3 4-3 transmission hodder kasztenny & fischer backupconsiderations
TRANSCRIPT
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
1/43
Copyrigh t © Hydro One Netwo rks, Inc. and SEL 2012
Backup Considerations for LineCurrent Differential Protection
Steven HodderHydro One Networks, Inc.
Bogdan Kasztenny and Normann FischerSchweitzer Engineering Laboratories, Inc.
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
2/43
Outline
• Line protection redundancy• Loss of 87L protection
• 87L backup schemes♦ POTT or DCB
♦ Zone 1 extension
♦ Stepped distance♦ Overcurrent
• Backup protection strategies
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
3/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
4/43
Line Protection Considerations
• Critical fault clearing time – protection type• Forced outages avoided – protection
availability
• HV / EHV applications♦ Breaker failure protection
♦ Communications-assisted schemes♦ Parallel redundancy of protection
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
5/43
Hydro One Example
• Operates Ontario transmission system(500, 230, and 115 kV)
• Follows NPCC guidelines
• Categorizes BES lines♦ Impactive
♦ Nonimpactive
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
6/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
7/43
Instantaneous Tripping Lost
• BES-impactive circuit♦ Independent electricity system operator
(IESO) must be notified within 5 minutes ofsecond failure
♦ Forced line outage is immediate
• Non-BES-impactive circuit♦ Line typically removed from service
♦ If removal has adverse impact on customerload, leave line in service and rely on timed
backup only
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
8/43
Line Current Differential Protection
• Inherently selective• Very sensitive
• Immune tosystem conditions
• Easy to set
• Dependent oncommunications
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
9/43
Loss of 87L Protection
• 87L element blocked• Relay out of service
• Problems with communications♦ Channel loss
♦ Channel brownout
• Inability to align local and remotecurrents – loss of time referencewhen using asymmetrical channels
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
10/43
Loss of Time Reference
• IRIG-B connection severed• IRIG-B signal noisy
• Time source (external clock) malfunction
• Time source not locked
• GPS problems
Using IEEE C37.118-compliant clocksthat report time quality is important
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
11/43
87L Adaptivity to
Channel Problems
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
12/43
Primary Channel
Hot Standby Channel
Hot StandbyLogic
Hot StandbyLogic
87L 87L
87L Relay 87L Relay
Hot Standby Logic
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
13/43
Primary Channel
Hot Standby Channel
Hot StandbyLogic
Hot StandbyLogic
87L 87L
87L Relay 87L Relay
Hot Standby Logic
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
14/43
Channel 1
C h a n n e l 2 C h a n
n e l 3
Master Master
Master
87L1
87L2
87L
3
Three-Terminal Applications
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
15/43
Three-Terminal Applications
C h a n n e l 2 C h a n
n e l 3
Slave Slave
Master
87L1
87L2
87L
3
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
16/43
87L
87L
87L
Stub Bus Zone
Line ZoneMaster
Master
Master
Channel Loss Under Stub Bus
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
17/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
18/43
CommunicationsRedundancy
A87LMain Path
B87L Alternate Path
SONETRing #1
A87L
Alternate Path
B87L
Main Path
SONET
Ring #2
Add / Drop
MUX
A87L B87L
DS1MUX
DS1MUX
DS1MUX
DS1MUX
Add / DropMUX
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
19/43
Hydro One ProtectionPhilosophy With SONET
DS0 Protection Circuits Static (Pinned)
• Avoid complexity (e.g., testing), especiallyas SONET network grows
• Support protection scheme designed towork despite single communications failure
• Ensure channel symmetry, especially forbusiness-class SONET equipment
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
20/43
SONET Path Routing forThree-Terminal Lines
1 2
3
Line
Distance
Line
Distance
LineDistance
Main1-2
Main2-1
Alternate1-3
Alternate
3-1
Alternate2-4
Main
3-4
Alternate4-2
Main
4-3
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
21/43
Communications Contingencies
• Channel redundancy is preferred solutionfor POTT or DCB over SONET
• Channel redundancy is limited option for
87L schemes♦ Available for two-terminal schemes only
when direct point-to-point channels are used
♦ SONET path switching may cause problems
• 87L backup is preferred over 87L channelredundancy
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
22/43
87L Backup
• Backup required for rare occasions when87L is unavailable♦ Channel problems
♦ Timing problems
• Backup integrated within multifunction 87Lrelay acceptable and beneficial
• Selectivity requirements can be relaxed if87L backup engaged only when needed
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
23/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
24/43
Directional Comparison
• Not practical in many cases – requireschannel in addition to 87L channel
• More difficult to set compared with 87L
• Sensitive if 67Q / 67G used, maycause sequential tripping
• Less secure compared with 87L
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
25/43
Zone 1 Extension Logic
• Substitute for extra channel atexpense of selectivity♦ Trips from overreaching Z1
♦ Reduces Z1 reach before reclosing
• Less sensitive compared with 87L
• Susceptible to load and power swings• Supplemented with 51Q / 51G and
67Q / 67G for high-resistance faults
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
26/43
Stepped Distance
• Time-delayed for selectivity and coordination• Part of remote backup strategy (if used)
• More difficult to set (infeed)
• Less sensitive compared with 87L
• Susceptible to load and power swings
• Supplemented with 51Q / 51G and67Q / 67G for high-resistance faults
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
27/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
28/43
87L Backup Strategies
• Fully operational backup• Backup engaged only upon loss of 87L
• Adaptive backup
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
29/43
Fully Operational Backup
• Parallel with 87L scheme• Requires no information about 87L state –
standalone implementation
• Biases protection toward dependability
• Must be set conservatively to maintainsecurity – faces settings challenges
• Not justified if redundant system operational
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
30/43
Backup Engaged if 87L Lost
• Does not adversely impact security• Can follow simpler operating principles –
stepped distance
• Can be biased toward dependability –Zone 1 extension
• Faces fewer settings challenges
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
31/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
32/43
87L
21
87L
21
87L 21
Backup Engaged if 87L Lost
• Master-slave mode uponfirst channel failure
• Backup remains blocked
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
33/43
87L
21
87L
21
87L 21
Backup Engaged if 87L Lost
Backup engaged whensecond channel fails
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
34/43
87L
21
87L
21
87L 21
Backup Engaged if 87L Lost
Or…
Backup engaged ifany relay is slave
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
35/43
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
36/43
Adaptive Backup Examples
87L /21P /21G
87L /21P /21G
Z AX
Terminal A Terminal C
Zone 2 (Timed)Zone 1 (Instantaneous)
ZCX
ZBX
Terminal B
87L / 21P / 21G
X
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
37/43
87L /21P /21G
87L /21P /21G
Z AX
Terminal A Terminal C
Zone 2 (Timed)Zone 1 (Instantaneous)
ZCX
ZBX
Terminal B
87L / 21P / 21G
X
Adaptive Backup Examples
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
38/43
DTT A-C-B
DTT C-B
Master-Slave Configuration
87L21P21G
87L21P21G
87L, 21P, 21G
Terminal A Terminal C
Terminal B
DTT A-C
DTT A-B
21-1
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
39/43
Stub Bus
DTT Rem2 _ Local_Rem1
DTT Rem1 _ Local_Rem2
Z2_Pickup (Rem1)Z2_Pickup (Rem2)
Local_Stub_Bus
DTT Local_Rem1
DTT Local_Rem2
Local_DTT_TX
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
40/43
Conclusions
• 87L is selective, sensitive, and secure• Communications paths and equipment
affect overall 87L availability
• Communications and timing contingenciescan render 87L unavailable
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
41/43
Conclusions
• 87L backup covers failures incommunications and timing, not relays
• Regulatory requirements and internal
practices impact selection of backup• Typical backup schemes include 21T,
Z1EXT, 51, and POTT or DCB
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
42/43
Conclusions
• Settings backup schemes are typicallymore involved than 87L
• 87L backup elements integrated within
same protective device are prudent• Backup only engages upon loss of 87L
♦ Benefits security
♦ Simplifies settings selection
-
8/9/2019 3 4-3 Transmission Hodder Kasztenny & Fischer BackupConsiderations
43/43
Questions?