2013-vii. flow sheeting

Upload: bagus-prakasa

Post on 02-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 2013-VII. Flow Sheeting

    1/43

    Chemical Engineering Drawing

    Menggambar Teknik Proses(ENCH600014)

    Topic VII

    Process Flowsheeting

    Departement of Chemical Engineering

    Universitas Indonesia

  • 8/10/2019 2013-VII. Flow Sheeting

    2/43

  • 8/10/2019 2013-VII. Flow Sheeting

    3/43

    Types of diagrams

    Block Diagram

    Material Flow Sheet

    Energy Flow Sheet

    Process Flow Diagram

    Information Flow Diagram

    Piping & Instrumentation

    Diagram

  • 8/10/2019 2013-VII. Flow Sheeting

    4/43

    Block Diagram

    Simplest form of presentation

    Each Block can be represent

    a single piece of equipment or

    a complete stage in the process

    For complex processes,

    1. usage of block diagram is limited to showing the overall

    process

    2. represent only the principle stages

    Useful for representing a process in a simplified form in reports and

    text books, but have only a limited use as engineering document

    Stream flow rates and compositions can be shown

    oadjacent to stream lines when only a small amount of information

    is shown

    o in a separate table

  • 8/10/2019 2013-VII. Flow Sheeting

    5/43

    Liquid

    storage

    LS- 01

    Liquid

    storage

    LS- 02

    Mixing

    M-03

    Reactor

    R-04

    For recycling

  • 8/10/2019 2013-VII. Flow Sheeting

    6/43

    Process Flow Diagram (PFD)

    Is the pictorial representation of the process layout with standard

    symbols

    Equipment should be drawn approximately to the scale (mainlyprincipal equipment)

    All equipment should be labeled

    Is shown the sequence of unit operations and stream connections

    Slide 7

    Usually include auxiliary services to the process

    circulating oil

    air

    water

    Steam

    flue gas

    refrigeration, etc. Slide 8

  • 8/10/2019 2013-VII. Flow Sheeting

    7/43

    Slide 6

  • 8/10/2019 2013-VII. Flow Sheeting

    8/43

    Fragment of PFD

  • 8/10/2019 2013-VII. Flow Sheeting

    9/43

    Reactor

    Heat exchange

    Tray columnFluid

    contacting

    column

    Sealed tank

    Standard symbols

    BS 8888 ; BS 1553

  • 8/10/2019 2013-VII. Flow Sheeting

    10/43

  • 8/10/2019 2013-VII. Flow Sheeting

    11/43

  • 8/10/2019 2013-VII. Flow Sheeting

    12/43

  • 8/10/2019 2013-VII. Flow Sheeting

    13/43

    Material Flow Sheet

    Is drawn with standard symbols and labeled and include all data

    obtained

    If no space available to label equipment, a equipment key can be

    drawn at the bottom of the flow sheet

    Following data should be shown on the flow sheet in deferent ways

    flow rate of each component

    total stream flow rate

    percentage composition

    Simplest method suitable for simple processes with few

    equipments, tabulate the data in blocks alongside the process

    stream Slide 14

    Better method applicable for all complex processes, stream line is

    numbered and the data tabulated at the top or bottom of the sheet

    (above and below the equipment layout) Slide 15

  • 8/10/2019 2013-VII. Flow Sheeting

    14/43

  • 8/10/2019 2013-VII. Flow Sheeting

    15/43

  • 8/10/2019 2013-VII. Flow Sheeting

    16/43

    Energy Flow Sheet

    Energy balance is to determine the energy requirement of the

    process:

    the heating, cooling and power required.

    In energy flow sheet

    Inlet and outlet energy flow rates should be shown separately for

    each piece of equipment

    Include

    energy (calculated by total enthalpy form or using specific

    capacity data) of each component in all (inlet and outlet)streams

    - process conditions of all (inlet and outlet) streams

    - process conditions of the specific equipment

    S

  • 8/10/2019 2013-VII. Flow Sheeting

    17/43

    Energy Balance Sheet

  • 8/10/2019 2013-VII. Flow Sheeting

    18/43

    Information Flow Diagram (IFD)

    Is used in simulation programmes

    Is presented by blocks

    Each block represents a calculation module in the

    simulation programme, usually a process unit or

    part of a unit

    units in which no change of composition ortemperature or pressure occurs are omitted from

    IFD

    But other operations not shown on the process

    flow diagram as actual pieces of equipment, butwhich can cause changes in the stream

    composition must be shown.

    Flow of information should be shown with lines and

    arrow

    Pi i & I t t ti Di (P & I)

  • 8/10/2019 2013-VII. Flow Sheeting

    19/43

    Piping & Instrumentation Diagram (P & I)

    Shows the engineering details of equipment, instrument, piping,

    valves and fittings and their arrangement

    Sometimes called as Engineering Flow Sheet or Engineering Line

    Diagram

    P & I should be included with

    All process equipment identified by equipment number

    All pipes identified by a line number. Pipe size and material of

    construction should be shown (material may include as a part of the

    identification number)

    All valves with an identification no. along with their type & size

    should be shown

    Ancillary fittings that are part of piping system such as inline sight

    glasses, strainers and stream traps with an identification no.

    Pumps identified by a suitable code no.

    All control loops and instruments with identification

  • 8/10/2019 2013-VII. Flow Sheeting

    20/43

  • 8/10/2019 2013-VII. Flow Sheeting

    21/43

    MeasuredVariable TypeofConditioner TypeofComponent

    F=Flow R=Recorder T=Transmitter

    L=Level I=Indicator M=Modifier

    P=Pressure C=Controller E=Element

    Q=Quantity A=Alarm

    T=Temperature

    nstrument dentification

  • 8/10/2019 2013-VII. Flow Sheeting

    22/43

    Pure oxygen is manufactured by liquefying air and distilling it to

    recover pure oxygen and nitrogen. The entering air is contactedwith potassium hydroxide solution in a CO2 absorption tower to

    remove carbon dioxide. The air (free of carbon dioxide) is then

    sent through a compressor to increase its pressure to 200 atm. In

    this process the temperature of arises to 50 0C and this is cooled

    to 30 0C in a water-cooled heat exchanger. The resultant air at200 atm and 30 0C is cooled to -30 0C in a first stage cooler and it

    is further cooled to -180 0C in a second stage cooler. The liquefied

    air mixture (N2 and O2) is distilled in a distillation column to

    produce a distillate product of 98% N2 and 2% O2 and a bottom

    product of 99% O2 and 1% N2.

    Draw a block diagram for the above process and indicate all

    process streams by arrows and label all streams and process

    units with pressure, temperature and compositions as per the

    above process description

    Example :

    KOH

  • 8/10/2019 2013-VII. Flow Sheeting

    23/43

    Absorption

    CoolerCooler

    Heat

    Exchanger

    Compressor

    Distillation

    Unit

    Air

    KOH

    CO2

    CO2 Free

    Air

    Compressed air

    500

    C, 200 Atm

    Water

    WaterCooled air

    300C, 200 Atm

    Cooled air

    -300C, 200 Atm

    Liquified Air Mixture

    -1800CDistilled Product

    N2 98%

    O2 2%

    Bottom Product

    N2 1%

    O2 99%

  • 8/10/2019 2013-VII. Flow Sheeting

    24/43

    Approach for Conceptual Design

    T i l W kfl I F d D i

  • 8/10/2019 2013-VII. Flow Sheeting

    25/43

    Typical Workflow In Front-end Design

    Projects

  • 8/10/2019 2013-VII. Flow Sheeting

    26/43

    Work Flow For Developing P&ID and PFD

    EquipmentData Sheet

    Plot Plan

    Process Flow Diagram(PFD)

    Piping & Instrument Diagram(P&ID)

    Material Selection Diagram(MSD)

    Piping ServiceClass

    PerhitunganHidrodinamika

    ClientSpecification

    PipingDesign

    InstrumentDesign

    MainFlow

    &

    ControlSystem

    Equipment Sizing

    EquipmentLocation

    Material Piping sizel

    Client requirementMaintenance Philosophy

  • 8/10/2019 2013-VII. Flow Sheeting

    27/43

    Introduction to notation for various important

    equipments in P&ID

  • 8/10/2019 2013-VII. Flow Sheeting

    28/43

    Numbering of equipments and instruments

    Agitators, Mixers

    Equipment/Item Number

    Title/Service

    Power Requirements

    Materials of Construction

    Vessels/Tanks

    Equipment/Item Number

    Title/Service

    Size, Capacity

    Design Pressure @ Temperature Materials of Construction

    Trim

    Insulation

  • 8/10/2019 2013-VII. Flow Sheeting

    29/43

    5. Penomoran Pipa (Line Numbering)

    Jika kita akan memulai penomoran line (pipa) dari angka 100 untuk membedakandan memudahkan pencarian. Dan pipa untuk service fluida HC terdiri dari 5 kelasuntuk berbagai rating dan maximum working pressure yang dapat dicapai, makapenotasian dapat berupa kelas A s/d E untuk service fluida HC ini, yang dibedakandengan ratingnya, misalnya kelas C s/d E untuk rating pipa yang lebih tinggi karenaadanya kontaminan CO2 dalam fluida HC tersebut.

    Selanjutnya berapa ukuran pipa yang dimaksud (setelah dipastikan denganperhitungan proses tentunya) adalah penotasian berikutnya, sehingga penotasianlengkap dapat berupa :

    100 - A - 2" atau 100 - HC - A - 2"

    Berarti : angka 100 adalah line number, huruf HC merupakan jenis fluida,

    huruf A adalah kelas yang dimaksud misal kelas 150#,

    2" adalah ukuran pipanya.

    Semua hal ini harus cocok dengan notasi pada gambar isometrik perpipaan yangada serta segala macam gambar yang diproduksi oleh departemen piping.

  • 8/10/2019 2013-VII. Flow Sheeting

    30/43

    6. Pengenalan berbagai simbol dalam P&ID

  • 8/10/2019 2013-VII. Flow Sheeting

    31/43

    Simbol Valve

  • 8/10/2019 2013-VII. Flow Sheeting

    32/43

    Simbol Garis

  • 8/10/2019 2013-VII. Flow Sheeting

    33/43

    Simbol Pipa

  • 8/10/2019 2013-VII. Flow Sheeting

    34/43

    Simbol Instrumentasi

  • 8/10/2019 2013-VII. Flow Sheeting

    35/43

    7. Pengenalan komponen penting lainnya dalam P&ID

    Drawing index : berisi daftar nomor P&ID dan judul-judul dari P&ID alurprocess/utilities yang dibuat, revisi yang pernah dibuat serta status P&IDtersebut apakah gambar dibuat untuk keperluan konstruksi atau untukkeperluan demolish/removal. Judul yang dapat dibuat untuk sebuah P&IDbisa berupa penggambaran satu buah equipment dalam alur prosesutamanya, misal High Pressure Separator (V-2001 A). Drawing index ini

    penomorannya dapat dimulai dari 00, melanjutkan contoh diatas makanomor drawing index adalah DM-PP-2000 sheet 1 of 3, dengan judul :Drawing Index.

    Simbol-simbol baik simbol statik/rotating equipment, instrumentasi,piping, elektrikal yang diperlukan dalam proyek tersebut yang dipecah jadibeberapa sheet bila diperlukan maka penomorannya bisa dicontohkanDM-PP-2000 sheet 2 and 3 of 3, melanjutkan notasi penomoran daridrawing index, dengan berjudul standard symbol and legend.

    Sambungan (link) antara berbagai P&ID harus match baik itu pipingnya :ukuran, spek, line numbernya maupun posisinya. Kemudian juga sinyalinstrumentasi yang ada, baik itu signal elektrikal ataupun pneumatic.Tentunya bagan to and from dari dan ke berbagai P&ID untukpenotasian piping atau sinyal itu harus dicantumkan lengkap disitu

    sehingga memudahkan pencarian dan pengertiannya aliran atau dari dankemana sin al itu ber alan.

  • 8/10/2019 2013-VII. Flow Sheeting

    36/43

    Penulisan simbol

  • 8/10/2019 2013-VII. Flow Sheeting

    37/43

    Contoh P&ID

  • 8/10/2019 2013-VII. Flow Sheeting

    38/43

    Control valve loop

    FC

    4300#

    PC

    005

    PY

    005

    PV

    005

    I/P

    H

    L

    PT

    005

    4

  • 8/10/2019 2013-VII. Flow Sheeting

    39/43

    LT/FT Cascade Control

    FC

    4300#

    FV102

    4

    6-PL-10042-AA11-N

    FT102

    FE102

    300#

    LT

    105DISP

    SP

    LI105

    H

    L

    FC102

    6-PL-10042-AA11-N

  • 8/10/2019 2013-VII. Flow Sheeting

    40/43

    Split range control(1)

    H

    L

    PT001

    I/P

    8-PG-10043-AA11-N

    FC/TSO4300#

    PY001D

    PV001B

    I/P

    6-PG-10042-BA21-N

    FC

    4300#

    PY001C

    PV001A

    a

    2xa

    2x(a-50)

    0 100PIC OUTPUT

    100

    0

    A

    CVOPENING

    6

    6-PG-10043-BA21-N

    6

    4

    PY001A

    PY001B

    P

    PC001

  • 8/10/2019 2013-VII. Flow Sheeting

    41/43

    Split range control(2)

    2-PG-10102-AA11-N

    I/P

    3-PG-10101-AA11-N

    1-1/2

    PY001D

    PY001A

    a

    2x(50-a) 2x(a-50)

    0 100PIC OUTPUT

    100

    0

    A

    CVOPE

    NING

    I/P

    FC1

    PY001C

    PV001A

    PC001

    AH

    AL

    PT001

    FC

    PV001B

    2

    3

    1-1/2

    2

    PY001B

  • 8/10/2019 2013-VII. Flow Sheeting

    42/43

    Typical centrifugal compressor

  • 8/10/2019 2013-VII. Flow Sheeting

    43/43