2016-0712 presentation for port · presentation to port commission - july 12, 2016 agenda: •...

16
Fire Station 35 - The Boathouse Earthquake Safety and Emergency Response (ESER) 2014 SFFD PRESENTATION TO PORT COMMISSION - JULY 12, 2016 Agenda: • Project • Marine Engineering • Context • Precedents

Upload: others

Post on 04-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

Fire Station 35 - The Boathouse Earthquake Safety and Emergency Response (ESER) 2014

SFFDPRESENTATION TO PORT COMMISSION - JULY 12, 2016

Agenda:

• Project• Marine Engineering• Context• Precedents

Page 2: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 2Building Design & Construction 2

Project: AERIAL PHOTO OF EXISTING SITE

photo credit: COWI

Page 3: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 3Building Design & Construction 3

• Existing Pier/Dock/Parking: 14,820 GSF • Remaining Pier (After Demo): 7,000 GSF • Proposed New Pier*: 19,400 GSF• Existing Pier Remaining: 7,000 GSF• Total Shadow (Remaining + New): 26,400 GSF

Bay Trail

PIER 24

FS 35

Shed

Bay Trail

PIER 24

FS 35

Pier Length - 180 ft

Pier Width - 80 ft

15 ft

Bay Trail

PIER 24

FS 35

* includes: Barge or Pier = 14,400 sf; Ramp = 2,000 sf; Float (200’x15’) = 3,000 sffor total shadow of all three NEW components on the Bay

Project: COMPARISON: SHADOW STUDY ON BAY: EXISTING - TO BE DEMOLISHED - PROPOSED NEW

Page 4: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 4Building Design & Construction 4

EXISTING FACILITY (Historic and Shed) 6,100 gsf

NEW PROPOSED FACILITY 18,305 gsf Existing Program (Resized to correct Code and Program Requirements) 8,890 sf Dormitory (adequately sized) Officers’ Quarters Kitchen Dining Room Lockers/Showers/Toilets (separate genders) Day Room Fitness + Study Rooms Storage Circulation and Gross Factor to accomodate walls, structure, and mechanical

Existing Offsite Program 1,975 sf Jet Skis Rescue Boats Port Response Vehicles Oil Containment Room Fire Fighting Hose Fire Fighting Foam Scuba/Tank Filling Specialty Gear/Rescue Gear Storage

Fire Department Program Requirements 7,440 sf Fireboat Working Area Ambulance Access out of Public Viewing Patient area Cranes To Raise/Lower Small Watercraft Proper Waste Separation Proper Decontamination Marine EOC Wet suit + life jacket storage Workshop / Boson’s Room /Hotwork room Extractor/ Dryer Room Decontamination Room Safe Fuel Storage Public Accessable Toilet Elevator + Stairs (Proper Handicap Access and Exiting) Circulation and Gross Factor to accomodate walls, structure, and mechanical

Project: PROGRAM

Dormitory (inadequate) Kitchen Dining/Day Room Lockers/Showers/Toilets (single sex) Fitness Storage Workshop

Page 5: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 5Building Design & Construction 5

Existing Station No. 35 Capacity

Assets Two Fire Boats One Fire Engine 7 SFFD staff “24/7”

Liabilities • Structurally Unstable

Berthing Areas • No Oil Spill Equipment

or Jet Skis • Limited Storage Areas • Limited Rescue

Unloading Areas • No Changing Facilities

for Women

Project: EXISTING CAPACITY

Page 6: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 6Building Design & Construction 6

Proposed New Station Capacity

Assets Three Fire Boats One Engine 12 Staff “24/7” Jet Skills & Small Rescue Boats

Enhancements • Structurally stable building

& berthing areas for three fire boats

• Organized storage areas for Fire Safety Equipment e.g. Oil Spill Equipment

• Ambulatory Access • Equipment for boat access

& loading & unloading • Changing facilities for

Women

Project: PROPOSED CAPACITY

Two Fire Boats

Page 7: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 7Building Design & Construction 7

Project: PLAN - HISTORIC AND NEW: FIRST FLOOR

BOAT EQUIPMENT STORAGE

SMALL CRAFTSTORAGE

EQUIPMENT LOCKERS

EMERGENCY OPERATIONS

CENTER STORAGE

180’-0”

MECHANICALNIGHTWATCH BOSON’S ROOM

PUBLICENTRY

SAN FR

ANC

ISCO

BAY

80’-0”

EMBARCADERO

WORK SPACESEQUIPMENT

WORK ROOMS

Page 8: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 8Building Design & Construction 8

DORMITORY

OFFICER’SQUARTERS

(OPEN TO BELOW)

CORRIDOR

STUDY

LOCKERS, SHOWERS,

BATHROOMSKITCHEN/

DINING

DAYROOM

OUTDOORDECK

PANTRYLAUNDRY STORAGE

SCALE: 1/16” = 1’-0”

180’-0”

80’-0”

Project: PLAN - HISTORIC AND NEW: SECOND FLOOR

Page 9: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 9Building Design & Construction 9

South Elevation (NTS)

(E) HISTORICFIRE STATION 35

CONCRETEGFRC PANELS

FOUR-FOLD DOORS

WINDOW ATNIGHTWATCH

LIGHTWEIGHT SKINMATERIAL

WINDOWS ATDAYROOM

WINDOWS ATDORMITORY

PAINTED STUCCO

Project: ELEVATION OF EXISTING HISTORIC FS 35 + NEW BOATHOUSE

Table 2-2 Vessel specifications for fire boats at Pier 22.5

Name Guardian Phoenix "New Fireboat"

Builder Yarrows, Ltd., Esquimalt, British Columbia

Hugh F. Munroe of Plant Shipyard, Alameda, CA

Vigor Industrial, Seattle WA

Year 1951 1955 2016

Type of vessel Fireboat Fireboat Fireboat

Displacement 185 long tons 146 tons 260 long tons (300 GRT ITC)

Length overall (LOA) 88 ft. 89 ft. 88 ft.

Page 10: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 10Building Design & Construction 10

+7.77’ Projected 2070 MHHW (50 yrs)

+12.72’ Current MHHW

+15.50’ New Pier

+3.0’ Wave Action & 3.5’ 100-Yr Flood

+10.90’ Current Top of Pier

+6.22’ Current 2015 MHHW

+3.0’ Wave Action & 3.5’ 100-Yr Flood

+14.30’ Projected 2070 MHHW (50 yrs)

+4.6’ Higher than Current Pier

N.T.S. N.T.S.

180’-0”

4.6’

40’ M

AX.

+7.77’ Projected 2070 MHHW (50 yrs)

+12.72’ Current MHHW

+3.0’ Wave Action & 3.5’ 100-Yr Flood

+10.90’ Current Top of Pier

+6.22’ Current 2015 MHHW

+3.0’ Wave Action & 3.5’ 100-Yr Flood

+14.30’ Projected 2070 MHHW (50 yrs)

N.T.S. N.T.S.

5’ a

t all

times

40’ M

AX.

180’-0”

PIER OPTION

BARGE OPTION

Context: SEA LEVEL RISE

Page 11: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 11Building Design & Construction 11

Steel Barge Steel Barge with Guide Piles and Ramp

Steel Barge with Deck Slab

Marine Engineering: COWI PROPOSAL: STEEL BARGE

Page 12: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 12Building Design & Construction 12

Marine Engineering: EXAMPLES OF FLOATING PIERS (BY OTHERS)

Gildersleeve School (Ketchikan, Alaska)The Gildersleeve School in Ketchikan, Alaska was constructed on a 68 ft x 80 ft reinforced concrete barge. The school building has two levels with an apartment on 2nd level.

Vernon C. Bain Prison Barge (New York, NY)Built in New Orleans along the Mississippi River brought to New York in 1992. The 625 ft x 125 ft steel barge is equipped with 14 dormitories and 100 cells for inmates.

Movement Comfort criteria, RMS value

Roll 2°

Vertical acceleration 0.02 g or 0.66 ft/s2

Lateral acceleration 0.03 g or 0.98 ft/s2

› Limit of comfort values for roll, vertical and horizontal accelerations in cruise liners (Faltinsen, 1990).

› Criteria to be satisfied under operational conditions.

› During episodes of extreme weather conditions (design conditions), some people will feel uncomfortable.

Comfort Criteria (by COWI)

Brook St. Pier Ferry Terminal (Australia)Concrete Barge, Ferry Berth, mark and Restaurants.

Floating Steel CofferdamSR 520, Seattle 44 ft x 36 ft tall.

Barge 225 Floating Offi ces (Cleveland, OH)150 ft x 45 ft Steel barge was converted to a restaurant and then in 2013 to an offi ce space.

Page 13: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 13Building Design & Construction 13

Pros ConsBuild on site Building roof will be higher for Planning review

More contractor participation due to conventional construction

Pier and building will be subjected to high seismic loading

No dredging and sheet pile required Need to place pier higher than sea level rise prediction

Residents in the building not subject to motion. Steel piles and beams require corrosion protection and inspection for life of pierRequire impact pile driving. Environmental issue, limited work window.

Building roof will be lower for planning review Limited contractors could do the project

No dredging and sheet pile required Need special treatment coating and sacrificial steel for corrosion protection for life of the project

Adaptable to sea level rise Residents in the building will be subject to motion of the pier

Limited impact from Seismic activity Utilities to the shore will need flexible joints

Less environmental impact, fewer piles to drive. Access ramp will need to adjust per tides

Separate boarding float may not be required Require periodic dive inspectionLimited locations in Bay area where it can be built. Need to be transported to site.

Building roof will be lower for planning review Limited contractors could do the project

More durable against corrosion and deterioration Need epoxy coated rebar for corrosion protection for life of the project

Adaptable to sea level rise Residents in the building will be subject to motion of the pier, less than steel floating pier.

Limited impact from Seismic activity Utilities to the shore will need flexible joints

Less environmental impact, fewer piles to drive. Access ramp will need to adjust per tides

Separate boarding float may not be required Require dredging and sheet pile Limited locations in Bay area where it can be built. Need to be transported to site.

Marine Engineering: BUDGET and PROS + CONS OF COWI’S DIFFERENT PIER OPTIONS

Type of Pier

FIXED PIERPier Construction = $6.4 MTotal Site and Building = $14 M

Total Construction Cost = $23.3 M

TOTAL PROJECT COST= $36.7 M

FLOATING STEEL PIERPier Construction = $6.3 MTotal Site and Building = $14 M

Total Construction Cost = $23.1 M

TOTAL PROJECT COST = $36.6 M

FLOATING CONCRETE PIERPier Construction = $8.6 MTotal Site and Building = $16.3 M

Total Construction Cost = $27 M

TOTAL PROJECT COST = $42.4 M

Page 14: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 14Building Design & Construction 14

Context: COMPARISON OF CONTEXT - SIDE VIEWS FOR LENGTH AND HEIGHT

Pier 26 - Adjacent Pier

Pier 28

28’

51’

42’

24’

45’

Page 15: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 15Building Design & Construction 15

Project: SCHEDULE

Project Schedule

Prepared by San Francisco Public Works, Project ManagementApril 19, 2016

Agency Approvals

Construction

Q3 Q1 Q2

ESER 2014 Bond - Fire Station No. 35 (Pier 22½)

Q4

Concept

Environmental

Design

2021Q3 Q4

2015 2016Q3 Q4 Q1 Q2 Q2 Q3 Q4 Q1 Q2

Closeout

SFFD Occupancy

Design/Build Procurement

2019 2020Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2017 2018Q1

April 19, 2016

Page 16: 2016-0712 Presentation for Port · presentation to port commission - july 12, 2016 agenda: • project • marine engineering • context • precedents. firestation 35 - the boathouse

FIRESTATION 35 - THE BOATHOUSEJULY 12TH, 2016 16Building Design & Construction 16

DISCUSSION

DISCUSSION