4th ed.develop project charter
TRANSCRIPT
-
7/28/2019 4th Ed.Develop Project Charter
1/8
1 | P a g e
PROJECT CHARTER
Process Group: Initiating
Knowledge Area: Project Integration Management
efore a project will commence, a document will have to be prepared and
released to officially start off the project. This document is a document of
power and authority. It describes, among other things, the project that is to
be undertaken, what is to be achieved at the end and the objectives of achieving that
end. It establishes key stakeholders [like project sponsor, program and portfolio
managers, etc.] and outlines their roles on the project. A project charter also
indicates who signs off on the project as successful. A Project Charter must indicate
acceptance criteria and assign some person or persons who inspect the final
deliverable and state whether or not the projects objectives have been delivered.
Another crucial role or assignment a project charter establishes is who is to be the
project manager the one to lead a team to attain the objectives of the project. This
assignment gives the project manager the authority to command and apply resources
within the project area (just as when a president is sworn in, the activity gives him
the authority to command a nations resources). The power or authority level of aproject manager will vary from one organization to another, and from one project to
another based on how much the requesting organization will want him to have.
Most of the times, the organization type [projectized, functional or matrix] sets the
precedence for the varying degree of power a project manager exerts on a project.
A Project Charter is a document that formally authorizes a project.
A project charter is typically prepared by the requesting organization, project
sponsor, or any team the requesting organization deem fit. But it is recommended
that a project manager joins in. If the project will be performed by the requesting
organization, then the organization is likely to have its own project manager, who
can join in the preparation of the charter right from the start.
B
-
7/28/2019 4th Ed.Develop Project Charter
2/8
2 | P a g e
If the project is to be carried out by an external organization, it means the requesting
organization is separate from the organization that would perform the work, and the
project charter should include a contract document to spell out conditions of
partnership or agreement.
Some charters will go further to highlight pre-identified risks, constraints and
assumptions associated with the project. On complex projects, some information
derived during the later planning stage may even be included [by iteration of
course] in the project charter. What is included is dependent on the needs of the
project and what is of serious concern to the requesting organization.
In multi-phased projects, a project charter should authorize all phases that exist
within the project. However, some multi-phased projects may prepare separate
charters to authorize each phase. Much is dependent on the reason for phasing and
a justification for the preparation of separate project charters for each phase.
The Project initiator or sponsor signs the project charter to officially authorize the
project. A Charter may contain the signature of other stakeholders as well. Now,
lets take a look at what goes into the preparation of a project charter:
DEVELOP PROJECT CHARTER
Develop Project Charter is the process of preparing a document to formally
authorize a project or a phase and stipulating initial requirements that fulfill
stakeholders needs and expectations. On the project charter level, these
requirements are documented on a high-level. When we talk of high-level we refer
to definitions that are usually in brief sum as against definitions that are
comprehensively elaborated. For instance, if a project is to come out with a 40-room
Iteration is the practice of going back and forth to update a document because [new] relevant
information has been realized or obtained.
-
7/28/2019 4th Ed.Develop Project Charter
3/8
3 | P a g e
office complex, a narrative description of what is to be created can only be on a high-
level definition within the project charter like the one below:
to put up a three-storey 40-room office complex
This is a high-level definition. By this we are only able to tell in sum what the project
is expected to create. The items to be contained in the building, their quality and
quantity, etc. will all be comprehensively elaborated during the planning stage. The
project charter as a matter of fact usually contains only high-level definitions. These
contents only set precedence for detailed planning.
INPUTS
1. Project statement of work
Product Scope Description
A project statement of work is that aspect of the charter that spells out or describes
the product or service that the project is required to deliver.
Take a look at my own statement of work as I put together this very book you are
presently reading:
This project is to come out with a book that will offer a simplistic rendition to
the study of PMP with easy-to-understand English that will use simple but
enduring words, interspersed with contextual examples.
Tools & TechniquesInputs Outputs
1. Project Statement of work2. Business Case3. Contract4. EEFs5. OPAs
1. Expert Judgment 1. Project Charter
-
7/28/2019 4th Ed.Develop Project Charter
4/8
4 | P a g e
Business Need
This is not all. A project statement of work should also include the need or why the
project is being undertaken in the first place. This is known as the business need.
This need is what triggers the project, hence, the business need usually points to the
project triggers: market demand, legal requirement, technological advancement, you
know them. Yours is to look through to find which need compels you to undertake
the project. Take a look at mine:
This project is to come out with a book that will offer a simplistic rendition to the study of
PMP with easy-to-understand English that will use simple but enduring words, interspersed
with contextual examples to assist students preparing to write their PMP Examination.
Did you see that? To assist students preparing to write their PMP Examination is
the rationale for my project. It is akin to a market demand, because I know there are
students out there, especially those of whom English is a non-native language, and
would need assistance in a more simplistic approach to study for their examination.
Strategic Plan
A project statement of work should also link the product/service that is to beproduced to the organizations strategic plan or goal. No one who would want to be
influential in the music industry goes about all day working on wood carvings. Every
organization has its own strategic goal, and whatever an organization undertakes
must be aligned to their strategic goals. Take a look at my strategic goal:
To be influential in the offering of PMP Education
Now, do you think the production of this book is aligned to my strategic goal as a
PMP lecturer?
-
7/28/2019 4th Ed.Develop Project Charter
5/8
5 | P a g e
A project statement of work starts from a product scope description through to a
business need to a strategic plan.
Project statement of work:
Product scope description what are we doing? Business need why are we doing it?
Strategic plan where does it fall on our strategic plan as an organization?
For external projects (an external organization that is being asked to undertake the
project), a project statement of work will be presented in a contract, a bid document
or other like documents. How else would an external organization know what to do
if it is not told?
2. Business Case
Notice that a business case is the second input in preparing a project charter. Do not
confuse it with the business need. So, what is the business case?
When you make a case for something, you make a justification for it; you make a
defense for it; you state why it is necessary and worthwhile for that thing to be
undertaken by outlining its benefits.
In making a business case for a project, you state why a project needs to be
undertaken from a business standpoint. You state why the project deserves the
required resources, energy, effort, time and attention. A project trigger may not
make sense to a company, business or organization if it stands to gain nothing from
the project. In shorts, the identified business need must contain benefits which the
organization will want to have.
Typically, we say that a cost-benefit analysis is added to a business need to make abusiness case for the project.
Business Case = Costbenefit Analysis + Business Need
-
7/28/2019 4th Ed.Develop Project Charter
6/8
6 | P a g e
One may ask, what is benefit? Benefit is a gain that can only be measured in relative
terms. Most business benefits are expressed in terms of money, profit or something
of a sort: directly or indirectly. A project to expand an office building may not bring
in direct monetary profits as compared to a project to put up estate houses that
would be put up for sale on completion. But the office building expansion surely
would bring in benefits that would facilitate operations and even go a long way to
influence monetary profits. Not-for-profit organizations undertake projects that may
not accrue monetary gains, but such benefits as they would call good gain.
3. Contract
When the project is to be performed by an external organization (different from a
requesting organization), a contract is needed to bind the two parties together. A
contract is a legally binding document that is subject to remedy in a court of law. We
will study more of contracts under Project Procurement Management.
A contract document is needless when the requesting organization will
perform its own project.
4. EEFs
The organization must take a look at Enterprise Environmental Factors that would
have a profound effect on the project, its execution, and the product/service it
would create. See Enterprise Environmental Factors to know more about what they are
and sample lists.
5. OPAs
There may be a couple of Organizational Process Assets that would help in thepreparation of a project charter. Some helpful OPAs, if they exist, include Project
Charter templates, Historical information, learned lessons, etc.
-
7/28/2019 4th Ed.Develop Project Charter
7/8
7 | P a g e
A quick review of Inputs to develop project charter:
1. Project statement of work
Product scope description
Business need
Strategic plan
2. Business case
3. Contract
4. EEFs
5. OPAs
TOOLS AND TECHNIQUES1. Expert Judgment
Throughout the PMP Course, we will come across expert judgment as a technique in
many processes. When we talk of expert judgment, we mean person(s) with technical
knowledge or expertise in the area under discussion. Expert judgment includes but is
not limited to team members with highlighted expertise, external persons acting as
consultants, professional unions, subject matter experts, etc. In order to know which
expert judgment is applicable, dont hesitate to look at the heading of the process or
the activity to be accomplished, and then you will know which experts are needed to
furnish any information or fix a problem. This process is Develop Project Charter.
In developing project charters, expert judgment is used to analyze the inputs and
integrate them to form a project charter. This expert judgment may include persons
who have been preparing project charters, persons with technical knowledge and
information in the deliverable that is to be created, persons abreast with the project
environment within which the project will take place, etc.
-
7/28/2019 4th Ed.Develop Project Charter
8/8
8 | P a g e
OUTPUT
1. Project Charter
We set forth to develop project charter; hence, a project charter is what we have.
When you go back to re-peruse the inputs and their accompanying explanation, youshould get the content of the project charter.
A sample project charter can include the following details:
Project/Product description (High-level) a narrative description of what the
project is intended to create (product/service).
Business need
Customer need fulfillment the product will bring to those who will use it.
Business case/project justification
Project Objectives
Success/Acceptance Criteria criteria to measure project success.
Requirements (High-level) what we need to achieve the projects deliverable.
Pre-identified risks (High-level)
Summary milestone schedule periods at which sub-deliverables are expected to
be delivered.
Summary budget
Project Sponsor Project Manager Assigned responsibility and authority level.
Assignment
Please attempt this assignment to figure out the product scope description, the business need
and the strategic plan of Milano, a manufacturing company.
Milano Co. Ltd. is a manufacturing company engaged in the production of food and
beverages for sub-Saharan Africa. The company is poised to roll out a project next
year to come out with a powdered milk to be packaged in 40g sachet packs. Cowley
Co. Ltd. is a rival company that came out with a similar product last year, and
Cowley seems to be growing its brand among the student population.