Developing a Work Order

Financial Approval Process

Tony Buffington, Sr. Consultant, Vesta Partners, LLC

[

Page 2: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[

2

Learning Points

The business need for developing this solution in SAP

Configuration and Master Data components necessary for

developing the Approval process

Reporting required to support the internal controls and

enforce the business process

Page 3: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[

3

Business Requirements

If people knew what a maintenance activity cost, would they

think twice about making the request?

If management were involved in reviewing and approving

certain requests, would the priorities change?

Requirement:

Formalize authorization for maintenance work

Build cost awareness

Page 4: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[

4

Work Processes

Where does this fit in the Maintenance Work Processes?

Should there be a notification approval to cull out certain requests???

1) Planned Costs

2) Permits

Why?

Page 5: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Work Order Approval Process s

Page 6: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Master Data related setup

Characteristics

PM_MAINT_PLANT

PM_PLAN_COST

PM_ORDER_TYPE*

Classification

PM_PERMIT

Class type 049

Permits

Creation of permits for approval

Assignment of values to characteristics

*Note: If not all order types are subject to

the approval process, this characteristic will

need to be added.

Page 7: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Configuration related setup

Define Permit Categories

Define Permit Groups

Page 8: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Four steps prior to Permit Master Record setup

Page 9: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Create Permit Characteristics

PM_MAINT_PLANT

Page 10: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Create Permit Characteristics

PM_PLAN_COST

Page 11: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Create Permit Characteristics

PM_ORDER_TYPE

Page 12: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Four steps prior to Permit Master Record setup

Page 13: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Create a Permit Class

Page 14: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Four steps prior to Permit Master Record setup

Page 15: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Assign Permit Characteristics to Permit Class

Page 16: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Four steps prior to Permit Master Record setup

Page 17: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Configure the Permit Group

Page 18: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Define the Permits used for Approval

Page 19: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Define the Permits

Approval Levels

Level 1 – greater than $10,000 but less than $25,000

Level 2 – greater than / equal to $25,000 but less than $75,000

Level 3 – greater than / equal to $75,000

Single Permit Approval required (no overlapping approvals

necessary)

Multiple Plants can be assigned

Multiple Orders Types can be included

Note: Permits can be created that are specific to maintenance

plant and to work order type utilizing these characteristics.

Page 20: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Define the Permits

Level 1 Permit Approval required:

Page 21: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Define the Permits

Level 2 Permit Approval required:

Page 22: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Define the Permits

Level 3 Permit Approval required:

Page 23: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Plan the Work Order

Page 24: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Work Order Planning - Labor

Labor is planned on the Operation tab:

Page 25: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Work Order Planning - Materials

Spare part is added on the Component tab:

Page 26: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Work Order Planning – Determine Costs

Planned Costs are calculated once the Determine Cost button

is selected:

Page 27: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Work Order Planning - Permit Assigned

Once costs are determined the permit is automatically assigned

to the order:

Page 28: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Work Order Planning - Permit Assigned

Page 29: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Issuing the Work Order Approval Permit

Page 30: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – Individual Work Order

Select Permit Issue button:

Page 31: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – Individual Work Order (continued)

Select (highlight) Permit to Issue and click on the

Permit Issue button:

User ID of the

approver appears to

confirm permit issued:

Page 32: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – List Edit – Selection Criteria

List Edit Selection criteria – emphasis on highlighted fields:

Page 33: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – List Edit

Resulting List of Orders needing Permits Issued:

Review Order detail by highlighting line item and selecting the

Display Order button:

Page 34: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – List Edit

Issue Permit – by selecting the line item and clicking the Permit

Issue button:

The “Approved by” field has been populated by the approver:

Page 35: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – List Edit

Reset Approval – by selecting the line item and clicking the

Reset Approval button:

Message about the permit being reset:

Page 36: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Permit Issue – List Edit

List edit report may still show the approvers name in

the list, but the traffic light shows that the permit

has been reset:

And the work order detail shows where the permit

needs approval once again:

Page 37: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Enforcing Approval Process

37

Page 38: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Security Authorization Object

I_SOGEN

38

Page 39: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Restricting access

Adding the Maintenance Plant and Permit Key restrictions to a

users role provide a way to enforce the approval process so

that only the authorized approvers can move the maintenance

activity forward:

List plants and permits individually or have a naming

convention for the permit key which allows the use of the

wildcard (*) – i.e. APV* as opposed to APV1, APV2, APV3.

39

Page 40: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[

40

Key Learnings

Established that Work Orders have to be planned for costs to

be available.

Set up automated permit assignments using classification and

characteristics.

There can be many variations of permits to be used for

approvals (i.e. maintenance plant, planned costs, and work

order types).

Security Access can play a major role in enforcing the Work

Order Approval Process

Need to make sure the Business Processes are in place to

support an approval process.

Page 41: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ Questions?

Page 42: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[ References

Vesta White Paper, SAP Permit Functionality, Using Standard

Permit Functionality in SAP Plant Maintenance, version 1.0,

December 31, 2008, prepared by Phil Vallie. Contact

[email protected] for more information.

Page 43: 2612 developing a_work_order_financial_approval

Real Experience. Real Advantage.

[

43

[

] Thank you for participating.

SESSION CODE:

INSERT SESSION CODE

Please remember to complete and return your

evaluation form following this session.

For ongoing education on this area of focus, visit the

Year-Round Community page at www.asug.com/yrc

Presenter Contact Info: [email protected]