCA 10b Structure Wash Point

S.37

S.49

S.79

S.80

S.81

Space

Hangar

Mechanic

Wash Bays

Work Pit

Workshop

-

-

-

-

-

Page 28: › ... › Docs › 160929DefenceNSPRequirements1.pdf · NATIONAL SUB-METER PROGRAM REQUIREMENTS1.8 Program Sponsor The NSP is sponsored by the Directorate of Energy Efficiency,

DEPARTMENT OF DEFENCE NSP REQUIREMENTS

Version 1.0 (October 2016) Page 27