22396525 part i sld bb layout

Upload: prateek43513

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 22396525 Part I Sld Bb Layout

    1/50

    1

    Presentation on

    SUB STATION BASIC : PARTI

    Single Line Diagram

    Bus Bar Arrangement

    Sub Station Layout

  • 7/28/2019 22396525 Part I Sld Bb Layout

    2/50

    2

    IntroductionThe economics of generation of electrical energy and

    the huge demands for power in the modern timesrequires creation of bigger POWER STATIONS.The power stations may be far from the load centre /consumers and so long high voltage transmissionlines are necessary for transfer of bulk power from

    power station to different load centres. In between power station and ultimate consumers anumber of transformation and switching stations areto be created. Such stations are known as Sub Station.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    3/50

    3

    Concept of Power System

  • 7/28/2019 22396525 Part I Sld Bb Layout

    4/50

    4

    What is Sub Station ?A SUBSTATION is a subsidiary station of an electricity

    Generation, Transmission and Distribution systemwhere voltage is transformed from high to low or viseversa using transformers. Electric power may flowthrough several substationsbetween generating plantand consumer, and may bechanged in voltage inseveral steps.A Step-up transformer increases the voltage andproportionally decreases the current, while a step-down transformer decreases the voltage andproportionally increases the current for domestic andcommercial distribution.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    5/50

    5

    House Electrification

    DISTRIBUTION BOARD

    3- & 1- MCBsBUS BAR STRIPS

    SOURCE CABLE (Incoming)

    3- LOAD CABLE (Outgoing)

    1- LOAD CABLE (Outgoing)

    1-

    LOAD CABLE (Outgoing)

    1- LOAD CABLE (Outgoing)

  • 7/28/2019 22396525 Part I Sld Bb Layout

    6/50

    6

    General Arrangement

    LIGHTNING ARRESTOR

    POTENTIAL

    TRANSFORMER

    TR. LINE

    (INCOMER / OUTGOING)

    TR. LINE

    (INCOMER)

    CURRENT TRANSFORMER

    WAVE TRAP

    EARTH SWITCH

    ISOLATOR

    CIRCUIT BREAKER

    ISOLATOR

    CAP. VOLTAGE TRANSFORMER POWER

    TRANSFORMER

    SUBSTATION

    BUS

    BAR

  • 7/28/2019 22396525 Part I Sld Bb Layout

    7/50

    7

    Single Bus Bar Scheme

    BUS BAR

    SUB STATION POWER STATION LOAD CENTRE

    Faulty

    Faulty

  • 7/28/2019 22396525 Part I Sld Bb Layout

    8/50

    8

    Advantage & DisadvantageSINGLE BUS BAR (UPTO 33kV SS)Advantages Lowest cost Small land area required Easily expandable Simple in concept and operationDisadvantages Lowest reliability Failure of a circuit breaker causes loss of the feeder Bus fault causes loss of the entire substation

  • 7/28/2019 22396525 Part I Sld Bb Layout

    9/50

    9

    ImprovementMain Disadvantage ? Loss of the entire Sub Station in case of Bus fault.Requirement ? Avoid loss of entire bus i.e., entire Sub Station in Bus

    fault.How to Achieve ? By Sectionalizing the Single Bus Bar.Arrangement ? Sectionalisation of Single Bus Bar Arrangement.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    10/50

    10

    Sectionalization of Single Bus Bar Scheme

    BUS SECTION - I BUS SECTION - II

    SUB STATION POWER STATION LOAD CENTRE

    Faulty

    Faulty

    SECTIONALIZING CB

  • 7/28/2019 22396525 Part I Sld Bb Layout

    11/50

    11

    Advantage & DisadvantageSECTIONALIZATION BUS BAR (33kV & 66kV SS)Advantages Flexible operation Higher reliability than single bus scheme Isolation of bus sections for maintenance Loss of only part of the substation for a bus faultDisadvantages Loss of circuit for breaker failure A sectionalized bus arrangement has a higher costthan a single bus scheme asadditional circuit breakerand isolators are required for sectionalizing

  • 7/28/2019 22396525 Part I Sld Bb Layout

    12/50

  • 7/28/2019 22396525 Part I Sld Bb Layout

    13/50

    13

    Main and Transfer Bus Bar Scheme

    MAIN BUS I

    SUB STATION POWER STATION

    TRANSFER BUS

    LOAD CENTRE

    Faulty

    Faulty

    TRANSFER BUS

    COUPLER (TBC)

  • 7/28/2019 22396525 Part I Sld Bb Layout

    14/50

    14

    Advantage & DisadvantageMAIN & TRANSFER BUS BAR (132kV SS)Advantages Circuit breaker outage / maintenance does not disruptthe service of feeder / circuit Reasonable in cost Fairly small land area Easily expandableDisadvantages Bus Fault causes disruption of service of entire substation An additional circuit breaker is required for bus tie

  • 7/28/2019 22396525 Part I Sld Bb Layout

    15/50

    15

    ImprovementMain Disadvantage ? Bus fault in a sub station having more nos. of circuits

    causes greater interruption of power. In Main andTransfer Bus Bar arrangement bus fault results loss ofentire sub station i.e., all circuits.Requirement ? Avoid loss of too many circuits in case of bus fault.How to Achieve ? By providing another Main Bus for connection ofcircuits.Arrangement ? Double Main Bus Bar Arrangement.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    16/50

    16

    Double Main Bus Bar Scheme

    MAIN BUS I

    MAIN BUS II

    SUB STATION POWER STATION LOAD CENTRE

    Faulty

    Faulty

    BUS COUPLER (BC)

    Single Bus Scheme Mode

  • 7/28/2019 22396525 Part I Sld Bb Layout

    17/50

  • 7/28/2019 22396525 Part I Sld Bb Layout

    18/50

    18

    ImprovementMain Disadvantage ? Double Main Bus arrangement is an alternative toMain & Transfer Bus scheme. In both cases, the

    investment is same. The only difference is that inDouble Main Bus the outage of Bus Bar and in Main &Transfer Bus the outage of Breaker is prioritized. Interruption of Power during Isolator operation.Requirement ? Both Bus fault and Circuit Breaker outage are to betaken care off.How to Achieve ? By using one of the Main Buses as Main Cum TransferBus.Arrangement ? Double Main Cum Transfer Bus Bar Arrangement.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    19/50

    19

    Double Main Cum Transfer Bus Bar Scheme

    BUS I CUM

    TRANSFER

    BUS II

    SUB STATION POWER STATION LOAD CENTRE

    Faulty

    Faulty

    BC

    Single Bus Scheme Modeain and Transfer Bus Scheme Mode

  • 7/28/2019 22396525 Part I Sld Bb Layout

    20/50

    20

    Advantage & DisadvantageDOUBLE MAIN CUM TRANSFER BUS BAR (220kV SS)Advantages Bus Bar outage / maintenance does not disrupt theservice of any feeder / circuit Circuit Breaker outage does not cause disruption ofservice of that feeder Reasonable in cost Fairly small land area Easily expandableDisadvantages Additional Isolator in each circuit increases the cost

  • 7/28/2019 22396525 Part I Sld Bb Layout

    21/50

    21

    ImprovementMain Disadvantage ? Double Main Cum Transfer Bus Bar arrangementoutage of Circuit Breaker and Bus together causes lossof faulty Circuit Breaker feeder. Interruption of Power during Isolator Operation.Requirement ? Avoid loss of feeder in case of simultaneous outage ofCircuit Breaker and a Main Bus.How to Achieve ? By providing separate transfer Bus along with DoubleMain Buses.Arrangement ? Double Main and Transfer Bus Bar Arrangement.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    22/50

    22

    Double Main and Transfer Bus Bar SchemeSUB STATION POWER STATION LOAD CENTRE

    BUS I

    BUS II

    TRANSFER BUS

    Faulty

    Faulty

    BC

    TBC

    INTERRUPTION

    Single Bus Scheme Modeain and Transfer Scheme Mode

  • 7/28/2019 22396525 Part I Sld Bb Layout

    23/50

    23

    Advantage & DisadvantageDOUBLE MAIN AND TRANSFER BUS BAR (220kV SS)Advantages Bus Bar outage / maintenance does not disrupt theservice of any feeder / circuit Circuit Breaker outage does not cause disruption of

    service of that feeder Maintenance of Bus and CB does not interrupt supplyDisadvantages Additional Isolator and Circuit Breaker required fortransfer Bus tie.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    24/50

    24

    ImprovementMain Disadvantage ? Interruption of Power during Isolator operation. Interruption of Power is likely to cause majordisturbance if the feeders are important and heavilyloaded.Requirement ? Avoid interruption of important and heavily loadedfeeders during bus fault or outage of Circuit Breaker.How to Achieve ? By connection of circuits for double feed throughCircuit Breakers and avoid Isolator switching.Arrangement ? One and a Half Breaker Bus Bar Arrangement.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    25/50

    25

    One and a Half Breaker Bus Bar SchemeBUS I BUS II

    MAIN CB MAIN CBTIE CB

    MAIN CB MAIN CBTIE CB

    SUB STATION

    POWER STATION

    LOAD CENTRE

    Faulty Faulty

    Faulty

    Faulty

  • 7/28/2019 22396525 Part I Sld Bb Layout

    26/50

    26

    Advantage & DisadvantageONE & HALF BREAKER BUS BAR (400kV SS)Advantages Flexible operation High reliability Can isolate either main bus for maintenance withoutdisrupting service Can isolate any circuit breaker for maintenancewithout disrupting service Double feed to each circuit Bus fault does not interrupt service to any circuits All switching done with circuit breakersDisadvantages One-and-a-half breakers are required per circuit

  • 7/28/2019 22396525 Part I Sld Bb Layout

    27/50

    27

    ImprovementImportant In transmission system the highest reliable Bus Bar

    Arrangement adopted by POWERGRID is One and aHalf Bus Bar Scheme. However, where bulk powerevacuation without alternative path is concerned,further reliable arrangement may be adopted.What Arrangement ? Connection of circuits in Double Bus Bar Arrangementwhere each circuit will have a spare Circuit Breaker inservice.Where can be used ? In large Generating Plants where implication ofgeneration outage is much higher than the cost ofCircuit Breakers.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    28/50

    28

    Double Breaker Bus Bar SchemeBUS I BUS II

    SUB STATION

    POWER STATION

    LOAD CENTRE

    Faulty

    Faulty

  • 7/28/2019 22396525 Part I Sld Bb Layout

    29/50

    29

    Advantage & DisadvantageDOUBLE BREAKER BUS BAR (Mega Generating Units)Advantages Flexible operation Very high reliability Isolation of either main bus for maintenance withoutdisrupting service Isolation of any circuit breaker for maintenance

    without disrupting service Double feed to each circuit No interruption of service to any circuits from busfault Loss of only one circuit for breaker failure All switching with circuit breakersDisadvantages This configuration carries a high cost Two circuit breakers are required for each circuit.

  • 7/28/2019 22396525 Part I Sld Bb Layout

    30/50

    30

    PHOTOGRAPHS

  • 7/28/2019 22396525 Part I Sld Bb Layout

    31/50

    31

    Photographs

    BUSBAR

  • 7/28/2019 22396525 Part I Sld Bb Layout

    32/50

    32

    CIRCUIT BREAKER ISOLATOR AND EARTH SWITCH

    Photographs

  • 7/28/2019 22396525 Part I Sld Bb Layout

    33/50

    33

    CURRENT TRANSFORMER POTENTIAL TRANSFORMER

    Photographs

  • 7/28/2019 22396525 Part I Sld Bb Layout

    34/50

    34

    LIGHTNING ARRESTER

    CAPACITOR VOLTAGE

    TRANSFORMER

    Photographs

  • 7/28/2019 22396525 Part I Sld Bb Layout

    35/50

    35

    WAVE TRAP TRANSMISSION LINE

    Photographs

  • 7/28/2019 22396525 Part I Sld Bb Layout

    36/50

    36

    TRANSFORMER

    Photographs

  • 7/28/2019 22396525 Part I Sld Bb Layout

    37/50

    37

    REACTOR

    Photographs

  • 7/28/2019 22396525 Part I Sld Bb Layout

    38/50

    38

    Photographs

    SUB STATION

  • 7/28/2019 22396525 Part I Sld Bb Layout

    39/50

    39

    LAYOUT & SECTION

  • 7/28/2019 22396525 Part I Sld Bb Layout

    40/50

    40

    DRAWING EXAMPLE : 1

    CL-CT

    CL-WT

    CL-CVT

    CL-LA

    A

    A

    B

    B

    CL-ISO

    CL-CB

    CL-ISO

    CL-LA

    CL-TFR.

    SLIDE : 1 of 3

  • 7/28/2019 22396525 Part I Sld Bb Layout

    41/50

    41

    Ground LevelLA CVT WT CT ISO & ES CB ISO

    SECTION - AA

    DRAWING EXAMPLE : 1

    SLIDE : 2 of 3

    Earth Wire

    Gantry

  • 7/28/2019 22396525 Part I Sld Bb Layout

    42/50

    42

    Ground LevelLA CT ISO CB ISO

    SECTION - BB

    DRAWING EXAMPLE : 1

    SLIDE : 3 of 3

    Transformer

    A B

  • 7/28/2019 22396525 Part I Sld Bb Layout

    43/50

    43

    DRAWING EXAMPLE : 2

    SLIDE : 1 of 3

    CL-CT

    CL-WT

    CL-CVT

    CL-LA

    A

    CL-ISO

    CL-CB

    CL-ISO

    CL-LA

    CL-TFR.

    CL-ISO

  • 7/28/2019 22396525 Part I Sld Bb Layout

    44/50

    44

    SECTION - AA

    DRAWING EXAMPLE : 2

    SLIDE : 2 of 3

    Ground LevelLA CVT WT CT ISO & ES CB ISO ISO

    Gantry

    Earth Wire

  • 7/28/2019 22396525 Part I Sld Bb Layout

    45/50

    45

    SECTION - BB

    DRAWING EXAMPLE : 2

    SLIDE : 3 of 3

    Ground LevelCT ISO & ES CB ISO ISO

    Gantry

    LATransformer

    Earth Wire

  • 7/28/2019 22396525 Part I Sld Bb Layout

    46/50

    46

  • 7/28/2019 22396525 Part I Sld Bb Layout

    47/50

    47

    QUESTIONWhat are the different parts of Power System ?What is Sub Station ?What is Single Line Diagram ?Explain BUS BAR ?What do you understand by Bus Bar Arrangement ?What are the limitations of Single Bus Bar Scheme ?What is the advantage of Sectionalisation of Single Bus

    Bar over Single Bus Arrangement ?Bus Bar Arrangement for 132kV Sub Station is .

  • 7/28/2019 22396525 Part I Sld Bb Layout

    48/50

    48

    QUESTIONWhat are the limitations of Main & Transfer Bus BarScheme ?How does Double Main Bus Scheme differ from Main &Transfer Bus Arrangement ?What is the difference between Double Main Bus and

    Double Main Cum Transfer Bus Arrangement ?What is the Bus Bar Arrangement for Sub Station havingvoltage class 400kV & above ?What is the advantages of One and a half Breaker BusBar Scheme ?What is the advantage & Disadvantage of Two BreakerBus Bar Scheme and where the same is used ?

  • 7/28/2019 22396525 Part I Sld Bb Layout

    49/50

    49

    QUESTIONExplain the purpose of using

    (a) Circuit Breaker(b) Isolator(c) Earth Switch(d) Lightning Arrestor(e) Current Transformer(f) Potential Transformer(g) Capacitor Voltage Transformer(h) Wave Trap(i) Power Transformer

  • 7/28/2019 22396525 Part I Sld Bb Layout

    50/50