County of Fairfax, Virginia 2017 VDOT Repaving and Restriping – Springfield, VA MARCH 28, 2017 ADAM LIND – PROJECT MANAGER DEPARTMENT OF TRANSPORTATION Bicycle, Pedestrian, and Traffic Safety Improvements

Upload: fairfax-county

Post on 09-Apr-2017

275 views

Category:

News & Politics


0 download

TRANSCRIPT

Page 1: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

2017 VDOT Repaving and Restriping – Springfield, VA

MARCH 28, 2017ADAM LIND – PROJECT MANAGER

DEPARTMENT OF TRANSPORTATION

Bicycle, Pedestrian, and Traffic Safety Improvements

Page 2: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Overview•Why are we here?•What projects are being proposed?•Where are we in the process?•What are we asking from the community?•What are the next steps?

DEPARTMENT OF TRANSPORTATION 2

Page 3: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

VDOT Annual Repaving•VDOT Summer repaving includes several roads in the Hunter Mill District. Opportunity to review pavement markings and street design. Proposals are limited to restriping the existing pavement.

•Opportunity to slow speeding traffic, provide transportation options, and improve traffic, bicycle, and pedestrian safety

•No additional cost for the County

•Want to hear from the community about issues/concerns• Some concerns may be addressed through restriping

For information on all paving in Lee District visit:www.virginiaroads.org

DEPARTMENT OF TRANSPORTATION 3

Page 4: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

•Commerce Street ◦Old Keene Mill to Franconia Road – 1.2 mi

•Loisdale Road◦Franconia Road to Spring Mall Dr – 0.4 mi

DEPARTMENT OF TRANSPORTATION 4

Streets Under Review

Page 5: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 5

Bicycle Master PlanAdopted by the Board of SupervisorsOctober 28, 2014

Bike Lanes

Bike Lanes

Bike Lanes Sharrow

Page 6: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Bicycle Facility Types

•Sharrow•Climbing Lane•Striped Shoulder•Bike Lane•Buffered Bike Lane More dedicated space and comfort

Less dedicated space and comfort

Page 7: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Bicycle Facility Types Sharrow-Shared Lane Markings (SLMs), or “sharrows,” are road markings used to indicate a shared lane environment for bicycles and automobiles. Among other benefits shared lane markings reinforce the legitimacy of bicycle traffic on the street, recommend proper bicyclist positioning, and may be configured to offer directional and wayfinding guidance

Page 8: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Bicycle Facility Types Striped Shoulder-Creates dedicated space to be used by people bicycling. 3’-4’ in width, but not the full width of a bike lane (5’). Added benefit of creating additional buffer space between vehicles and people walking on the sidewalk.

Page 9: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Bicycle Facility Types Bike Lane-Bike lanes designate an exclusive space for bicyclists through the use of pavement markings and signage. The bike lane is located adjacent to motor vehicle travel lanes and flows in the same direction as motor vehicle traffic.

Page 10: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Bicycle Facility Types Climbing Lane-A climbing lane incorporates two different facilities on the same roadway segment; a bike lane is provided in the uphill direction to accommodate slower moving bicyclists and a sharrow is provided in the downhill direction, where bicyclists can typically travel at a speed closer to motorists.

Page 11: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Bicycle Facility Types Buffered Bike Lane-Buffered bike lanes are conventional bicycle lanes paired with a designated buffer space separating the bicycle lane from the adjacent motor vehicle travel lane and/or parking lane.

Page 12: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Lane Diets

DEPARTMENT OF TRANSPORTATION 12

A Lane Diet is generally described as narrowing travel lanes from a roadway and utilizing the space for other uses and travel modes. Does not involve reducing the number of travel lanes Benefits

◦ Providing transportation alternatives and options◦ Increasing safety for non-motorized users◦ Reduce speeding

Page 13: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, VirginiaLane Width and Vehicle Speeds

DEPARTMENT OF TRANSPORTATION 13

Page 14: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Road Diet• Removing travel lanes from a roadway and

reallocating the space for other uses

• Rule of thumb: Roads with less than 20,000 vehicles per day don’t need four (or more) travel lanes

• Have now implemented road diets in several places in Fairfax County◦ Lawyers Rd, Soapstone Dr, Kingstowne Village Parkway, Westbranch

Dr, Greensboro Dr, Park Run Dr, Beacon Hill Road, Ravensworth Rd

DEPARTMENT OF TRANSPORTATION 14

Page 15: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Commerce Street- Existing

DEPARTMENT OF TRANSPORTATION 15

•Old Keene Mill to Franconia Rd•Fall 2016 Traffic Count: 10,500 vehicles per day (vpd)• VDOT 2015: 23,000 vpd between Backlick

Rd and Franconia Rd

•Speed Limit: 35 MPH•Three segments:

• 1) Old Keene Mill to Amherst Avenue• 2) Amherst Avenue to Brandon Avenue• 3) Brandon Avenue to Old Keene Mill

Page 16: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 16

•Section 1) Old Keene Mill to Amherst Avenue

Commerce Street - Existing

Page 17: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 17

Segment 1 Old Keene Mill to Amherst Avenue: 10,500 vpd

Commerce St– Traffic & Speed Data

Southbound DirectionSpeed Limit: 35 mph

85th Percentile: 37 mph76% Traffic: ≤ 35 mph19% Traffic: 36-40 mph4% Traffic: 41-45 mph0.5% Traffic: 46-50 mph

Northbound DirectionSpeed Limit: 35 mph

85th Percentile: 38 mph67% Traffic: ≤ 35 mph24% Traffic: 36-40 mph7% Traffic: 41-45 mph1% Traffic: 46-50 mph

Page 18: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 18

•1) Old Keene Mill to Amherst Avenue• Convert the outside travel lane in each direction to a buffered bike lane• Evaluate the addition of two new crosswalks with potential concrete refuge island (funded, but separate

from repaving and restriping)

•2) Amherst Avenue to Brandon Avenue• Narrow the existing travel lanes to 11’• Add bike lane east bound towards the bridge• Shared lane/sharrow west bound away from the bridge

•3) Brandon Avenue to Old Keene Mill• Narrow the existing travel lanes to 11’• Create 4’ shoulder for bicycle use

Page 19: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 19

•Section 1) Old Keene Mill to Amherst Avenue• Convert the outside travel lane in each direction to a buffered bike lane• Evaluate the addition of two new crosswalks with potential concrete refuge island (funded, but separate

from repaving and restriping)

•Section 2) Amherst Avenue to Brandon Avenue• Narrow the existing travel lanes to 11’• Add bike lane east bound towards the bridge• Shared lane/sharrow west bound away from the bridge

•Section 3) Brandon Avenue to Old Keene Mill• Narrow the existing travel lanes to 11’• Create 4’ shoulder for bicycle use

Commerce Street- Proposed

Page 20: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 20

•Section 1) Old Keene Mill to Amherst Avenue (street width varies)

Commerce Street- Proposed

Existing Proposed

Page 21: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 21

•Section 1) Old Keene Mill to Amherst Avenue

Commerce Street- Proposed

Page 22: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 22

•Section 1) Old Keene Mill to Amherst Avenue

Commerce Street- Proposed

Page 23: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 23

•Old Keene Mill Intersection• No changes to the lane configuration approaching the intersection

Commerce Street- Proposed

Page 24: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 24

•Amherst Avenue Intersection

Commerce Street- Proposed

Existing Proposed

Through+ right

Through+ right

Page 25: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 25

•Section 1) Old Keene Mill to Amherst Avenue•Road Diet benefits everyone by:

• Improving sight distance• Shortening crossing distance• Reducing # of travel lanes to cross in a vehicle or on foot• Providing refuge space• Creating buffer between travel cars and vehicles• Creating dedicated space for people to safely bicycle• Reducing top end speeding

Commerce Street- Proposed

Page 26: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Traffic Impacts• Intersections evaluated on average delay or Level of

Service (LOS)• Intersections grade A-F, based off LOS• Proposed changing of signal timing to

mitigate loss of one through lane EBLevel of Service

Average Delay

A <10 sec

B >10-20 sec

C >20-35 sec

D >35-55 sec

E >55-80 sec

F >80 sec

Page 27: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, VirginiaTraffic Impacts – Commerce St

AM LOS Existing

AM LOS Road Diet

PM LOS Existing

PM LOS Road Diet

Amherst Ave

D(42.5 sec)

D(44.2 sec)

D(47.5 sec)

D(50.5 sec)

• Eastbound Commerce St at Amherst Avenue

• Eastbound Commerce St 50% que length changed from 74’ to 151’ (AM) and 84’ to 196’ (PM)

• VDOT has ability to change signal timing to mitigate delay impact from changing lane configuration

Page 28: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 28

•Section 2) Amherst Avenue to Brandon Avenue•Amherst Avenue to Backlick Rd

• Was repaved in 2015 when Amherst Ave and Backlick Ave were repaved

• No proposed changes at this time, but may be able to add sharrows sharrows

Commerce Street- Proposed

Page 29: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 29

•Backlick Rd to Brandon Avenue• Narrow Travel Lanes, EB bike lane, WB sharrow

Existing Proposed

Commerce Street- Proposed

Page 30: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 30

•Section 3) Brandon Avenue to Old Keene Mill• Narrow Travel Lanes, 4’ striped shoulder in each direction (5’ in

some places)Existing Proposed

Commerce Street- Proposed

Shoulder

Shoulder

Page 31: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 31

•1) Old Keene Mill to Amherst Avenue• Convert the outside travel lane in each direction to a buffered bike lane• Evaluate the addition of two new crosswalks with potential concrete refuge island (funded, but separate

from repaving and restriping)

•2) Amherst Avenue to Brandon Avenue• Narrow the existing travel lanes to 11’• Add bike lane east bound towards the bridge• Shared lane/sharrow west bound away from the bridge

•3) Brandon Avenue to Old Keene Mill• Narrow the existing travel lanes to 11’• Create 4’ shoulder for bicycle use

Page 32: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Loisdale Road - Existing

DEPARTMENT OF TRANSPORTATION 32

•Franconia Rd to Spring Mall Dr•VDOT 2015: 23,000 vpd

•Speed Limit: 35 MPH•Two segments:

• 1) Franconia Rd to Loisdale Ct• 2) Loisdale Ct to Spring Mall Dr

Page 33: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 33

•Section 1) Franconia Road to Loisdale Ct

Loisdale Road - Existing

Page 34: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 34

•Section 1) Franconia Road to Loisdale Ct• Narrow Travel Lanes, 5’ bike lanes in each direction

Existing Proposed

Loisdale Road - Proposed

Page 35: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 35

•Section 2) Loisdale Ct to Spring Mall Drive

Loisdale Road - Existing

Page 36: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

DEPARTMENT OF TRANSPORTATION 36

•Section 2) Loisdale Ct to Spring Mall Drive• Keep travel lanes at same width, add sharrows

Loisdale Road - Existing

Existing Proposed

Page 37: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Past Repaving Projects2015 Road Diet Project – Westbranch Drive•Pre-Project Conditions• Five travel lanes 12’ wide

•Post-Project Conditions• Three travel lanes 12’ wide• Two buffered (6’) bike lanes 6’ wide

DEPARTMENT OF TRANSPORTATION 37

Page 38: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia2015 Project – Westbranch Drive: Before

DEPARTMENT OF TRANSPORTATION 38

Page 39: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia2015 Project – Westbranch Drive: After

DEPARTMENT OF TRANSPORTATION 39

Page 40: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Past Repaving Projects2015 Lane Diet Project-Annandale Road•Pre-Project Conditions• Two travel lanes 16’+ wide•Two parking lanes 8’ wide

•Post-Project Conditions• Two travel lanes 11’ wide• Two bike lanes 5’ wide• Two parking lanes 8’ wide

DEPARTMENT OF TRANSPORTATION 40

Page 41: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia2015 Project-Annandale Road: Before

DEPARTMENT OF TRANSPORTATION 41

Page 42: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia2015 Project-Annandale Road: After

DEPARTMENT OF TRANSPORTATION 42

Page 43: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

After – Annandale Rd

DEPARTMENT OF TRANSPORTATION 43

Post Lane Diet + Bike Lanes•Speed/Traffic counts at two locations in Fall 2016

•Highest average speed was 35 mph

•No 85% percentile speed over 39 mph

Page 44: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Big Picture

DEPARTMENT OF TRANSPORTATION 44

“Safety in numbers: more walkers and bicyclists, safer walking and bicycling” Peter Jacobsen, 2000

•Research in the US and internationally shows that when more people walk/bike the safer it becomes

Page 45: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Big Picture

DEPARTMENT OF TRANSPORTATION 45

Page 46: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

Next Steps•Comment period open for two weeks

• April 14, 2017

•FCDOT and VDOT will review input and update designs•Finalize design plans spring 2017 and repaving occurs in summer/fall 2017

DEPARTMENT OF TRANSPORTATION 46

Page 47: 2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and Traffic Safety Improvements

County of Fairfax, Virginia

How to Comment•Fill out comment sheets and submit tonight•Mail comment sheets in over next three weeks•E-mail comments to [email protected] •Presentation will be available online: http://www.fairfaxcounty.gov/fcdot/bike/commerce-loisdale-streetsimprovements2017.htm

Thank You for Participating

DEPARTMENT OF TRANSPORTATION 47