  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    1/27

    1

    Application of

    Synchrophasor Technology ToCREZ System

    CREZ Technical Conference

    January 26, 2010

    Navin Bhatt

    American Electric Power

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    2/27

    2

    Outline

    1.Synchrophasor Technology

    2.Potential Applications

    3.Applications to Consider for

    CREZ System

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    3/27

    3

    1. Synchrophasor Technology

    Phasor: An electrical quantity with magnitude

    and phase (angle) Synchrophasors: Time-synchronized phasors

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    4/27

    4

    Phasor Representation

    Courtesy: CERTS/EPG

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    5/27

    5Courtesy: Eastern Interconnection Phasor Project (EIPP)

    Synchrophasor Infrastructure

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    6/27

    6

    SCADA Data Vs. Synchrophasors

    SCADA Conventional Situational AwarenessTechnology

    Advantages of Synchrophasor Technology Direct measurement (as opposed to calculated values using

    model-based SE solutions from SCADA data)

    8/14/03 Blackout: AEP SE could not converge; PMU

    data kept coming Time-stamped data, accurate within tens of micro-seconds

    of UTC

    High resolution (10-60 samples per second)

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    7/27

    7

    Technology Promise

    Synchrophasor Technology Can provide situational awareness on a

    sub-second basis over wide area

    Instantaneous measure of power systemstress between wide area locations Instantaneous measure of power system

    dynamics at given location

    MRI of power system vs. X-Ray by SCADAtechnology

    PMU data well suited to activate automatedcontrols

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    8/27

    8

    AEP Synchrophasor Project

    AEP/Texas

    AEP is taking a leading role in DOE/ERCOT efforts to installsynchrophasors in ERCOT

    AEP was the first utility in ERCOT

    to install PMUs

    Provide real-time data feed to ERCOT

    Work in progress to display modal analysis results in

    AEP Transmission Operations

    AEP/East

    Synchrophasor infrastructure includes 25 PMUs

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    9/27

    9

    2. Potential Applications

    Industry Challenge: Research, Develop andDeploy Applications

    Develop Practical Data Tools for Operators

    Do NOT need more PMU data

    Need Actionable Information

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    10/27

    10

    2. Potential Applications

    Industry Resources

    Opportunities to Learn & Get Involved

    North American Synchrophasor Initiative (NASPI)

    (www.naspi.org)

    NERC Real-Time Application of PMUs to ImproveReliability (RAPIR) Task Force

    IEEE

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    11/27

    11

    NASPI

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    12/27

    12

    NASPI

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    13/27

    13

    IEEE

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    14/27

    14

    3. Applications for CREZ System

    Large Penetration of Wind Generation

    Opportunity

    To provide leadership in the DOE 20% by 2030 vision

    To show it can be done!

    Challenges

    Lower overall system inertia

    Altered frequency response

    Altered small signal stability performance

    Energy balance requirements due to generation variability.

    Can we take advantage of synchrophasortechnology?

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    15/27

    15

    Using PMUs for Renewable

    Resource Integration

    Wind Farm connected to AEPs Ajo Station

    PMU data from AEP stations (including Ajo)in ERCOT Control Center

    The Last Mile is bringing the PMU data into the Control Center

    for Wide Area Monitoring and Control

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    16/27

    16

    3. Applications for CREZ System

    Potential Applications to Consider

    Visualization

    Small Signal Stability Performance

    Model Validation

    Voltage Stability Performance Advanced Automated Controls

    ..

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    17/27

    17

    3. Applications for CREZ System

    Visualization

    RTDMS already deployed at ERCOT

    PMU Data Display: Added Value?

    Information (Requires R&D)

    Acceptable ranges of quantities displayed

    Alarms

    Corrective actions to take

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    18/27

    18

    3. Applications for CREZ System

    Small Signal Stability Performance

    Modal Analysis (Dominant Frequencies & AssociatedDamping)

    Off-Line Analysis

    Listen to what the system is telling you

    Detect Trends: Daily, Seasonal, Long Term

    Correlate with Levels of Wind Generation

    Real Time Analysis

    Detect damping problems

    Tools already available

    Take corrective actions

    Will require R&D

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    19/27

    19

    3. Applications for CREZ System

    Validation of Dynamic Models

    Need high resolution data (e.g. PMU data)

    Calibrate & fine-tune simulation models bycomparing simulation results with synchrophasordata

    WECC Model Validation WG efforts

    Opportunity to use data from PMUs at windgeneration collection point (transmission buses) tovalidate wind generation and other dynamicmodels

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    20/27

    20

    3. Applications for CREZ System

    Voltage Stability Performance

    Especially of benefit for a scenario involving fastvoltage collapse

    PMU data can be used to monitor performance inreal time through a nomogram developed from off-line simulation studies

    Tools being developed to calculate margin in realtime (e.g. EPRI Measurement-Based Real TimeVoltage Stability Monitoring)

    An extension of the classic power transfer equation:P12 =V1*V2*Sin 12/X12

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    21/27

    21

    3. Applications for CREZ System

    Advanced Automated Controls

    Grid operated with margin for anticipated contingencies

    Bodes well to maintain reliable bulk power system

    Introduces inefficiencies

    Can we rely on real time corrective controls under selectedoperating scenarios, instead?

    Todays controls too myopic

    Designed to address local abnormalities

    Centralized coordinated controls are rare

    PMU Data

    High resolution & instantaneous

    Could be used to develop coordinated, centralized wide areacontrols

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    22/27

    22

    Summary

    Synchrophasor technology is promising.

    Killer apps are still in works.

    R&D is needed

    Demonstration to adopt / adapt an application isnecessary (e.g. visualization with meaningful alarms)

    We must work together to apply the technology to CREZsystem

    Will require R&D + Cooperation with NASPI, NERC, et al

    Our efforts will pay off.

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    23/27

    23

    Questions

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    24/27

    24

    Extra Slides

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    25/27

    25

    Synchrophasor Infrastructure

    1.Measurement Layer Phasor Measurement Unit (PMU)

    Measures voltage & current waveformsat high sampling rates

    Calculates voltage & current phasors,

    frequency and line flows

    Installed at substations

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    26/27

    26

    Synchrophasor Infrastructure

    2. Data Collection Layer Phasor Data Concentrator (PDC)

    A hardware/software devicePerforms precise time alignment ofdata from multiple PMUs

    Usually centrally locatedArchives PMU data (optional)

    Processes and displays PMU data

    (optional)

  • 7/31/2019 3Bhatt Synchrophasor Presentation to ERCOT 012610

    27/27

    27

    Synchrophasor Infrastructure

    3. Application Layer

    Local (Substation) Applications

    Centralized (EMS) Applications

    Off-Line (Planning) Applications