30487030_glass-lined steel process equipment

Upload: vasilica-barbarasa

Post on 02-Mar-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    1/21

    GLASS-LINED STEEL PROCESS EQUIPMENT

    DEP 30.48.70.30-Gen.

    August 2005

    DESIGN AND ENGINEERING PRACTICE

    This document is restricted. Neither the whole nor any part of this document may be disclosed to any third party without the prior written consent of Shell GlobalSolutions International B.V. and Shell International Exploration and Production B.V., The Netherlands. The copyright of this document is vested in these companies. All

    rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval system or transmitted in any form or by any means(electronic, mechanical, reprographic, recording or otherwise) without the prior written consent of the copyright owners.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    2/21

    DEP 30.48.70.30-Gen. August 2005

    Page 2

    PREFACE

    DEPs (Design and Engineering Practice) publications reflect the views, at the time of publication, of:

    Shell Global Solutions International B.V. (Shell GSI)

    and

    Shell International Exploration and Production B.V. (SIEP)

    and

    Shell International Chemicals B.V. (SIC)

    and

    other Service Companies.

    They are based on the experience acquired during their involvement with the design, construction, operation andmaintenance of processing units and facilities, and they are supplemented with the experience of Group Operatingcompanies. Where appropriate they are based on, or reference is made to, international, regional, national and industrystandards.

    The objective is to set the recommended standard for good design and engineering practice applied by Groupcompanies operating an oil refinery, gas handling installation, chemical plant, oil and gas production facility, or any other

    such facility, and thereby to achieve maximum technical and economic benefit from standardization.The information set forth in these publications is provided to users for their consideration and decision to implement.This is of particular importance where DEPs may not cover every requirement or diversity of condition at each locality.The system of DEPs is expected to be sufficiently flexible to allow individual operating companies to adapt theinformation set forth in DEPs to their own environment and requirements.

    When Contractors or Manufacturers/Suppliers use DEPs they shall be solely responsible for the quality of work and theattainment of the required design and engineering standards. In particular, for those requirements not specificallycovered, the Principal will expect them to follow those design and engineering practices which will achieve the samelevel of integrity as reflected in the DEPs. If in doubt, the Contractor or Manufacturer/Supplier shall, without detractingfrom his own responsibility, consult the Principal or its technical advisor.

    The right to use DEPs is granted by Shell GSI, SIEP or SIC, in most cases under Service Agreements primarily withcompanies of the Royal Dutch/Shell Group and other companies receiving technical advice and services from Shell GSI,SIEP, SIC or another Group Service Company. Consequently, three categories of users of DEPs can be distinguished:

    1) Operating companies having a Service Agreement with Shell GSI, SIEP, SIC or other Service Company. Theuse of DEPs by these operating companies is subject in all respects to the terms and conditions of the relevantService Agreement.

    2) Other parties who are authorized to use DEPs subject to appropriate contractual arrangements (whether as partof a Service Agreement or otherwise).

    3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the saidusers comply with the relevant standards.

    Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI, SIEPand SIC disclaim any liability of whatsoever nature for any damage (including injury or death) suffered by any companyor person whomsoever as a result of or in connection with the use, application or implementation of any DEP,combination of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI,SIEP or other Service Company. The benefit of this disclaimer shall inure in all respects to Shell GSI, SIEP, SIC and/orany company affiliated to these companies that may issue DEPs or require the use of DEPs.

    Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shallnot, without the prior written consent of Shell GSI and SIEP, be disclosed by users to any company or personwhomsoever and the DEPs shall be used exclusively for the purpose for which they have been provided to the user.They shall be returned after use, including any copies which shall only be made by users with the express prior writtenconsent of Shell GSI, SIEP or SIC. The copyright of DEPs vests in Shell GSI and SIEP. Users shall arrange for DEPs tobe held in safe custody and Shell GSI, SIEP or SIC may at any time require information satisfactory to them in order toascertain how users implement this requirement.

    All administrative queries should be directed to the DEP Administrator in Shell GSI.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    3/21

    DEP 30.48.70.30-Gen. August 2005

    Page 3

    TABLE OF CONTENTS

    1. INTRODUCTION ........................................................................................................4 1.1 SCOPE........................................................................................................................4 1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS .........4 1.3 DEFINITIONS .............................................................................................................4 1.4 CROSS-REFERENCES .............................................................................................5 1.5 SUMMARY OF CHANGES SINCE PREVIOUS EDITION .........................................5 1.6 COMMENTS ON THIS DEP .......................................................................................5

    2. MATERIALS ...............................................................................................................6 2.1 GENERAL...................................................................................................................6 2.2 CARBON STEEL ........................................................................................................6 2.3 LINING MATERIAL .....................................................................................................6 2.4 GASKETS ...................................................................................................................7

    3. DESIGN AND MANUFACTURE ................................................................................8 3.1 DESIGN ......................................................................................................................8 3.2 MANUFACTURE ........................................................................................................8

    3.3 CONNECTIONS .........................................................................................................8

    3.4 TOLERANCES............................................................................................................9 3.5 DEFECTS ...................................................................................................................9

    4. TESTING, INSPECTION AND DOCUMENTATION ................................................11 4.1 TESTING...................................................................................................................11 4.2 INSPECTION ............................................................................................................11 4.3 DOCUMENTATION ..................................................................................................12

    5. REPAIR PROCEDURE ............................................................................................14 5.1 REPAIR PLUGS .......................................................................................................14 5.2 IMPURITIES..............................................................................................................15

    6. PACKAGING, TRANSPORTATION AND INSPECTION ........................................16 6.1 GENERAL.................................................................................................................16 6.2 PACKAGING AND TRANSPORTATION..................................................................16 6.3 ARRIVAL INSPECTION............................................................................................16

    7. INSTALLATION ........................................................................................................17 7.1 GENERAL.................................................................................................................17 7.2 CONNECTIONS .......................................................................................................17 7.3 BOLTING ..................................................................................................................17 7.4 WELDING .................................................................................................................17 7.5 MARKING .................................................................................................................17

    8. OPERATION .............................................................................................................18 8.1 THERMAL SHOCK ...................................................................................................18 8.2 ACID SPILLS ............................................................................................................18 8.3 STEAM HAMMER.....................................................................................................18

    9. MAINTENANCE, INSPECTION AND REPAIR ........................................................19 9.1 MAINTENANCE........................................................................................................19 9.2 INSPECTION ............................................................................................................19 9.3 REPAIRS ..................................................................................................................19 9.4 CLEANING OF THE JACKET SPACE .....................................................................19

    10. REFERENCES .........................................................................................................20

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    4/21

    DEP 30.48.70.30-Gen. August 2005

    Page 4

    1. INTRODUCTION

    1.1 SCOPE

    This DEP specifies requirements and gives recommendations for the manufacture,

    inspection and supply of process equipment, and components made of glass-lined carbonsteel. Typical operating temperature for glass-lined steel process equipment is from -25 Cto +230 C.

    This DEP specifies the quality requirements and the tests to be carried out by theManufacturer as well as the necessary actions for repairing defects. Installation, operationand maintenance aspects are also included in the scope of this DEP.

    This DEP is a revision of the DEP of the same number dated July 1998; a summary of themain changes is given in (1.5).

    1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS

    Unless otherwise authorized by Shell GSI and SIEP, the distribution of this DEP is confined

    to companies forming part of the Royal Dutch/Shell Group or managed by a Groupcompany and, where necessary, to Contractors and Manufacturers nominated by them.

    This DEP is intended for use in oil refineries, chemical plants, gas plants, exploration andproduction facilities and, where applicable supply/marketing installations.

    When DEPs are applied, a Management of Change (MOC) process should beimplemented; this is of particular importance when existing facilities are to be modified.

    If national and/or local regulations exist in which some of the requirements may be morestringent than in this DEP, the Contractor shall determine by careful scrutiny which of therequirements are the more stringent and which combination of requirements will beacceptable as regards safety, economic and legal aspects. In all cases the Contractor shallinform the Principal of any deviation from the requirements of this document which isconsidered to be necessary in order to comply with national and/or local regulations. ThePrincipal may then negotiate with the Authorities concerned with the object of obtainingagreement to follow this document as closely as possible.

    1.3 DEFINITIONS

    1.3.1 General definitions

    The Contractor is the party which carries out all or part of the design, engineering,procurement, construction and commissioning or management of the project or operation ofa facility. The Principal may sometimes undertake all or part of the duties of the Contractor.

    The Manufacturer/Supplier is the party which manufactures or supplies equipment andservices to perform the duties specified by the Contractor.

    The Principal is the party which initiates the project and ultimately pays for its design andconstruction. The Principal will generally specify the technical requirements. The Principalmay also include an agent or consultant, authorised to act for, and on behalf of thePrincipal.

    The word shall indicates a requirement.

    The word should indicates a recommendation.

    1.3.2 Specific definitions

    Glass-lined steel Composite material produced by smelting a vitreous and enamelcoat onto a steel substrate.

    Thermal shock Sudden change of temperature resulting from contact with ashock medium (heating or cooling).

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    5/21

    DEP 30.48.70.30-Gen. August 2005

    Page 5

    1.4 CROSS-REFERENCES

    Where cross-references to other parts of this DEP are made, the referenced sectionnumber is shown in brackets. Other documents referenced by this DEP are listed in (10).

    1.5 SUMMARY OF CHANGES SINCE PREVIOUS EDITIONThe previous edition of this DEP was dated July 1998; a summary of the main changessince the last edition is given below.

    Section Change

    General - Increased alignment with ISO Standards, EN Standards and DEPs- Rearranged Chapters and Sections

    Appendices1, 2 and 3

    Have been removed, and partly integrated in the updated Chapters

    1.6 COMMENTS ON THIS DEP

    Comments on this DEP may be sent to the DEP Administrator at [email protected] . Shell staff may also post comments on this DEP on the Surface Global Network (SGN)under the Standards/DEP 30.48.70.30-Gen. folder. The DEP Administrator and DEP Authormonitor these folders on a regular basis.

    mailto:[email protected]:[email protected]:[email protected]
  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    6/21

    DEP 30.48.70.30-Gen. August 2005

    Page 6

    2. MATERIALS

    2.1 GENERAL

    As glass lining for process equipment and components, a vitreous and porcelain enamel,

    normally with a thickness in the range from 1 mm to 2 mm, is applied by smelting onto asteel substrate.

    2.2 CARBON STEEL

    Unalloyed and low-allow carbon steels, suitable for glass lining, with a minimum yieldstrength of 210 N/mm 2, shall be used as base material in accordance withDEP 30.10.02.11-Gen.

    The carbon steel equipment shall be in accordance with the design codes specified by thePrincipal.

    2.3 LINING MATERIAL

    2.3.1 General

    Glass-lining enamels include all-vitreous enamel, all-semi crystalline enamal, vitreousenamel on a semi-crystalline intermediate layer, and semi-crystalline enamel on a vitreousintermediate layer.

    The Manufacturer shall specify the composition of the enamel lining and the colour.

    The main criteria for assessing enamel quality are resistance to chemical attack andthermal shock, and the structure of the enamel lining.

    2.3.2 Chemical resistance

    The glass lining material shall meet the following corrosion resistance requirements:

    1. Corrosion rate in hydrochloric acid, tested in accordance with ISO 2743 orEN 14483-2, shall be not greater than 0.08 mm per year;

    2. Corrosion rate in sodium hydroxide solutions, tested in accordance with ISO 2745or EN 14483-4, shall be not greater than 0.40 mm per year. The ratio of the volumeof attacking sodium hydroxide solution in cubic centimetres to the exposed enamelsurface in square centimetres shall be 3.5.

    2.3.3 Thermal shock resistance

    The thermal shock resistance depends on several factors, including the physical propertiesof the enamel, material characteristics of the steel, design of the apparatus, enamellingprocess, and the service conditions.

    For glass-lined steel, a distinction is drawn between a thermal shock on the glass-lined side(e.g. filling of a process vessel) and a thermal shock on the steel side (e.g. heating andcooling of a process vessel). This DEP applies to operating temperatures from -25 C to+ 230 C. Exceeding this temperature range shall be subject to the approval of thePrincipal. The Manufacturer shall define the thermal shock limits (heating and cooling), andprovide thermal shock diagrams for the glass-lined system in accordance withprEN 15159-3.

    The measure for thermal shock resistance is the crack formation temperature, testedaccording to ISO 13807. The crack formation temperature for glass lining used in processvessels shall be at least 190 C.

    For enamels used in components, e.g. agitators, baffles, pumps, and piping, the crackformation temperature shall be at least 170 C.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    7/21

    DEP 30.48.70.30-Gen. August 2005

    Page 7

    2.4 GASKETS

    Gaskets shall be 100 % bi-axially expanded PTFE (known as "e-PTFE"), manufacturedfrom 100 % virgin PTFE, without any addition of pigments or fillers, in accordance withISO 13000.

    The use of other gasket materials shall be subject to the approval of the Principal.The gasket material shall be compatible with the fluid over the full design temperaturerange. Chemical resistance and temperature limits for non-metallic materials, includingPTFE, and several elastomer seal materials shall be in accordance withDEP 30.10.02.13-Gen.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    8/21

    DEP 30.48.70.30-Gen. August 2005

    Page 8

    3. DESIGN AND MANUFACTURE

    3.1 DESIGN

    The design shall be in accordance with the purchase order unless the components are the

    Manufacturer's standard items, in which case the Manufacturer shall submit fully detaileddescriptions and drawings for checking and approval by the Principal. The Manufacturershall be responsible for the appropriate design and construction.

    3.2 MANUFACTURE

    3.2.1 Glass lining

    3.2.1.1 General

    The type of enamel and, if relevant, the colour shall be subject to the approval of thePrincipal.

    The characteristic composition of individual enamel layers shall correspond with specimensubmitted for laboratory testing.

    The Manufacturer shall confirm that the type(s) of enamel selected is/are suitable for theapplication stated by the Principal.

    The glass lining shall have a uniform, smooth and fully fused surface, free from impurities(see 3.5.3).

    3.2.1.2 Lining thickness

    The thickness of glass lining on steel substrate shall range from 1.0 mm to 2.2 mm, and themaximum value may be exceeded by 0.2 mm on concave surfaces.

    The glass lining may be 0.2 mm thinner than the specified minimum values in limited areas

    on concave surfaces.Linings on small parts with a radius less than 5 mm, e.g. valve-stems or pump rotors, shallhave a minimum thickness of 0.6 mm.

    Any changes in thickness shall be gradual.

    3.2.2 Steel surface preparation

    The steel surface to be lined shall be smooth, clean and free from pitting, cavities, porosity,scale or other deposits and shall be blast-cleaned to a surface finish corresponding toSa 2 in accordance with ISO 8501-1. Directly after blast cleaning of the steel substrate,the grit, dust, etc. shall be removed.

    3.2.3 External surface protection

    After completion of the glass lining, the steel parts shall painted externally in accordancewith DEP 30.48.00.31-Gen.

    3.3 CONNECTIONS

    3.3.1 Flanges

    Connections with glass-lined equipment and/or piping shall be flanged. The type of flangesshall be in accordance with the equipment design code and/or the piping class, as specifiedby the Principal.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    9/21

    DEP 30.48.70.30-Gen. August 2005

    Page 9

    3.3.2 Gaskets

    The expanded PTFE gasket material (2.4) shall suit the pressure, temperature andchemical resistance capabilities of the process equipment and piping. The minimumthickness of the gasket should be 3 mm.

    3.4 TOLERANCES

    General tolerances shall be as follows:

    Vessels DIN 28005

    Agitator vessels DIN 28006

    Columns DIN 28007

    Concentricity of impellersand pump rotors

    DIN 28161

    Piping, flanges DEP 31.38.01.11-Gen

    3.5 DEFECTS

    3.5.1 General

    Defects shall be examined visually as described in (4.2).

    3.5.2 Unrepairable defects

    Defects unacceptable in the finished product, and which shall justify rejection or re-lining,are the following:

    a) Defects which cannot be repaired by using plugs (5.1), i.e.:

    Defects extending over an area with a diameter greater than 8 mm;

    Defects on inaccessible locations; Defects in vessels and columns, as described in (3.5.4).

    b) Bubble lines, i.e. fused-in bubbles arranged in a distinct line;

    c) Fused strain lines recognised as lines with colours different from the surroundingenamel;

    d) Areas not properly fused (recognised as rough surfaces);

    e) Devitrified areas in vitreous enamel or over crystallised areas in semi-crystallisedenamel (recognised as dull or rough surfaces);

    f) Spot-like discolorations;

    g) Cracks, e.g. those detected by a Statiflux test (4.1.3);h) Spots with a diameter greater than 30 mm caused by grinding and polishing during the

    removal of impurities.

    3.5.3 Repairable defects

    Repairable defects are imperfections in the glass lining that can be repaired so as to allowfurther use of the glass-lined equipment. The following defects may be repaired:

    defects revealed by high voltage spark testing (4.1.2); isolated spots showing a loss of thickness of more than 25 % of the nominal thickness; blisters, such as circular holes in the lining; isolated impurities, such as fire clay particles, which shall be removed. Dust-like

    impurities on the surface may be accepted. Scale fused into the surface shall beremoved where it extends parallel to the surface with a width of more than 3 mm, and/oris not a flat particle, or is not fused-in parallel to the surface.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    10/21

    DEP 30.48.70.30-Gen. August 2005

    Page 10

    3.5.4 Vessels and columns

    Tables 1 and 2 list the maximum permissible number of repairable defects to be coveredwith plugs. However, in the following cases, repair by plugging shall not be allowed:

    a) The complete neck area around nozzles, and any nozzle with a nominal diameter of

    150 mm or less;b) Convex and concave surfaces with a radius of 75 mm or less;

    c) Sealing areas.

    The Principal shall specify if no plug repairs are permitted, i.e. specify as PLUG-FREE.

    Table 1 Maximum permissible number of plugged enamel defects in vessels

    NOMINAL VOLUME VESSELS WITHSEPARATE COVER

    ONE-PIECEVESSELS

    OTHERVESSELS

    VESSEL COVER

    up to 4 m 3 0 0 0 0

    4 m 3 up to 10 m 3 1 1 1 1

    10 m 3 up to 20 m 3 N/A N/A 2 3

    20 m 3 up to 32 m 3 N/A N/A 3 4

    32 m 3 up to 40 m 3 N/A N/A 4 5

    40 m 3 up to 80 m 3 N/A N/A N/A 6

    80 m 3 and greater N/A N/A N/A 7

    Table 2 Maximum permissible number of plugged enamel defects in columns

    COLUMN DIAMETER COLUMN HEIGHTup to 2000 mm 2000 mm

    up to5000 mm

    5000 mm andhigher

    Up to 600 mm 0 0 0

    Over 600 mm up to 1200 mm 0 1 2

    Over 1200 mm 1 2 3

    3.5.5 Accessories

    Accessories, e.g. agitators, baffles, inlet pipes, manhole covers, etc, shall not be repairedby plugging.

    3.5.6 Fittings and pump components

    Fittings and pump components shall not be repaired by plugging.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    11/21

    DEP 30.48.70.30-Gen. August 2005

    Page 11

    4. TESTING, INSPECTION AND DOCUMENTATION

    4.1 TESTING

    4.1.1 General All testing, measuring and inspection equipment shall be maintained and calibrated to anaccuracy suitable for the parameter being measured.

    All tests specified in this DEP shall be carried out by, or witnessed and certified by, anindependent third-party agent to be approved by the Principal.

    The surfaces to be tested shall be clean, dry, sufficiently illuminated, and easily accessible.Tested components and test reports (4.3) shall be marked to allow proper identification.

    4.1.2 High voltage test

    The complete glass-lined surface shall be inspected for defects by a high voltage test, inaccordance with ISO 2746 or EN 14430. The first test carried out shall be performed at20 kV. Following tests shall be carried out at a lower voltage setting of 12 kV. Tests with ahigher voltage may be carried out, if so agreed with the Manufacturer.

    On all-side glass-lined components, testing shall be performed with an A.C. voltage or apulsed D.C. voltage.

    Exceptions apply to the following:

    a) Enamelled probes shall be tested with a D.C. voltage of 7 kV;

    b) Components coated with conductive and/or dissipative enamel shall only be checkedvisually, and shall be marked by the Manufacturer.

    4.1.3 Test for cracks

    The Statiflux test method shall be used to check areas where cracks are suspected.Cracks so detected shall not be permitted.

    4.1.4 Performance test

    The Manufacturer shall check the performance of the glass-lined components afterassembly. Particular attention shall be paid to the proper performance of rotating equipment(4.2.3.3).

    4.2 INSPECTION

    4.2.1 Visual examination

    The surfaces of glass-lined process equipment and components shall be checked visuallyfor defects (3.5). Optical instruments, such as 10 magnifying glasses and a monochromaticlamp may be used.

    4.2.2 Lining thickness

    The glass-lining thickness shall be measured according to ISO 2178, using a calibratedmeasuring device with an accuracy of at least 5 %. The surfaces to be checked shall bemeasured on a grid of width between 200 mm and 500 mm. Critical areas, such as shortradii, uneven surfaces and localised increased thickness, shall be measured separately,using smaller grids.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    12/21

    DEP 30.48.70.30-Gen. August 2005

    Page 12

    4.2.3 Dimensions

    4.2.3.1 General

    All dimensions shall be compared with the baseline values given on the Manufacturers

    drawings.4.2.3.2 Vessels and columns

    The following dimensions shall be determined:

    a) diameter and roundness of the vessel (inside);

    b) diameter and roundness of the assembly flange and main flange;

    c) wavelike distortion of the sealing surfaces of the assembly flange and main flange;

    d) out-of-plane angle of the sealing surface and nozzles;

    e) thickness of gaskets;

    f) distance between the support ring, brackets and legs, and a reference plane;

    g) variations in the distance between the various circumferential points of the support ring,between the individual brackets and legs, and a reference plane;

    h) ground clearance of the agitator.

    Any out-of-tolerance dimensions shall not be accepted.

    4.2.3.3 Rotating equipment

    The concentricity of impellers and pump rotors after assembly shall be measured, and shallnot exceed the maximum value to be specified by the Manufacturer.

    The maximum eccentricity of agitators, impeller assemblies, delivered as separate items,shall be documented. Measurements shall be taken by the Manufacturer after machiningand with the impellers still mounted in the lathe.

    4.3 DOCUMENTATION

    The Manufacturer shall maintain quality records to demonstrate that the necessary checkshave been carried out at all stages of production.

    The Manufacturer shall submit a certified record of inspection and testing together withcertificates and statement of compliance with this DEP. The records shall include thefollowing:

    a) All information necessary for identification of the samples tested, including:

    name of the Manufacturer;

    product and product size;

    ordering details (e.g. date and number of the order);

    drawing number;

    enamel quality.

    b) Type and scope of testing (e.g. enamel quality testing, dimensional check, performancetest).

    c) Results of the tests, inspections, and:

    where relevant, the general state of the components at the time of testing (e.g. clean,dry, hardly accessible, partly dirty);

    results of visual examination;

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    13/21

    DEP 30.48.70.30-Gen. August 2005

    Page 13

    voltage used in high voltage test and the results obtained;

    where relevant, the results of the crack detection test;

    lining thickness;

    sketch or description of the location and the number of defects repaired with plugs; results of dimensional checks;

    eccentricity of agitators and pump rotors.

    d) Deviations from the specified procedure.

    e) Unusual features (anomalies) observed during the test.

    f) Date of testing, name and signature of inspector(s).

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    14/21

    DEP 30.48.70.30-Gen. August 2005

    Page 14

    5. REPAIR PROCEDURE

    5.1 REPAIR PLUGS

    Enamel defects shall be repaired with tantalum plugs and PTFE gaskets, see Figures 1 and

    2. Other plug or gasket materials shall be subject to the approval of the Principal.Plugs shall be positioned at right angles to the surface. The plug bearing surface shall be infull contact with the gasket. The length of the plug thread shall be sufficient to ensureadequate seating. The distance between the centre lines of two plugs shall be at least100 mm.

    The maximum permissible number of defects repaired by plugging shall be in accordancewith Tables 1 and 2 (3.5.4). The Manufacturer shall provide the Principal with a sketchshowing the locations of repairs.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    15/21

    DEP 30.48.70.30-Gen. August 2005

    Page 15

    5.2 IMPURITIES

    Impurities (3.5.3) shall be removed by grinding and polishing, under the followingconditions:

    a) remaining enamel thickness shall be at least 0.9 mm for vitreous enamel, and 1.1 mmfor semi-crystallized enamel;

    b) maximum grinding depth shall not exceed 0.5 mm;

    c) following the removal of impurities, no coarse bubble structure shall be allowed.

    If these conditions cannot be met, these enamel defects shall be repaired with plugs.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    16/21

    DEP 30.48.70.30-Gen. August 2005

    Page 16

    6. PACKAGING, TRANSPORTATION AND INSPECTION

    6.1 GENERAL

    Glass-lined apparatus and components are sensitive to mechanical shock loading, e.g.

    impact or local deformation. The type of packaging shall be chosen by the Manufacturer toensure that glass-lined products withstand the expected transport conditions. Appropriatepackaging shall take into account the size, mass and rigidity of the glass-lined products, themeans of loading and unloading, the means of transportation and transfers and, ifnecessary, the storage conditions once the products have reached their destination.

    6.2 PACKAGING AND TRANSPORTATION

    Accessories inside the vessels shall be secured so as to avoid direct contact with othercomponents. Small components should be packed in separate boxes.

    Nozzles shall be covered with rubber or plastic lids that are thick enough to ensuresufficient protection of flange faces.

    The packed products shall bear clearly visible information, or a pictogram in accordancewith ISO 780, regarding the care with which they should be handled during transport.

    Vessels shall be wedged and held in place on square timber frames. Care shall be takenthat the nameplate, attached on the side or top of the vessel, is visible and legible fromabove or the side and that the manholes are positioned to allow easy access.

    Bare metal surfaces, such as fitting surfaces machined to particularly close tolerances,shall be protected against atmospheric corrosion.

    6.3 ARRIVAL INSPECTION

    In order to detect any defects or damage resulting from transportation, the equipment shallbe visually inspected and spark tested (test voltage up to 8 kV). Any defects shall be

    reported to the Manufacturer.

    Presence of the Manufacturer's representative(s) at any of these inspections shall beagreed beforehand and stated in the order.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    17/21

    DEP 30.48.70.30-Gen. August 2005

    Page 17

    7. INSTALLATION

    7.1 GENERAL

    The installation of glass-lined equipment is similar to that of normal flanged steel equipment

    with respect to supporting, thermal expansion, etc. Welded supports shall not be applied.

    7.2 CONNECTIONS

    On factory-assembled vessels the main flange gaskets, agitator flange gasket and man-way gaskets are tailor-made and shall be replaced in the same position after disassembly.

    7.3 BOLTING

    Flange bolts shall be tightened with a torque wrench, using greased bolts and nuts, in thesequence and to the torque values specified by the Manufacturer of the glass-linedequipment.

    7.4 WELDING

    No welding shall be performed on glass-lined equipment, nor may it be used as a weldingearth, as this can cause damage to the lining.

    7.5 MARKING

    The glass-lined equipment shall be marked to identify it as glass-lined, in order to preventinadvertent damage of the lining, e.g. by welding.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    18/21

    DEP 30.48.70.30-Gen. August 2005

    Page 18

    8. OPERATION

    8.1 THERMAL SHOCK

    During operation, the temperature change of glass-lined equipment shall be kept within the

    Manufacturers specified thermal shock limits (2.3.3).

    8.2 ACID SPILLS

    Severe corrosion damage may be caused to glass-lined equipment if acid is spilled onto theexternal carbon steel surfaces. Acid spills may cause a reaction with the steel, i.e. produceatomic hydrogen, which can penetrate through the vessel wall and may cause fracture ofthe glass lining.

    8.3 STEAM HAMMER

    The injection of hot steam into cold liquids can cause damage to the glass lining when rapidcondensation (implosion) and subsequent shock waves occur. This phenomenon should be

    avoided through the use of proper mixing devices so that the steam is condensed before itenters the vessel.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    19/21

    DEP 30.48.70.30-Gen. August 2005

    Page 19

    9. MAINTENANCE, INSPECTION AND REPAIR

    9.1 MAINTENANCE

    Correctly designed and properly manufactured glass-lined process equipment will require

    only minimal maintenance.If it is necessary to enter the glass-lined vessel, and to use a ladder inside the vessel, theladder shall have suitably cushioned feet to prevent damage to the lining. Personnelentering a glass-lined vessel should wear clean and soft, e.g. rubber-soled, footwear.

    Glass lining is easily damaged, e.g. by dropping tools, and therefore soft, e.g. rubber-covered inspection tools, secured against dropping, should be used.

    9.2 INSPECTION

    Condition monitoring of the glass lining should be primarily by visual inspection (4.2.1), andmay be supplemented by high voltage testing (4.1.2). Statiflux testing should be performedif crack-like defects are suspected.

    9.3 REPAIRS

    Repairs shall be conducted in accordance with the Manufacturers approved procedures.

    The competence of operators conducting the repair work shall be established inaccordance with these procedures.

    No welding, flame cutting, etc, shall be performed on glass-lined equipment, and glass-lined equipment shall not be used as a welding earth.

    9.4 CLEANING OF THE JACKET SPACE

    Heating or cooling media used in the jacket may cause a gradual build-up of rust or scaledeposits that can hinder heat transfer. Acid scale and rust removing agents in the jacket ofthe glass-lined vessel endanger the glass lining due to hydrogen diffusing into or throughthe steel. Only those cleaning agents that passivate the steel surface and prevent theabsorption of nascent hydrogen in the steel may be used, e.g. alkaline cleaning agents,which dissolve rust and scale by forming complex compounds.

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    20/21

    DEP 30.48.70.30-Gen. August 2005

    Page 20

    10. REFERENCES

    In this DEP reference is made to the following publications:

    NOTES: 1. Unless specifically designated by date, the latest issue of each publication shall be used (togetherwith any amendments/supplements/revisions thereof).

    2. The DEPs and most referenced external standards are available for Shell users on the SWW(Shell Wide Web) at address http://sww05.europe.shell.com/standards.

    SHELL STANDARDS

    Metallic materials - selected standards DEP 30.10.02.11-Gen

    Non-metallic materials selection and application DEP 30.10.02.13-Gen

    Painting and coating of new equipment DEP 30.48.00.31-Gen.

    Piping - general requirements DEP 31.38.01.11-Gen.

    EUROPEAN STANDARDS

    Vitreous and porcelain enamels High voltage test EN 14430

    Vitreous and porcelain enamels Determination ofresistance to chemical corrosion Part 2:Determination of resistance to chemical corrosionby boiling acids, neutral liquids and/or theirvapours

    EN 14483-2

    Vitreous and porcelain enamels Determination ofresistance to chemical corrosion Part 4: Determination ofresistance to chemical corrosion by alkaline liquids using acylindrical vessel

    EN 14483-4

    Vitreous and porcelain enamels glass-lined apparatus forprocess plants Part 3: Thermal shock resistance

    prEN 15159-3

    CENEuropean Committee for StandardizationRue de Strassart 35Belgium B-1050Brussels

    GERMAN STANDARDS

    General tolerances for glass-lined vessel DIN 28005

    General tolerances for fabrication of agitator

    vessels, glass-lined steel agitator vessels

    DIN 28006

    General tolerances for columns, glass-lined steel columns DIN 28007

    Testing the concentricity of impellers and pump rotors DIN 28161

    Issued by:DINBurggrafenstrasse 6Berlin, D-10787Germany

    INTERNATIONAL STANDARDS

    Pictorial marking for handling of goods ISO 780

    Non-magnetic coatings on magnetic substrates Measurement of coating thickness Magnetic method

    ISO 2178

  • 7/26/2019 30487030_glass-Lined Steel Process Equipment

    21/21

    DEP 30.48.70.30-Gen. August 2005

    Page 21

    Vitreous and porcelain enamels - Determination ofresistance to condensing hydrochloric acid vapour

    ISO 2743

    Vitreous and porcelain enamels Determination ofresistance to hot sodium hydroxide

    ISO 2745

    Vitreous and porcelain enamels Enamelled articles forservice under highly corrosive conditions high voltage test

    ISO 2746

    Preparation of steel substrates before application of paintsand related products - Visual assessment of surfacecleanliness - Part 1: Rust grades and preparation grades ofuncoated steel substrates and steel substrates after overallremoval of previous coatings.

    ISO 8501-1

    Plastics Polytetrafluoroethylene (PTFE) semi-finishedproducts Part 1: Requirements and designation

    ISO 13000

    Vitreous and porcelain enamels Determination of crackformation temperature in the thermal shock testing of

    enamels for the chemical industry

    ISO 13807

    Issued by:International Organisation for StandardisationCase Postale 56CH-1211 Geneva 20, Switzerland.

    Copies can also be obtained through national standards organisations.