8310 irr sheet 21 nov 12

Upload: kbmit

Post on 02-Jun-2018

236 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    1/95

    Cells that do not contain any formula, but the correct valu

    Cells that contain the actual formula, but equal zero as co

    No content, due to confidentiality

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    2/95

    e itself (since the formula draws on confidential input data)

    nfidential input data were eliminated.

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    3/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    4/95

    Item Value

    Number of WTG of type Vestas V112 82

    Ratedcapacity per turbine of type Vestas V112 3.08

    Total capacity of wind farm 252.15

    Plant load factor (PLF) 33.91%

    Hours per year 8760

    Estimated gross electricity generation 904,237.00

    Estimated electricity generation (P70_10-year correlatedvalue)

    749,079.00

    Planned construction start 1/1/2014

    Planned operation start 1/1/2015

    Percentage of operational time in first year 100%

    Percentage of operational time in last year 100%

    Operational life time 20

    WTG Type Vestas V112 (3 MW)

    Sum -

    Surveys and tests

    Construction facilities

    Foundations

    Crane pads

    Roads

    CAPEX (Capital Expenditures)

    Wind Turbine Generators (WTGs)

    Civil works

    Technical details

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    5/95

    VAT amount -Sum Civil Works (excluding taxes) -

    Sum Civil Works -

    Grid connection cost (Transmission Line 115 kV)

    Main substation

    Collector substations

    CFE substation (Zacatecas II)Internal electrical distribution and communicationsystemVAT amount -

    Sum Electrical Works (excluding taxes) -

    Sum Electrical Works -

    Total Investment Costs excluding taxes 460,815,358.59

    Total Investment Costs including taxes 475,505,815.97

    Service Contract (excluding taxes)Operational Management (excluding taxes)

    Insurance: Property damage,production loss and liability(excluding taxes)

    0.50%

    Landscaping (excluding taxes)

    LLA Rent fixed (excluding taxes)Time LLA rent has to be paid per yearNumber of land owner

    LLA Rent variable

    CFE transmission Fee 143.95

    Average annual OPEX 31,611,511.01

    Electrical works

    Total Investment Costs

    OPEX (Operational Expenditures)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    6/95

    Up-Front Fee

    Equity rate

    Equity amount

    Debt rate

    Debt amount

    Total financing period 16

    TIIE 28 (variable) (Interbank offered lending rate) 11.54%

    Cost of funding (IPAB)

    Financing margin during construction

    Financing margin year 1 to 3

    Financing margin year 3 to 6

    Financing margin year 7 to 9

    Financing margin last year 10 onwards

    Comittment fee

    Depreciation rate for movable goods 100%

    Interest rates:

    Financing parameters

    Depreciation

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    7/95

    Depreciation base for movable goods -

    Depreciation rate for Civil Works 5%

    Depreciation base for Civil Works -

    Depreciation rate for Electrical Works 5%

    Depreciation base for Electrical Works -

    Depreciation period 20

    Book value in the final year -

    Costs for deconstruction -

    Income from realization of assets -

    Costs for realization of assets -

    Fair value in the final year -

    VAT rate 16.00%

    Taxes

    Fair value

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    8/95

    Income tax rate from 2014 onwards 28.00%

    IETU (Corporate tax standard rate) 17.50%

    Exchange rate: 1 Euro in US$ 1.30

    Exchange rate: 1 Mexican Peso in US$ 0.08

    Inflation rate - Euro 2.07%

    Inflation rate - MXN Pesos 3.55%

    Inflation rate - MXN Pesos (for CFE transmission feeonly)

    4.04%

    Inflation rate - US-Dollar 2.38%

    Exchange rates

    PPA Price Calculation

    Inflation

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    9/95

    PPA price (2011) 1213.35

    PPA price (2011) in US$ 92.38

    Benchmark in Mexico (real terms) 11.20%

    Expected Inflation Rate - Mexico 3.00%

    Benchmark in Mexico (nominal terms) 14.20%

    Benchmark

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    10/95

    Unit

    units

    MW per WTG

    MW

    %

    hours

    MWh / year

    MWh / year

    %

    %

    years

    US$ per unit

    US$ for all units

    MXN

    MXN

    MXN

    MXN

    MXN

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    11/95

    MXNUS$

    US$

    USD

    US$

    US$

    US$

    US$

    US$US$

    US$

    US$

    US$

    Euro / year% of gross energy revenues/ year

    % of net annual revenues

    Euro / year

    MXN / MW / yeartimes

    % of semestral gross energy revenues

    MXN / MWh

    US$ / year

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    12/95

    %

    %

    US$

    %

    US$

    years

    % per year

    % per year

    % per year

    % per year

    % per year

    % per year

    % per year

    % per year of remaining debt

    % / year

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    13/95

    US$

    % / year

    US$

    % / year

    US$

    years

    US$

    US$

    US$

    US$

    US$

    %

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    14/95

    % on net incomes

    % on EBITDA

    US$

    US$

    %

    % p.a.

    % p.a.

    %

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    15/95

    MXN/MWh

    US$/MWh

    %

    %

    %

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    16/95

    Reference

    Please see annual energy production calculation:20120213_Mezquite_AEP_P75_82xV112_3MW_HH84.pdf , p. 1),stored under:download\20120604_ME083_Mezquite_Validation documents\5. Technology

    Please see: 20110428_Type Certificate_V112 3.0MW_0016-9941.pdf , p.2 , stored under:download\20120604_ME083_Mezquite_Validation documents\5. Technology

    calculated.

    Calculated.

    Please see third party expertise: 20120706_ME083_Windfarm Expertise_Mezquite.pdf , p. 4),storedunder: download\20120604_ME083_Mezquite_Validation documents\Validation 2\5. Technology

    Please see third party expertise: 20120706_ME083_Windfarm Expertise_Mezquite.pdf , p. 4),storedunder: download\20120604_ME083_Mezquite_Validation documents\Validation 2\5. Technology

    Please see "Planned operation start" (above) and "Operational life time" (below).

    Please see "Planned operation start" (above) and "Operational life time" (below).

    Please see: 20110428_Type Certificate_V112 3.0MW_0016-9941.pdf ,stored under:download\20120604_ME083_Mezquite_Validation documents\5. Technology

    calculated.

    Key assumptions & input data

    Equity IRR Calculation - Mezquite

    Please see calculation: 20120522_ME083_BOQ_Civil_Works_Rev01.xlsPlease see reference: 20111104_ConsultantEmail_CivilWorks_prices.msg;20111025_Consultant_Engineering_UnitPrices.xls ; storedunder:download\20120604_ME083_Mezquite_Validation documents\4. Investment Analysis\CAPEX

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    17/95

    calculated.calculated.

    calculated.

    calculated.calculated.

    calculated.

    calculated.

    calculated.

    Please see indication provided by consultant: 20120604_Insurance cost indication_consultant.msg;stored under: download\20120604_ME083_Mezquite_Validation documents\4. InvestmentAnalysis\OPEX

    Please see: 20070919_Contract_Landscaping.pdf, storedunder:download\20120604_ME083_Mezquite_Validation documents\4. Investment Analysis\OPEX

    Please see: 20120518_Cargos por Servicios Transmission 2011_CRE.pdf, available under:http://www.cre.gob.mx/articulo.aspx?id=171, stored under:download\20120604_ME083_Mezquite_Validation documents\4. Investment Analysis\OPEXPlease see also: 20100416_RES_CRE_CARGOS SERVICIOS DE TRANSMISION.pdf, p.5 (availableunder: http://www.sener.gob.mx/res/Acerca_de/RES_-066-2010_CARGOS%20SERVICIOS%20DE%20TRANSMISION_16-04-2010.pdf) ; stored under:download\20120604 ME083 Mez uite Validation documents\4. Investment Anal sis\OPEXPlease see calculation in sheet "Equity IRR calculation".

    Please see calculation: 20120503_ME083_BOQ_82x3.0MW.xlsPlease see reference: 20111201_ConsultantEmail_ElectricalWorks_prices.msg;20111025_Consultant_Engineering_UnitPrices.xls ; stored under:download\20120604_ME083_Mezquite_Validation documents\4. Investment Analysis\CAPEX

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    18/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    19/95

    calculated.

    Please see: 20101231_LEY DEL IMPUESTO SOBRE LA RENTA.pdf, Artclo 40 I.b) (p.51),available under: http://www.diputados.gob.mx/LeyesBiblio/pdf/82.pdf,stored under:download\20120604_ME083_Mezquite_Validation documents\1. Laws & Licenses

    calculated.

    Please see: 20101231_LEY DEL IMPUESTO SOBRE LA RENTA.pdf, Artclo 40 I.b) (p.51),available under: http://www.diputados.gob.mx/LeyesBiblio/pdf/82.pdf,stored under:download\20120604_ME083_Mezquite_Validation documents\1. Laws & Licenses

    calculated.

    Please see:20110428_Type Certificate_V112 3.0MW_0016-9941.pdf, stored under:download\20120604_ME083_Mezquite_Validation documents\5. Technology

    calculated.

    Costs not taken into consideration due to conservative approach of analysis.

    Please see: 20100428_Contrato de Interconexin ER y Cogeneracin_CRE.pdf, SEPTIMA, storedunder: download\20120604_ME083_Mezquite_Validation documents\1. Laws & Licenses

    Costs not taken into consideration due to conservative approach of analysis.

    calculated.

    Please see:20091207_Ley del IVA.pdf, available under:http://www.diputados.gob.mx/LeyesBiblio/pdf/77.pdf,stored under:download\20120604_ME083_Mezquite_Validation documents\1. Laws & Licenses

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    20/95

    20101231_LEY DEL IMPUESTO SOBRE LA RENTA.pdf, T TULO II Artculo 10, p.10, availableunder: http://www.diputados.gob.mx/LeyesBiblio/pdf/82.pdf,stored under:download\20120604_ME083_Mezquite_Validation documents\1. Laws & Licenses

    Please see: 20071001_Ley del Impuesto Empresarial a Tasa Unica IETU.pdf , CAPITULO III,available under: http://www.diputados.gob.mx/LeyesBiblio/pdf/LIETU.pdf,stored under:download\20120604_ME083_Mezquite_Validation documents\1. Laws & Licenses

    Please see: European Central Bank:http://sdw.ecb.europa.eu/browseTable.do?type=&node=2018794&CURRENCY=USD&sfl1=4&SERIES_KEY=120.EXR.D.USD.EUR.SP00.A&DATASET=0&sfl3=4&start=01-01-2012&end=01-04-2012&submitOptions.x=41&submitOptions.y=4&trans=N&vf=&q=&type= ; Please select daily rates,Data table, Data ran e, to download data

    Please see: http://www.banxico.org.mx/portal-mercado-cambiario/index.html ; Please select USDexchange rate and the interval and calculate the average value of the column "Para Pagos"/"Para

    solventar obligaciones").

    Please see:http://epp.eurostat.ec.europa.eu/tgm/table.do?tab=table&language=de&pcode=tsieb060&tableSelection=1&footnotes=yes&labeling=labels&plugin=1

    National Consumper Price Index, (INPC - Indice Nacional de Precios al Consumidor):20120418_INPC_1997-2011_Banxico.xls. Please see:http://www.banxico.org.mx/SieInternet/consultarDirectorioInternetAction.do?accion=consultarCuadro&idCuadro=CP154&sector=8&locale=es(Select INPC, period and "inflacion accumulada anual")National Producer Price Index (INPP = Indice Nacional de Precios Productor): 20120418_INPP_1997-2011_Banxico.xls. Please see:http://www.banxico.org.mx/SieInternet/consultarDirectorioInternetAction.do?accion=consultarCuadro&idCuadro=CP154&sector=8&locale=esSelect INPP, eriod and "inflacion accumulada anual"

    Please see: ftp://ftp.bls.gov/pub/special.requests/cpi/cpiai.txt

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    21/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    22/95

    Remarks

    The wind farm design of the project activity considers 82 WTGs. The turbine type most likely to be installed is the Vestas V1123MW, representing the economically most attractive option at the time of PDD submission.

    The nominal capacity of the Vestas V112 is 3.00 MW. However, at wind speeds over 12 m/s, its rated power exceeds the nominalcapacity and achieves up to 3.075 MW. For the calculation of the energy production of the turbines and of the whole wind farm,the internal calculations took the actual power curve with values up to 3.075 MW and applied appropriate losses.Please see explanation above concerning the nominal capacity of the GE100 1.6MW.According to Annex 11, GUIDELINES FOR THE REPORTING AND VALIDATION OF PLANT LOAD FACTORS (Version

    01), the Plant Load Factor was calculated following option II.3.(b): "The plant load factor determined by a third party contractedby the project participants." The PLF can be calculated based on the net electricity generation (gross energy production minusappropriate estimated losses) and uncertainty reductions (for P70 value) and the installed capacity of the wind farm of 160.4 MW.

    Since investors and financiers regularly require an acceptable level of uncertainty for the estimated value for electricitygeneration, the P70 long-term correlated value was considered within the calculation. Please note that several losses wereconsidered (e.g. electrical losses) which is a confirmation for a realistic NET electricity generation. In order to reach an even

    The operation start of the wind farm is planned for January 2015 and the operational life time of the project is twenty years.

    The operation start of the wind farm is planned for January 2015 and the operational life time of the project is twenty years.

    The assessed design life time of a WTG published by the manufacturer and defined for the V112 is 20 years.

    Please note that according to the indicative offer, and in juxtaposition to the costs for civil and electrical works, WTG prices arevalid if delivery occurs within 2013 and no inflation adjustment has been made.

    Civil works prices are based on prices per unit in MXN pesos, obtained by a contracted independent consultant (see:20111104_ConsultantEmail_CivilWorks_prices.msg; 20111025_Consultant_Engineering_UnitPrices.xls) and are calculatedaccording to the expected amounts required for the realization of the project activity (see calculation:20120522_ME083_BOQ_Civil_Works_Rev01.xls; The categorization used for the equity IRR calculation is indicated in lightblue in column "G").

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    23/95

    prices do not include VAT.

    Please note that the costs of civil works are based on unit prices provided by a consultant end of 2011. To reflect appropriatelyany currency and price developments over time and especially to be comparable to other cost and revenue items included in thiscalculation, the total cost for civil works will be adated to inflation until the expected contract signature for such works. This isassumed to be on 31/08/2013 (equal WTG supply contract signature) and thus an inflation adjustment is to be made in thefollowing spreadsheets (adjustment for 1 year to maintain a conservative approach). Since no payment conditions are defined atthe time being, the most conservative approach (payment at the time of contract signature) has been considered to determine the

    prices do not include VAT.

    Please note that the costs of electrical works are based on unit prices provided by a consultant end of 2011. To reflect

    appropriately any currency and price developments over time and especially to be comparable to other cost and revenue itemsincluded in this calculation, the total cost for electrical works will be adated to inflation until the expected contract signature forsuch works. This is assumed to be on 31/08/2013 (equal WTG supply contract signature) and thus an inflation adjustment is to bemade in the following spreadsheets (adjustment for 1 year to maintain a conservative approach). Since no payment conditions aredefined at the time being, the most conservative approach (payment at the time of contract signature) has been considered to

    According to an independent consultant, the typical range for insurance costs to be considered is 0.5-1.5% of annual forecastedrevenue based on net electricity generation. Following a conservative approach, the least cost for the project activity (0.5% ofannual revenues) is assumed for insurance costs. Since the forecasted revenues do not include VAT, the costs for insurance are

    The transmission fees are defined by the grid operator CFE for each project. Since the exact value is unknown at the time of PDDsubmission, the general legal basis has been selected as a reference value. Since electricity generation is regularly transmitted athigh voltage levels in order to reduce transmission losses and as end-customers typically receive low-voltage electricity, a realisticscenario is to consider all voltage levels: High voltage + medium voltage + low voltage. The fees were initially defined in theresolution of the Energy Secretary SENER published in the "Diario Oficial" (see reference on the left) and adapted to inflationannually. The latest available annual average transmission fees (2011) are published by the Energy Regulation Comission CRE

    lease see s readsheet: CFE fees . Therefore, all values defined for 2011 are inflation ad usted for 2 ears until the investment

    Electrical works prices are based on prices per unit in US$ obtained by a contracted independent consultant (see:20111201_ConsultantEmail_ElectricalWorks_prices.msg; 20111025_Consultant_Engineering_UnitPrices.xls) and are calculatedaccording to the expected amounts required for the realization of the project activity (see calculation:20120503_ME083_BOQ_82x3.0MW.xls; The categorization used for the equity IRR calculation is indicated in light blue incolumn "G").

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    24/95

    Please note that the upfront fee is payable on the actual total debt amount (see reference on the left), i.e. on debt portion of totalinvestment costs accrueing in the construction year (2014). To reflect appropriately currency and price developments over timeand especially to be comparable to other cost and revenue items included in this calculations, the total fee on the left, will bebased on investment cost (partially) adapted to inflation until 31/08/2013 (please see remarks on the items: "Sum WTGs", "SumCivil works" and "Sum Electrical works"). Please note that the Mexican inflation rate is to be considered since the loan conditions

    According to the Ley de Impuesto Sobre la Renta (Article 40, XII.), machinery and equipment (working assets) for renewableenergy projects may be depreciated 100% within a year, whenever the project's operation continues at least five years afterwards.Alternatively, machinery and equipment may be depreciated 5% annually (Article 41, I.). From a tax perpective, the mostattractive depreciation option is to write off 100% within the first year (construction year), which is when mayor investment costs

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    25/95

    The depreciation base is the original investment cost (WTG price in this case), including taxes actually paid except VAT. Source:20101231_LEY DEL IMPUESTO SOBRE LA RENTA.pdf, Artclo 37 (p.49), available under:http://www.diputados.gob.mx/LeyesBiblio/pdf/82.pdf,stored under: download\20120604_ME083_Mezquite_Validation

    5% is the maximum depreciation rate applicable for construction works (fixed assets).

    The depreciation base is the original investment cost (civil works in this case), including taxes actually paid except VAT. Source:20101231_LEY DEL IMPUESTO SOBRE LA RENTA.pdf, Artclo 37 (p.49), available under:

    http://www.diputados.gob.mx/LeyesBiblio/pdf/82.pdf,stored under: download\20120604_ME083_Mezquite_Validation

    5% is the maximum depreciation rate applicable for construction works (fixed assets).

    The depreciation base is the original investment cost (electrical works in this case), including taxes actually paid except VAT.Source: 20101231_LEY DEL IMPUESTO SOBRE LA RENTA.pdf, Artclo 37 (p.49), available under:http://www.diputados.gob.mx/LeyesBiblio/pdf/82.pdf,stored under: download\20120604_ME083_Mezquite_ValidationThe depreciation period is 20 years as the project activity has a lifetime of 20 years based on the design lifetime of the turbines,defined in the V112_3MW type certificate.

    The book value in the final year corresponds to the sum of the depreciation base for movable and immovable goods that are notdepreciated at the end of the operational life time of the wind farm. As movable goods are depreciated with a rate of 5% per yearduring 20 years of operational life time, summing up to 100% during 20 years, the book value of the movable goods equals zero.According to the Environmental Impact Assessment (Manifestacin de Impacto Ambiental_Parque Elico Dominica, Cap.II,p.47, available under: http://sinat.semarnat.gob.mx/dgiraDocs/documentos/slp/estudios/2011/24SL2011E0005.pdf) , the projectowner is obliged to completely dismantle all project assets at the end of the project life time. The life time of the project activity is20 years as the technical life time of the turbines is limited to 20 years (see remark and reference under "Depreciation period").This dismantling will enhance high costs such as for the machinery and work force for the deconstruction of the wind turbinesand the infrastructure, its transportation and proper waste disposal. However, these costs are difficult to estimate. Therefore andThe possible income from a realization of the assets is very limited and impossible to predict: Firstly, according to theInterconnection Contract draft to be signed with CFE, the project owner is obliged to donate the the entire transmission line andelectrical infrastructure for the grid connection to CFE (see reference on the left) .Secondly, any roads constructed or improved aspart of the civil works related to the project are designed as a property for the landowners, which is only in possession of the

    project developer during the validity of the land lease agreement (see reference under "LLA Rent", Clause: NOVENA, b)). Thus,no income can be derived out of any possibly remaining value of the assets through a deconstruction and extraction of rawmaterials. As for the fair value of an remainin infrastructure works, the rice for the materials mainl co er and steel that,for proper isolation of copper from the cable coatings and the costs for transportation to possible place of sale (as the project islocated at a long distance from other industry installation or big cities with potential purchasers.) However, these costs aredifficult to estimate. Therefore and due to the conservative approach of this analysis, the costs for the realization of the assets

    The fair value in the final year is assumed to equal zero. This assumption can still be considered as a conservative because of thefollowing reasons: 1. The high costs for deconstruction accruing to the project owner are not taken into consideration. 2. Thecosts of the potential realization of the assets are not taken into consideration. 3. As explained above, no income from therealization of assets is to be considered. Furthermore, it is not considered that large part of the assets cannot be sold after 20years, but will have to be deposited or recycled without producing income. 4. The fair value in the final year is considered as netcash inflow after taxes, without taken into account that taxes would have to be paid on this income, which would reduce the

    income and thus the IRR.

    According to the Value Added Tax law (Ley del Impuesto al Valor Agregado), the VAT in Mexico is 16%.

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    26/95

    According to the Mexican tax law (Ley del Impuesto Sobre la Renta), the applicable Mexican income tax rate for 2010-2012 is30% (p.333), for 2013 29% (p.334) and from 2014 onwards is defined to be 28% (p.10).

    According to the law of the single rate business tax (Impuesto Empresarial a Tasa Unica - IETU), every business located inMexico is obliged to pay taxes as per the IETU tax rate, if this tax burden exceeds the conventional income tax burden which iscalculated based on net profits. The IETU is calculated based on earnings deducted by expenses, but before interests, depreciationand loan repayments (EBITDA), whereas the conventional income tax is calculated based on net profits. If in a fiscal year, theIETU is to paid by the company, the total tax burden is calculated as follows: (Tax burden with income tax - Tax burden with

    As exchange rate, the average of the daily exchange rates between January 1st, 2012 and June 3th, 2012 were taken. This datavintage was chosen in order to have a middle-term average to balance the influence of the exchange rate fluctuation on theanalysis. January 1st, 2012 was chosen in order to have an average for the year 2012, obtaining thus an average exchange ratevalid and realistic at the time of validation. June 3th, 2012 was chosen as the PDD was handed in on June 4th, 2012 and on theda of handin in the PDD, the investment decision had not been taken et. Please also refer to the timetable rovided in Section

    s exc ange ra e, e average o e a y exc ange ra es e ween anuary s , an une , were a en. s a avintage was chosen in order to have a middle-term average to balance the influence of the exchange rate fluctuation on theanalysis. January 1st, 2012 was chosen in order to have an average for the year 2012, obtaining thus an average exchange ratevalid and realistic at the time of validation. June 3th, 2012 was chosen as the PDD was handed in on June 4th, 2012 and on the

    day of handing in the PDD, the investment decision had not been taken yet. (Please also refer to the timetable provided in Section

    Eurostat, the statistical office of the EU. The only contract that is subject to inflation that will be concluded in Euro as currency isthe Service Contract. Euro inflation data is only available since 1997 (see link on the left). Therefore, the data vintage for thefollowing parameters was chosen to be 14 years in order to always use the same data vintage in the present calculation:Interbanking lending rates (TIIE28-days), Euro inflation rate, MXN inflation rate (INPC) and US$ inflation rate (CPI).

    The data vintage chosen to estimate the inflation rate development is 14 years, in order to represent a comparable time series to

    the one applied for Euro inflation rates (1997- 2011).

    The CFE transmission fees will be inflation adapted with the Produce Price Index published by the Mexican Central Bank, asdefined in the document: 20100428_Anexo TB-RC_Inflation Adaptation Factor.pdf (available under:http://www.cre.gob.mx/documento/1757.pdf). The data vintage chosen to estimate the inflation rate development is 14 years, inorder to represent a comparable time series to the one applied for Euro inflation rates (1997- 2011).

    The data vintage chosen to estimate the inflation rate development is 14 years, in order to represent a comparable time series tothe one applied for Euro inflation rates (1997- 2011). Values considered are the yearly average inflation rates of the ConsumerPrice Index of the USA, published by the U.S. Department Of Labor, Bureau of Labor Statistics. Even though the priceindications of the different items of the OPEX are partly indicated in Euro (due to the fact that the contracts used as references arein Euro the contracts for the Mez uite Wind Farm that are sub ect to inflation will be - exce t the Service Contract - concluded

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    27/95

    nce at t e t me o su m ss on no se -supp y customer a een se ecte yet, nor a any ower urc ase greement(PPA) for self-supply purposes been signed and market data for realistic electricity prices under this scheme and in the region ofthe project activity are not publicly available, the average electricity price published by the Energy Secretary (SENER) has beenanalyzed. However, the project will operate under the self supply scheme ("autoabastecimiento") and electricity customers willonly opt for this scheme if a lower price is offered, i.e. electricity costs for them are reduced. Therefore a discount rate on theseaverage electricity prices needs to be considered. According to the interconnection contract for the self-supply scheme, in case ofany electricity generation surplus from the project activity, the grid operator (CFE) is obliged to purchase such electricity excessat 85% of the short term marginal cost ("Costo Total de Corto Plazp - CTCP") incurred in the respective region and period of

    time (see: 20100428_Contrato de Interconexin ER y Cogeneracin_CRE.pdf, DECIMA QUINTA XV.3, p.10). As the CTCPvaries considerably between regions, seasons and day-times and a final PPA customer is no yet defined, the average electricityprice published by SENER has been considered instead of a very specific and potentially unrealistic CTCP. This assumption(average electricity prices x 85% instead of 85% x CTCP) reflects the upper limit for achievable PPA prices, since the averageelectricit rices are end- customer rices and the CTCP reflects the urchasin rice for enerated electricit at a certain timesee above

    According to the tool (see link on the left, p. 7), the applicable value for energy industries - such as wind power - is the value forGroup 1 . For Mexico, this value is 11.20%.

    According to the Guidelines on the Assessment of Investment Analysis (Version 05, p. 8), "in situations where an investmentanalysis is carried out in nominal terms, project participants can convert the real term values provided [] to nominal values

    by adding the inflation rate.The inflation rate shall be obtained from the inflation forecast of the central bank of the host country

    for the duration of the crediting period. If this information is not available, the target inflation rate of the central bank shall be

    used. If this is also not available, then the average forecasted inflation rate for the host country published by the IMF [...] of the

    World Bank for the next five years after the start of the project activity shall be used."The Mexican central bank has conductedan inquiry amongst economy specialists on their expectations on the inflation rate development amongst others. Since the startdate of the crediting period is 01/01/2015 (or the date of CDM registration, whichever latest), the applicable vintage to estimatethe Mexican Inflation Rate first creditin eriod is 2015 - 2022. This data vinta e is sli htl lon er than the in uir which onl

    Real term benchmark of Mexico adapted by inflation rate = Nominal term benchmark.

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    28/95

    Item Value

    Benchmark in Mexico (nominal terms) 14.20%

    Equity IRR 3.65%

    Sensitivity analysis:

    Energy output +10% 6.61%

    PPA price +10% 6.61%

    CAPEX -10% 6.10%

    OPEX -10% 4.54%

    Equi

    3.

    0%

    1%

    2%

    3%

    4%

    5%

    6%

    7%

    8%

    9%

    10%11%

    12%

    13%

    14%

    15%

    16%

    17%

    EquityIRR(in%)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    29/95

    Reference

    Please see calculation under "Benchmark" on the excel sheet "Key assumptions" of this document.

    Please see excel sheet "Equity IRR Calculation" of this document.

    Please see the calculation in the excel sheet "Energy output +10%" of this document.

    Please see the calculation in the excel sheet "PPA price +10%" of this document.

    Please see the calculation in the excel sheet "CAPEX -10%" of this document.

    Please see the calculation in the excel sheet "OPEX -10%" of this document.

    Results

    ty IRR

    5%

    nergy output +10%

    6.61%PPA price +10%

    6.61% CAPEX -10%

    6.10%OPEX -10%

    4.54%

    Equity IRR

    Energy output +1

    PPA price +10%

    CAPEX -10%

    OPEX -10%

    Benchmark =

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    30/95

    Remarks

    Calculated based on the following tool: UNFCCC (2011): Annex 5 Guidelines on the Assessment of InvestmentAnalysis (Version 05), source: http://cdm.unfccc.int/Reference/Guidclarif/reg/reg_guid03.pdf.

    Calculated based on the profit after taxes of the Mezquite Wind Farm.

    For this calculation, the energy output has been increased by 10%. The adapted values are marked in yellow in theexcel sheet "Energy output +10%".

    For this calculation, the PPA price has been increased by 10%. The adapted values are marked in yellow in the excelsheet "PPA price +10%".

    For this calculation, the capital expenditures (CAPEX) have been reduced by 10%.

    For this calculation, the operational expenditures (OPEX) have been reduced by 10%.

    0%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    31/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    32/95

    Unit 2013

    Project life (including construction) 0

    PPA price US$ / MWh

    Energy Output MWh

    Revenues from PPA US$

    Fair value in the final year US$

    CAPEX (Capital Expenditures)Wind Turbine Generators (WTGs) US$

    Civil works US$

    VAT on civil works US$

    Electrical works US$

    VAT on electrical works US$Effective upfront fee (2.5%) US$

    Total CAPEX, inflation adapt., excl. VAT US$

    OPEX (Operational Expenditures)Service Contract (excluding taxes) US$

    Operational Management (excluding taxes) US$

    Insurance: Property damage,production loss and liability

    (excluding taxes)US$

    Landscaping (excluding taxes) US$

    LLA Rent fixed (excluding taxes) US$

    LLA Rent variable US$

    CFE transmission Fee US$

    Total, adapted to inflation US$VAT US$

    Total OPEX,inflation adapt., excl. VAT US$

    EBITDAPrincipal repayment US$

    Financing costs (interes + comittment fee) US$

    EBTDA (earnings before taxes, depreciation andamortization), after debt service

    US$

    Depreciation US$IETU (Corporate tax standard rate) %

    Taxes as per IETU US$

    Income tax rate from 2014 onwards %

    Taxes as per Income tax US$

    Applicable tax rate %

    Total TAX burden US$

    Profit after taxes US$

    PPA price calculation

    Cash flow in

    Cash flow out

    Financing

    Tax

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    33/95

    2014 2015 2016 2017

    1 2 3 4

    102.59 106.23 110.01 113.92

    749,079.00 749,079.00 749,079.00

    79,578,199.57 82,406,459.20 85,335,236.98

    -

    -

    -

    -

    --

    -

    - - -

    - - -

    (397,891.00) (412,032.30) (426,676.18)

    - - -

    - - -

    - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (23,403,007.77) (24,104,838.16) (24,829,775.38)(2,170,212.20) (2,183,399.87) (2,197,056.24)

    (23,403,007.77) (24,104,838.16) (24,829,775.38)

    (141,642,841.02) 56,175,191.79 58,301,621.04 60,505,461.60

    - - - -

    - - - -

    (199,069,094.22) (1,920,892.32) 205,536.93 2,409,377.49

    (373,590,767.93) (4,590,767.93) (4,590,767.93)17.50% 17.50% 17.50% 17.50%

    - (9,830,658.56) (10,202,783.68) (10,588,455.78)

    28.00% 28.00% 28.00% 28.00%

    - - (703,805.60) (1,638,425.78)

    28.00% 17.50% 17.50% 17.50%

    - (9,830,658.56) (10,202,783.68) (10,588,455.78)

    (199,069,094.22) (11,751,550.88) (9,997,246.76) (8,179,078.29)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    34/95

    2018 2019 2020 2021

    5 6 7 8

    117.97 122.16 126.50 131.00

    749,079.00 749,079.00 749,079.00 749,079.00

    88,368,105.38 91,508,763.84 94,761,043.29 98,128,910.82

    - - - -

    - - - -

    (441,840.53) (457,543.82) (473,805.22) (490,644.55)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (25,578,636.96) (26,352,270.80) (27,151,556.34) (27,977,405.72)(2,211,197.97) (2,225,842.30) (2,241,007.09) (2,256,710.86)

    (25,578,636.96) (26,352,270.80) (27,151,556.34) (27,977,405.72)

    62,789,468.42 65,156,493.04 67,609,486.96 70,151,505.10

    - - - -

    - - - -

    4,096,042.64 6,463,067.26 8,916,061.18 10,953,899.55

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)17.50% 17.50% 17.50% 17.50%

    (10,988,156.97) (11,402,386.28) (11,831,660.22) (12,276,513.39)

    28.00% 28.00% 28.00% 28.00%

    (2,440,137.36) (3,533,253.61) (4,722,261.72) (5,835,194.28)

    17.50% 17.50% 17.50% 17.50%

    (10,988,156.97) (11,402,386.28) (11,831,660.22) (12,276,513.39)

    (6,892,114.33) (4,939,319.02) (2,915,599.04) (1,322,613.84)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    35/95

    2022 2023 2024 2025

    9 10 11 12

    135.66 140.48 145.47 150.64

    749,079.00 749,079.00 749,079.00 749,079.00

    101,616,474.49 105,227,988.39 108,967,857.77 112,840,644.49

    - - - -

    - - - -

    (508,082.37) (526,139.94) (544,839.29) (564,203.22)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (28,830,765.10) (29,712,615.92) (30,623,976.24) (31,565,902.21)(2,272,972.75) (2,289,812.59) (2,307,250.93) (2,325,309.05)

    (28,830,765.10) (29,712,615.92) (30,623,976.24) (31,565,902.21)

    72,785,709.39 75,515,372.47 78,343,881.53 81,274,742.27

    - - - -

    - - - -

    13,588,103.85 16,317,766.93 18,759,766.18 21,690,626.92

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)17.50% 17.50% 17.50% 17.50%

    (12,737,499.14) (13,215,190.18) (13,710,179.27) (14,223,079.90)

    28.00% 28.00% 28.00% 28.00%

    (7,259,391.64) (8,826,623.18) (10,408,571.16) (12,336,390.72)

    17.50% 17.50% 17.50% 17.50%

    (12,737,499.14) (13,215,190.18) (13,710,179.27) (14,223,079.90)

    850,604.70 3,102,576.74 5,049,586.91 7,467,547.02

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    36/95

    2026 2027 2028 2029

    13 14 15 16

    155.99 161.54 167.28 173.22

    749,079.00 749,079.00 749,079.00 749,079.00

    116,851,072.50 121,004,033.66 125,304,593.69 129,757,998.35

    - - - -

    - - - -

    (584,255.36) (605,020.17) (626,522.97) (648,789.99)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (32,539,489.47) (33,545,874.70) (34,586,237.18) (35,661,800.44)(2,344,008.95) (2,363,373.47) (2,383,426.21) (2,404,191.65)

    (32,539,489.47) (33,545,874.70) (34,586,237.18) (35,661,800.44)

    84,311,583.02 87,458,158.96 90,718,356.51 94,096,197.91

    - - - -

    - - - -

    24,727,467.67 27,874,043.61 31,134,241.16 34,512,082.56

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)17.50% 17.50% 17.50% 17.50%

    (14,754,527.03) (15,305,177.82) (15,875,712.39) (16,466,834.63)

    28.00% 28.00% 28.00% 28.00%

    (14,484,196.19) (16,885,751.43) (19,580,479.93) (22,614,432.62)

    17.50% 28.00% 28.00% 28.00%

    (14,754,527.03) (16,885,751.43) (19,580,479.93) (22,614,432.62)

    9,972,940.64 10,988,292.18 11,553,761.23 11,897,649.93

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    37/95

    2030 2031 2032 2033

    17 18 19 20

    179.38 185.76 192.36 199.19

    749,079.00 749,079.00 749,079.00 749,079.00

    134,369,679.84 139,145,263.41 144,090,574.24 149,211,644.55

    - - - -

    - - - -

    (671,848.40) (695,726.32) (720,452.87) (746,058.22)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (36,773,833.99) (37,923,655.03) (39,112,630.34) (40,342,178.18)(2,425,695.09) (2,447,962.79) (2,471,021.89) (2,494,900.52)

    (36,773,833.99) (37,923,655.03) (39,112,630.34) (40,342,178.18)

    97,595,845.85 101,221,608.38 104,977,943.90 108,869,466.37

    - - - -

    - - - -

    97,595,845.85 101,221,608.38 104,977,943.90 108,869,466.37

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)17.50% 17.50% 17.50% 17.50%

    (17,079,273.02) (17,713,781.47) (18,371,140.18) (19,052,156.62)

    28.00% 28.00% 28.00% 28.00%

    (26,041,421.82) (27,056,635.33) (28,108,409.27) (29,198,035.56)

    28.00% 28.00% 28.00% 28.00%

    (26,041,421.82) (27,056,635.33) (28,108,409.27) (29,198,035.56)

    71,554,424.03 74,164,973.05 76,869,534.63 79,671,430.81

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    38/95

    2034

    21

    206.27

    749,079.00

    154,514,720.95

    -

    -

    (772,573.60)

    -

    -

    -

    (8,210,269.14)

    (41,613,770.27)(2,519,627.82)

    (41,613,770.27)

    112,900,950.68

    -

    -

    112,900,950.68

    (4,590,767.93)17.50%

    (19,757,666.37)

    28.00%

    (30,326,851.17)

    28.00%

    (30,326,851.17)

    82,574,099.51

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    39/95

    Construction Year

    Unit 0

    Period Start 1/1/2014

    Period End 1/1/2015

    Days per period 365

    Remaining repayment periods 16

    Balance at start of period US$ -

    Principal Repayments US$ -

    Balance at end of period US$ -

    Debt Fully Repaid? yes

    TIIE 28 days p.a. % per year 11.54%

    Cost of funding % per year 0.00%

    Financing margin % per year 0.00%Total interest rate % per year 11.54%

    Interests US$ -

    Comittment fee % per year 0.00%

    Comittment payment US$ -

    Total financing costs US$ -

    Annuity (P+I) US$ -

    Principle Repayment US$ -

    Debt Account

    Interests

    Repayment Method

    Financing

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    40/95

    Operational Year Operational Year Operational Year Operational Year

    1 2 3 4

    1/2/2015 1/3/2016 1/3/2017 1/4/2018

    1/2/2016 1/2/2017 1/3/2018 1/4/2019

    365 365 365 365

    15 14 13 12

    - - - -

    - - - -

    - - - -

    11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00%11.54% 11.54% 11.54% 11.54%

    - - - -

    0.00% 0.00% 0.00% 0.00%

    - - - -

    - - - -

    - - - -

    - - - -

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    41/95

    Operational Year Operational Year Operational Year Operational Year

    5 6 7 8

    1/5/2019 1/6/2020 1/6/2021 1/7/2022

    1/5/2020 1/5/2021 1/6/2022 1/7/2023

    365 365 365 365

    11 10 9 8

    - - - -

    - - - -

    - - - -

    11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00%11.54% 11.54% 11.54% 11.54%

    - - - -

    0.00% 0.00% 0.00% 0.00%

    - - - -

    - - - -

    - - - -

    - - - -

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    42/95

    Operational Year Operational Year Operational Year Operational Year

    9 10 11 12

    1/8/2023 1/9/2024 1/9/2025 1/10/2026

    1/8/2024 1/8/2025 1/9/2026 1/10/2027

    365 365 365 365

    7 6 5 4

    - - - -

    - - - -

    - - - -

    11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00%11.54% 11.54% 11.54% 11.54%

    - - - -

    0.00% 0.00% 0.00% 0.00%

    - - - -

    - - - -

    - - - -

    - - - -

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    43/95

    Operational Year Operational Year Operational Year Operational Year

    13 14 15 16

    1/11/2027 1/12/2028 1/12/2029 1/13/2030

    1/11/2028 1/11/2029 1/12/2030 1/13/2031

    365 365 365 365

    3 2 1 0

    - - - -

    - - - -

    - - - -

    11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00%11.54% 11.54% 11.54% 11.54%

    - - - -

    0.00% 0.00% 0.00% 0.00%

    - - - -

    - - - -

    - - -

    - - - -

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    44/95

    Construction Year Operational Year

    Unit 0 1

    Period Start 1/1/2014 1/2/2015

    Period End 1/1/2015 1/2/2016

    Days per period 365 365

    Remaining repayment periods 16 15

    Balance at start of period US$ - -

    Principal Repayments US$ - -

    Balance at end of period US$ - -

    Debt Fully Repaid? yes

    TIIE 28 days p.a. % per year 11.54% 11.54%

    Cost of funding % per year 0.00% 0.00%

    Financing margin % per year 0.00% 0.00%

    Total interest rate % per year 11.54% 11.54%

    Interests US$ - -

    Comittment fee % per year 0.00% 0.00%

    Comittment payment US$ - -

    Total financing costs US$ - -

    Annuity (P+I) US$ - -

    Principle Repayment US$ - -

    Note: This sheet has been included mer

    Financing

    Debt Account

    Interests

    Repayment Method

    Modification parameter:

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    45/95

    Operational Year Operational Year Operational Year Operational Year Operational Year

    2 3 4 5 6

    1/3/2016 1/3/2017 1/4/2018 1/5/2019 1/6/2020

    1/2/2017 1/3/2018 1/4/2019 1/5/2020 1/5/2021

    365 365 365 365 365

    14 13 12 11 10

    - - - - -

    - - - - -

    - - - - -

    11.54% 11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00% 0.00%

    11.54% 11.54% 11.54% 11.54% 11.54%

    - - - - -

    0.00% 0.00% 0.00% 0.00% 0.00%

    - - - - -

    - - - - -

    - - - - -

    - - - - -

    90%ly to calculate the financing costs if CAPEX is reduced by 10%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    46/95

    Operational Year Operational Year Operational Year Operational Year Operational Year

    7 8 9 10 11

    1/6/2021 1/7/2022 1/8/2023 1/9/2024 1/9/2025

    1/6/2022 1/7/2023 1/8/2024 1/8/2025 1/9/2026

    365 365 365 365 365

    9 8 7 6 5

    - - - - -

    - - - - -

    - - - - -

    11.54% 11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00% 0.00%

    11.54% 11.54% 11.54% 11.54% 11.54%

    - - - - -

    0.00% 0.00% 0.00% 0.00% 0.00%

    - - - - -

    - - - - -

    - - - - -

    - - - - -

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    47/95

    Operational Year Operational Year Operational Year Operational Year Operational Year

    12 13 14 15 16

    1/10/2026 1/11/2027 1/12/2028 1/12/2029 1/13/2030

    1/10/2027 1/11/2028 1/11/2029 1/12/2030 1/13/2031

    365 365 365 365 365

    4 3 2 1 0

    - - - - -

    - - - - -

    - - - - -

    11.54% 11.54% 11.54% 11.54% 11.54%

    0.00% 0.00% 0.00% 0.00% 0.00%

    0.00% 0.00% 0.00% 0.00% 0.00%

    11.54% 11.54% 11.54% 11.54% 11.54%

    - - - - -

    0.00% 0.00% 0.00% 0.00% 0.00%

    - - - - -

    - - - - -

    - - - -

    - - - - -

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    48/95

    Base value (2011): 1213.35 MXN/MWh

    Base value in US$ 92.38 US$/MWh

    MXN annual inflation rate: 3.55% 1997-2011

    (Sources: See "Key Assumptions" sheet)

    YEAR 2012 2013 2014 2015 2016 2017 2018

    PPA price in US$/MWh

    (inflation adjusted)95.67 99.07 102.59 106.23 110.01 113.92 117.97

    Average consumer electricity prices in Mexico, applying a 15% discount to estimate the

    PPA price (inflation adjusted):

    0

    50

    100

    150

    200

    250

    2012

    2013

    2014

    2015

    2016

    2017

    2018

    2019

    2020

    2021

    2022

    2023

    2024

    2025

    2026

    2027

    2028

    2029

    2030

    2031

    2032

    2033

    2034

    2035

    Expected PPA price in US$/MWh (inflation adjusted)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    49/95

    2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

    122.16 126.50 131.00 135.66 140.48 145.47 150.64 155.99 161.54 167.28 173.22 179.38

    Reference scenario published by CFE (POISE 2011-2025.pdf, p.1-7, figure 1Trading\CDM\SoWiTec trading - CDM Projects\Mexico\ME094_Tepetate\PDfarms Mex): Anticipated scenario (blue), high cost scenario (red) and low c

    PPA price

    achievable self-supply Reference scenario: Trayectory of total average elect

    case scenario 2010-2

    The reference scenario clearly shows that the assumed PPA price ev

    the national grid operator CFE and is thus extremely conservative.

    PPA price in US$/MWh(inflation adjusted)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    50/95

    2031 2032 2033 2034 2035

    185.76 192.36 199.19 206.27 213.60

    .4, stored under: P:\SoWiTec\PDD sources\7. Energy market MEX\Wind

    ost scenario (green).

    icity prices: Planned, worst and best

    025.

    n exceeds the highest price exectations of

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    51/95

    CFE transmission fees for renewable energies of efficient cogeneration 20available under: http://www.cre.gob.mx/articulo.aspx?id=171

    2011 High voltage unit Medium voltage unit

    January 0.03161 MXN/kWh 0.03161 MXN/kWhFebuary 0.03179 MXN/kWh 0.03179 MXN/kWhMarch 0.03230 MXN/kWh 0.03230 MXN/kWhApril 0.03311 MXN/kWh 0.03311 MXN/kWhMay 0.03331 MXN/kWh 0.03331 MXN/kWhJune 0.03343 MXN/kWh 0.03343 MXN/kWhJuly 0.03332 MXN/kWh 0.03332 MXN/kWhAugust 0.03342 MXN/kWh 0.03342 MXN/kWhSeptember 0.03349 MXN/kWh 0.03349 MXN/kWhOctober 0.03388 MXN/kWh 0.03388 MXN/kWhNovember 0.03442 MXN/kWh 0.03442 MXN/kWhDecember 0.03490 MXN/kWh 0.03490 MXN/kWh

    Annual average 2011: 0.03325 MXN/kWh 0.03325 MXN/kWh

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    52/95

    11:

    Low voltage unit

    0.06321 MXN/kWh0.06358 MXN/kWh0.06459 MXN/kWh0.06622 MXN/kWh0.06662 MXN/kWh0.06687 MXN/kWh0.06665 MXN/kWh0.06684 MXN/kWh0.06699 MXN/kWh0.06775 MXN/kWh0.06885 MXN/kWh0.06979 MXN/kWh

    0.06650 MXN/kWh

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    53/95

    Modification parameter: 110%Unit 2013

    Project life (including construction) 0

    PPA price + 10 % US$

    Energy Output MWh 0

    Revenues from PPA US$ -

    Fair value in the final year US$

    CAPEX (Capital Expenditures)Wind Turbine Generators (WTGs) US$

    Civil works US$

    VAT on civil works US$

    Electrical works US$

    VAT on electrical works US$Effective upfront fee (2.5%) US$

    Total CAPEX, inflation adapt., excl. VAT US$

    OPEX (Operational Expenditures)

    Service Contract (excluding taxes) US$

    Operational Management (excluding taxes) US$

    Insurance: Property damage,production loss and liability

    (excluding taxes)US$

    Landscaping (excluding taxes) US$

    LLA Rent fixed (excluding taxes) US$

    LLA Rent variable US$

    CFE transmission Fee US$

    Total, adapted to inflation US$

    VAT US$

    Total OPEX,inflation adapt., excl. VAT US$

    EBITDAPrincipal repayment US$

    Financing costs (interes + comittment fee) US$

    EBTDA (earnings before taxes, depreciation andamortization), after debt service

    US$

    Depreciation US$

    IETU (Corporate tax standard rate) %

    Taxes as per IETU US$

    Income tax rate from 2014 onwards %

    Taxes as per Income tax US$

    Applicable tax rate %

    Total TAX burden US$

    Profit after taxes US$

    PPA price calculation

    Cash flow in

    Cash flow out

    Financing

    Tax

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    54/95

    2014 2015 2016 2017 2018

    1 2 3 4 5

    112.85 116.86 121.01 125.31 129.77

    0 749,079.00 749,079.00 749,079.00 749,079.00

    - 87,536,019.52 90,647,105.12 93,868,760.68 97,204,915.92

    -

    -

    -

    -

    -

    -

    -

    - - - -

    - - - -

    (437,680.10) (453,235.53) (469,343.80) (486,024.58)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (23,552,503.77) (24,259,647.34) (24,990,086.58) (25,744,645.72)

    (2,207,318.10) (2,221,824.53) (2,236,846.54) (2,252,402.44)

    (23,552,503.77) (24,259,647.34) (24,990,086.58) (25,744,645.72)

    (141,642,841.02) 63,983,515.75 66,387,457.78 68,878,674.11 71,460,270.20

    - - - - -

    - - - - -

    (199,069,094.22) 5,887,431.64 8,291,373.67 10,782,589.99 12,766,844.42

    (373,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    - (11,197,115.26) (11,617,805.11) (12,053,767.97) (12,505,547.29)

    28.00% 28.00% 28.00% 28.00% 28.00%

    - - (2,967,839.89) (3,982,925.28) (4,867,961.86)

    28.00% 17.50% 17.50% 17.50% 17.50%

    - (11,197,115.26) (11,617,805.11) (12,053,767.97) (12,505,547.29)

    (199,069,094.22) (5,309,683.62) (3,326,431.45) (1,271,177.98) 261,297.14

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    55/95

    2019 2020 2021 2022

    6 7 8 9

    134.38 139.15 144.10 149.22

    749,079.00 749,079.00 749,079.00 749,079.00

    100,659,640.22 104,237,147.62 107,941,801.90 111,778,121.94

    - - - -

    - - - -

    (503,298.20) (521,185.74) (539,709.01) (558,890.61)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (26,524,179.62) (27,329,574.90) (28,161,751.18) (29,021,662.31)

    (2,268,511.20) (2,285,192.48) (2,302,466.62) (2,320,354.69)

    (26,524,179.62) (27,329,574.90) (28,161,751.18) (29,021,662.31)

    74,135,460.61 76,907,572.72 79,780,050.72 82,756,459.63

    - - - -

    - - - -

    15,442,034.83 18,214,146.95 20,582,445.18 23,558,854.08

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50%

    (12,973,705.61) (13,458,825.23) (13,961,508.88) (14,482,380.43)

    28.00% 28.00% 28.00% 28.00%

    (6,047,364.53) (7,325,725.74) (8,531,187.06) (10,051,201.71)

    17.50% 17.50% 17.50% 17.50%

    (12,973,705.61) (13,458,825.23) (13,961,508.88) (14,482,380.43)

    2,468,329.23 4,755,321.72 6,620,936.30 9,076,473.65

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    56/95

    2023 2024 2025 2026 2027

    10 11 12 13 14

    154.52 160.02 165.70 171.59 177.69

    749,079.00 749,079.00 749,079.00 749,079.00 749,079.00

    115,750,787.22 119,864,643.55 124,124,708.94 128,536,179.75 133,104,437.02

    - - - - -

    - - - - -

    (578,753.94) (599,323.22) (620,623.54) (642,680.90) (665,522.19)

    - - - - -

    - - - - -

    - - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (29,910,297.73) (30,828,683.80) (31,777,885.20) (32,759,006.47) (33,773,193.47)

    (2,338,878.52) (2,358,060.70) (2,377,924.62) (2,398,494.52) (2,419,795.49)

    (29,910,297.73) (30,828,683.80) (31,777,885.20) (32,759,006.47) (33,773,193.47)

    85,840,489.49 89,035,959.75 92,346,823.73 95,777,173.27 99,331,243.55

    - - - - -

    - - - - -

    26,642,883.95 29,451,844.40 32,762,708.38 36,193,057.92 39,747,128.20

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (15,022,085.66) (15,581,292.96) (16,160,694.15) (16,761,005.32) (17,382,967.62)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (11,717,655.94) (13,402,353.06) (15,436,573.52) (17,694,561.46) (20,210,215.11)

    17.50% 17.50% 17.50% 28.00% 28.00%

    (15,022,085.66) (15,581,292.96) (16,160,694.15) (17,694,561.46) (20,210,215.11)

    11,620,798.29 13,870,551.44 16,602,014.23 18,498,496.46 19,536,913.09

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    57/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    58/95

    2033 2034

    20 21

    219.11 226.90

    749,079.00 749,079.00

    164,132,809.01 169,966,193.05

    - -

    - -

    (820,664.05) (849,830.97)

    - -

    - -

    - -

    (8,210,269.14) (8,210,269.14)

    (40,622,487.91) (41,904,042.39)

    (2,564,475.25) (2,591,675.28)

    (40,622,487.91) (41,904,042.39)

    123,510,321.10 128,062,150.66

    - -

    - -

    123,510,321.10 128,062,150.66

    (4,590,767.93) (4,590,767.93)

    17.50% 17.50%

    (21,614,306.19) (22,410,876.37)

    28.00% 28.00%

    (33,297,474.89) (34,571,987.16)

    28.00% 28.00%

    (33,297,474.89) (34,571,987.16)

    90,212,846.21 93,490,163.49

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    59/95

    Modification parameter: 110%Unit 2013

    Project life (including construction) 0

    PPA price US$ / MWh

    Energy Output MWh 0

    Revenues from PPA US$ -

    Fair value in the final year US$

    CAPEX (Capital Expenditures)Wind Turbine Generators (WTGs) US$

    Civil works US$

    VAT on civil works US$

    Electrical works US$

    VAT on electrical works US$

    Effective upfront fee (2.5%) US$

    Total CAPEX, inflation adapt., excl. VAT US$

    OPEX (Operational Expenditures)

    Service Contract (excluding taxes) US$

    Operational Management (excluding taxes) US$

    Insurance: Property damage,production loss and liability (excluding

    taxes)US$

    Landscaping (excluding taxes) US$

    LLA Rent fixed (excluding taxes) US$

    LLA Rent variable US$

    CFE transmission Fee US$

    Total, adapted to inflation US$

    VAT US$

    Total OPEX,inflation adapt., excl. VAT US$

    EBITDAPrincipal repayment US$

    Financing costs (interes + comittment fee) US$

    EBTDA (earnings before taxes, depreciation and amortization), afterdebt serviceUS$

    Depreciation US$

    IETU (Corporate tax standard rate) %

    Taxes as per IETU US$

    Income tax rate from 2014 onwards %

    Taxes as per Income tax US$

    PPA price calculation

    Cash flow in

    Cash flow out

    Financing

    Tax

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    60/95

    Applicable tax rate %

    Total TAX burden US$

    Profit after taxes US$

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    61/95

    2014 2015 2016 2017 2018

    1 2 3 4 5

    102.59 106.23 110.01 113.92 117.97

    0 823,986.90 823,986.90 823,986.90 823,986.90

    - 87,536,019.52 90,647,105.12 93,868,760.68 97,204,915.92

    -

    -

    -

    -

    -

    -

    -

    - - - -

    - - - -

    (437,680.10) (453,235.53) (469,343.80) (486,024.58)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (23,552,503.77) (24,259,647.34) (24,990,086.58) (25,744,645.72)

    (2,207,318.10) (2,221,824.53) (2,236,846.54) (2,252,402.44)

    (23,552,503.77) (24,259,647.34) (24,990,086.58) (25,744,645.72)

    (141,642,841.02) 63,983,515.75 66,387,457.78 68,878,674.11 71,460,270.20

    - - - - -

    - - - - -

    (199,069,094.22) 5,887,431.64 8,291,373.67 10,782,589.99 12,766,844.42

    (373,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    - (11,197,115.26) (11,617,805.11) (12,053,767.97) (12,505,547.29)

    28.00% 28.00% 28.00% 28.00% 28.00%

    - - (2,967,839.89) (3,982,925.28) (4,867,961.86)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    62/95

    28.00% 17.50% 17.50% 17.50% 17.50%

    - (11,197,115.26) (11,617,805.11) (12,053,767.97) (12,505,547.29)

    (199,069,094.22) (5,309,683.62) (3,326,431.45) (1,271,177.98) 261,297.14

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    63/95

    2019 2020 2021 2022 2023

    6 7 8 9 10

    122.16 126.50 131.00 135.66 140.48

    823,986.90 823,986.90 823,986.90 823,986.90 823,986.90

    100,659,640.22 104,237,147.62 107,941,801.90 111,778,121.94 115,750,787.22

    - - - - -

    - - - - -

    (503,298.20) (521,185.74) (539,709.01) (558,890.61) (578,753.94)

    - - - - -

    - - - - -

    - - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (26,524,179.62) (27,329,574.90) (28,161,751.18) (29,021,662.31) (29,910,297.73)

    (2,268,511.20) (2,285,192.48) (2,302,466.62) (2,320,354.69) (2,338,878.52)

    (26,524,179.62) (27,329,574.90) (28,161,751.18) (29,021,662.31) (29,910,297.73)

    74,135,460.61 76,907,572.72 79,780,050.72 82,756,459.63 85,840,489.49

    - - - - -

    - - - - -

    15,442,034.83 18,214,146.95 20,582,445.18 23,558,854.08 26,642,883.95

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (12,973,705.61) (13,458,825.23) (13,961,508.88) (14,482,380.43) (15,022,085.66)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (6,047,364.53) (7,325,725.74) (8,531,187.06) (10,051,201.71) (11,717,655.94)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    64/95

    17.50% 17.50% 17.50% 17.50% 17.50%

    (12,973,705.61) (13,458,825.23) (13,961,508.88) (14,482,380.43) (15,022,085.66)

    2,468,329.23 4,755,321.72 6,620,936.30 9,076,473.65 11,620,798.29

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    65/95

    2024 2025 2026 2027 2028

    11 12 13 14 15

    145.47 150.64 155.99 161.54 167.28

    823,986.90 823,986.90 823,986.90 823,986.90 823,986.90

    119,864,643.55 124,124,708.94 128,536,179.75 133,104,437.02 137,835,053.06

    - - - - -

    - - - - -

    (599,323.22) (620,623.54) (642,680.90) (665,522.19) (689,175.27)

    - - - - -

    - - - - -

    - - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (30,828,683.80) (31,777,885.20) (32,759,006.47) (33,773,193.47) (34,821,635.00)

    (2,358,060.70) (2,377,924.62) (2,398,494.52) (2,419,795.49) (2,441,853.51)

    (30,828,683.80) (31,777,885.20) (32,759,006.47) (33,773,193.47) (34,821,635.00)

    89,035,959.75 92,346,823.73 95,777,173.27 99,331,243.55 103,013,418.06

    - - - - -

    - - - - -

    29,451,844.40 32,762,708.38 36,193,057.92 39,747,128.20 43,429,302.70

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (15,581,292.96) (16,160,694.15) (16,761,005.32) (17,382,967.62) (18,027,348.16)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (13,402,353.06) (15,436,573.52) (17,694,561.46) (20,210,215.11) (23,023,097.16)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    66/95

    17.50% 17.50% 28.00% 28.00% 28.00%

    (15,581,292.96) (16,160,694.15) (17,694,561.46) (20,210,215.11) (23,023,097.16)

    13,870,551.44 16,602,014.23 18,498,496.46 19,536,913.09 20,406,205.54

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    67/95

    2029 2030 2031 2032 2033

    16 17 18 19 20

    173.22 179.38 185.76 192.36 199.19

    823,986.90 823,986.90 823,986.90 823,986.90 823,986.90

    142,733,798.19 147,806,647.82 153,059,789.75 158,499,631.66 164,132,809.01

    - - - - -

    - - - - -

    (713,668.99) (739,033.24) (765,298.95) (792,498.16) (820,664.05)

    - - - - -

    - - - - -

    - - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (35,905,564.46) (37,026,261.53) (38,185,054.00) (39,383,319.60) (40,622,487.91)

    (2,464,695.48) (2,488,349.27) (2,512,843.74) (2,538,208.75) (2,564,475.25)

    (35,905,564.46) (37,026,261.53) (38,185,054.00) (39,383,319.60) (40,622,487.91)

    106,828,233.73 110,780,386.29 114,874,735.74 119,116,312.06 123,510,321.10

    - - - - -

    - - - - -

    47,244,118.38 110,780,386.29 114,874,735.74 119,116,312.06 123,510,321.10

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (18,694,940.90) (19,386,567.60) (20,103,078.75) (20,845,354.61) (21,614,306.19)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (26,179,402.65) (29,733,093.14) (30,879,510.99) (32,067,152.36) (33,297,474.89)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    68/95

    28.00% 28.00% 28.00% 28.00% 28.00%

    (26,179,402.65) (29,733,093.14) (30,879,510.99) (32,067,152.36) (33,297,474.89)

    21,064,715.72 81,047,293.15 83,995,224.75 87,049,159.70 90,212,846.21

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    69/95

    2034

    21

    206.27

    823,986.90

    169,966,193.05

    -

    -

    (849,830.97)

    -

    -

    -

    (8,210,269.14)

    (41,904,042.39)

    (2,591,675.28)

    (41,904,042.39)

    128,062,150.66

    -

    -

    128,062,150.66

    (4,590,767.93)

    17.50%

    (22,410,876.37)

    28.00%

    (34,571,987.16)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    70/95

    28.00%

    (34,571,987.16)

    93,490,163.49

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    71/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    72/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    73/95

    2014 2015 2016 2017 2018

    1 2 3 4 5

    102.59 106.23 110.01 113.92 117.97

    - 749,079.00 749,079.00 749,079.00 749,079.00

    - 79,578,199.57 82,406,459.20 85,335,236.98 88,368,105.38

    -

    -

    -

    -

    -

    -

    -

    - - - -

    - - - -

    (397,891.00) (412,032.30) (426,676.18) (441,840.53)

    - - - -

    - - - -

    - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (23,320,591.94) (24,019,493.22) (24,741,397.22) (25,487,117.78)

    (2,170,212.20) (2,183,399.87) (2,197,056.24) (2,211,197.97)

    (23,320,591.94) (24,019,493.22) (24,741,397.22) (25,487,117.78)

    (127,478,556.92) 56,257,607.63 58,386,965.99 60,593,839.76 62,880,987.60

    - - - - -

    - - - - -

    (179,162,184.80) 3,971,131.93 6,100,490.28 8,307,364.06 10,056,904.40

    (336,231,691.14) (4,131,691.14) (4,131,691.14) (4,131,691.14)

    17.50% 17.50% 17.50% 17.50% 17.50%

    - (9,845,081.34) (10,217,719.05) (10,603,921.96) (11,004,172.83)

    28.00% 28.00% 28.00% 28.00% 28.00%

    - - (2,289,767.02) (3,193,482.01) (3,979,854.11)

    28.00% 17.50% 17.50% 17.50% 17.50%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    74/95

    - (9,845,081.34) (10,217,719.05) (10,603,921.96) (11,004,172.83)

    (179,162,184.80) (5,873,949.41) (4,117,228.76) (2,296,557.90) (947,268.43)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    75/95

    2019 2020 2021 2022 2023

    6 7 8 9 10

    122.16 126.50 131.00 135.66 140.48

    749,079.00 749,079.00 749,079.00 749,079.00 749,079.00

    91,508,763.84 94,761,043.29 98,128,910.82 101,616,474.49 105,227,988.39

    - - - - -

    - - - - -

    (457,543.82) (473,805.22) (490,644.55) (508,082.37) (526,139.94)

    - - - - -

    - - - - -

    - - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (26,257,498.98) (27,053,416.26) (27,875,777.69) (28,725,525.14) (29,603,635.66)

    (2,225,842.30) (2,241,007.09) (2,256,710.86) (2,272,972.75) (2,289,812.59)

    (26,257,498.98) (27,053,416.26) (27,875,777.69) (28,725,525.14) (29,603,635.66)

    65,251,264.86 67,707,627.03 70,253,133.13 72,890,949.35 75,624,352.73

    - - - - -

    - - - - -

    12,427,181.66 14,883,543.83 16,975,288.15 19,613,104.36 22,346,507.74

    (4,131,691.14) (4,131,691.14) (4,131,691.14) (4,131,691.14) (4,131,691.14)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (11,418,971.35) (11,848,834.73) (12,294,298.30) (12,755,916.14) (13,234,261.73)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (5,030,846.16) (6,170,580.41) (7,244,372.85) (8,600,919.53) (10,088,905.76)

    17.50% 17.50% 17.50% 17.50% 17.50%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    76/95

    (11,418,971.35) (11,848,834.73) (12,294,298.30) (12,755,916.14) (13,234,261.73)

    1,008,210.31 3,034,709.10 4,680,989.85 6,857,188.22 9,112,246.01

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    77/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    78/95

    (13,729,928.63) (14,243,531.16) (15,430,385.88) (17,681,094.01) (20,198,882.29)

    11,101,102.57 13,522,371.66 15,376,511.13 16,276,679.98 17,023,543.17

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    79/95

    2029 2030 2031 2032 2033

    16 17 18 19 20

    173.22 179.38 185.76 192.36 199.19

    749,079.00 749,079.00 749,079.00 749,079.00 749,079.00

    129,757,998.35 134,369,679.84 139,145,263.41 144,090,574.24 149,211,644.55

    - - - - -

    - - - - -

    (648,789.99) (671,848.40) (695,726.32) (720,452.87) (746,058.22)

    - - - - -

    - - - - -

    - - - - -

    (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14) (8,210,269.14)

    (35,527,415.47) (36,634,672.89) (37,779,548.06) (38,963,401.72) (40,187,645.88)

    (2,404,191.65) (2,425,695.09) (2,447,962.79) (2,471,021.89) (2,494,900.52)

    (35,527,415.47) (36,634,672.89) (37,779,548.06) (38,963,401.72) (40,187,645.88)

    94,230,582.88 97,735,006.95 101,365,715.35 105,127,172.52 109,023,998.67

    - - - - -

    - - - - -

    40,604,879.06 97,735,006.95 101,365,715.35 105,127,172.52 109,023,998.67

    (4,131,691.14) (4,131,691.14) (4,131,691.14) (4,131,691.14) (4,131,691.14)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (16,490,352.00) (17,103,626.22) (17,739,000.19) (18,397,255.19) (19,079,199.77)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (23,025,310.69) (26,208,928.43) (27,225,526.78) (28,278,734.79) (29,369,846.11)

    28.00% 28.00% 28.00% 28.00% 28.00%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    80/95

    (23,025,310.69) (26,208,928.43) (27,225,526.78) (28,278,734.79) (29,369,846.11)

    17,579,568.37 71,526,078.52 74,140,188.57 76,848,437.73 79,654,152.56

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    81/95

    2034

    21

    206.27

    749,079.00

    154,514,720.95

    -

    -

    (772,573.60)

    -

    -

    -

    (8,210,269.14)

    (41,453,745.80)

    (2,519,627.82)

    (41,453,745.80)

    113,060,975.16

    -

    -

    113,060,975.16

    (4,131,691.14)

    17.50%

    (19,785,670.65)

    28.00%

    (30,500,199.53)

    28.00%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    82/95

    (30,500,199.53)

    82,560,775.63

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    83/95

    Modification parameter: 90%Unit 2013 2014

    Project life (including construction) 0 1

    PPA price US$ / MWh 102.59

    Energy Output MWh -

    Revenues from PPA US$ -

    Fair value in the final year US$

    CAPEX (Capital Expenditures)Wind Turbine Generators (WTGs) US$ -

    Civil works US$ -

    VAT on civil works US$ -

    Electrical works US$ -

    VAT on electrical works US$ -

    Effective upfront fee (2.5%) US$ -

    Total CAPEX, inflation adapt., excl. VAT US$ -

    OPEX (Operational Expenditures)Service Contract (excluding taxes) US$

    Operational Management (excluding taxes) US$

    Insurance: Property damage,production loss and liability

    (excluding taxes)US$

    Landscaping (excluding taxes) US$

    LLA Rent fixed (excluding taxes) US$

    LLA Rent variable US$

    CFE transmission Fee US$

    Total, adapted to inflation US$

    VAT US$

    Total OPEX,inflation adapt., excl. VAT US$

    EBITDA (141,642,841.02)

    Principal repayment US$ -

    Financing costs (interes + comittment fee) US$ -

    EBTDA(earnings before taxes, depreciation and

    amortization), after debt service US$ (199,069,094.22)

    Depreciation US$

    IETU (Corporate tax standard rate) % 17.50%

    Taxes as per IETU US$ -

    Income tax rate from 2014 onwards % 28.00%

    Taxes as per Income tax US$ -

    Applicable tax rate % 28.00%

    PPA price calculation

    Cash flow in

    Cash flow out

    Financing

    Tax

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    84/95

    Total TAX burden US$ -

    Profit after taxes US$ (199,069,094.22)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    85/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    86/95

    (10,253,191.69) (10,638,060.18) (11,036,896.41) (11,450,197.39) (11,878,477.58)

    (9,759,608.99) (7,945,228.98) (6,065,001.04) (4,713,923.79) (2,694,888.60)

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    87/95

    2020 2021 2022 2023 2024

    7 8 9 10 11

    126.50 131.00 135.66 140.48 145.47

    749,079.00 749,079.00 749,079.00 749,079.00 749,079.00

    94,761,043.29 98,128,910.82 101,616,474.49 105,227,988.39 108,967,857.77

    - - - - -

    - - - - -

    (426,424.69) (441,580.10) (457,274.14) (473,525.95) (490,355.36)

    - - - - -

    - - - - -

    - - - - -

    (7,389,242.22) (7,389,242.22) (7,389,242.22) (7,389,242.22) (7,389,242.22)

    (24,348,074.63) (25,088,199.92) (25,852,972.63) (26,643,272.09) (27,460,010.48)

    (2,016,906.38) (2,031,039.77) (2,045,675.47) (2,060,831.33) (2,076,525.84)

    (24,348,074.63) (25,088,199.92) (25,852,972.63) (26,643,272.09) (27,460,010.48)

    70,412,968.66 73,040,710.90 75,763,501.86 78,584,716.29 81,507,847.29

    - - - - -

    - - - - -

    11,719,542.88 13,843,105.36 16,565,896.32 19,387,110.75 21,923,731.94

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (12,322,269.52) (12,782,124.41) (13,258,612.83) (13,752,325.35) (14,263,873.28)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (5,507,236.60) (6,644,171.91) (8,093,173.53) (9,686,039.45) (11,294,481.57)

    17.50% 17.50% 17.50% 17.50% 17.50%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    88/95

    (12,322,269.52) (12,782,124.41) (13,258,612.83) (13,752,325.35) (14,263,873.28)

    (602,726.63) 1,060,980.95 3,307,283.49 5,634,785.40 7,659,858.66

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    89/95

    2025 2026 2027 2028 2029

    12 13 14 15 16

    150.64 155.99 161.54 167.28 173.22

    749,079.00 749,079.00 749,079.00 749,079.00 749,079.00

    112,840,644.49 116,851,072.50 121,004,033.66 125,304,593.69 129,757,998.35

    - - - - -

    - - - - -

    (507,782.90) (525,829.83) (544,518.15) (563,870.67) (583,910.99)

    - - - - -

    - - - - -

    - - - - -

    (7,389,242.22) (7,389,242.22) (7,389,242.22) (7,389,242.22) (7,389,242.22)

    (28,304,134.06) (29,176,624.51) (30,078,500.26) (31,010,817.97) (31,974,673.93)

    (2,092,778.14) (2,109,608.06) (2,127,036.12) (2,145,083.59) (2,163,772.48)

    (28,304,134.06) (29,176,624.51) (30,078,500.26) (31,010,817.97) (31,974,673.93)

    84,536,510.43 87,674,447.99 90,925,533.39 94,293,775.72 97,783,324.43

    - - - - -

    - - - - -

    24,952,395.07 28,090,332.64 31,341,418.04 34,709,660.36 38,199,209.07

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (14,793,889.32) (15,343,028.40) (15,911,968.34) (16,501,410.75) (17,112,081.77)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (13,249,685.80) (15,425,798.38) (17,856,616.27) (20,581,597.31) (23,646,828.05)

    17.50% 28.00% 28.00% 28.00% 28.00%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    90/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    91/95

    2030 2031 2032 2033 2034

    17 18 19 20 21

    179.38 185.76 192.36 199.19 206.27

    749,079.00 749,079.00 749,079.00 749,079.00 749,079.00

    134,369,679.84 139,145,263.41 144,090,574.24 149,211,644.55 154,514,720.95

    - - - - -

    - - - - -

    (604,663.56) (626,153.69) (648,407.58) (671,452.40) (695,316.24)

    - - - - -

    - - - - -

    - - - - -

    (7,389,242.22) (7,389,242.22) (7,389,242.22) (7,389,242.22) (7,389,242.22)

    (32,971,205.60) (34,001,593.25) (35,067,061.55) (36,168,881.29) (37,308,371.22)

    (2,183,125.58) (2,203,166.51) (2,223,919.70) (2,245,410.47) (2,267,665.04)

    (32,971,205.60) (34,001,593.25) (35,067,061.55) (36,168,881.29) (37,308,371.22)

    101,398,474.23 105,143,670.15 109,023,512.69 113,042,763.26 117,206,349.74

    - - - - -

    - - - - -

    101,398,474.23 105,143,670.15 109,023,512.69 113,042,763.26 117,206,349.74

    (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93) (4,590,767.93)

    17.50% 17.50% 17.50% 17.50% 17.50%

    (17,744,732.99) (18,400,142.28) (19,079,114.72) (19,782,483.57) (20,511,111.20)

    28.00% 28.00% 28.00% 28.00% 28.00%

    (27,106,157.77) (28,154,812.62) (29,241,168.53) (30,366,558.69) (31,532,362.91)

    28.00% 28.00% 28.00% 28.00% 28.00%

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    92/95

    (27,106,157.77) (28,154,812.62) (29,241,168.53) (30,366,558.69) (31,532,362.91)

    74,292,316.47 76,988,857.53 79,782,344.16 82,676,204.57 85,673,986.83

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    93/95

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    94/95

    Most important items of the financial plan.

    Unit 2014 2015 2016

    PPA price US$ / MWh 102.59 106.23 110.01

    Energy Output MWh - 749,079.00 749,079.00

    Revenues from PPA US$ - 79,578,199.57 82,406,459.20Profit after tax US$ (199,069,094.22) (11,751,550.88) (9,997,246.76)

    Unit 2019 2020 2021

    PPA price US$ / MWh 122.16 126.50 131.00

    Energy Output MWh 749,079.00 749,079.00 749,079.00

    Revenues from PPA US$ 91,508,763.84 94,761,043.29 98,128,910.82

    Profit after tax US$ (4,939,319.02) (2,915,599.04) (1,322,613.84)

    Unit 2024 2025 2026

    PPA price US$ / MWh 145.47 150.64 155.99

    Energy Output MWh 749,079.00 749,079.00 749,079.00

    Revenues from PPA US$ 108,967,857.77 112,840,644.49 116,851,072.50

    Profit after tax US$ 5,049,586.91 7,467,547.02 9,972,940.64

    Unit 2029 2030 2031

    PPA price US$ / MWh 173.22 179.38 185.76

    Energy Output MWh 749,079.00 749,079.00 749,079.00

    Revenues from PPA US$ 129,757,998.35 134,369,679.84 139,145,263.41

    Profit after tax US$ 11,897,649.93 71,554,424.03 74,164,973.05

    Unit 2034

    PPA price US$ / MWh 206.27

    Energy Output MWh 749,079.00

    Revenues from PPA US$ 154,514,720.95

    Profit after tax US$ 82,574,099.51

  • 8/10/2019 8310 IRR Sheet 21 Nov 12

    95/95

    2017 2018

    113.92 117.97

    749,079.00 749,079.00

    85,335,236.98 88,368,105.38(8,179,078.29) (6,892,114.33)

    2022 2023

    135.66 140.48

    749,079.00 749,079.00

    101,616,474.49 105,227,988.39

    850,604.70 3,102,576.74

    2027 2028

    161.54 167.28

    749,079.00 749,079.00

    121,004,033.66 125,304,593.69

    10,988,292.18 11,553,761.23

    2032 2033

    192.36 199.19

    749,079.00 749,079.00

    144,090,574.24 149,211,644.55

    76,869,534.63 79,671,430.81