2012 project
TRANSCRIPT
-
7/28/2019 2012 Project
1/66
CONTENTS
CHAPTER TITLE PAGE NOS
ABSTRACT
LIST OF FIGURES
LIST OF TABLES
I INTRODUCTION 1
1.1 LOAD FLOW 1
1.2 IMPORTANCE OF LOAD FLOW 3
1.3 DISBUT SOFTWARE 4
1.4 CASE STUDY 4
II DETAILED DISCRIPTION OF GENERATION
TRANSMISSION AND DISTRIBUTION
2.1 INTRODUCTION 5
2.2 CLASSIFICATION OF POWER SYSTEMS 6
III AP TRANSCO PLANNING CRITERIA
3.1 INTRODUCTION 93.2 TRANSMISSION PLANNING 10
REQUIREMENTS
3.3 SUBSTATION DATA 10
3.4 DISTRIBUTION LOAD FORECAST 11
3.4.1 SYSTEM LOAD FORECAST 11
3.4.2 GLOBAL LOAD FORECAST 11
3.5 PERSPECTIVE PLANNING 12
IV LOAD FLOW STUDIES ON SUBSTATION
4.1 INTRODUCTION 13
4.2 VOLTAGE SPREAD 13
4.3 EFECTS OF VOLTAGE SPREAD 15
-
7/28/2019 2012 Project
2/66
ON UTILIZATION EQUIPMENTS
4.4 INDUCTION MOTORS 16
4.5 VOLTAGE ZONES 17
4.5.1 FAVOURABLE ZONE
4.5.2 TOLERABLE ZONE
4.5.3 EXTREME ZONE
4.6 UTILIZATION EQUIPMENT VOLTAGE RATING 18
4.7 VOLTAGE DROP IN SYSTEM COMPONENTS 19
4.7.1 RESIDENTIAL FEEDERS
4.7.2 DISTRIBUTION FEEDERS
4.7.3 PRIMARY FEEDERS
4.7.4 RURAL FEEDERS
4.7.5 INDUSTRIAL FEEDERS
4.8 VOLTAGE REGULATION BASED ON P.F AND 25
D.F
4.8.1 POWER FACTOR
4.8.2 DIVERSITY FACTOR
4.9 METHODS OF IMPROVING VOLTAGE 26
REGULATION
V SOFTWARE DESCRIPTION 28
5.1 OPEN SYSTEMS 28
5.2 CUSTOMIZED GUI 28
5.3 FULL GRAPHICS 28
5.4 DIGITISATION 28
5.4.1 NETWORK
5.4.2 GEOGRAPHICAL INFORMATION
5.5 SYSTEM ANALYSIS 29
5.5.1 LOAD FLOW ANALYSIS
5.5.2 SHORT CIRCUIT STUDY
5.5.3 PROTECTIVE CO ORDINATION
-
7/28/2019 2012 Project
3/66
5.5.4 LOAD MODEL
5.6 SYSTEM PLANNING 29
5.6.1 TRENDS OF GROWTH
5.6.2 GLOBAL LOAD FORECAST
5.6.3 SPATIAL LOAD FORECAST
5.6.4 LOCATION AND SIZING OF SUBSTATION
5.6.5 PERSPECTIVE PLANS
VI CASE STUDY 32
MAPS
6.1 SINGLE LINE DIAGRAMS OF FEEDERS 32
6.2 CASE I 37
6.3 CASE II 38
6.4 HAND CALCULATIONS 42
6.5 OBSERVATIONS. 56
VII RESULTS 57
VIII CONCLUSION 64
-
7/28/2019 2012 Project
4/66
CHAPTER-1
INTRODUCTION
1.1 LOAD FLOW.
Power Flow studies are also known as load flow studies. The principal
information obtained from these studies is the voltage at each bus and real and reactive power
flowing in each line. There by calculates voltage regulation of each feeder, power flow in all
branches, feeder circuits, losses in each branch and total system power losses. A typical power
system single line diagram comprising generation, transmission and distribution is given below.
The main parts of power system are as follows:
1. Generating stations.
2. Transmission systems.
3. Distribution networks
The description about the following parts of the power system would be given in detail in
the next chapter.
-
7/28/2019 2012 Project
5/66
GENERATOR 11KV
TRANSFORMER 11KV/400 KV
400KV/220KV
EHV
TRANSMISSION
HT LOAD
33KV/11KV
HIGH VOLTAGE
DISTRIBUTION 11KV
11KV/0.4KV
LOW VOLTAGE DISTRIBUTION
0.4 KV
-
7/28/2019 2012 Project
6/66
1.2 IMPORTANCE OF LOAD FLOW
The importance of these studies is planning the future expansion of power
system as well as in determining the best operation of existing system. Load flow is an importanttool involving numerical Analysis applied to power system . Power flow analysis is very
important in planning stages of new networks in additional to existing ones.
It is helpful in determining the best location as well as optimal capacity of proposed generating
stations and substations
The conventional method of calculating voltage regulation is simple based onKVA KM loading of conductors.
Also, the conventional method to evaluate the demand loss (or) peak power
loss on a distribution feeder is based on the use of loss constants. The conventional technique is
simple but may not result in correct computation of loss for the following reasons:
The loss constants are obtained on the assumptions that voltage at all buses along the
length of feeder is the rated voltage.
The drop in voltage of the feeder from source to tail end and the consequent increase in
loss are not considered.
The demand loss in each feeder segment increases the power flow in all preceding
feeder segments up to the source. The effect of such loss is not considered in the demand loss
in each feeder segment increase the power flow in all preceding feeder segments up to the source.
The effect of such loss is not considered in the conventional method.
At present power utilization increased leaps and bounds thus posing requirement of bulk
generation and transmission of power. As in example generation installed capacity of AP is
15000 MW in 2011 a against 4065 MW in 1991 similarly the bulk power generated at pit heads
or projects need to be transported to the load centers necessitating EHV network that is
-
7/28/2019 2012 Project
7/66
operated at higher voltages i.e from 132 KV to 220 KV and much more to 400 KV and 765 KV
which is under progress. Ultimately all this power need to be deliver to the door steps of various
consumers through sub transmission and distribution networks. All these stages of power system
is capital oriented thus necessitating lot of studies for effective capital investment and
remunerative technically as well as economically.
Latest technology/ powerful software tools are finding place in calculating such
cumbersome calculations in power systems.
1.3 DISBUT SOFTWARE.
DISBUT software used in APTRANSCO is very accurate and well defined to
meet the above requirements.
The power flow techniques such as Newton- Raphson method, fast decoupled load
flow method etc, are used to solve well behaved power systems effectively. But, when these
techniques are applied to ill-conditioned (or) poorly initialized power systems have led to
many short comings . Whereas the DISBUT package is more suitable for calculating voltages,
currents, active and reactive power flowing in each line, there by voltage regulation and power
loss of radial feeders at different voltage levels ( i.e.., 33kv , 11kv etc).
1.4 CASE STUDY.
As a case study, the voltage regulation and power loss of the following 33kv
feeders were considered.
1. Mustyal ----------Tharigoppula
2. Raghunathpalli-----------Quilashapur
3. Jangoan-------------Gandiramaram
4. Jangoan------------ Adavikeshapur
5. Ghanpur------------Tadikonda
6. Ghanpur------------Malkapur
7. Mustyal-------------Dhoolmitta
-
7/28/2019 2012 Project
8/66
The results were analyzed duly applying optimization techniques like adding of a new
sections for alignment of loads on 33 KV side. Adding of new feeders and new 132/33KV
substations at optimal location was suggested.
CHAPTER-2
DETAILED DESCRIPTION OF GENERATION ,
TRANSMISSION AND DISTRIBUTION
2.1 INTRODUCTION:
Energy provides power to progress. We need energy in various forms like heat, light ,sound
etc .The development new technology made it possible to convert electrical energy into any form
of energy. This gives electrical energy an important position in the world. The running of the
modern industrial structure depends on the low cost and the uninterrupted supply of electricity.
In short we can say that a country is developed if the per capita consumption of electrical energy
is much higher.
Electrical energy is considered to be superior over other energy forms the following facts gives
the proof for it.
1. Convenient energy form: Electrical energy could be considered as the most
convenient form of energy as it could be converted from one form to another easily.
2. Flexibility: Another important aspect of electricity is the flexibility, it is very easy to
carry electricity from one place to other by using conductors
3. Cheapness: Electrical energy is much cheaper compared to other forms of energy.
The cost of production and availability is much larger compared to other forms of
energy and hence it is an inevitable component in all sectors of the modern world.
4. Cleanliness: Electrical energy is not associated with polluting factors such as smoke,
dust, fumes ,poisonous gases etc thus it offers a healthy atmosphere to each and all
living organism in the world.
-
7/28/2019 2012 Project
9/66
5. High Transmission Efficiency: The transmission efficiency of electrical energy
is much higher.
2.2 CLASSIFICATION OF POWER SYSTEM
The main parts of the electrical energy power system are:
Generating stations.
Transmission systems.
Distribution network.
2.2.1 Generating stations: electrical energy generation
Electrical energy is being generated in large hydro, thermal, and nuclear power stations
but the stations are located far away from the load centers. Large and long transmission
networks are wheeling the generated power from the sending end stations to sub stations
and the load centers. Several electrical equipments are pressed into service for proper
transmission and distribution of the generated power.
Economic dispatch is an important aspect to be studied in a power system. As generator
is the prime source of energy, hence economic operation of generators is very much
necessary to be analyzed.
Now a days, the major electrical equipment in power stations that is being used for
highest practical voltage for generation is 33kv though 11kv/12kv/13kv/15kv are the
most usual. If a generator is to feed a network at 33kv there is a strong case for
generation for 33kv as it will avoid the use of step up transformers.
There are two methods of electrical generations:
Conventional
Non-conventional
The conventional energy sources of electrical generations are
Thermal stations
Hydro electric stations
Nuclear power stations
-
7/28/2019 2012 Project
10/66
Diesel electric stations
The non-conventional energy sources of electrical generations are
Wind energy
Solar energy
Fuel cells
Tidal power generation
Geo-thermal energy
2.2.2 Transmission systems:
Electric-power transmission is the bulk transfer ofelectrical energy, from
generatingpower plantsto electrical substationslocated near demand centers.Transmission lines,
when interconnected with each other, become transmission networks. Transmission system
design will require a study of choice with reference to transmission voltage, constants of
transmission, design interference with neighboring communication circuits behind line insulation
and corona problems.
Electricity is transmitted athigh voltages(110 kV or above) to reduce the energy lost in
long distance transmission. There are two types of transmission lines which are as follows:
Overhead transmission lines
Underground transmission lines
Power is usually transmitted through overhead power lines. Underground power
transmission has a significantly higher cost and greater operational limitations but is sometimes
used in urban areas or sensitive locations.
2.2.3 Distribution network:
Electricity distribution is the final stage in the deliveryofelectricityto end
users. A distribution system'snetworkcarries electricity from the transmission systemand
delivers it to consumers. Typically, the network would include medium-voltage (less than 50 kV)
power lines, substations and pole-mounted transformers, low-voltage (less than 1 kV)
distribution wiring and sometimes meters. The modern distribution system begins as the primary
circuit leaves the sub-station and ends as the secondary service enters the customer's meter
http://en.wikipedia.org/wiki/Electrical_energyhttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/Overhead_power_linehttp://en.wikipedia.org/wiki/Power_deliveryhttp://en.wikipedia.org/wiki/Electricityhttp://en.wikipedia.org/wiki/Electricityhttp://en.wikipedia.org/wiki/Grid_(electricity)http://en.wikipedia.org/wiki/Grid_(electricity)http://en.wikipedia.org/wiki/Electric_power_transmissionhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electricity_meterhttp://en.wikipedia.org/wiki/Electricity_meterhttp://en.wikipedia.org/wiki/Electrical_energyhttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/Overhead_power_linehttp://en.wikipedia.org/wiki/Power_deliveryhttp://en.wikipedia.org/wiki/Electricityhttp://en.wikipedia.org/wiki/Grid_(electricity)http://en.wikipedia.org/wiki/Electric_power_transmissionhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electricity_meter -
7/28/2019 2012 Project
11/66
socket. Distribution circuits serve many customers. The voltage used is appropriate for the
shorter distance and varies from 2,300 to about 35,000 volts depending on utility standard
practice, distance, and load to be served. Distribution circuits are fed from a transformerlocated
in anelectrical substation, where the voltage is reduced from the high values used for power
transmission. Conductors for distribution may be carried on overhead
pole lines, or in densely-populated areas where they are buried underground. Urban and
suburban distribution is done with three-phase systems to serve both residential , commercial,
and industrial loads. Distribution in rural areas may be only single-phase if it is not economical
to install three-phase power for relatively few and small customers.
Only large consumers are fed directly from distribution voltages; most utility customers are
connected to a transformer, which reduces the distribution voltage to the relatively low voltage
used by lighting and interior wiring systems. The transformer may be pole-mounted or set on the
ground in a protective enclosure. In rural areas a pole-mount transformer may serve only one
customer, but in more built-up areas multiple customers may be connected. In very dense city
areas, a secondary network may be formed with many transformers feeding into a common bus
at the utilization voltage. Each customer has an "electrical service" or "service drop" connection
and a meter for billing. (Some very small loads, such as yard lights, may be too small to meter
and so are charged only a monthly rate.)
http://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Three-phase_electric_powerhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Three-phase_electric_power -
7/28/2019 2012 Project
12/66
CHAPTER-3
AP TNANSCO PLANNING CRITERIA
3.1 INTRODUCTION
We all know electrical energy cannot be stored, it is getting utilized
simultaneously while generated. Also load is very dynamic which poses challenge to the
system operators. To balance generation and demand, the system operator shall be
facilitated with sufficient data bank of past trends of load and expected load in future over a
stipulated period. This knowledge of old data and predicted future is system planning. Also
power system planning is to provide an orderly and economic expansion to meet the utility
future electric demand and acceptable reliability. Correct planning requires a proper forecast.
The quality and accuracy of this forecast is crucial to electric utility since it dictates the
planning of generation, transmission and distribution facilities. If the forecast is understated
it results in shortage in generation capacity and in adequacy of transmission and distribution
facilities. Similarly if it is over stated the result is excessive financial investments in facilities
in advance of actual needs and there by blocking of scarce capital which could have been
otherwise utilized in a more profitable way.
Planning of system involves determining
The correct sizes
Location
Interconnection
Timing future additions to this equipment
-
7/28/2019 2012 Project
13/66
Such planning is a difficult task, compounded by resent trends in tightening the
design margins. Correct planning of capacity of equipment requires a forecast of future
geographical distribution of electric demand.
During last decade a number of practical and efficient automated computerized
methods have been developed as an aid to system planning and design and determine minimum
cost plan. These automatic produces produce substantial saving over traditional methods, but
require high resolution projection future loads. Therefore to gain maximum benefit from these
produces, development of accurate forecast methods have been subject of increasing attention
during last few years.
3.2 TRANSMISSION PLANNING REQUIREMENTS:
Basic requirements for carrying a transmission planning study are:
Information on the existing transmission facilities.
Load forecast
Generation planning
Information on the existing transmission facilities:
Collection of all the available information on the existing system forms the first stage in the
planning process. Data required is as given below. Data is usually available in the records
maintained at the substations. Basic parameters required are,
Transmission line data line voltage, number of conductors per phase, size and type of
conductor and shield wire.
Line resistance, resistance and susceptance (positive and zero sequence)
Thermal capacity
Size and location of line connected shunt reactors
Size and location of series capacitive compensation
3.3 SUBSTATION DATA
Data required for transmission planning purposes, at the substation level and for each year
consists of
Real and reactive demand (MW and MVAR)
-
7/28/2019 2012 Project
14/66
Peak and minimum demand
Seasonal variation of demand
Single line diagram and layout plan
Transformer rating, impedance, tap changer ranges and type
Transformer winding arrangement
Transformer grounding arrangement
Circuit breaker continues and interrupting current ratings
Shunt reactor/capacitor ratings
3.4DISTRIBUTION LOAD FORECAST CAN BE CLASSIFIED INTO:
3.4.1System load forecast :viz. , forecast of the load for entire study area.
Spatial or small area load forecast: viz. , divide the utility area in to sufficiently large
number of small areas and forecast for each small area. There are number of different approaches
small areas and forecasting generally falling into two categories viz., trending and simulation
methods.
I. Trending method: Trending methods produces the future electric demand by extrapolation
the past trends, or pattern of load growth in small areas.
II .Multivariate method: This method builds relationship with one set of data viz. customer
demand data, and another class of data set such as controlled data that is pattern of land use,
number of customers in each class etc. the demand variables are forecasted given historical and
future set of control variables.
III. Land used based simulation method: in this methoda mathematical relationship has
been developed between.
a. Changes in electric usage on per customer basis,
b. Changes in the number and location of customers which drives the geographic spread ofelectricity demand.
Trend methods requires historical demand data for last 4-5 years, whereas
multivariate and land use simulation, methods requires historical land use data and customer
number in each class and also future land use and customer spread in small area.
-
7/28/2019 2012 Project
15/66
Global load forecast:Evaluates the energy and demand of the study area globally on
Long term basis using, time series different trend curves, regression techniques linking energy
and demand to various demographic and economic factors and end use method.
3.5 PRESPECTIVE PLANNING:
APTRANSCO adopts trends method for conducting feasibility studies for the
planning of 132/33 KV substations in AP.
A Case load flow study is done on 33kv feeders from 132/33kv-
mustyal,Raghunathpally, Jangaon, Ghanapur substations was presented in this thesis.
-
7/28/2019 2012 Project
16/66
CHAPTER-4
LOAD FLOW STUDIES ON SUBSTATION
4.1 INTRODUCTIONThe primary objective of system voltage control is to provide power to each user at
specified voltage that is directed by regulator.Ideally, the output of most power supplies should be a constant voltage. Unfortunately,
this is difficult to achieve. Voltage drop exists in each part of the power system from the source
to the consumer service drop. It also occurs in interior wiring. System voltage regulation is
essentially no more than maintaining the voltage at the consumer service entrance with in
permissible limits by the use of voltage control equipment.
In general the voltage drop is the difference between the voltage at the transmitting and
receiving ends of a feeder, main or service. There are two factors that can cause the output
voltage to change. First, the ac line voltage is not constant. The second factor that can change the
dc output voltage is a change in the load resistance. Many circuits are designed to operate with a
particular supply voltage. When the supply voltage changes, the operation of the circuit may be
adversely affected. Consequently, some types of equipment must have power supplies that
produce the same output voltage regardless of changes in the load resistance or changes in the ac
line voltage.
4.2 VOLTAGE SPREAD:
It is the difference between maximum and minimum voltage at a particular point in the
distribution system. It will vary in magnitude depending upon the particular location within the
system where the spread is measured. An illustration of the voltage spreads occurring at the
utilization point is shown in the figure below.
-
7/28/2019 2012 Project
17/66
FIG:4.1
Consumer A, which is the first consumer served by the feeder, has a voltage spread of
just 1 volt when going from light load (230v) to heavy load (229v) conditions. Consumer B
which is the last consumer served by the feeder has a voltage spread of seven volts i.e: 218v at
heavy load conditions to 225v at light load conditions. The utilization voltage at consumers A or
B for load conditions between the maximum and minimum values of the respective voltage
spreads.
The voltage spread at the utilization point of any other consumer on the same feeder
would have a voltage spread with somewhere between one and seven volts, depending upon the
location.
-
7/28/2019 2012 Project
18/66
Similar voltage spreads are found at the utilization points of every consumer on the
system. The average voltage spread at the utilization points are generally wider for rural
distribution feeders than residential feeders or urban feeders. Consumers on urban feeders
generally have smallest average voltage spread because the feeders are shorter in length and the
conductor sizes are larger.
FIG:4.2
4.3 EFFECT OF VOLTAGE SPREAD ON UTILIZATION EQUIPMENT:
Whenever the voltage applied to the terminals of utilization device varies from the
rated or nameplate voltage of the device, performance characteristics and equipment life will also
change. The extent of the change may be minor or serious depending upon the device, how it is
applied, and how much the terminal voltage deviates from the nameplate rating.
-
7/28/2019 2012 Project
19/66
Voltage drop will result in huge losses in network.
4.3.1 SOME MORE EFFECTS DUE TO VARIATION OF VOLTAGE ARE AS
FOLLOWS:
Lamps: a 10% reduction in lamp voltage results in a 30% reduction in light output it
means 30% of the investment is lost.
Fluorescent lamps will operate satisfactorily over a wide range of voltage spread and
their life is less affected. In general 1% variation in line voltage will change the
lumen output only by about 1%
Electronic equipment: the emission of all electron tubes is affected seriously by voltage
variation. The cathode life is curve indicates that the life is reduced by half for each 5%
increase in cathode voltage.
Capacitors: the kilowatt output of capacitors varies with the square of the impressed
voltage . a drop 10% in the supply voltage reduces the kilowatts by almost 20% .
4.4 INDUCTION MOTORS:
as voltage fails below rated rated voltage the starting torque reduces substantially,
because starting torque varies as the square of the applied voltage.
For an applied voltage 10% below rated voltage, the starting torque decreases to
81% of normal.
The reduction in the starting torque with low voltage may be significant and costly
in motor applications., driving high inertia equipment.
The table lists the general effects of voltage variation on induction motor.
Voltage variation
90% voltage Function of
voltage
110% voltage 120% voltage
Starting and
maximum
-
7/28/2019 2012 Project
20/66
1)Running
torque
2)Synchronous
speed
3)% slip
4)Full load
speed
Decreases
19%
No change
Increases 23%
Decreases 11/2
(voltage)2
Constant
1/(voltage)2
(syn. Speed-
slip)
Increases 21%
No change
Decreases
17%
Increases 1%
Increases 44%
No change
Decreases
30%
Increases1.5%
Efficiency
1)full load
2)3/4 load
3)1/2 load
Decrease 2 pt
Practically no
change
Increases 1 to
2 pts
-------
-------
-------
Increases to
1 pt
Practically no
change
Decreases 1 to
2 pts
Small increase
Decreases to
to 2 pts
Decreases 7 to
2 pts
Power factor
1)full load
2)3/4 load
3)1/2 load
4)Full load
current
Increases 1 pt
Increases 2 to
3 pts
Increases 4 to
5 pts
Increases 11%
-------
-------
-------
-------
Decreases 3
pts
Decreases 4
pts
Decreases 5 to
6 pts
Decreases 7%
Decreases 5 to
15 pts
Decreases 10
to 30 pts
Decreases 15
to 40 pts
Decreases
11%
Starting
current
Decrease 10
to 12%
voltage Increases 10
to 12%
Increase 25%
Temp rise ,full
load
Increase 6-7
degree
centigrade
--------
Decraeses 3-4
degree
centigrade
Decreases 5-6
degree
centigrade
Maximum
overload
capacity
Decreases
19%
(voltage)2 Increases 21% Increases 44%
Mag.noise- no Decreases Increases Noticeable
-
7/28/2019 2012 Project
21/66
-
7/28/2019 2012 Project
22/66
4.6 UTILIZTION EQUIPMENT VOLTAGE RATINGS:
The design (nameplate) voltage of utilization equipment is generally matched to the
utilization voltage that occurs during the time when it is most frequently used. Appliances which
are used for long duration and during any load conditions, light or heavy have design voltages the
same as nominal system voltage. Appliances of shorter time usage and relatively high demands
have a design voltage slightly less than nominal also the voltage spread used s a basis of design
for utilization equipment will vary depending upon the time usage and demand. For eg: the small
household cooking appliances have design voltage spread of 100 to 120 volts, while the large
household cooking appliances have design voltage spread of 107 to 122 volts.
4.7 VOLTAGE DROP IN SYSTEM COMPONENTS:
The system component voltage drop will be discussed only for the various types of
feeders from the location on the feeder of the first consumer served to the last.
4.7.1 RESIDENTIAL FEEDERS:
The voltage at the point of utilization when keeping with in the favorable zone can be 217
to 230 volts. The logical primary feeder designed to permit maximum loading and area coverage
is to permit the first consumer electrically nearest to the source to have maximum voltage of 230
volts during maximum load conditions. The most remote consumer electrically from the source to
have the minimum permissible voltage of 217 volts. The average voltage drop for residential
interior wiring during maximum load conditions is approximately three volts; hence, to have the
utilization voltage no lower than 217volts, the voltage at the consumers service entrance or meter
socket must be 220volts or above.
The feeder components of a residential feeder are shown in one-line diagram below.
Studies of residential feeder design have shown that at a definite amount of voltage drop can be
allocated to each component for maximum economy.
-
7/28/2019 2012 Project
23/66
FIG:4.7.1 Residential Feeder
4.7.1(A) SERVICE DROP:
The voltage drop most generally found for service drops during heavy load conditions
is 1 volt.
-
7/28/2019 2012 Project
24/66
4.7.1(B) SECONDARY LINE:
Secondary conductors when installed generally have a voltage drop of approximately two
to two and half volts, and as load increases the voltage drop is permitted to increase to three or
three and half volts. When the voltage drop reaches the upper limit another
distribution transformer is added between the existing, and the secondary line is split between the
new and existing units. Such a procedure reduces the secondary voltage drop to less than 1 volt.
4.7.2 DISTRIBUTION TRANSFORMER:
At the time of installation in a developed residential area, the transformer
loading during peak periods is generally 80 to 100 percent. For the average distribution
transformer rating this represents a voltage drop of 1.75 to 2.5 volts the transformer remains in
service until the peak load increases to about 140 to 160 percent. This represents a voltage drop
of 3.25 to 4 volts. The amount of voltage drop allocated to the distribution transformer out of the
permissible 12 volts spread is generally 3 volts.
4.7.3 PRIMARY FEEDERS INCLUDING LATEARLS:
The voltage drop allocated to the primary portion of the residential feeder is 3 volts, on a
120-volt base, and is as measured from the primary terminals of the first distribution transformer
on the feeder to the last or most remote transformer electrically. Where single phase laterals are
tapped off the three phase main, they generally have a voltage drop from one to three volts, with
the last lateral having about one volt drop, and the lateral tapped off near the first distribution
transformer on the feeder three volts.
4.7.4 RURAL FEEDERS:
Rural feeders are also similar to residential feeders. Length of the feeders is more i.e 5 to
10 times longer in rural feeder. Age loads play predominant role in rural feeders which contribute
poor power factor thus more voltage drops.
-
7/28/2019 2012 Project
25/66
FIG: 4.7.4 Rural Feeder
Below table shows typical voltage drop allocations for rural feeder components. The table
values keep the service voltage within the favorable zone. Even with the increased primary line
-
7/28/2019 2012 Project
26/66
drop as compared to the residential feeder, it is often necessary to add some supplementary
voltage boost out on the feeder.
FEEDER
COMPONENTS
RESIDENTIAL
FEEDER
RURAL
FEEDERMAXIMUM
LOAD
CONDITION
MINIMUM
LOAD
CONDITION
MAXIMUM
LOAD
CONDITION
MINIMUM
LOAD
CONDITION
Primary feeder From
first distribution
transformer to
Last
Distribution
Transformer
3.5
1.0 6 2.0
Distribution
transformer3
1.0 3 1.0
Secondary line
3.5
1.0
Total
11.0 volts 3.3 volts 11.0volts 4.0 volts
-
7/28/2019 2012 Project
27/66
4.7.5 INDUSTRIAL FEEDERS:
Industrial feeders are relatively short feeders and serve any where from one to several
consumers. They are similar to rural feeders, in that there are generally no secondaries, as each
consumer has his own transformer. Many industrial consumers purchase energy directly at the
primary voltage level and own the step-down transformer.
There are no recommended allocations of voltage drop for industrial feeder
components. Each industrial consumer on a feeder should have the supply voltage to the
transformer or transformers which serve the plant fall within the zone shown in columns 2 and 3
in the below table .The voltage spread for the primary supply should be four percent and should
fall within the recommended voltage zone.
NOMINAL
SYSTEM
VOLTAGE
ZONE OF VOLTAGES OF
PRIMARY ON
TRANSFORMERS
PRIMARY VOLTAGE
SPREAD
COLUMN 1
VOLTS
COLUMN 2
MINIMUM
VOLTS
COLUMN 3
MAXIMUM
VOLTS
COLUMN 4
% OF
COLUMN 1
COLUMN 5
VOLTS
2400
4160
4800
6900
11500
13300
2130
3680
4260
6100
10200
12200
2520
4360
5040
7250
12100
14500
4%
4%
4%
4%
4%
4%
100
170
190
280
460
550
-
7/28/2019 2012 Project
28/66
TABLE: 4.7.5 Industrial Feeders
4.8 VOLTAGE REGULATION BASED ON POWER FACTOR ANDDIVERSITY FACTOR:
As we know that voltage regulation is the difference between the maximum and
minimum voltage at a point in the distribution system, it can be based on the following
Power factor
Diversity factor
4.8.1 POWER FACTOR :Poor power factor of load results in bad or very high voltage regulation. Power factor of some
of the common types of loads are given below:
LOAD
POWER FACTOR
Incandescent lamp
Arc lamps used in for advertisements
Florescent lamps
Fans
Electric drills
Resistance heaters
Induction heaters
Arc furnaces
Arc welders
Resistance welders
Induction motors
1.0
0.3 to 0.7
0.4 to 0.5
0.6 to 0.8
0.5 to 0.8
0.9
1.0
0.85
0.85
0.3 to 0.4
0.65
0.4 to 0.8
-
7/28/2019 2012 Project
29/66
With the increasing trend to use more motorized gadgets by the domestic consumers, the power
factor of the system will further decrease. It is not practicable to impose power restrictions on the
small individual consumers.
4.8.2 DIVERSITY FACTOR:
There is general tendency to assume high diversity factor at the designed stage of feeders in
order to reduce the cost f the scheme and thus make the same remunerative as per the
departmental standards. Reasonable diversity factors for 11 kv and LT feeders are 3 and 1.5
respectively. While these serve as general guide the diversity factors can be different provided
they can substantiated with actual diversity factors obtainable in a particular area of feeder. The
departmental practice at present is to design the 11 kv feeders for 10% regulation with DF of 2.5
or 3 and LT FEEDERS FOR 5% regulation may be adopted for LT feeders when the distribution
transformer LT voltage in 433 volts as this would still satisfy the IE rules.
4.9 METHODS OF IMPROVING VOLTAGE REGULATION:
There are several methods of improving voltage regulation throughout the distribution system.
The various methods of improving voltage regulation through a distribution system are listed
below. Each method has its own characteristics concerning amount of voltage improvement, cost-
per-volt improvement, and flexibility.
1. Use of generator voltage regulators.
2. Application of voltage regulation equipment in the distribution substations.
3. Application of capacitors in the distribution substation.
4. Balancing of the loads on the primary feeder.
5. Increasing of feeder conductor size.
6. Changing of feeder sections from single-phase to multi-phase.
7. Transferring of loads to new feeders.
8. Installing of new substations and primary feeders.
9. Increasing of primary voltage level.
In order to evaluate the performance of a power distribution network and to examine
the effectiveness of proposed alterations to a system in the planning stage, it is essential that a
-
7/28/2019 2012 Project
30/66
load flow analysis of the network is carried out. The load flow studies are normally carried out to
determine:
The flow of active and reactive power in network branches.
No circuits are overloaded, and the bus bar voltages are within acceptable limits.
Effect of additions or alterations on a system such as voltage regulators, shunt & series
capacitors.
Effect of loss of circuits under emergency conditions.
Optimum system loading conditions.
Optimum system losses.
The load flow in distribution networks is carried out for simple radial networks in
this project, which is largely self evident.
-
7/28/2019 2012 Project
31/66
CHAPTER-5
SOFTWARE DESCRIPTION
The code DISBUT developed by A.P.S.E. Board aims to meet the requirements of the
distribution system planning and design. It is a complete integrated code for Computer Aided
Distribution System analysis optimization.
5.1 OPEN SYSTEMS:
DISBUT is based on open systems concept using UNIX operating system conforming
to IEEE POSIX standards, X-windows and X lib. The software is capable of working in
networking environment on DEC, SUN, HP, SG, IBM workstations and one can choose the
workstation platform of their choice.
5.2 CUSTOMISED GUI:
DISBUT is totally user friendly and interactive with Customized Graphical User
Interface (GUI) with features like pop up menus to select options, dialogue boxes to enter data
interactively and with scroll bar frames to display results.
5.3 FULL GRAPHICS:
Implements full graphics interface, providing zooming & panning and de cluttering functions.
Zoom & pan allows user to view a particular area in detail. De cluttering allows user to define the
level of details to be displayed.
5.4 DIGITISATION
5.4.1NETWORK:
-
7/28/2019 2012 Project
32/66
DISBUT provides a powerful tool to digitize the electrical distribution network with
all its entities like substations, transformers, capacitors, regulators, branches, and links including
graphic points and their connectivity and also creates spatial and network connectivity data bases.
Facility to edit network like add, modify and delete any entity is provided. Facility to input
transformer capacity at each bus while digitizing the network and calculate length of line
segments based on scale map are provided.
5.4.2 GEOGRAPHICAL INFORMATION:
The geographical features of area like administrative boundaries, roads, rivers, tanks
etc.., can be digitized creating a true life image of field conditions.
5.4.3 SINGLE LINE DIAGRAM:
Creates a single line diagram of each feeder to display network parameters or study
5.5 SYSTEM ANALYSIS:
5.5.1 LOAD FLOW ANALYSIS:
Load flow analysis is made to identify pockets of low voltage and high power
losses, using a special iterative radial load flow algorithm, which guarantee convergence in 2 or 3
iterations, even for the ill conditioned feeder with 20% or 30% voltage drops, with accurateresults. Facility to conduct load flow analysis of multi voltage networks and 3phase load flow
analysis for unbalanced and unsymmetrical networks is also provided.
5.5.2 SHORT CIRCUIT STUDY:
Computes the fault current and fault MVA at each bus for single phase to ground and
three phase faults with fault impedances.
5.5.3PROTECTIVE COORDINATION: Provides protective coordination of relay and fuses in the network.
5.5.4 LOAD MODEL:
Evaluates annual load factor, loss factor and load duration curve of a feeder or substation.
5.6 SYSTEM PLANNING
-
7/28/2019 2012 Project
33/66
5.6.1TRENDS OF GROWTH:
Evaluates the trend parameters of load development for different tariff categories
from historical load data and displays trend curves.
5.6.2 GLOBAL LOAD FORECAST:
Evaluates the energy and demand of the study area globally on Long term basis
using, time series different trend curves, regression techniques linking energy and demand to
various demographic and economic factors and end use method.
5.6.3SPATIAL LOAD FORECAST:
Distribution planning requires quantum, location and timing of load growth, for each
small area. The module determines the demand of each small area using time series of different
trend curves and Land use based simulation techniques, considering development plans of the
state and local authorities.
5.6.4LOCATION & SIZING OF SUBSTATION:The module determines the number, location and size of Distribution substations for
least cost system expansion plan over long term period by minimizing fixed charges of
substations and cost of network losses.
User has to give the potential substation sites and the feasible capacity options at
each location. The program generates optimal and sub-optimal solutions determining the number,
location and capacity of substations and the total cost of plan, in three steps. First step creates
node loss table indicating the incremental losses in the network, when each node is fed from a
given substation using principle of shortest path of algorithm and modeling losses as quadratic
function. Second step creates minimal power loss tree, considering the constraints of substation
size, voltage drop and load transfer using Zero one voltage drop and load transfer using Zero One
programming. Third step generates optimal and sub-optimal feasible solutions using Branch and
Bound techniques.
-
7/28/2019 2012 Project
34/66
Another algorithm based on growth rate of KVAOHM of feeder is provided to
choose optimal substation locations from potential sites. KVAOHM of a feeder is defined as the
sum of products of power flows and resistance of line segments constituting the feeder. This
algorithm gives good results in the absence of Spatial load forecast as it considers load growth
and its location and is useful to utilities in developing countries where spatial load forecast may
not be available.
5.6.5 PERSPECTIVE PLANS:
Develops Perspective Plans for Distribution system expansion for a given period,
giving Physical and Financial Estimates.
The above package is used in APTRANSCO, for conducting load flow studies for
future plans, optimal utilization of existing network and minimize losses due to over loading etc.
As a case study load flow of 33kv feeders from 132/33kv mustyal,
Raghunathpally, Janagon, Ghanapur, substations was presented in this thesis
-
7/28/2019 2012 Project
35/66
CHAPTER 6
CASE STUDY
The load flow was carried out on the following 7nos 33 kV feeders in Warangal districtwith actual data. Individual single line diagrams are given below with actual distances and
connected load are self explanatory:
6.1 FEEDER DIAGRAMS:
(i) FEEDER 1:MUSTYAL THARIGOPPULA ANKSHAPUR2095KVA
REBARTHY3325KVA
MUSTYAL 3.7 KM 3.16 KM
6.25 KM 13.24 KM
6.98KM THARIGOPPULA5050KVA
VELDANDA
3067KVA
-
7/28/2019 2012 Project
36/66
(ii)FEEDER 2: RAGUNATHAPALLY-QUILASHPUR
RAGHUNATHPALLY NARMETTA5.33KM 5.92KM 5.53KM 0.83KM
4477KVA
QUILASHAPUR 0.67KM 4KM
3991KVA
MEKALAGUTA
1400KVA
ADDABATA
1714KVA
(iii)FEEDER 3: JANGAON-GANDIRAMARAM
JANGAON BOMMAKUR15.27 KM 7500KVA
8.53 KM
-
7/28/2019 2012 Project
37/66
GANDIRAMARAM
7500KVA
(iv) FEEDER 4: JANGAON-ADAVIKESHAPUR
JANGAON ADAVIKESHAPUR
14.55 KM 5000KVA
2.
72 KM
HANU MANTHAPUR
5000KVA
(v) FEEDER 5: GHANPUR- TADIKONDA
GHANAPUR THATIKONDA
8.02KM 5000KV
4.66KM
-
7/28/2019 2012 Project
38/66
5000KVA
FATEHPURAM
(vi) FEEDER 6: GHANAPUR MALKAPUR
RAHAVARAM
5000KVA
GHANAPUR
5.3KM 1.45KM 1.11KM 9.63KM 3.95KM
2.56 KM PICHARA
MALKAPUR 5000KVA10000KVA
PEDDAPENDIAL
8150KVA
-
7/28/2019 2012 Project
39/66
(vii) FEEDER 7: MUSTYAL-DHOOLMITTA
MUSTYAL MUSTYAL DHOOLMITTA
10000KVA0.9 KM 7.09 KM 5.84 KM
2.66 KM
AKUNUR5000KVA
BEKKAL
5000KVA
3.64 KM
KUTTIGAL
3100KVA
The study was carried out assuming the load is balanced and pf was constant i.e., 0.8
Two types of studies are conducted one with optimization techniques like add feeder,
section or shunt capacitor etc presented as case I. Second study by proposing a new 132/33 kV
SS in the scheme area that is at Narmetta with 5nos new 33 kV feeders as case-II. In both the
-
7/28/2019 2012 Project
40/66
cases projection of load growth for 5 years at the rate of 9.7% is also calculated as per the
planning criteria of APTRANSCO
According to load flow studies the voltage regulations are as follows:
Sl.
No.
Name of the 33 kV feeder No. of
33/11
kV SS
Name of the
33/11 kV SS
% Voltage Regulations
BaseYear
Horizonyear
1. Mustyal - Tharigoppula 4 Rebathy,Veldanada,
Tharigoppula,Ankshapur(P)
8.46 13.44
2. Ragunathpalli- Quilashapur 4 Quilashapur,Mekalagattu
Narmetta,
Addabata
5.97 9.48
3. Jangoan - Gandiramaram 2 Gandiramaram (LI),Bommakur (LI)
14.20 14.20
4. Jangoan - Adavikeshapur 2 Hanmathapur,Adavikeshapur
3.78 6.01
5. Ghanpur -Tadikonda 2 Tadikonda,Fatehpuram
1.87 2.97
6. Ghanpur - Malkapur 4 Peddapendial,Malkapur,
Rajavarm,Peechara
10.01 15.90
7. Mustyal - Dhoolmitta 5 Mustyal,Aknuru,Dhoolmitta,
Bekkal,
Kutigal
8.70 13.82
TABLE 6.1: Voltage regulations at base year
As per the above results, the voltage regulation on feeders 3&6 are beyond permissible limits in
base year. Voltage regulations on feeders at Sl No. 1,2,&7 is beyond permissible limits at the
horizon year . Jangoan Gandiramaram (Sl No. 3) is independent feeder feeding a constant
load, hence projection of load for horizon year is not allowed.
-
7/28/2019 2012 Project
41/66
6.2 CASE-I
1. 2 MVAR capacitor banks proposed at Tharigoppula to improve voltage regulation onfeeder at Sl no: (1).
2. 2 MVAR capacitor banks is proposed at 33/11 kV SS Addabata SS to improve
voltage regulation on feeder at Sl no (2).
3. A new 33 kV feeder is proposed from Raghunathpalli SS to Gandiramaram toimprove voltage regulation on feeder at Sl n: (3)
4. A new 33 kV feeder is proposed from Ghanapur SS to improve voltage regulation on
feeder at Sl no (6) and also 2MVAR capacitor banks at 33/11 Pechara SS.5. A new 33 kV feeder is proposed from Mustyal SS to kutigal to improve voltage
regulation on feederat Sl no: (7).
The voltage regulations are given below table.
Sl.
No.
Name of the 33 kV feeder No. of
33/11kV SS
Name of the
33/11 kV SS
% Voltage Regulations
Base
Year
Horizon
year
1. Mustyal - Tharigoppula 3 Rebathy,
Veldanada,
Tharigoppula,
4.91 7.81
2. Ragunathpalli- Quilashapur 4 Quilashapur,
MekalagattuNarmetta,
Addabata
4.79 7.56
3. Jangoan - Gandiramaram 1 Bommakur (LI)
5.08 5.08
4. Jangoan - Adavikeshapur 2 Hanmathapur,Adavikeshapur
3.78 6.01
5. Ghanpur -Tadikonda 2 Tadikonda,Fatehpuram
1.87 2.97
6. Ghanpur - Malkapur 2 Peddapendial,Rajavarm,
2.05 3.25
7. Mustyal - Dhoolmitta 3 Mustyal,Aknuru,
Dhoolmitta,
4.81 7.65
-
7/28/2019 2012 Project
42/66
8 MUSTYAL-KUTIGAL 3 KUTIGAL,Bekkal,Ankushapur
4.63 7.35
9 Ragunathpalli-Gandiramaram
1 Gandiramaram 5.63 5.63
10 Ghanpur - Peechara 2 Peechara, Malkapur 4.99 7.92
6.3 Case II:Studies were also conducted by proposing new 132/33 kV SS in the scheme area is at Narmettawith 5 nos new feeders as the listed below:
Sl.No Name of 33 kV feeder
Length of
new
33kV
line(Km)
Name of 33/11 kV
SS to be transferred
No. of
SS s to betransferred
to new SS
1 Narmetta Narmetta 1Narmetta,
Addabata
2
2.Narmetta - Gandiramaram
5Gandiramaram 1
3.Narmetta Tharigoppula
6Tharigoppula,
Ankushapur
2
4. Narmetta Kutigal 10 Kutigal,Bekkal
2
5.Narmetta Malkapur
15Malkapur 1
The voltage regulations new 132/33 kV SS are given below table.
Sl.No.
Name of the 33 kV feeder No. of33/11
kV SS
Name of the33/11 kV SS
% Voltage Regulations
BaseYear
Horizonyear
1. Mustyal - Tharigoppula 2 Rebathy,Veldanada,
2.65 4.21
2. Ragunathpalli- Quilashapur 2 Quilashapur,
Mekalagattu
1.47 2.34
-
7/28/2019 2012 Project
43/66
3. Jangoan - Gandiramaram 1
Bommakur (LI)
5.08 5.08
4. Jangoan - Adavikeshapur 2 Hanmathapur,
Adavikeshapur
3.78 6.01
5. Ghanpur -Tadikonda 2 Tadikonda,Fatehpuram 1.87 2.97
6. Ghanpur - Malkapur 3 Peddapendial,
Rajavarm,Peechara
3.79 6.03
7. Mustyal - Dhoolmitta 3 Mustyal,
Aknuru,Dhoolmitta,
4.81 7.65
8 Narmetta-narmetta 2 Narmetta,
Addabata
0.60 0.95
9 Narmetta- Gandiramaram 1 Gandiramaram 1.39 1.39
10 Narmetta- Tharigoppula 2 Tharigoppula,Ankushapur
2.01 3.19
11 Narmetta-kutigal 2Kutigal,
Bekkal
1.99 3.16
12 Narmetta-- Malkapur 1 Malkapur 5.06 8.03
TABLE 6.3.2: Details of the voltage regulations after erection of substation.
Any of the two cases may be implemented duly considering other criteria like financial
viability and field conditions.
6.4. CALCULATION OF VOLTAGE REGULATION BY
CONVENTIONAL METHOD:
-
7/28/2019 2012 Project
44/66
Voltage regulation on sub transmission or on distribution feederswhich are radial feeders are also calculated through conventional method byassuming regulation constants per 100kva per km.
The regulation constants for commonly used conductors are
given bellow:
DETAILS OF THE
CONDUCTOR
% REGULATION PER 100KVA PER KM
415 KV 11KV 33KV
7/2.00 (SQUIRREL) 20sq.mm
7/2.00 (WEASEL) 30sq.mm
7/3.15 (RABBIT) 50sq.mm
7/4.26 (DOG)
100sq.mm
83.75
59.4
40.09
-
0.1211
0.08062
0.05853
0.03294
-
-
0.0064
0.00394
TABLE 6.4: Details of the conductors.
FORMULA:
Total KVA KM x regulation constant per 100 KVAper KMPercentage regulation =-------------------------------------------------------------------------------
100x Diversity Factor
Here diversity factor is taken as constant 1.
CONVENTIONAL CALCULATION
FEEDER 1: MUSTYAL - THARIGOPPULA
-
7/28/2019 2012 Project
45/66
REBARTHY ANKSHAPUR
3.7 KM3.16KM
MUSTYAL
6.25KM 13.24KM
6.98KMTHARIGOPPULA
VELDANDA
= 98424.5
CALCULATION OF % REGULATION ON EACH FEEDER
CALCULATIONS:
KVA at ANKSHAPUR = load on the feeder x the distance from the feeder to the substation.
= 2095 x (13.24+6.25+3.16)
= 2095 x 22.65
= 47451.75
KVA at THARIGOPPULA= 5050 x (13.24+6.25)
= 5050 x 19.49
= 98424.5
KVA at VELDANDA = 3067 x (6.98+6.25)= 3067 x 13.23
.= 40576.41
KVA at REBARTHY = 3325 x (3.7+6.25)
= 3325 x 9.25
-
7/28/2019 2012 Project
46/66
= 30 756.25
Total KVA KM = 47451.75+98424.5+40576.41+30 756.25= 217208.91
% regulation = total KVA KM x constant factor /100
= 217208.91 x 0.00394/100
=855.80311/100= 8.55%
FEEDER 2: RAGUNATHAPALLY-QUILASHPUR
RAGHUNATHPALLY NARMETTA
-
7/28/2019 2012 Project
47/66
5.33KM 5.92KM 5.53KM 0.83KM
QUILASHAPUR 0.67KM 4KM
MEKALAGUTA
ADDABATA
CALCULATION:
KVA at NARMETTA= 4477 x (0.83+05.53+5.92+5.33)
= 4477 x 17.61
= 78839.97
KVA at ADDABATA= 1714 x (4+5.53+5.92+5.33)
= 1714 x 20.78
= 35616.92
KVA at MEKALGUTTA = 1400 x (0.67+5.92+5.33)
= 1400 x 11.92
= 16688
KVA at QUILASHAPUR = 3991 x 5.33
-
7/28/2019 2012 Project
48/66
-
7/28/2019 2012 Project
49/66
-
7/28/2019 2012 Project
50/66
JANGAON ADAVIKESHAPUR 14.55 KM
2.72 KM
2286KVA
HANUMANTHAPUR
CALCULATION:
KVA at HANUMANTHPUR = 2286 x (2.72+14.55)
= 2286 x 17.27
= 39479.22
50
KVA at ADAVIKESHAVPUR = 3239 x 14.55
= 47127.45
Total KVA KM = 39479.22+47127.45
= 86606.67
-
7/28/2019 2012 Project
51/66
-
7/28/2019 2012 Project
52/66
GHANAPUR THATIKONDA
8.02KM 3070KVA
4.66KM
1500KVA
FATEHPURAM
CALCULATION:
KVA at FATEHPURAM = 1500 x (4.66+8.02)
= 1500 x 12.88
= 19320
KVA at THATIKONDA = 3070 x 8.02
= 24621.4
Total KVA km = 19320+24621.4
= 43941.4
% Regulation at FATEHPURAM = 43941.4 x 0.00394/100
= 1.73%
FEEDER 6: GHANAPUR MALKAPUR
-
7/28/2019 2012 Project
53/66
RAHAVARAM
GHANAPUR
5.3KM 1.45KM 1.11KM 9.63KM 3.95KM
MALKAPUR PICHARA
2.56 KM
4001KVA
PEDDAPENDIAL
CALCULATION:
KVA at PICHARA = 2744 x (3.95+9.63+1.45+5.3)
= 2744 x 20.33
= 55785.52
KVA at MALKAPUR = 9297 x (9.63+1.45+5.3)
= 9297 x 16.38
= 152284.86
KVA at RAJAVARAM = 4573 x (1.45+5.3+1.11)
= 4573 x 7.86
-
7/28/2019 2012 Project
54/66
= 35943.78
KVA at PEDDAPENDIYALA = 4001 x (2.56+5.3)
= 4001 x 3.09
= 12363.09
Total KVA km = 55785.52+152284.86+35943.78+12363.09
= 256377.25
% Regulation at PICHARA = 256377.25 x 0.00394/100
= 10.10%
FEEDER 7: MUSTYAL-DHOOLMITTA
-
7/28/2019 2012 Project
55/66
MUSTYAL 5000 KVA
MUSTYAL DHOOLMITTA
0.9 KM 7.09 KM 5.84 KM
8955 KVA
2.66 KM
3.43 KM
AKUNUR
BEKKAL
5000 KVA
3.64 KM
KUTIGAL
3100 KVA
CALCULATION:
KVA at KUTIGAL = 3100 x (3.64+3.43+5.84+7.09+0.9)
= 3100 x 20.09
= 62279
KVA at BEKKAL =2854 x (3.43+5.84+7.09+0.9)
-
7/28/2019 2012 Project
56/66
= 2854 x 17.26
= 49260.04
KVA at DHOOLMITTA = 8955 x (5.84+7.09+0.9)
= 8955 x 13.83
= 123847.65
KVA at AKUNUR = 2705 x (2.66+7.09+0.9)
= 2705 x 10.65
= 28808.25
KVA at MUSTYAL = 8478 x 0.9
= 7630.2
Total KVA km = 62279+49260.04+123847.65+28808.25+7630.2
= 271825.14
% Regulation at MUSTYAL = 271825.14 x 0.00394/100
= 10.70%
6.5 OBSERVATIONS:
1. MUSTYAL-THARIGOPPULA
We can observe here that when we calculate voltage regulation through hand, the voltage
regulation at this feeder is 8.55 and system analysis gives the result as 8.46.
2. RAGUNATHPALLY- GANDIRAMARAM
-
7/28/2019 2012 Project
57/66
We can observe here that when we calculate voltage regulation through hand, the voltage
regulation at this feeder is 6.005 and system analysis gives the result as 5.97.
3.JANGAON- GANDIRAMARAM
We can observe here that when we calculate voltage regulation through hand, the voltage
regulation at this feeder is 11.43 and system analysis gives the result as 14.20.
4.JANGAON- ADAVIKESHAPUR
We can observe here that when we calculate voltage regulation through hand, the voltage
regulation at this feeder is 3.41 and system analysis gives the result as 3.78.
5. GHANPUR- TADIKONDA
We can observe here that when we calculate voltage regulation through hand, the voltage
regulation at this feeder is 1.73 and system analysis gives the result as 1.87.
6. GHANPUR- MALKAPUR
We can observe here that when we calculate voltage regulation through hand, the
voltage regulation at this feeder is 10.10 and system analysis gives the result as 10.01.
7. MUSTYAL-DHOOLMITTA
We can observe here that when we calculate voltage regulation through hand, the voltage
regulation at this feeder is 10.70 and system analysis gives the result as 8.70.
From the above all results and analysis we can observe that the voltage regulations
obtained through conventional method are more than the results of voltage regulation obtained
from system analysis.
Therefore we can concludes that system analysis for load flow studies is the most
appropriate method.
-
7/28/2019 2012 Project
58/66
CHAPTER 7
RESULTS
7.1 BASE STUDY
TABLE: FEEDER DATA
Feeder
no.
Name of the
feeder
no. of
substation
Transformer
s capacitykva
Load
factor
Length
km
Starting
voltagekv
12
3
4
56
7
Mstl-tgplRgpl-qspr
Jgn-grvm
Jgn-akpr
Gpr-tkdGpr-mkpr
Mstl-dmt
44
2
2
24
5
2500020000
15000
10000
1000028150
35000
0.500.50
0.50
0.50
0.500.50
0.50
33.3322.28
23.80
17.27
12.6824.20
23.56
33.0033.00
33.00
33.00
33.0033.00
33.00
total 23 143150 157.12
TABLE: FEEDER ANALYSIS
Feederno.
Name ofthe feeder
Activeload kw
Reactiveload
kvar
Energyloss l.u
Powerlosskw
% reg %energy
loss
1
2
34
5
67
Mstl-tgpl
Rgpl-qspr
Jgn-grvmJgn-akpr
Gpr-tkd
Gpr-mkprMstl-dmt
11464.
8759.
13451.4559.
3708.
14712.15629.
8850.
6703.
10664.3475.
2802.
11419.12008.
16.69
8.84
38.273.66
1.37
25.5218.95
635.
336.
1456.139.
52.
971.721.
8.46
5.97
14.203.78
1.87
10.018.70
3.32
2.30
6.501.84
0.84
3.962.77
total 72283. 55919. 113.29 4311. 14.20
maximum
3.58
-
7/28/2019 2012 Project
59/66
-
7/28/2019 2012 Project
60/66
7.1 CASE-1: AFTER ADDING FEEDERS AND CAPACITOR BANKS.
BASE YEAR:TABLE
S.No Name of
the feeder
no. of
substation
Transformer
s capacitykva
Load
factor
Length
km
Starting
voltage kv
1
2
34
5
6
78
9
10
Mstl-tgpl
Rgpl-qspr
Jgn-grvmJgn-akpr
Gpr-tkd
Gpr-mkpr
Mstl-dmtMstl-ktl
Rgpl-grvm
Gpr-pcr
3
4
12
2
2
33
1
2
20000
20000
750010000
10000
13150
2500015000
7500
15000
0.50
0.50
0.500.50
0.50
0.50
0.500.50
0.50
0.50
31.82
22.28
20.9217.27
12.68
12.63
18.1223.20
16.83
16.54
33.00
33.00
33.0033.00
33.00
33.00
33.0033.00
33.00
33.00total 23 143150 192.29
FEEDER ANALYSIS:
Feederno.
Name of thefeeder
Activeload in
kw
Reactiveload in
kvar
Powerloss kw
Energyloss l.u
% reg %energy
loss
1
234
5
6
78
9
10
Mstl-tgpl
Rgpl-qsprJgn-grvmJgn-akpr
Gpr-tkd
Gpr-mkpr
Mstl-dmtMstl-ktl
Rgpl-grvm
Gpr-pcr
9470.
8684.6269.4559.
3708.
5816.
11793.5277.
6300.
8355.
5419.
4797.4809.3475.
2802.
4401.
8958.4037.
4844.
4590.
316.
261.269.139.
52.
100.
286.199.
300.
328.
8.31
6.857.083.66
1.37
2.62
7.515.22
7.89
8.61
4.91
4.765.083.78
1.87
2.05
4.814.63
5.63
4.99
2.00
1.802.581.84
0.84
1.03
1.452.26
2.86
2.35
total 70231. 48132. 2250. 59.12 5.63 1.92
-
7/28/2019 2012 Project
61/66
HORIZON YEAR:
Feeder
no.
Name of the
feeder
Source
load kw
Power loss
kw
Energy
loss l.u
% reg % energy
loss
123
4
5
67
8
910
Mstl-tgplRgpl-qsprJgn-grvm
Jgn-akpr
Gpr-tkd
Gpr-mkprMstl-dmt
Mstl-ktl
Rgpl-grvmGpr-pcr
15044.13796.6269.
7243.
5891.
9239.18735.
8383.
6300.13273.
798.658.269.
352.
131.
251.721.
501.
300.827.
20.9817.307.08
9.25
3.45
6.6118.94
13.18
7.8921.73
7.817.565.08
6.01
2.97
3.257.65
7.35
5.637.92
3.182.862.58
2.92
1.34
1.632.31
3.59
2.863.74
Total 104174. 4810. 126.41
-
7/28/2019 2012 Project
62/66
-
7/28/2019 2012 Project
63/66
TABLE: FEEDER ANALYSIS AT HORIZON YEARHORIZON YEAR:2015
Feederno. Name of thefeeder Source loadkw Powerloss kw Energyloss l.u % reg % energyloss
1
2
3
45
6
78
9
1011
12
Mstl-tgpl
Rgpl-qspr
Jgn-grvm
Jgn-akprGpr-tkd
Gpr-mkpr
Mstl-dmtNrmt-nrmt
Nrmt-grm
Nrmt-trgNrmt-ktg
Nrmt-mlk
8295.
6292.
6269.
7243.5891.
12291.
18735.7175.
6071.
9221.5489.
10287.
271.
101.
269.
352.131.
483.
721.35.
71.
223.134.
699.
7.13
2.66
7.08
9.253.45
12.70
18.940.92
1.86
5.873.52
18.37
4.21
2.34
5.08
6.012.97
6.03
7.650.95
1.39
3.193.16
8.03
1.96
0.97
2.53
2.921.34
2.36
2.310.29
0.70
1.451.46
4.08
total 103260 3491. 91.75
TABLE: SUBSTATION DEMAND AND CAPACITY.
S.No.
Name of the
substation
Before improvements After improvements proposed
capacity
mva
Transformer
capacity
Demand
kva
Demand
existingkva
demand at
horizonyear kva
12
3
45
mustyalr pally
janagoan
ghanpurNARMETTA
6347.5
32
47.5
59300.46850.
27180.
45700.
46470.40781.
17916.
36793.33023.
59045.43701.
21291.
45248.47986.
Total demand 174983. 217271.
.
-
7/28/2019 2012 Project
64/66
CHAPTER 8
CONCLUSION
As discussed in earlier chapters load flow is most efficient and useful tool in Power
System planning and operation. Load flow on actual sub-transmission network in Warangal
district was studies necessary improvements were also suggested to improve the voltage
wherever they are beyond permissible limits in this project work.
The load flow can also be carried out for arriving network losses and remedial measures
for reducing losses may also be studied in future. Reduction of network losses is very important
in the prospect of any utility.
63
-
7/28/2019 2012 Project
65/66
-
7/28/2019 2012 Project
66/66