4th BEPCII IMAC Meeting - 1 - April 26 - 28, 2006
Status of BEPCII Storage Rings
Ma Li
April 26, 2006
4th BEPCII IMAC Meeting - 2 - April 26 - 28, 2006
SRF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 3 - April 26 - 28, 2006
SRF System 2 superconducting RF cavities
#2 cavity assembly has been completed in the last month and moved into the test station. Input coupler aging and horizontal high-power test of the cavity will be performed soon.
#1 cavity assembly is carrying on at present. The crack on the ferrite surface of one HOM damper SBP-2 has
been found in December 2005. At least 6-7 months is needed to fabricate a new damper. To keep the cavity assembly on schedule, we borrowed a damper from KEK.
2 klystrons and power supplies Klystrons and power supplies have been installed and passed the
acceptance tests in December 2004 and January 2006, respectively. Low-level RF control system Assembly is in progress. Cryogenic system Cryogenic system for SRF with the dummy load has been tested.
Control accuracy of pressure, LHe level satisfies the requirement.
4th BEPCII IMAC Meeting - 4 - April 26 - 28, 2006
bakeout HOM damper clean room
HOM damper
4th BEPCII IMAC Meeting - 5 - April 26 - 28, 2006
#2 cavity in test station
LHe lines
Waveguide and doorknob
4th BEPCII IMAC Meeting - 6 - April 26 - 28, 2006
installation and test the second klystron and power supply
4th BEPCII IMAC Meeting - 7 - April 26 - 28, 2006
wiring and commissioning of LLRF
4th BEPCII IMAC Meeting - 8 - April 26 - 28, 2006
test of cryogenic system for SRF with dummy load
valve box
2000L control dewar
pressure curve
dummy load
4th BEPCII IMAC Meeting - 9 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 10 - April 26 - 28, 2006
Magnet System 95% of the ring magnets has been fabricated and field measured
48 dipoles (67B) 44 old dipoles (70B), field measurement only 88 quads (105Q) 28 old quads (110Q), coil modification 6 old quads (160Q), field measurement only 72 sextupoles (130S) 48 vertical dipole correctors 4 injection kickers 2 wigglers, one is repaired in-vacuum PM wiggler
Following magnets are still in fabrication 1 quad, for SR mode only 8 skew quads 6 special dipole correctors
4th BEPCII IMAC Meeting - 11 - April 26 - 28, 2006
injection kicker magnets and power supplies in test
discharge circuit controller
kicker
HV PS
4th BEPCII IMAC Meeting - 12 - April 26 - 28, 2006
new PM wiggler 1W2
4th BEPCII IMAC Meeting - 13 - April 26 - 28, 2006
4W2 in-vacuum PM wiggler We had a problem of demagnetization for the in-vacuum PM wiggler
. The field is reduced by 30% after nearly 3-year operation in the BEPC storage ring. Study shows that the reason might be the heating caused by HOM and SR. There was no water cooling applied.
The old wiggler has been repaired and upgraded. New NdFeB blocks with demagnetization temperature of 180ºC is
used. Water cooling will be used during the operation and the experime
nt of the cooling effect has been performed. A movable beam chamber has been added to reduce the impedan
ce for the colliding mode. The upgraded 4W2 has been installed into the ring tunnel at present.
4th BEPCII IMAC Meeting - 14 - April 26 - 28, 2006
demagnetized in-vacuum PM wiggler 4W2
burn here
4th BEPCII IMAC Meeting - 15 - April 26 - 28, 2006
repaired in-vacuum PM wiggler 4W2
movable chamber
4th BEPCII IMAC Meeting - 16 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 17 - April 26 - 28, 2006
Power Supply SystemPower supply Qty Amps Volts Status
OB 2 1050 170 installed
IB 2 950 310
105Q 128 200 65 installed
130S 36 200 55 installed
BT 60 25 20 delivered
BV, BH 84 40 26
ISPB 1 1450 100 3 IR special magnet PS
Q1a 1 1750 116 in fabrication and to be delivered in June
Q1b 1 1400 176
Q2, Q3 8 500 40 installed
110Q 6 570 16
AS1 2 1380 14 16 superconducting magnet PS
AS2, AS3, SVCB, SKQ 10 65 12 installed and commissioning underway
SCQ, SCB 4 600 8
4th BEPCII IMAC Meeting - 18 - April 26 - 28, 2006
assembly and commissioning superconducting magnet PS
install B, Q, S-magnet power supplies of rings
4th BEPCII IMAC Meeting - 19 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 20 - April 26 - 28, 2006
Vacuum System 80 arc chambers all delivered 120 straight section chambers 48 (about 40%) is complete. Expect all will be delivered in May. TiN coating for e+ ring chambers Coating for arc chambers has been completed. Coating for straight section chambers is underway. Measurement results show that maximum SEY are 1.6-1.9. 175 discrete photon absorbers 129 (73.7%) complete 180 RF shielded bellows all delivered vacuum valves, pumping and monitoring devices all delivered
4th BEPCII IMAC Meeting - 21 - April 26 - 28, 2006
Arc chamber distortion We found an arc chamber problem in October of last year, when ¾ o
f the chambers were completed and 24 of 80 chambers were pre-assembled.
The baking temperature is required below 150ºC. The vendor overheated during the bakeout, causing the chambers to be depressed by as much as over 10 mm. This closes the 15 mm high anti-chamber gap and blocks the SR.
The simulation has been made and the height of anti-chamber gap of minimum 10 mm is decided. We measured all 80 arc chambers and found 20 have to be fixed.
Several methods were tested to recover the chamber distortion and two of them have been used finally. Fill the gas N2 into the chamber to 3.8 atm to pump back the cha
mber dimension. (for small distortion) Pull outward and distort the chamber locally. (for large distortio
n)
4th BEPCII IMAC Meeting - 22 - April 26 - 28, 2006
BEPC chamber
depressed BEPCII chamber
distortion here
4th BEPCII IMAC Meeting - 23 - April 26 - 28, 2006
filling compressed gas N2
gas N2 input
4th BEPCII IMAC Meeting - 24 - April 26 - 28, 2006
pulling outward jack tooling block jack
4th BEPCII IMAC Meeting - 25 - April 26 - 28, 2006
max. distortions before and after corrections
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79
真空盒序号
最大
变形
量(mm)
矫形前矫形后
From here bakeout temp. was asked to be lower than
120ºC.
(date of delivery)
4th BEPCII IMAC Meeting - 26 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 27 - April 26 - 28, 2006
Control System Device control Development of hardware and software of control system for PS, vacu
um, SRF, cryogenics, etc has been completed. Main tasks of the next step are installation and commissioning.
Timing system Event timing system has been setup and provides trigger signals to the
linac. Server computer and network Installed Accelerator high-level applications Optics, COD correction, iBump, transport line, etc. nearly complete Interlock and machine protection system in progress
4th BEPCII IMAC Meeting - 28 - April 26 - 28, 2006
installation and commissioning for PS control system
4th BEPCII IMAC Meeting - 29 - April 26 - 28, 2006
event timing system
4th BEPCII IMAC Meeting - 30 - April 26 - 28, 2006
commissioning cryogenic control system
4th BEPCII IMAC Meeting - 31 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 32 - April 26 - 28, 2006
Beam Instrumentation System 134 beam position monitors all arc chamber BPM complete 2 bunch current monitors hardware delivered, software development in progress 2 tune measurement system components ordered 150 beam loss monitors processing electronics in fabrication. 2 DC current monitors ready for installation 2 synchrotron light monitors ready for installation 2 transverse bunch-by-bunch feedback prototype electronics tested in BEPC one of the two 4-strip kickers delivered and tested
4th BEPCII IMAC Meeting - 33 - April 26 - 28, 2006
SLM BPM
button
4th BEPCII IMAC Meeting - 34 - April 26 - 28, 2006
transverse bunch-by-bunch feedback system
feedback off feedback on
sideband
prototype
4th BEPCII IMAC Meeting - 35 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 36 - April 26 - 28, 2006
IR System 2 superconducting IR magnets delivered and installed 2 septum bending magnets (ISPB) delivered and field measured 4 two-aperture quads (Q1) delivered and field measured 8 slim quads (Q2, Q3) in fabrication 12 dipole correctors in fabrication IR vacuum chambers in fabrication, expect to be complete in May
4th BEPCII IMAC Meeting - 37 - April 26 - 28, 2006
install superconducting IR magnets SC wires
4th BEPCII IMAC Meeting - 38 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 39 - April 26 - 28, 2006
Pre-assembly and Installation The pre-assembly and pre-alignment on magnet/chamber rafts
restarted at the beginning of last December after one-month interruption caused by the arc chamber problem.
Now 50 (59.5%) rafts have been completed. All 84 rafts will be completed in the early July according to the updated schedule.
The installation of the first magnet raft has started on March 2. 29 (34.5%) have been located since then.
A traveler (inspection sheet) is designed for QA. This traveler includes pertinent pre-assembly records and inspection results.
The procedure for the combined commissioning of magnet, PS and control systems has been established. The step-by-step inspection will be performed before the commissioning.
4th BEPCII IMAC Meeting - 40 - April 26 - 28, 2006
50 rafts pre-assembled 29 rafts installed
4th BEPCII IMAC Meeting - 41 - April 26 - 28, 2006
traveler of pre-assembly
signatures
4th BEPCII IMAC Meeting - 42 - April 26 - 28, 2006
procedure for inspection and combined commissioning of magnet, PS and control systems
4th BEPCII IMAC Meeting - 43 - April 26 - 28, 2006
dismantling of old ring components
4th BEPCII IMAC Meeting - 44 - April 26 - 28, 2006
installation
4th BEPCII IMAC Meeting - 45 - April 26 - 28, 2006
install RF shielded bellows
4th BEPCII IMAC Meeting - 46 - April 26 - 28, 2006
RF SystemMagnet SystemPower SuppliesVacuum SystemControl System
Beam InstrumentationInteraction Region
Pre-assembly and InstallationScheduleSummary
4th BEPCII IMAC Meeting - 47 - April 26 - 28, 2006
Backup scheme without SCQ A backup scheme for the IR lattice configuration will be adopted.
Two normal conducting dipoles (70B) are used to replace the two superconducting IR magnets. With this backup scheme, the outer ring, the electron ring and positron ring can be commissioned, respectively.
The main purpose of the backup scheme is to save the time of about 3 months for the SCQ field measurement with detector solenoid and the field mapping of the detector solenoid itself.
4th BEPCII IMAC Meeting - 48 - April 26 - 28, 2006
beam orbit in IR for the backup scheme
70B dipole 70B dipole
4th BEPCII IMAC Meeting - 49 - April 26 - 28, 2006
IR layout of the backup scheme
70B dipole 70B dipole
4th BEPCII IMAC Meeting - 50 - April 26 - 28, 2006
Schedule of IR
-2006/05/03 install SCQ and valve-box and wiring2006/05/04-2006/06/10 38 preparation & check for SCQ cryogenic system2006/06/11-2006/07/08 28 commissioning SCQ cryogenic system2006/07/09-2006/08/27 50 SCQ field measurement in IR without detector2006/08/28-2006/09/07 11 move out SCQ from IR2006/09/08-2006/09/21 14 install IR components (backup scheme)2006/09/22-2006/10/09 18 commissioning vacuum, PS etc. of IR2006/10/10- start commissioning of the rings
2006/09/08-2006/09/18 11 install SCQ at BESIII pre-assembly location2006/09/19-2006/10/22 34 commissioning cryogenic system2006/10/23-2007/01/15 84 field measurements for SCQ and detector soli.
4th BEPCII IMAC Meeting - 51 - April 26 - 28, 2006
Beam Commissioning Schedule
2006/10/10-2006/11/08 30 commissioning outer ring for SR mode
2006/11/09-2006/12/28 50 commissioning beam lines and SR operation
2006/12/29-2007/01/25 28 commissioning e ring
2007/01/26-2007/02/22 28 commissioning e ring
2007/02/23-2007/03/31 37 move SCQ into the IR
2007/04/01-2007/04/20 20 commissioning e ring
2007/04/21-2007/05/10 20 commissioning e ring
2007/05/11-2007/06/09 30 commissioning for collision mode
2007/06/10-2007/08/23 75 commissioning for colli. mode with large current
2007/08/24-2007/09/18 26 move BESIII detector into the IR
2007/09/19-2007/10/14 27 commissioning for collision mode
2007/10/15- HEP operation with detector
Jiuqing will give detailed descriptions for each step of commissioning.
4th BEPCII IMAC Meeting - 52 - April 26 - 28, 2006
Summary
Many problems were encountered and resolved. Progress has been made since the last IMAC meeting.
The BEPC old ring has been removed in the last July. Installation of magnet/chamber rafts started on March 2 of this year.
Comparing with the schedule presented on the last IMAC meeting, the updated schedule delayed by several months, due to arc chamber problem, delay of straight section chambers, delay of superconducting equipments and cryogenic system.
Installation, horizontal test, field measurement of superconducting IR magnets is one of the critical paths of the project. A backup scheme of using two normal conducting dipoles instead of SC IR magnets will be adopted, in order to start the commissioning of the BEPCII rings in the last quarter of this year.
4th BEPCII IMAC Meeting - 53 - April 26 - 28, 2006
Thank you for attentions !