47189_1248369986_773

Upload: chiuchaorong

Post on 08-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 47189_1248369986_773

    1/17

    4 0

    V o l . 3 6 No . 2 J une 2 0 0 3

    1. Introduction

    Located almost at the center of the Honshu-Shikoku

    Bridge Onomichi-Imabari Route (Nishiseto Expressway

    or popularly called Shimanami Kaido), the Tatara

    Bridge is the worlds longest cable stayed bridgemeasuring 1 480 m in total length and 890 m in center

    span, linking Ikuchijima Island in Hiroshima Prefecture

    and Ohmishima Island in Ehime Prefecture. The Third

    Construction Bureau of the Honshu-Shikoku Bridge

    Authority placed orders for design, fabrication and

    erection of the bridge in January 1994 and the IHI-

    Yokogawa-NKK-Takigami-Matsuo Specified Construction

    Joint Venture was put in charge of the Ohmishima

    Island (Ehime Pref.) side of the bridge.

    This paper provides general information on the design

    of the Tatara Bridge.

    2. Outline of the Tatara Bridge

    The Tatara Bridge is the worlds longest cable stayed

    bridge, whose 890 m center span is longer than that of

    the Normandy Bridge in France by 34 m. Fig. 1

    shows the general arrangement of the Tatara Bridge,while the main tower and the main girder section are

    shown in Fig. 2 and Fig. 3, respectively. The section

    distribution is shown in Fig. 4. The main tower is 220

    m high and designed as an inverted Y shape. It has a

    cross-shaped section with corners cut for higher wind

    stability and better landscaping.

    The main girder section consists of three spans, 270

    m, 890 m, and 320 m, and measures 1 480 m in total

    length. As either side span is shorter than the center

    span, PC girders are installed at each end of both side

    span sections as counterweight girders to resist negative

    Design of Tatara Bridge

    YABUNO Masashi : Design Department, Bridge & Road Construction Division,

    Logistics Systems & Structures

    FUJIWARA Toru : Manager, Planning & Development Department, Honshu-

    Shikoku Bridge Authority

    SUMI Kazuo : Manager, Bridge Maintenance Section, Naruto Operation

    Office, Honshu-Shikoku Bridge Authority

    NOSE Takashi : Manager, Overseas Project Department, Bridge & Road

    Construction Division, Logistics Systems & Structures

    SUZUKI Masanao : Manager, Design Department, Bridge & Road Construction

    Division, Logistics Systems & Construction

    The Tatara Bridge is the worlds longest steel-concrete hybrid cable stayed bridge. It measures 1 480 m intotal length and 890 m in the center span. The side spans consist of steel and prestressed concrete (PC) girders.

    IHI, as one of the joint venture member companies, received the order for design, fabrication, and erection of

    the Ohmishima Island side of the bridge in 1994. The bridge design is described.

    1 480 000

    890 00050 000 170 00050 000

    105 500

    PC girder

    1 312 000

    Steel girder

    T.P.+0.000

    T.P.-33.000

    T.P.+44.460

    Ikuchijima Island side

    (Hiroshima Pref.)

    39000

    25 000

    T.P.+6.000 N.H.H.W.L. T.P.+2.200

    T.P.+47.661

    T.P.+46.215 T.P.+28.200

    T.P.+226.000

    25 000

    19000

    T.P.-13.000

    Ohmishima Island side

    (Ehime Pref.)

    T.P.+44.135

    T.P.+6.000T.P.+46.215

    T.P.+226.000

    62 500

    PC girder

    270 000 50 000

    M M M K K MM

    3P P3 4P2PP11A P2

    (Note) T.P. : Mid-tide in Tokyo Bay (unit : m)N.H.H.W.L : Nearly highest tide level (unit : m)

    Fig. 1 General arrangement (unit : mm)

  • 8/7/2019 47189_1248369986_773

    2/17

    4 1

    V o l . 3 6 No . 2 J une 2 0 0 3

    reaction. This cable stayed bridge thus uses a steel and

    PC connection girder.

    The bridge has a total width of 30.6 m, including a

    road for motorized bicycles and pedestrians (hereafter

    called sidewalk) and a girder height of 2.7 m. It uses

    flat box girders attached with fairings to ensure wind

    stability. Cables installed in 21 levels were two-plane

    multi-fan cables (maximum cable length: about 460 m).

    Cables of the bridge have indented surfaces in the

    polyethylene cable coating, similar to dimples on a golfball, to resist vibration caused by both windy and rainy

    weather (rain vibration) (Fig. 5).

    The outline of the erection is illustrated in Fig. 6.

    The main girders were erected in a balancing method,in which girders for the main span and side spans are

    erected alternately block by block, up to the seventh

    level. Then, about 100 m long steel girders were

    25 00043 000

    12 000 12 000

    17 000 8 5008 500

    T.P.+226.000

    T.P.+45.400

    T.P.+46.215

    T.P.+38.500

    32 500

    15 420

    3000

    3000

    6000

    19000

    32500

    2500

    36900

    220000

    180600

    6 0006 000

    C1C42

    C41

    C40

    C39

    C38

    C37

    C36

    C35

    C3

    4

    C33

    C32

    C31

    C30

    C29

    C28

    C27

    C26

    C25

    C24

    C23

    C22

    C43 C4

    4

    C45 C4

    6

    C47 C4

    8

    C49 C5

    0

    C51 C5

    2

    C53 C5

    4

    C55 C

    56

    C57 C

    58

    C59

    C60

    C61

    C62

    C63

    C2

    C3 C4

    C5 C

    6

    C7 C

    8

    C9

    C10

    C11 C

    12

    C13

    C14

    C15

    C16

    C17

    C18

    C19

    C20

    C21

    C84

    C83

    C82

    C81

    C80

    C79

    C78

    C77

    C

    76

    C75

    C74

    C73

    C72

    C71

    C70

    C69

    C68

    C67

    C66C

    65

    C64

    25 000

    2P 3P

    43 000

    T.P.+6.000

    12 000 12 000

    17 000

    T.P.+226.000

    T.P.+45.400

    T.P.+46.215

    T.P.+38.500

    N.H.H.W.L.T.P.+2.200

    32 500

    15 420

    3000

    3000

    6000

    39000

    32500

    2500

    36900

    220000

    180600

    T.P.+6.000

    T.P.-33.000

    T.P.-13.000

    N.H.H.W.L.T.P.+2.200

    Fig. 2 General arrangement (main tower) (unit : mm)

    2 500 2 5002 245 2 245295

    9 500

    6 380 6 380

    2700

    9 040

    21 8004 400 4 400

    Center distance of cable anchor points 23 000

    30 600

    Road forbicycles

    andpedestrians

    Road formotorizedbicycles

    Road forbicycles

    andpedestrians

    Road formotorizedbicycles

    9 500260260295

    1% 2%

    Shikoku-bound lane Honshu-bound lane

    2% 1%

    Cross section of steel girder

    Diaphragm section Lateral rib section

    2 500 2 5002 245 2 245

    295

    9 500

    21 8004 400 4 400

    Center distance of cable anchor points 23 000

    30 600

    1 0001 000 9 500

    260

    260

    295

    2700

    Shikoku-bound lane Honshu-bound lane

    Cross section of PC girder

    Side span section Supporting point

    1% 2% 2% 1%

    Fig. 3 General arrangement (main girder section) (unit : mm)

    Fig. 5 Indent of cable surface

  • 8/7/2019 47189_1248369986_773

    3/17

    4

    2

    890 000

    30 000 2222 000 28 000

    28 000 22 000

    9 000108 000

    = 80 000

    4 20 000

    = 80 000

    19 20 000 = 380 000 19 20 000 = 380 000 2 000 13 000

    11 000

    9 000 16 000

    170 000

    5 500 Steel girders 1 312 000

    161616

    16

    19

    19

    19

    19

    14

    16

    1212 14141413 1111 10

    320

    320

    240

    6

    3202408

    320

    240

    8

    22

    22

    22

    22

    15

    25025

    25025

    25025

    25025

    20022

    20022

    20022

    20022

    16016

    17016

    20022

    20022

    200192001925025 20019 1901923022

    16

    16 14 14 12

    250 000 60 00060 000 40 00040 00060 00060 000 60 00060 000

    60 000 20 00020 000 20 00020 00032 000 21 000 21 021 000 14 000 32 500

    32 00010 500

    1622

    50 00050 000

    1 480 000

    2PP11A P2

    CL

    2221201918171615

    JIGEDCBA

    141312

    BCD

    1110987654321

    Interval of cableanchor points

    Side span length

    EGIJLMLJIHN

    Fig. 4 Section distribution (unit : mm)

    Section number

    Section classification

    Sectional changelength

    Steel plate deckflat rib

    Steel plate deck thickness

    Steel plate deck trough rib

    External web platethicknessExternal webplate flat rib

    Internal web platethickness

    Lower flange thickness

    Lower flange trough rib

    Internal webplate flat rib

  • 8/7/2019 47189_1248369986_773

    4/17

  • 8/7/2019 47189_1248369986_773

    5/17

    4 4

    V o l . 3 6 No . 2 J une 2 0 0 3

    altogether erected as a single large block with floating

    cranes to the PC girder section.

    The length of the large girder block in the side span,

    which is about 100 m, was determined and designed

    to be self-supporting as a single beam. It is the first

    time in the world that both balancing erection and largeblock erection were used for erection of girders. For

    the center span, the work of main-girder cantilever

    erection using traveler cranes was conducted block by

    block for both work areas.

    3. Basic design conditions

    3.1 Design conditions

    The Joint Venture started its detailed design work in

    January 1994 and continued for about one and a half

    years. Table 1 shows the design specifications, while

    Table 2 shows a list of quantities used in the design.

    3.2 LoadsTable 3 and 4 show design loads and combinations of

    loads, respectively.

    4. General structural analysis

    4.1 Analytical procedure

    The general structural analysis flowchart is shown in

    Fig. 7. To begin with, cable prestress was determined

    by infinitesimal deformation analysis to finalize the

    condition of the final profile. Then, sectional force

    analysis was conducted for each loading case by

    linearized finite displacement analysis using this

    completed system model in which initial internal forcewas set under this condition of the final profile. Then,

    sectional force, displacement and reaction were

    calculated and the results were edited for use in design

    of each member.

    4.2 Analytical model

    4.2.1 Modeling of main girders

    A three-dimensional skeleton model was used for

    analysis of the overall structure (Fig. 8). It is a fishbone

    model in which each girder is a single road and virtual

    members are extended to cable anchor points. During

    modeling, the axial centers of girders were placed at

    the middle point between the diagram center and theshear center so as to allow it to be used also as a

    dynamic analysis model.

    4.2.2 Modeling of main tower

    Cable length was taken into consideration for analysis

    of the main tower by creating a main tower model in

    which virtual members are extended from the axial

    center of the tower to cable anchor points (Fig. 9). In

    reality, even though the target points of cables for the

    center span and the side spans are set on the axial line

    of the main tower with some deviation from each other,

    they are sometimes designed as identical in structural

    analysis. In this case, it is easy, in analysis, to makebending moment of the main tower zero by balancing

    the horizontal components of cable tension in the final

    profile. But if we try to manage an actual bridge with

    this tension and balance horizontal components of force,

    bending moment will occur in the tower and can slopethe tower due to misaligned setting of target points in

    the actual structure and the defective consequence will

    appear in the form of camber errors in girder.

    Item Description

    Route 317 (Onomichi-Imabari route)

    Tatara Bridge

    Three-span continuous composite cable stayed bridge

    L = 1 480

    L = 270 + 890 + 320

    B live load (Specifications for Highway Bridges)Feb. 1994

    Category 1, Class 3

    V= 80

    4 lanes (9.5 m 2) + sidewalk (2.5 m 2)

    2.0 straight line

    1.0 straight line

    A = 300, R = 600

    Straight line to a plane

    A = 539.838, R = 599.700

    0.65 grade to straight line

    0.325 parabola

    26 m from nearly highest tide level(T.P.+2.200+26.000)

    Inverted Y shape with steel slits (base designedas a trapezoidal structure with the bottom sideshorter than the topside)

    H= 220 (T.P. + 226.000)

    Base : 12TT 8.5LL, Top : 6TT 6LL

    (LL : direction of bridge axis; TT : directionperpendicular to bridge axis)

    Steel girder section: 3-cell steel box girderPC girder section: 3-cell PC box girder

    H= 2.7(at the center of the bridge of the standard part)

    Total width : 30.6, Outside web interval : 21.8,Cable anchoring width : 23.0

    Two-plane multi-fan 21-level non-grout PWS(strand f 7 mm)

    Asphalt pavement

    Steel girder section : 65, PC girder section : 75

    30

    Steel girder section : Steel plate deck,PC girder section : PC slab

    Fixing block method

    Web-mounting square column anchoring method

    SS400, SM490Y, SM570

    SS400, SM490Y

    sck= 24{sck= 240}

    s= 640

    {s= 6 400}

    (Note) F : FIX

    M : MOVE

    (N/mm2

    ){kgf/cm2}

    ( N/mm2)

    {kgf/cm2}

    1A

    F

    F

    M

    P1

    F

    M

    M

    P2

    F

    M

    M

    P3

    F

    M

    M

    4P

    F

    F

    M

    2P

    F

    F

    K= 2 000 t/m

    3P

    F

    F

    K= 2 000 t/m

    Table 1 Design specification

    Cross grade

    Road name

    Bridge name

    Bridge type

    Bridge length (m)

    Span length (m)

    Design live load

    Road specification

    Design speed (km/h)

    Number of lanes

    Under clearance (m)

    Main tower

    Main girder

    Cable shape

    Deck slab type

    PC girder member standarddesign strength

    Cable strand allowablestress

    Vertical direction

    Direction of bridge axis

    Direction perpendicular to bridge axisSupportingconditions

    Pavement

    Anchoringmethod

    Main steelmembers

    Horizontalalignment

    Verticalalignment

    Roadway (%)

    Sidewalk (%)

    Side span (%)

    Shape

    Tower height (m)

    Sectional dimension (m)

    Girder height (m)

    Girder width (m)

    Type

    Main tower side

    Main girder side

    Main tower

    Main girder

    Roadway (mm)

    Sidewalk (mm)

    Shape

    Center span (%)

    Side span on the 1A side (m)

    Center span

    Side span on the 4P side (m)

  • 8/7/2019 47189_1248369986_773

    6/17

    4 5

    V o l . 3 6 No . 2 J une 2 0 0 3

    0.607

    0.607

    0.009

    0.000

    0.000

    0.000

    0.007

    0.002

    0.001

    0.000

    0.000

    0.004

    0.005

    0.010

    0.000

    0.009

    0.016

    0.004

    0.030

    0.021

    0.011

    0.000

    0.000

    0.002

    0.000

    0.134

    0.740

    0.113

    0.004

    0.117

    0.002

    0.003

    0.001

    0.000

    0.005

    0.122

    2.532

    0.005

    0.183

    0.073

    2.793

    0.023

    0.033

    0.008

    0.002

    0.003

    0.003

    0.001

    0.072

    2.865

    1.219

    12.501

    12.501

    0.193

    0.004

    0.009

    0.001

    0.141

    0.035

    0.024

    0.005

    0.006

    0.086

    0.106

    0.206

    0.008

    0.188

    0.332

    0.074

    0.620

    0.440

    0.218

    0.007

    0.001

    0.041

    0.007

    2.753

    15.254

    2.325

    0.078

    2.403

    0.038

    0.052

    0.011

    0.009

    0.109

    2.513

    52.164

    0.109

    3.768

    1.500

    57.541

    0.473

    0.673

    0.155

    0.045

    0.059

    0.055

    0.018

    1.477

    59.018

    25.121

    16 401

    16 401

    285

    6

    14

    2

    209

    52

    36

    8

    9

    127

    157

    305

    12

    278

    492

    109

    917

    651

    323

    10

    2

    61

    10

    4 075

    20 476

    3 441

    116

    3 557

    56

    77

    16

    13

    162

    3 719

    11 476

    24

    829

    330

    12 659

    104

    148

    34

    10

    13

    12

    4

    325

    12 984

    37 179

    910

    910

    19

    0

    1

    1

    13

    3

    2

    0

    3

    8

    9

    18

    0

    20

    31

    0

    72

    31

    18

    1

    0

    2

    0

    252

    1 162

    476

    16

    492

    0

    0

    0

    1

    1

    492

    3 387

    6

    274

    0

    3 667

    28

    32

    8

    0

    0

    0

    0

    68

    3 735

    5 389

    8 902

    8 902

    148

    3

    8

    1

    115

    28

    19

    3

    6

    69

    82

    159

    6

    160

    260

    41

    496

    356

    164

    5

    1

    32

    5

    2 167

    11 069

    1 763

    58

    1 821

    28

    38

    8

    7

    81

    1 902

    5 756

    12

    418

    165

    6 351

    52

    74

    17

    5

    6

    6

    2

    162

    6 513

    19 484

    7 499

    7 499

    137

    3

    6

    1

    94

    24

    17

    5

    3

    58

    75

    146

    6

    118

    232

    68

    421

    295

    159

    5

    1

    29

    5

    1 908

    9 407

    1 678

    58

    1 736

    28

    39

    8

    6

    81

    1 817

    5 720

    12

    411

    165

    6 308

    52

    74

    17

    5

    7

    6

    2

    163

    6 471

    17 695

    Steel girder

    Steel girder - subtotal

    Base structures of accessories A

    Base structures of accessories B

    Drainage A

    Access door

    Rail for maintenance vehicle A

    Rail for maintenance vehicle B

    Supporting member in girder A

    Supporting member in girder B

    Bridge light base

    Maintenance gangway

    Safety fencing for vehicles A (median strip)

    Safety fencing for vehicles B (shoulder)

    Safety fencing for vehicles B2 (shoulder integrated)

    Fairings A (shop attachment)

    Fairings B (field attachment)

    Fairings C (PC)

    Sidewalk (1) (shop installation)

    Sidewalk (2) (shop installation)

    Handrailing of sidewalk

    NTT supporting (1)

    NTT supporting (2) (PC)

    Chugoku Electric Power Co. supporting (1)

    Chugoku Electric Power Co. supporting (2) (PC)

    Main girder accessories - subtotal

    Main girder related - total

    Cable

    Socket

    Cable - subtotal

    Anchor block for main tower

    Anchor block for main girders

    Shim plate

    Cable cover

    Cable attachments - subtotal

    Cable related - total

    Main tower

    Remaining materials for erection of main tower

    Welding of main tower

    Fixing block

    Main tower proper - subtotal

    Connecting corridor

    Accessories for internal tower

    Accessories for external tower

    Accessories of tower top

    Cable waterproofing pipe

    Obstacle light

    Tower-attached management equipment

    Accessories of main tower - subtotal

    Main girder

    Main girder

    accessories

    Cable

    Cable

    attachments

    Main tower

    Main tower

    accessories

    Grand total of Tatara Bridge

    Main tower related - total

    (Note) The mass of steel per square meter was calculated based on the effective width of 20.6 m.

    Mass ofsteel/m2

    (t/m2)

    Mass ofsteel/m(t/m)

    Total of entireTatara Bridge

    work (t)

    IHI portion

    (t)

    Phase 1work - total

    (t)

    Phase 2work - total

    (t)RemarksItem

    Table 2 Amount of quantity

    Calculated assuming steel girder length is 1 312 m

    Calculated assuming bridge length is 1 480 m

    Total for steel girder section

    Calculated assuming bridge length is 1 480 m

    Calculated assuming tower height is 220 m

    Calculated assuming bridge length is 1 480 m

  • 8/7/2019 47189_1248369986_773

    7/17

    4 6

    V o l . 3 6 No . 2 J une 2 0 0 3

    11.01

    17.05

    1.00

    1.10

    0.36

    13.47

    19.51

    3.13

    0.43

    3.56

    0.00

    0.14

    0.24

    0.18

    0.04

    0.60

    4.16

    0.03

    0.18

    0.05

    0.06

    0.20

    0.52

    0.15

    0.02

    0.17

    0.03

    0.10

    0.13

    0.82

    18.45

    24.49

    63.91

    92.14

    1.10

    65.01

    93.24

    3.46

    0.35

    0.25

    4.06

    0.14

    0.460.16

    0.17

    0.93

    0.11

    0.21

    0.18

    0.04

    0.54

    5.53

    0.05

    0.06

    0.20

    0.31

    0.15

    0.02

    0.17

    0.00

    0.48

    71.02

    99.25

    Input

    waves

    Accessories

    Vehicle live load

    Management road live load

    Seismic live load

    Applicable standard

    Bridge

    surface work

    Pavement

    Ground

    covering

    Handrail

    of safety

    fence

    Bridge surface work - subtotal

    Accessories - subtotal

    Managementfacilities

    Utility

    Road section

    Sidewalk section

    Cable anchor points

    Subtotal

    Median strip

    ShoulderInside of sidewalk

    Outside of sidewalk

    Subtotal

    Median strip

    Shoulder

    Inside and outside of sidewalk

    Safety fence against falling objects

    Subtotal

    Drainage device

    Maintenance vehicle rail

    Road lights

    Fire hydrants

    Electric equipment

    Subtotal

    Chugoku Electric Power Co.

    NTT

    Subtotal

    Rail for maintenance vehicles inside girders

    Cable attachments

    Subtotal

    Short-cycle spectra

    Long-cycle spectra

    Long-cycle time history waveform

    Vertical spectra

    Hyogoken Nambu Earthquake

    Purpose

    For design

    For design

    For check

    For design

    For check

    B live load (Feb. 1994, Specifications for Highway Bridges)

    Superstructure design standard 2.3.2

    L (EQ) = 1/2 [L* (H) ]

    L* (H) : p2 (equivalent distribution) of main load and sub load was provided to the entire bridge.

    Acceleration response spectra for Tatara Bridge substructure design

    Design acceleration response spectra of the seismic design standard

    Earthquake waveform for checking of superstructure of Tatara Bridge

    One half of both long-cycle and short-cycle spectra

    Seismic motion (spectra) observed at the Kobe Marine Meteorological Observatory

    Accessories

    Bridge

    proper

    Table 3 Design loads

    Dead load strength (tf/m/Br)

    Dead loads - total

    Bridge proper

    Sidewalk

    Fairing (including inspection road)

    Erection reinforcement

    Subtotal

    Completed system Remarks

    PC section included in the bridge proper

    Steel girder PC girder

    Live loads

    Onomichi-Imabari Route Wind Resistance Design Standard and its Commentaries (fourth plan), May 1994

    Wind load

    Seismic force

  • 8/7/2019 47189_1248369986_773

    8/17

    4 7

    V o l . 3 6 No . 2 J une 2 0 0 3

    P + Li + T+ SD + E

    P + W+ T+ SD + E

    P + W+ T+ SD + E

    P + EQ + L (EQ) + T+ SD + E

    P = D + PS + PT+ CR + SH+ CW

    Li = L + I

    L (EQ) : live load during earthquakeFor temperature during a storm (+15C), both cases with and without its

    influence should be considered and extracted.

    P

    P + Li + SD

    P + Li + T+ SD

    P + Li + W+ SD

    P + EQ + L ( EQ ) + T+ SD

    (Note) EQ : Seismic load

    SD : Movement of supporting point

    I : Impact coefficient

    Li : Live load (including impact)

    CW: Counterweight

    PT : Prestress inside PC girder

    CR : Creep

    L (EQ) : Live load during earthquake

    E : Fabrication/erection error load

    W: Wind load

    T : Temperature

    L : Live load

    P : Main load

    SH: Dry shrinkage

    PS : Prestress

    P = D + PS + PT+ CR + SH+ CW

    Li = L + I

    L (EQ) : live load during earthquake

    SD should take a value 50% reduced.

    1

    2

    3

    4

    1

    2

    3

    4

    5

    1.00

    1.50

    1.40

    1.50

    Allowable bending

    compression stress

    N/mm2 {kgf/cm2}

    Allowable

    tensile stress

    N/mm2 {kgf/cm2}

    Remarks

    Remarks

    Additional factorof

    allowable stress

    Additional factor

    of

    allowable stress

    Members appliedSteel structure section

    PC girder section

    Maingirder

    Maintower Cable Support

    1.00

    1.00

    1.15

    1.50

    1.50

    14 {140}

    14 {140}

    16 {161}

    21 {210}

    21 {210}

    { 0}

    { 0}

    { 5}

    {25}

    {30}

    0

    0

    0.5

    2.5

    3.0

    Table 4 Combinations of loads

    Static analysis

    Li, T, SD, W, L (EQ)

    Creep and dry shrinkageanalysis

    CR, SH

    Seismic responseanalysis

    EQ

    Determination of PS

    Calculation of cable

    prestress (PS)

    Loading of dead loads (D2)

    excluding PC girder dead load (D1)

    Preparation of simple

    beam PC girder model

    Loading of PC girder

    dead load (D1)

    Preparation of two

    dimensional skeleton

    Loading calculation of

    counterweight (CW)

    Main tower buckling analysis

    Main girder buckling analysis

    Skeleton analysis for floor

    arrangement system

    To design of each

    members section

    To PC girder

    section design

    FEM analyses forindividual reviews, such

    as cable fixing points

    Summation of sectional force, displacement and reaction of completed system

    (ordinary time, storm and earthquake)

    Determination of final profile (D1

    + D2

    + PS + CW)

    Summation of sectional force, displacement, reaction, acceleration, and response

    amplitude of erected system (ordinary time, storm and earthquake)

    To member check, erection reinforcement

    and erection machinery and equipment

    Erected system seismicresponse analysis

    (at the time of balancing erection)

    (at the time of cantilever erection)

    Gust response analysis atthe erection stage

    (at the time of balancing erection)

    (at the time of cantilever erection)

    Analysis of erection

    stage

    (all erection step)

    Preparation of twodimensional final profilemodel for erection stage

    Preparation of 3D erection stage model

    Fig. 7 Flowchart of analysis

    Analysis of final profile Analysis of erection stage

    Preparationoffinalprof

    ilemodel

    Analysisofsectionalforc

    e

    forfinalprofile

    Individual

    analyses

    Section

    design

    Preparation of 3D skeleton for the entire bridge

  • 8/7/2019 47189_1248369986_773

    9/17

    4 8

    V o l . 3 6 No . 2 J une 2 0 0 3

    For ordinary bridges, such an impact is not so

    influential and causes no practical damage, but the

    Tatara Bridge is very long and its girder rigidity is

    relatively soft and thus any slight error in target points

    will give a serious impact on the girder camber shape.

    In order to reduce the influence of such minor error in

    target points on the model, prestress was determined

    and the actual structure of the bridge was precisely

    simulated in the initial modeling stage in which the final

    profile is generated. Then, the deviation of target points

    was reflected on the model.

    4.2.3 Cable modelingA cable is converted to a rod model, with its sectional

    area alone being considered. The bending rigidity of

    the cable is ignored. Converted modulus of elasticity

    Eeq by the equation of H. J. Ernst, as shown below, is

    used to consider reduction of rigidity by the influence

    of cable sag.

    ..........................(1)

    E0 : Modulus of elasticity of a straightcable (2.0 105 N/mm2)

    g : Unit volumetric weight of cable

    = w/A (N/mm3)

    E

    L E+

    0

    2 20

    31

    12

    Eeq =

    L : Horizontal projection length of cable

    (mm)

    s : Tensile stress of cable = T/A (N/mm2)

    w : Weight per unit length of cable

    (N/mm)

    T : Cable tension (N)A : Cable sectional area (mm2)

    Note that the value ofT is the value when the final

    profile is prepared (when prestress was studied, T= (D

    + PS) given in the basic design was used). When the

    loading was calculated for each loading case after

    determination of the final profile model, cable tension

    T = (D2 + PS) determined in the detail design phase

    was used to set Eeq (where D, PS, and D2 represent

    dead load, cable prestress and dead loads other than

    PC girder dead load).

    4.3 Cable prestress (PS)

    When cable prestress for the Tatara Bridge wasdetermined, the following points were considered.

    (1) Bending moment of steel girders should be reduced

    and made uniform.

    (2) The main tower should have no displacement in

    the direction of bridge axis in the condition of (D2+ PS) (bending moment of the main tower M

    0).

    (3) There should be no void of cable tension.

    (4) Cable section should be uniform.

    (5) Girders sectional force at the center of the center

    span should be reduced (axial force N= 0, M

    small).The bending moment at the PC girder section due to

    the dead load of PC girders (D1) is extremely large

    compared with the steel girder section and adjustment

    of such bending moment by means of cable prestressing

    alone is not realistic. Therefore, it was decided that no

    improvement of bending moment of PC girders by

    means of cable prestressing would be made. The

    counterweight CWfor the PC girder section was excluded

    from the conditions used for determination of cable

    prestress because of the following reasons.

    (1) The counterweight itself is effective against

    reaction, but its impact on the final profile is smalland therefore may be ignored when determining

    prestress.

    (2) The counterweight CWwas to be determined so

    as to satisfy the negative reaction check method,

    but if the counterweight CW is to be involved in

    determination of prestress, it will require a

    convergent calculation with the entire analysis,

    complicating the setting conditions of the

    counterweight CW and requiring a convergent

    calculation for the final profile. Thus, the entire

    analysis can be very complicated.

    (3) In case the unit weight of the counterweight orthe range of counterweights CW to be driven

    changes for some reason, it will become unclear

    about for which final profiles cable prestress was

    Point of intermediate member

    Cable

    Main girder

    Panel point at fixing position

    (Note) A : Sectional areaI : Inertia moment of sectionJ : Torsion modulus

    Pin structure

    Direction of bridge axis

    Virtual member( A, I, J= )

    2P

    1A

    3P

    4P

    R side (north side)

    L side (south side)

    Fig. 8 Skeleton model for analysis

    Center span

    Towerwall

    Tower shaft

    Virtual member

    Cable

    Cable

    Horizontal

    Fixing pointof cable strand

    Side span Center spanSide span

    Modeling

    (a) Main tower fixing point structure (b) Main tower fixing point model

    Fig. 9 Modeling of main tower

  • 8/7/2019 47189_1248369986_773

    10/17

    4 9

    V o l . 3 6 No . 2 J une 2 0 0 3

    set. Thus, it is desirable not to relate the

    counterweight CW to determination of cable

    prestress.

    The relative rigidity method was therefore used for

    calculations to determine cable prestress.

    4.4 PC girder deadweight loading for compositecable stayed bridge

    For a steel and PC composite cable stayed bridge, the

    difference of girder dead loads is so large that it becomes

    difficult to make uniform the bending moment of all

    girders by cable prestress. The major role of PC girders

    used for part of the side spans of the Tatara Bridge

    is to serve as a counterweight. Then, there are two

    options, whether we should make the dead load of PC

    girders, which are part of the girders, influence the

    final profile or not influence it by taking the PC girders

    merely as counterweights. Which method is favorable

    should be reviewed depending on the structuralcharacteristics or conditions of each bridge.

    For the Tatara Bridge, the dead load of PC girders

    at the side spans (D1) was not loaded on the final profile

    model, but the structural design of the bridge was made

    by combining the values obtained from analysis with

    a simple beam PC girder model with the analysis of

    the final profile model. In conclusion, in our model

    calculation, rigidity alone is present in the entire bridge

    model, girders are those with no deadweight, and the

    PC girders are treated completely as counterweights.

    4.5 Fabrication/erection error load (E)

    1/2 000 of the tower height for error of inclination ofthe tower and 5% of working stress for main girders

    and cables are generally allowed for in a basic design

    with regard to fabrication and erection error loads. But

    as the error of inclination of the tower ended up being

    within 5% of working stress, 5% of working stress was

    allowed for as fabrication/erection error in the detail

    design.

    5. Seismic design

    5.1 Seismic analysis

    Design and design check were carried out by two seismic

    analytical methods: spectral response analysis, which

    is one of the mode analysis techniques, and time historyresponse analysis, which is a time-domain analysis

    using mode analysis. Load combinations used in the

    design are shown by the following equation.

    ..............(2)

    D : Dead load

    CW : Counterweight

    L(EQ) : Live load during earthquake

    SD : Influence of supporting point

    movementPS : Prestress

    EQ : Influence of earthquake

    T : Influence of temperature change

    E : Fabrication/erection error

    The safety factor of allowable stress is 1.5 for

    earthquake. Seismic analytical cases are shown in Table

    5.

    5.2 Results of seismic analysis

    5.2.1 Results of spectral response analysis

    Cross section design of major structural parts, or main

    girders, main tower and cables, was not based on any

    condition in case an earthquake occurs. Of bearing,reaction in the direction perpendicular to bridge axis

    was largest in an earthquake. Movement of the supporting

    points in the direction of bridge axis and the direction

    perpendicular to bridge axis was greatest in an

    earthquake. Therefore, the values of bearing movement

    and those of expansion devices for the earthquake case

    were used as the standard.

    D PS CW EQ L EQ

    T SD E

    + + + + +

    + +

    ( )

    AnalysisNo.

    Analytical method Input wave Input method

    Input direction

    Bridge axis VerticalPerpendicularto bridge axis

    Calculation of groundspring

    Kurushima Method

    Aseismic Method

    Aseismic Method

    Aseismic Method

    Kurushima Method

    Response spectral analysis(CQC method)

    A short-cycle spectra

    B long-cycle spectra

    C long-cycle time history

    D long-cycle time history

    E Spectra observed fromthe Hyogoken Nanbu

    Earthquake

    Same phase(multiple point

    simultaneous input)

    Same phase(multiple point

    simultaneous input)

    Same phase(multiple point

    simultaneous input)

    Same phase(multiple point

    simultaneous input)

    Phasal difference

    Response spectral analysis(CQC method)

    Time history responseanalysis

    Time history responseanalysis

    Response spectral analysis(CQC method)

    1

    2

    3

    4

    5

    (Note) Ground spring was calculated based on the following standards:- Kurushima Method: Kurushima Bridge Steel Foundation Aseismic Calculation Method (proposed)- Aseismic Method: Honshu-Shikoku Bridge Authority Aseismic Design Standard (February 1977)

    Table 5 Earthquake analysis cases

  • 8/7/2019 47189_1248369986_773

    11/17

    5 0

    V o l . 3 6 No . 2 J une 2 0 0 3

    5.2.2 Results of time

    history response

    analysis

    Sectional force, displacement

    and acceleration of major

    structural components, or maintower, main girders and cables,

    were generally smaller in value

    than those obtained from the

    analysis of spectral response.

    This fact confirmed safety from

    the design viewpoint. Bearing

    reaction and movement were

    also confirmed to be below the design value by the

    results of time history response analysis.

    6. Wind resistant design

    Wind resistant design was carried out in accordance withthe Onomichi-Imabari Route Wind Resistant Design

    Standard and its Commentaries (fourth draft), May

    1994, Honshu-Shikoku Bridge Authority. Various wind

    tunnel tests were also conducted, which will be reported

    some other time.

    6.1 Wind resistant design for completed system

    6.1.1 Design wind resistance

    Wind load to be applied to girders and cables:

    PD = 1/2 m2 r Uz2 CD An ......................(3)

    Wind load to be applied to the tower

    PD = 1/2 m3 r Uz2 CD An ....................(4)

    Where

    Uz = m1 U10 ..............................................(5)

    m1 = (Z/10)1/7 ............................................(6)

    m2 : Corrective coefficient for gust

    response for girders and cables

    m3 : Corrective coefficient for gust

    response for the main tower

    Z : Average elevation

    r : Air density (1.225 N s2

    /m4

    )CD : Drag coefficient

    An : Projected area

    Note that design standard wind speed U10 is 37 m/s

    (29 m/s during erection). See Table 6 for drag coefficient

    and Table 7 for corrective coefficient for gust response.

    6.1.2 Wind load application

    (1) Wind load in the direction perpendicular to bridge

    axis

    q For girders, all loads were applied to the

    effective projected area at the windward side.

    w For the tower, the wind load was applied to

    the axial line of the tower block each at thewindward and leeward side.

    e For cables, wind loads working on the cables

    were applied as intensive loads half by half

    equally to each cable fixing point of the girder

    side and the tower side.

    In applying wind loads in the direction

    perpendicular to the bridge axis, it was known

    from wind tunnel tests that quartering wind near

    around a horizontal deflection angle of 35 degrees

    prevails. So, the load in the direction of thebridge axis was simultaneously applied in order

    to take quartering wind into consideration. At

    this time, the strength against wind load in the

    direction of the bridge axis used was 50% of

    total strength.

    (2) Wind load in the direction of bridge axis

    q For girders, wind loads in the direction of

    bridge axis were uniformly applied.

    w For the tower, wind loads calculated assuming

    all sections including the tower blocks and

    horizontal members are effective were uniformly

    applied.e For cables, wind loads were caused to work

    on cables by considering the slope of the cables

    and applied half by half equally to each cable

    fixing point at the girder side and the tower side

    as intensive loading.

    (3) Displacement

    In designing structural components, such as

    bearings and expansion devices, for which

    displacement would be a major issue, the total

    strength against wind load in the bridge axial

    direction and 50% strength against wind load in

    the direction perpendicular to bridge axis weresimultaneously applied.

    6.2 Wind resistant design for erection system

    For wind loads to be applied to the bridge during

    Drag coefficient

    CD

    1.2

    0.6

    1.2

    1.3

    1.8

    1.3

    1.8

    1.0

    0.3

    0.7

    Remarks

    Wind tunnel

    test value

    Wind resistant

    design standard

    Schematic diagram

    Upperpart

    Lowerpart

    Table 6 Drag coefficient

    Subject structure

    Windward

    Perpendicular to bridge axis

    Cable

    Bridge axis

    Lower part of the lee side

    Upper part

    Lower part

    Horizontal beam at the lower part

    Intermediate horizontal beam at the upper part

    Upper part of the lee side

    Maintower

    Maingirder

    Perpendicularto bridge axis

    Bridge axis

    For design of girders For design of towers

    Directionperpendicularto bridge axis

    1.90

    1.90

    1.90

    1.65

    1.65

    1.65

    Directionof bridge axis

    Directionperpendicularto bridge axis

    Directionof bridge axis

    1.35

    1.35

    1.50

    1.35

    1.35

    1.50

    Before cable erection

    (1.80)

    m2

    m2

    m3

    Table 7 Corrective coefficient for Gust responce

    Main girderCable

    Main tower

  • 8/7/2019 47189_1248369986_773

    12/17

    5 1

    V o l . 3 6 No . 2 J une 2 0 0 3

    erection, the two conditions that were considered very

    susceptible to wind load, or the maximum overhang

    condition immediately before center span closing, and

    the maximum balancing condition before large side-span

    block erection, were studied to determine appropriate

    wind loads.6.2.1 Maximum balancing condition

    When cables are installed to the seventh level, the

    bridge would look like a balancing toy. As it was

    important to ensure stability of the bridge under such

    a condition against wind, wind tunnel tests were

    conducted, which indicated that excessive negative

    reaction would occur at the diagonal bent by gust

    response. Subsequent analytical study lead to re-

    examination of the erection procedure to reduce negative

    reaction at the diagonal bent. To be specific, large

    main-girder blocks in side spans were erected at the

    lower first and second level cables under the side spans.No tension was given until the system became stabilized

    so as not to generate negative reaction at the diagonal

    bent.

    6.2.2 Maximum cantilever condition

    The maximum cantilever erection of the center span

    goes to about 430 m, the largest ever in the world. How

    to stabilize the cantilever against wind load had been

    one of the earliest issues. Before commencement of the

    design work by the Joint Venture, various wind tunnel

    tests were conducted to work on the issue. Major points

    of focus were identified as follows.

    (1) Characteristics of local wind were studied by awind tunnel test using a model formed after the

    local topography. It was found that quartering wind

    with very hard turbidity is likely to blow because

    of the influence of the mountains behind the Tatara

    Bridge.

    (2) The maximum cantilever span length is 430 m

    and its primary natural frequency is about 16 sec.

    If this condition is handled by a conventional

    vibration-damping device, the device would have

    to be very big and could not be manufactured

    because of its size.

    With these points in mind, analyses and windtunnel tests were conducted to work on the design

    of sections and vibration control during actual

    erection. The following points were actually

    reviewed.

    q Erection machinery was converted into a model,

    which was used in an erection system wind force

    test. Then, detailed data, such as aerodynamic

    coefficient, necessary for design work were

    obtained.

    w Gust response analysis of the maximum

    cantilever erection system was conducted and the

    gust response coefficient for the main girdererection stage was newly established to be 2.0

    (while it is 1.9 for the final profile).

    e Considering the effect of quartering wind on

    reduction of wind speed and spatial correlation

    of quartering wind, it was confirmed that the

    safety factor of allowable stress is 1.7, and that

    the first horizontal bending mode would be

    satisfied.

    rAs an extra vibration-damping countermeasure,a tie-down plan to connect sinkers under the

    water and girders was checked by wind tunnel

    tests and analyses, which confirmed the

    effectiveness of the method and indicated a

    possibility of reducing both girder horizontal

    displacement and bending moment of girders at

    the bases of the towers to about 60% compared

    with the case of no such plan.

    t It was finally decided that no special

    countermeasure would be taken because of the

    special characteristics of wind direction and

    speed, low reproduction probability and theproven fact that the first horizontal mode would

    be satisfied.

    7. Check of stability of main girdersagainst buckling

    In case axial compressive stress in the bridge axial

    direction prevails for a long-span cable stayed bridge

    with flattened box girder, such as the Tatara Bridge,

    it is essential to study stability against whole buckling.

    One of the standard methods to evaluate stability

    against whole buckling is use of the stability inspection

    equation using effective buckling length (Le), as givenin the Specifications for Highway Bridges (SHB).

    But if this method is applied to variable sectional

    members, as seen in main girders of a cable stayed

    bridge, the effective buckling length at the center span

    where axial compressive strength level is low becomes

    too long and the resultant design would have to be

    made based on a practically unassumable buckling

    length. Then, uneconomical cross sections could result.

    Today, thanks to the improved capability of computers,

    in some cases, elastoplastic analysis of an entire system

    with residual stress and initial irregularity taken into

    consideration is conducted to carry out stabilityinspection. For the Tatara Bridge, the Bridge Planning

    Committee for the Tatara Bridge (hereafter called

    Tatara Committee) of the Honshu-Shikoku Bridge

    Authority decided to carry out elastoplastic analysis

    for an entire system and also carried out buckling

    experiments using an entire system model. It was

    ultimately found that the experiment results have a

    good agreement with the elastoplastic analysis results

    for buckling modes and buckling load capacity and

    confirmed the validity of the analysis.

    These reports indicated that critical points in terms

    of buckling are the same members whose effectivebuckling length was found shortest by the buckling

    analysis. For the Tatara Bridge, the sectional design

    that satisfies the stability inspection equation given in

  • 8/7/2019 47189_1248369986_773

    13/17

    5 2

    V o l . 3 6 No . 2 J une 2 0 0 3

    the SHB by using their effective buckling length was

    used only for members whose effective buckling length

    was shortest, located near the main tower.

    When the effective buckling length was calculated,

    the effective shearing modulus method (Ef method)

    was used. As a result, the effective buckling length forthe main girders (Le) turned out to be 34.9 m, almost

    twice (40 m) the cable fixing interval. This value was

    rounded off to 35 m and the stability inspection equation

    was applied only to the main girders near the towers.

    Fig. 10 shows the portions to which the buckling stability

    inspection was conducted. For allowable stress relative

    to local buckling, values given by the block model

    approach were used.

    8. Design of main tower

    8.1 Design outline of main tower

    The design of the main tower was developed based onsupplementary review, including FEM, in addition to

    the use of the sectional force used in the whole bridge

    analysis. The major components to be designed were

    as follows.

    (1) The tower anchor frame and the base of the

    tower

    (2) Tower blocks

    (3) Crossing zone and knuckle parts

    (4) Lower horizontal beam (horizontal beam at the

    level of the road)

    (5) Upper and intermediate horizontal beam

    (6) Cable anchorThe major design points of the tower are as follows.

    q The shape of the main tower is an inverted Y

    with a cut-off corner section, which was found

    to be excellent in wind resistance by the wind

    tunnel tests. Corner cut-off is different between

    the lower part of the tower and the upper part.

    The corner cut-off for the lower part is effective

    in controlling the vortex induced vibration. The

    corner cut-off for the upper part is designed to

    provide a section effective against galloping.

    w For the cross section of the main tower, as

    ease of production and erection was consideredimportant, a single chamber box section was

    adopted. A three-chamber section divided by

    vertical diaphragms had to be used for the

    crossing zone and knuckle of the lower horizontal

    members and the cable anchor in the upper part

    for unavoidable structural reasons.

    e The tower blocks were designed as block

    members for the axial force and two-directional

    bending. Since the in-plane effective buckling

    length is close to the out-plane effective buckling

    length, the bi-axial bending stability inspection

    equation was adopted.r Since the large blocks for the lower part were

    to be assembled on the ground, each block volume

    was determined to be 160 tons considering the

    lifting capability of companies. Single member

    erection blocks for the upper parts were

    determined to be less than 145 tons each so that

    they could be handled by cranes to be set up at

    the site.

    t Blocks were all connected by friction joints

    using high tensile bolts (HTB). The steel plates

    were to be designed as 50% metal touch. Large

    block interfaces and horizontal members weredesigned as 100% high tensile bolts to absorb

    production and erection errors.

    8.2 Effective buckling length of main tower

    The effective buckling length of the main tower was

    determined based on the values calculated from the

    three methods as follows.

    (1) The effective buckling length of all members

    was calculated based on Pcr(buckling load) of the

    primary mode.

    (2) The effective buckling length was calculated

    based on Pcrof the primary mode of each member.

    (3) Inflection points of a mode in which each memberbuckles were selected from the mode diagram and

    the effective buckling length was calculated using

    the mode diagram.

    8.3 Design of crossing zone and knuckle

    At a crossing zone of a conventional rectangular cross-

    section, flange forces of horizontal members are

    transmitted to the webs of the tower blocks as shear

    via the diaphragms of the crossing zones. But since the

    Tatara Bridge has a single-chamber 12-angle cross

    section with cut-off corners, stress would not smoothly

    transmit. For stress of webs of horizontal members,

    smooth stress transmission would not be realized dueto the small width of the webs in the tower blocks.

    Thus, internal webs were extended for the crossing

    zones of the horizontal members to turn the cross section

    near the crossing zones into a three-chamber shape for

    positioning stays of horizontal members (Fig. 11). In

    terms of calculation, the plate thickness of the internal

    web and the external web was converted as a single

    plate so that the cross-section is interpreted as a single-

    chamber rectangular shape and the Okumura-Ishizawa

    Method was used to carry out simple design. Then, the

    3D FEM analysis was used to check the design before

    finally determining the plate thickness.For the Tatara Bridge, knuckle points of the tower

    blocks were aligned with the line of the girder edge

    for the appearance and thus there is a clearance of

    The stability inspection equation was applied only to this range.

    The minimum effective buckling

    length was used.

    Fig. 10 Check for buckling stability of main girder

  • 8/7/2019 47189_1248369986_773

    14/17

  • 8/7/2019 47189_1248369986_773

    15/17

    5 4

    V o l . 3 6 No . 2 J une 2 0 0 3

    compression check was conducted since it was

    impossible to ignore stress in the direction

    perpendicular to the bridge axis caused by cable

    fixing.

    r For the cable anchor, square column anchors

    were used at the outside of external web plates.The detailed structure was determined after

    fatigue testing and FEM analysis.

    t Composite girders play a pivotal role in

    connecting PC girders to steel box girders. Rear

    face fixing, a composite girder system with

    proven performance from the Ikuchi Bridge

    experience, was used. For backing concrete, high-

    fluidity concrete was cast in-situ to realize

    downsizing of blocks, use of smaller erection

    cranes, and reduction in site work.

    9.2 Design of wide stiffened plates

    At the center cell of the Tatara Bridge, the intervalof web plates is 9.04 m and that of lateral ribs is 2.5

    m. They are sufficiently wide compression-stiffened

    plates with an aspect ratio (a) of 0.277. The SHB,

    however, assumes compression stiffened plates of about

    2 in aspect ratio and defines a level of stiffness of

    stiffened plates that makes the buckling mode become

    nodes at the lateral rib positions. According to the

    regulation of compression-stiffened plates in the

    superstructure design standard of HSBA, the definition

    of the SHB is used as an applicable specification. But

    for such wide compression-stiffened plates as used for

    the Tatara Bridge, the required stiffness for a stiffenedplate would be so large that it would be a large cross-

    section of unrealistic size.

    The Tatara Committee then came up with the Tatara

    Bridge Design Procedure (draft), based on which wide

    stiffened plates were designed for longitudinal and

    lateral stiffeners and allowable stress of local buckling

    was calculated using the block model approach. For

    longitudinal ribs of the Tatara Bridge, closed section

    ribs (U ribs) were to be used both at the steel plate

    deck side and the bottom flange side and thus the load

    capacity curve in the Buckling Design Guideline (Japan

    Road Association) that is almost equal to the StandardLoad Capacity Curve (V) in the SBH (Feb. 1994, Japan

    Society of Civil Engineers) was used for ultimate

    strength of effective stiffeners used in the block model

    approach. Since steel plate decks are supported at cable

    fixing points and loaded by in-plane compression in the

    direction of bridge axis and the direction perpendicular

    to bridge axis, they were given bi-axial buckling checks.

    9.3 Longitudinal ribs

    Trough ribs (320 240 8) were used for all

    longitudinal ribs at the steel plate deck side and almost

    all other longitudinal ribs except for those of bottom

    flanges around the center of the center span. Ribsmeasuring 320 240 6 were used for some bottom

    flanges near the center of the center span. Since

    longitudinal ribs form part of the main girders of the

    bridge, axial compressive force acts on them due to

    horizontal components of cable tension. Therefore, it

    is necessary to check longitudinal ribs for their resistance

    to local buckling.

    For 8-mm-thick trough ribs, blocks composed of deck

    plates and trough ribs were put to load capacity teststo confirm that no local buckling will occur. Based on

    the results of buckling tests and elastoplastic analysis,

    a structural arrangement in which another row of bolts

    is added only to splice plates at one side, as shown in

    Fig. 14, was applied to reduce the stress concentration

    immediately before the splices so as not to reduce load

    capacity at joints. For 6-mm-thick trough ribs, elastic

    buckling analysis was made to set allowable stress with

    regard to local buckling to 167 N/mm2 {1 700 kgf/cm2}.

    9.4 Design of cable anchor

    Web plate fixing square column anchors were used for

    cable fixing. Where stress was expected to intensify,the results of large fatigue tests, conducted in an earlier

    stage of design, as well as other reviews including FEM

    analysis were used to determine shapes of elements,

    such as the fillet shape of bearing plates used for cable

    fixing assemblies. The structure of the cable anchor is

    shown in Fig. 15.

    The following points were reviewed in designing the

    section of the cable anchor.

    (1) Structure of bearing plate (FEM analysis)

    (2) Stress check at anchor and the area near it (FEM

    analysis)

    (3) Load sharing ratio of vertical component of cabletension (grid analysis)

    (4) Main girder in-plane bending stress distribution

    (FEM analysis)

    A - A

    AA

    75

    5

    Fig. 14 Joint of longitudinal rib (unit : mm)

    Fig. 15 Cable anchor (main girder)

    Deck plate

    Diaphragm

    Bottom flange External web plate

    Internalstrengtheningweb

    Internalstrengtheningflange

    Internalstrengtheningstructure

    Anchorflange

    Anchor rib

    Auxiliary rib

    Squarecolumnanchor

    Bearing plate

  • 8/7/2019 47189_1248369986_773

    16/17

  • 8/7/2019 47189_1248369986_773

    17/17

    5 6

    V o l . 3 6 No . 2 J une 2 0 0 3

    is large. As a proactive safety measure against huge

    earthquakes, it was confirmed that if friction of this

    bearing is considered as attenuation, response

    displacement decreases to about 20%.

    According to this review, stoppers in the bridge axial

    direction, which were to be installed in the basic designstage, were canceled in the detailed design stage based

    on the assumption that frictional force of bearings will

    work in the case of anomalies or earthquakes. It is

    therefore a matter-of-course that movement was

    calculated at the design seismic level assuming that

    they were ordinary movable bearing shoes and that no

    frictional force is expected.

    Acknowledgment

    The authors acknowledge the staff of Third Construction

    Bureau of the Honshu-Shikoku Bridge Authority andthe members of the Tatara Committee for their guidance

    and cooperation in planning, designing, fabrication and

    erection of the Tatara Bridge construction work. In

    particular, the authors wish to thank Prof. Toshiyuki

    Kitada of Osaka City University for his valuable

    comments on application of wide stiffened plate design

    for main girders and Prof. Chihiro Miki of Tokyo

    Institute of Technology for his valuable instructions on

    detailed review of fatigue of steel plate decks.

    The authors feel that all our hard work in solving

    numeral technological difficulties and developing safety

    measures for work instantly turns into a heart-warmingsatisfaction the moment we see the beautiful shape of

    the Tatara Bridge located at the middle of the

    Shimanami Kaido (Fig. 17).

    REFERENCES

    (1) T. Fujiwara and A. Moriyama : Wind-Proof

    Design on the Tower of Tatara Bridge, Honshi

    Technical Report Vol.19 No.74 Apr. 1995 pp.24-

    37

    (2) M. Kitagawa, R. Toriumi and H. Katsuchi :

    Study on Large Scale Wind Tunnel Test of TataraBridge, Honshi Technical Report Vol.19 No.20

    Jan. 1996 pp.38-45

    (3) H. Akiyama, R. Toriumi and Y. Ohtani : Large

    Scale Wind Tunnel Test of the Tatara Bridge (2nd

    report) Gust Response in Complicate Topography,

    Honshi Technical Report Vol.21 No.83 July 1997pp.30-36

    (4) N. Hirahara : Erection of Superstructure of Tatara

    Bridge (Report I) Tower Erection and Large Block

    Erection of Deck at Tower, Honshi Technical

    Report Vol.21 No.84 Oct. 1997 pp.33-40

    (5) N. Hirahara and T. Murata : Erection of

    Superstructure of Tatara Bridge (Report II)

    Erection of Steel Girder and Cables, Honshi

    Technical Report Vol.22 No.88 Oct. 1998 pp.28-

    37

    (6) T. Nose, T. Murata and M. Yabuno : Precision

    Control during Balancing Erection for Tatara Bridge,Proceedings of the 54th Annual Conference of the

    Japanese Society of Civil Engineers, 1-(A) Sep.

    1999 pp.724-725

    Fig. 17 View of Tatara Bridge