Title page
Alcatel-Lucent 9130
BSC/MFS Evolution |
Installation Manual
3MN-00467-1011-RJZZA
Issue 1 | March 2012
Legal notice
Legal notice
Alcatel, Lucent, Alcatel-Lucent and the Alcatel-Lucent logo are trademarks of Alcatel-Lucent. All other trademarks are the property of their respective
owners.
The information presented is subject to change without notice. Alcatel-Lucent assumes no responsibility for inaccuracies contained herein.
Copyright © 2012 Alcatel-Lucent. All rights reserved.
Note:
Not to be used or disclosed except in accordance with applicable agreements.
Contents
About this document
Purpose ............................................................................................................................................................................................. ixix
Reason for reissue ........................................................................................................................................................................ ixix
New in this release ....................................................................................................................................................................... ixix
Intended audience ......................................................................................................................................................................... ixix
How to use this document ........................................................................................................................................................... xx
Safety information ......................................................................................................................................................................... xx
Prerequisites ..................................................................................................................................................................................... xx
Conventions used ........................................................................................................................................................................... xx
Related information ....................................................................................................................................................................... xx
Document support .......................................................................................................................................................................... xx
Technical support .......................................................................................................................................................................... xixi
How to order ................................................................................................................................................................................... xixi
How to comment ........................................................................................................................................................................... xixi
1 Safety Information
Structure of safety statements ............................................................................................................................................... 1-11-1
2 Overview
Overview ...................................................................................................................................................................................... 2-12-1
Presentation ................................................................................................................................................................................. 2-12-1
Preparation .................................................................................................................................................................................. 2-62-6
Scheduling ................................................................................................................................................................................... 2-72-7
Resources ..................................................................................................................................................................................... 2-82-8
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
iii
3 Scenario
Overview ...................................................................................................................................................................................... 3-13-1
Before Going Onsite
Overview ...................................................................................................................................................................................... 3-33-3
Before You Start
Before You Start ........................................................................................................................................................................ 3-43-4
Install Rack
Prepare Floor .............................................................................................................................................................................. 3-53-5
Rack Delivery and Positioning ............................................................................................................................................ 3-73-7
Prepare Site Cable Way ........................................................................................................................................................ 3-113-11
Fix Rack ..................................................................................................................................................................................... 3-133-13
Install Protective Earth and Power Supply Cables
How to Install Protective Earth and Power Supply Cables ..................................................................................... 3-223-22
Install Cables in Site Cable Way ....................................................................................................................................... 3-233-23
C1: Rack Top Entry of Cables ........................................................................................................................................... 3-253-25
C2: Rack Bottom Entry of Cables .................................................................................................................................... 3-283-28
Connect Earth Cable (GND) .............................................................................................................................................. 3-313-31
Connect DC 48 Volts Power Cables ................................................................................................................................ 3-343-34
Test Power Supply ................................................................................................................................................................. 3-383-38
Install PCM Cables
Run 120 Ohm PCM Cables ................................................................................................................................................ 3-413-41
Run 75 Ohm PCM Cables ................................................................................................................................................... 3-473-47
Install Cables in Cable Way ................................................................................................................................................ 3-563-56
O2: Install Second Equipment in Rack
Install PCM Cables ................................................................................................................................................................ 3-583-58
Install Second ATCA Shelf ................................................................................................................................................. 3-593-59
Contents
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
iv Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Install Second LIU Shelf ..................................................................................................................................................... 3-673-67
Install Internal Ethernet Cables ......................................................................................................................................... 3-703-70
O3, O4, O5, O6, O7: Install Ethernet Cables
O3: Install OMC-R Router Cables ................................................................................................................................... 3-713-71
O4: Install A-GPS Server Cable ....................................................................................................................................... 3-723-72
O5: Install External Alarm Box ......................................................................................................................................... 3-733-73
O6: Install SGSN Router Cables ...................................................................................................................................... 3-743-74
O7: Install Ethernet Cables for IP Telecom Traffic in Release B11 ..................................................................... 3-753-75
O8: Install Optical Cables for STM1 in Release B11
How to Install Optical Cables for STM1 in Release B11 ........................................................................................ 3-763-76
Install Optical Cables in Cable Way ................................................................................................................................ 3-773-77
Install SFP Modules .............................................................................................................................................................. 3-793-79
Route Optical Cables ............................................................................................................................................................ 3-813-81
Finish Installation
How to Finish Installation ................................................................................................................................................... 3-853-85
Contents
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
v
Contents
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
vi Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
List of figures
2-1 9130 MFS/BSC Evolution Rack (Front View) ............................................................................................... 2-22-2
2-2 9130 MFS/BSC Evolution Configurations ...................................................................................................... 2-32-3
3-1 Fixing Items to be Removed on Shelf Back Side ........................................................................................ 3-103-10
3-2 Level Rack then Fix Rack to Concrete Floor ................................................................................................ 3-143-14
3-3 Raised Floor Fixing Example ............................................................................................................................. 3-163-16
3-4 Mechanical Assembling of Frame .................................................................................................................... 3-183-18
3-5 Fixing Raised Floor at Same Level of Earthquake Frame) ...................................................................... 3-203-20
3-6 Top Cable Entry ....................................................................................................................................................... 3-263-26
3-7 Power Cables Outlet General View .................................................................................................................. 3-273-27
3-8 Bottom Cable Entry ................................................................................................................................................ 3-293-29
3-9 Metallic Braid Fixed to Raised Floor Cable Way ........................................................................................ 3-303-30
3-10 Power Cables Connection .................................................................................................................................... 3-353-35
3-11 Site Fuse Breaker Example ................................................................................................................................. 3-363-36
3-12 Label Power Cables ................................................................................................................................................ 3-373-37
3-13 Bind Cables ............................................................................................................................................................... 3-413-41
3-14 Cable Routing Front View ................................................................................................................................... 3-423-42
3-15 Top Rack Cable Entry General View ............................................................................................................... 3-433-43
3-16 Cable Routing Front View ................................................................................................................................... 3-453-45
3-17 Cable Routing Side View ..................................................................................................................................... 3-463-46
3-18 Bottom Cable Entry ................................................................................................................................................ 3-523-52
3-19 Cable Routing Front View ................................................................................................................................... 3-543-54
3-20 Cable Routing Side View ..................................................................................................................................... 3-553-55
3-21 Wrong Handling of ATCA Shelf ........................................................................................................................ 3-603-60
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
vii
3-22 Ground Cable and ESD Jack Connection ...................................................................................................... 3-613-61
3-23 Rear View of ATCA Shelf Variant Before 3BK 27291 ABxx ................................................................. 3-623-62
3-24 Ground Cable and ESD Jack Connection ...................................................................................................... 3-643-64
3-25 Rear View of ATCA Shelf from Shelf Variant 3BK 27291 ABxx On ................................................. 3-653-65
3-26 Brackets at Shelf Rear ........................................................................................................................................... 3-673-67
3-27 Brackets at Shelf Front .......................................................................................................................................... 3-683-68
3-28 Install Optical Cable in cable tray ..................................................................................................................... 3-773-77
3-29 Cables Rack Top Entry .......................................................................................................................................... 3-813-81
3-30 Cables Routing Bottom Entry - Rear View ................................................................................................... 3-833-83
3-31 Optical Cable Connection on JBXTP3 Board .............................................................................................. 3-843-84
3-32 Fit Rack Bottom Cover Plate .............................................................................................................................. 3-853-85
3-33 Close Doors ............................................................................................................................................................... 3-863-86
List of figures
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
viii Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
About this documentAbout this document
Purpose
This document describes how to install onsite an Alcatel-Lucent BSS 9130 MFS/BSC
Evolution and how to install a second equipment in an 9130 MFS/BSC Evolution rack.
Reason for reissue
Issue number Reason for reissue
Edition 01 First official release of the document.
New in this release
This section contains information about changes to the current document.
New features
None.
Other changes
None.
Intended audience
This document is intended for:
• Installers
• Site administrators
• Supervisors
• Project managers
• Field service technicians
• Occasional users.
...................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
ix
How to use this document
No specific recommendation applies regarding the way readers should read this
document.
Safety information
For your safety, this document contains safety statements. Safety statements are given at
points where risks of damage to personnel, equipment, and operation may exist. Failure to
follow the directions in a safety statement may result in serious consequences.
Prerequisites
You must have a basic understanding of the following:
• Alcatel-Lucent BSS equipment
• Experience of electrical mounting and cabling.
Conventions used
This section gives information on conventions.
Vocabulary conventions
None.
Typographical conventions
The following typographical conventions are used in this document:
Appearance Description
Italicized text Emphasized information.
graphical user interface text Text that is displayed in a graphical user interface or in a
hardware label.
Document reference, reference
number
Related document that is referenced in the document.
Related information
None.
Document support
For support in using this or any other Alcatel-Lucent document, contact Alcatel-Lucent at
one of the following telephone numbers:
• 1-888-582-3688 (for the United States)
• 1-317-377-8618 (for all other countries)
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
x Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Technical support
For technical support, contact your local Alcatel-Lucent customer support team. See the
Alcatel-Lucent Support web site (http://www.alcatel-lucent.com/support/) for contact
information.
How to order
To order Alcatel-Lucent documents, contact your local sales representative or use Online
Customer Support (OLCS) (http://support.alcatel-lucent.com)
How to comment
To comment on this document, go to the Online Comment Form (http://infodoc.alcatel-
lucent.com/comments/) or e-mail your comments to the Comments Hotline
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
xi
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
xii Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
1 1Safety Information
Structure of safety statements
Overview
This topic describes the components of safety statements that appear in this document.
General structure
Safety statements include the following structural elements:
Item Structure element Purpose
1 Safety alert symbol Indicates the potential for personal injury
(optional)
2 Safety symbol Indicates hazard type (optional)
3 Signal word Indicates the severity of the hazard
4 Hazard type Describes the source of the risk of damage or
injury
5 Safety message Consequences if protective measures fail
6 Avoidance message Protective measures to take to avoid the hazard
SAMPLEB C D
E F
G
H
Lifting this equipment by yourself can result in injurydue to the size and weight of the equipment.
Always use three people or a lifting device to transportand position this equipment. [ABC123]
CAUTION
Lifting hazard
...................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
1-1
Item Structure element Purpose
7 Identifier The reference ID of the safety statement
(optional)
Signal words
The signal words identify the hazard severity levels as follows:
Signal word Meaning
DANGER Indicates an extremely hazardous situation which, if not avoided, will
result in death or serious injury.
WARNING Indicates a hazardous situation which, if not avoided, could result in
death or serious injury.
CAUTION Indicates a hazardous situation which, if not avoided, could result in
minor or moderate injury.
NOTICE Indicates a hazardous situation not related to personal injury.
Safety Information Structure of safety statements
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
1-2 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2 2Overview
Overview
Purpose
This Overview gives information needed by project managers and foremen, for
presentation to the customer and for site planning.
Contents
Presentation 2-1
Preparation 2-6
Scheduling 2-7
Resources 2-8
Presentation
Hardware Description
The following sections describe the hardware.
Rack Layout and Configurations
The following figure shows the front view of the 9130 MFS/BSC Evolution rack.
...................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2-1
The following figure shows all 9130 MFS/BSC Evolution possible configurations.
Figure 2-1 9130 MFS/BSC Evolution Rack (Front View)
Overview Presentation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-2 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Regardless of the configuration, the installation principle is the same.
Weight and Dimensions
The following table gives the dimensions and weight of the cabinet.
Description Dimensions
Width
Depth
Height (including a 100 mm plinth)1
*
600 mm
600 mm
2000 mm
Weight ≈ 300 kg (maximum configuration)
Notes:
1. * Earthquake option is not included in total height
Cases
The following cases apply:
• C1: Concrete floor installation
• C2: Raised floor installation.
Figure 2-2 9130 MFS/BSC Evolution Configurations
Overview Presentation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2-3
Options
The following options apply:
• O1: Earthquake fixing.
• O2: Install the second equipment in a rack
• O3: Ethernet cables installation towards the OMC-R
• O4: A-GPS server cable installation
• O5: External Alarm box installation.
• O6: Ethernet cables installation towards SGSN
• O7: Ethernet cables installation for IP telecom traffic, applies for Release B11
• O8: Optical cables installation for STM1, applies for Release B11.
Initial State
Before the installation, the rack and installation kits are packed and delivered onsite.
Final State
After finishing the installation:
• The rack is ready for commissioning
• The rack is not powered up.
Restrictions
None.
Grouped Task Sequence
The following figure shows the task sequence for dismantling onsite an Alcatel-Lucent
BSS 9130 MFS/BSC Evolution.
Overview Presentation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-4 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Overview Presentation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2-5
Preparation
Prerequisites
The following prerequisites apply:
• The site must comply with the safety rules given in the General Wiring Handbook
• The site is ready to receive the racks, according to the SPP 59 - Specification for 9130
BSC/MFS Evolution Site Preparation.
Site Specific Information
You must have the following specific information to complete the scenario.
Site:
• Grounding plate location
• Power supply cabinet location
• Fuse breaker locations in the power box
• 2 wire or 3 wire power system (if applicable)
• Precise rack location
• PCM terminal block location
• Usage of External Alarm Block
• Number of STM1 cables to be installed
• Number of alarms to be connected.
Rack:
• Door opening direction (left or right)
• Rack fixing (wall, raised floor, steel construction, concrete foundation).
Kits:
PCM cables impedance (120-ohm, 75-ohm).
Overview Preparation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-6 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Scheduling
Time based on technical constraints
The number of resources shown in the table below does not take into account individual
customer or safety requirements.
Task Time / Task
1st person
Time / Task
2nd person
“Before Going Onsite” (p. 3-3) 15 min. 15 min.
“Before You Start” (p. 3-4) 15 min. 15 min.
“Install Rack” (p. 3-5)1
* 15 min.
“Prepare Floor” (p. 3-5) 15 min. 15 min.
“Rack Delivery and Positioning” (p. 3-7) 15 min. 15 min.
“Prepare Site Cable Way” (p. 3-11) 15 min. 15 min.
“Fix Rack” (p. 3-13) 15 min. 15 min.
“How to Install Protective Earth and Power Supply
Cables” (p. 3-22)
“Install Cables in Site Cable Way” (p. 3-23) 10 min. -
“C1: Rack Top Entry of Cables” (p. 3-25) - 10 min.
“C2: Rack Bottom Entry of Cables” (p. 3-28) 10 min. 10 min.
“Connect Earth Cable (GND)” (p. 3-31) 10 min. -
“Connect DC 48 Volts Power Cables” (p. 3-34) - 10 min.
“Test Power Supply” (p. 3-38) 10 min. 10 min.
“Install PCM Cables” (p. 3-41)
“Install Cables in Cable Way” (p. 3-56) 10 min. 10 min.
“Run 120 Ohm PCM Cables” (p. 3-41) 20 min. 20 min.
“How to Finish Installation” (p. 3-85) 15 min. 15 min.
Total Time 2h 55 min. 2h 55 min.
Notes:
1. * Transportation time to final location depending of the site
The following table gives the duration for the optional tasks.
Overview Scheduling
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2-7
Task Time / Task
1st person
Time / Task
2nd person
“O2: Install Second Equipment in Rack” (p. 3-58)
“Install PCM Cables” (p. 3-58) 30 min. 30 min.
“Install Second ATCA Shelf” (p. 3-59) 30 min. 30 min.
“Install Second LIU Shelf” (p. 3-67) 10 min. 10 min.
“O3, O4, O5, O6, O7: Install Ethernet Cables”
(p. 3-71)
“O3: Install OMC-R Router Cables” (p. 3-71) 10 min. -
“O4: Install A-GPS Server Cable” (p. 3-72) - 10 min.
“O5: Install External Alarm Box” (p. 3-73) 10 min. -
“O6: Install SGSN Router Cables” (p. 3-74) 10 min. -
“O8: Install Optical Cables for STM1 in Release B11”
(p. 3-76)
15 min. 15 min.
Resources
Tools
The following tables describe the necessary hardware tools, software tools, and forms.
Installation Kits
Use the following table to check, onsite, the mandatory or optional delivery item kits.
The following symbols apply:
• • mandatory kit
• ∇ technical choice kit
• ◊ customer option kit.
Mandatory kits Mnemonic Reference
Quan-
tity
• Cabinet equipped JRXMX 3BK 27154 AA 1
• Basic installation kit JDMX 3BK 27244 AB 1
◊ PCM cables 120 Ohm: - - -
∇ 120 ohm - 8 LIU (20 m) PVCABE10 1AB 060540027 1
∇ 120 ohm - 8 LIU (30 m) PVCABE11 1AB 060540023 1
∇ 120 ohm - 8 LIU (40 m) PVCABE13 1AB 060540026 1
Overview Scheduling
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-8 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Mandatory kits Mnemonic Reference
Quan-
tity
◊ PCM cables 75 Ohm -
∇ 75 ohm - 8 LIU (20 m) JLIU75E1 3BK 15053 AAAF *
∇ 75 ohm - 8 LIU (30 m) JLIU75E1 3BK 15054 AAAF *
∇ 75 ohm - 8 LIU (40 m) JLIU75E1 3BK 15055 AAAF *
◊ Jumpers for DDF: - - -
∇ 120 ohm L904 (roll 100 m) CA120S 3BK 08941 AA -
◊ GND cable Yellow/Green 1 x 35 mm2
(roll
100 m)
PC35YG1D 3BK 08960 BA 1
◊ DC 48 Volts power cables
For distance 0m < L < 20m:
▸ ∇ -48V blue 1 x 16 mm2
(roll 100 m) PC16BL1D 3BK 08955 BB -
▸ ∇ 0V black 1 x 16 mm2
(roll 100 m) PC16B1D 3BK 08956 BA -
For distance 20m < L < 40m:
▸ ∇ -48V blue 1 x 25 mm2
(roll 100 m) PV25BL1D 3BK 08963 BA -
▸ ∇ 0V black 1 x 25 mm2
(roll 100 m) PV25B1D 3BK 08963 BB -
◊ Ethernet cable straight (roll 30 m) ALETHD 3BW 01804 JA 1
◊ Ethernet cable crossed (roll 30 m) ALETHC 3BW 01805 JA 1
◊ Wall support for 4 x MP24 DDF 1AD 02846 0001 -
◊ Terminal block 64E1 120 TERBLO1 1AB 23960 0001 1
◊ Terminal block 32 E1 75 BNC TERBLO2 1AB 27681 0002 1
BNC connector M BNCCON1 1AB 00642 0011 128
◊ Terminal block 32 E1 75 1656 TERBLO3 1AB 27681 0001 1
1656 connector M FLEX BNCCON2 1AB 02546 0013 128
◊ LABO rack 43U LABRAC1 1AD 03905 0001 1
◊ Vertical cable way JDTCO 3BK 25297 AA 2
◊ External alarm box EABMX 1AB 24048 0001 1
◊ Raised floor fixing JDTCFF 3BK 25341 AA 1
◊ Earthquake kit for raised floor fixing JDSISM 3BK 25284 AA 1
◊ STM1 cabling kit - - 1
SFP modules 8
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2-9
Mandatory kits Mnemonic Reference
Quan-
tity
Optical Fibre Cable JLOPT6 Depending of length:
• 3BK28064 GLAA
for L=15m
• 3BK 28064 HAAA
for L=20m
• 3BK 28064 HLAA
for L=25m
• 3BK 28064 JAAA lor
L=30m
• 3BK 28064 JFAA for
L=35m
• 3BK 28064 JLAA for
L=40m
4
Basic installation kit for Optical Fibre
cable
OFC3SEC 3BK27700ABAA 1
Hardware Tools
Refer to the Tools Catalogue for Field Activity for more information.
Kit name Reference Calibration
Basic kit tools OUT 001 no
Forms
You must have the following forms:
• SPP 10 - Site Condition Inspection Specification (All SPG/SPP)
(8BL 00704 0016 DRBRA)
• Site Premises Inspection Form (CEL)
8BL 00704 0015 DRBRA
Supplies
The installer must supply these kits (not included in Alcatel-Lucent kits).
Item Quantity
Set of rubber sleeves for all cables 1
Wire terminal Ø 8 mm for 16 mm2
cable (lug) 4
Wire terminal Ø 6 mm for 16 mm2
cable (lug) 5
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-10 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Applicable Documents
You must have the following documents or have electronic access to the following
documents:
• Catalogue of Instruction Operation (IO)
• Catalogue of Technical and Logistic Information (ITL–PRO)
• General Wiring Handbook
• Tools Catalogue for Field Activity
• CI-08 Site Equipment Inventory
• Dismantling Manual Generic CCL
• BSS Methods Handbook
• Install and Commission External Alarm Box
• Completion Check List (CCL)
• SPP 59 - Specification for 9130 BSC/MFS Evolution Site Preparation
• Install 9130 - BSC / MFS Evolution Digital Distribution Frame
• JLIU75E1 Wiring List, (3EJ 02719 AAAA JLZZA)
• JLIU75E1 Assembly Drawing, (3EJ 02719 AAAA HDZZA)
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
2-11
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-12 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3 3Scenario
Overview
Purpose
This Scenario presents all checks needed before beginning the scenario, and all detailed
tasks to be performed onsite.
Contents
Before Going Onsite 3-3
Overview 3-3
Before You Start 3-4
Before You Start 3-4
Install Rack 3-5
Prepare Floor 3-5
Rack Delivery and Positioning 3-7
Prepare Site Cable Way 3-11
Fix Rack 3-13
Install Protective Earth and Power Supply Cables 3-22
How to Install Protective Earth and Power Supply Cables 3-22
Install Cables in Site Cable Way 3-23
C1: Rack Top Entry of Cables 3-25
C2: Rack Bottom Entry of Cables 3-28
Connect Earth Cable (GND) 3-31
Connect DC 48 Volts Power Cables 3-34
Test Power Supply 3-38
Install PCM Cables 3-41
...................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-1
Run 120 Ohm PCM Cables 3-41
Run 75 Ohm PCM Cables 3-47
Install Cables in Cable Way 3-56
O2: Install Second Equipment in Rack 3-58
Install PCM Cables 3-58
Install Second ATCA Shelf 3-59
Install Second LIU Shelf 3-67
Install Internal Ethernet Cables 3-70
O3, O4, O5, O6, O7: Install Ethernet Cables 3-71
O3: Install OMC-R Router Cables 3-71
O4: Install A-GPS Server Cable 3-72
O5: Install External Alarm Box 3-73
O6: Install SGSN Router Cables 3-74
O7: Install Ethernet Cables for IP Telecom Traffic in Release B11 3-75
O8: Install Optical Cables for STM1 in Release B11 3-76
How to Install Optical Cables for STM1 in Release B11 3-76
Install Optical Cables in Cable Way 3-77
Install SFP Modules 3-79
Route Optical Cables 3-81
Finish Installation 3-85
How to Finish Installation 3-85
Scenario Overview
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-2 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Before Going Onsite
Overview
Overview
Before going onsite, check that the following information and supplies are available:
• All “Prerequisites” (p. 2-6) are met
• The customer has been informed of the following information:
You must indicate:
– Date and time
– Site name and address
– Purpose of the operation.
• Personnel are available; refer to “Scheduling” (p. 2-7)
• “Site Specific Information” (p. 2-6) is available
• “Tools” (p. 2-8) are available and ready for operation
• “Installation Kits” (p. 2-8) are available and ready for operation
• “Supplies” (p. 2-10) are available and ready for operation
• “Applicable Documents” (p. 2-11) are available.
Scenario
Before Going Onsite
Overview
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-3
Before You Start
Before You Start
Checks
Perform the following operations:
• Check that all “Prerequisites” (p. 2-6) are met
• Check applicable notifications and operating instructions (refer to the Catalogue of
Instruction Operation (IO) and Catalogue of Technical and Logistic Information
(ITL–PRO))
• Check the availability of all necessary “Tools” (p. 2-8), “Installation Kits” (p. 2-8) and
“Supplies” (p. 2-10)
• Refer to the SPP 10 - Site Condition Inspection Specification (All SPG/SPP) and
complete the Site Premises Inspection Form (CEL)
• Check that the safety precautions are taken in accordance with the safety instructions
described in the B11 BSS Methods Handbook
• Complete the header field of the CCL. Complete the CCL as each instruction is
carried out.
Attention: Among the “Cases” (p. 2-3) and the “Options” (p. 2-4), identify which
cases and options apply to you.
Required Knowledge
You must be familiar with the following:
• Safety Rules and Precautions
• How to document Faults and Anomalies.
Scenario
Before You Start
Before You Start
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-4 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Install Rack
Prepare Floor
Overview
Note: To be compliant with EN 60950 rules, it is mandatory that the rack be fixed to
the floor (refer to SPP 59 - Specification for 9130 BSC/MFS Evolution Site
Preparation).
There are two installation cases:
• Fixing to a concrete floor
• Fixing to a raised floor.
C1: Concrete Floor Drilling
The following figure shows concrete floor drilling.
Drill the concrete floor:
...................................................................................................................................................................................................
1 Using the supplied template, mark the concrete foundation.
...................................................................................................................................................................................................
2 Drill holes in the concrete foundation (Ø 12 mm, h = 70 mm).
C2: Raised Floor Drilling
The following figure shows raised floor drilling.
Drill the raised floor:
...................................................................................................................................................................................................
1 Using a template, cut a rectangular hole in the tile to pass the cables.
...................................................................................................................................................................................................
2 Using a template, drill the following holes.
Scenario
Install Rack
Prepare Floor
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-5
E N D O F S T E P S...................................................................................................................................................................................................
You must:
• Drill the tile Ø12 mm
• Drill the floor Ø12 mm, h = 60 mm +/-3 mm.
Scenario
Install Rack
Prepare Floor
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-6 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Rack Delivery and Positioning
Overview
The following figure shows the rack delivery and positioning.
Scenario
Install Rack
Rack Delivery and Positioning
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-7
Scenario
Install Rack
Rack Delivery and Positioning
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-8 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Procedure
Position the rack:
...................................................................................................................................................................................................
1 Place the rack in position.
You must:
• Lift the rack by crane with packaging or,
• Lift the rack by crane using eyebolts of rack or,
• Transport the rack by pallet near to its final position.
...................................................................................................................................................................................................
2 Unpack the rack.
...................................................................................................................................................................................................
3 Remove the bottom cover plate of rack.
...................................................................................................................................................................................................
4 At top of the rack, remove the craning eyebolts.
...................................................................................................................................................................................................
5 A box with four Ethernet cables is delivered inside the rack. Leave the cables in the rack.
The cables are connected during commissioning.
...................................................................................................................................................................................................
6 On the back side of the ATCA shelf, remove metallic parts used during transportation. If
two shelves are equipped, remove the metallic parts on both shelves.
Note: If the metallic parts used for transportation are removed during the installation,
keep the parts safely onsite to be reused for transportation in the case of dismantling.
Scenario
Install Rack
Rack Delivery and Positioning
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-9
...................................................................................................................................................................................................
7 Slightly unfasten the screws fixing the JSXPDU (one or two turns).
...................................................................................................................................................................................................
8 Shift the JSXPDU to the top of the rack as much as possible.
...................................................................................................................................................................................................
9 Fasten the screws to fix the JSXPDU.
Figure 3-1 Fixing Items to be Removed on Shelf Back Side
Scenario
Install Rack
Rack Delivery and Positioning
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-10 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Prepare Site Cable Way
C1: Top Rack Entry of Cables
Nr Materials Reference Kit
1 Vertical cable way kit 3BK 25297 AAAA JDTCO
2 Edge protection 1AD 01782 0001 JDMX
The following figure shows the cable way.
Procedure
Prepare the cable way:
...................................................................................................................................................................................................
1 Cut a hole in the site cable way for each used cable entry.
Scenario
Install Rack
Prepare Site Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-11
...................................................................................................................................................................................................
2 Cover the cut-out with edge protection (1AD 01782 0001).
...................................................................................................................................................................................................
3 Fix the support to the rack.
...................................................................................................................................................................................................
4 Fix the separating corner to the vertical cable way.
...................................................................................................................................................................................................
5 Fix the vertical cable way to the support at top of rack.
...................................................................................................................................................................................................
6 Fix the vertical cable way to the site cable way.
...................................................................................................................................................................................................
7 Follow the same procedure to install the second vertical cable way.
C2: Bottom Rack Entry of Cables
No specific preparation of cable way. Use the same rules for cable separating.
Scenario
Install Rack
Prepare Site Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-12 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Fix Rack
C1: Concrete Floor Fixing
Nr Materials Reference Kit
1 Expanding plug for hole Ø 12 mm 1AD 01166 0001 3BK 27244 ABAA
(JDMX)2 Screws HM 8 x 65 mm 1AD 00215 0042
3 Washer Ø 8 mm 1AD 00087 0149
The following figure shows how to level the rack then fix the rack to the concrete floor.
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-13
Figure 3-2 Level Rack then Fix Rack to Concrete Floor
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-14 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Procedure
Fix the rack to the concrete floor:
...................................................................................................................................................................................................
1 Put the expanding plug in the concrete floor.
...................................................................................................................................................................................................
2 Place the rack to its final position.
...................................................................................................................................................................................................
3 Level the rack.
...................................................................................................................................................................................................
4 Screw the screw with the washer to fix the rack.
C2: Raised Floor Fixing
Nr Materials Reference Kit
1 Screw Ø 8 mm x 80 mm 1AD 00215 0092 3BK 25341 AA
(JDTCFF)
+
3BK 27244 AB
(JDMX)
2 Washer Ø 8 mm 1AD 00087 0149
3 Frame of rack -
4 Raised floor support 3BK 08094 AA
5 Coupling nut Ø 8 mm 1AD 01655 0001
6 Threaded rod Ø 8 mm 1AD 01660 0003
7 Hexagon nut Ø 8 mm 1AD 00197 0006
8 Washer Ø 8 mm 1AD 00087 0149
9 Wall plug Ø 8 mm for hole Ø 12 mm 1AD 01666 0001
The following figure shows a raised floor fixing.
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-15
E N D O F S T E P S...................................................................................................................................................................................................
Note: In this case, do not level the rack.
Fix the rack to the raised floor:
...................................................................................................................................................................................................
1 Place the rack to its final position.
Figure 3-3 Raised Floor Fixing Example
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-16 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
2 Put the expanding plug (9) in the concrete floor (see Figure 3-3, “Raised Floor Fixing
Example” (p. 3-16)).
...................................................................................................................................................................................................
3 Screw the threaded rod (6), then the washer (8) and nut (7).
...................................................................................................................................................................................................
4 Screw the coupling nut (5) as shown in Figure 3-3, “Raised Floor Fixing Example”
(p. 3-16).
...................................................................................................................................................................................................
5 Screw the screw (1) with the washer (2).
O1: Earthquake Fixing
Attention: This option can be installed only with a raised floor exactly 34 cm high
from the concrete ground.
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-17
E N D O F S T E P S...................................................................................................................................................................................................
Figure 3-4 Mechanical Assembling of Frame
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-18 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Nr Materials Reference Kit
1 Pedestal 3BK 25339 AAAA 3BK 25284 AAAA
(JDSISM)2 Bracket 3BK 25340 AAAA
3 Screw 16 x 40 1AD 00204 0059
4 Washer M16 1AD 00254 0006
5 Screw 8 x 35 1AD 00254 0038
6 Washer M8 1AD 00254 0003
7 Nut H8 1AD 00197 0006
8 Expanding wall plug 1AD 02655 0001
9 Washer M10 1AD 00453 0005
10 Screw 10 x 65 1AD 00050 0010
The following figure shows how to fix an earthquake frame.
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-19
Fix the earthquake frame:
...................................................................................................................................................................................................
1 Assemble the earthquake frame using screw (3) and washer (4) (see Figure 3-4,
“Mechanical Assembling of Frame” (p. 3-18)).
Figure 3-5 Fixing Raised Floor at Same Level of Earthquake Frame)
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-20 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
2 Using the earthquake frame, mark the concrete ground.
...................................................................................................................................................................................................
3 Drill the ground and fit the wall plug (8) (see Figure 3-5, “Fixing Raised Floor at Same
Level of Earthquake Frame)” (p. 3-20)).
...................................................................................................................................................................................................
4 Fix the earthquake frame using the washer (9) and screw (10).
...................................................................................................................................................................................................
5 Fix the rack to the frame using (5) (6) (7).
...................................................................................................................................................................................................
6 Cut and fit the tiles around the earthquake frame.
Scenario
Install Rack
Fix Rack
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-21
E N D O F S T E P S...................................................................................................................................................................................................
Install Protective Earth and Power Supply Cables
How to Install Protective Earth and Power Supply Cables
Overview
DANGER
Electric-shock hazard
Risk of electrocution to personnel and damage to equipment.
Before making any electrical connections to the rack, ensure that the safety instructions
are followed.
It is essential that:
• The electrical power supply is disconnected. Ensure all breakers or fuses devoted to
the new rack into the site connection box are switched OFF
• The protective EARTH (GND) must be connected to the equipment before DC power
cable connection. It must be firstly connected at site side and secondly at rack side.
Ensure that the safety rules are applied.
Scenario
Install Protective Earth and Power Supply Cables
How to Install Protective Earth and Power Supply Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-22 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Install Cables in Site Cable Way
Overview
The following figure shows how to install the cables in the site cable way.
Procedure
Install the cables in the cable way:
...................................................................................................................................................................................................
1 Install a yellow/green cable in the power compartment of the cable way.
...................................................................................................................................................................................................
2 Install DC 48V power cables in the power compartment of the cable way (BATA, BATB
and BATR cables).
...................................................................................................................................................................................................
3 Attach the cables with plastic tie wraps.
Scenario
Install Protective Earth and Power Supply Cables
Install Cables in Site Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-23
...................................................................................................................................................................................................
4 Cut the cables to the required length.
Scenario
Install Protective Earth and Power Supply Cables
Install Cables in Site Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-24 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
C1: Rack Top Entry of Cables
Procedure
Run the cables:
...................................................................................................................................................................................................
1 Remove the top cover plate.
...................................................................................................................................................................................................
2 Cover the cable entry window with edge protection.
...................................................................................................................................................................................................
3 Fit the corner profile to the left or to the right of the cabinet according to the site
configuration.
...................................................................................................................................................................................................
4 Fix the 200 mm braid to the cable way (mechanical ground) (see Figure 3-7, “Power
Cables Outlet General View” (p. 3-27)).
...................................................................................................................................................................................................
5 Fix the earth braid to the specific stud of the rack.
Additional information
The following figure shows the top cable entry.
Scenario
Install Protective Earth and Power Supply Cables
C1: Rack Top Entry of Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-25
E N D O F S T E P S...................................................................................................................................................................................................
The following figure shows a general view of the power cable outlet.
Figure 3-6 Top Cable Entry
Scenario
Install Protective Earth and Power Supply Cables
C1: Rack Top Entry of Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-26 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Figure 3-7 Power Cables Outlet General View
Scenario
Install Protective Earth and Power Supply Cables
C1: Rack Top Entry of Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-27
C2: Rack Bottom Entry of Cables
Procedure
Run the cables:
...................................................................................................................................................................................................
1 Cover the cable entry windows with edge protection.
...................................................................................................................................................................................................
2 Pass the power cables for branch A through the left cable entry.
Scenario
Install Protective Earth and Power Supply Cables
C2: Rack Bottom Entry of Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-28 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
3 Pass the GND cable and power cables for branch B through the right cable entry.
...................................................................................................................................................................................................
4 Fix the metallic braid to the raised floor cable way.
Figure 3-8 Bottom Cable Entry
Scenario
Install Protective Earth and Power Supply Cables
C2: Rack Bottom Entry of Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-29
...................................................................................................................................................................................................
5 Cut the metallic sheet to the required length and fit a lug.
...................................................................................................................................................................................................
6 Screw the metallic sheet to the dedicated studs of the rack.
...................................................................................................................................................................................................
7 Run the power cables for branch A through the left cable duct to the top of the rack.
...................................................................................................................................................................................................
8 Run the GND cable and power cables for branch B through the right cable duct to the top
of the rack.
Figure 3-9 Metallic Braid Fixed to Raised Floor Cable Way
Scenario
Install Protective Earth and Power Supply Cables
C2: Rack Bottom Entry of Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-30 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Connect Earth Cable (GND)
Overview
Nr Materials Reference Kit
1 90° bent lugs Depending on diameter of cables Basic kit 3BK 27244 ABAA
(JDMX)
2 Tie wrap - Consumable supplies
3 Label -
The following figure shows how to connect the earth cable.
Scenario
Install Protective Earth and Power Supply Cables
Connect Earth Cable (GND)
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-31
Procedure
Connect the earth cable:
...................................................................................................................................................................................................
1 Label the site end of the GND cable (for example: 9130 MFS/BSC Evolution N° 4).
...................................................................................................................................................................................................
2 Crimp an adapted lug at the site side and at the rack side of the GND yellow/green cable.
Scenario
Install Protective Earth and Power Supply Cables
Connect Earth Cable (GND)
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-32 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
3 Before connecting to the rack, connect the yellow/green GND cable to the site earth plate.
...................................................................................................................................................................................................
4 Connect the yellow/green GND cable to the rack.
Scenario
Install Protective Earth and Power Supply Cables
Connect Earth Cable (GND)
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-33
E N D O F S T E P S...................................................................................................................................................................................................
Connect DC 48 Volts Power Cables
Overview
Nr Materials Reference Kit
1 Labels 3BK 25932 AAAA Basic kit 3BK 27244 ABAA
(JDMX)2 90° bent lugs Depending on diameter of cables
3 Tie wrap - Consumable supplies
Procedure
Install the power cables:
...................................................................................................................................................................................................
1 Remove the protective covers for Branch A and Branch B.
...................................................................................................................................................................................................
2 Crimp a Ø 6 lug at rack side for each power cable.
...................................................................................................................................................................................................
3 Fit sleeves on all cables.
...................................................................................................................................................................................................
4 Connect the black cables to BATR studs.
...................................................................................................................................................................................................
5 Connect the -48 Volts blue cables to BATA and BATB studs.
Scenario
Install Protective Earth and Power Supply Cables
Connect DC 48 Volts Power Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-34 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
6 Crimp an adapted lug for all cables at the site side.
...................................................................................................................................................................................................
7 Connect the cables to the site fuse breakers.
Figure 3-10 Power Cables Connection
Scenario
Install Protective Earth and Power Supply Cables
Connect DC 48 Volts Power Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-35
...................................................................................................................................................................................................
8 Label the ends of each cable.
Figure 3-11 Site Fuse Breaker Example
Scenario
Install Protective Earth and Power Supply Cables
Connect DC 48 Volts Power Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-36 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Figure 3-12 Label Power Cables
Scenario
Install Protective Earth and Power Supply Cables
Connect DC 48 Volts Power Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-37
E N D O F S T E P S...................................................................................................................................................................................................
Test Power Supply
Procedure
Test the power supply:
...................................................................................................................................................................................................
1 On the site power cabinet, check if DC 48 volts fuse breakers are switched OFF (BATA
and BATB).
...................................................................................................................................................................................................
2 On the rack side, check that all power breakers on JSXPDU are switched OFF;
otherwise switch them OFF.
...................................................................................................................................................................................................
3 On the rack side, check that the power breakers on all JBXPSs are switched OFF;
otherwise switch them OFF.
...................................................................................................................................................................................................
4 On the rack side, on the connection box, with an ohmmeter, test if there is no short
circuit between -48 volts (BATA or BATB) and 0 volts (BATR).
Scenario
Install Protective Earth and Power Supply Cables
Test Power Supply
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-38 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
5 On the rack side, perform the same test between the -48V cables.
...................................................................................................................................................................................................
6 On the site power cabinet, check that the site fuse breakers correspond to the
recommendations from SPP 59 - Specification for 9130 BSC/MFS Evolution Site
Preparation.
...................................................................................................................................................................................................
7 On the site power cabinet, switch ON the DC 48 volts fuse breakers (BATA and BATB).
...................................................................................................................................................................................................
8 On the rack side, measure if 48 V is present on the BATA and verify the polarity.
Scenario
Install Protective Earth and Power Supply Cables
Test Power Supply
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-39
...................................................................................................................................................................................................
9 On the rack side, measure if 48 V is present on the BATB and verify the polarity.
...................................................................................................................................................................................................
10 On the site power cabinet, switch OFF the site fuse breakers.
...................................................................................................................................................................................................
11 When all power lines are checked, replace the JSXPDU covers and fix them with the
provided screws.
Scenario
Install Protective Earth and Power Supply Cables
Test Power Supply
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-40 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Install PCM Cables
Run 120 Ohm PCM Cables
C1: Top Entry of Cables
Route the cables from the top:
...................................................................................................................................................................................................
1 Bind the cables in groups of eight cables as shown in the following figure.
...................................................................................................................................................................................................
2 Run the group of eight cables through the cable ducts to the bottom of the rack.
...................................................................................................................................................................................................
3 Run the cables under the rack through the side cable entries of the rack.
Figure 3-13 Bind Cables
Scenario
Install PCM Cables
Run 120 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-41
...................................................................................................................................................................................................
4 Run the cables to the JSXLIU shelf through the front cable entry of the rack.
...................................................................................................................................................................................................
5 Separate the cables.
...................................................................................................................................................................................................
6 Label the PCM cables.
...................................................................................................................................................................................................
7 Leave the cables near JSXLIU shelf, not connected.
...................................................................................................................................................................................................
8 If a second ATCA shelf must be installed, run the cables before ATCA shelf installation.
Figure 3-14 Cable Routing Front View
Scenario
Install PCM Cables
Run 120 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-42 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Figure 3-15 Top Rack Cable Entry General View
Scenario
Install PCM Cables
Run 120 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-43
E N D O F S T E P S...................................................................................................................................................................................................
C2: Bottom Entry of Cables
Route the cables from the bottom:
...................................................................................................................................................................................................
1 Run the cables through the front window in the bottom plate (see Figure 3-8, “Bottom
Cable Entry” (p. 3-29)).
...................................................................................................................................................................................................
2 Attach the cables to the rack using adhesive cable ties.
...................................................................................................................................................................................................
3 Label the PCM cables.
...................................................................................................................................................................................................
4 Leave the cables near the JSXLIU shelf, not connected.
...................................................................................................................................................................................................
5 If a second ATCA shelf must be installed, run the cables before ATCA shelf installation.
Scenario
Install PCM Cables
Run 120 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-44 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Figure 3-16 Cable Routing Front View
Scenario
Install PCM Cables
Run 120 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-45
Figure 3-17 Cable Routing Side View
Scenario
Install PCM Cables
Run 120 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-46 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Run 75 Ohm PCM Cables
Top Entry of Cables
Route the cables:
...................................................................................................................................................................................................
1 For the first eight cables on each side of the rack, run the free end of the cables, from the
bottom, through the cable duct to the top of the rack.
...................................................................................................................................................................................................
2 If more than eight cables are required on each side, run the cables between the cable duct
and the rack back side, close to the side walls.
Attention: Ensure that the PCM cables:
• Are as close as possible to the side wall
• Do not block a potential JSXLIU shelf dismantling from the back side of the rack
• Cannot be damaged when running out at the rack top (edge protection is
available).
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-47
...................................................................................................................................................................................................
3 Run the cables under the JXSLIU shelf.
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-48 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
4 Ensure that the PCM cables are close to the rack side panels.
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-49
...................................................................................................................................................................................................
5 Label the PCM cables.
...................................................................................................................................................................................................
6 Connect the PCM cables to the JBXLIU boards.
...................................................................................................................................................................................................
7 Fit the PCM cables at the required length.
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-50 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
8 Disconnect the PCM cables from the JBXLIU boards and leave them near the JSXLIU
shelf, not connected. PCM cable connection is performed during commissioning,
according to customer requirements.
Bottom Entry of Cables
Route the cables from the bottom:
...................................................................................................................................................................................................
1 Run the cables through the front window in the bottom plate.
Note: If two JSXLIU shelves are used, the PCM cables can also be routed through the
side cable windows.
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-51
E N D O F S T E P S...................................................................................................................................................................................................
...................................................................................................................................................................................................
2 Attach the cables to the rack using adhesive cable ties.
...................................................................................................................................................................................................
3 Label the PCM cables.
...................................................................................................................................................................................................
4 Connect the PCM cables to the JBXLIU boards.
Figure 3-18 Bottom Cable Entry
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-52 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
5 Fit the PCM cables at the required length.
...................................................................................................................................................................................................
6 Disconnect the PCM cables from the JBXLIU boards and leave them near the JSXLIU
shelf, not connected. PCM cable connection is performed during commissioning,
according to customer requirements.
The following figures show a front and side view for the cable routing solution.
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-53
Figure 3-19 Cable Routing Front View
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-54 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Figure 3-20 Cable Routing Side View
Scenario
Install PCM Cables
Run 75 Ohm PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-55
E N D O F S T E P S...................................................................................................................................................................................................
Install Cables in Cable Way
Overview
Note: Refer to “Site Specific Information” (p. 2-6) to know the quantity of PCM
cables to install.
If a second ATCA shelf must be installed, install the PCM cables now for this ATCA
shelf.
Nr Materials Reference Kit
1 Tie wraps - Consumable supplies
Note: Before starting the installation, ensure that the PCM cables have the required
length.
Scenario
Install PCM Cables
Install Cables in Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-56 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Procedure
Install the cables in the cable way:
...................................................................................................................................................................................................
1 Install cables in the PCM compartment of the cable tray.
...................................................................................................................................................................................................
2 Attach the cables with plastic tie wraps.
...................................................................................................................................................................................................
3 Mark the cables with a marker.
Scenario
Install PCM Cables
Install Cables in Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-57
E N D O F S T E P S...................................................................................................................................................................................................
O2: Install Second Equipment in Rack
Install PCM Cables
Procedure
To install the PCM cables for the second equipment, refer to “Install PCM Cables”
(p. 3-41).
Scenario
O2: Install Second Equipment in Rack
Install PCM Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-58 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Install Second ATCA Shelf
Prepare ATCA Shelf
Before starting the installation:
...................................................................................................................................................................................................
1 Unpack the second ATCA shelf.
...................................................................................................................................................................................................
2 Visually check that the ATCA shelf is in a good state.
...................................................................................................................................................................................................
3 Check on the rack that the 16 screws and/or nuts required for second ATCA shelf
installation are available.
...................................................................................................................................................................................................
4 Ensure that nothing can block the second ATCA shelf insertion in the cabinet.
...................................................................................................................................................................................................
5 Ensure that PCM cables for the second ATCA shelf are already installed; if they are not,
install the PCM cables before ATCA shelf installation.
Install ATCA Shelf
Install the second ATCA shelf:
...................................................................................................................................................................................................
1 Put on an ESD wrist strap.
...................................................................................................................................................................................................
2 Connect the strap to the shelf by attaching the front or rear ESD jack.
...................................................................................................................................................................................................
3 Lift the shelf and place it above the existing one.
Attention: Do not hold the ATCA shelf from inside; hold it by the side panels.
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-59
E N D O F S T E P S...................................................................................................................................................................................................
...................................................................................................................................................................................................
4 Fasten the shelf to the rack with the provided screws.
Install ATCA Shelf Power Cables
Perform the following steps:
...................................................................................................................................................................................................
1 Depending on the ATCA shelf variant
Apply the appropriate case:
• “Install ATCA Shelf Power Cables in Case of Shelf Variant Before 3BK 27291 ABxx”
(p. 3-61)
• “Install ATCA Shelf Power Cables in Case from Shelf Variant 3BK 27291 ABxx On”
(p. 3-64).
Figure 3-21 Wrong Handling of ATCA Shelf
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-60 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
E N D O F S T E P S...................................................................................................................................................................................................
Install ATCA Shelf Power Cables in Case of Shelf Variant Before 3BK 27291 ABxx
Connect the ground and power cables to the second ATCA shelf:
...................................................................................................................................................................................................
1 Open the back door of the rack.
...................................................................................................................................................................................................
2 Connect the ground cable to the ground stud of the shelf.
...................................................................................................................................................................................................
3 Remove the M6 nuts and lockwashers from each of the connections on the JBXPSs and
set aside.
...................................................................................................................................................................................................
4 Install the power cables to the connections on the JBXPSs with the M6 nuts and
lockwashers previously removed. Torque nuts to 7.1 Nm (63 lbf.in).
...................................................................................................................................................................................................
5 Connect the power cables.
As follows:
• -48V blue cable labeled Shelf 4 A1 M83 to JBXPS1 Power studs
• 0V blue-black cable labeled Shelf 4 A1 M83 to JBXPS1 Return studs
• -48V blue cable labeled Shelf 4 A1 M81 to JBXPS3 Power studs
• 0V blue-black cable labeled Shelf 4 A1 M81 to JBXPS3 Return studs
Figure 3-22 Ground Cable and ESD Jack Connection
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-61
• -48V blue cable labeled Shelf 4 B1 M82 to JBXPS2 Power studs
• 0V blue-black cable labeled Shelf 4 B1 M82 to JBXPS2 Return studs
• -48V blue cable labeled Shelf 4 B1 M80 to JBXPS4 Power studs
• 0V blue-black cable labeled Shelf 4 B1 M80 to JBXPS4 Return studs
...................................................................................................................................................................................................
6 Fit the rubber protection caps on the terminals.
Figure 3-23 Rear View of ATCA Shelf Variant Before 3BK 27291 ABxx
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-62 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
...................................................................................................................................................................................................
7 Switch JBXPSs handle switch to the Closed position.
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-63
...................................................................................................................................................................................................
8 Disconnect the wrist strap from the shelf.
...................................................................................................................................................................................................
9 Remove the ESD wrist strap from your hand.
...................................................................................................................................................................................................
10 Close the back door of the rack.
Install ATCA Shelf Power Cables in Case from Shelf Variant 3BK 27291 ABxx On
Connect the ground and power cables to the second ATCA shelf:
...................................................................................................................................................................................................
1 Open the back door of the rack.
...................................................................................................................................................................................................
2 Connect the ground cable to the ground stud of the shelf.
...................................................................................................................................................................................................
3 Remove the M6 nuts and lockwashers from each of the connections on the JBXPSs and
set aside.
Figure 3-24 Ground Cable and ESD Jack Connection
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-64 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
...................................................................................................................................................................................................
4 Install the power cables to the connections on the JBXPSs with the M6 nuts and
lockwashers previously removed. Torque nuts to 7.1 Nm (63 lbf.in).
...................................................................................................................................................................................................
5 Connect the power cables.
As follows:
• -48V blue cable labeled Shelf 4 A1 M81 to JBXPS1 Power studs
• 0V blue-black cable labeled Shelf 4 A1 M81 to JBXPS1 Return studs
• -48V blue cable labeled Shelf 4 B1 M82 to JBXPS2 Power studs
• 0V blue-black cable labeled Shelf 4 B1 M82 to JBXPS2 Return studs
Note: Do not remove the protection from the free end of the unused power cables.
...................................................................................................................................................................................................
6 Fit the rubber protection caps on the terminals.
Figure 3-25 Rear View of ATCA Shelf from Shelf Variant 3BK 27291 ABxx On
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-65
...................................................................................................................................................................................................
7 Disconnect the wrist strap from the shelf.
...................................................................................................................................................................................................
8 Remove the ESD wrist strap from your hand.
...................................................................................................................................................................................................
9 Close the back door of the rack.
Scenario
O2: Install Second Equipment in Rack
Install Second ATCA Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-66 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Install Second LIU Shelf
Prepare Second LIU Shelf
Before starting the installation:
...................................................................................................................................................................................................
1 Unpack the second LIU shelf.
...................................................................................................................................................................................................
2 Visually check that the LIU shelf is in a good state.
...................................................................................................................................................................................................
3 Ensure that nothing can block the second LIU shelf insertion in the cabinet.
...................................................................................................................................................................................................
4 Identify the installation case.
As follows:
• The existing LIU shelf is installed from the rear
• The existing LIU shelf is installed from the front.
...................................................................................................................................................................................................
5 Perform the following steps only if the shelf must be installed from the front.
...................................................................................................................................................................................................
6 Loosen the screws fixing the brackets at the rear of the shelf and remove the brackets.
Figure 3-26 Brackets at Shelf Rear
Scenario
O2: Install Second Equipment in Rack
Install Second LIU Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-67
...................................................................................................................................................................................................
7 Fit the screws to the former position.
...................................................................................................................................................................................................
8 Loosen the screws at the front of the shelf.
...................................................................................................................................................................................................
9 Mount the fixation brackets at the front of the shelf and fix them with the screws.
Figure 3-27 Brackets at Shelf Front
Scenario
O2: Install Second Equipment in Rack
Install Second LIU Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-68 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Install LIU Shelf
Install the LIU shelf:
...................................................................................................................................................................................................
1 Put on an ESD wrist strap.
...................................................................................................................................................................................................
2 Connect the strap to the shelf by attaching the front or rear ESD jack.
...................................................................................................................................................................................................
3 Lift the shelf and place it above the existing one.
As follows:
• From the back when the existing LIU shelf is installed from the rear
• From the front when the existing LIU shelf is installed from the front.
Attention: Do not hold the LIU shelf from inside; hold it by the side panels.
...................................................................................................................................................................................................
4 Fasten the shelf to the rack with the provided screws.
...................................................................................................................................................................................................
5 Connect the power cables to the JBXPEM boards.
Scenario
O2: Install Second Equipment in Rack
Install Second LIU Shelf
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-69
E N D O F S T E P S...................................................................................................................................................................................................
Install Internal Ethernet Cables
Procedure
Install the internal Ethernet cables:
...................................................................................................................................................................................................
1 Connect the first JLCAT6 Ethernet cable (1AB 22983 0005) between ATCA shelf 4,
JAXSSW1, Ethernet port 2 and the GbE port on JBXMUX1 (slot 10) in JSXLIU shelf 2.
...................................................................................................................................................................................................
2 Connect the second JLCAT6 Ethernet cable (1AB 22983 0005) between ATCA shelf 4,
JAXSSW2, Ethernet port 2 and the GbE port on JBXMUX2 (slot 12) in JSXLIU shelf 2.
Scenario
O2: Install Second Equipment in Rack
Install Internal Ethernet Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-70 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
O3, O4, O5, O6, O7: Install Ethernet Cables
O3: Install OMC-R Router Cables
Overview
Nr Materials Reference Kit
1 Labels OMC-R
Ethernet cables
- Basic kit 3BK 27244 ABAA (JDMX)
2 OMC-R Ethernet
cables (ALETHD)
3BW 01804 JA -
Procedure
Install the OMC-R (and CBC for the 9130 BSC Evolution) router cables:
...................................................................................................................................................................................................
1 Refer to “Site Specific Information” (p. 2-6) for quantity and cabling of OMC-R cables.
...................................................................................................................................................................................................
2 Pass the cables into the cabinet the same way as for PCM cables.
...................................................................................................................................................................................................
3 Attach the cable to the rack.
...................................................................................................................................................................................................
4 If the connecting position is unknown, do not connect the cables.
...................................................................................................................................................................................................
5 Label the cables at each end, near the connectors.
Scenario
O3, O4, O5, O6, O7: Install Ethernet Cables
O3: Install OMC-R Router Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-71
E N D O F S T E P S...................................................................................................................................................................................................
O4: Install A-GPS Server Cable
Overview
Nr Materials Reference Kit
1 Labels A-GPS
Ethernet cable
- Basic kit 3BK 27244 ABAA (JDMX)
2 A-GPS Ethernet
cables (ALETHD)
3BW 01804 JA -
Procedure
Install the A-GPS cables:
...................................................................................................................................................................................................
1 Refer to “Site Specific Information” (p. 2-6) for quantity and cabling of A-GPS cables.
...................................................................................................................................................................................................
2 Pass the cables into the cabinet the same way as for the PCM cables.
...................................................................................................................................................................................................
3 Attach the cable to the rack.
...................................................................................................................................................................................................
4 If the connecting position is unknown, do not connect the cables.
...................................................................................................................................................................................................
5 Label the cables at each end, near the connectors.
Scenario
O3, O4, O5, O6, O7: Install Ethernet Cables
O4: Install A-GPS Server Cable
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-72 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
O5: Install External Alarm Box
Overview
Nr Materials Reference Kit
1 Labels EAB
Ethernet cable
- Basic kit 3BK 27244 ABAA (JDMX)
2 External Alarm Box 3BW 01804 JA -
Procedure
Install the External Alarm Box:
...................................................................................................................................................................................................
1 Refer to External Alarm Box Installation and Commissioning.
...................................................................................................................................................................................................
2 Pass the cable for EAB into the cabinet in the same way as for the PCM cables.
...................................................................................................................................................................................................
3 Attach the cable to the rack.
...................................................................................................................................................................................................
4 If the connecting position is unknown, do not connect the cable.
...................................................................................................................................................................................................
5 Label the cable at each end, near the connectors.
Scenario
O3, O4, O5, O6, O7: Install Ethernet Cables
O5: Install External Alarm Box
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-73
E N D O F S T E P S...................................................................................................................................................................................................
O6: Install SGSN Router Cables
Overview
Nr Materials Reference Kit
1 Labels SGSN
Ethernet cables
- Basic kit 3BK 27244 ABAA (JDMX)
2 SGSN Ethernet
cables (ALETHD)
3BW 01804 JA -
Procedure
Install the SGSN router cables:
...................................................................................................................................................................................................
1 Refer to “Site Specific Information” (p. 2-6) for the quantity and cabling of SGSN cables.
...................................................................................................................................................................................................
2 Pass the cables into the cabinet the same way as for the PCM cables.
...................................................................................................................................................................................................
3 Attach the cable to the rack.
...................................................................................................................................................................................................
4 If the connecting position is unknown, do not connect the cables.
...................................................................................................................................................................................................
5 Label the cables at each end, near the connectors.
Scenario
O3, O4, O5, O6, O7: Install Ethernet Cables
O6: Install SGSN Router Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-74 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
O7: Install Ethernet Cables for IP Telecom Traffic in Release
B11
Overview
Nr Materials Reference Kit
1 Labels IP telecom
traffic Ethernet
cables
- Basic kit 3BK 27244 ABAA (JDMX)
2 IP telecom traffic
Ethernet cables
(ALETHD)
3BW 01804 JA -
Procedure
Install the IP telecom traffic router cables:
...................................................................................................................................................................................................
1 Refer to the BSS Telecom Routing Configuration.
...................................................................................................................................................................................................
2 Pass the cables into the cabinet the same way as for the PCM cables.
...................................................................................................................................................................................................
3 Attach the cable to the rack.
...................................................................................................................................................................................................
4 If the connecting position is unknown, do not connect the cables.
...................................................................................................................................................................................................
5 Label the cables at each end, near the connectors.
Scenario
O3, O4, O5, O6, O7: Install Ethernet Cables
O7: Install Ethernet Cables for IP Telecom Traffic in Release
B11
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-75
E N D O F S T E P S...................................................................................................................................................................................................
O8: Install Optical Cables for STM1 in Release B11
How to Install Optical Cables for STM1 in Release B11
Overview
Note: This task must be performed only if the STM1 option was selected at BSC side.
An optical fiber cable (patch cord) is a very sensitive object. Please handle it with
care.
When routing the optical fiber cables, ensure that the bending radius is higher than the
minimum bending radius provided by the manufacturer. Generally the bending radius
of a optical cable is greater than 20D, where D is the diameter of cable.
Follow the manufacturer's recommendations.
Refer to “Site Specific Information” (p. 2-6) for the number of STM1 cables to install.
Scenario
O8: Install Optical Cables for STM1 in Release B11
How to Install Optical Cables for STM1 in Release B11
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-76 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
Install Optical Cables in Cable Way
Overview
Nr Materials Reference Kit
1 Basic installation
kit for Optical Fibre
cable
3BK27700ABAA Consumable supplies
Procedure
Install the optical cables in the cable way:
...................................................................................................................................................................................................
1 Install the optical cables in the STM1 compartment of the cable tray.
...................................................................................................................................................................................................
2 Attach the optical cables with plastic tie wraps.
Figure 3-28 Install Optical Cable in cable tray
Scenario
O8: Install Optical Cables for STM1 in Release B11
Install Optical Cables in Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-77
...................................................................................................................................................................................................
3 Mark the optical cables with a marker.
Scenario
O8: Install Optical Cables for STM1 in Release B11
Install Optical Cables in Cable Way
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-78 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Install SFP Modules
Procedure
Install an SFP Module:
...................................................................................................................................................................................................
1 Connect the anti-static wrist strap.
...................................................................................................................................................................................................
2 Replace the protective rubber from the SFP module and insert straight into the slot until
the module clicks firmly into place. When inserting the SFP, be sure that the hinged face
is closed.
Scenario
O8: Install Optical Cables for STM1 in Release B11
Install SFP Modules
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-79
...................................................................................................................................................................................................
3 Disconnect the anti-static wrist strap.
Scenario
O8: Install Optical Cables for STM1 in Release B11
Install SFP Modules
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-80 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Route Optical Cables
Overview
Note: The optical fiber cable cannot be cut to the correct length. You must therefore
adjust the cable length by making loops with the cable in the rack or cable tray.
C1: Route Optical Cables by Top Entry of Rack
Run the optical cables from the top of rack:
...................................................................................................................................................................................................
1 Run the optical cables at the top rack entry.
...................................................................................................................................................................................................
2 Run the optical cables at the back of the rack from top to bottom. Attach the optical cables
with plastic tie wraps.
Figure 3-29 Cables Rack Top Entry
Scenario
O8: Install Optical Cables for STM1 in Release B11
Route Optical Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-81
...................................................................................................................................................................................................
3 From the bottom of the rack pass optical cable in front of the rack, route them until you
reach front of the JBXTP3 boards. Attach the optical cables with plastic tie wraps from
this point. Refer to Figure 3-31, “Optical Cable Connection on JBXTP3 Board” (p. 3-84).
C2: Route Optical Cables by Bottom Entry of Rack
Note: The optical fibre cable cannot be cut to the correct length. You must therefore
adjust the cable length making loops with the optical cable in the rack or cable tray.
Perform the following steps:
...................................................................................................................................................................................................
1 Run the optical cables at the bottom rack entry.
...................................................................................................................................................................................................
2 Run the optical cables from the bottom of the rack to the front side of the JBXTP3.
Scenario
O8: Install Optical Cables for STM1 in Release B11
Route Optical Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-82 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Figure 3-30 Cables Routing Bottom Entry - Rear View
Scenario
O8: Install Optical Cables for STM1 in Release B11
Route Optical Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-83
The following figure shows the optical fibre cable connection positions on the front plate
of the JBXTP3 boards.
Figure 3-31 Optical Cable Connection on JBXTP3 Board
Scenario
O8: Install Optical Cables for STM1 in Release B11
Route Optical Cables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-84 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................
Finish Installation
How to Finish Installation
Procedure
Finish the installation:
...................................................................................................................................................................................................
1 Fit the plinth cover.
...................................................................................................................................................................................................
2 Fit the top cover and fix it with provided screws.
...................................................................................................................................................................................................
3 Fit the labels to the rack (for example: 9130 MFS/BSC Evolution n°12).
...................................................................................................................................................................................................
4 Close the front door and leave the rack key to the door with the customer.
Figure 3-32 Fit Rack Bottom Cover Plate
Scenario How to Finish Installation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
3-85
...................................................................................................................................................................................................
5 Clear away packaging.
...................................................................................................................................................................................................
6 Clean the site. Do not put packages into the customer bin.
Figure 3-33 Close Doors
Scenario
Finish Installation
How to Finish Installation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
3-86 Alcatel-Lucent 9130 BSC/MFS
3MN-00467-1011-RJZZA
Issue 1 March 2012
E N D O F S T E P S...................................................................................................................................................................................................