3420

Upload: mayank-agrawal

Post on 06-Apr-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 3420

    1/3

    Mobile Cranes: The

    Importance Of Lift

    Assessments

    Mobile crane work involves lifting and placing

    many types of materials in both safe and haz-ardous locations. Although large or complicated

    lifts are easily recognized as being of a critical

    nature requiring additional

    planning, the hazards associ-

    ated with smaller lifts may be

    less obvious. Therefore, it is

    important to conduct a lift

    assessment regardless of the

    specifics of the lift. Equally as

    important is a firm under-

    standing of the operatorsand supervisors responsibili-

    ties during any type of lift.

    LIFT ASSESSMENT PROCESS

    Currently, there is no consensus standard

    regarding when formal lift plans are required. One

    widely recognized standard, from the

    Construction Safety Association of Ontario,

    defines a critical lift as those where the gross

    load is within 75 percent of the rated capacity of

    the crane. Another standard is the Exxon Crane

    guide, which defines a critical lift as greater than

    90 percent of the rated capacity. The bottom line

    is that each company should establish its own

    critical lift guidelines. The degree to which the

    guidelines are applied depends on the results of

    the Lift Assessment Process. Lifts can be classi-

    fied by the degree of difficulty. An example of a

    Lift Assessment Process, as developed and rec-

    ommended by Exxon, is discussed below. A Lift

    Classification Flow Chart describes the process.

    - A lift planner should use the Lift Classification

    Flow Chart in determining the classification of

    the lift and the planning required.

    - All critical lifts should have a formal Critical Lift

    Plan. Outside engineering help may be required

    to fully assess and resolve all important load

    and site factors.

    - More routine lifts are classified as Non-

    Standard. The Lift Planning Process is less

    involved than for a Critical Lift and is

    documented on a Lift Evaluation Form.

    DAILY CRANE OPERATION LOG

    Most lifts will be classified as Standard and

    require less planning and documentation. This

    type of planning can be documented in a Daily

    Crane Operation Log. A Daily Crane Operation

    Log is designed to record basic lift information

    and confirms the load is within the rated capac-

    ity of the crane. One of the main reasons for

    completing a log is that it requires the crane

    operator to document even the most fundamen-

    tal aspects of a lift, thereby decreasing the

    chances of lifts being made in an unsafe manner.

    RISK BULLETIN

  • 8/3/2019 3420

    2/3

    2 MOBILE CRANES: THE IMPORTANCE OF LIFT ASSESSMENTS

    LIFT EVALUATION FORM

    A Lift Evaluation Form (LEF) should be used

    when a lift is determined to be Non-Standard.

    The LEF is a one-page document. To completethe LEF, the supervisor must evaluate the basic

    questions noted in the flow chart on page 2, and

    with the aid of the operator, determine if the

    gross load is (1) less than 20 tons, and (2)

    between 80 percent and 90 percent of the man-

    ufacturers load chart during all parts of the lift.

    This information, in addition to some basic site

    evaluation remarks, is recorded on the LEF.

    Sign-offs should include the operator, lift super-

    visor, area supervisor and engineer.

    CRITICAL LIFT PLAN A Critical Lift Plan (CLP) consists of drawings,

    specifications and procedures necessary to

    accurately assess all important load and site fac-

    tors relating to a critical lift. However, most lifts

    do not involve all of the factors listed in the flow

    chart above, in which case a minimum level of

    information is required to comprise an adequate

    lift plan. Main components of the CLP include:

    - Elevation View Drawing

    - Plan View Drawing

    - Lift Analysis

    All potential complicating issues for any lift

    should be addressed in the lift plan. Some of the

    precautions that should be addressed by the

    CLP are:

    - Supporting Surface Ground compact and

    stable?

    - Blocking Outrigger blocking used and

    crawlers on pads or cribbing (unless the crane

    sits on a concrete pad)?

    - Level Machinery deck or boom foot pins

    absolutely level?

    - Load Load weight determined exactly?

    - Center of Gravity Location of the loads

    center of gravity determined and the crane

    hook positioned above it?

    - Load Radius Measured exactly?

    - Boom Length Determined exactly?

    - Boom Angle Boom angle, if necessary for

    determining the cranes capacity, determined

    exactly? (Do not rely on the cranes boom

    angle indicator.)

    - Wind Wind effects considered? (If wind

    speeds are greater 30 mph, do not make the

    lift. If greater than 20 mph, consider

    postponing.)

    - Overhead Exposures measure clearence

    exactly

    - Reeving Balanced?

    - Load Rigging Checked for adequacy and

    security? Exact weight of rigging known?

    - Operation Reinforced the need to make all

    controls, machine and load movements as

    slowly and smoothly as possible?

    - Unstable Load Large, thin or potentially

    - Load to be lifted overequipment?or

    - are 2 cranes to beused?or

    - Special l iftingequipment required?or

    - Is load >90% of ratedcapacity?or

    - Is load >20 tons andalso >80% of ratedcapacity?

    - Is load

  • 8/3/2019 3420

    3/3

    unstable pieces to be lifted?

    - Multi-crane Lifts Will the load require more

    than one crane to perform the lift?

    - Congested Areas Will the lift be performedin areas where structures, pipe racks, power

    lines or other obstacles are present?

    - Turning Will the lift involve turning or flipping

    a piece from one side to the other?

    - Power Line Exposure Lines de-energized -

    mandatory distance from arching?

    The site supervisor is responsible for ensuring

    the CLP is developed and reviewed before the lift

    is made. The Plan should be presented to the

    facility owner as appropriate. Responsibilities for

    the lift are divided among several individuals

    including the operator and the site supervisor.

    Note: In the event that it becomes necessary todeviate from the CLP, the lift should be re-evalu-ated and the CLP should be revised.

    CONCLUSION

    The lift plan process should be followed regard-

    less of the specifics of the lift. The general guide-

    lines outlined above are important factors for any

    company to consider when developing and

    implementing a Lift Assessment Process.

    The information contained herein is intended for informational

    purposes only and does not constitute legal advice. For legal

    advice, seek the services of a competent attorney. Any descrip-

    tions of insurance provisions are general overviews only.

    "XL Insurance" is the global brand used by XL Group plcs

    (NYSE: XL) insurance companies. Coverages underwritten by

    Greenwich Insurance Company, Indian Harbor Insurance

    Company, XL Insurance America, Inc., XL Specialty Insurance

    Company and XL Insurance Company LimitedCanadian

    Branch. Coverages not available in all jurisdictions.

    3420-104

    XL Environmental

    Risk Control Division

    505 Eagleview Boulevard

    Suite 100

    PO Box 636

    Exton, PA 19341-0636

    Phone: 800-327-1414

    Fax: 610-458-7285

    www.xlenvironmental.com

    XL Environmental is a Division of XL Specialty Insurance Company.

    3 MOBILE CRANES: THE IMPORTANCE OF LIFT ASSESSMENTS