2015 referendum district wide additions & renovations ...€¦ · isd #273 – edina public...
TRANSCRIPT
Edina Public Schools
Independent School District #273
2015 Referendum
District Wide
Additions & Renovations
REVIEW
AND
COMMENT
SUBMITTAL
Presented to:
Minnesota Department of Education
January 26, 2015
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc Commission No. 9999
TABLE OF CONTENTS
Page
Introduction / Key Information 1
___ 1. Geographic Area and Population to be Served 2
a) PK-12 Enrollment History
b) PK-12 Enrollment Projections
___ 2. List of Existing Facilities 4
a) Description of Existing Facilities
b) Utilization / Uses
c) Available Alternate Facilities
___ 3. Specific Deficiencies of the School Facilities 16
a) Demonstrating Need
b) Process Used to Determine Deficiencies
c) List of How Deficiencies will be Addresses
d) Specific Benefits to Students, Teachers and Community
___ 4. Description of Proposed Projects 23
a) Site and Outdoor Acreage
b) Square Footage Allocations
c) Estimated Expenditures
d) Schedule
___ 5. Financing the Project 44
a) Applicable Statutory Citations
b) Scheduled Date and Required Notice
c) Schedule of Bond Payments
d) Property Tax Input
___ 6. Obligating Documents 49
a) Governing Municipal Contracts
b) Sustainable Design
c) Commissioning
d) Acoustical Performance
e) State Fire Code
f) Building Codes
g) Consultation with Local Governments on Infrastructure
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 1 Commission No. 9999
In accordance with Minnesota Statute 123B.71 (2000), the School Board submits the following educational facility
proposal for Review and Comment. The projects presented are the result of extensive District review of facility conditions,
capacity of buildings compared to enrollment projections, and program initiatives and equity within the District. The
specific information is as follows:
Key Information:
Address: Independent School District #273
Edina Public Schools
5701 Normandale Road
Edina, MN 55424
Contact: Dr. Ric Dressen, Superintendent of Schools
Phone: (952) 848-3900
Fax: (952) 848-3901
School Board Randy Meyer, Chair
Lenny Wallen-Friedman, Vice Chair
Regina Neville, Clerk
Cathy Cella, Treasurer
Sarah Patzloff, Assistant Treasurer
David Goldstein, Assistant Clerk
Lisa O’Brien, Assistant Clerk
Financing: $ 124,900,000 General Obligation Bonds
Architect/Engineer Wold Architects and Engineers
305 St. Peter Street
St. Paul, Minnesota 55102
Contact: Vaughn Dierks, AIA
Phone: (651) 227-7773
Fax: (651) 223-5646
Fiscal Consultant: Ehlers
3060 Centre Pointe Drive
Roseville, MN 55113-1105
Contact: Joel Sutter
Phone: (651) 697-8572
Fax: (651) 697-8555
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 2 Commission No. 9999
1. The Geographic Area and Population to be Served
a. Preschool Through Grade 12 Student Enrollments for the Past Five Years,
b. Current Year Student Enrollment and Student Enrollment Projections for the Next Five Years.
Geographic Area to be Served:
As of October 1 of the 2014-15 school year, the student enrollment was 8,442 students in programs from
Kindergarten through 12 th grade. These students are utilizing six active elementary schools, two middle school
program buildings, one high school, and the Edina Community Center (ECC) for early childhood, special education
and District Offices and programs.
Map of ISD #273
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 3 Commission No. 9999
Neighboring School Districts with contiguous borders include
SSD # 1 Minneapolis
ISD # 270 Hopkins
ISD # 271 Bloomington
ISD # 272 Eden Prairie
ISD # 280 Richfield
ISD # 283 St. Louis Park
Since this referendum includes work at every facility in the District, the population to be served by this project
are the students, associated school district staff and community throughout the entire District boundary.
K-12 student population in the Edina Public Schools has grown from 7,871 students in the 2008-09 school
year to a current enrollment of 8,442 in the 2014-15 school year. Projections increase that enrollment to
8,620 by the 2019-20 school year.
The current state of the Edina area shows construction on home permits continue, supporting the enrollment
projections for the District.
K-12 Enrollments Past Five Years, Current Enrollment, and Projections
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 4 Commission No. 9999
2. A List of Existing School Facilities
a. by year constructed,
b. their uses, and
c. an assessment of the extent to which alternate facilities are available within the school district boundaries and
in adjacent school districts.
Description of Existing Facilities/Utilization
The Edina Public School District is currently operating six (6) active elementary school facilities, two (2) full middle
school facilities, and one (1) high school facility. They also operate the Edina Community Center [ECC] and the
Transportation Bus Garage.
Elementary
Schools
Grade
Org.
10/1/2014 Student
Enrollment
Original
Building
Additions Site Size in
Acres
Adjacent
Public Acres
Building
Area SF
Concord Elementary K - 5 736 1950 1952,
2004
9.78 0 80,240
Cornelia Elementary K - 5 585 1962 2004 20.53 6.208 68,678
Countryside
Elementary
K - 5 600 1965 NA 13.38 11.686 67,996
Creek Valley
Elementary
K - 5 590 1968 NA 13.38 20.476 77,118
Highlands Elementary K - 5 566 1956 2004 9.86 29.131 68,538
Normandale
Elementary
K - 5 638 (See ECC) - Shared w/
ECC, SV
- -
Secondary Schools Grade
Org.
10/1/2014 Student
Enrollment
Original
Building
Additions Site Size in
Acres
Adjacent
Public Acres
Building
Area SF
South View Middle
School
6-9 1,312 1954 1993,
2004
20.53 0 212,783
Valley View Middle
School
6-9 1,394 1964 2004 Shared w/
EHS
0 200,573
Edina High School 10-12 2,021 1972 2004 55.22 44.474 411,717
District Support
Facilities
Grade
Org.
1/1/2014 Student
Enrollment
Original
Building
Additions Site Size in
Acres
Adjacent
Public Acres
Building
Area SF
Edina Community
Center [ECC]
NA
NA
1948 1952,
1964
20.53
Shared w/
ECC
0 385,082
Transportation Garage NA NA
1913 1968 1.0 0
The district has reviewed the availability of other facilities both within and outside of the School District. No other facilities
of significant size and adequate function have been identified to meet the needs of the District and/or to be available for
use.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 5 Commission No. 9999
Edina High School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 6 Commission No. 9999
Edina High School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 7 Commission No. 9999
Valley View Middle School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 8 Commission No. 9999
South View Middle School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 9 Commission No. 9999
Concord Elementary School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 10 Commission No. 9999
Cornelia Elementary School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 11 Commission No. 9999
Countryside Elementary School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 12 Commission No. 9999
Creek Valley Elementary School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 13 Commission No. 9999
Highlands Elementary School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 14 Commission No. 9999
Normandale Elementary School
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 15 Commission No. 9999
Edina Community Center (ECC)
(Normandale – Level 2)
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 16 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities
a) Demonstrating Need
b) Process Used to Determine Deficiencies
c) List of How Deficiencies will be Addresses
d) Specific Benefits to Students, Teachers and Community
Process
As part of an on-going examination of District alignment with strategic goals, the District is continuously studying
necessary facility improvements. Over the past four years, several key areas of study have looked at ways that facility
improvements could enhance the educational experience, including:
2009 District conducts Fields Study related to outdoor program and competition spaces.
2010 District commissions Wold Architects and Engineers to conduct an Educational Adequacy study related
to facilities.
2011 District conducts Facility Inventory to build a database of physical conditions and needed
improvements. This in turn leads to a robust 2 and 10 year facility plan to address significant
maintenance needs through Alternative Facilities bonding and levy.
2012 District completes new Next Generation Strategic Plan for all areas of operation within the District. A
major component of the plan focuses on better alignment of facilities to learner needs and the
importance of continued investment in District resources.
2012 District begins Secondary Study to look at delivery methods related to secondary instruction, grade
organization and other needs for 6th -12th grade.
2013 District begins Birth to Grade 5 (BG5) study to look at early childhood and elementary needs in
conjunction with on-going secondary study.
2013 District initiates a Facilities Committee composed of both District personnel and community members
to look at facility conditions related to overall District Standards.
2014 District convenes a Facilities Advisory Task Force (FATF) in August to begin a broad based community
input process on facilities.
24 members including current students, staff, school-age parents, alumni and community
members
(6) weekly meeting beginning August 26
Process built on findings from the District Studies to determine needs and develop potential
resolutions to address needs
Report and recommendations presented to the Board in October
2014 Board discussion and additional study through work sessions and stakeholder dialogues to consider
FATF recommendations and potential referendum question to address needs.
Administration presents recommended Next Generation Facilities Concept Plan to Board in
December
2015 Board approves at the January 12 Board meeting the Facilities Concept Plan and a resolution to bring
Facility Proposal forward as a May 5, 2015 referendum vote.
The culmination of the FATF process included recommendations to bring forward to the Board for consideration which
became the foundation for the referendum. Those recommendations and potential responses are included on the following
pages. (Potential Project Costs and Timelines noted were draft versions at that time. Revised budgets and estimates are
included in the next section of this Review & Comment).
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 17 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities (Continued)
FATF Recommendations:
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 18 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities (Continued)
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 19 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities (Continued)
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 20 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities (Continued)
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 21 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities (Continued)
Specific Deficiencies to be Addressed
Every building in the District is designed in a “traditional”, double loaded corridor system which means that
all educational space is within a typical 800-900 square foot classroom arranged on either side of a hallway.
The schools were all built between 1948 and 1972 which would have been typical for that age building. This
differs considerably from current design models for educational facilities which would provide a greater
variety and type of learning space at all age levels. A majority of the projects would address this issue by
creating additional and varied learning environments at all buildings.
While the current 2 and 10-year Alt Facilities plans address some of the District physical needs (in
particular HVAC renovation and replacement, roofing work, and exterior envelope maintenance) there are
still significant interior physical needs to address. The proposed renovation projects will be able to address
many of these needs in the process.
The majority of Special Education spaces in the District are currently in areas that were not originally
designed for Special Education, much less a design focus on a current approach to students with special
needs. The proposed projects include renovations at Special Education areas at all buildings.
Similar to classroom and instructional space, the media centers at all schools are designed around a typical
approach including multiple book shelves to hold all circulation material in a manner that allows students to
search and retrieve by seeing all material available at once. However, contemporary thought on media center
approach would rely less on “media retrieval” and more on “media creation”. The proposed projects would
include renovations at all media centers within the District to provide increased area for independent and
small group activity and less floor space allocated to book shelves through high density storage. This would
work in conjunction with other extended learning environments in the building to better align with District
initiatives and goals.
The majority of District furniture is 30-40 years or more old, and is very rigid in design and function. When
looking at alignment to facility needs, furniture plays a critical role in having the flexibility to easily
transform a space from a lecture based format to small group activities, seminar discussion, or presentation
style learning. Additionally, today’s educational experience relies more on personal electronic devices in
both laptops and tablets to supplement a student’s possibilities. A portion of the referendum is allocated
towards replacing furniture in educational spaces to provide this flexibility and greater integration with both
power and data needs.
Between the elementary schools there is inequity in both the size and quantity of specialist areas (including
music, art, science, physical education, etc.). The proposed work would ensure similar quantities of
specialist space at all elementary schools through minor additions where needed.
The District has a shortage of both indoor and outdoor activity spaces. The ones that do exist are in need of
physical improvements based on age and wear. The shortage of spaces currently requires student athletes
to practice at multiple sites as opposed to at the High School (which means additional student driving). This
creates a demand at Middle School sites for after school use of athletic space preventing Middle School
programming due to space. Additionally, club space for programs such as robotics and other activities is
non-existent. The proposed project would significantly increase activity space at the High School to meet
this demand and create greater availability at all District sites to allow more varied after school programming
activities.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 22 Commission No. 9999
3. A List of the Specific Deficiencies of the Facilities (Continued)
The spaces currently dedicated to Early Childhood within the District accommodate the current enrollments,
but they are at capacity and do not allow for additional demand. Given the availability of other options for
early education in the District through private programs the District does not intend to have a 100% capture
of these students. However, through expansion of the early childhood spaces available there would be the
possibility of expanding programming to align with District initiatives and provide greater opportunity for
integration into the District for more students.
Recent events related to shootings and attempted threats within schools nationwide and within the State
have made this need aware to a larger audience. The District has performed a security audit of all the
buildings and determined that providing secure vestibules at all schools would provide needed
improvements to how visitors are controlled for access into buildings. The referendum projects would
provide this needed step at all buildings where this is currently not the case.
Parking is undersized at the High School currently based on the assembly load and current student
enrollment. The proposed projects would add parking to this location to ease this issue. Additionally, traffic
patterns at each site will be studied to determine if additional modifications are needed.
The District’s transportation facility is inadequate on multiple issues. There is limited on-site parking for
drivers. Most are accommodated through street parking or agreements with drivers and adjacent property
owners, or unauthorized parking in adjacent areas. There is not enough garage space to accommodate
buses owned by the District indoors, so a percentage of vehicles need to be stored outside decreasing the
life cycle of the vehicle. The maintenance bays are inadequate to meet the daily need for work on vehicles.
The height of the existing garage doors is unable to accommodate new buses, and due to structure of the
garage this condition is unable to be modified. The existing facility also inhibits the ability to operate more
efficiently by bringing contracted services under direct District operation (for example, Special Education).
Allocation for a new District transportation facility is included within the project scope.
Benefits to Students, Teachers and Community:
Greater focus on a personalized learning approach to support a wider variety of instructional delivery
Equity in programming in all areas of the District
Expanded Early Childhood programming will offer greater opportunities throughout the District
Expanded extra-curricular spaces with multi-purpose activity based additions at both elementary and
secondary levels
Continued investment in District quality of life, commitment to educational endeavors, and greater ability for
community use of facilities at all age levels.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 23 Commission No. 9999
___ 4. A Description of the Project including:
a) Site and Outdoor Acreage
b) Square Footage Allocations
c) Estimated Expenditures
d) Schedule
Site and Outdoor Acreage
The site sizes for the Buildings where additions are proposed is as follows:
Edina High School 55.2 Acres
Concord Elementary 9.8 Acres
Cornelia Elementary 20.5 Acres
Countryside Elementary 13.4 Acres
Creek Valley Elementary 13.4 Acres
Highlands Elementary 9.9 Acres
The majority of these sites are on the low end of the State Guidelines for construction. However, given Edina’s
location as a first ring suburban District available land is at a premium. The additions at the elementary schools are
relatively small in footprint and should be able to easily be accommodated on the land available. Many of these sites
are also adjacent to city park areas expanding the available green space for student use.
The land for the High School is more difficult to work with. The areas proposed for expansion are located within the
side of significant hills. Funds towards structural concerns and soil work have been included for the projects.
Additionally the District’s consultants are working with regional watershed authorities to study the impact of storm
water runoff and other environmental issues to ensure appropriate design and stewardship.
The additions at the elementary schools will not add any capacity and are not expected to increase vehicular traffic as
a result. With the relocation of 9th grade to the High School vehicular traffic is intended to decrease at South View
Middle School. This will also be affected by relocation of the main entry for visitors to the parking on the south side
as opposed to along South View Lane. District consultants are and will continue to work with the City of Edina in
studying traffic patterns at the High School / Valley View Middle School site to accommodate both current and new
traffic loads.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 24 Commission No. 9999
___ 4. A Description of the Project (Continued)
Next Generation Learning Spaces:
High School
28-30 teaching station addition to the High School to accommodate relocation of 9th grade from the (2)
Middle Schools to the High School. This will be a combination of some classroom and lab space as well as
specialist areas and personalized learning environments to accommodate a wider variety of instructional
styles. (Note: It is not intended that the addition accommodate 9 th grade only, but will be designed by
looking at 9-12 th grade needs.)
Core Expansion (toilets, lockers, etc.)
Renovation of Media Center
Special Education renovations
Personalized and extended learning environments in existing classroom areas through renovation
Activities spaces for athletics, clubs, organizations and extra- curricular activities, including courts, labs,
classrooms and support areas.
Replacement of outdated and rigid educational furniture with flexible, technology ready fixtures
Estimated Cost:
Construction:
Additions 135,000 sf $ 39,100,000
Renovations 40,500 sf $ 6,680,000
$ 45,780,000
Contingency $ 4,305,000
Fees, Testing, Services $ 6,805,000
Furniture, Fixtures & Equipment $ 3,775,000
Project Cost $ 60,665,000
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 25 Commission No. 9999
Next Generation Learning Spaces: High School
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 26 Commission No. 9999
Next Generation Learning Spaces: High School
Diagram of Media Center Renovation Concept
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 27 Commission No. 9999
High School – Multi-Purpose Activity Space
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 28 Commission No. 9999
High School – Multi-Purpose Activity Space
Program
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 29 Commission No. 9999
___ 4. A Description of the Project (Continued)
Next Generation Learning Spaces:
Middle Schools
Relocation of 9th Grade to High School – relocation allows for creation of personalized and extended
learning environments in existing classroom areas through renovation
Renovation of existing areas to create student commons areas for social interaction and student
development
Renovation of Media Center
Special Education renovations
Creation of STEM Lab and Studio space through renovation of existing areas
Classroom improvements / upgrades to coincide with Alt Facilities HVAC work
Replacement of outdated and rigid educational furniture with flexible, technology ready fixtures
Estimated Costs:
South View Middle School:
Construction 28,900 sf $ 5,435,000
Contingency $ 545,000
Fees, Testing, Services $ 815,000
Furniture, Fixtures & Equipment $ 545,000
Project Cost $ 7,340,000
Valley View Middle School:
Construction 31,625 sf $ 5,930,000
Contingency $ 595,000
Fees, Testing, Services $ 890,000
Furniture, Fixtures & Equipment $ 595,000
Project Cost $ 8,010,000
Middle School Total $ 15,350,000
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 30 Commission No. 9999
South View Middle School
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 31 Commission No. 9999
Valley View Middle School
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 32 Commission No. 9999
___ 4. A Description of the Project (Continued)
Next Generation Learning Spaces:
Elementary Schools
Creation of equitable and appropriate specialist spaces (Music, Art, Gifted/Talented, Computer,
Band/Orchestra, Science) at all elementary schools through renovations and minor additions
Renovation of Media Center and existing areas to create student learning commons areas and flexible
learning space
Special Education renovations
Classroom improvements / upgrades to coincide with Alt Facilities HVAC work
Replacement of outdated and rigid educational furniture with flexible, technology ready fixtures
Cornelia Elementary
Construction:
Additions 7,800 sf $ 2,067,000
Renovations 6,500 sf $ 1,025,000
$ 3,092,000
Contingency $ 280,000
Fees, Testing, Services $ 463,000
Furniture, Fixtures & Equipment $ 310,000
Project Cost $ 4,145,000
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 33 Commission No. 9999
Concord Elementary
Construction:
Additions 3,600 sf $ 1,026,000
Renovations 10,045 sf $ 1,680,000
$ 2,706,000
Contingency $ 245,000
Fees, Testing, Services $ 405,000
Furniture, Fixtures & Equipment $ 270,000
Project Cost $ 3,626,000
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 34 Commission No. 9999
Countryside Elementary
Construction:
Additions 2,100 sf $ 556,500
Renovations 6,700 sf $ 1,105,000
$ 1,661,500
Contingency $ 150,000
Fees, Testing, Services $ 249,500
Furniture, Fixtures & Equipment $ 165,000
Project Cost $ 2,226,000 NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 35 Commission No. 9999
Creek Valley Elementary
Construction:
Additions 2,000 sf $ 530,000
Renovations 9,000 sf $ 1,450,000
$ 1,980,000
Contingency $ 180,000
Fees, Testing, Services $ 295,000
Furniture, Fixtures & Equipment $ 200,000
Project Cost $ 2,655,000
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 36 Commission No. 9999
Highlands Elementary
Construction:
Additions 4,000 sf $ 1,060,000
Renovations 7,065 sf $ 1,153,000
$ 2,213,000
Contingency $ 200,000
Fees, Testing, Services $ 330,000
Furniture, Fixtures & Equipment $ 220,000
Project Cost $ 2,963,000
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 37 Commission No. 9999
Normandale Elementary
Construction:
Renovations 26,100 sf $ 4,555,000
Contingency $ 400,000
Fees, Testing, Services $ 685,000
Furniture, Fixtures & Equipment $ 450,000
Project Cost $ 6,090,000
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 38 Commission No. 9999
___ 4. A Description of the Project (Continued)
Early Childhood Education
Creation of additional early childhood programming space for classrooms, family education, and sibling
care on lower level of ECC
Relocation of after school programming to third floor
Classroom improvements / upgrades to coincide with Alt Facilities HVAC work
Replacement of outdated and rigid educational furniture with flexible, technology ready fixtures
Construction:
Renovations 11,750 sf $ 2,350,000
Contingency $ 215,000
Fees, Testing, Services $ 350,000
Furniture, Fixtures & Equipment $ 235,000
Project Cost $ 3,150,000
Outdoor Learning and Competition Spaces
Development of external space for classroom work and exploration
Playground Improvements at all Elementary Schools
Conversion of (4) worn out natural turf fields with synthetic turf to accommodate a wider range of activities
and extended use (2 fields at EHS, 2 fields at ECC)
Rebuild and resurface track at ECC to improve substructure
Resurface tennis courts at EHS
Rebuild practice Baseball field at ECC to improve drainage
Rebuild / develop service drive on EHS property to lower fields
Construction $ 6,000,000
Contingency $ 600,000
Fees, Testing, Services $ 900,000
Fixtures & Equipment $ 250,000
Project Cost $ 7,750,000
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 39 Commission No. 9999
Outdoor Learning and Competition Spaces
NOTE: Diagrams show
potential locations
only. Exact project
details and locations
will be subject to
design meetings and
further development
upon successful
referendum passage.
NOTE: After review with the neighborhoods to the east and
west of EHS and listening to concerns related to the potential
for connecting Creek Valley Road, providing vehicular access
from those points, or providing general parking at the lower
fields area the District has made the decision to not make any
traffic or parking changes in this area, and will be
accommodating any needed expansion to parking at the upper
site area, and will provide service vehicle and ADA access
only from a service drive on EHS property.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 40 Commission No. 9999
Outdoor Learning and Competition Spaces
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 41 Commission No. 9999
___ 4. A Description of the Project (Continued)
Building Security
Relocation and/or renovation of existing Main Office at every facility to increase supervision of entry.
Creation of secure vestibules at all sites – single point entry after school starts. All visitors must pass
through administration / office to gain access to buildings
Development of zoned lock-down areas within buildings to provide greater separation during an emergency
event
Additional technology infrastructure focused on security systems, cameras, intercom, etc.
Construction $ 6,335,000
Contingency $ 570,000
Fees, Testing, Services $ 950,000
Fixtures & Equipment $ 125,000
Project Cost $ 7,980,000
Transportation Facility
Development of a new transportation facility on a site TBD. (Note: cost of site anticipated to be offset by sale
of existing land / transportation site)
On-site parking for 100 drivers / staff
Parking bays for (84) Buses minimum
Maintenance and wash bays
Construction $ 6,385,000
Contingency $ 480,000
Fees, Testing, Services $ 955,000
Fixtures & Equipment $ 480,000
Project Cost $ 8,300,000
NOTE: Diagrams show potential
locations only. Exact project details and
locations will be subject to design
meetings and further development upon
successful referendum passage.
Square Foot allocations for all referendum component projects will meet or exceed the Guidelines for School
Construction as they continue to develop through the design process.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 42 Commission No. 9999
___ 4. A Description of the Project (Continued)
Estimated Expenditures for the Projects:
Building Security
Technology Infrastructure $ 2,000,000
Office Improvements $ 5,980,000
$ 7,980,000
Next Generation Learning Spaces
High School: Additions & Renovations $ 60,665,000
Middle Schools: Renovations $ 15,350,000
Elementary Schools: Additions & Renovations $ 21,705,000
Early Childhood Renovations $ 3,150,000
$ 100,870,000
Infrastructure Improvements
Outdoor Learning & Competition Areas $ 7,750,000
Transportation Facility $ 8,300,000
$ 16,050,000
PROJECT TOTAL $ 124,900,000
Note: It is anticipated by the School Board that any surplus from the above noted projects
(if any) will be used for yet unidentified deferred maintenance, capital expenditures
for technology and/or equipment, or space expansion as the need may arise.
Note: Legal and Fiscal Costs, Capitalized Interest and Estimated Earnings outlined in
Section 5 are all calculated within noted Project Costs outlined in Section 4 of the
Review & Comment. Total Project Costs remain $124,900,000.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 43 Commission No. 9999
___ 4. A Description of the Project (Continued)
Estimated Operational Expenditures:
The District has reviewed the impact of the proposed additional square feet to buildings in relation to utility and
facility expenses, operational staffing expense and any additional equipment required for the project not allocated
within the construction budgets. Anticipated costs include:
Custodial staff – (6) custodians $ 440,000
Utilities $ 290,000
Supplies $ 85,000
Equipment (1 time cost) $ 70,000
Additional administration or teachers are not anticipated to be required as the work is not related to significant
enrollment change but rather differentiated learning approaches.
For the coming Fiscal Year these costs will be absorbed into the capital budget. The District has a renewal Levy
pending for 2017 and will be reviewing all District costs and expenditures at that time.
Schedule:
Project Schedule
Review and Comment Submittal to MDE February 2015
Review and Comment MDE Review February-March 2015
Referendum May 5, 2015
Project Design & CD Preparation May 2015 - May 2016
Project Construction Documents Issue January 2016 - September 2016
Project Construction April 2016 - July 2018
Occupancy Summer 2017 and 2018
Project Completion Fall 2017 for 2017-18 School Year
Fall 2018 for 2018-19 School Year
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 44 Commission No. 9999
___ 5. A Specification of the Source of Project Financing including:
a) Applicable Statutory Citations
b) Scheduled Date and Required Notice
c) Schedule of Bond Payments
d) Property Tax Input
Availability and Manner of Financing
The project would be financed through General Obligation Bonds to be voted on in the May 5 referendum.
The District has worked with Ehlers to determine the financial impact of the proposed referendum on local property
taxes as well as how this funding will overlap with other current funding programs and components within the
District. The attached information (prepared by Ehlers) contains information specific to the referendum as well as
more detailed information encompassing the referendum impact with other planned financing.
Attachment 1 shows the detailed long-range financing plan, with estimated payments and levies for the proposed
bonds plus other debt and capital levies as well as the estimated debt equalization aid.
Attachment 2 shows the estimated payments and initial tax levies for the proposed building bonds
Attachment 3 shows estimated tax rates for all of the levy categories included on the first attachment
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 45 Commission No. 9999
___ 5. A Specification of the Source of Project Financing (continued):
Attachment 1:
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 46 Commission No. 9999
___ 5. A Specification of the Source of Project Financing (continued):
Attachment 1:
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 47 Commission No. 9999
___ 5. A Specification of the Source of Project Financing (continued):
Attachment 2:
Note: Legal and Fiscal Costs, Capitalized Interest and Estimated Earnings are all calculated within noted Project
Costs outlined in Section 4 of the Review & Comment. Total Project Costs remain $124,900,000.
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 48 Commission No. 9999
___ 5. A Specification of the Source of Project Financing (continued):
Attachment 3:
ISD #273 – Edina Public Schools 2015 Referendum Projects
Review and Comment Submittal January 26, 2015
S:\ISD273\Planning\2014 Planning\Review & Comment\ISD 273 R&C 2015.doc 49 Commission No. 9999
___ 6. Documentation: