2016 annual lake victoria water servics board report
TRANSCRIPT
In Pursuit of Quality Access
Lake Victoria South Water Services Board
ANNUAL STAKEHOLDERS REPORT
2015/16
Photo: Completed Migori Water Project financed by AfDB
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 ii
ABBREVIATIONS
AFD : French Development Agency
AfDB : African Development Bank
ASK : Agricultural Society of Kenya
CEO : Chief Executive Officer
CoK : Constitution of Kenya
EACC : Ethics and Anti-Corruption Commission
EIB : European Investment Bank
GoK : Government of Kenya
ISCs : Inspectorate of State Corporations
KFW : German Development Bank
KICC : Kenyatta International Convention Centre
KIDDP : Kenya-Italy Debt for Development Programme
KOICA : Korea International Cooperation Agency
LTIs : Long Term Interventions
LVSWSB : Lake Victoria South Water Services Board
LVWATSAN : Lake Victoria Region Water and Sanitation Initiative
MWI : Ministry of Water and Irrigation
NRW : Non-Revenue Water
ORIO : Facility for Infrastructure Development of Netherlands
PS : Principal Secretary
PWDs : People With Disabilities
SPA : Service Provision Agreement
STRWSSP : Small Towns Rural Water Supply and Sanitation Projects
UNICEF : United Nations Children Education Fund
WSBs : Water Services Boards
WSPs : Water Service Providers
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 iii
TABLE CONTENT
ABBREVIATIONS ........................................................................................................................ ii
INSTITUTIONAL BACKGROUND .......................................................................................... 1
CORPORATE MISSION ............................................................................................................. 1
CORPORATE VISION ................................................................................................................ 1
CORE VALUES ............................................................................................................................ 1
CORE FUNCTIONS ..................................................................................................................... 1
STRATEGIC OBJECTIVES .......................................................................................................... 2
BOARD OF DIRECTORS ............................................................................................................ 3
CORPORATE GOVERNANCE STATEMENT ........................................................................ 5
MANAGEMENT STAFF ............................................................................................................. 6
QUALITY POLICY STATEMENT ............................................................................................. 8
CHAIRMAN‟S STATEMENT .................................................................................................... 9
ACTING CHIEF EXECUTIVE OFFICER‟S STATEMENT ................................................... 12
PROJECTS‟ REPORT ................................................................................................................. 14
PHOTO GALLERY .................................................................................................................... 39
OTHER SUCCESSES AND ACHIEVEMENTS ..................................................................... 40
EVENTS BY STAKEHOLDERS................................................................................................ 40
CORPORATE SOCIAL RESPONSIBILITIES ......................................................................... 41
CUSTOMER SATISFACTION ................................................................................................. 41
CHALLENGES ........................................................................................................................... 41
WAY FORWARD ....................................................................................................................... 42
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 1
INSTITUTIONAL BACKGROUND
Lake Victoria South Water Services Board (LVSWSB) is a non-commercial State
Corporation under the Ministry of Water and Irrigation (MWI). The Board was
established by the Water Act (2002) vide Gazette Notice No. 1714 of 12th March 2004
with the mandate of “ensuring efficient and economic provision of Water and
Sanitation Services in its area of jurisdiction”. Geographically, it covers 21,720 Sq. Km
in the host Counties of Kisumu, Siaya, Migori, Homa Bay, Bomet, Kericho, Nyamira,
Kisii and parts of Nandi and Narok Counties. The aggregate jurisdictional population is
estimated at 8.75 million with a distribution of 21% in urban and 79% in rural areas.
LVSWSB has signed Service Provision Agreements (SPAs) with eight (8) urban and over
eighty six (86) rural Water Services Providers (WSPs) to operate and maintain its service
provision assets.
CORPORATE MISSION
The Board‟s Mission is “to provide adequate water and sanitation infrastructure and
related services in a sustainable manner”.
CORPORATE VISION
The Board‟s vision is “to be the most efficient and effective Water Services Board in
Kenya”.
CORE VALUES
The Board upholds these fundamental beliefs which define our expected standards of
behaviour and culture:
Professionalism
Transparency
Accountability
Equity
Involvement
Consistency
CORE FUNCTIONS
Developing national public water and sanitation works.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 2
Formulating water services development and investment plan for rural and urban
areas.
Mobilizing resources for infrastructure development and improvement of water
services delivery.
Facilitating establishment and efficient operations of cross-county and other water
services providers.
Providing technical assistance in water infrastructural development.
Ensure proper co-ordination of stakeholders for enhanced synergy and increased
impact in water services.
STRATEGIC OBJECTIVES
The Constitution of Kenya [CoK] (2010) bestows on every individual the right to clean
and safe water in adequate quantities. The attainment of economic and social rights in
the framework of our mandate demands a clear roadmap that is aligned to Kenya‟s
Vision 2030. In this endeavour, LVSWSB prepared a five year strategic plan (2013-17)
realigned to the Kenya‟s second Medium Term Plan (2013-2017) and performance
contracting guidelines. Our strategic objectives include:
Strategic objective 1: To develop and manage national public water and
sanitation, infrastructure to increase water services
coverage from 53% to 63% (water) from 30% to 50%
(sanitation) by 2017.
Strategic objective 2: To develop, contract and regulate viable and
sustainable water service providers (WSPs).
Strategic objective 3: To provide technical support in water services
provision for sustainability and operational
efficiencies.
Strategic objective 4: To mobilize resources and facilitate funding for
infrastructure development to enhance service
delivery.
Strategic objective 5:
To enhance collaborations and synergies with actors
and stakeholders both within and outside water
sector.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 3
Strategic objective 6:
Strategic objective 7:
To update development and investment plans for
water and sanitation services.
To strengthen internal processes and human
resource capacity to enhance equity and efficiency
in service delivery.
BOARD OF DIRECTORS
The LVSWSB is governed by the Board of Directors in accordance with Section 51 of the
Water Act (2002) and Section 6 of the State Corporations Act (2015).
The Code of Governance for State Corporations, Mwongozo (2015), defines the role and
functions of the Board of Directors as follows:
Exercise of their role collectively and not individually;
Determine the organization‟s mission, vision, purpose and core values;
Set and oversee the overall strategy and approve significant policies of the
organizations;
Ensure that strategy is aligned with the purpose of the organization and the
legitimate interests of its shareholders and other stakeholders;
Ensure that strategy of the organization is aligned to the long term goals of the
organization on sustainability so as not to compromise ability of the future
generalizations to meet their own needs;
Approve the organization‟s structure;
Approve annual budget of the organization;
Monitor the organization‟s performance and ensure sustainability;
Ensure the corporate image of the organization;
Ensure availability of adequate resources for the achievement of the
organization‟s objectives;
Hire the CEO on such terms and conditions of service as may be approved by the
relevant Government organ(s) and approve appointment of senior management
staff; and
Ensure effective communication with the stakeholders.
The current Board of Directors was constituted by the Kenya Gazette Notice 2914 of 27th
April 2015 (Directors), No. 2919 of 27th April 2015 (Chairman), and No. 4468 of 17th June
2016 (additional members). In addition, there are three (3) Alternate Directors to
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 4
Principal Secretary (PS) Ministry of Water and Irrigation (MWI), PS National Treasury,
and Director Inspectorate of State Corporations (ISCs).
Dir. Hudson Mugodo Alternate to PS, Treasury
Hon. Amb. John Arap Koech Chairman
Dir. Joshua Ouma Alternate to PS, MWI
Dir. Dr. Betty Korir Independent Director
Dir. David Gichuhi Alternate to Director, ISCs
Dir. Rosemary Rumo Independent Director
Dir. George Ayugi Independent Director
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 5
Other Directors appointed vide Gazette Notice No.4468 of 17th June 2016 are:
Dir. Joash Barack Owuor - Independent Director
Dir. Consolata Adhiambo Onguto - Independent Director
Dir. Victor Omanwa - Independent Director
Dir. Rose Aluoch Gonda - Independent Director
CORPORATE GOVERNANCE STATEMENT
The Board of Directors of LVSWSB is committed to the values and principles of good
corporate governance. Good corporate governance requires that the Board must govern
the Corporation with integrity and in a manner that entrenches and enhances corporate
mandate under Section 53 of the Water Act (2002). This mandate embraces the
Corporation‟s collaboration with Government agencies and other stakeholders such as
Dir. Hellen Makone Independent Director
Dir. Hilary Alila Independent Director
Dir. Andrew Sunkuli Independent Director
Dir. Violet Omwamba Independent Director
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 6
sector regulators, County Governments, development partners, business community,
WSPs, consumers of water services, media, pressure groups and the general public.
The Chairman Board of Directors, Board members and Management of LVSWSB regard
corporate governance as pivotal to the successes of the Board and are unreservedly
committed to ensuring that good corporate governance is practiced. This guarantees the
Board as a sustainable and viable vehicle towards realization of sector development.
As a public service organization, LVSWSB‟s decisions are guided by the core tenets
prescribed in the Public Officers Ethics Act, and internal codes of conduct. We
continually strive to strengthen and sustain the trust that the Government, the water
sector and the public have placed on us.
Accordingly, the Board and its Committees regularly evaluate the latest national and
international standards with the aim of incorporating them in the operational processes
of LVSWSB so as to consistently deliver on our mandate.
MANAGEMENT STAFF
The LVSWSB Management is responsible for day-to-day institutional operations. The
Chief Executive Officer (CEO) is the Board‟s Accounting Officer and communicates
policy matters to other employees. There are four departments headed by Chief
Managers: Technical Services, Finance, Corporate Planning, and Human Resource and
Administration. The heads of Procurement and Legal Services report directly to the
CEO, while the Internal Auditor functionally reports to the Board of Directors but
administratively to the CEO. The departments are subdivided into divisions which are
headed by Managers.
Chrispine O. Juma, HSC - Ag. Chief Executive Officer
Mr. Chrispine Omondi Juma is currently the LVSWSB‟s acting Chief Executive Officer. He is a graduate of the University of Nairobi with BSc (Geology) and has MSc (Geology) from the same University. Mr. Juma also holds BSc (Geo-Hydrology) from University of Orange Free State in Bloemfontein, South Africa. He is currently pursuing PhD course in Water Resources Modelling at University of Poitiers in France.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 7
Eng. Sammy Mburu - Chief Manager Technical Services
Eng. Sammy Mwangi Mburu is a graduate of University of
Nairobi with BSC in Civil Engineering. He is a full member of
the Engineers‟ Registration Board (ERB) and an elected
member of the Institution of Engineers of Kenya (IEK). Eng.
Mburu also holds Master of Business Administration in
Strategic Management from the University of Nairobi.
Mr. Josiah Arabu Moriasi - Chief Manager Corporate
Planning
Mr. Josiah Arabu Moriasi is LVSWSB‟s Chief Manager
Corporate Planning. He holds Master of Business
Administration in Finance from Kenyatta University and
Bachelor of Education and Human Resources from Egerton
University. Currently, he is pursuing PhD in Business
Administration (Finance) at Jomo Kenyatta University of
Agriculture and Technology. Mr. Moriasi is also a Certified
Public Secretary (CPS-K) and a Certified Security and
Investment Analyst (CSIA-K).
Mr. Sammy. K. Kigen - Chief Manager Human Resources
and Administration
Mr. Sammy Kigen is a holder of BA in Anthropology and
Governance from the University of Nairobi. He is also a
holder of higher Diploma in Human Resources Management
and full member of the Institute of Human Resource
Management (IHRM). Mr. Kigen has a vast work experience in
Human Resource Management spanning a period of over 30
years.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 8
Ms. Phyllis Chepkemboi - Manager Legal and Compliance
Ms. Phyllis Chepkemboi is an Advocate of the High Court of
Kenya and a member of the Law Society of Kenya. She also
holds Master of Business Administration in Human Resource
Management from Maseno University. Currently, she is
pursuing Certified Public Secretary (CPS) course at KASNEB.
CPA Francis Otieno Odera - Chief Manager Finance
CPA Francis Otieno Odera is LVSWSB‟s Chief Finance Manager. He is a graduate of Catholic University of Eastern Africa (CUEA) with Bachelor of Commerce and Master of Business Administration (Finance). CPA. Odera is a member of Institute of Certified Public Accountants – Kenya (ICPAK).
QUALITY POLICY STATEMENT
LVSWSB is ISO 9001:2008 Certified. Its quality policy statement provides a framework
for establishing and sustaining quality objectives.
“Lake Victoria Water Services Board is committed to providing quality customer service
by developing and effectively managing water and sanitation facilities as well as
establishing viable Water Service Providers for efficient supply of safe, adequate and
reliable water and sewerage services at an affordable tariff.
The Board, management and staff of Lake Victoria South Water Services Board are
committed to do this by:
Establishing and maintaining an effective Quality Management System in line
with ISO 9001:2008 requirements;
Measuring all aspects of the Quality Management System as a basis for continual
improvement;
Improving the system through training and investment in new facilities and
technology;
Complying with statutory, regulatory, customer and other requirements; and
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 9
Promote a culture in which all employees share in this quality policy for
continuous improvement.
CHAIRMAN’S STATEMENT
Hon. Amb. John Arap Koech Chairman Board of Directors – LVSWSB
LADIES AND GENTLEMEN
On behalf of the Board of Directors of Lake Victoria South Water Services Board, I take
this ample opportunity to sincerely welcome you to this year‟s Annual Stakeholders
Conference. The theme for this year‟s conference, “Collaboration for Quality Water
Access”, symbolizes the need and urgency for a more coordinated approach in fast-
tracking water asset development and realization of our strategic goals.
Over the last one year, the Board has maintained stability in delivering services to the
Kenyan citizens in accordance with its mandate as spelled out in the Section 53 of the
Water Act (2002). Further to this, I assure you of the Board‟s commitment towards
improving service provision in all areas comprising our jurisdiction. This commitment
subsequently serves as a basis upon which our stakeholders are called to participate in
project identification, financing, implementation and management.
Investment Volume
In the FY 2015/16, the Board injected Ksh.1.24 billion into asset development to serve an
approximated population of 319,497 people in our host Counties. This volume of
investment increased water coverage from 58% in 2014/15 to an average of 60% this
year. Within the same period, sanitation coverage went up from 38% to 43%. We owe
these achievements to the support from the Government of Kenya through the Ministry
of Water and Irrigation, host County Governments, development partners, Water
Service Providers and other esteemed stakeholders.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 10
Implementation of Strategic Plan 2013-17
The LVSWSB family is united by its vision of being “an effective and efficient Water
Services Board in Kenya”. Realization of this dream is guided by our corporate strategy
which defines our long term goals and means to success. In the FY 2015/16, the Board
continued to monitor implementation of its strategic plan 2013-17 to ensure realization
of water service coverage target of 63% and sanitation of 50% by June 2017. We
successfully carried out mapping of our stakeholders and relevant actors, and now we
are at advanced stage of developing investment plans for both rural and urban areas,
taking into consideration the County Integrated Development Plans.
Upholding National Values
The National Values as enshrined in Article 10 of the Constitution gives us
responsibility as a public institution to be at the forefront in upholding and promoting
them. These essential values have always been fundamental in guiding our corporate
and individual actions. In the FY 2015/16, the Board promoted equity and sustainable
development by ensuring fair distribution of project activities in all our host Counties.
We also championed integrity in use of public resources by partnering with responsible
national agencies such as EACC. Under good corporate governance, the Directors
expressed their commitment by signing the Mwongozo code of conduct. Moreover, the
Board continued to encourage public participation in all project activities to enhance
broader ownership and sense of responsibility.
Recruitment of Senior Managers
The Board of Directors appreciates the technical support from the Corporation‟s senior
management and the staff in general. Their synergy and mastery of individual roles and
responsibilities have indeed been reliable in shifting the Board to another higher level of
service delivery. In the FY 2015/16, the Board strengthened top management by
successfully recruiting three substantive departmental heads for Finance, Corporate
Planning and Technical Services. In addition, the Board recruited Manager in charge of
Urban Water Service Provision.
Operational Challenges
Access to clean and safe water is a subject of many challenges which we all have to deal
with in the quest of realizing the constitutional threshold enshrined in Article 43(1)(d).
Some of the challenges include trans-boundary disputes, limited cash-flows, increasing
operational costs, litigations in land acquisitions and way-leaves, and anxiety created by
delayed passage of the Water Bill. These challenges could easily be mitigated if our
concerted efforts are unified by the desire to serve Kenya and her citizens.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 11
National Goals
Finally, I would like to reiterate that asset development and management is
fundamental in achieving our national aspirations. Coupled with prudent service
management, it is a recipe to a vibrant water sector that can drive the Kenyan economy
towards meeting present and emerging challenges. And, we shall have contributed
immensely towards reduction of poverty, attainment of Sustainable Development Goals
and realization of Vision 2030.
With these few remarks, Ladies and Gentlemen, I strongly believe that we will continue
to work as a team and give our people the services they so urgently desire.
I NOW declare this year‟s Annual Stakeholders Conference officially Open.
Hon. Amb. John Arap Koech Chairman Board of Director - LVSWSB
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 12
ACTING CHIEF EXECUTIVE OFFICER’S STATEMENT
Mr. Chrispine O. Juma, HSC Ag. Chief Executive Officer - LVSWSB
I am delighted and indeed I consider this a special privilege to welcome all of you, our
esteemed stakeholders to this all-important Stakeholders Conference, which is
convened under the theme “Collaboration for Quality Water Access”. The reasoning
behind this year‟s theme is anchored on your unwavering support and our collective
thoughts that we exist for the service of others.
The FY 2015/16 marked yet another milestone for the LVSWSB as we endeavoured to
fulfil our mandate of “ensuring efficient and economic provision of water and
sanitation services in our area of jurisdiction”. In this front, we strengthened our
corporate reputation in core areas such as investment planning, project implementation
and water supply management.
The Board‟s performance commitments in FY 2015/16 were based on our Strategic Plan
2013-17, which was designed to actualize 63% water coverage and 50% coverage in
sanitation by June 2017. Through the support of the Government of Kenya and our
development partners, I am happy to report that one year before closure we are at 60%
and 43% water and sanitation coverage respectively. Our planned project activities in
the FY 2016/17 are thus geared towards meeting and even exceeding the set service
provision levels.
As a State Corporate in an essential and „development-enabler‟ sector, the LVSWSB
plays a critical role towards realization of national economic goals. Currently, we are
implementing FOUR Vision 2030 flagship projects which include Kisii Water Supply
and Sanitation Project (financed by KFW & GoK), Siaya-Bondo Water Supply and
Sanitation Project (financed by AfDB & GoK), Bonyunyu Multipurpose Dam (finance by
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 13
ORIO & GoK), and Rehabilitation and Expansion of Kisumu Sewerage Project (financed
by AFD & GoK). At completion, these projects will serve a population of 967,000 (water)
and 150,000 (sewerage) up to the year 2035.
The Board is also implementing Priority Projects in Kericho, Keroka, Isebania, Nyamira
and Litein towns under LVWATSAN II financed by AfDB and GoK. Moreover, there
are 34 projects in difference phases of implementation financed through the
Constituency Development Programme by the Government of Kenya.
To enhance water service provision in our region‟s small towns, the Board is finalizing
feasibility studies and detailed designs for 10 projects before making proposals to the
financiers. Several interventions are also ongoing in the rural areas through our
partnership with various Community Based Organizations.
In the period under review, the Board engaged itself in various Corporate Social
Responsibilities which served our specific intent of promoting access to water and
sanitation services, while at the same time executing our advocacy role in national
cohesion and upholding of national values. In this respect, the Board identified 46
public primary and secondary schools as deserving beneficiaries of 10M3 plastic water
tanks to promote rain water harvesting and storage. We also sensitized the Youth,
Women and People with Disabilities on public tendering to meet the Government
threshold of 30% reservation. In addition, we held public sessions on HIV/Aids at
various project areas to promote awareness and behaviour change.
I restate the Chairman‟s view that the water sector is prone to several challenges. And
under these challenges our expectation is to thrive. This could easily be realized in the
stability and spirit of our oneness, a reason why we convene here today.
Finally, I sincerely thank the LVSWSB Board of Directors and staff for their superior
dedication in ensuring that we perform our mandate for the benefit of the current and
future generations.
Thank you and God bless you.
Mr. Chrispine O. Juma, HSC Ag. Chief Executive Officer
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 14
In Pursuit of Quality Access
PROJECTS’ REPORT
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 15
SUMMARY OF PROJECTS
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
1 Migori Migori and Uriri
Migori Water supply Project
AfDB & GoK
1,250
Construction of 10m wide intake weir on river Oyani. Construction of 2.4 km long precast concrete culverts of 900mm diameter raw water main. Construction of 19,000m3/day water treatment plant consisting of 3no flocculation chambers, 3no sedimentation basins and 6no. rapid sand filters. Laying of 200m DN 400 steel rising main, Construction of 1no 1000m3clear water tank at treatment plant, 1no. 5000m3RC tank at Magongo hill, 2no. 1500m3RC tank at Kadika hills and Migori town, 1no 250m3RC tank at Kakrao and 1no.100m3RC tank at Nyasare, Laying of 53Km pipeline (28.3km transmission mains pipe diameter ranging from 450,400,300 and 200mm and 24.7km distribution pipeline pipe diameters ranging from 100, 80 and 50mm). Supply and installation of 3no electric pumps. Construction of a booster station consisting of pump house, double family house, generator shed, 250m3 reinforced concrete sump tank, installation of 630 KVA generator, installation of 630 KVA substations. Construction of 15no water kiosks and 4no revenue collection offices. Installation of a piped water system for
Project completed and is operational (awaiting
commissioning).
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 16
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
Uriri sub-county by drilling and equipping 7no boreholes, construction of 6m high concrete water tower, supply and installation of 1no 10m3 plastic water tank to each borehole. Rehabilitation of existing spring water source at Uriri, construction 100m3 masonry tank, laying of 590m DN 80mm GI pumping line from the spring source to the 100m3masonry tank. Laying of 21.1 km distribution lines of 100, 80, 50 and 32 mm GI pipes from the boreholes and spring source. Construction of 7no water Kiosks for Uriri. Supply of operation and maintenance equipment consisting of 2no exhausters, 3no double cabin vehicles, 8 no. motor cycles, 2 no. leak detection equipment‟s, 1no JVC Excavator, 5 tonne lorry, 1no meter repair bench complete with measuring devises and 1no mobile workshop. The project is to serve a population of 200,000 people up to 2034 in Migori towns and environs.
2 Kisumu Kisumu Town West and East
Kisumu Water supply project
AFD & GoK
2,303.657
Construction of Kajulu intake weir, Laying of 100m DN 600mm raw water steel pipeline. Construction of 36,000m3 /day treatment plant consisting of 3no. flocculation tanks, 3no. Sedimentation tanks and 6no. Rapid sand filters) Construction of 7 no. reinforced concrete ground level reservoirs (1no.1000 m3
Project completed and is operational (awaiting
Commissioning).
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 17
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
backwash tank at Kajulu, 1 no.5000m3 contact tank at Kajulu, 1 no. 1300m3 at Obwolo, 1 no. 5000 m3at Mamboleo, 1 no. 2100 m3at Kanyamedha, 2 no. 6000 m3 at Kibuye). Construction of 2 no. steel elevated steel tanks (250m3at LVSWSB compound and 100m3 at Dunga). Laying of 94.5 km pipeline (16.37km transmission line from DN 200 to DN 700 and 78.082km distribution network from DN90 to DN 700). Supply of 6560 consumer meters and 250 prepaid consumer meters. Supply of materials for Nyalenda Delegated Management Model; 34.8km OD12 Upvc pipes, 0.8km of OD50 Upvc pipes plus valves and fittings. The project is to serve 663,000 people for Kisumu City up to 2030.
3 Kisumu Kisumu Town West and East
Kisumu Sewerage
Project LTAP
Package 3
AFD & GoK
1,284
Rehabilitation of KISAT treatment works, Construction of 3no. new pumping stations including supply and installation of pumps at Mumias road pumping to Kisat treatment plant, Sunset pumping station to Nyalenda ponds and Tom Mboya pumping station to Nyalenda ponds., Desludging of 9 no. Nyalenda pond of total volume 174,00m3.
Construction of3 no. new Anaerobic ponds and 3 no. new maturation ponds at Nyalenda ponds. Laying of 20.01km sewer
Project completed and is operational (awaiting commissioning).
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 18
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
line trunk mains and tertiary sewer lines both concrete and steel pipes DN 600. Construction of 393 manholes. Supply of Operation and Maintenance Equipment‟s; 1 no. single cabin, 5no. Motor cycles Backhoe excavator, mechanical rodding equipment‟s, meter repair bench and leak detection equipment‟s. The project aims to serve over 300,000 people in Kisumu City up to 2030.
4 Siaya Bondo, Gem, Alego Usonga
Siaya - Bondo Water supply project
AfDB & GoK
1,560
Rehabilitation of Sidindi Malanga intake works,Laying of new 305m DN 450 steel raw water main, Construction of 12,000m3/day new treatment plant, Rehabilitation of existing treatment plant to produce 7000m3/day, Laying of 4.1km DN450 steel rising main from Sidindi Malanga to Nyamninia reservoir. Rehabilitation 4.1km DN 350 existing rising main. Construction 1 no. 1000m3RC clear water contact tank at Sidindi Malanga, Construction 1 no. 1000m3RC BPT tank at Ngiya, Construction of 2 no. 3000m3 RC storage tanks at Gobei ( supply Bondo town) and Sigana ( supply Siaya town). Construction of 3300m3 RC storage reservoir at Nyamninia. Laying of 46km DN450/350 steel/Upvc transmission main from Nyamninia reservoirs to Bondo and Siaya towns. Laying of 48km DN315/160
Project commenced in March 2013 and is expected to be completed by September 2016.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 19
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
Upvc distribution lines in Bondo and Siaya towns. Construction of 24 community water points along the pipeline route. Construction of 5 no. 150m3 elevated steel tanks. Extension of 35km distribution lines of DN160, DN110, DN90 and DN 50 GI/Upvc pipes. Supply and installation of 5 no hydro turbines, Supply of 500 consumer meters. Supply of Operation and maintenance equipment‟s 2 no. double cabin vehicle, 2 no. leak detection equipment and 5 no. motor cycles. The project s to serve 200,000 people in Siaya and Bondo towns and its environment.
5 Kericho Ainamoi
Kericho Sewerage Improve
ment Project
AfDB & GoK 201
Installation of Kericho CBD and South CBD sewer line consisting of 365m DN 280 Upvc, 1725m DN 315 Upvc, 1080m DN 450 concrete pipe, 460m DN 525 concrete pipe, 2323m DN 225 Upvc, 209m DN 225 concrete pipe, 1100m DN 160 Upvc pipe. Rehabilitation of Kericho sewerage treatment work comprising of increasing the inlet structure by 500mm, refurbishment of 2 no. primary and secondary sedimentation tanks. Reconstruction of two trickling filters, placing of filter media and introduction of culture. Rehabilitation of four sludge digesters. Refurbishment of sludge drying
The project commenced in April 2014 and its physical progress is at 70% complete.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 20
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
beds. Replacing of 2 no. reticulation pumps Installation of a masonry perimeter fence and steel gate. Provision of lighting within the treatment works. The project is to serve 70,000 additional people. It will serve 60% of the town by treating 10,000 m3
6 Nyamira Keroka
Keroka water
supply project
AfDB & GoK
769.3
Construction of intake weir on river Kuja, Construction of 3000m3/day treatment plant, Construction of 1 no. 500m3 clear water tank and 1 no. 150m3backwash elevated steel tanks, Laying of 11km DN 250mm steel rising main. Laying of 16.5km DN160-DN40 Upvc distribution lines. Construction of 1no. 500m3 RC tank in Keroka town. Construction 150m3 elevated steel tank at Ichuni. Construction of 2 no. 50m3 masonry tanks. Supply and installation of 4 no. electrical pumps (raw water and clear water). Supply and installation of 1 no. pump station standby Diesel Engine Generator set. The project targets to serve 56, 000 people in Keroka town and its environment.
The project started in January 2015 and is 80% complete. Expected completion date in December 2016.
7 Migori Isebania Isebania Water supply
AfDB & GoK
Construction of intake weir on river Hibwa, Construction of 3000m3/day treatment plant, Construction of 1 no. 500m3RC clear water tank and 1 no. 150m3backwash elevated steel tank at
The project started in January 2015 and is 80% complete. Expected completion date in December 2016.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 21
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
treatment plant, Laying of 9.6km DN 250mm steel rising main. Laying of 19.5km DN250-DN40 Upvc distribution lines. Construction of 1no. 1000m3 RC storage tank in Isebania town. Construction of 1 no. 50m3 masonry tank. Supply and installation of 4 no. electrical pumps (raw water and clear water). Supply and installation of 1 no. pump station standby Diesel Engine Generator set. The project targets to serve 56, 000 people in Keroka town and its environment.
8 Homa bay
Rangwe
Rangwe water
supply project ( Kosiga dam)
GoK 45
Dam rehabilitation to increase its capacity by 10,000m3, construction of treatment works (2 no. 25m3/hr CFU), Construction of 25m3 steel back wash tankconstruction of 100m3 RC clear water tank, Laying of 1km DN 150 rising main, Construction of 250m3 RC tank at Aimo hills. Construction of pump house, supply and installation of 2 no. high lift and back wash pumps. The project targets to serve 15,000 people.
The project commenced in February 2015 and is expected to be completed in August 2016.
9 Kericho Belgut/ Buret
Litein water
supply system
KFW & GoK
560
Construction of new river intake on River Kimugu, Construction of 7660m DN 600 raw water gravity main. Construction of 13,000m3/day treatment plant. Construction of 1 no. 250m3 elevated backwash steel tank, 1 no. 5000m3 RC storage tank and 1 no. 1000m3 RC tank at
For Short term intervention tendering at advanced stage. Construction expected to commence in August 2016 and to end in August 2017. Long term intervention detailed design reports
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 22
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
Kipsirkong. Laying of 50.6km from DN 60 to DN 600 steel and Upvc transmission and distribution pipelines. Supply and installation of electromechanical equipments. The project targets to serve 118,000 people in Kericho town and 32,400 in Litein town.
submitted. Tender documents issued to pre-qualified contractors. Ground breaking for Long Term Intervention in January 2017. The project expected to be completed in December 2019.
10 Kisii
Nyaribari - chache, Kitutu - chache and Bonchari
Kisii water
supply expansion works
KFW & GoK
1,500
Improvement of existing Kegati Intake works on river Gucha by construction of steel girder bridge with a spanof 25m across river Gucha over the existing intake weir. Laying of 150m length DN 700 steel raw water pumping main. Expansion of existing Kegati treatment works from capacity of 6500m3/day to 27,000m3/day. Laying of 3.4km DN 700 steel treated water pumping main from Kegati treatment works to Bobaracho tanks. Laying of 2.8km DN 400 steel treated water pumping main from Bobaracho to Nyanguru tank. Construction of 1 no. 5000m3 RC tank at Bobaracho and 1 no. 500m3 RC tank at Nyanguru. Construction of a Booster pumping station at Bobaracho with a capacity 5,700m3/day. Laying of 35km DN 80 to DN 400 Upvc and steel distribution mains. The project targets to serve 150,000 people in Kisii and Nyamira County.
For Short term intervention tenders opened, evaluation ongoing. Construction expected to commence in August 2016 and to end in August 2017. Long term intervention detailed design reports submitted. Tender documents to be issued to pre-qualified contractors. Ground breaking for Long Term Intervention in January 2017. The project expected to be completed in December 2019.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 23
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
11 Nyamira West Mugirango
Nyamira water
supply
KFW & GoK 461
Rehabilitation of intake works, Construction of 1.3km DN 200 steel new raw pumping main. Rehabilitation of existing Nyamira water treatment plant capacity 4000m3/day. Construction of 1.0km DN 200 steel new treated water pumping main from Nyamira treatment works to Nyamira Hospital storage tank. Improvement of existing Kebirigo pumping station of capacity 1350m3/day by construction of new pump house, installation of new pumps and associated works. Rehabilitation of existing of distribution network with new pipelines sizes DN 50 to DN 200 approximate total length 30km. Construction of 3 no 500m3 RC tank at Ibara, Rangenyo and Nyamira hospital. The project targets to serve 110,000 people in Nyamira.
For Short term intervention tendering at advanced stage. Construction expected to commence from August 2016 and to end in August 2017. Long term intervention detailed design reports submitted. Tender documents issued to pre-qualified contractors. Ground breaking for Long Term Intervention in January 2017. The project expected to be completed in December 2019.
12 Nyamira and Kisii
Kisii
Kisii Water
Storage (Bonyuny
u Dam) Project
ORIO 5,838
The project will require the construction of new physical infrastructure comprising: A dam and storage reservoir at Bonyunyu, an intake structure, 1.5 km long raw water main and treatment plant at Girango, with a daily capacity of 41,000 m3; 11.5 km long treated water transmission main, operating under gravity flow conditions and including passage via a tunnel under Boboracho hill to inlet water tanks near Kisii High school; Extension of the
Review of feasibility study (Development phase) commenced in May 2016. The study is to be completed in February 2017.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 24
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
transmission main to Tombe Hills, Minihydropower facility, Water storage tanks Distribution network, several Kiosks/standpipes
13 Homa bay
Rachuonyo north
West Karachuonyo water supply project
KIDDP 87
Construction of Intake works, 4000m3/day treatment plant, 2.9 km rising main, installation of 2 no. low lift and 2no. High lift pumps The project targets to serve 79,410 people.
The project commenced in October 2013 and is currently at 85%. Physical progress. Construction on going to be commissioned by December 2016.
14 Homa bay
Suba
Sindo water supply project
KIDDP
70
Construction of intake works, 1800 m3/day treatment plant, 10 km distribution pipelines, tanks and water kiosks. The project targets to serve 12,000 people.
The project started in August 2009 and stalled in 2011 at 60%. The Board retendered incomplete works in 2015 and Contractor has mobilized to site. Work commenced in January 2016 is expected to be completed in September 2016.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 25
S/No
County Constituency Project Name
Financier Cost (Millions)
Scope & Target Areas Status
15
Kisumu, Siaya, Homa Bay, Kisii, Nyamira, Bomet, Kericho
Seme, Alego, Rangwe, Bomet Central, North Mugirangu, Ainamoi, Nyaribari Chache and Ugunja
Constituency Development projects
GoK
100
The project comprises drilling and equipping of 5 no. Boreholes, construction of 8 no. pans/dams, construction of 2 no. gravity water supply schemes at Manyororo Murereti and Chuboit and Rehabilitation of Kisumu rural water supply. The projects targets to serve 80,000 people in eight Constituencies.
The projects started in January 2015 and to be completed by December 2016.
16
Migori and Homa Bay
Migori Town, Homa Bay Town
Migori – Homa Bay Sewerage Works (Migori- Homa bay Wastewater (Trilateral Program))
KFW & Israel &
GoK
1,900
The project is prepared under Trilateral Development Cooperation between Governments of Kenya, Germany and Israel. The project comprises construction of new sewerage network and treatment system in Migori of capacity 4,000m3/day , expand sewerage network in Homa Bay from 1750m3/day to 4,000m3/day ,develop Industrial Wastewater Control Tool kit, on job –training facility in Kisumu for operators of wastewater systems in LVSWSB region
At proposal formulation stage
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 26
PLANNED PROJECTS
S/No
County Town/Location Project Name Financier Approximate cost
in millions KSH Approximate No. of people to be served
Status
1 NAROK Kilgoris Kilgoris water supply and sanitation project
Proposed to AfDB under STRWSSP II
380 80,000 Feasibility study and detailed designs ongoing.
2 NAROK
Lolgorian Lolgorian water supply and sanitation project
Proposed to AfDB under STRWSSP II
100 40,000
Feasibility study and
detailed designs
ongoing.
3 Nandi Hills County
Nandi Hills Nandi Hills water supply and sanitation project
Proposed to AfDB under STRWSSP II
720 85,000
Feasibility study and
detailed designs
ongoing.
4 SIAYA Ugunja, Ukwala and Sega
Sega, Ugunja and Ukwala water and sanitation project
Proposed to AfDB under STRWSP II
850 100,000
Feasibility study and
detailed designs
ongoing.
5 Bomet Bomet Bomet water supply and sanitation project
Proposed to AfDB under STRWSSP II
960 40,000
Feasibility study and
detailed designs
ongoing.
6 Homa bay
Kendu Bay Kendu bay water supply and sanitation project
Proposed to AfDB under STRWSSP II
780 30,000
Feasibility study and
detailed designs
ongoing.
7 Homa bay
Oyugis Oyugis water supply and sanitation project
Proposed to AfDB under STRWSSP II
940 50,000
Feasibility study and
detailed designs
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 27
S/No
County Town/Location Project Name Financier Approximate cost
in millions KSH Approximate No. of people to be served
Status
ongoing.
8 Homa bay
Mbita Mbita bay water supply and sanitation project
Proposed to AfDB under LVWATSAN III
350 30,000
Feasibility study and
detailed designs
ongoing.
9 Homa Bay
Ndhiwa Ndhiwa water supply and sanitation project
Proposed to AfDB under STRWSSP II
350 30,000
Feasibility study and
detailed designs
ongoing.
10 Migori Kehancha Kehancha water supply and sanitation project
Proposed to AfDB under LVWATSAN III
400 35,000
Feasibility study and
detailed designs
ongoing.
CONSTITUENCY DEVELOPMENT PROJECTS FUNDED BY GoK
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
1 BOREHOLE DRILLING, CAPPING & TEST PUMPING
1.1 Nyamira North Mugirango
Nyamatuta Borehole
Drilling, test pumping and capping of 1No. Borehole.
Ksh.2,498,756.00
The borehole has been drilled to completion.
1.2 Nyamira North Nyamusi Drilling, test Ksh.2,883,876.00 Borehole drilling
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 28
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
Mugirango Borehole
pumping and capping of 1No. Borehole.
Completed with a yield of 14M3/hour
1.3 Nyamira North Mugirango
Gitwebe Borehole
Drilling, test pumping and capping of 1No. Borehole.
Ksh.2,723,680.00
Borehole drilled to completion with a yield of 10M3/hour.
1.4 Kisii Nyaribari Chache
Kabosi Borehole Drilling, test pumping and capping of 1No. Borehole
Ksh.2,520,448.00
Borehole drilled to completion, equipped and now operational.
1.5 Siaya Ugunja Sikalame Borehole and Tingare Boreholes
Drilling, test pumping and capping of 2No. Boreholes
Ksh.3,591,128.00
Both boreholes drilled to completion and test pumped with yields of 28 M3/hour for Sikalame and 4M3/hr for Tingare
2 WATER PAN & ASSOCIATED WORKS
2.1 Homabay Rangwe Amake Dam Construction of Dam
Ksh.4,750,240.00
Work in progress 70%.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 29
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
2.2 Homabay Rangwe Kogonda Dam Construction of Dam
Ksh.4,700,284.60
Complete and operational
2.3 Siaya Alego Rabuor Pan Construction of pan and associated works
Ksh.3,412,706.00
Complete and operational
2.4 Siaya Alego Nyawere Pan Construction of pan and associated works
Ksh.3,554,958.00
Work ongoing. Progress 60%
2.5 Siaya Alego Koga Pan Construction of pan and associated works
Ksh.2,747,839.00
Complete and operational
2.6 Siaya Alego Ulafu Pan Construction of pan and associated works
Ksh 1,978,285.00
Works ongoing. Progress 75%
2.7 Bomet Bomet Central Berirbei Dam Construction dam and associated works
Ksh.4,947,877.00
Complete and operational
2.8 Bomet Bomet Central Soliot Pan Construction of pan and associated works
Ksh.3,806,081.20
Complete and operational
3 SMALL RURAL WATER SUPPLY SCHEMES
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 30
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
3.1 Kericho Ainamoi Manyoro Mureret Water Supply
Construction of gravity scheme water supply. Spring protection, Pipeline, 1No.50m3tank,
Ksh.12, 881,539.00.
Work in progress. Overall progress 30%
3.2 Homabay Suba Civil works for water supply to suba District Hospital, waondo Youth polytechnic and Majengo
Civil works for supply of water to Suba District Hospital
Ksh.22,979,198.60 Overall work progress is 40%.
Works in progress.
3.3 Kisumu Seme Rehabilitation of Kisumu Rural Water Supply
Scope of works entails rehabilitation of the water supply, repair of pipelines, filter media, kiosks. Scope of works scaled down
kshs. 6,887,100.00.
Work progress 40%
3.4 Kericho Kipkelion East Juboit
Construction of Dam.
Ksh 14,000,000.00
Work ongoing. Progress 30%
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 31
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
4 PLANNED RURAL WATER PROJECTS
4.1 Kericho Kipkelion West Kapngetuny Water Supply
Construction of intake works,gravity mains and ground masonry tanks,.
Design work ongoing Under design and tender document preparations
4.2 Kericho Kipkelion East Kiptangit Lemotit water project
Rising main and distribution main of total length 5.4 km
Under Design and Tender document preparations
Design and tender documentation under review
4.3 Kericho Kipkelion East Tulwap Gravity Water supply
8 km pipeline, spring protection, and construction ofb50 m3 ground masonry tank.
Under Design and tender document preparations
Design and tender documentation under review
4.4 Kericho Kipkelion Kapseger Borehole
Drilling and equipping of borehole
Under Design and tender document preparations
Design and tender documentation under review
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 32
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
4.5 Siaya Ugunja Naya Community borehole water supply
Pump installation Rising main, construction 50 m3 ground masonry tank, 850 meter rising main, 3 km distribution pipelines, solar pumping system
Design completed, Tender preparation for borehole equipping and other civil works in progress.
Design and tender documentation under review
4.6 Siaya Ugunja Uluthe Community borehole water supply
Pump installation Rising main, construction 50 m3 ground masonry tank, 850 meter rising main, 3 km distribution pipelines, solar pumping system
Design completed, Tender preparation for borehole equipping and other civil works in progress
Design and tender documentation under review
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 33
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
4.7 Kericho Kipkelion Kimologit water project
Gravity main and distribution pipelines
Under design Under design and tender document preparations
4.8 Kericho Kipkelion Kutung - techasis water project
Intake, pipelines and ground tank 50 m3
Under Design Under design and tender document preparations
4.9 Kericho Kipkelion Mogire Water project
Intake, gravity main and distribution pipelines and ground tank 50 m3 capacity
Under design Under design and tender document preparations
4.10 Kericho Kipkelion Mariam Water project
Pipeline and main tank construction of capacity 50 m3
Under design Under design and tender document preparations
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 34
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
4.11 Kericho Kipkelion Timbilil water Project
Intake works and pipeline
Under design Under design and tender document preparations
4.12 Kericho Kipkelion Nduro Water project
Pipeline and tank construction.
Under planning and design Under design and tender document preparations
4.13 Kericho Kipkelion Tendwet water project
Pipelines and 50 m3 masonry ground tank
Under planning and design Under design and tender document preparations
4.14 Bomet Chepalungu Nderemiat water pan
Dam Construction
Under planning and design Under design and tender document preparations
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 35
S/No. County Constituency Project name Scope of works
Estimate cost Remarks
4.15 Bomet Sotik Kimugul Water Pan
Construction of dam
Under design Under design and tender document preparations
4.16 Homabay Rangwe Ngegu Water supply
Construction of gravity water supply
Under design Under design and tender document preparations
4.17 Homabay Mbita Tinga(Oseno) Dam
Construction of a dam
Under design Under design and tender document preparations
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 36
OUR STAKEHOLDERS
Engaging and building relationships with all Board stakeholders is key to sustainably
realizing our strategic objectives. Our stakeholders include individuals, groups of
individuals and organizations that directly or indirectly affect or are affected by our
activities, services and associated performance.
The stakeholder base is broad, including Government of Kenya (through Ministry of
Water and Irrigation), regulatory authorities, County Governments, development
partners, business community, employees, media, WSPs, water consumers and general
public. This means that there are many different views and expectations that LVSWSB
needs to respond to and manage to ensure operational sustainability.
Our approach is to have frank conversations on issues that concern our stakeholders as
tabulated:
Stakeholder Why we engage Stakeholder expectations
How we engage
Ministry of Water and Irrigation
The MWI is our primary development partner through which the Board obtains development counterpart funds. It sets policy framework that guides asset development in the sector.
Sector regulation; improved sector performance; and realization of policy objectives.
Quarterly performance reports; financial reports; circular feedbacks, consultative fora; and official visits.
Regulatory Authorities (WASREB, NEMA, WARMA and others)
The water sector is highly regulated and the Board has committed to comply with all legal provisions and guidelines.
Compliance with regulations; environmental protection; cascading policy; and sector information.
Approvals; regular reports; audits and surveillance.
County Governments
We engage with the host County Governments to ensure a coordinated approach in project formulation and
Transfer of devolved functions, improved coverage and sector
Project formulation, partnering on key programmes, representation in WSPs, consultations
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 37
implementation through resource mobilization and asset management.
performance, collaboration and synergy.
and public for a.
WSPs One of the most important ways we interact with our customers is through our SPA partnership with WSPs. As custodians of our mandate, we engage with WSPs to ensure excellent customer service across all the areas of jurisdiction.
User-friendly SPAs; infrastructure improvements; institutional capacity building; sector information; friendly regulations.
Public participations; project formulation; consultative fora; operational reports; performance audits
Development Partners
As the providers of capital necessary to support our growth, we engage with our development partners to keep them up to date on the financial need, performance and overall project sustainability.
Prudent management of resources; transparency, accountability and good governance; effective project implementation.
Annual and interim reports; quarterly operational reviews; consultative fora; and approvals.
Employees Our employees are the heart and soul of our existence. Their skills and involvement determine our ability to realize our vision, best value and best service, and to fulfil our purpose of empowering Kenya.
Career development; improved knowledge sharing; simplicity and agility; engagement; building skills in line with the future business growth; and fair remuneration
Performance contracting and appraisals, team meetings, intranet, newsletters, social media.
Business Contractors/Consultants and suppliers impact on
Timely payment and fair terms;
Supplier forums; ongoing site visits;
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 38
Community our ability to provide services. They are required to comply with our health, safety and ethical procurement standards. Engaging with them contributes to business continuity, viability and operational efficiency.
improving health and safety standards; and partnering on environmental solutions.
audits; and regular direct engagements
Media As a stakeholder, the media plays a role in keeping LVSWSB stakeholders informed of operational developments, services and the impact of our activities.
Being informed of key activities; timely payments; and transparency.
Face-to-face and telephone engagement; interviews with the Chairman and key Executives; media releases and publicity; site visits; and project reports.
General Public The general public is central to the sustainability of our operations. To build trust among members of public, engagement also helps us to better manage operational risk.
Improved service delivery; and investments that reflect value for money.
Websites; public participations; mainstream and social media; public fora; and CSR.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 39
PHOTO GALLERY
Completed Migori Water Supply financed AfDB and GoK. CS. Hon. Eugene Wamalwa inspecting the
completed Migori Water Supply
On - going works at Keroka Water Supply CS. Hon Eugene Wamalwa at The LVSWSB Stand at the World Water Day in Naivasha
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 40
Inspection of on-going works at Siaya-Bondo Water Project Malongo Nyangwethe Rural
Water Project in Suba
OTHER SUCCESSES AND ACHIEVEMENTS
In the year under review, the Board realized other successes and achievements as
follows:
Smart Metering by acquiring and installing auto-transmission bulk-meters for
accurate and real-time monitoring of water flow to reduce human error and
NRW in Kisii and Litein towns;
Acquisition of the most advanced Terrameter for hydrogeological survey. The
equipment is available for hire by qualified hydrogeologists from the region.
Promotion of National Cohesion and National Values through equitable
distribution of development projects, public participation, and review of Board
policies in line with the requirements of Article 10(2) of the CoK;
Collaboration with EACC to audit Board‟s financial systems and sensitize
Directors and Management on integrity and corruption prevention; and
Involvement and empowerment of Youth, Women and PWDs in national
development by ensuring uptake of 30% tenders reservation.
EVENTS BY STAKEHOLDERS
The Board participated in a number of events organized by some of our stakeholders as
follows:
National World Water Day celebrations held on 22nd March 2016 in Naivasha;
Regional World Water Day celebrations held on 22nd March 2016 at River Auji in
Kisumu;
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 41
Kisii Entrepreneurship Summit held on 24th to 26th February 2016 in Kisii town;
10th Regional Nile Day celebrations on 22nd February 2016 in Vihiga County;
Annual Tree Planting Day by the Agricultural Society of Kenya (ASK) on 20th
May 2016 at Otieno Oyoo Secondary School in Kisumu County;
Annual Stakeholders Forum organized by Lake Victoria North Water Services
Board on 24th June 2016; and
African Public Service Day organized by the Ministry of Public Service, Youth
and Gender Affairs on 23rd June 2016 at KICC Nairobi.
CORPORATE SOCIAL RESPONSIBILITIES
The Board has identified 46 deserving public primary and secondary schools from all
the Counties under jurisdiction to benefit from 10M3 capacity plastic water-tanks in
quest of promoting rain water harvesting and storage. In addition, the Board held a
public sensitization on HIV/Aids and behaviour change at Siaya-Bondo Water Project
where residents received free status counselling.
CUSTOMER SATISFACTION
The Board conducted a customer satisfaction survey in June 2016 to establish the impact
of its various activities and performance in the FY 2015/16. Data were obtained by
stratification from sampled individuals and institutions having direct relationship with
the Board. Subsequent analysis showed a positive index-shift from 91% recorded in
2014 to 94%. This was attributed to widening service coverage, ongoing project
activities and visibility initiatives undertaken by the Board and its stakeholders.
CHALLENGES
The Board met the following challenges during the year under review:
Unpaid bills to contractors and suppliers due to delayed disbursement of
counterpart funds;
Low revenue mobilization from WSPs due to operational challenges;
Delay in land and way-leave acquisition. For instance, in Keroka and Isebania
Long Term Interventions (LTIs), the Board is still unable to access land for the
construction of sanitary landfill and fecal sludge treatment plants;
High operational costs and water-supply disruptions due to power
disconnections; and
Anxiety caused by delayed passage of Water Bill.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 42
WAY FORWARD
In the FY 2016/17, the Board of Directors and Management will seek to address
identified challenges by:
Engaging national authorities to fast-track disbursement of counterpart funds;
Continue to partner with host County Governments and other stakeholders to
mitigate devolution-related challenges;
Timely acquisition of land and way-leaves through collaborative engagements
with both the County and National Governments;
Continue to embrace gravitational designs and renewable energy options to
lower operational costs; and
Review SPAs with WSPs to befit the requirements of devolved functions.
Lake Victoria South Water Services Board
Annual Stakeholders Report 2015/16 43
In Pursuit of Quality Access