5/13/2016
1
Rehabilitation of Division Street Bridge
Structural Engineers Association of Illinois13th Annual Midwest Bridge SymposiumApril 28, 2016
Presented By: Brad Noack, PE, SEProject Manager
Rehabilitation of Division Street Bridge 2
Rehabilitation of Division Street Bridge
Owner:City of Blue Island
Engineering Team:Prime Consultant – LochnerRoadway/Survey/Civil Sub-Consultant – Robinson EngineeringElectrical Sub-Consultant – AAA Engineering
Construction Management:Lochner
Contractor:Kenny Construction
Rehabilitation of Division Street Bridge 3
Location Map
Project LocationProject Location
N
5/13/2016
2
Existing Camelback Thru Truss Bridge
Rehabilitation of Division Street Bridge 4
Rehabilitation of Division Street Bridge 5
Existing Camelback Thru Truss Bridge
6
• Large assets for suburb of 20,000• No maintenance in 40 years, 10 tons posted in 2003
Rehabilitation of Division Street Bridge 6
Background
Previous 1921 Structure
5/13/2016
3
7
• 2004 Phase I study by Robinson Engineering• No Phase III funding, project stalls
Rehabilitation of Division Street Bridge 7
Background
8
• Lochner named NBIS Program Manager• Begins hands-on inspection of Chatham/Division bridges
Rehabilitation of Division Street Bridge 8
2007 Fracture Critical Inspection
9
• Findings -
Rehabilitation of Division Street Bridge 9
2007 Fracture Critical Inspection
Severe corrosion under floor drains and joints!
5/13/2016
4
10
Recommendations:• Reduce posting to 3 tons• Major repairs needed!
Result:• No emergency vehicle/school bus crossing• No funding for repairs
Rehabilitation of Division Street Bridge 10
2007 Fracture Critical Inspection
11
• No funds for required hands-on fracture critical inspection• Visual inspection shows worsening conditions
Rehabilitation of Division Street Bridge 11
2010 Closure
12
Illinois Major Bridge Program funding request was rejected, but yielded valuable feedback
Reasons given:• Lack of justification for costs (up-to-date scope and cost
estimates needed)• Low ADT = 4,000 (2030)
Action Items:• Update Phase I study• City to develop TIF District
Rehabilitation of Division Street Bridge 12
Quest for Rehabilitation Funding
5/13/2016
5
13
Scope:• Hands-on Inspection• Load Rating Analysis• BCR w/ Life Cycle Cost Analysis• Repair or Replace?
Rehabilitation of Division Street Bridge 13
2012 Phase I Update
Load up the barge!
14
Scope:• No As-Builts exist – field
measure everything
Rehabilitation of Division Street Bridge 14
2012 Phase I Update
Many members are different than original plans suggest…up to 25% larger
Roadway stringers:Per Plan = W24x76Field Verified = W27x94
15
Scope:• Load Rating Analysis
o AASHTOWare BrRo As-Built and As-Inspected Ratings
Rehabilitation of Division Street Bridge 15
2012 Phase I Update
5/13/2016
6
16
Scope:• Load Rating Analysis
o BrR Truss Module for Span 2o BrR FB/Stringer Module for Span 1, 3 & 4o Use field measured sectionso Input section loss % as measured
Rehabilitation of Division Street Bridge 16
2012 Phase I Update
17
Scope:• Load Rating Analysis
o HS-20 Inventory Rating Results Stringers RF = 0.00 in 8 locations Floorbeam RF = 0.42 under north truss joint Truss Chord RF = 1.61
Gusset Plates RF = ???
Interior FB’s RF = 1.04 (Controlling As-Built)
Rehabilitation of Division Street Bridge 17
2012 Phase I Update
18
Scope:• FHWA Gusset Plate Load Rating
o Complete Field Documentationo Measure remaining section in corrosion areas
Rehabilitation of Division Street Bridge 18
2012 Phase I Update
5/13/2016
7
Scope:• FHWA Gusset Plate Load
Ratingo Failure Modes Fasteners Yielding Fracture Rupture Buckling
o Huge MathCad efforto AASHTOWare BrR now
handles gusset plates
19Rehabilitation of Division Street Bridge 19
2012 Phase I Update
20
Scope:• FHWA Gusset Plate Load Rating - Results
Rehabilitation of Division Street Bridge 20
2012 Phase I Update
HS-20 Gusset Inventory RF = 1.82
GOOD!
(Does not control over Truss Chord
RF = 1.61)
21
Scope:• Bridge Condition Report
o Rehab Option Replace Deck (>30% defects) Replace Span 1, 3 & 4 Superstructure Replace Stringers 2 & 6/End FB’s in Span 2 Clean/Repaint Span 2
Rehabilitation of Division Street Bridge 21
2012 Phase I Update
5/13/2016
8
22
Scope:• Bridge Condition Report
o Replacement Option Backspan distance/depth not available for Plate Girder Truss or Tied Arch
Rehabilitation of Division Street Bridge 22
2012 Phase I Update
23
Scope:• Life Cycle Cost Analysis (follows NCHRP Report 483)
o Assumed rehab extends life 35 yearso Analysis Period = 100 yearso Assumed maintenance cycleso Initial Costs = $6.8M for rehab, $12.0M for replacement
o Life Costs = $12.6M for rehab, $14.5M for replacement
Rehabilitation Option Recommended
Rehabilitation of Division Street Bridge 23
2012 Phase I Update
24
Reasons given for previous IMBP rejection:• Lack of justification for costs (accurate data, better
justifications, proper scope and cost estimates needed)• Chatham closed permanently, ADT = 9,000 (2040)
Case made for project:• Emergency vehicle/school bus rerouting• Effects on local business• Local fund match secured through TIF• Submit fund request September 2013
Rehabilitation of Division Street Bridge 24
Quest for Rehabilitation Funding (Take 2)
5/13/2016
9
25Rehabilitation of Division Street Bridge
Scope:• Safety/durability/aesthetic improvements• Reduce Fracture Critical Members• P, S & E for complete rehabilitation
25
2014 Phase II
26
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 26
2014 Phase II
27
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 27
2014 Phase II
5/13/2016
10
28
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 28
2014 Phase II
Joint & drain reduction• 6 open joints 4 sealed joints• 90 floor drains 8 scuppers
29
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 29
2014 Phase II
30
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 30
2014 Phase II
5/13/2016
11
31
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 31
2014 Phase II
32
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 32
2014 Phase II
33
Scope:• Safety/durability/aesthetic improvements
Rehabilitation of Division Street Bridge 33
2014 Phase II
5/13/2016
12
34
Scope:• Safety/durability/aesthetic improvements
o Additional improvements New weathering steel New deck is HPC Non-composite FB’s made composite
Rehabilitation of Division Street Bridge 34
2014 Phase II
35
Scope:• Reduce Fracture Critical Members (4 FB’s Removed)
Rehabilitation of Division Street Bridge 35
2014 Phase II
36
Scope:• Reduce Fracture Critical Members
o Consider additional loading on existing substructureo IDOT BCR Procedures Abbreviated Analysis (for “Good” condition, <115% DL) Detailed Analysis (for other cases)
Rehabilitation of Division Street Bridge 36
2014 Phase II
5/13/2016
13
37
Scope:• Reduce Fracture Critical Members
o Consider additional loading on existing substructureo IDOT BCR Procedures Abbreviated Analysis (“Good” condition, 115% DL) Detailed Analysis
Rehabilitation of Division Street Bridge 37
2014 Phase II
38
Scope:• Reduce Fracture Critical Members
o Consider additional loading on existing substructureo IDOT BCR Procedures Abbreviated Analysis (“Good” condition, 115% DL) Detailed Analysis
Rehabilitation of Division Street Bridge 38
2014 Phase II
30 Ton Plans Pile Capacity x (1.36)= 40.8 Tons for Rehab Design
39
Scope:• Screed analysis
o Goals No negative/excessive fillets
o Challenges No camber diagrams in plans Variable existing deck thickness
Rehabilitation of Division Street Bridge 39
2014 Phase II
5/13/2016
14
40
Scope:• Screed analysis
o Solution Deck survey at stringers NDT for deck thickness Combine for stringer
profile STAAD model Existing w/ old deck Existing w/o deck Existing w/ new deck
Determine camber anddeflection
Rehabilitation of Division Street Bridge 40
2014 Phase II
Average Existing Deck Thickness = 7.31”
41
Scope:• Maintain water main service
o Goal 8 hour outage maximum
o Challenges Water main is attached to deck Existing deck will be removed!
Rehabilitation of Division Street Bridge 41
2014 Phase II
42
Scope:• Maintain water main service
o Solution Temporary water main
Rehabilitation of Division Street Bridge 42
2014 Phase II
5/13/2016
15
43
NBIS inspection reports on the evening news…
Rehabilitation of Division Street Bridge 43
“Breaking” News
44
Blue Island Bridges get media attention after Ashland also closed
Rehabilitation of Division Street Bridge 44
“Breaking” News
“A bridge problem in Blue Island has residents fuming, the state of Illinois scrambling and a new mayor dealing with a transportation nightmare” – abc7chicago 3/27/2014
45
Lots of progress….
FUNDING SECURED per May 2014 IMBP letter!
Phase II P, S & E SUBMITTED in January 2015
Project FAST-TRACKED to June 2015 Letting
Rehabilitation of Division Street Bridge 45
Quest for Rehabilitation Funding
5/13/2016
16
46
Lots of progress….
FUNDING SECURED per May 2014 IMBP letter!
Phase II P, S & E SUBMITTED in January 2015
Project FAST-TRACKED to June 2015 Letting
Rehabilitation of Division Street Bridge 46
Quest for Rehabilitation Funding
47
Construction begins in September 2015• Phase III Engineer – Lochner• Phase III Contractor – Kenny Construction
Rehabilitation of Division Street Bridge 47
2015-2016 Phase III
48Rehabilitation of Division Street Bridge 48
2015-2016 Phase III
5/13/2016
17
49Rehabilitation of Division Street Bridge 49
2015-2016 Phase III
50Rehabilitation of Division Street Bridge 50
2015-2016 Phase III
51Rehabilitation of Division Street Bridge 51
2015-2016 Phase IIITruss chord web repair – 5 Contract Plan locations
5/13/2016
18
52
Additional defects found after deck removal…
Rehabilitation of Division Street Bridge 52
2015-2016 Phase III
Truss chord web repair – 5 Change Order locations
53
Additional defects found after deck removal…
Rehabilitation of Division Street Bridge 53
2015-2016 Phase III
FB stiffener repair – 5 Change Order locations
54
Additional defects found after deck removal…
Rehabilitation of Division Street Bridge 54
2015-2016 Phase III
FB tension rod replace – 14 Change Order locations
5/13/2016
19
55
Additional defects caused by deck removal…
Rehabilitation of Division Street Bridge 55
2015-2016 Phase III
56
Additional defects caused by deck removal…
Rehabilitation of Division Street Bridge 56
2015-2016 Phase III
57
Additional defects caused by deck removal…
Rehabilitation of Division Street Bridge 57
2015-2016 Phase III
5/13/2016
20
58Rehabilitation of Division Street Bridge 58
2015-2016 Phase III
59Rehabilitation of Division Street Bridge 59
2015-2016 Phase III
60Rehabilitation of Division Street Bridge 60
2015-2016 Phase III
5/13/2016
21
61Rehabilitation of Division Street Bridge 61
2015-2016 Phase III
62Rehabilitation of Division Street Bridge 62
2015-2016 Phase III
Division Street Bridge
Structural Engineers Association of Illinois13th Annual Midwest Bridge SymposiumApril 28, 2016
Anticipated open to traffic July 2016
5/13/2016
22
THANK YOU!!!QUESTIONS???