  • 8/10/2019 2014-07-22 Construction Meeting Minutes.pdf

    1/4

  • 8/10/2019 2014-07-22 Construction Meeting Minutes.pdf

    2/4

    Page 2of 4

    design change (elevating the granite) via

    Bulletin 12 Their opinion is that the

    changes leave no room for error on step

    footings, etc. and bringing the concrete

    flush with the pavers is more labor. MK

    asked ACP to provide a more detailed

    information to substantiate the price

    increase.

    1.1.2. The previous granite curb sample

    was rejected due to blemishes. Syrstone

    representatives provided a new sample

    today with saw-cut edges and split seam

    face. Syrstone can provide any type of

    face, but the price point will change.

    Sasaki concerned that the split face may

    cause waving in the paving lines. Sasaki

    requested photographs of previous

    installations using the split face curb.Syrstone is suggesting a herringbone

    pattern instead of the running bond, per

    RFI 20. Supplier noted that industry

    standards discourage running bond

    applications where there is vehicular

    traffic, particularly when the running bond

    is parallel to direction of traffic. Sasaki

    asked if there was less concern because

    they are using a thicker paver. Syrstone

    responded that yes, that may help the

    vehicular traffic concerns, but the concernremains that with the running pattern any

    grade changes are noticeable.

    Syrstone asked for clarification of what

    color polymeric (joining) sand to use.

    Sasaki has selected one color (tan)

    already, per Submittal 82.

    Sasaki noted that a sealant is still called

    for where the pavers meet a vertical

    surface.

    Syrstone will submit an RFI regarding

    weep hole placement through the slab.

    Syrstone is questioning the response to

    RFI 15where the trench drain

    manufacturer requested pavers on top of

    drains be mortared in place. Syrstone

    suggested that mortaring some pavers

    may affect the movement of the pavers

    around it.

    Clarified that the sand cement setting

  • 8/10/2019 2014-07-22 Construction Meeting Minutes.pdf

    3/4

    Page 3of 4

    bed is a typo. The setting bed has been

    priced as sand. The sand cementis not

    sturdier, and will weather more over time.

    1.2.

    P&CG (Contract #3B):

    1.2.1.

    Lighting Submittal #13R3open

    issues for Sasaki? need schedule

    from manufacturer

    1.2.2.

    Kiosk Submittal #21hole in base

    plate to be enlarged to 3 x 6 oval;

    Sasaki to coordinate conduit feeds

    up to kiosk

    1.2.1. The gauge of the bolts in Submittal

    13R3 is still not acceptable. DT 505 says

    extra strong, - Sasakis intent was for a

    higher gauge. MK asks that the supplier

    has a phone call with the designer so they

    can hash it out. BP says he will set up a

    phone call.

    MK requests that all of the required

    resubmittals are submitted now so they

    dont hold up the ordering any longer. BP

    says another Selux submittal will be sent

    today (13R4) which will address all of the

    outstanding questions.

    BP asks if individual photo cells are

    necessary when the utility panel alreadyhas a photo cell installed. Sasaki asks that

    an RFI is submitted, and a phone call is set

    up with necessary parties to come to a

    decision.

    Kiosk Submittal #21Design team is

    discussing options for conduit feeding into

    the kiosk with the manufacturer.

    2.

    DESIGN, FIELD DIRECTIVES

    2.1.

    TTC Alley & Home Dairy Alley: Design for

    TTC issued 7/21; Vault infill required at

    #1562.2.

    Electric Panel & Kiosk Housekeeping Pads:

    Bulletin #13 issued 7/14/14; Sasaki to

    revise SKL-16 to reverse layout of kiosk

    and LP-4

    3.

    CRITICAL PATH ITEMS

    3.1.

    Simeons: Demo and temp exterior wall

    to be complete 7/22; Vacri to re-install

    plywood fence for pedestrian walkway

    7/23

    Vacri can start re-installing fence

    tomorrow. May use the chain link fence

    which is currently at the Aurora St

    intersection. The City would prefer the

    plywood panels from Bank Alley be used.

    3.2.

    P&CG: Finish install of LP-4, kiosk conduit,housekeeping pads, and bollards; move

    to 200 Block E State

    Sasaki issued a sketch this morning thatshows the underground mate is required.

    Anchor bolts are not required.

    3.3.

    NYSEG Gas:2nd crew starts 7/22; Branch

    saddles in progress; need decision on 171

    E State low pressure or medium by 7/23;

    Aurora Street stub>pressure test>gas up

    main week of 7/28; work on Saturdays?;

    Second crew will work on branch saddle

    into Mias. DS mentionedthat a crew will

    need a half day to replace broken valve

    boxes on Bank Alley. Simeons

    intersection should be open to DDS

  • 8/10/2019 2014-07-22 Construction Meeting Minutes.pdf

    4/4

    Page 4of 4

    repair/replace water curb box at 148 E

    State

    tomorrow (7/23).

    DS concerned about grading on Tioga

    the one inch line off of the drip is sticking

    out of the ground where they have

    regraded.

    171 E State St (Center Ithaca) decision

    needs to be made about connecting low

    or medium pressure service. DDS may

    need to give them low pressure now and

    then come back in a few years to retire it.

    Medium pressure decision may take up to

    two years so they cant wait on that

    decision.

    NYSEG will discuss with DDS if working on

    Saturdays is an option.

    3.4.

    NYSEG Electric: Overhead wire at Aurora

    complete; need to disconnect feed at SW

    corner of intersection btw HH and lightpole; JC to provide start date for pulling

    wire to Aurora St

    3.5.

    202 E State Waterproofing: Notify

    property owner of schedule for demo

    paving above vault

    3.6.

    Pavilion Lighting: MK to issue summary of

    meeting with City Inspector and City

    Electrician

    4.

    M&PTP: MAINTENANCE & PROTECTION

    OF TRAFFIC & PEDESTRIANS

    4.1.

    Fence Reinstallation: PCG to reinstallfence in front of Trader Ks

    Already reinstalled

    4.2.

    Vacri to submit work sequence to City for

    review of pedestrian access, etc. prior to

    start of Bank Alley work (sidewalk demo,

    grading/compaction testing, set valve

    boxes, MH covers, slab pour, pavers, etc.)

    4.3.

    Site Maintenance: Vacri to mark out

    boxes; DDS & P&CG to locate and dig out

    valve boxes and remove excess material;

    All trash and debris must be removed on

    a weekly basis5. New Business: Open RFIs, submittals,

    concerns, etc.

    ADDITIONAL NOTES

    Concern about paint finish color possible discrepancy between snakehead boxes and utility

    panels. Sasaki will send color sample of what they approved.