CGS WORLDWIDE SOLUTIONS CGS: 3.05 QUALITY AUDIT Project Title: Date Prepared: Project Auditor: Audit Date: Area Audited: (Indicate what was audited) Project Project processes Project documents Product Product requirements Product documents Approved change implementation Corrective or preventive action implementation Defect/deficiency repair Quality Management Plan Organizational policies Organizational procedures Description of Good Practices to Share: Describe any good or best practices that can be shared with other projects. Description of Areas for Improvement: Describe any areas that need improvement and the specific improvements or measurements that need to be achieved. Description of Deficiencies or Defects: ID Defect Action Responsibl e Party Due Date Describe deficiencies or defects. Describe the action needed to be taken to correct defects. Assigned Person Due date

Upload: projectrunx-nig-ltd

Post on 26-Sep-2015

213 views

Category:

Documents


0 download

DESCRIPTION

AUDIT

TRANSCRIPT

Project Title:

PAGE

CGS WORLDWIDE SOLUTIONS CGS: 3.05 QUALITY AUDIT

Project Title:

Date Prepared:

Project Auditor:

Audit Date:

Area Audited: (Indicate what was audited)

Project

Project processes

Project documents

Product

Product requirements

Product documents

Approved change implementation

Corrective or preventive action implementation

Defect/deficiency repair

Quality Management Plan

Organizational policies

Organizational procedures

Description of Good Practices to Share:

Describe any good or best practices that can be shared with other projects.

Description of Areas for Improvement:

Describe any areas that need improvement and the specific improvements or measurements that need to be achieved.

Description of Deficiencies or Defects:

ID

Defect

Action

Responsible Party

Due Date

Describe deficiencies or defects.

Describe the action needed to be taken to correct defects.

Assigned Person

Due date

Comments: