8 reducing project durations
DESCRIPTION
Project ManagementTRANSCRIPT
Reducing Project Duration or
Project Crashing
Why Reduce Project Duration?• Time Is Money: Cost-Time Tradeoffs
– Reducing the time of a critical activity usually incurs additional direct costs.
• Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project.
– Reasons for imposed project duration dates:• Customer requirements and contract commitments• Time-to-market pressures• Incentive contracts (bonuses for early completion)• Unforeseen delays• Overhead and goodwill costs• Pressure to move resources to other projects
Reducing Project Completion Time• Reduced project completion time is “crashing”• Crashing is the same whether you have used
CPM or PERT.
Project & Activity Costs• PROJECT DIRECT COSTS: Directly assigned to work
package or activity– “Normal” costs for “normal” time
• Direct labor expenses• Materials• Equipment• Subcontractors
– Crashing activities increases direct costs
• INDIRECT EXPENSES: Cannot be associated with any work package or activity– Overhead expenses
• including supervisory expenses• administration• contractual penalties or early completion incentives
– Consulting
Crashing Activities• Activity & project duration may be influenced by resource
allocation decisions…more resources—less time needed• Sometimes, we can expedite completion of a task by assigning
more people or equipment. Thus, total direct costs tend to vary inversely with project duration. Indirect costs, however, tend to increase with overall project completion time.
TotalCosts
IndirectCosts
DirectCosts
Project duration
Expe
nse
Time-Cost Tradeoffs in CPM• Basic Assumption: Some activities can be
expedited, at a cost• Why accelerate an activity?
– Complete the task in a shorter duration, thereby reducing the duration of the critical path, thereby reducing the length of the project• Avoid late penalties• Earn early completion incentive payments
• Time Cost Problem: Determine the optimum project duration based on time-cost tradeoffs
Time & Costs: Normal vs. Crash• For the time-only CPM project schedule, we
typically assume that activity duration is fixed at its NORMAL TIME, or the duration with the lowest direct activity cost (i.e., NORMAL COST).
• However, some activities may be expedited if higher resource levels are available. The shortest activity duration is called CRASH TIME. The cost to complete an activity in that amount of time is called CRASH COST.
Constructing Project Cost vs. Duration Graph
• Find total direct costs for selected project durations.
• Find total indirect costs for selected project durations.
• Sum direct and indirect costs for these selected project durations.
• Compare additional cost alternatives for benefits.
Constructing a Project Cost vs. Duration Graph • Determining Activities to Shorten
– Shorten the activities with the smallest increase in cost per unit of time.
– Assumptions:
• The cost relationship is linear.• Normal time assumes low-cost, efficient methods to
complete the activity.• Crash time represents a limit—the greatest time reduction
possible under realistic conditions.• Slope represents a constant cost per unit of time.• All accelerations must occur within the normal and crash
times.
Linear Time-Cost TradeoffIn theory, the normal or expected duration of a task can be reduced by assigning additional resources to the task
Time
Cost
Crash Point
Normal Point
Slope (bj) = Increase in cost by reducing task by one time unit
Normal timeCrash time
Normal cost
Crash cost
tjNtjc
Cjc
CjN
Selecting Activities to Crash• Cost Slope = Rise / Run• Cost Slope = CC – NC / NT – CT• = CC – NC NT – CT• where,
– CC = Crash Cost– NC = Normal Cost– NT = Normal Time– CT = Crash Time
• Calculate for each activity on Critical Path
= CC – NC = $800 - $400
NT – CT 10 – 5
= $400/5 = $80 per unit of time
Time/Cost Trade-off Analysis• You might think that total project costs will
increase when we begin to crash activities• But, total project costs consist of both
indirect (project-based) costs (PBC) and direct (activity-based) costs (ABC)– ABC (direct) go up when we crash activities in
an effort to finish the project early– But, PBC (the indirect costs) go down if we
finish the project early
Which Activities are the Best Candidates for Crashing?
• Any activity that is on the critical path• Activities with relatively long durations• Bottleneck activities (that appear on multiple
critical paths)• Activities with relatively low costs to crash• Activities that are not likely to cause quality
problems if crashed• Activities that occur relatively early in the
schedule and are labor intensive
Options for Crashing Activities• Adding Resources• Outsourcing Project Work• Overtime• Establishing Core Project Team• Temporary Fixes• Fast-Tracking• Critical Chain PM• Brainstorming• Reducing Scope• Phasing Project Deliverables
Potential Problems with Crashing • Reduced flexibility and less margin for
errorincreased risk of failure to complete project on time
• Raises potential for poor quality• Increases potential for staff burnout, stress, and
turnover (from what Your don calls Death March projects)
• Raises activity-based costs• May negatively affect other projects• May create unrealistic expectations for future projects• Hard to know true indirect costs
Time-Cost Tradeoff Heuristic1. Set each activity duration to its normal time.2. Determine the critical path(s) and project duration
based on the current activity times.3. Calculate total direct costs and indirect costs for the
current schedule.4. Chose an activity or activities that can be expedited to
reduce project duration by one time unit. Use cost slopes and critical path information to guide your choice. If no further reduction in project duration is possible, go to step 5. Otherwise, go to step 2.
5. Plot the project's direct and indirect costs for each possible duration. Select the duration that minimizes total costs.
Network Crashing ExampleActivity ID
Normal Time
Normal cost
Maximum allowable crash time
Crash cost per day
A 3 50 1 20B 6 80 2 40C 10 60 1 30D 11 50 4 25E 8 100 2 30F 5 40 1 30G 6 70 0 00
Network Crashing Example
A
3
B
6
D
11
C
10
E
8
F
5
G
6
Initial TotalDirect Cost = $450
Select activity “A”[smallest slope] and
reduce time by 1 unit (xin next panel indicates
activity crashed bymaximum
TotalDuration = 25 units
Network Crashing Example
A
2x
B
6
D
11
C
10
E
8
F
5
G
6
TotalDirect Cost = $470
Activities Changed
A$20
TotalDuration = 24 units
Network Crashing Example
A
2x
B
6
D
10
C
10
E
8
F
5
G
6
TotalDirect Cost = $495
TotalDuration = 23 units
Activities Changed
D$25
Network Crashing Example
A
2x
B
6
D
10
C
10
E
8
F
4x
G
6
TotalDirect Cost = $525
TotalDuration = 22 units
Activities Changed
F$30
Network Crashing Example
A
2x
B
6
D
9
C
9x
E
7
F
4x
G
6
TotalDirect Cost = $610
Activities Changed
C
$30
TotalDuration = 21 units
D E
$25 $30
Network Crashing Example
PROJECTDURATION
DIRECTCOSTS
INDIRECTCOSTS
TOTALCOSTS=+
2524232221
$450470495525610
$400350300250200
$850820795775810
Practical Considerations
• Using the project cost—duration graph• Crash times• Linearity assumption• Choice of activities to crash revisited• Time reduction decisions and sensitivity
Reducing the Time of a Project (crashing)Activi
tyPredecesso
r
Normal Time (wk)
Normal Cost ($)
Crash Time
Crash Cost ($)
Max. weeks of reduction
Reduce cost per
weekA -- 4 8,000 3 11,000 1 3,000B A 6 30,000 5 35,000 1 5,000C A 3 6,000 3 6,000 0 0D B 6 24,000 4 28,000 2 2,000E D 14 60,000 12 72,000 2 6,000F C 5 5,000 4 6,500 1 1500G E,F 2 6,000 2 6,000 0 0H G 2 4,000 2 4,000 0 0I G 3 4,000 2 5,000 1 1,000J H,I 4 4,000 2 6,400 2 1,200K J 2 5,000 2 5,000 0 0
Crashing Example: Suppose the Cables By project manager wants to reduce the new product project from 41 to 36 weeks.
• Crashing Costs are considered to be linear• Look to crash activities on the critical path• Crash the least expensive activities on the critical path first
(based on cost per week)– Crash activity I from 3 weeks to 2 weeks $1000– Crash activity J from 4 weeks to 2 weeks $2400– Crash activity D from 6 weeks to 4 weeks $4000– Recommend Crash Cost $7400
• Question: Will crashing 5 weeks return more in benefits than it costs?
Crashed Network Diagram
Crashing Summary
• In planning, crashing can pull your project into the delivery window
• Once started, a late project can get pulled back in to schedule compliance
• Crashing can increase the size of the “critical core,” thereby reducing flexibility
• Capability in MS Project