Page 1: 3G Drive Test Procedure_ By Md Joynal Abaden

3G Drive Test Procedure

Md. Joynal Abaden

RF EngineerAuspiciousbd

Page 2: 3G Drive Test Procedure_ By Md Joynal Abaden

Contents

1 Introduction

2 Drive test tools

3 Drive test type

4 Site Verification

5 Rigging Audit

6 Cluster Drive Test Optimization

Page 3: 3G Drive Test Procedure_ By Md Joynal Abaden

Introduction:

Objectives:

The purpose of the drive test to perform the RF design verification, identify any coverage and quality problems to optimise WCDMA network performance.

At this stage, the main focus is on fundamental end-to-end service accessibility target (e.g. Calls set up and drop rates) and on performance targets such as coverage related targets (such as CPICH RSCP and CPICH Ec/No), and HSDPA/HSUPA speed performance.

For this case it was needed each other from drive test data collection and also Physical site changes like tilting, antenna orientation and antenna height.

RF Solution Department

Page 4: 3G Drive Test Procedure_ By Md Joynal Abaden

Drive Test Tools:

Hardware:• 1x Laptop• 2x/3x/4x Smart Phones (2G/3G/LTE)• 1x FDD Data Dongle (should be supporting 3G 42M)• 1x GPS (G-Star IV)• 1x Car DC/AC Inverter• 1x Car.• 3x SIM Cards (Data & Normal) & 4x SIM Cards (Data & Normal) 5x SIM Cards (Data & Normal)Software:• TEMS Investigation 16.1• Map Tools (Map Info & Google Earth)• Cell File

RF Solution Department

Page 5: 3G Drive Test Procedure_ By Md Joynal Abaden

Drive Test Type

Site Verification Individual cell verification test : To investigate detail of site performance by checking all single sectors with AMR call and Throughput test. In addition also required to perform small area dedicated test for Intra/Intercell HO.

Cluster Optimization Normal Drive To frame the potential area of the new site planned. Also to improve the important neighboring sites for which the handover to be defined. Cluster Optimization Dedicated Drive

Performed call to the test number and drive to the potential area given to determine

i) call set up time ii) call set up success iii) drop call iv) SHO

v) HSDPA ( Average & Maximum) Speedvi) Coverage Status ( Technology)vii) Pilot polution

RF Solution Department

Page 6: 3G Drive Test Procedure_ By Md Joynal Abaden

When the site is completely integrated, Drive tester team will start to perform site

investigation. The detail sub-activities are outlined below:

1. Rigging Audit2. Site Verification3. Site corrective action (cross feeder, inconsistent data, functionality

problem, etc.)4. Acceptance Test

The site has been built and integrated as planned and that the planned coverage has been achieved

Site Verification:

RF Solution Department

Page 7: 3G Drive Test Procedure_ By Md Joynal Abaden

All Tests Clear?

Corrective Actions

NoYes

New On Air Site Flow

New Site Integration

1. Consistency Check2. Rigging Audit3. Site Verification

Site Acceptance

Site Verification:

RF Solution Department

Page 8: 3G Drive Test Procedure_ By Md Joynal Abaden

• Voice / Video calls

• Verify on per cell basis for all carriers:• RSCP• EC/No• Scrambling Code• LAC / RAC• Cell ID• Etc.

• Data / Throughput test• HSDPA and HSUPA /

Internet Browsing• Verify on per cell basis for all

carriers:• RSCP• EC/No• Scrambling Code• LAC / RAC• Cell ID• Max/Ave Speed• Etc.

Site Verification:

RF Solution Department

Page 9: 3G Drive Test Procedure_ By Md Joynal Abaden

Static test At the best radio location required to perform for all carriers 1. Voice call to determine if any call failure or block calls 2. Video call succesful 3. IRAT test for network reselection 4. Throughput R99/ HSDPA/HSUPA/Latency test using http / fttp and speedtest. 5. Internet browsing succesful

Mobility Test 1. Check intra cell HO in dedicated mode clockwise and anti clockwise 2 rounds for each direction 2. Check inter cell HO in dedicated mode for the 1st layer per cell both ways.

Site Verification:

RF Solution Department

Page 10: 3G Drive Test Procedure_ By Md Joynal Abaden

Rigging Audit

Test Items in Rigging Audit:Antenna Installation Verification

- Azimuth- Height- Location- Cross-feeder/s

Rigging Tools :- Safety Belt- Compass- GPS

- Measurement tape- Digital Inclinometer

Site Audit required from the Rigger

1. Panoramic photos surrounding sites including antenna sectors/objective area

2. Ensure no blocking sectors from the main beam antenna3. Antenna mechanical/electrical tilt was in correct value4. Antenna was in correct orientation for the objective/target area5. Site Height6. Site Coordinates

RF Solution Department

Page 11: 3G Drive Test Procedure_ By Md Joynal Abaden

• Cluster Definition, Site Information Data and Site Location Map• With Site/Cell ID, Site name, Primary SC, Neighbour list, RNC ID

and Cluster border highlighted• Prepare Route Map for Drive Testing• Perform drive test either Idle mode or Dedicated mode• Identify Problematic Areas• The result from the data will showing of Network performance such

as 1. Drop call rate 2. Accessibility – mobile originated/terminated call set up success rate 3. Coverage – RSCP and Ec/No

Cluster Drive test Optimization:

RF Solution Department

Page 12: 3G Drive Test Procedure_ By Md Joynal Abaden

Cluster Drive test Optimization:

RF Solution Department

Page 13: 3G Drive Test Procedure_ By Md Joynal Abaden

• The area which doesn't meet the criteria below is defined as "Problematic Area“

• Coverage Problem Area

• Dominance Problem Area

• Pilot Pollution

Best Server’s CPICH RSCP < - 99 dBm

Best Server’s CPICH Ec/No < -14 dB

4th Best Server’s CPICH RSCP > - 99 dBm

Cluster Drive test Optimisation:

RF Solution Department

Page 14: 3G Drive Test Procedure_ By Md Joynal Abaden

Thank You