2.11 transportation and traffic - sandiegocounty.gov€¦ · 2.11 transportation and traffic ......
TRANSCRIPT
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-1
2.11 Transportation and Traffic
This section describes the results of a Traffic Impact Study (August 2015) conducted by KOA
Corporation to evaluate the transportation-related impacts of the Warner Ranch Project (project)
on transit, bicycle, and pedestrian movements. The Traffic Impact Study, prepared in compliance
with the County’s Report Format and Content Requirements for Traffic Analysis is included in
this Environmental Impact Report (EIR) as Appendix M. This EIR section is based on the Traffic
Impact Study, and when possible, tables from the Traffic Impact Study are incorporated into the
analysis to make it easier for the reader to obtain the relevant information.
2.11.1 Existing Conditions
2.11.1.1 Traffic Network
The project site is located in the San Luis Rey River Valley, approximately 6 miles east of
Interstate 15 (I-15). It is located on the north side of State Route 76 (SR 76), immediately west of
the Pala Casino, which is on the south side of SR 76 (Figure 2.11-1, Project Study Area).
SR 76 runs generally west to east through the San Luis Rey River Valley and is the dominant
route to access the valley. SR 76 varies in classification from a two-lane highway, to a four-lane
collector, to a four-lane major roadway. It has a painted median and a posted speed limit of 55
miles per hour. Project access would be from SR 76. The majority of SR 76 in the study area is
classified as a two-lane State Route with a portion from I-15 classified as a four-lane major
roadway (see Figure 3-1 of Appendix M).
SR 76 has been the subject of three improvement projects by Caltrans: the SR 76 West Project
(between I-5 and Melrose Drive) completed in 1999, the SR 76 Middle Project (from approximately
Melrose Drive to South Mission Road) completed in 2012, and the SR 76 East Project (from
approximately South Mission Road to and including the SR 76/I-15 interchange ramps) for which
phase I was completed in 2013 and phase 2 is currently underway (TransNet 2016).
Since the baseline date for the TIS analysis for the Warner Ranch project, the SR 76 Middle
Project between Melrose Drive and South Mission Road, was completed by Caltrans (in 2012 as
previously indicated). Construction of the Middle Project expanded the existing highway from
two lanes to four and project features included:
Installing new signalized and full access intersections to improve the functionality of the
roadway, including better local access,
Constructing a new two-lane bridge over the San Luis Rey River for eastbound traffic,
reconfiguring the existing San Luis Rey River Bridge for westbound traffic, and
Replacing both the Bonsall Creek Bridge and the Ostrich Farm Creek Bridge.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-2
The EIR/Environmental Impact Statement (EIS) for the Caltrans SR 76 East Project was finalized in
January 2012. The SR 76 East Segment is the final segment in a series of the three improvement
projects to the SR 76 corridor located between I-15 and I-5. The East Segment stretches 5.2 miles
from South Mission Road to I-15 and serves local, intraregional, and interregional traffic.
Construction of the East Segment will widen and realign SR 76 to a four-lane highway to meet
present travel needs and accommodate future growth. The first phase of the East Project improved
the interchange at SR 76 and I-15 and was opened to traffic in August 2013.
Physical Improvements to the East Segment include:
Widening the roadway from South Mission Road to Old Highway 395 to create a
four-lane highway
Expanding the Park & Ride at SR 76 and Old Highway 395
Widening and upgrading the SR 76/I-15 interchange, including improvements to existing
on- and off-ramps and the addition of two loop on-ramps to I-15, to improve traffic
operations and efficiency
Construction of the second phase will widen and realign SR 76 to a four-lane highway from just
east of South Mission Road to the newly improved SR 76/I-15 interchange. In support of that
project, pre-construction work efforts such as clearing dense brush and trees began in February
2014. Major construction efforts for the second phase of the project began in November 2014
and will last about three years. The Caltrans SR 76 East Project has identified TransNet as a
funding source, with completion in Fall 2017 (Caltrans 2015a; TransNet 2016).
Pala Temecula Road runs generally north to south between the City of Temecula and the
Community of Pala, intersecting SR 76 approximately one mile east of the project site. It is a
two-lane rural collector with a posted speed limit of 30 miles per hour.
Pala Mission Road is the main road of the Pala Community, and is located north of SR 76. It
runs roughly parallel to SR 76 from approximately the eastern edge of the project, crosses Pala
Temecula Road, and then rejoins SR 76. It is a two-lane local road with a painted median and a
posted speed limit of 25 miles per hour.
Traffic conditions, for both existing and projected conditions, are described in terms of Level of
Service (LOS). For roadway segments, LOS is a qualitative measure of conditions in terms of
speed, travel time, freedom to maneuver, comfort, convenience, and safety. LOS for roadway
segments varies between LOS A, with no congestion and free flow, and LOS F, with
considerable congestion and forced or breakdown of flow (Table 2.11-1a, Roadway Segment
Level of Service Definitions, Table 2.11-1b, SANTEC/ITE Measure of Significant Project
Traffic Impacts, and Appendix M). For intersections, LOS is a measure of delay. It is based on
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-3
the elapsed time between when a vehicle stops at the end of a queue and when it departs from the
stop line. For signalized intersections, LOS A indicates a delay of less than 10 seconds, while
LOS F indicates a delay of greater than 80 seconds (Table 2.11-2, Signalized Intersection Level
of Service). More detailed information is included in the Traffic Impact Study, Appendix M of
this EIR.
Existing conditions pertinent to the proposed project are those conditions within the defined
traffic study area. County of San Diego Guidelines specify that a roadway segment or
intersection should be analyzed if it will carry 25 Peak Hour peak direction project trips or more.
The San Diego Association of Governments (SANDAG) has a Congestion Management
Program (CMP) to identify the regionally significant circulation system. The CMP requires
projects generating greater than 2,400 average daily trips to analyze CMP roadways within the
study area. CMP roadways within this study area include SR 76 and I-15, and these are included
in the Traffic Impact Study.
2.11.1.2 Roadway Segments
The resulting study area includes all of SR 76 between E. Vista Way (approximately 8 miles
west of I-15) and Cole Grade Road (approximately 15 miles east of I-15 and approximately 9
miles east of the proposed project) (Figure 2.11-1). The study area also includes two other road
segments just east of the project site: Pala Temecula Road and W. Pala Mission Road.
This approximately 23-mile stretch of SR 76 is broken into 16 segments (Figure 2.11-1). Of the
16 segments, six are west of I-15:
Between west of E. Vista Way and N. River Road (currently LOS F )
Between N. River Road and Camino Del Rey/Olive Hill Road (LOS F)
Between Camino Del Rey/Olive Hill Road and S. Mission Road (LOS F)
Between S. Mission Road and Gird Road (LOS F)
Between Gird Road and Old Highway 395 (LOS F)
Between Old Highway 395 and the I-15 ramps (LOS D).
The seventh segment of SR 76 is that stretch between the I-15 ramps, currently operating at LOS E.
The study area has nine segments of SR 76 east of I-15 (Figure 2-11-1):
1. Between the I-15 ramps and Pankey Road (currently LOS A)
2. Between Pankey Road and Horse Ranch Creek Road (LOS A)
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-4
3. Between Horse Ranch Creek Road and Rice Canyon Road (LOS C)
4. Between Rice Canyon and Couser Canyon Road (LOS C)
5. Between Couser Canyon and W. Pala Mission Road (LOS C)
6. Between W. Pala Mission Road and E. Pala Mission Road (LOS C)
7. Between E. Pala Mission Road and Lilac Road (LOS C)
8. Between Lilac Road and Adams Drive (LOS C)
9. Between Adams Drive and Cole Grade Road (currently LOS C).
In addition to the SR 76 segments, the study area has two other road segments (Figure 2.11-1):
1. W. Pala Mission Road between SR 76 and Pala Temecula Road (LOS C)
2. Pala Temecula Road north of SR 76 (currently LOS D).
Two freeway mainlines are within the study area: I-15 north of SR 76 and I-15 south of SR 76.
2.11.1.3 Intersections
Twenty intersections met the criteria for inclusion in the study area. Of those 20 intersections, 19 are
intersections with SR 76. And of those 19 SR 76 intersections, six are west of I-15 (Figure 2.11-1):
1. SR 76 and E. Vista Way (AM Peak Hour LOS F, PM Peak Hour LOS E)
2. SR 76 and N. River Road (AM Peak Hour LOS C, PM Peak Hour LOS C)
3. SR 76 and Camino Del Rey / Olive Hill Road (AM Peak Hour LOS D, PM Peak Hour LOS D
4. SR 76 and S. Mission Road (AM Peak Hour LOS C, PM Peak Hour LOS C)
5. SR 76 and Gird Road (AM Peak Hour LOS B, PM Peak Hour LOS B)
6. SR 76 and Old Highway 395 (AM Peak Hour LOS C, PM Peak Hour LOS C).
Two of the intersections are at I-15:
1. SR 76 and I-15 southbound ramps (AM Peak Hour LOS C, PM Peak Hour LOS E)
2. SR 76 and I-15 northbound ramps (AM Peak Hour LOS C, PM Peak Hour LOS D).
The remaining 11 intersections with SR 76 are east of I-15 (Figure 2.11-1):
SR 76 and Pankey Road (AM Peak Hour LOS B, PM Peak Hour LOS B)
SR 76 and Horse Ranch Creek Road (NA)
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-5
SR 76 and Rice Canyon Road (AM Peak Hour LOS B, PM Peak Hour LOS B)
SR 76 and Couser Canyon Road (AM Peak Hour LOS B, PM Peak Hour LOS B)
SR 76 and Project Entry (AM Peak Hour LOS A, PM Peak Hour LOS A)
SR 76 and W. Pala Mission Road (AM Peak Hour LOS C, PM Peak Hour LOS C)
SR 76 and Brittain Road (AM Peak Hour LOS A, PM Peak Hour LOS B)
SR 76 and E. Pala Mission Road (AM Peak Hour LOS B, PM Peak Hour LOS C)
SR 76 and Lilac Road (AM Peak Hour LOS B, PM Peak Hour LOS B)
SR 76 and Adams Drive (AM Peak Hour LOS B, PM Peak Hour LOS B)
SR 76 and Cole Grade Road (AM Peak Hour LOS C, PM Peak Hour LOS C).
The twentieth intersection is located at W. Pala Mission Road and Pala Temecula Road. It has an
existing AM Peak Hour LOS A, and an existing PM Peak Hour LOS B.
2.11.1.4 Trip Generation
Trip generation is a measure or forecast of the number of trips that begin or end at the project site
and is a function of the extent and types of land use proposed as part of a proposed project
(Appendix M). Vehicular traffic generation characteristics for projects are estimated based on
established rates. These rates identify the probable traffic generation of various land uses based
studies of developments in comparable settings. The rates used in this analysis are determined
based on rates contained in the (SANDAG) Brief Guide of Vehicular Traffic Generation Rates for
the San Diego Region (2002). This manual provides standards and recommendations for the
probable traffic generation of various land uses based upon local, regional and nationwide
studies of existing developments in comparable settings. For the proposed project, each single
family dwelling unit is expected to generate 10 trips per day; each multifamily unit is expected to
generate eight trips per day; the park is expected to generate 50 trips per acre per day; and the
fire station is expected to generate 50 trips per day. These trips are shown in Table 2.11-3,
Project Trip Generation, and include a breakdown of the number of trips expected during the AM
and PM Peak Hour periods. The AM Peak Hour period is between 7 a.m. and 9 a.m., and the PM
Peak Hour is between 4 p.m. and 6 p.m. These periods are the times during which the largest
numbers of vehicles are entering and exiting the project site. Because of the multiple factors and
ensuing rounding of numbers done by predictive models, rows and columns may not total
exactly. As seen in Table 2.11-3, the proposed project is predicted to produce 7,570 daily trips.
During the AM Peak Hour, 178 trips are predicted to enter the project site, and 443 trips are
predicted to exit the project site. During the PM Peak Hour, 524 trips are predicted to enter the
project site, and 234 trips are predicted to exit the project site.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-6
2.11.1.5 Trip Distribution and Assignment
Trip distribution and assignment is the process of identifying probable trip destinations, and then
the directions and routes that traffic will affect. Once the proposed developments trips have been
estimated, they are assigned to the study area network. The trip distribution and assignment for
this project is based on SANDAG’s computerized travel forecast model (Series 11 Select Zone
analysis). All project traffic moves on to SR 76, and then travels either east or west on SR 76.
The project has many potential local services to link up to in the community of Pala, which
begins half a mile to the east.
Local factors affecting trip destinations are potential employment at the Pala Casino and
additional casinos to the east; shopping at the casinos and the stores in the Community of
Pala; and trips to the schools, churches, and play fields in the Community of Pala. These
services include:
Employment at Pala Casino (or further east at Pauma Casino);
Education at Vivian Banks Charter School, Ashwet Patia School, and Pala State Preschool;
Limited shopping at Pala Store (including produce, groceries, sundries), Pala Minimart and
additional shopping and entertainment at the casino;
Other services including a Catholic Church, the Pala Buffet, a fire station, Wells Fargo
Bank, play fields.
A detailed breakdown of predicted trips is provided in Figures 1.3 through 1.6 in the Traffic
Impact Study (Appendix M). The maximum number of trips predicted to leave the project site
onto SR 76 during one time period is the 443 trips of the AM Peak Hour (Table 2.11-3).
Projections of this traffic show 273 trips turning west on SR 76, and 170 trips turning east on SR
76. Some of these westbound 273 trips turn onto intersecting streets (Couser Canyon Road, Rice
Canyon Road, Horse Ranch Creek Road, Pankey Road; see Figure 2.11-1). At I-15, 152 trips
remain on SR 76. Of these 152 trips, 10 are predicted to go north on I-15, and 101 trips turn
south onto I-15. The remaining 51 trips continue west on SR 76.
The bulk of the predicted 170 project traffic trips that turn east on SR 76, then turn into the Pala
Casino, into the Community of Pala, or north on Pala Temecula Road towards Temecula. The
remaining 35 trips continue east on SR 76.
2.11.1.6 Level of Service
Level of Service (LOS) designations comprise a professional industry standard by which the
operating condition of a given roadway, state route, freeway segment, or intersection is
measured. LOS designation is reported differently for signalized and unsignalized intersections,
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-7
as well as for roadway segments. LOS is defined using letter designations from “A” to “F,”
wherein LOS A represents the best operating conditions and LOS F represents the worst
operating conditions. The County’s Average Daily Traffic (ADT) is the number of vehicles that
pass a point on a roadway over a 24-hour period. The increase in ADT that would result in a
LOS E and LOS F for different roadway designations is shown below:
For LOS E
o Two-lane road – 200 ADT increase
o Four-lane road – 400 ADT increase
o Six-lane road – 600 ADT increase
o Two-lane highway – 325 ADT increase
For LOS F
o Two-lane road – 100 ADT increase
o Four-lane road – 200 ADT increase
o Six-lane road – 300 ADT increase
o Two-lane highway – 225 ADT increase
The volume-to-capacity ratio (V/C) is a measure of traffic demand on state and local facilities
(expressed as volume) compared to its traffic-carrying capacity. In evaluating the performance of
roadway segments under the existing conditions, V/C is considered together with LOS.
2.11.1.7 Regulatory Setting
Federal
2000 Highway Capacity Manual
Prepared by the Transportation Research Board, the 2000 HCM is a joint effort between the
Transportation Research Board, Federal Highway Administration (FHWA), and American
Association of State Highway and Transportation Officials to provide concepts, guidelines,
and computational procedures for calculating capacity and quality of service for highway
facilities, including freeways, intersections (signalized and unsignalized), and rural
highways. In addition, the 2000 HCM addresses the effects of transit, pedestrians, and
bicycles on transportation system performance.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-8
State Transportation Improvement Program
The California STIP, approved by the U.S. Department of Transportation in October 2006, is a
multi-year, statewide, intermodal program of transportation projects that is consistent with the
statewide transportation plan and planning processes, metropolitan plans, and Title 23 of the
Code of Federal Regulations. The STIP is prepared by Caltrans in cooperation with the
Metropolitan Planning Organizations (MPOs) and the regional transportation planning agencies.
In San Diego County, the MPO and regional transportation planning agency is SANDAG. The
STIP contains all capital and non- capital transportation projects or identified phases of
transportation projects for funding under the Federal Transit Act and Title 23 of the U.S. Code,
including federally funded projects.
San Diego Association of Governments Congestion Management Program (CMP)
The purpose of a CMP is to monitor the performance of a region’s transportation system, develop
programs to address near- and long-term congestion, and better integrate transportation and land use
planning. Within SANDAG’s CMP, the Land Use Analysis Program requires assessment of impacts
to state highways and regionally significant arterials from projects that generate 2,400 or more ADT
or 200 or more Peak Hour trips. I-15 and SR 76 are CMP roadways.
County of San Diego General Plan, Mobility Element
The Mobility Element establishes policies and implementation measures for the assessment and
mitigation of traffic impacts of new development. An objective in the Transportation Section is
the provision of LOS D or better on County Mobility Element Roads; LOS D is an off-site
mitigation limit for discretionary projects. If the existing LOS is D, a LOS of D may be allowed.
Projects that significantly increase congestion of roads already operating at LOS E or F must
provide mitigation. Mitigation can consist of road improvements, or a fair share contribution to
an established program or project to mitigate the project’s impacts. Select applicable General
Plan policies are listed below:
M-1 Balanced Road Network. A safe and efficient road network that balances regional
travel needs with the travel requirements and preferences of local communities.
M-1.2 Treatment of High-Volume Roadways. Consider narrower rights-of-way, flexibility
in design standards, and lower design speeds in areas planned for substantial
development in order to avoid bisecting communities or town centers. Reduce noise,
air, and visual impacts of new freeways, regional arterials, and Mobility Element
roads, through landscaping, design, and/or careful location of facilities.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-9
M-2 Responding to Physical Constraints and Preservation Goals. A road network that
provides adequate capacity to reasonably accommodate both planned land uses and
regional traffic patterns, while supporting other General Plan goals such as providing
environmental protections and enhancing community character.
M-2.1 Level of Service Criteria. Require development projects to provide associated road
improvements necessary to achieve a level of service of “D” or higher on all Mobility
Element roads except for those where a failing level of service has been accepted by
the County pursuant to the criteria specifically identified in the accompanying text
box (Criteria for Accepting a Road Classification with Level of Service E/F). When
development is proposed on roads where a failing level of service has been accepted,
require feasible mitigation in the form of road improvements or a fair share
contribution to a road improvement program, consistent with the Mobility Element
road network.
M-2.2 Access to Mobility Element Designated Roads. Minimize direct access points to
Mobility Element roads from driveways and other non-through roads to maintain the
capacity and improve traffic operations.
M-2.3 Environmentally Sensitive Road Design. Locate and design public and private roads
to minimize impacts to significant biological and other environmental and visual
resources. Avoid road alignments through floodplains to minimize impacts on
floodplain habitats and limit the need for constructing flood control measures. Design
new roads to maintain wildlife movement and retrofit existing roads for that purpose.
Utilize fencing to reduce road kill and to direct animals to under crossings.
M-3 Transportation Facility Development. New or expanded transportation
facilities that are phased with and equitably funded by the development that
necessitates their construction.
M-3.2 Traffic Impact Mitigation. Require development to contribute its fair share toward
financing transportation facilities, including mitigating the associated direct and
cumulative traffic impacts caused by their project on both the local and regional road
networks. Transportation facilities include road networks and related transit,
pedestrian and bicycle facilities, and equestrian.
M-3.3 Multiple Ingress and Egress. Require development to provide multiple ingress/egress
routes in conformance with State law and local regulations.
M-4.3 Rural Roads Compatible with Rural Character. Design and construct public roads to
meet travel demands in Semi-Rural and Rural Lands that are consistent with rural
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-10
character while safely accommodating transit stops when deemed necessary, along
with bicyclists, pedestrians, and equestrians. Where feasible, utilize rural road design
features (e.g., no curb and gutter improvements) to maintain community character.
[See applicable community plan for possible relevant policies.]
M-4.5 Context Sensitive Road Design. Design and construct roads that are compatible with
the local terrain and the uses, scale and pattern of the surrounding development.
Provide wildlife crossings in road design and construction where it would minimize
impacts in wildlife corridors.
M-5.2 Impact Mitigation for New Roadways and Improvements. Coordinate with Caltrans
to mitigate negative impacts from existing, expanded, or new State freeways or
highways and to reduce impacts of road improvements and/or design modifications to
State facilities on adjacent communities.
Public and Private Road Standards
The County has road standards for both public and private roadways. These standards provide
minimum design and construction requirements for roadways. The Mobility Element includes
LOS standards for Mobility Element roads, which are based upon typical peak traffic periods.
Non-Mobility Element roads do not include LOS standards, but target design capacities.
Mobility Element roads are constructed based on the Public Road Standards. Private roads are
constructed based on the Private Road Standards and do not include LOS standards, but are
based on average daily trips (ADT).
County of San Diego Transportation Impact Fee Program/Ordinance
The Transportation Impact Fee (TIF) Program requires payment of fees as a fair share
contribution towards the construction costs of the planned transportation facilities that are
affected by a proposed development to mitigate cumulative impacts. The primary purpose of the
TIF is to fund the construction of identified roadway facilities needed to reduce or mitigate
projected cumulative traffic impacts and to allocate the costs of these roadway facilities
proportionally among future developing properties based upon their individual cumulative traffic
impacts (County Guidelines for Determining Significance-Traffic). TIF fees are collected as a
condition of approval of a project or prior to issuance of a development permit, typically a
building permit. Existing deficiencies in transportation infrastructure cannot be financed with
these fees. Mitigation of direct impacts of future development is the responsibility of individual
projects. The TIF is designed to be updated when there is an adopted change to the General Plan
land uses and/or Mobility Element. As stated in the TIF program, “[t]here is a reasonable
relationship between the amount of the fee and the cost of transportation facilities, or portions
thereof, attributable to future development because the TIF is derived from a TDU formula that
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-11
considers trip generation rates and vehicle miles traveled by land use type to correlate impact to
specific development types” (Section 77.203[5]).
2.11.2 Analysis of Project Effects and Determination as to Significance
2.11.2.1 Roadway Segments
Guidelines for Determination of Significance
The County of San Diego’s Guidelines for Determining Significance and Report Format and
Content Requirements – Transportation and Traffic (County of San Diego 2011) states that traffic
volume increases from projects would result in a significant traffic volume or LOS traffic impact if:
The additional or redistributed ADT generated by the proposed land development project will
cause on-site Circulation Element Roads to operate below LOS C during peak traffic hours;
The additional or redistributed ADT generated by the proposed project will significantly
increase congestion on a Circulation Element Road or State Highway currently operating at
LOS E or LOS F, or will cause a Circulation Element Road or State Highway to operate at
a LOS E or LOS F as a result of the proposed project as identified in Table 2.11-1; or
The additional or redistributed ADT generated by the proposed project will cause a
residential street to exceed its design capacity.
Caltrans Facilities
As shown in Table 2.11-1.5, Measures of Significant Project Impacts to Congestion: Allowable
Increases on Two-Lane Highways with Signalized Intersection Spacing under 1 Mile, the
SANTEC/ITE Guidelines were utilized to determine traffic impacts to facilities under the
jurisdiction of Caltrans.
Two-Lane Highways with Signalized Intersection Spacing Over 1 Mile
Traffic volume increases from public or private projects that result in one or more of the
following criteria will have a significant traffic volume or level of service traffic impact on a
two-lane highway facility with signalized intersection spacing greater than 1 mile:
The additional or redistributed ADT generated by the proposed project will significantly
increase congestion on a two-lane highway segment currently operating at LOS E or LOS
F, as identified in Table 2.11-4, Measures of Significant Project Impacts to Congestion:
Allowable Increases On Two-Lane Highways with Signalized Intersection Spacing over
1 Mile, or will cause a two-lane highway segment to operate at LOS E or LOS F as a
result of the proposed project.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-12
Two-Lane Highways with Signalized Intersection Spacing Under 1 Mile
Traffic volume increases from public or private projects that result in one or more of the
following criteria will have a significant traffic volume or level of service traffic impact on a
two-lane highway facility with signalized intersection spacing less than 1 mile:
The additional or redistributed ADT generated by the proposed project will significantly
increase congestion on a two-lane highway segment currently operating at LOS E or LOS
F, as identified in Table 2.11-5, or will cause a two-lane highway segment to operate at
LOS E or LOS F as a result of the proposed project.
Analysis
Construction
Construction of the proposed project would result in the temporary addition of vehicles on
surrounding circulation network, primarily for travel to and from the site. As cut and fill for
grading is expected to be balanced on-site, no dirt import or export trucks would travel to and
from the project site. It is not estimated that the project would require any street closures during
construction. There are no sidewalks in the area, as such, sidewalk closures would not be an
issue. In addition, construction impacts on the area are projected to be minimal since
construction vehicles are estimated to contribute fewer vehicles during the peak hours than the
project would after completion. As construction would result in the temporary addition of
minimal vehicles to the surrounding circulation network, impacts would be less than significant.
Operation
The thresholds of significance described previously are in terms of the allowable increase in
traffic, which also relates directly to the change in the volume to capacity ratio. Where roadways
segments operate at LOS D or better, impacts are not considered significant.
Table 2.11-6, Summary of Roadway Segment Conditions, contains information on the 18
roadway segments identified in the study area. The v/c ratios and resulting LOS are listed for
four scenarios: Existing Conditions establishes the baseline traffic operations within the study
area. Existing Conditions Plus the Project represents the existing transportation network with the
addition of traffic from the proposed project. Existing Conditions Plus Cumulative Conditions
represents cumulative traffic conditions (the existing baseline traffic with traffic from
foreseeable land development projects, without the project). Existing Conditions Plus the Project
Plus Cumulative Conditions represents cumulative traffic conditions (the existing baseline traffic
with traffic from foreseeable land development projects, and traffic from buildout of the
proposed project.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-13
Existing Plus Project (Direct Impacts)
The Existing Plus Project analysis includes existing traffic volumes (2012 baseline) with the
addition of the traffic generated by the project (Table 2.11-7, Summary of Mitigated Roadway
Segments – Existing Plus Project Conditions). No significant impacts to I-15 either north or
south would occur (Appendix M). The following six roadway segments of SR 76 are shown to
operate at LOS E or F under both Existing Conditions and Existing Conditions Plus the Project:
Impact TR-1 SR 76 from west of E. Vista Way to N. River Road
Impact TR-2 SR 76 from N. River Road to Camino Del Rey
Impact TR-3 SR 76 from Camino Del Rey to S. Mission Road
Impact TR-4 SR 76 from S. Mission Road to Gird Road
Impact TR-5 SR 76 from Gird Road to Old Highway 395
Impact TR-6 SR 76 between the I-15 northbound and southbound ramps
The first five of these segments operate at LOS F in the existing baseline condition and would
continue at LOS F with the proposed project, with a worsening of the v/c ratio. The last segment
presently operates at LOS E in the existing baseline condition and with the proposed project
would operate at LOS F, with a worsening of the v/c ratio (Table 2.11-6).
2.11.2.2 Intersections
Guidelines for Determination of Significance
The County of San Diego’s Guidelines for Determining Significance and Report Format and
Content Requirements: Transportation and Traffic (County of San Diego 2011) states that traffic
volume increases from projects would result in a significant traffic volume or LOS traffic impact
on a signalized intersection if:
The additional or redistributed ADT generated by the proposed project will significantly
increase congestion on a signalized intersection currently operating at LOS E or LOS F, or
will cause a signalized intersection to operate at a LOS E or LOS F; or
Based upon an evaluation of existing accident rates, the signal priority list, intersection
geometrics, proximity of adjacent driveways, sight distance, or other factors, the project
would significantly impact the operations of the intersection.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-14
The County of San Diego’s Guidelines for Determining Significance and Report Format and
Content Requirements: Transportation and Traffic (County of San Diego 2011) states that
traffic volume increases from projects would result in a significant impact to an unsignalized
intersection if:
The additional or redistributed ADT generated by the proposed project will add 21 or
more Peak Hour trips to a critical movement of an unsignalized intersection and cause
an unsignalized intersection to operate below LOS D, or
The additional or redistributed ADT generated by the proposed project will add 21 or
more Peak Hour trips to a critical movement of an unsignalized intersection currently
operating at LOS E, or
The additional or redistributed ADT generated by the proposed project will add six or
more Peak Hour trips to a critical movement of an unsignalized intersection and cause
the unsignalized intersection to operate at LOS F, or
The additional or redistributed ADT generated by the proposed project will add six or
more Peak Hour trips to a critical movement of an unsignalized intersection currently
operating at LOS F, or
Based upon an evaluation of existing accident rates, the signal priority list, intersection
geometrics, proximity of adjacent driveways, sight distance, or other factors, the project
would significantly impact the operations of the intersection.
Analysis
Construction
Construction of the proposed project would result in the temporary addition of vehicles on
surrounding circulation network, primarily for travel to and from the site. As cut and fill for
grading is expected to be balanced on-site, no dirt import or export trucks would travel to and
from the project site. It is not estimated that the project would require any street closures during
construction. There are no sidewalks in the area, as such, sidewalk closures would not be an
issue. In addition, construction impacts on the area are projected to be minimal since
construction vehicles are estimated to contribute fewer vehicles during the peak hours than the
project would after completion. As construction would result in the temporary addition of
minimal vehicles to the surrounding circulation network, impacts would be less than significant.
Operation
The thresholds of significance described previously are in terms of the allowable increase in
traffic, which also relates directly to the change in the volume to capacity ratio. Where
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-15
intersections operate at LOS D or better, impacts are not considered significant. Tables 2.11-8
and 2.11-9 give a summary of intersection performance during the AM and PM Peak Hours, for
Existing Conditions, Existing Conditions Plus the Project, Existing Plus Cumulative and Existing
Plus Cumulative Plus Project.
Existing Plus Project (Direct Impacts)
Under the Existing Plus Project condition (2012 baseline), the project would have the following
significant impacts to four intersections as described below (Table 2.11-10, Summary of
Mitigated Intersections – Existing Plus Project Conditions):
Impact TR-7 SR 76/E. Vista Way. This intersection operated at LOS F for the AM Peak Hour
and at LOS E for the PM Peak Hour. Project traffic creates additional significant
delays at both Peak Hours by increasing delays over two seconds.
Impact TR-8 SR 76/I-15 southbound ramps. This intersection operated at LOS E for the PM
Peak Hour. Project traffic creates additional significant delay in the PM Peak
Hour by increasing delays over 12 seconds.
Impact TR-9 SR 76/I-15 northbound ramps. This intersection operated at LOS D for the
PM Peak Hour. Project traffic creates additional significant delay in the PM
Peak Hour resulting in an LOS of E with additional delays over six seconds.
Impact TR-10 SR 76/Project driveway (Figure 1-12, Circulation Plan). Analysis of this
intersection shows that it will fulfill the warrant for signalization (Appendix M).
2.11.2.3 Hazards and Alternative Transportation
Guidelines for Determination of Significance
The County of San Diego’s Guidelines for Determining Significance and Report Format
and Content Requirements: Transportation and Traffic (County of San Diego 2011)
states that a significant transportation or traffic impact may occur if the project causes a
transportation hazard. The determination of significant hazards to an existing
transportation design feature shall be on a case-by-case basis, considering the following
factors: Design features/physical configurations of access roads may adversely affect the
safe movement of all users along the roadway.
The percentage or magnitude of increased traffic on the road due to the proposed project
may affect the safety of the roadway.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-16
The physical conditions of the project site and surrounding area, such as curves,
slopes, walls, landscaping or other barriers, may result in conflicts with other users or
stationary objects.
Conformance of existing and proposed roads to the requirements of the private or public
road standards, as applicable.
The County of San Diego’s Guidelines for Determining Significance and Report Format and
Content Requirements: Transportation and Traffic (County of San Diego 2011) the
determination of significant hazards to pedestrians or bicyclists shall be on a case-by-case basis,
considering the following factors:
Design features/physical configurations on a road segment or at an intersection that may
adversely affect the visibility of pedestrians or bicyclists to drivers entering and exiting
the site, and the visibility of cars to pedestrians and bicyclists.
The amount of pedestrian activity at the project access points that may adversely affect
pedestrian safety.
The preclusion or substantial hindrance of the provision of a planned bike lane or
pedestrian facility on a roadway adjacent to the project site.
The percentage or magnitude of increased traffic on the road due to the proposed project
that may adversely affect pedestrian and bicycle safety.
The physical conditions of the project site and surrounding area, such as curves,
slopes, walls, landscaping or other barriers that may result in vehicle/pedestrian,
vehicle/bicycle conflicts.
Conformance of existing and proposed roads to the requirements of the private or public
road standards, as applicable.
The potential for a substantial increase in pedestrian or bicycle activity without the
presence of adequate facilities.
Analysis
Hazards
The proposed project would include numerous roadway and circulation improvements including:
internal residential streets, internal intersections, off-site intersection improvements, pedestrian
walkways and sidewalks, equestrian trails, and bicycle facilities as described in Chapter 1,
Project Description. All internal circulation improvements conform with the would comply with
the County’s Private Road Standards (County of San Diego 2012) and applicable roadway/
highway design standards/design manuals as they apply to safety of motorists, pedestrians, and
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-17
bicyclists. The County Public Road Standards are intended to “provide for the service and
protection of the public. No design exceptions are being requested for this project. The project is
consistent with the County Mobility Element Goal 4, Safe and Compatible Roads. Relevant
policies pursuant to Goal M-4 and the project’s consistency with each are listed below:
Policy M-4.1 (Walkable Village Roads), the project would provide a multi-modal
transportation system, consisting of private roads, bicycle paths, pedestrian and equestrian
trails is proposed, to support both the growth within the SPA and the adjoining existing and
planned communities. The project also includes a network of pathways and trails that
meander along streets and within the open space areas. The Specific Plan includes
objectives and policies to develop a comprehensive transportation system that would
provide safe and efficient movement of people with in the SPA, the Pala Pauma
Subregional Area, and the regional circulation network, while protecting sensitive
environmental resources and community character.
Policy M-4.2 (Interconnected Local Roads) requires the provision of an
interconnected and appropriately scaled local public road network. The project area
would be accessed by a central entry road (Figures 1-12 and 1-13 (Community Entry
Plan)) that would be constructed north of SR 76. An all-way traffic signal would be
installed at the intersection. The entry road would be a public road from SR 76 to the
project’s gate. Additionally, a 350-foot long and 12-foot wide acceleration/
deceleration lane is proposed adjacent to the project’s main entry. Conceptual plans
for neighborhood entry roads as well as primary and secondary theme roads are
shown in Figures 1-14, 1-15, and 1-16 (Road Sections – Entry, Residential Internal,
and Alley). All other on-site roads would be private roads built to County Private
Road Standards with maintenance funded by the HOA. The on-site roads would still
be interconnected with the public roadway system in that the on-site roadway allows
traffic from off-site to enter the project, and also provide emergency evacuation
routes to the adjacent SR 76.
Policy M-4.4 (Accommodate Emergency Vehicles) requires the design and construction
of public and private roads to allow for necessary access by appropriately sized fire
apparatus and emergency vehicles while accommodating outgoing vehicles with residents
evacuating from the project. Roads within the project site are designed to accommodate
emergency vehicles and also allow residents to evacuate efficiently if necessary. Although
the project includes gated access points throughout the road system would be interconnected
and would provide at least two ways in and out for all residents as required by current safety
regulations. Emergency access would be provided by two roads on the eastern and western
boundaries connecting to SR 76. Both of these alternate access routes would be gated and
will triggered by either a buried sensor or an optical sensor would be used for egress. For
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-18
ingress, keypads and remotes would be used. The emergency accesses proposed on the
eastern and western boundaries along SR 76 would only be used for emergency purposes.
Policy M-4.6 (Context Sensitive Road Design) requires the design and construction of
roads that are compatible with the local terrain and the uses, scale and pattern of the
surrounding development. Development has been generally clustered to confine
grading to the flatter areas of the property (140 acres of 0-15 percent slopes) and the
pattern of the roads within the project site would follow the site’s terrain while still
providing a safe and efficient road network. The project will provide a public multi-
use trail (0.5 mile) along the project’s frontage which would be built and dedicated to
the County and maintained by the County. This multi-use public trail is situated along
the southern boundary of the project adjacent to SR 76 and would be 8 feet wide
within a 15-foot-wide public easement. The trail would be constructed of stabilized
decomposed granite or other material deemed suitable by the County.
Policy M-4.6 (Interjurisdictional Coordination) requires coordination with adjacent
jurisdictions so that roads that cross jurisdictional boundaries are designed to provide
consistent cross-section and capacity. To the extent practical, coordinate with adjacent
jurisdictions to construct road improvements concurrently or sequentially to optimize and
maintain road capacity. Over the past 5 years, the Warner Ranch project team has been
closely coordinating with CalTrans. The project team has incorporated recommendations
and safety measures into the proposed project related improvements, including the
proposed project frontage improvements, signalization, and off-site intersection
improvements. Off-site improvements would be made or funds contributed to help pay
for future improvements for two intersections to mitigate project traffic impacts.
As described above, the project gains its access from SR 76 which has been constructed in accordance
with Caltrans Standards. Overall, the road network design for the project would provide adequate
ingress and egress for residents as well as emergency access, safe trail system, and conform to
Goal M-4 of the General Plan Mobility Element. With conformance to applicable safety design
standards as set forth by the County and Caltrans, as well as close coordination between the
project team and Caltrans, impacts related to roadway hazards as a result of the project would be
less than significant.
Alternative Transportation
A multi-modal transportation system, consisting of public and private roads, bicycle paths,
pedestrian and equestrian trails is proposed, to support both the growth within the SPA and the
adjoining existing and planned communities. The project would develop a comprehensive
transportation system that would provide safe and efficient movement of people with in the
project site, the Pala Pauma Subregional Area, and the regional circulation network.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-19
Additionally, as stated in Chapter 1, Project Description, the project proposes housing types that
would be affordable to the workforce in the area; such housing is presently in short supply. A
better balance of job/housing should reduce commuting and overall miles traveled, as well as
vehicles on the roadways.
The project would not interfere with the General Plan’s overall intent to reduce the demand of
roadways by provision of alternative transportation or any other means. Therefore, the project
would not conflict with the alternative transportation policies of the General Plan and impacts
would be less than significant.
2.11.2.4 Mobility Element
This section discusses the correlation between the General Plan Land Use Element and Mobility
Element at build-out of the Land Use Element as amended by the proposed project. It also
provides a General Plan conformance discussion including consistency with Mobility Element
Policy 2.1, which addresses balancing adequate road capacity to reasonably accommodate build-
out of the Land Use Element, with the need to support other General Plan goals such as
providing environmental protections. Policy 2.1 acknowledges that the preservation of valuable
resources may outweigh the benefits of road improvements. Therefore, a lower LOS along
specified roadways may be acceptable. Table M-4 of the Mobility Element identifies the
deficient roadways and describes the rationale for accepting deficient roadway segments.
Mobility Element Policy 2.1 requires development projects to provide associated road
improvements necessary to achieve a level of service of “D” or higher on all Mobility Element
roads except for those where a failing level of service has been accepted by the County pursuant
to the specified criteria. The applicable situations for accepting a road classification where a LOS
E or F is forecast includes those instances when the adverse impacts of adding travel lanes do not
justify the resulting benefit of increased traffic capacity. This would include the following
relevant situations:
When marginal deficiencies are characterized along a short segment of a road and
classifying the road with a designation that would add travel lanes for the entire road would
be excessive; or
When adding travel lanes to a road would adversely impact environmental and cultural
resources or in areas with steep slopes where widening roads would require massive
grading, which would result in adverse environmental impacts and other degradation of the
physical environment.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-20
Build-out Under the General Plan
As shown in Table 6-2 of Appendix M, the following roadway segments of SR 76 are projected
to operate at substandard LOS E/F under buildout of the General Plan without the project:
N. River Road to Camino Del Rey – LOS E
Camino Del Rey and S. Mission Road – LOS F
S. Mission Road to Gird Road – LOS F
Gird Road to Old Highway 395 – LOS E
Old Highway 395 to the I-15 southbound ramp – LOS E
Couser Canyon Road and W. Pala Mission Road – LOS F
W. Pala Mission Road to E. Pala Mission Road – LOS E
E. Pala Mission Road to Lilac Road – LOS E
Adams Drive to Cole Grade Road – LOS E
SR 76 east of Couser Canyon Road was downgraded from a planned four-lane road to a two-lane
road with approval of the General Plan in 2011, as it was determined that widening the roadway
to four lanes would result in adverse environmental impacts and degradation of the physical
environment. With this, an approximately 2.2 miles stretch of SR 76 between Pala del Norte and
Sixth Street in Pala (which includes Warner Ranch) was accepted at LOS E/F in the General
Plan’s Mobility Element. The project would increase the stretch of SR 76 at LOS E/F from the
current 2.2 miles to 8.2 miles, and would therefore have to amend Table M-4 of the Mobility
Element to include the added 5.9-mile deficiency, as shown on Figure 2.11-2, Proposed Mobility
Element Network Amendment. With the addition of the project to the General Plan build-out
condition, the following roadway segments would operate at substandard LOS E or F (Table 6-2
of Appendix M):
N. River Road to Camino Del Rey. LOS F; and the project would add 528 ADT
Camino Del Rey and S. Mission Road. LOS F; and the project would add 594 ADT
S. Mission Road to Gird Road. LOS F; and the project would add 683 ADT
Gird Road to Old Highway 395. LOS E; and the project would add 773 ADT
Old Highway 395 to the I-15 southbound ramp. LOS F; and the project would add
855 ADT
Horse Ranch Creek Road to Rice Canyon Road. LOS E; and the project would add
4,069 ADT
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-21
Rice Canyon Road and Couser Canyon Road. LOS E; and the project would add 4,426 ADT
Couser Canyon Road and W. Pala Mission Road. LOS F; and the project would add
4,581 ADT
W. Pala Mission Road to E. Pala Mission Road. LOS F; and the project would add
594 ADT
E. Pala Mission Road to Lilac Road. LOS E; and the project would add 594 ADT
Adams Drive to Cole Grade Road. LOS E; and the project would add 363 ADT
The easternmost portion of SR 76 impacted by the project is Cole Grade Road which is 11 miles
east of Couser Canyon Road (Figure 2.11-1). This portion includes the impacted intersections of
SR 76/E. Pala Mission Road, SR 76/Lilac Road, and SR 76/Cole Grade Road. The project would
provide abutting improvements at the project frontage. However, this would not fully mitigate
the contribution to cumulative impacts. To fully alleviate the impacts, SR 76 would need to be
widened with two additional lanes for the length of the 8.2 miles of deficient highway and
possibly more to avoid traffic bottlenecks. However this road is not under the jurisdiction and
control of the County.
The planned classification of two lanes with LOS E/F acceptance is based on the County General
Plan land uses. Without the project’s proposed General Plan Amendment to accept the
deficiencies on SR 76, mitigation to four lanes would be appropriate, but there is no Caltrans’ or
Pala Reservation project funding or program currently in place for adding additional lanes or
other improvements to SR 76 in any part of this 11-mile section for the applicant to make a fair
share contribution or build.
The project would amend the Land Use Element to increase density on the project site, which
would generate more traffic than was included in the County’s General Plan forecast for the
roadway segments identified above. Several of these roadway segments would operate at LOS E
or F without the project at build-out of the General Plan. As noted above, the General Plan
accepts a 2.2 mile portion of SR 76 east of the project between Pala del Norte and Sixth Street in
Pala (which includes the frontage of Warner Ranch) to a LOS E/F in the General Plan’s Mobility
Element. The project would add additional traffic SR 76 that was not considered when the
Mobility Element was adopted. In particular, the project would increase the stretch of SR 76 that
would operate at LOS E/F from the current 2.2 miles to 8.2 miles. Therefore, if the project’s
Land Use density increases, the Mobility Element must also be amended to maintain the
correlation between the Land Use Element and Mobility Element. The 8.2 miles of SR 76 that
would be operating at a deficient operating capacity would require either an upgrade to the
designated roadway classifications or a determination that the further reduction in LOS at build-
out would be acceptable.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-22
Pursuant to Mobility Element Policy 2.1, a lower LOS along specified roadways may be
acceptable as described above. The widening of segments of SR 76 to add travel lanes would
require considerable grading that would potentially result in impacts to sensitive biological, and
cultural resources. A biological resources and cultural resources memorandum were prepared to
assess the potential of a SR 76 road widening alignment project. The biological resources
memorandum indicates that the area surrounding the SR 76 segment is characterized by riverine
terrace with south-facing slopes. Based on regional MSCP mapping provided by SANDAG, the
area includes chaparral, disturbed land, grassland, marsh (freshwater), open water (natural flood
channel), oak woodland, and riparian woodland communities (Dudek 2007). The main natural
feature and resource is the San Luis Rey River and various tributary drainages north of the river.
The cultural resources background study, consisting of a record search and literature review,
concluded that ten cultural resources sites have been recorded within or adjacent to the SR 76
segment considered for widening (CA-SDI-683, CA-SDI-744, CA-SDI-12584, CA-SDI-13004,
CA-SDI-13007H, CA-SDI-13767, CA-SDI-13768, CA-SDI-13769, CA-SDI-14609 and P-37-
016051). Therefore, the adverse impacts of adding travel lanes may not justify the resulting
benefit of increased traffic capacity for the additional 5.9 miles of SR 76 that the project
proposes to add to the list of Mobility Element roads for which LOS E or F is acceptable as a
part of the project. The project would amend Table M-4 of the Mobility Element and thus would
be consistent with the Mobility Element of the General Plan.
2.11.3 Cumulative Impacts
The Traffic Impact Study (Appendix M) utilized the SANDAG Series 11 Year 2030 traffic
forecast model, which assumes buildout of each parcel to its General Plan land use. Additionally,
the analysis assumes any project requiring a General Plan Amendment within the study area is
approved and implemented, and that all five casinos are built out to their ultimate density (Table
2.11-11, Cumulative Projects – General Plan Amendments and Casinos). Of these projects, the
Meadowood Project is estimated to generate 8,740 trips, and the Campus Park Project is
estimated to generate 19,941 trips. Planned improvements required to be built by these projects
at the intersections of SR 76/Pankey Road and SR 76/Horse Ranch Creek Road associated with
cumulative projects are assumed.
2.11.3.1 Roadway Segments
Guidelines for Significance
Guidelines for significance of impacts to roadways are the same for direct impacts and for
cumulative impacts. Guidelines for significance of impacts to roadways are provided in Section
2.11.2.3, Hazards and Alternative Transportation.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-23
Analysis
Tables 2.11-6 and 2.11-12 (Summary of Mitigated Roadway Segments – Cumulative
Conditions) contain information on the roadway segments identified in the study area, including
the scenario of Existing Plus Project Plus Cumulative traffic. Three significant impacts to
roadway segments would result:
Impact TR-11 SR 76 from west of E. Vista Way to N. River Road
Impact TR-12 SR 76 from N. River Road to Camino Del Rey
Impact TR-13 SR 76 from Camino Del Rey to S. Mission Road
Under the Existing Plus Cumulative Conditions the LOS remains at F, but the v/c ratio worsens.
Under the Existing Plus Project Plus Cumulative Conditions, the LOS remains at F, but the v/c
ratio further worsens (Tables 2.11-6 and 2.11-12) and are considered significant impacts. These
are discussed together because they are contiguous roadway segments (Figure 2.11-1) and all
would include the same mitigation measure.
Impact TR-14 SR 76 from S. Mission Road to Gird Road
Impact TR-15 SR 76 from Gird Road to Old Highway 395
Impact TR-16 SR 76 from Old Highway 395 to the I-15 southbound ramps
Impact TR-17 SR 76 from the I-15 southbound ramps to the I-15 northbound ramps
This portion of SR 76 is located west of I-15. Under the Existing Plus Cumulative scenario, these
roadway segments would operate at LOS F. They would continue at LOS F under the Existing
Plus Project Plus Cumulative scenario, with worsened v/c ratios (Tables 2.11-6 and 2.11-12).
These are considered significant impacts. These are contiguous roadway segments and would
all include the same mitigation measure.
Impact TR-18 SR 76 between Horse Ranch Creek Road and Rice Canyon Road
Impact TR-19 SR 76 between Rice Canyon Road and Couser Canyon Road
This portion of SR 76 is east of I-15. All of these segments function at LOS C under the existing
conditions, but are reduced to LOS F under the Existing Plus Cumulative scenario. The segments
remain at LOS F under the Existing Plus Project Plus Cumulative scenario, with worsened v/c
ratios (Tables 2.11-6 and 2.11-12). These are considered significant impacts. These are
contiguous roadway segments and would include the same mitigation measure.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-24
Impact TR-20 SR 76 between Couser Canyon Road and W. Pala Mission
Impact TR-21 SR 76 from W. Pala Mission Road to E. Pala Mission Road
Impact TR-22 SR 76 from E. Pala Mission Road to Lilac Road
Impact TR-23 SR 76 from Lilac Road to Adams Drive
Impact TR-24 SR 76 from Adams Drive to Cole Grade Road
The project’s contribution to existing cumulative impacts to the roadway segments listed above
would be cumulatively considerable.
2.11.3.2 Intersections
Guidelines for Determination of Significance
Guidelines for significance of impacts to intersections are the same for direct impacts and for
cumulative impacts. Guidelines for significance of impacts to intersections are provided in
Section 2.11.2.4, Mobility Element.
Analysis
Tables 2.11-8, 2.11-9, and 2.11-13 (Summary of Mitigated Intersections – Cumulative
Conditions) provide a summary of intersection performance during the AM and PM Peak Hours,
for Existing Conditions Plus the Project Plus Cumulative Impacts. Thirteen intersections would
experience significant impacts as defined above:
Impact TR-24 SR 76/E. Vista Way (existing LOS F in the AM Peak Hour and LOS E in the
PM Peak Hour)
Impact TR-25 SR 76/N. River Road (existing LOS C both Peak Hours)
Impact TR-26 SR 76/Camino Del Rey (existing LOS D both Peak Hours)
These intersections are located on the portion of SR 76 west of I-15. All would function at LOS
F in both Peak Hour periods under both the Existing Plus Cumulative and Existing Plus Project
Plus Cumulative scenarios. The v/c ratios and change in ADT further worsen under the Existing
Plus Project Plus Cumulative scenario (Tables 2.11-8, 2.11-9, and 2.11-13). These are considered
significant impacts. These three intersections would include the same mitigation measure.
Impact TR-27 SR 76/S. Mission Road (existing LOS C in both Peak Hours)
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-25
Impact TR-28 SR 76/Gird Road (existing LOS B in both Peak Hours)
Impact TR-29 SR 76/Old Highway 395 (existing LOS C in both Peak Hours)
These intersections are located on the portion of SR 76 west of I-15 and crossing I-15. All would
function at LOS F in both Peak Hour periods under both the Existing Plus Cumulative and
Existing Plus Project Plus Cumulative scenarios. The v/c ratios and change in ADT further
worsen under the Existing Plus Project Plus Cumulative scenario (Tables 2.11-8, 2.11-9, and
2.11-13). These are considered significant impacts. These three intersections would include the
same mitigation measure.
Impact TR-30 SR 76/I-15 southbound ramps (LOS C in the AM Peak Hour, LOS E in the
PM Peak Hour under Existing Conditions)
Impact TR-31 SR 76/I-15 northbound ramps (LOS C in the AM Peak Hour, LOS D in the
PM Peak Hour under Existing Conditions)
All of the intersections with the ramps would function at LOS F in both Peak Hour periods under
both the Existing Plus Cumulative and Existing Plus Project Plus Cumulative scenarios. The v/c
ratios and change in ADT further worsen under the Existing Plus Project Plus Cumulative
scenario (Tables 2.11-8, 2.11-9, and 2.11-13). These are considered significant impacts. The
impacts at SR 76 and all the ramps are identified together as they have the same proposed
mitigation approach.
Impact TR-32 SR 76/Rice Canyon Road (existing LOS B both Peak Hours)
Impact TR-33 SR 76/Couser Canyon Road (existing LOS B both Peak Hours)
Both of these intersections would function at LOS F in both Peak Hour periods under both the
Existing Plus Cumulative and Existing Plus Project Plus Cumulative scenarios. The v/c ratios
and change in ADT further worsen under the Existing Plus Project Plus Cumulative scenario,
with the intersection of SR 76/Rice Canyon Road rated as “overflow” (Tables 2.11-8, 2.11-9, and
2.11-13). These intersections are located on the portion of SR 76 east of I-15. These are
considered significant impacts. These intersections would include the same mitigation measure.
Impact TR-34 SR 76/E. Pala Mission Road (LOS B in the AM Peak Hour, LOS C in the PM
Peak Hour under Existing Conditions). During the AM Peak Hour period, SR
76/E. Pala Mission Road would operate at LOS D under the Existing Plus
Cumulative scenario, and at LOS E under the Existing Plus Project Plus
Cumulative scenario.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-26
Impact TR-35 SR 76/Lilac Road (existing LOS B both peak periods). The intersection of SR
76/Lilac Road would operate at LOS D under either Existing Plus Cumulative
scenario or the Existing Plus Project Plus Cumulative in the AM Peak Hour.
Impact TR-36 SR 76/Cole Grade Road (existing LOS C in both Peak Hours). The
intersection of SR 76/Cole Grade Road would operate at LOS F under either
the Existing Plus Cumulative scenario or the Existing Plus Project Plus
Cumulative scenario in the AM Peak Hour.
These intersections are located on the portion of SR 76 east of I-15. During the PM Peak Hour,
all three intersections would function at LOS F under both the Existing Plus Cumulative and
Existing Plus Project Plus Cumulative scenarios. The v/c ratios and change in ADT further
worsen under the Existing Plus Project Plus Cumulative scenario (Tables 2.11-8, 2.11-9, and
2.11-13). These are considered significant impacts.
The project’s contribution to existing cumulative impacts to the intersections listed above would
be cumulatively considerable (Appendix M).
2.11.4 Significance of Impacts Prior to Mitigation
2.11.4.1 Direct Impacts
SR 76 Under the Existing Plus Project condition, the project would have a significant direct
impact on the following Roadway segments:
SR 76 from west of E. Vista Way to N. River Road (Impact TR-1)
SR 76 from N. River Road to Camino Del Rey (Impact TR-2)
SR 76 from Camino Del Rey to S. Mission Road (Impact TR-3)
SR 76 from S. Mission Road to Gird Road (Impact TR-4)
SR 76 from Gird Road to Old Highway 395 (Impact TR-5)
SR 76 crossing of I-15, between the freeway ramps. (Impact TR-6)
Four intersections with SR 76 would be significantly impacted.
SR 76 intersection with E. Vista Way (Impact TR-7)
SR 76 intersection at the I-15 southbound ramps (Impact TR-8)
SR 76 intersection at the I-15 northbound ramps. (Impact TR-9)
SR 76 intersection with project entry (Impact TR-10)
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-27
2.11.4.2 Cumulative Impacts
The project’s contribution to existing cumulative impacts to the following roadway segments of
SR 76 would be cumulatively considerable:
SR 76 from E. Vista Way to N. River Road (Impact TR-11)
SR 76 from N. River Road to Camino Del Rey (Impact TR-12)
SR 76 between Camino Del Rey and S. Mission Road (Impact TR-13)
SR 76 from S. Mission Road to Gird Road (Impact TR-14)
SR 76 from Gird Road to Old Highway 395 (Impact TR-15)
SR 76 from Old Highway 395 to the I-15 southbound ramp (Impact TR-16)
SR 76 between the I-15 ramps (Impact TR-17)
SR 76 between the I-15 NB ramp to Pankey Road (Impact TR-18)
SR 76 between Horse Ranch Creek Road and Rice Canyon Road (Impact TR-19)
SR 76 between Rice Canyon Road and Couser Canyon Road (Impact TR-120)
SR 76 between Couser Canyon Road and W. Pala Mission Road (Impact TR-21)
SR 76 from W. Pala Mission Road to E. Pala Mission Road (Impact TR-22)
SR 76 from E. Pala Mission Road to Lilac Road (Impact TR-23)
SR 76 from Lilac Road to Adams Drive (Impact TR-24)
SR 76 from Adams Drive to Cole Grade Road (Impact TR-25)
The project’s contribution to existing cumulative impacts to the following thirteen intersections
with SR 76 would be cumulatively considerable:
SR 76/E. Vista Way (Impact TR-26)
SR 76/N. River Road (Impact TR-27)
SR 76/Camino Del Rey (Impact TR-28)
SR 76/S. Mission Road (Impact TR-29)
SR 76/Gird Road (Impact TR-30)
SR 76/Old Highway 395 (Impact TR-31)
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-28
Two intersections are located at I-15:
SR 76/I-15 southbound ramps (Impact TR-32)
SR 76/I-15 northbound ramps (Impact TR-33)
Five of the intersections with SR 76 are east of I-15:
SR 76/Rice Canyon Road (Impact TR-34)
SR 76/Couser Canyon Road (Impact TR-35)
SR 76/E. Pala Mission Road (Impact TR-36)
SR 76/Lilac Road (Impact TR-37)
SR 76/Cole Grade Road (Impact TR-38)
2.11.5 Mitigation
2.11.5.1 Direct Impacts Mitigation
Roadway Segments
The following mitigation measure M-TR-1 reduced direct roadway segment impacts on SR 76
from E. Vista Way to S. Mission Road (Impacts TR-1 through TR-3).
M-TR-1 Implementation of the Caltrans SR 76 Middle Project, which widened SR 76
from two lanes to four lanes between Melrose Drive on the west to S.
Mission Road.
The Caltrans SR 76 Middle Project was completed in 2012 as a four-lane facility with right-of-
way and grading to accommodate a possible future widening (TransNet 2016); see Figure 2.11-3,
Direct Impact Locations, for location. Impacts TR-1 through TR-3 have been mitigated to less
than significant by improving the LOS to an acceptable level.
The following mitigation measure M-TR-2 reduced direct roadway segment impacts on SR 76
from S. Mission Road to the I-15 northbound ramp (Impacts TR-4 through TR-6).
M-TR-2 Implementation of the Caltrans SR 76 East Project, which will widen SR 76 from
two lanes to four lanes between S. Mission Road and I-15.
Caltrans has begun construction of the SR 76 East Project which will widen and realign SR 76 to
a four-lane highway from just east of South Mission Road to the newly improved SR 76/I-15
interchange (TransNet SR 76 Widening) (Caltrans 2015b). The timeframe for construction of the
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-29
Warner Ranch project begins in 2016 and ends in 2021, while the SR 76 East Project
improvements are expected to be completed by 2017. The SR 76 East Project is the last of the
projects on this major link between Interstate 5 and I-15 and will complete one of the high-
priority transportation projects included in the region’s TransNet Early Action Program. Once
the SR 76 East project is completed, the LOS to this segment will be acceptable. However, until
the Caltrans project is completed, the impact will remain significant unavoidable because the
improvement, necessary to reduce the significant impact, is the responsibility of another
jurisdiction. If a component of the project is occupied before Caltrans completes the SR 76 East
project, the Proposed Project would result in a temporary (short-term), unmitigated impact to
those certain segments of SR 76 identified as Impact TR-4 through Impact TR-5, until such time
as Caltrans completes the SR 76 East project. If the ongoing SR 76 East widening is completed
prior to Project implementation, no significant direct temporary Project impacts would occur. As
explained above, the SR 76 East project is within the responsibility and jurisdiction of another
government agency and is outside the jurisdiction of the County. Since CEQA does not clearly
define the level to which a significant impact must be mitigated before a statement of overriding
considerations become unnecessary and because the SR 76 East project is within the jurisdiction
of another agency, this EIR has taken the cautious approach of adopting such a statement for
Impacts TR-4 through Impact TR-6.
Intersections
Impacts to the intersection of SR 76/E. Vista Way (Impact TR-7) are mitigated through
implementation of M-TR-1. Impact TR-7 has been mitigated to less than significant by
improving the LOS to an acceptable level.
Impacts to the following intersections are reduced through implementation of M-TR-3:
SR 76 / I-15 SB Ramp (Impact TR-8)
SR 76 / I-15 NB Ramp (Impact TR-9)
M-TR-3 Implementation of the Caltrans SR 76 East Project to reconfigure the SR 76/
I-15 interchange.
The Caltrans SR 76 East Project relative to reconfiguring the SR 76/I-15 interchange has been
completed; therefore, Impacts TR-8 and TR-9 are mitigated to less than significant by
improving the LOS to an acceptable level.
The impact at the SR 76/project entry intersection (Impact TR-10) will be reduced through
implementation of M-TR-4.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-30
M-TR-4 Improve the project frontage and channelized/signalize the main public entrance
intersection on SR 76 so that there are dual left turns for eastbound to northbound
movements and a deceleration lane for westbound to northbound traffic.
The project would mitigate Impact TR-10 by improving the operation of the SR 76 facility at
the project entry location to less than significant. A Traffic Signal Warrant worksheet is
attached to Appendix M.
Table 2.11-14, Direct Impacts and Mitigation Measures, summarizes direct impacts and
mitigation measures for the roadway segments and intersections.
2.11.5.2 Cumulative Impacts Mitigation
Roadway Segments
The following cumulatively impacted segments would be reduced through implementation of the
following mitigation measure; however, it has been determined to be infeasible.:
SR 76 from E. Vista Way to N. River Road (Impact TR-11)
SR 76 from N. River Road to Camino Del Rey (Impact TR-12)
SR 76 between Camino Del Rey and S. Mission Road (Impact TR-13)
Infeasible Mitigation Measure: Construct identified roadway segments of SR 76 to a six-
lane Expressway classification.
While improvement of this segment to a six-lane Expressway classification would mitigate the
project impact, such mitigation is infeasible. A commitment to funding under the TIF or from
another source has not been identified for construction of a six-lane Expressway needed to
mitigate the cumulative impact identified; therefore this portion would remain at four lanes.
The Caltrans SR 76 Middle Project has been completed in which this portion of SR 76 has been
widened from two to four lanes. However, the Circulation Element of the General Plan identified
this improvement as a six-lane Expressway in order to accommodate the build out of the General
Plan. The project would amend the Land Use Element to increase density on the project site,
which would generate more traffic than was included in the County’s General Plan forecast for
the roadway segments identified above. The proposed project contributes approximately 1.4, 1.9
and 1.8 percent, of the total trips respectively, to these road segments in the cumulative traffic
condition. Since improvements to SR 76 is the responsibility of another jurisdiction (Caltrans),
and no program is available to which the applicant could make a fair-share contribution, no
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-31
feasible mitigation measures are available and the cumulative Impacts TR-11 through TR-13
would remain significant and unavoidable.
In addition, imposing this widening on the project would be infeasible because the mitigation
would not be proportional to the project’s proportional share of the impact. The proposed project
contributes approximately 1.4 to 1.9 percent of the total trips to this road segment in the
cumulative traffic condition. The cost of improving this road segment (approximately 2.9 miles)
would be $20,581,300 million (equivalent to $7,097,000/mile) according to the County of San
Diego TIF Update Facilities Cost Analysis (2012). The project’s small contribution to the
cumulative condition would not be roughly proportional to the cost of mitigation of improving
these roadway segments of SR 76. Pursuant to CEQA Guidelines Section 15126.4(a)(4)(B),
mitigation measures must be roughly proportional to the environmental impacts caused by the
project. Therefore, because the project’s contribution to the cumulative traffic condition is not
roughly proportional to the improvements required to mitigate the impact, conditioning this
project to construct the road improvements is not feasible under CEQA, and the cumulative
impacts would remain significant and unavoidable.
The following cumulatively impacted segments would be reduced through implementation of
mitigation measure M-TR-2:
SR 76 from S. Mission Road to Gird Road (Impact TR-14)
SR 76 from Gird Road to Old Highway 395 (Impact TR-15)
SR 76 from Old Highway 395 to the I-15 southbound ramp (Impact TR-16)
SR 76 between the I-15 ramps (Impact TR-17)
These cumulative impacts would be reduced through implementation of mitigation measure M-
TR-2, but not to less than significant. Cumulative Impacts TR-14 through TR-17 would remain
significant and unavoidable, because if a component of the project is occupied before Caltrans
completes the SR 76 East project, the proposed project would result in a temporary (short-term),
unmitigated impact to those certain segments of SR 76 identified as Impact TR-14 through Impact
TR-16, until such time as Caltrans completes the SR 76 East project. If the ongoing SR 76 East
widening is completed prior to project implementation, no significant cumulative impacts would
occur. As explained above, the SR 76 East project is within the responsibility and jurisdiction of
another government agency and is outside the jurisdiction of the County. Since CEQA does not
clearly define the level to which a significant impact must be mitigated before a statement of
overriding considerations become unnecessary, this EIR has taken the cautious approach of
adopting such a statement for Impacts TR-14 through Impact TR-16.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-32
The following cumulatively impacted segments would be reduced to less than significant through
implementation of the following mitigation measure; however, it has been determined to be
infeasible.SR 76 between I-15 NB ramp to Pankey Road (Impact TR-18)
Infeasible Mitigation Measure: Reclassify this segment to six lanes and construct
additional lanes which would increase the its capacity.?
The roadway has already been improved to more than 4 lanes along portions of this length and
further widening is not appropriate since the intersections at each end are operating adequately.
The intersections are more indicative of whether the corridor has capacity. Nonetheless, since
improvements to SR 76 is the responsibility of another jurisdiction (Caltrans), and no
program is available to which the applicant could make a fair-share contribution, no feasible
mitigation measures are available and Impact TR-18 would remain cumulatively significant
and unavoidable.
The following cumulatively impacted segments would be reduced to less than significant
through implementation of mitigation measure M-TR-5:
SR 76 between Horse Ranch Creek Road and Rice Canyon Road (Impact TR-19)
SR 76 between Rice Canyon Road and Couser Canyon Road (Impact TR-20)
M-TR-5 Prior to issuance of any building permit for new structures within the project, the
applicant, or its designee, shall pay all applicable fees to the TIF Program, which
should be updated to include the changes to the Land Use and Mobility Elements
proposed by the project.
The TIF Program was specifically designed to address cumulative impacts. The TIF Program
includes road improvements required to provide adequate circulation through Year 2030.
Required improvements are specified and funds are collected from projects to pay for the road
improvements. Since the TIF Program was designed to address cumulative traffic impacts,
participation in the TIF Program constitutes effective and adequate mitigation for cumulative
traffic impacts. These identified roadway segments are included in the TIF and payment of the
TIF fees would mitigate the cumulative impact. Therefore, payment of TIF fees would reduce the
cumulative impacts to TR-19 through TR-20 to less than significant.
The following cumulatively impacted segments would be reduced through implementation of
mitigation measure M-TR-6:
SR 76 between Couser Canyon Road and W. Pala Mission Road (Impact TR-21)
SR 76 from W. Pala Mission Road to E. Pala Mission Road (Impact TR-22)
SR 76 from E. Pala Mission Road to Lilac Road (Impact TR-23)
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-33
SR 76 from Lilac Road to Adams Drive (Impact TR-24)
SR 76 from Adams Drive to Cole Grade Road (Impact TR-25)
M-TR-6 Design and construct improvements at the intersection of SR 76 with Cole Grade
Road to the satisfaction of Caltrans (either a signal or roundabout as determined
through a review under the I.C.E. Policy).
These cumulative impacts would be reduced through implementation of mitigation measure
M-TR-6, but not to less than significant. The portions of SR 76 described above (M-TR-21
through M-TR-25) are designated under the County’s General Plan Circulation Element as a two
lane collector. Expansion of the roadway to four lanes would be needed to mitigate the
cumulative impacts but such improvements are under the jurisdiction of Caltrans and are outside
of the jurisdiction and control of the County. County staff coordinated with Caltrans, and
Caltrans confirmed that it has no project, funding, or program to make the necessary
improvements to which the applicant can make a fair-share contribution.
In addition, mitigation measures would be infeasible for Impacts TR-22 through TR-25 because;
the mitigation would not be proportional to the project’s proportional share of the impact. The
proposed project contributes approximately 12 percent of total trips along SR 76 between Couser
Canyon Road and W. Pala Mission Road (Impact TR21), 6 percent of the total trips along SR
76 between W. Pala Mission Road and E. Pala Mission Road (Impact TR-22), 2 percent of the
total trips along SR 76 from E. Pala Mission Road to Lilac Road (Impact TR-23), 2 percent of
the total trips along SR 76 between Lilac Road and Adams Drive (Impact TR-24) and 1 percent
of the total trips along SR 76 from between Adams Drive and Cole Grade Road (Impact TR-
25); see Table 2.11-15, Project Traffic Percentages. The cost of improving this portion of SR 76
would be $41,872 million (equivalent to $7,097,000/mile) according to the County of San Diego
TIF Update Facilities Cost Analysis (2012). The project’s contribution to the cumulative
condition would not be roughly proportional to the cost of mitigation of improving these
roadway segments of SR 76. Pursuant to CEQA Guidelines Section 15126.4(a)(4)(B), mitigation
measures must be roughly proportional to the environmental impacts caused by the project.
Therefore, because improvements necessary to reduce significant cumulative impacts are the
responsibility of another jurisdiction, and no program is available to which the applicant could
contribute, mitigation is infeasible. Furthermore, the improvements required to mitigate impacts
to the majority of the segments to SR 76 would not be roughly proportional to the project’s
contribution to the cumulative effect and conditioning this project to construct the road
improvements is yet another reason that mitigation is not feasible under CEQA. Therefore,
cumulative impacts TR-21 through TR-25 will remain significant and unavoidable.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-34
Intersections
The following cumulatively impacted intersections would be reduced through implementation of
infeasible mitigation measure identified above: construct identified roadway segments to 6 lanes.:
SR 76/E. Vista Way (Impact TR-26)
SR 76/N. River Road (Impact TR-27)
SR 76/Camino Del Rey (Impact TR-28)
While improvement of this segment to a six-lane Expressway classification would mitigate the
project impact, such mitigation is infeasible. A commitment to funding under the TIF or from
another source has not been identified for construction of a six-lane Prime Arterial needed to
mitigate the cumulative impact identified; therefore this portion would remain at four lanes.
Therefore, Impacts TR-26 though TR-28 and would remain significant and unavoidable.
Impacts to the following intersections would be reduced through implementation of mitigation
measure M-TR-2, but not to a level below significance because, as previously described, the
mitigation measure calls for completion of SR 76 East project, which is within the responsibility
and jurisdiction of another government agency and is outside the jurisdiction of the County.
Until the improvements are complete, Impacts TR-29 through TR-31 would remain significant
and unavoidable until completion of the SR 76 East project.
SR 76/S. Mission Road (Impact TR-29)
SR 76/Gird Road (Impact TR-30)
SR 76/Old Highway 395 (Impact TR-31)
The following cumulatively impacted intersections would be reduced to less than significant
through implementation of mitigation measure M-TR-7:
SR 76/I-15 southbound ramps (Impact TR-32)
SR 76 / I-15 northbound ramps (Impact TR-33)
M-TR-7 Although the interchange is now improved; developer has agreed to make a fair-
share contribution of up to 12.3 percent (see Table 8-3) of the unfunded cost of
approximately $10M based upon Caltrans formula for calculating fair share as set
forth in the Caltrans Guide for the Preparation of Traffic Studies.
Caltrans has determined that the contribution will mitigate the Impacts TR-32 and TR-33 to less
than significant by reducing the effect of the project’s contribution of cumulative traffic to an
acceptable level.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-35
The following cumulatively impacted intersections would be reduced to less than significant
through implementation of mitigation measure M-TR-5:
SR 76/Rice Canyon Road (Impact TR-34)
SR 76/Couser Canyon Road (Impact TR-35)
SR 76 intersections with Rice Canyon and Couser Canyon Roads are included in the TIF
and payment of the TIF fees mitigates the cumulative contribution of the project to less
than significant.
One of the following three cumulatively impacted intersections would be reduced to less than
significant through implementation of mitigation measure M-TR-6, as further described below:
SR 76/E Pala Mission Road (Impact TR-36)
SR 76/Lilac Road (Impact TR-37)
SR 76/Cole Grade Road (Impact TR-38)
These cumulative impacts would be reduced through implementation of mitigation measure M-
TR-6 because a series of meetings with the County, Caltrans, and the applicant were held to
develop feasible and commensurate mitigation. Based on these, the project will design and
construct the needed improvements to the intersection of SR 76 / Cole Grade Road, to include
channelization and signalization (M-TR-6). The improvements to the intersection of SR 76 /
Cole Grade Road and the improvements to the project frontage (M-TR-4) will improve traffic
flow and safety at the improvement location and on the surrounding portions of SR 76. However,
even with these mitigation measures, cumulative impacts TR-36 and TR-37 will remain
significant and unavoidable because the LOS will not be reduced to an acceptable level.
Mitigation measure M-TR-6 would, however, reduce the LOS impacts to the SR 76/Cole Grade
Road intersection (Impact TR-38) to less than significant.
Tables 2.11-16, Cumulative Impacts and Mitigation Measures—Roadway Segments, and
2.11-17, Cumulative Impacts and Mitigation Measures—Intersections, summarize cumulative
impacts and mitigation measures for roadway segments and intersections, respectively.
2.11.6 Conclusions
The following discussion provides the significance conclusion reached after application of the
mitigation measures in each of the above impact analyses, and the level of impact that would
result after implementation of the project with mitigation. Where mitigation measures do not
reduce impacts to less than significant, this section focuses on the feasibility of mitigating the
impacts. All project traffic impacts requiring mitigation are associated with SR 76, all roadway
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-36
segments requiring mitigation are SR 76 segments, and all intersections requiring mitigation are
intersections involving SR 76.
2.11.6.1 Direct Impacts
Direct impacts are shown on Figure 2.11-3.
Roadways
Mitigation measure M-TR-1 would reduce direct roadway segment impacts on SR 76 from E.
Vista Way to S. Mission Road (Impact TR-1 through TR-3). The Caltrans SR 76 Middle
Project was completed in 2012 as a four-lane facility with right-of-way and grading to
accommodate a possible future widening.
Mitigation measure M-TR-2 would reduce direct roadway segment impacts on SR 76 from
S. Mission Road to the I-15 northbound ramp (Impacts TR-4 through TR-6). Caltrans is
currently constructing the SR 76 East Project which will widen and realign SR 76 to a four-
lane highway from just east of South Mission Road to the newly improved SR 76/I-15
interchange. However, until this project is completed the impact will remain significant
unavoidable because the improvement, necessary to reduce the significant impact, is the
responsibility of another jurisdiction (Caltrans).
Intersections
Impacts to the intersection of SR 76/E. Vista Way (Impact TR-7) are mitigated through
implementation of M-TR-1. The Caltrans SR 76 East Project relative to reconfiguring the SR
76/I-15 interchange has been completed and therefore impacts TR-8 and TR-9 are mitigated to
less than significant (M-TR-3). Impacts to the SR 76/project entry intersection (Impact TR-10)
would be reduced to less than significant through implementation of M-TR-4.
2.11.6.2 Cumulative Impacts
Cumulative impacts are shown on Figure 2.11-4, Cumulative Impact Locations.
Roadways
Cumulative impacts to SR 76 from E. Vista Way to S. Mission Road (Impacts TR-11 through
TR-13) would be reduced through implementation of migration measure M-TR-5. While
improvement of this segment to a six-lane Expressway classification would mitigate the project
impact, such mitigation is infeasible. A commitment to funding has not been identified for
construction of a six-lane Prime Arterial needed to mitigate the cumulative impact identified;
therefore, this portion would remain at four lanes. Impacts TR-11 through TR-13 would remain
significant and unavoidable.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-37
Impacts to SR 76 from S. Mission Road to the I-15 ramps (Impacts TR-14 through TR-17) would
be reduced through implementation of mitigation measure M-TR-2, but not to a level below
significance. Impacts TR-14 through TR-17 would remain significant and unavoidable.
Impacts to SR 76 from the I-15 northbound ramps to Pankey Road (Impact TR-18) could be
reduced to less than significant through reclassifying the segment to a higher capacity to match
configuration and the construction of additional lanes along this length. However, the roadway
has already been improved and further widening is not appropriate since the intersections at each
end are operating adequately and more than 4 lanes have been built along portions of this length.
In any event, said improvement to SR 76 is the responsibility of another jurisdiction
(Caltrans), and no program is available to which the applicant could make a fair-share
contribution, no feasible mitigation measures are available and Impact TR-18 would remain
cumulatively significant and unavoidable.
Impacts to SR 76 from Horse Ranch Creek Road to Couser Canyon Road (Impacts TR-19
through TR-20) would be reduced to less than significant through implementation of mitigation
measure M-TR-5. These identified roadway segments are included in the TIF and payment of
the TIF fees would mitigate the cumulative impact.
Cumulative impacts to SR 76 from Couser Canyon Road to Cole Grade Road (Impacts TR-21
through TR-25) would be reduced through implementation of mitigation measure M-TR-6, but not
to a level less than significant. Because the improvements necessary to reduce significant cumulative
impacts to a level less than significant are the responsibility of another jurisdiction, and no program is
available to which the applicant could contribute, mitigation is infeasible. Therefore, cumulative
impacts TR-21 through TR-25 will remain significant and unavoidable.
Intersections
For reasons described above for direct Impact TR-26 through Impact TR-28, constructing
identified roadway segments to 6 lanes is an infeasible mitigation measure. A commitment to
funding under the TIF or from another source has not been identified for construction of a six-
lane Prime Arterial needed to mitigate the cumulative impact identified; therefore this portion
would remain at four lanes. There are no feasible mitigation measures to fully mitigate Impacts
TR-25 though TR-27 and therefore they would remain significant and unavoidable.
Impacts to SR 76/S. Mission Road, SR 76/Gird Road, and SR 76/Old Highway 395 (Impact
TR-29 through Impact TR-31) would be reduced through implementation of mitigation measure
M-TR-2, but as previously described, the mitigation measure calls for completion of SR 76 East
project, which is within the responsibility and jurisdiction of another government agency and is
outside the jurisdiction of the County. Until the improvements are complete, Impacts TR-29
through TR-31 would remain significant and unavoidable.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-38
Caltrans has determined that the fair share contribution will mitigate (M-TR-7) the impacts
to SR 76 at the north and southbound I-15 ramps (TR-32 and TR-33) to less than significant
by reducing the effect of the project’s traffic to an acceptable level. See Table 2.11-18, Fair
Share Percentages.
Impacts to SR 76/Rice Canyon Road (Impact TR-34) and SR 76/Couser Canyon Road (Impact
TR-35) would be reduced to less than significant through implementation of mitigation measure
M-TR-5, as described above.
The improvements to the intersection of SR 76 / Cole Grade Road (M-TR-6) and the
improvements to the project frontage (M-TR-4) will improve traffic flow and safety at the
intersections of SR 76/E Pala Mission Road (Impact TR-36), SR 76/Lilac Road (Impact
TR-37) and SR 76/Cole Grade Road (Impact TR-38). Even with these mitigation measures,
cumulative impacts TR-36 and TR-37 will remain significant and unavoidable; however,
(Impact TR-38) would be reduce to less than significant.
Table 2.11-1a
Roadway Segment Level of Service Definitions
LOS V/C Congestion/Delay Traffic Description
(Used for surface streets, freeways, expressways and conventional highways)
“A” <0.41 None Free flow.
“B” >0.41-0.62 None Free to stable flow, light to moderate volumes.
“C” >0.62-0.80 None to minimal Stable flow, moderate volumes, freedom to maneuver noticeably restricted.
“D” >0.80-0.92 Minimal to substantial Approaches unstable flow, heavy volumes, very limited freedom to maneuver.
“E” >0.92-1.00 Significant Extremely unstable flow, maneuverability and psychological comfort extremely poor.
(Used for surface streets and conventional highways)
“F” >1.00 Considerable Forced or breakdown flow. Delay measured in average travel speed (MPH). Signalized segments experience delays >60.0 seconds/vehicle.
(Used for freeways and expressways)
“F(0)” >1.00-1.25 Considerable
0-1 hour delay
Forced flow, heavy congestion, long queues form behind breakdown points, stop and go.
“F(1)” >1.25-1.35 Severe
1-2 hour delay
Very heavy congestion, very long queues.
“F(2)” >1.35-1.45 Very Severe
2-3 hour delay
Extremely heavy congestion, longer queues, more numerous breakdown points, longer stop periods.
“F(3)” >1.45 Extremely Severe
3+ hours of delay
Gridlock
Source: Appendix M.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-39
Table 2.11-1b
SANTEC/ITE Measure of Significant Project Traffic Impacts
Level of Service (LOS) with Project Allowable Change Due to Project
E & F (or ramp meter delays above 15
min.) Freeways Roadway Segments
Signalized Intersections Ramp Metering
V/C Speed (mph) V/C Speed (mph) Delay (sec) Delay (min.)
0.01 1 0.02 1 2 2
Source: County of San Diego 2011.
Table 2.11-2
Signalized Intersection Level of Service
Control Stopped Delay Per Vehicle (seconds) Level of Service (LOS) Characteristics
<10 LOS A describes operations with very low delay. This occurs when progression is extremely favorable, and most vehicles do not stop at all. Short cycle lengths may also contribute to low delay.
>10 – 20 LOS B describes operations with generally good progression and/or short cycle lengths. More vehicles stop than for LOS A, causing higher levels of average delay.
>20 – 35 LOS C describes operations with higher delays, which may result from fair progression and/or longer cycle lengths. Individual cycle failures may begin to appear at this level. The number of vehicles stopping is significant at this level, although many still pass through the intersection without stopping.
>35 – 55 LOS D describes operations with high delay, resulting from some combination of unfavorable progression, long cycle lengths, or high volumes. The influence of congestion becomes more noticeable, and individual cycle failures are noticeable.
>55 – 80 LOS E is considered to be the limit of acceptable delay. Individual cycle failures are frequent occurrences.
>80 LOS F describes a condition of excessively high delay, considered unacceptable to most drivers. This condition often occurs when arrival flow rates exceed the capacity of the intersection. Poor progression and long cycle lengths may also be major contributing causes to such delay.
Source: Appendix M.
Table 2.11-3
Project Trip Generation
Land Use Intensity Unit Rate/Trips Daily Trips
AM Peak Hour PM Peak Hour
Total In Out Total In Out
Single Family (3–6 DU/acre)
534 dwelling unit
Rate 10 8% 30% 70% 10% 70% 30%
Trips 5,340 428 129 300 534 374 161
Condominium (6–20 DU/acre)
246 dwelling unit
Rate 8 8% 20% 80% 10% 70% 30%
Trips 1,968 158 32 127 197 138 60
Developed Park 4.23 acre Rate 50 13% 50% 50% 9% 50% 50%
Trips 212 28 14 14 20 10 10
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-40
Table 2.11-3
Project Trip Generation
Land Use Intensity Unit Rate/Trips Daily Trips
AM Peak Hour PM Peak Hour
Total In Out Total In Out
Fire Station 1 Station Rate 50 8% 60% 40% 10% 40% 60%
Trips 50 4 3 2 5 2 3
Totals 7,570 618 178 443 756 524 234
Source: Appendix M. DU/acre = dwelling units per acre.
Table 2.11-4
Measures of Significant Project Impacts to Congestion: Allowable Increases On Two-Lane
Highways with Signalized Intersection Spacing over 1 Mile
Level of Service LOS Criteria Impact Significance Level
LOS E > 16,200 ADT > 325 ADT
LOS F > 22,900 ADT > 225 ADT
Source: San Diego County 2011. Note: Where detailed data are available, the Director of Public Works may also accept a detailed level of service analysis based upon the two-lane highway analysis procedures provided in the Chapter 20 Highway Capacity Manual.
Table 2.11-5
Measures of Significant Project Impacts to Congestion: Allowable Increases on Two-Lane
Highways with Signalized Intersection Spacing under 1 Mile
Level of Service LOS Criteria
LOS E Intersection delay of 2 seconds
LOS F Intersection delay of 1 second, or 5 peak hour trips on a critical movement
Source: San Diego County 2011. Notes: 1. A critical movement is one that is experiencing excessive queues. 2. By adding proposed project trips to all other trips from a list of projects, this same table is used to determine if total cumulative impacts
are significant. If cumulative impacts are found to be significant, each project that contributes any trips must mitigate its share of the cumulative impacts.
3. The County may also determine impacts have occurred on roads even when a project’s traffic or cumulative impacts do not trigger an unacceptable level of service, when such traffic uses a significant amount of remaining road capacity.
Table 2.11-6
Summary of Roadway Segment Conditions
Roadway Segment Lanes/ Class*
LOS E Capacity
Existing Existing + Project
Traffic v/cADT V/C LOS ADT V/C LOS
State Route 76
E. Vista Way to N. River Road 2SR 22,900 28,805 1.258 F 29,207 1.275 F 402 0.018
N. River Road to Camino Del Rey
2SR 22,900 39,736 1.735 F 40,274 1.759 F 538 0.023
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-41
Table 2.11-6
Summary of Roadway Segment Conditions
Roadway Segment Lanes/ Class*
LOS E Capacity
Existing Existing + Project
Traffic v/cADT V/C LOS ADT V/C LOS
Camino Del Rey to S. Mission Road
2SR 22,900 39,316 1.717 F 39,922 1.743 F 606 0.026
S. Mission Road to Gird Road 2SR 22,900 26,752 1.168 F 27,448 1.199 F 696 0.030
Gird Road to Old Hwy 395 2SR 22,900 23,789 1.039 F 24,577 1.073 F 788 0.034
Old Hwy 395 to I-15 SB Ramp 4C 34,200 29,407 0.860 D 30,279 0.885 D 872 0.025
I-15 SB Ramp to I-15 NB Ramp 2SR 22,900 19,359 0.845 E 21,176 0.925 E 1,817 0.079
I-15 NB Ramp to Pankey Road 4MR 37,000 11,031 0.298 A 13,795 0.373 A 2,764 0.075
Pankey Road to Horse Ranch Creek Road
4MR 37,000 11,031 0.298 A 14,379 0.389 A 3,348 0.090
Horse Ranch Creek Road to Rice Canyon Road
2SR 22,900 11,031 0.482 C 15,179 0.663 D 4,148 0.181
Rice Canyon Road to Couser Canyon Road
2SR 22,900 11,031 0.482 C 15,543 0.679 D 4,512 0.197
Couser Canyon Road to W. Pala Mission Road
2SR 22,900 10,224 0.446 C 14,894 0.650 D 4,670 0.204
W. Pala Mission Road to E. Pala Mission Road
2SR 22,900 10,329 0.451 C 10,935 0.478 C 606 0.026
E. Pala Mission Road to Lilac Road
2SR 22,900 8,821 0.385 C 9,427 0.412 C 606 0.026
Lilac Road to Adams Drive 2SR 22,900 9,456 0.413 C 9,850 0.430 C 394 0.017
Adams Drive to Cole Grade Road
2SR 22,900 9,090 0.397 C 9,460 0.413 C 370 0.016
W. Pala Mission Road
State Route 76 and Pala Temecula Road
2RC 16,200 4,711 0.291 C 5,929 0.366 C 1,218 0.075
Pala Temecula Road
Pala Mission Road to Trujillo Road
2RC 16,200 8,318 0.513 D 9,264 0.572 D 946 0.058
Source: Appendix M. Note: * 2RC: Two-lane Rural Collector; 2SR: Two-lane State Route; 2SR w/ LTL: Two-lane State Route w/ left-turn lanes; 4C: Four-lane
Collector; 4M: Four-lane Major; 6PA: Six-lane Prime Arterial.
Table 2.11-7
Summary of Mitigated Roadway Segments – Existing Plus Project Conditions
Roadway Segment
Mitigated Lanes/ Class
LOS E Capacity
Existing Existing + Project +
Mitigation
Mitigated? ADT V/C LOS ADT V/C LOS
State Route 76
E. Vista Way to N. River Road 4MR 37,000 28,805 1.258 F 29,207 0.789 C Yes
N River Road to Camino Del Rey 4MR 37,000 39,736 1.735 F 40,274 1.088 F Yes
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-42
Table 2.11-7
Summary of Mitigated Roadway Segments – Existing Plus Project Conditions
Roadway Segment
Mitigated Lanes/ Class
LOS E Capacity
Existing Existing + Project +
Mitigation
Mitigated? ADT V/C LOS ADT V/C LOS
Camino Del Rey to S. Mission Road 4MR 37,000 39,316 1.717 F 39,922 1.079 F Yes
S. Mission Road to Gird Road 4MR 37,000 26,752 1.168 F 27,448 0.742 C Yes
Gird Road to Old Hwy 395 4MR 37,000 23,789 1.039 F 24,577 0.664 B Yes
I-15 SB Ramp to I-15 NB Ramp 4MR 37,000 19,359 0.845 E 21,176 0.572 B Yes
Source: Appendix M. Note: 4MR: Four-lane Major Road.
Table 2.11-8
Summary of Intersection Conditions AM Peak Hour
Intersection
Existing Existing +
Project Existing +
Cumulative
Existing + Cumulative +
Project
Delay LOS Delay LOS Delay LOS Delay LOS
AM Peak Hour
1. SR 76/E. Vista Way 84.1 F 88.1 F 252.1 F 256.6 F
2. SR 76/N. River Road 21.1 C 22.3 C 220.3 F 226.7 F
3. SR 76/Olive Hill Road/Camino Del Rey 36.7 D 38.1 D 136.4 F 139.3 F
4. SR 76/S. Mission Road 28.8 C 29.0 C 184.9 F 188.9 F
5. SR 76/Gird Road 13.4 B 13.5 B 165.7 F 173.4 F
6. Old Highway 395/SR 76 31.1 C 31.3 C 160.4 F 162.7 F
7. I-15/SR 76 SB Ramp 31.1 C 44.2 D 197.6 F 221.1 F
8. I-15/SR 76 NB Ramp 23.6 C 28.4 C 95.8 F 127.7 F
9. SR 76/Pankey Road 10.7 B 14.6 B 21.0 C 22.0 C
10. SR 76/Horse Ranch Creek Road N/A N/A N/A N/A 17.9 B 18.2 B
11. SR 76/Rice Canyon Road 11.2 B 16.0 C 114.7 F 465.8 F
12. SR 76/Couser Canyon Road 12.3 B 17.4 C 69.3 F 232.7 F
13. SR 76/Driveway 0.5 A 18.8 B 1.6 A 17.8 B
14. SR 76/W. Pala Mission Road 26.4 C 28.5 C 23.9 C 25.3 C
15. Pala Mission Road/Pala Temecula Road 9.7 A 10.4 B 13.3 B 15.2 C
16. SR 76 /Brittian Road 9.1 A 9.2 A 10.8 B 11.0 B
17. SR 76/E. Pala Missions Road 12.5 B 13.2 B 34.0 D 39.5 E
18. SR 76/Lilac Road 11.8 B 12.3 B 25.8 D 28.5 D
19. SR 76/Adams Drive 10.1 B 10.2 B 13.9 B 14.2 B
20. SR 76/Cole Grade Road 17.0 C 17.5 C 287.0 F 307.2 F
Source: Appendix M.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-43
Table 2.11-9
Summary of Intersection Conditions PM Peak Hour
Intersection
Existing Existing + Project Existing +
Cumulative
Existing + Cumulative +
Project
Delay LOS Delay LOS Delay LOS Delay LOS
PM Peak Hour
1. SR 76/E. Vista Way 68.7 E 71.9 E 248.2 F 253.9 F
2. SR 76/N. River Road 34.5 C 37.0 D 310.1 F 318.4 F
3. SR 76/Olive Hill Road/Camino Del Rey 40.7 D 42.6 D 206.5 F 211.1 F
4. SR 76/S. Mission Road 31.9 C 34.1 C 283.8 F 290.7 F
5. SR 76/Gird Road 11.6 B 12.0 B 241.7 F 251.7 F
6. Old Highway 395/SR 76 30.8 C 31.3 C 240.0 F 246.5 F
7. I-15/SR 76 SB Ramp 58.8 E 74.6 E 335.5 F 357.9 F
8. I-15/SR 76 NB Ramp 51.1 D 60.1 E 240.0 F 272.9 F
9. SR 76/Pankey Road 11.1 B 19.8 C 29.1 C 33.2 C
10. SR 76/Horse Ranch Creek Road N/A N/A N/A N/A 18.7 B 19.7 B
11. SR 76/Rice Canyon Road 13.3 B 26.7 D 531.2 F Overflow F
12. SR 76/Couser Canyon Road 14.8 B 23.9 C 297.6 F 933.8 F
13. SR 76/Driveway 0.5 A 11.5 B 2.3 A 19.3 B
14. SR 76/W. Pala Mission Road 27.6 C 32.2 C 25.0 C 35.5 D
15. Pala Mission Road/Pala Temecula Road 11.2 B 12.7 B 17.3 C 22.5 C
16. SR 76/Brittian Road 10.1 B 10.5 B 19.3 C 20.5 C
17. SR 76/E. Pala Mission Road 16.7 C 18.4 C 512.9 F 600.1 F
18. SR 76/Lilac Road 13.1 B 15.7 C 93.0 F 167.6 F
19. SR 76/Adams Drive 13.4 B 13.8 B 32.3 D 33.9 D
20. SR 76/Cole Grade Road 17.9 C 18.5 C 967.0 F Overflow F
Source: Appendix M.
Table 2.11-10
Summary of Mitigated Intersections – Existing Plus Project Conditions
Intersection
Existing Existing + Project Existing + Project
+ Mitigation Fully Mitigated? Delay LOS Delay LOS Delay LOS
AM Peak Hour
1. SR 76/E. Vista Way 84.1 F 88.1 F 39.2 D Yes
PM Peak Hour
1. SR 76/E. Vista Way 68.7 E 71.9 E 44.9 D Yes
7. I-15/SR 76 SB Ramp 58.8 E 74.6 E 27.5 C Yes
8. I-15/SR 76 NB Ramp 51.1 D 60.1 E 27.9 C Yes
Source: Appendix M.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-44
Table 2.11-11
Cumulative Projects – General Plan Amendments and Casinos
Name Permit No. Description
Campus Park West TM 5424 Residential, Commercial, Office, and Park
Meadowood TM 5354 Residential, School, and Park
Olive Hill TM 4976 Residential
Pala Mesa Highlands TM 5187 Residential, Community Center, and Park
Pala Mesa Resort TM 5534 Hotel
Palomar Community College MUP 87-021 Community College
Passerelle/Campus Park TM 5338 Residential, Commercial, Office, Park, and Sports Complex
Rancho Lilac TM 5385 Residential, Commercial, Fire Station, Sheriff Annex, Park, and Agriculture
— TM 5263 Residential
Spanish Valley Ranch (Loranda) TM 5173 Residential
Vista Valley Country Club MUP 77-128 Club House
— TM 5166 Residential
Hidden Meadows TM 5175 TM 5176
Residential
San Pasqual Casino — Casino, Hotel, and Restaurant
Rincon Casino — Casino, Hotel, and Restaurant
Pala Casino — Casino and Restaurant
Pauma Casino — Casino, Hotel, Restaurant, and Office
Santa Ysabel Casino — Casino and Restaurant
La Jolla Casino — Casino, Hotel, and Restaurant
Segal Ranch TM 5173 Residential, Market, and Community Park
Source: Appendix M.
Table 2.11-12
Summary of Mitigated Roadway Segments – Cumulative Conditions
Roadway Segment Mitigated
Lanes/ Class LOS E
Capacity
Existing + Cumulative Existing + Cumulative + Project + Mitigation
Mitigated? ADT V/C LOS ADT V/C LOS
State Route 76
E. Vista Way to N. River Road
4MR 37,000 56,706 2.476 F 57,108 1.543 F No2
N. River Road to Camino Del Rey
4MR 37,000 66,900 2.921 F 67,438 1.823 F No2
Camino Del Rey to S. Mission Road
4MR 37,000 72,950 3.186 F 73,556 1.988 F No2
S. Mission Road to Gird Road
4MR 37,000 48,854 2.133 F 49,550 1.339 F Yes3
Gird Road to Old Hwy 395 4MR 37,000 42,830 1.870 F 43,618 1.179 F Yes3
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-45
Table 2.11-12
Summary of Mitigated Roadway Segments – Cumulative Conditions
Roadway Segment Mitigated
Lanes/ Class LOS E
Capacity
Existing + Cumulative Existing + Cumulative + Project + Mitigation
Mitigated? ADT V/C LOS ADT V/C LOS
Old Hwy 395 to I-15 SB Ramp
4MR 37,000 41,913 1.226 F 42,785 1.156 F Yes3
I-15 SB Ramp to I-15 NB Ramp
4MR 37,000 33,810 1.476 F 35,627 0.963 E Yes4
I-15 NB Ramp to Pankey Road
4MR 37,000 30,811 0.833 D 33,575 0.907 E Yes
Horse Ranch Creek Road to Rice Canyon Road
4MR 37,000 29,361 1.282 F 33,509 0.906 E Yes
Rice Canyon Road to Couser Canyon Road
4MR 37,000 29,308 1.280 F 33,820 0.914 E Yes
Source: Appendix M. Notes: 1 4MR: 4-lane Major; 2SR: 2-lane state route. 2 Funding for 6 lanes is not identified. 3 Undesirable LOS levels for this facility have been anticipated and accepted in the Mobility Element. 4 A substantial contribution to the cost of improvements has been identified at this location.
Table 2.11-13
Summary of Mitigated Intersections – Cumulative Conditions
Intersection
Existing
Existing + Cumulative + Project
Existing + Cumulative + Project + Mitigation Fully
Mitigated? Delay LOS Delay LOS Delay LOS
AM Peak Hour
1. SR 76/E. Vista Way 252.1 F 256.6 F 57.8 E No1
2. SR 76/N. River Road 220.3 F 226.7 F 27.5 C Yes
3. SR 76/Olive Hill Road/Camino Del Rey 136.4 F 139.3 F 61.2 E No1
4. SR 76/S. Mission Road 184.9 F 188.9 F 70.1 E Yes2
5. SR 76/Gird Road 165.7 F 173.4 F 26.1 C Yes
6. Old Highway 395/SR 76 160.4 F 162.7 F 32.5 C Yes
7. I-15/SR 76 SB Ramp 197.6 F 221.1 F 42.3 D Yes
8. I-15/SR 76 NB Ramp 95.8 F 127.7 F 26.1 C Yes
11. SR 76/Rice Canyon Road 114.7 F 465.8 F 14.6 B Yes
12. SR 76/Couser Canyon Road 25.8 D 28.5 D 13.4 B Yes
20. SR 76/Cole Grade Road 287.0 F 307.2 F 19.7 B Yes
PM Peak Hour
1. SR 76/E. Vista Way 248.2 F 253.9 F 106.9 F No1
2. SR 76/N. River Road 310.1 F 318.4 F 57.8 E No1
3. SR 76/Olive Hill Road/Camino Del Rey 206.5 F 211.1 F 105.7 F No1
4. SR 76/S. Mission Road 283.8 F 290.7 F 52.3 D Yes
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-46
Table 2.11-13
Summary of Mitigated Intersections – Cumulative Conditions
Intersection
Existing
Existing + Cumulative + Project
Existing + Cumulative + Project + Mitigation Fully
Mitigated? Delay LOS Delay LOS Delay LOS
5. SR 76/Gird Road 241.7 F 251.7 F 24.1 C Yes
6. Old Highway 395/SR 76 240.0 F 246.5 F 39.9 D Yes
7. I-15/SR 76 SB Ramp 335.5 F 357.9 F 79.0 E Yes
8. I-15/SR 76 NB Ramp 240.0 F 272.9 F 45.5 D Yes
11. SR 76/Rice Canyon Road 531.2 F Overflow F 11.8 B Yes
12. SR 76/Couser Canyon Road 297.6 F 933.8 F 23.9 C Yes
20. SR 76/Cole Grade Road 967.0 F Overflow F 16.3 B Yes
Source: Appendix M. Notes: 1 Funding for 6 lanes has not been identified. 2 Unacceptable LOS has previously been identified and accepted. 3 A substantial contribution to the cost of improvements has been identified for the interchange.
Table 2.11-14
Direct Impacts and Mitigation Measures
ID# Location Mitigation Measure Fully
Mitigated?
Direct Impacts
Segment
1 SR 76: West of E. Vista Way to N. River Road
The Caltrans SR 76 Middle Project, which widens SR 76 from two lanes to four lanes, is now complete.
Yes
2 SR 76: N. River Road to Camino Del Rey
3 SR 76: Camino Del Rey to S. Mission Rd
4 SR 76: S. Mission Road to Gird Road The Caltrans SR 76 East Project will widen SR 76 from two lanes to four lanes. Work on the ramps at the I-15 has been completed and construction has begun on the remainder.
Yes1
5 SR 76: Gird Road to Old Highway 395
6 SR 76: I-15 SB Ramp to I-15 NB Ramp
Intersection
1 SR 76 / E. Vista Way The Caltrans SR 76 Middle Project, which widens SR 76 from two lanes to four lanes, is now complete.
Yes
2 SR 76 / I-15 SB Ramp The Caltrans SR 76 East Project, which will reconfigure the interchange, is now completed.
Yes
3 SR 76 / I-15 NB Ramp
4 SR 76 / Project Entry2 Improve the project frontage and channelized/signalize the main public entrance intersection on SR 76 so that there are dual left turns for EB to NB movements and a deceleration lane for WB to NB traffic.
Yes
Source: Appendix M. Notes: 1 Caltrans Fact Sheet in Appendix M. 2 Signal warrants in Appendix M.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-47
Table 2.11-15
Project Traffic Percentages
Roadway Segment Existing Ex + Cum Project
Proj./ (Existing +
Proj.)
Project/ (Extg +
Cum+Proj)
SR 76 I-15 to Pankey 11031 33563 2764 20% 8%
SR 76 Pankey to Horse Creek Ranch 11031 32771 3348 23% 9%
SR 76 Horse Creek Ranch to Rice Canyon 11031 33493 4148 27% 11%
SR 76 Rice Canyon to Couser Canyon 11031 33802 4512 29% 12%
SR 76 Couser Canyon to W Pala Mission 10224 34010 4670 31% 12%
SR 76 W Pala Mission to E Pala Mission 10329 23580 606 6% 3%
SR 76 E Pala Mission to Lolac 8821 25904 606 6% 2%
SR 76 Lilac to Adams 9456 25390 394 4% 2%
SR 76 Adams to Cole Grade 9090 24376 370 4% 1%
Table 2.11-16
Cumulative Impacts and Mitigation Measures—Roadway Segments
ID# Location Mitigation Measure Fully
Mitigated?
Cumulative Impacts
Roadway Segment
1 SR 76: West of E. Vista Way to N. River Road Construct identified roadway segments to 6 lanes. No1
2 SR 76: N. River Road to Camino Del Rey
3 SR 76: Camino Del Rey to S. Mission Rd
4 SR 76: S. Mission Road to Gird Road Await the completion of the SR 76 East Project improvements to a 4 lane major roadway. Work on the ramps at I-15 is now complete and construction has begun on the remainder to obtain 4 lanes.
Yes2
5 SR 76: Gird Road to Old Highway 395
6 SR 76: Old Highway 395 to I-15 SB Ramp
7 SR 76: I-15 SB Ramp to I-15 NB Ramp
8 I-15 NB Ramp to Pankey Road Reclassify to a higher capacity to match configuration. Pay TIF fees for:
SR 76: Horse Ranch Creek Road to Rice Canyon Road
SR 76: Rice Canyon Road to Couser Canyon Road
No3
Yes4
9 SR 76: Horse Ranch Creek Road to Rice
Canyon Road
10 SR 76: Rice Canyon Road to Couser Canyon Road
11 SR 76: Couser Canyon Road to W. Pala Mission Road
Provide abutting improvements at the project frontage and design and construct improvements at the intersection of SR 76 with Cole Grade Road to the satisfaction of Caltrans (either a signal or roundabout as determined through a review under the I.C.E. Policy).
No5
12 SR 76: W. Pala Mission Road to E. Pala Mission Road
13 SR 76: E. Pala Mission Road to Lilac Road
14 SR 76: Lilac Road to Adams Drive
15 SR 76: Adams Drive to Cole Grade Road
Source: Appendix M.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-48
Notes: 1
The identified improvements are not included in the County’s TIF program and are outside of the jurisdiction and control of the County. Caltrans has no funding program in place into which the project could pay its fairshare, and it would be disproportionate to require the project to provide this improvement therefore, the cumulative impacts would remain significant and unmitigable.
2 Less than desirable levels of service have been disclosed and accepted for this portion of roadway in the recently adopted Mobility Element even after completion of the SR 76 East section improvements to a 4 lane expressway
3 The roadway has already been improved and further widening is not appropriate since the intersections at each end are operating adequately and more than 4 lanes have been built along portions of this length.
4 It is anticipated that the currently approve TIF program will be updated by the County to accommodate the land use changes that would result from the projects approval. This update would revise fee rates associated with incorporating the project’s land uses to the program. The TIF program enables the County new development to pay its “fairshare” by providing a mechanism to mitigate their cumulative impacts in accordance with CEQA requirements.
5 See correspondence with Caltrans in Appendix M.
Table 2.11-17
Cumulative Impacts and Mitigation Measures—Intersections
ID# Location Mitigation Measure Fully
Mitigated?
Cumulative Impacts
Intersection
1 SR 76 / E. Vista Way Improve SR 76 in this area to 6 lanes which also involves select intersection improvements to enhance their capacity.
No1
2 SR 76 / N. River Road
3 SR 76 / Camino Del Rey
4 SR 76 / S. Mission Road Await the completion of the SR 76 East Project improvements to a 4 lane major roadway which will also reconfigure the intersections. Work on this project has begun.
Yes2
5 SR 76 / Gird Road
6 SR 76 / Old Highway 395
7 SR 76 / I-15 SB Ramp Although the interchange is now improved; developer has agreed to make a fair-share contribution of up to 12.3% (see Table 8-3) of the unfunded cost of approximately $10M based upon Caltrans formula for calculating fair share as set forth in the Caltrans Guide for the Preparation of Traffic Studies.
Yes
8 SR 76 / I-15 NB Ramp
9 SR 76 / Rice Canyon Road1 Pay TIF fees. Yes3
10 SR 76 / Couser Canyon Road
11 SR 76 / E. Pala Mission Road1 Caltrans has indicated that it would accept the developer’s signalization and channelization at the intersection of Cole Grade Road/SR 76 for mitigation of impacts to SR 76 to be memorialized in a Highway Improvement Agreement between the developer and Caltrans.
No4
12 SR 76 / Lilac Road
13 SR 76 / Cole Grade Road1 Design and construct improvements at the intersection of SR 76 with Cole Grade Road to the satisfaction of Caltrans (either a signal or roundabout as determined through a review under the I.C.E. Policy).
Yes4
Source: Appendix M. Notes: 1 The identified improvements are not included in the County’s TIF program and are outside of the jurisdiction and control of the County.
Caltrans has no funding program in place into which the project could pay its fairshare, and it would be disproportionate to require the project to provide this improvement therefore, the cumulative impacts would remain significant and unmitigable.
2 Less than desirable levels of service have been disclosed and accepted for this portion of roadway in the recently adopted Mobility Element even after completion of the SR 76 East section improvements to a 4 lane expressway
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-49
3 It is anticipated that the currently approved TIF Program will be updated by the County to accommodate the land use changes that would result from the project’s approval. This update would revise fee rates associated with incorporating the project’s land uses to the program. The TIF program enables County new development to pay its “fair share” by providing a mechanism to mitigate their cumulative impacts in accordance with CEQA requirements.
4 See correspondence with Caltrans in Appendix M.
Table 2.11-18
Fair Share Percentages
Roadway Segment
Existing Total
Cumulative Growth Project Fair Share
ADT ADT ADT ADT % of
Growth
State Route 76
I-15 NB Ramp to Pankey Road1 11,031 33,575 22,544 2764 12.3%
1 This is the information on which to base the fair share contribution to the unfunded improvements at the I-15/SR 76 interchange. The payments would be collected proportionally to the permits issued for the project.
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-50
INTENTIONALLY LEFT BLANK
Project Study AreaFIGURE 2.11-1
WARNER RANCH PROJECT - ENVIRONMENTAL IMPACT REPORT
SOURCE: Shapouri
Project Site
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-52
INTENTIONALLY LEFT BLANK
^
^
^
^
^
§̈¦15
UV395
UV76
Old H
ighway 395
Old
Hw
y 39
5
Couser Canyon Rd
Lila
c Rd
Cole GradeRoad
PankeyRoad
Adams DriveSR-76 - Existing4 Lane Section
Pala DelNorte
SixthStreet
AdamsDrive
ColeGradeRoad
PALA-PAUMA MOBILITY ELEMENT NETWORKPROPOSED AMENDMENT
LegendWarner Ranch
SANGIS Parcels
SR-76 - Pala Road SegmentsFrom Pala Del Norte to SR-76 Existing 4 Lane Section 3.1 Miles
From Adams Drive to Cole Grade Road 1.9 Miles
From sixth Street to Pala Del Norte 2.2 Miles
From Sixth Street to Pala Del Norte 2.2 Miles
General Plan Accepted LOS F Segment
O0 0.5 10.25
MilesDate: 12/18/2015
From Pala Del Norte to the Existing 4 Lane Section East of Pankey Road
3.1 Miles
Proposed General Plan LOS F Segment
From Adams Drive to Cole Grade Road 1.9 Miles
Proposed General Plan LOS F Segment
Proposed Mobility Element Network AmendmentFIGURE 2.11-2
WARNER RANCH PROJECT - ENVIRONMENTAL IMPACT REPORT
SOURCE: Shapouri
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-54
INTENTIONALLY LEFT BLANK
Direct Impact LocationsFIGURE 2.11-3
WARNER RANCH PROJECT - ENVIRONMENTAL IMPACT REPORT
SOURCE: Shapouri
Project Site
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-56
INTENTIONALLY LEFT BLANK
Cumulative Impact LocationsFIGURE 2.11-4
WARNER RANCH PROJECT - ENVIRONMENTAL IMPACT REPORT
SOURCE: Shapouri
Project Site
2.11 Transportation and Traffic
December 2016 6653
Warner Ranch EIR 2.11-58
INTENTIONALLY LEFT BLANK