27.04.2013
TRANSCRIPT
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 27.04.13
1.Ground Floor slab Completed2.First Floor slab 1 & 2 flats Completed3.Remains Columns Work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 27.04.13
1.Ground Floor slab Completed2.First Floor slab flat no 01 & 02 completed 3 & 4 flats Bar Bending
and Shuttering Work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 27.04.13
1.Basement I slab Completed2.Ground Floor Flat No 01 Shuttering work in progress
STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 27.04.13
1.Ground Floor slab Completed2.First Floor 1 & 2 flats Slab Completed 3rd Flat Bar Bending work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 27.04.13
1.Ground Floor slab Completed2.First Floor Slab Flat No 01 Shuttering work in Progress
STATUS REPORT OF MY HOME ABHRA “TOTAL SITE & CENTRAL LAWN”As On 27.04.131.Total Site Ground Floor slab except Tower-C Remain all Completed
2.Total Site First Floor slab Tower : A-2 flats, B-2 flats & D-2 Flats Completed3.Central Lawn Basement II Slab 15% Completed