3420
TRANSCRIPT
-
8/3/2019 3420
1/3
Mobile Cranes: The
Importance Of Lift
Assessments
Mobile crane work involves lifting and placing
many types of materials in both safe and haz-ardous locations. Although large or complicated
lifts are easily recognized as being of a critical
nature requiring additional
planning, the hazards associ-
ated with smaller lifts may be
less obvious. Therefore, it is
important to conduct a lift
assessment regardless of the
specifics of the lift. Equally as
important is a firm under-
standing of the operatorsand supervisors responsibili-
ties during any type of lift.
LIFT ASSESSMENT PROCESS
Currently, there is no consensus standard
regarding when formal lift plans are required. One
widely recognized standard, from the
Construction Safety Association of Ontario,
defines a critical lift as those where the gross
load is within 75 percent of the rated capacity of
the crane. Another standard is the Exxon Crane
guide, which defines a critical lift as greater than
90 percent of the rated capacity. The bottom line
is that each company should establish its own
critical lift guidelines. The degree to which the
guidelines are applied depends on the results of
the Lift Assessment Process. Lifts can be classi-
fied by the degree of difficulty. An example of a
Lift Assessment Process, as developed and rec-
ommended by Exxon, is discussed below. A Lift
Classification Flow Chart describes the process.
- A lift planner should use the Lift Classification
Flow Chart in determining the classification of
the lift and the planning required.
- All critical lifts should have a formal Critical Lift
Plan. Outside engineering help may be required
to fully assess and resolve all important load
and site factors.
- More routine lifts are classified as Non-
Standard. The Lift Planning Process is less
involved than for a Critical Lift and is
documented on a Lift Evaluation Form.
DAILY CRANE OPERATION LOG
Most lifts will be classified as Standard and
require less planning and documentation. This
type of planning can be documented in a Daily
Crane Operation Log. A Daily Crane Operation
Log is designed to record basic lift information
and confirms the load is within the rated capac-
ity of the crane. One of the main reasons for
completing a log is that it requires the crane
operator to document even the most fundamen-
tal aspects of a lift, thereby decreasing the
chances of lifts being made in an unsafe manner.
RISK BULLETIN
-
8/3/2019 3420
2/3
2 MOBILE CRANES: THE IMPORTANCE OF LIFT ASSESSMENTS
LIFT EVALUATION FORM
A Lift Evaluation Form (LEF) should be used
when a lift is determined to be Non-Standard.
The LEF is a one-page document. To completethe LEF, the supervisor must evaluate the basic
questions noted in the flow chart on page 2, and
with the aid of the operator, determine if the
gross load is (1) less than 20 tons, and (2)
between 80 percent and 90 percent of the man-
ufacturers load chart during all parts of the lift.
This information, in addition to some basic site
evaluation remarks, is recorded on the LEF.
Sign-offs should include the operator, lift super-
visor, area supervisor and engineer.
CRITICAL LIFT PLAN A Critical Lift Plan (CLP) consists of drawings,
specifications and procedures necessary to
accurately assess all important load and site fac-
tors relating to a critical lift. However, most lifts
do not involve all of the factors listed in the flow
chart above, in which case a minimum level of
information is required to comprise an adequate
lift plan. Main components of the CLP include:
- Elevation View Drawing
- Plan View Drawing
- Lift Analysis
All potential complicating issues for any lift
should be addressed in the lift plan. Some of the
precautions that should be addressed by the
CLP are:
- Supporting Surface Ground compact and
stable?
- Blocking Outrigger blocking used and
crawlers on pads or cribbing (unless the crane
sits on a concrete pad)?
- Level Machinery deck or boom foot pins
absolutely level?
- Load Load weight determined exactly?
- Center of Gravity Location of the loads
center of gravity determined and the crane
hook positioned above it?
- Load Radius Measured exactly?
- Boom Length Determined exactly?
- Boom Angle Boom angle, if necessary for
determining the cranes capacity, determined
exactly? (Do not rely on the cranes boom
angle indicator.)
- Wind Wind effects considered? (If wind
speeds are greater 30 mph, do not make the
lift. If greater than 20 mph, consider
postponing.)
- Overhead Exposures measure clearence
exactly
- Reeving Balanced?
- Load Rigging Checked for adequacy and
security? Exact weight of rigging known?
- Operation Reinforced the need to make all
controls, machine and load movements as
slowly and smoothly as possible?
- Unstable Load Large, thin or potentially
- Load to be lifted overequipment?or
- are 2 cranes to beused?or
- Special l iftingequipment required?or
- Is load >90% of ratedcapacity?or
- Is load >20 tons andalso >80% of ratedcapacity?
- Is load
-
8/3/2019 3420
3/3
unstable pieces to be lifted?
- Multi-crane Lifts Will the load require more
than one crane to perform the lift?
- Congested Areas Will the lift be performedin areas where structures, pipe racks, power
lines or other obstacles are present?
- Turning Will the lift involve turning or flipping
a piece from one side to the other?
- Power Line Exposure Lines de-energized -
mandatory distance from arching?
The site supervisor is responsible for ensuring
the CLP is developed and reviewed before the lift
is made. The Plan should be presented to the
facility owner as appropriate. Responsibilities for
the lift are divided among several individuals
including the operator and the site supervisor.
Note: In the event that it becomes necessary todeviate from the CLP, the lift should be re-evalu-ated and the CLP should be revised.
CONCLUSION
The lift plan process should be followed regard-
less of the specifics of the lift. The general guide-
lines outlined above are important factors for any
company to consider when developing and
implementing a Lift Assessment Process.
The information contained herein is intended for informational
purposes only and does not constitute legal advice. For legal
advice, seek the services of a competent attorney. Any descrip-
tions of insurance provisions are general overviews only.
"XL Insurance" is the global brand used by XL Group plcs
(NYSE: XL) insurance companies. Coverages underwritten by
Greenwich Insurance Company, Indian Harbor Insurance
Company, XL Insurance America, Inc., XL Specialty Insurance
Company and XL Insurance Company LimitedCanadian
Branch. Coverages not available in all jurisdictions.
3420-104
XL Environmental
Risk Control Division
505 Eagleview Boulevard
Suite 100
PO Box 636
Exton, PA 19341-0636
Phone: 800-327-1414
Fax: 610-458-7285
www.xlenvironmental.com
XL Environmental is a Division of XL Specialty Insurance Company.
3 MOBILE CRANES: THE IMPORTANCE OF LIFT ASSESSMENTS