AiM™ CPPM Capital Project 1| Page AiM™ Navigation icons Capital Project Capital Project screen is the main source of information on a project. Capital Project is the central hub to which all other transactions will be associated. How to enter a Capital Project: 1) Click on ‘Capital Planning and Project Management’ from the menu channel. Budget Manager Date Manager Budget Revision

Upload: truongngoc

Post on 08-Jan-2019

236 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

1 | P a g e   

AiM™ Navigation icons

Capital Project

Capital Project screen is the main source of information on a project. Capital Project is the central hub to which all other transactions will be associated. How to enter a Capital Project: 1) Click on ‘Capital Planning and Project Management’ from the menu channel.

Budget Manager 

 

Date  Manager 

 

 

Budget Revision 

 

 

Page 2: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

2 | P a g e   

2) From the ‘Capital Planning and Project Management’ menu channel, click on ‘Capital Project’ link.

3) Click on the New Icon.

Click Here 

Click Here 

Page 3: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

3 | P a g e   

4) Complete the form as described below:

Add Capital Project information

a. Change ‘Capital Project’ field according to the project number which has be assigned.

ie. Capital Project – State 5-digit project number; add 3-digit task number Maintenance Reserve – State 5-digit project number/ task number Non-capital – BCOM number or University Internal Project number Foundation – Project Managers will assign AiM Project number

b. Add detailed description of the project

Click Here 

  Click Here 

  Click Here 

C

Page 4: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

4 | P a g e   

c. Type (must be selected before Status)

Click the Zoom icon The Type table will populate. Select which Project type; Capital, Maintenance Reserve, Non-Capital or VCU Foundations

Status will populate to Draft. Note: When Type is selected the Project Component Group will populate

The Project Component group is a reporting element that represents a roll up of all the project component information associated with a specific project.

d. Click the Zoom icon . The Institution search is displayed. Click the Search icon to select the appropriate Institution. Select the appropriate Department, the Organization will automatically populate based on the selection.

ie. Finance Administration as Owner; Institution – D Department – 1880 Organization - 114

Owners: University Department or VCU Foundation Projects (select the appropriate organization number).

e. Click the Zoom icon The Institution search is displayed. Click the Search icon to select the appropriate Institution (the Institution will always be D). Select the appropriate Department, the Organization will automatically populate based on the selection. If you know the Organization’s number, you can key into the field.

FM Planning and Design: Institution = D, Department = 1884, Organization =169 FM Construction: Institution = D, Department = 1886, Organization =165

Click the Zoom icon The Employee table will populate. Scroll through the table until you have located the Project Manager’s user name; click on the user’s name.

5) Click Save icon (at least items a-c must be completed prior to saving).

Page 5: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

5 | P a g e   

How to enter the project budget:

1) From the Capital Project click the Budget Manager icon to enter the project budget information

2) Click the Edit icon to activate the fields to begin entering the project budget for each chosen project component. 3) Enter the budget amounts for the applicable components.

4) Click Save icon

5) Click the Flag icon to return to the main Capital Project screen

Page 6: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

6 | P a g e   

How to enter the Project Team: 1) Navigate to the Capital Project

2) Click the Edit icon 3) Click View: Select, choose Project Team

4) Select the Employee code for each Responsibility known Note: PLAN PROJ MANAGER should be filled out at project creation

6) Load Other Contacts as needed a. Click Load Responsibility on the Other Contacts header b. Select desired Responsibility codes c. Click the Flag icon d. Enter the contact information for each entry

5) Click the Flag icon to return to the Capital Project screen

6) Click Save

Page 7: 510 CPPM Capital Project - Virginia Commonwealth Universityaim.vcu.edu/files/support/docs/training/510 CPPM Capital Project.pdf · AiM™ CPPM Capital Project 1 | Page AiM™ Navigation

AiM™ CPPM Capital Project

              

7 | P a g e   

Change Status to Pending Funding: After all project information has been entered, PM must change the status to Pending Funding for Financial Services to load the Account Setup information and activate the project. 1) Navigate to the Capital Project

2) Click the Edit icon

3) Click the Zoom icon , select Pending Funding from the Capital Project status table.

4) Click Save icon