2013 06 26 bch ts 74 phase 2 amendments final submission · final submission . bc hydro writes in...
TRANSCRIPT
British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3
www.bchydro.com
Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 [email protected] June 26, 2013 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor – 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: Project No. 3698694
British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro) Application to Amend Tariff Supplement (TS) No. 74 - Customer Baseline Load (CBL) Determination Guidelines for RS1823 Customers with Self-Generation Facilities (the “Application”) Final Submission
BC Hydro writes in compliance with BCUC Order No. G-91-13 to provide its Final Submission (Attachment 1) for the written review process related to the Application. Yours sincerely,
Janet Fraser Chief Regulatory Officer ac/kp Enclosure Copy to: BCUC Project No. 3698694 (BC Hydro Application to Amend TS No. 74)
Registered Intervener Distribution List.
BC HYDRO
APPLICATION TO AMEND TARIFF SUPPLEMENT No. 74-
CUSTOMER BASELINE LOAD (CBL) DETERMINATION GUIDELINES
FOR RATE SCHEDULE 1823 CUSTOMERS WITH
SELF-GENERATION FACILITIES
FINAL SUBMISSION
June 26, 2013
01249.97755.1DW.9209582.3
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 1 of 10
1.0 INTRODUCTION
1. In this Application, BC Hydro seeks approval for the addition of Attachment 8 -
Guidelines for RS 1823 Customers with Self-Generation Facilities (Attachment B
Guidelines) to Tariff Supptement N"o. 74 (TS No. 74). The Application also seeks
approval for ancillary amendments to the body of TS No. 7 4 resulting from the addition
of the Attachment B Guidelines.
2. After extensive consultation with customers and other interested parties, 1 BC Hydro filed
the Application with the British Columbia Utilities Commission (BCUC) in November
2012. The BCUC established a written hearing process for the Application, including two
rounds of information requests and written final submissions.2 BC Hydro filed its
response to the first round of information requests on January 28, 2013, and its
response to the second round of information requests on March 11, 2013.3
3. Two parties intervened: (1) the Association of Major Power Customers (AMPC), and
(2) Zellstoff Celgar Limited Partnership (Celgar).
2.0 INTERVENERS IN THIS PROCEEDING
4. AMPC is the only intervener in this proceeding with members that are BC Hydro Rate
Schedule (RS) 1823 customers. In its December 7, 201 2 1etter requesting intervener
status,4 AMPC confirmed its support for the Application as filed. AMPC did not file
information requests or intervener evidence.
5. No other BC Hydro customer or group representing BC Hydro customers intervened in
this proceeding. Celgar was the only other intervener.
6. Celgar is a FortisBC customer and not a BC Hydro customer. Celgar currently sells
electricity to BC Hydro under an Electricity Purchase Agreement (EPA). In its December
10, 20121etter requesting intervener status,5 Celgar stated that it will be "affected by the
1 Summarized in section 6.0 of this final submission. 2 Exhibits A-1, A-4 and A-8. 3 Exhibits 8-3, 8-4, 8-5 and 8-6. 4 Exhibit C1 -1. 5 Exhibit C2-1.
01249.97755.1DW.9209582.3
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 2 of 10
2
Application because the proposal to establish terms of service for self-generation
customers of BC Hydro will have direct or indirect consequences for self-generation
customers of FortisBC Inc."
7. In BC Hydro's January 25, 2013 cover letter to its response to Cergar Information
Request No. 1,6 BC Hydro responded to Celgar's asserted interest in the Application as
follows. The Attachment B Guidelines only apply to BC Hydro's RS 1823 customers,
and so do not apply to Celgar. Moreover, by Order No. G-202-12 and the accompanying
Reasons for Decision the BCUC confirmed that Celgar's electricity supplier, FortisBC,
may use mechanisms that are different than those used by BC Hydro to uphold a
consistent regulatory principle that other utility ratepayers should not be harmed by a
self-generator's arbitrage of embedded cost power. These mechanisms, together with
any FortisBC rates and tariffs applicable to Celgar, are matters between the BCUC,
FortisBC, Celgar and FortisBC's other customers.
8. Accordingly, in BC Hydro's view this Application has no direct or indirect consequence
for Celgar.7
3.0 Purpose of the Application
9. The Attachment B Guidelines set out criteria for Customer Baseline Load (CBL)8
determination, adjustment and reset specific to BC Hydro RS 1823 customers with
electrical power self-generation facilities. 9 The CBL forms part of RS 1823 under which
the majority of BC Hydro's transmission service customers receive service. For all
RS 1823 customers, including those with self-generation faci lities, the CBL is based on
historic annual electrical energy consumption, and energy billing is based on the annual
volume of RS 1823 energy purchases relative to the customer-specific CBL. Where an
6 Exhibit B-4, cover letter. 7 Ibid. 8 The terms "Energy CBL" and "CBL" are used interchangeably, and each refers to the Energy CBL determined under TS No. 74. 9 As per section 2(p) of the Attachment B Guidelines, "self-generation facilities" means electrical power generation facilities that are installed at the same site as the customer's plant, on the customer's side of the point of delivery, and are used to supply a portion of the customer's plant load.
01249. 97755.1DW.9209582.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 3 of 10
3
RS 1823 customer has self-generation facilities, both the CBL and RS 1823 energy
purchases are impacted by self-generation output.
10. Prior to the Application, TS No. 7 4 did not explicitly address circumstances related to
customer serf-generation, so BC Hydro relied on the TS No. 7 4 treatments for DSM
projects 10 and section 6.2.2 of TS No. 7 4: 11
"If a customer proposes adjustments that are not defined in these CBL
Determination Guidelines, BC Hydro will discuss the proposed adjustments with
the customer. In cases where BC Hydro agrees with the customer's proposed
adjustments and they are consistent with BC Hydro's overall rate design
principles, BC Hydro will file the proposed CBL with the Commission . "
11. This framework formed the basis for a comprehensive set of business practices for CBL
determination, adjustment and reset specific to RS 1823 customers with self-generation
facilities.
12. BC Hydro believes that these business practices are consistent with the principles set
out in section 1.0 of TS No. 74. The CBL-related treatment applied by BC Hydro was set
out in each customer's CBL determination letter and annual CBL Statement. The
customer-specific CBL determinations were filed with the BCUC for review and approval
under sections 58 to 61 of the Utilities Commission Act. The BCUC has approved each
CBL determination for RS 1823 customers with self-generation facilities as filed.
13. The Attachment B Guidelines incorporate into the tariff the comprehensive set of
business practices developed for RS 1823 customers with self-generation facilities,
closing the "information gap" where TS No. 74 did not explicitly prescribe these CBL
related treatments. The Attachment 8 Guidelines will provide additional information for
customers as to the CBL-related treatments that apply in relation to their self-generation
· output and for the BCUC in conducting annual CBL approvals.
10 The existing approved version of TS No. 7 4 treats load displacement that a customer has implemented at the customer's plant (meaning self-generation facilities) as demand side management (see TS No. 74 section 2.0 definition of"Demand Side Management (DSM) project"). 11 Application, section 1, pages 2-3; response to Celgar IR 1.1.0.
01249. 97755.1DW.92095S2.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 4 of 10
4
14. Section 4 of the Application, at pages 8 to 14, summarizes the structure and content of
the Attachment B Guidelines. That summary will not be repeated in this submission.
4.0 Matters that are not part of the Application
15. The information requests submitted to BC Hydro in this proceeding indicate considerable
interest in matters that are not part of the Application, as follows.
16. In June 2012, BC Hydro submitted its GBL Information Report to the BCUC for
information purposes. A copy of the GBL Information Report is on the record of this
proceeding as Exhibit A2-1 . BC Hydro is not seeking BCUC approval of the
GBL Information Report as part of the Application or otherwise.12
17. The Attachment B Guidelines are not related to the design or commercial terms of an
EPA or Load Displacement Agreement (LOA) between BC Hydro and a customer, nor
do they address eligibility criteria for entering into an EPA or LOA with BC Hydro. The
Attachment B Guidelines do not enable customers to sell electricity to BC Hydro or to
enter into a LOA with BC Hydro.
18. The Attachment B Guidelines do not address the rules that will apply if a customer
wishes to sell self-generated electricity to a third party.13
19. The Attachment B Guidelines do not apply to BC Hydro's RS 1823 customers who do
not have self-generation facilities.
20. The Attachment B Guidelines do not specify terms of service between FortisBC, or any
other utility, and its customers with self-generation facilities. The Attachment B
Guidelines do not relate to the terms of service of the kind suggested by many of the
information requests submitted by Celgar in this proceeding.14
12 Application, section 2, page 4; response to BCUC IR 1.2.2. 13 Application, section 4.2, page 8; responses to BCUC IRs 1.13.1 and 1.13.2. 14 Examples include Celgar IRs 1.1.5, 1.1.7, 1.2.1, 1.2.2, 1.2.7, 1.2.8, 1.2.9, 2.1.1 , 2.1.2, 2.1.5 and 2.4.1.
01249. 97755.1DW.9209582.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 5 of 10
5
5.0 Attachment B Guidelines - Use of GBLs
21. The information requests submitted in this proceeding also indicate considerable interest
in BC Hydro's determination and use of generator baselines (GBLs).
22. Two types of GBLs are used in the Attachment B Guidelines: 15
(1) Non-Contracted GBL (specific to a single non-contracted generating unit where
the customer does not have a contract with BC Hydro to make power; for a
customer with multiple non-contracted generating units the "Non-Contracted Site
GBL" is the sum of the Non-Contracted GBLs; for a customer with a single non
contracted generating unit, the Non-Contracted Site GBL is equal to the Non
Contracted GBL for that generating unit); and
(2) Contracted GBL (for a customer that has a contract (EPA and/or LOA) with
BC Hydro to make power from self-generation facilities; the Contracted GBL can
represent a single or multiple generating units).
23. Notwithstanding the type of GBL, the core purpose of each of the GBLs used in the
Attachment B Guidelines is the same: to identify the historical amount of self-generation
output normally used for self-supply so incremental self-generation output in excess of
the amount normally used for self-supply can be determined.
• For non-contracted generating units, incremental self-generation is measured
relative to the applicable Non-Contracted Site GBL.16
• For contracted generating units, incremental self-generation is measured relative to
the applicable Contracted GBL, which is an express or implied term of the EPA or
LOA.
24. Verified incremental self-generation output may be eligible for various CBL-related
treatments under the Attachment B Guidelines. The following sections 5.1 and 5.2 of this
15 The terms "Non-Contracted GBL", "Non-Contracted Site GBL" and "Contracted GBL" are defined in section 2 of the Attachment B Guidelines. 16 Refer to the definition of "Incremental Self-Generation Output" in section 2 of the Attachment B Guidelines.
01 249.97755.1DW.9209582.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 6 of 10
6
final submission summarize the differences between Non-Contracted GBLs and
Contracted GBLs, as used in the Attachment B Guidelines.
5.1 Non-Contracted GBLs
25. An RS 1823 customer generating unit that is used to make self-generation output in the
absence of a contract with BC Hydro in relation to any portion of that output is termed a
"Non-Contracted Generating Unit".17 All of the generating unit's output is used by the
customer for self-supply and displaces an equivalent volume of RS 1823 electricity
purchases from BC Hydro.
26. There is no arbitrage concern in relation to non-contracted generating units because, by
definition, there is no simultaneous sale and purchase of electricity. The customer is not
selling electricity to anyone. All of the customer's self-generation output is used for self
supply only. 18
27. BC Hydro will establish a Non-Contracted GBL for each non-contracted generating unit
where the customer requests recognition of their incremental self-generation output for
CBL treatment purposes.19 The Non-Contracted GBL is equal to the actual gross
metered output of the non-contracted generating unit during the 365 day period used to
determine the customer's CBL.20 The "Non-Contracted Site GBL" is equal to the sum of
the Non-Contracted GBLs for each non-contracted generating unit at the same site.21
28. The Non-Contracted GBL is the baseline amount of gross self-generation output that
displaced an equivalent portion of RS 1823 energy during the CBL determination year,
enabling determination of the amount, if any, of incremental self-generation output that
17 Attachment B Guid~lines, section 20). 18 Response to BCUC IR 1.13.2.1. 19 Attachment B Guidelines, section 3.1.2. 20 Attachment B Guidelines, sections 2(i). 21 Attachment B Guidelines, section 2(k).
01 249. 97755.1DW. 9209582.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 7 of 10
7
displaced an equivalent incremental portion of RS 1823 energy purchases in subsequent
billing years. 22
29. Section 3.0 of the Attachment B Guidelines sets out the criteria for determination,
adjustment and reset of CBLs for customer's with Non-Contracted GBLs. In short, the
Non-Contracted GBL is determined by gross self-generation output during the CBL
determination year, and incremental self-generation output is treated like customer
funded OSM and is an Energy Bill Adjustment for the billing year in which it occurs.
These provisions are summarized in sections 4.4 and 4.5 of the Application.
5.2 Contracted GBLs
30. An RS 1823 customer generating unit that is used to make self-generation output in
accordance with a LOA and/or an EPA with BC Hydro (an EPA or LOA is referred to
herein as a "contract") is termed a "Contracted Generating Unit".23
31. Where an RS 1823 customer has a contract, a Contracted GBL will be an express or
implied term of the contract. The Contracted GBL is intended to represent the amount of
self-generation output a customer would have generated for self-supply in a "normal"
year absent an EPA or LOA, and is generally fixed over the term of the contract. The
purpose of a Contracted GBL is to mitigate the risk of arbitrage that exists when a
customer is buying embedded-cost ·electricity from BC Hydro while, at the same time,
selling self-generated electricity to BC Hydro (or pursuant to a LOA, taking an incentive
from BC Hydro to make self-generation output for self-supply).
32. There may be more than one Contracted GBL if there is more than one type of contract
for the same contracted generating unit (e.g., a Contracted GBL for the EPA and a
Contracted GBL for the LOA). If there are multiple contracts, the commitments to make
self-generation output are prioritized.
33. The Attachment 8 Guidelines address the criteria for determination, adjustment and
reset of the CBL for a self-generator that has entered into a contract with BC Hydro.
22 Attachment 8 Guidelines, section 2(f) definition of "Incremental Self-Generation Output"; response to 8CUC IR 2.12.1. 23 Attachment 8 Guidelines, section 2(c).
01 249. 97755.1DW.9209582.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 8 of 10
8
34. The Attachment B Guidelines do not address eligibility to enter into a contract with
BC Hydro, nor do they address the principles or methodology to determine a Contracted
GBL for the contract. BCUC Order No. G-38-01 and BC Hydro's June 20, 2012 GBL
Information Report (Exhibit A2-1) articulate the principles underlying the negotiation of a
Contracted GBL between BC Hydro and a customer.
35. The BCUC has the jurisdiction to review an EPA and consider a Contracted GBL used in
such EPA as part of reviewing a contract filed under section 71 of the Utilities
Commission Act, if applicable. The BCUC may also consider Contracted GBLs in
reviewing a DSM expenditure schedule filing under section 44.2 of the Utilities
Commission Act, to the extent the expenditure schedule includes expenditures on LDAs
with Contracted GBLs.24
36. Section 4.0 of the Attachment B Guidelines sets out the criteria for CBL determination,
adjustment and reset where there is a contracted generating unit. This information is
summarized in sections 4.4 and 4.6 of the Application.
6.0 Pre-Filing Consultation
37. Before filing the Application, BC Hydro performed extensive consultation with RS 1823
customers, AMPC, BCUC staff and other interested parties. As set out in section 5.0 of
the Application, consultation included workshops with customers and BCUC staff in late
2010, province-wide workshops for all TSR customers, multiple one-on-one discussions
with self-generating customers, and a pre-filing workshop on October 12, 2012.
38. The pre-filing workshop was attended by AMPC, RS 1823 customers, BCUC staff,
FortisBC and Celgar. A copy of the workshop presentation ~an be found at Appendix A
of the Application.
24 Responses to BCUC IRs 1.1.3.2 and 2.1.2.
01249.97755.10W.9209582,3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 9 of 10
9
7.0 Conclusion
39. BC Hydro submits that the BCUC should approve the Attachment B Guidelines and
ancillary amendments to TS No. 7 4 as filed for the following reasons:
(1) The Attachment B Guidelines incorporate into the tariff existing business practices in
respect of CBL-related treatments for RS 1823 customers with self-generation
facilities. There are no incremental financial impacts to BC Hydro or other
ratepayers;25
(2) The Attachment B Guidelines provide additional information for customers with self
generation facilities as to the CBL-related treatments applicable to their self
generation output, and for the BCUC in conducting annual CBL approvals;
(3) · BC Hydro consulted extensively with RS 1823 customers and other interested
parties before the Application was filed; and
(4) The association (AMPC) that represents a broad cross-section of RS 1823
customers (both with and without self-generation facilities) supports the BCUC
approving the Application as filed. No BC Hydro customer or association
representing customers opposes the BCUC approving the Application as filed.
40. In short, the Attachment B Guidelines and related amendments toTS No. 74 will
incorporate existing business practices into the tariff, and are supported by customers.
ALL OF WHICH IS RESPECTFULLY SUBMITTED
lanD. Webb
Counsel for BC Hydro & Power Authority
25 Response to BCUC IR 1.12.5.
01249.97755.1DW.9209582.3
BC Hydro Final Submission
June 26, 2013
Application to Amend TS74 BC Hydro Final Submission
Attachment 1
Page 10 of 10