4.heat load calculations211207

Upload: sooraj-vs

Post on 14-Feb-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 4.Heat Load Calculations211207

    1/41

    Heat Load Calculations

  • 7/23/2019 4.Heat Load Calculations211207

    2/41

    Building Survey

    The orientation of the building is thefirst parameter that a hvac engineer

    should know before designing the

    system required. The south westcorner of the building will susceptible

    to the most intense heat rays from the

    sun if it is e!posed" compared to allother corners. So the heat transfer

    through that part will be higher.

  • 7/23/2019 4.Heat Load Calculations211207

    3/41

    #ield sketches complete

    architectural drawings civilplans are the basic aspects of

    the good survey. $very H%&C

    engineer should be aware

    about the importance of

    building survey.

  • 7/23/2019 4.Heat Load Calculations211207

    4/41

    'se of Space

    &pplication of the conditioned

    space is another parameter.

    (ffice Hospitals restaurantsfactories machine shops etc.

    &ccording to the application

    the air conditioning system will

    differ.

  • 7/23/2019 4.Heat Load Calculations211207

    5/41

    )hysical *imensions of &ir

    conditioning Space Length breadth height of the

    space+ distance between floor

    and ceiling+ distance betweenfloor and false ceiling is also

    an important factor. The area of

    the space to be air conditioned

    is a very important data.

  • 7/23/2019 4.Heat Load Calculations211207

    6/41

    Columns and Beams

    Si,e depth location of

    beams and columns

  • 7/23/2019 4.Heat Load Calculations211207

    7/41

    Construction material

    Type of material used forconstruction is another data

    with which the heat transfercan be calculated. *ifferent

    type of materials will have

    different type of heattransmission coefficient.

  • 7/23/2019 4.Heat Load Calculations211207

    8/41

    Heat transmission

    coefficient is defined as therate of heat transferredthrough the building barrier.

    -t is determined by ' /012/3 24 3 25 3 66667 where

    2 is the resistance offeredby different type ofmaterials.

  • 7/23/2019 4.Heat Load Calculations211207

    9/41

    Surrounding conditions

    -t should be checkedwhether the e!terior of walls

    windows and roofs areshaded by ad8acentbuildings or e!posed tosunlight whether thead8acent space is

    conditioned or not.

  • 7/23/2019 4.Heat Load Calculations211207

    10/41

    Location of *oors and

    9indows

    Type si,e and #requency of

    use of the doors and

    windows will affect theamount of heat transfer.

  • 7/23/2019 4.Heat Load Calculations211207

    11/41

    Stairways Lift corridors

    $scalators and open to non

    air conditioned areas

    -t is not easy to air

    condition open spaces as

    the level of infiltration will be

    very high. This will result inwastage of air conditioning.

  • 7/23/2019 4.Heat Load Calculations211207

    12/41

    (ccupancy

    Total number of people in thespace to be air conditioned. $ach

    and every human being will emit

    a lot of heat energy due to themetabolic activity of human body.

    *uration of the occupancy and

    nature of activity should also be

    known.

  • 7/23/2019 4.Heat Load Calculations211207

    13/41

    Lighting

    Type of lighting usedinside the space will be afactor as the lights usedwill emit lot of heatenergy. There are

    different types of lightsaccording to which theheat emitted differs.

  • 7/23/2019 4.Heat Load Calculations211207

    14/41

    The types of lightscommonly used areincandescent fluorescentrecessed and e!posed.

    The amount of air flowshould be known or elsethe estimate should be

    done on th basis ofwatts 0sq.ft.

  • 7/23/2019 4.Heat Load Calculations211207

    15/41

    &ppliances

    There will be differenttypes of appliances and

    equipments used in the space

    to be air conditioned Theequipment will deliver some

    heat inside the space to beconditioned.

  • 7/23/2019 4.Heat Load Calculations211207

    16/41

    Business machines

    electronic equipment etc canbe present in the area to be

    conditioned. The locationwattage rating and whether it is

    hooded or not are the different

    types of parameters to bechecked.

  • 7/23/2019 4.Heat Load Calculations211207

    17/41

    %entilation required There are different standards set for

    the different type of requirements. C#:0sq. ft

    C#:0person

    C#:0room

    These parameters should also be

    taken in to account. %entilationrequirement will in turn play aimportant role in maintaining good

    indoor air quality.

  • 7/23/2019 4.Heat Load Calculations211207

    18/41

    -ndoor unit and outdoor unit

    location )arameters for indoor unit location

    are There should be no obstruction to

    air flow and distribution ofconditioned air. There should enough space for

    servicing. )iping and wiring work can be easily

    connected. There should be a solid wall or

    ceiling to mount the unit.

  • 7/23/2019 4.Heat Load Calculations211207

    19/41

    )arameters for outdoor unitlocation are

    There should be good aircirculation

    There should be no other ma8orheat interference.

    The e!haust air should not besucked in once again for

    recirculation. The unit should not be kept

    very close to corrosive

    materials or environment.

  • 7/23/2019 4.Heat Load Calculations211207

    20/41

    $stimation of heat load

    #or summer air conditioning the airconditioned space has to be maintained

    at a lower temperature than the

    surrounding temperature. The moisturelevel also should be maintained at a lowe

    level compared to the atmospheric level.

    So there has to be heat transfer betweenthe conditioned space and the

    surroundings.

  • 7/23/2019 4.Heat Load Calculations211207

    21/41

    &fter building survey a H%&C

    engineer should know the amount

    of heat transfer that should take

    place between the space to be

    conditioned and the surroundings.#or this heat load calculation and

    estimation is required. Hence it is

    required for the design andselection of air conditioning

    equipment.

  • 7/23/2019 4.Heat Load Calculations211207

    22/41

    ;eneral )rocedure

    To calculate a design

    cooling or heating load

    information about buildingdesign and weather data at

    design conditions should beprepared.

  • 7/23/2019 4.Heat Load Calculations211207

    23/41

    (utside design conditions

    The first important step is to

    fi! the peak outside

    condition. ie+ the date andtime of year when the peak

    conditions can prevail.

  • 7/23/2019 4.Heat Load Calculations211207

    24/41

    -nside design conditions

    -ndoor air temperature to be

    maintained in each space

    should be dictated by theapplication.

    S l t i i i th h

  • 7/23/2019 4.Heat Load Calculations211207

    25/41

    Solar transmission gain through

    walls roofs glass and partitions

    &s a result of absorption of directradiation of sun temperature of wall

    roof glass and partitions rises

    above the ambient temperature.This results in large temperature

    difference with respect to the airconditioned space. The heat

    transfer coefficient or '

  • 7/23/2019 4.Heat Load Calculations211207

    26/41

  • 7/23/2019 4.Heat Load Calculations211207

    27/41

  • 7/23/2019 4.Heat Load Calculations211207

    28/41

  • 7/23/2019 4.Heat Load Calculations211207

    29/41

    Then compute the heat

    transmission loss for each kind of

    wall glass floor ceiling and roof in

    each building by multiplying the

    heat transfer coefficient in eachcase by area of the surface and

    temperature difference between

    indoor air and outdoor air orad8acent lower temperature spaces.

    -nfiltration

  • 7/23/2019 4.Heat Load Calculations211207

    30/41

    -nfiltrationCompute the heat loss associated with

    infiltration through cracks and openingsof doors and windows. These valuesdepend on the kind of crack and temp.difference of indoor and outdoor air. Theair blowing in the opposite direction ofthe building which is higher in moisturecontent and temperature to infiltrate

    through the cracks and openings. Thisresults in the sensible and latent heattransfer to the conditioned space and

    locali,ed heat gains.

  • 7/23/2019 4.Heat Load Calculations211207

    31/41

    % til ti

  • 7/23/2019 4.Heat Load Calculations211207

    32/41

    %entilation

    9hen positive ventilation

    using outside air is providedto the conditioned space

    energy required to conditionthis air to the temperaturerequired must be provided by

    the unit. So associated loaddue to fresh air should also becalculated. This is consider as

    a forced infiltration.

  • 7/23/2019 4.Heat Load Calculations211207

    33/41

  • 7/23/2019 4.Heat Load Calculations211207

    34/41

    -nternal Heat ;ain

    -nternal heat gain throughoccupancy lights and otherappliances should also be

    calculated. Human body throughmetabolism generates heat withinitself and releases it by radiation

    convection and evaporation fromthe surface. -lluminants will convertelectrical power to light and

    sensible heat.

  • 7/23/2019 4.Heat Load Calculations211207

    35/41

    9hy we require fresh airopening in the air

    conditioning system=

    - d &i > lit

  • 7/23/2019 4.Heat Load Calculations211207

    36/41

    -ndoor &ir >uality

    %entilation or outside fresh air in to

    the air conditioned space is veryimportant. -t is to replace the o!ygenconsumed and to dilute the carbon

    dio!ide and pollutants in the air.)ollutants are like bacteria fungusdust materials chemicals etc.Therefore it is important to removethe contaminants so that we canimprove the indoor air quality.

    #resh air intake will never remove

  • 7/23/2019 4.Heat Load Calculations211207

    37/41

    #resh air intake will never removethe contaminants but they willdilute them so that thecontaminants can be kept in thepermissible limits according to thestandard levels. (dour removal is

    handled by introducing freshoutdoor air in to the air handlingunit. This air is mi!ed with the

    return air to improve the air quality.This should be be done beforegetting the air treated at the

    cooling coil.

  • 7/23/2019 4.Heat Load Calculations211207

    38/41

    &pplication C#:1%ol.of#resh air7

    (ffice Space 4?

    2estaurants 4?

    Bars 5?

    Conference room 4?(perating rooms 5?

    Supermarkets /@

    &uditoriums /@

    Laboratries 4?

    Hotel rooms 5?

  • 7/23/2019 4.Heat Load Calculations211207

    39/41

    The following steps can improve

    indoor air quality

    :aintain a slight positive pressure

    inside the conditioned space so

    that infiltration can be prevented. &ir filtration is very important so

    that the particulates can be

    prevented from passing on to theconditioned space.

  • 7/23/2019 4.Heat Load Calculations211207

    40/41

    Cleaning of supply return and fresh airducts at the time of commissioning and a

    regular intervals of operation. The condensate should be prevented

    from getting stagnant in the drain pan.

    The condensate will become a breedingpoint of bacteria and fungi.

    &void fibre glass lined &H'As+ since it isinert by itself once it becomes wet thenit will become a collection area ofparticulate material and microbial growth.

  • 7/23/2019 4.Heat Load Calculations211207

    41/41

    )2($CTS