2017 ncdot contract administration workshop...• total number of projects = 223 • projects...
TRANSCRIPT
![Page 1: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/1.jpg)
March 16, 2017
2017 NCDOT Contract Administration Workshop
Lamar Sylvester, PE State Construction Engineer
![Page 2: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/2.jpg)
Project Delivery
2
![Page 3: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/3.jpg)
3
Project Delivery Expectations
• Safety • On Schedule • Teamwork • Timely Issue Resolution • Budget Conscious
![Page 4: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/4.jpg)
Project Delivery – All Projects Calendar Years 2012 – 2016
4
46.9%
31.8%
21.3% % Complete byOriginal CompletionDate% Complete byRevised CompletionDate% Not Complete byOriginal or RevisedCompletion Date
• Total Number of Projects = 2,918 • Projects Completed by the Original Completion Date = 1,369 • Projects Completed by the Revised Completion Date = 928 • Projects Not Completed by the Original or Revised Completion Date = 621
*Based on Final Estimates Paid
![Page 5: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/5.jpg)
Project Delivery – All Projects Calendar Year 2016
5
45.8%
36.3%
17.8% % Complete byOriginal CompletionDate% Complete byRevised CompletionDate% Not Complete byOriginal or RevisedCompletion Date
• Total Number of Projects = 622 • Projects Completed by the Original Completion Date = 285 • Projects Completed by the Revised Completion Date = 226 • Projects Not Completed by the Original or Revised Completion Date = 111
*Based on Final Estimates Paid
![Page 6: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/6.jpg)
Project Delivery – All Projects 2012 - 2016
Calendar Year
Total No. Projects
Complete by Contract
Completion Date
Complete by Revised
Completion Date
Not Complete by Contract Completion
Date or Revised Completion Date
2012 523 217 (41.5%)
168 (32.1%)
138 (26.4%)
2013 606 302 (49.8%)
177 (29.2%)
127 (21.0%)
2014 590 282 (47.8%)
176 (29.8%)
132 (22.4%)
2015 577 283 (49.0%)
181 (31.4%)
113 (19.6%)
2016 622 285 (45.8%)
226 (36.3%)
111 (17.8%)
6
![Page 7: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/7.jpg)
Project Delivery – All Projects Calendar Years 2012 - 2016
7
0%
10%
20%
30%
40%
50%
60%
2012 2013 2014 2015 2016
% Complete by OriginalCompletion Date
% Complete by RevisedCompletion Date
% Not Complete byOriginal or RevisedCompletion Date
![Page 8: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/8.jpg)
Project Delivery – Resurfacing Projects Calendar Years 2012 – 2016
8
49.6%
22.8%
27.6%
% Complete by OriginalCompletion Date
% Complete by RevisedCompletion Date
% Not Complete byOriginal or RevisedCompletion Date
• Total Number of Projects = 928 • Projects Completed by the Original Completion Date = 460 • Projects Completed by the Revised Completion Date = 212 • Projects Not Completed by the Original or Revised Completion Date = 256
*Based on Final Estimates Paid
![Page 9: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/9.jpg)
Project Delivery – Resurfacing Projects Calendar Year 2016
• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion Date = 62 • Projects Not Completed by the Original or Revised Completion Date = 63
9
43.9%
27.8%
28.3% % Complete byOriginal CompletionDate
% Complete byRevised CompletionDate
% Not Complete byOriginal or RevisedCompletion Date
*Based on Final Estimates Paid
![Page 10: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/10.jpg)
Project Delivery – Resurfacing Projects 2012 – 2016
10
Calendar Year
Total No. of
Projects
Complete by Contract
Completion Date
Complete by Revised
Completion Date
Not Complete by Contract or Revised
Completion Date
2012 163 72 (44.2%)
37 (22.7%)
54 (33.1%)
2013 178 90 (50.6%)
39 (21.9%)
49 (27.5%)
2014 172 87 (50.6%)
36 (20.9%)
49 (28.5%)
2015 192 113 (58.9%)
38 (19.8%)
41 (21.4%)
2016 223 98 (43.9%)
62 (27.8%)
63 (28.3%)
![Page 11: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/11.jpg)
Project Delivery – Resurfacing Projects 2012 – 2016
11
0%
10%
20%
30%
40%
50%
60%
70%
2012 2013 2014 2015 2016
% Complete byOriginal CompletionDate
% Complete byRevised CompletionDate
% Not Complete byOriginal or RevisedCompletion Date
![Page 12: 2017 NCDOT Contract Administration Workshop...• Total Number of Projects = 223 • Projects Completed by the Original Completion Date = 98 • Projects Completed by the Revised Completion](https://reader034.vdocuments.site/reader034/viewer/2022050117/5f4e3ad7306b88735717fa48/html5/thumbnails/12.jpg)
Questions?
12