2012 project

Upload: yashasvi-prashant-bhattiprolu

Post on 03-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 2012 Project

    1/66

    CONTENTS

    CHAPTER TITLE PAGE NOS

    ABSTRACT

    LIST OF FIGURES

    LIST OF TABLES

    I INTRODUCTION 1

    1.1 LOAD FLOW 1

    1.2 IMPORTANCE OF LOAD FLOW 3

    1.3 DISBUT SOFTWARE 4

    1.4 CASE STUDY 4

    II DETAILED DISCRIPTION OF GENERATION

    TRANSMISSION AND DISTRIBUTION

    2.1 INTRODUCTION 5

    2.2 CLASSIFICATION OF POWER SYSTEMS 6

    III AP TRANSCO PLANNING CRITERIA

    3.1 INTRODUCTION 93.2 TRANSMISSION PLANNING 10

    REQUIREMENTS

    3.3 SUBSTATION DATA 10

    3.4 DISTRIBUTION LOAD FORECAST 11

    3.4.1 SYSTEM LOAD FORECAST 11

    3.4.2 GLOBAL LOAD FORECAST 11

    3.5 PERSPECTIVE PLANNING 12

    IV LOAD FLOW STUDIES ON SUBSTATION

    4.1 INTRODUCTION 13

    4.2 VOLTAGE SPREAD 13

    4.3 EFECTS OF VOLTAGE SPREAD 15

  • 7/28/2019 2012 Project

    2/66

    ON UTILIZATION EQUIPMENTS

    4.4 INDUCTION MOTORS 16

    4.5 VOLTAGE ZONES 17

    4.5.1 FAVOURABLE ZONE

    4.5.2 TOLERABLE ZONE

    4.5.3 EXTREME ZONE

    4.6 UTILIZATION EQUIPMENT VOLTAGE RATING 18

    4.7 VOLTAGE DROP IN SYSTEM COMPONENTS 19

    4.7.1 RESIDENTIAL FEEDERS

    4.7.2 DISTRIBUTION FEEDERS

    4.7.3 PRIMARY FEEDERS

    4.7.4 RURAL FEEDERS

    4.7.5 INDUSTRIAL FEEDERS

    4.8 VOLTAGE REGULATION BASED ON P.F AND 25

    D.F

    4.8.1 POWER FACTOR

    4.8.2 DIVERSITY FACTOR

    4.9 METHODS OF IMPROVING VOLTAGE 26

    REGULATION

    V SOFTWARE DESCRIPTION 28

    5.1 OPEN SYSTEMS 28

    5.2 CUSTOMIZED GUI 28

    5.3 FULL GRAPHICS 28

    5.4 DIGITISATION 28

    5.4.1 NETWORK

    5.4.2 GEOGRAPHICAL INFORMATION

    5.5 SYSTEM ANALYSIS 29

    5.5.1 LOAD FLOW ANALYSIS

    5.5.2 SHORT CIRCUIT STUDY

    5.5.3 PROTECTIVE CO ORDINATION

  • 7/28/2019 2012 Project

    3/66

    5.5.4 LOAD MODEL

    5.6 SYSTEM PLANNING 29

    5.6.1 TRENDS OF GROWTH

    5.6.2 GLOBAL LOAD FORECAST

    5.6.3 SPATIAL LOAD FORECAST

    5.6.4 LOCATION AND SIZING OF SUBSTATION

    5.6.5 PERSPECTIVE PLANS

    VI CASE STUDY 32

    MAPS

    6.1 SINGLE LINE DIAGRAMS OF FEEDERS 32

    6.2 CASE I 37

    6.3 CASE II 38

    6.4 HAND CALCULATIONS 42

    6.5 OBSERVATIONS. 56

    VII RESULTS 57

    VIII CONCLUSION 64

  • 7/28/2019 2012 Project

    4/66

    CHAPTER-1

    INTRODUCTION

    1.1 LOAD FLOW.

    Power Flow studies are also known as load flow studies. The principal

    information obtained from these studies is the voltage at each bus and real and reactive power

    flowing in each line. There by calculates voltage regulation of each feeder, power flow in all

    branches, feeder circuits, losses in each branch and total system power losses. A typical power

    system single line diagram comprising generation, transmission and distribution is given below.

    The main parts of power system are as follows:

    1. Generating stations.

    2. Transmission systems.

    3. Distribution networks

    The description about the following parts of the power system would be given in detail in

    the next chapter.

  • 7/28/2019 2012 Project

    5/66

    GENERATOR 11KV

    TRANSFORMER 11KV/400 KV

    400KV/220KV

    EHV

    TRANSMISSION

    HT LOAD

    33KV/11KV

    HIGH VOLTAGE

    DISTRIBUTION 11KV

    11KV/0.4KV

    LOW VOLTAGE DISTRIBUTION

    0.4 KV

  • 7/28/2019 2012 Project

    6/66

    1.2 IMPORTANCE OF LOAD FLOW

    The importance of these studies is planning the future expansion of power

    system as well as in determining the best operation of existing system. Load flow is an importanttool involving numerical Analysis applied to power system . Power flow analysis is very

    important in planning stages of new networks in additional to existing ones.

    It is helpful in determining the best location as well as optimal capacity of proposed generating

    stations and substations

    The conventional method of calculating voltage regulation is simple based onKVA KM loading of conductors.

    Also, the conventional method to evaluate the demand loss (or) peak power

    loss on a distribution feeder is based on the use of loss constants. The conventional technique is

    simple but may not result in correct computation of loss for the following reasons:

    The loss constants are obtained on the assumptions that voltage at all buses along the

    length of feeder is the rated voltage.

    The drop in voltage of the feeder from source to tail end and the consequent increase in

    loss are not considered.

    The demand loss in each feeder segment increases the power flow in all preceding

    feeder segments up to the source. The effect of such loss is not considered in the demand loss

    in each feeder segment increase the power flow in all preceding feeder segments up to the source.

    The effect of such loss is not considered in the conventional method.

    At present power utilization increased leaps and bounds thus posing requirement of bulk

    generation and transmission of power. As in example generation installed capacity of AP is

    15000 MW in 2011 a against 4065 MW in 1991 similarly the bulk power generated at pit heads

    or projects need to be transported to the load centers necessitating EHV network that is

  • 7/28/2019 2012 Project

    7/66

    operated at higher voltages i.e from 132 KV to 220 KV and much more to 400 KV and 765 KV

    which is under progress. Ultimately all this power need to be deliver to the door steps of various

    consumers through sub transmission and distribution networks. All these stages of power system

    is capital oriented thus necessitating lot of studies for effective capital investment and

    remunerative technically as well as economically.

    Latest technology/ powerful software tools are finding place in calculating such

    cumbersome calculations in power systems.

    1.3 DISBUT SOFTWARE.

    DISBUT software used in APTRANSCO is very accurate and well defined to

    meet the above requirements.

    The power flow techniques such as Newton- Raphson method, fast decoupled load

    flow method etc, are used to solve well behaved power systems effectively. But, when these

    techniques are applied to ill-conditioned (or) poorly initialized power systems have led to

    many short comings . Whereas the DISBUT package is more suitable for calculating voltages,

    currents, active and reactive power flowing in each line, there by voltage regulation and power

    loss of radial feeders at different voltage levels ( i.e.., 33kv , 11kv etc).

    1.4 CASE STUDY.

    As a case study, the voltage regulation and power loss of the following 33kv

    feeders were considered.

    1. Mustyal ----------Tharigoppula

    2. Raghunathpalli-----------Quilashapur

    3. Jangoan-------------Gandiramaram

    4. Jangoan------------ Adavikeshapur

    5. Ghanpur------------Tadikonda

    6. Ghanpur------------Malkapur

    7. Mustyal-------------Dhoolmitta

  • 7/28/2019 2012 Project

    8/66

    The results were analyzed duly applying optimization techniques like adding of a new

    sections for alignment of loads on 33 KV side. Adding of new feeders and new 132/33KV

    substations at optimal location was suggested.

    CHAPTER-2

    DETAILED DESCRIPTION OF GENERATION ,

    TRANSMISSION AND DISTRIBUTION

    2.1 INTRODUCTION:

    Energy provides power to progress. We need energy in various forms like heat, light ,sound

    etc .The development new technology made it possible to convert electrical energy into any form

    of energy. This gives electrical energy an important position in the world. The running of the

    modern industrial structure depends on the low cost and the uninterrupted supply of electricity.

    In short we can say that a country is developed if the per capita consumption of electrical energy

    is much higher.

    Electrical energy is considered to be superior over other energy forms the following facts gives

    the proof for it.

    1. Convenient energy form: Electrical energy could be considered as the most

    convenient form of energy as it could be converted from one form to another easily.

    2. Flexibility: Another important aspect of electricity is the flexibility, it is very easy to

    carry electricity from one place to other by using conductors

    3. Cheapness: Electrical energy is much cheaper compared to other forms of energy.

    The cost of production and availability is much larger compared to other forms of

    energy and hence it is an inevitable component in all sectors of the modern world.

    4. Cleanliness: Electrical energy is not associated with polluting factors such as smoke,

    dust, fumes ,poisonous gases etc thus it offers a healthy atmosphere to each and all

    living organism in the world.

  • 7/28/2019 2012 Project

    9/66

    5. High Transmission Efficiency: The transmission efficiency of electrical energy

    is much higher.

    2.2 CLASSIFICATION OF POWER SYSTEM

    The main parts of the electrical energy power system are:

    Generating stations.

    Transmission systems.

    Distribution network.

    2.2.1 Generating stations: electrical energy generation

    Electrical energy is being generated in large hydro, thermal, and nuclear power stations

    but the stations are located far away from the load centers. Large and long transmission

    networks are wheeling the generated power from the sending end stations to sub stations

    and the load centers. Several electrical equipments are pressed into service for proper

    transmission and distribution of the generated power.

    Economic dispatch is an important aspect to be studied in a power system. As generator

    is the prime source of energy, hence economic operation of generators is very much

    necessary to be analyzed.

    Now a days, the major electrical equipment in power stations that is being used for

    highest practical voltage for generation is 33kv though 11kv/12kv/13kv/15kv are the

    most usual. If a generator is to feed a network at 33kv there is a strong case for

    generation for 33kv as it will avoid the use of step up transformers.

    There are two methods of electrical generations:

    Conventional

    Non-conventional

    The conventional energy sources of electrical generations are

    Thermal stations

    Hydro electric stations

    Nuclear power stations

  • 7/28/2019 2012 Project

    10/66

    Diesel electric stations

    The non-conventional energy sources of electrical generations are

    Wind energy

    Solar energy

    Fuel cells

    Tidal power generation

    Geo-thermal energy

    2.2.2 Transmission systems:

    Electric-power transmission is the bulk transfer ofelectrical energy, from

    generatingpower plantsto electrical substationslocated near demand centers.Transmission lines,

    when interconnected with each other, become transmission networks. Transmission system

    design will require a study of choice with reference to transmission voltage, constants of

    transmission, design interference with neighboring communication circuits behind line insulation

    and corona problems.

    Electricity is transmitted athigh voltages(110 kV or above) to reduce the energy lost in

    long distance transmission. There are two types of transmission lines which are as follows:

    Overhead transmission lines

    Underground transmission lines

    Power is usually transmitted through overhead power lines. Underground power

    transmission has a significantly higher cost and greater operational limitations but is sometimes

    used in urban areas or sensitive locations.

    2.2.3 Distribution network:

    Electricity distribution is the final stage in the deliveryofelectricityto end

    users. A distribution system'snetworkcarries electricity from the transmission systemand

    delivers it to consumers. Typically, the network would include medium-voltage (less than 50 kV)

    power lines, substations and pole-mounted transformers, low-voltage (less than 1 kV)

    distribution wiring and sometimes meters. The modern distribution system begins as the primary

    circuit leaves the sub-station and ends as the secondary service enters the customer's meter

    http://en.wikipedia.org/wiki/Electrical_energyhttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/Overhead_power_linehttp://en.wikipedia.org/wiki/Power_deliveryhttp://en.wikipedia.org/wiki/Electricityhttp://en.wikipedia.org/wiki/Electricityhttp://en.wikipedia.org/wiki/Grid_(electricity)http://en.wikipedia.org/wiki/Grid_(electricity)http://en.wikipedia.org/wiki/Electric_power_transmissionhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electricity_meterhttp://en.wikipedia.org/wiki/Electricity_meterhttp://en.wikipedia.org/wiki/Electrical_energyhttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/High_voltagehttp://en.wikipedia.org/wiki/Overhead_power_linehttp://en.wikipedia.org/wiki/Power_deliveryhttp://en.wikipedia.org/wiki/Electricityhttp://en.wikipedia.org/wiki/Grid_(electricity)http://en.wikipedia.org/wiki/Electric_power_transmissionhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electricity_meter
  • 7/28/2019 2012 Project

    11/66

    socket. Distribution circuits serve many customers. The voltage used is appropriate for the

    shorter distance and varies from 2,300 to about 35,000 volts depending on utility standard

    practice, distance, and load to be served. Distribution circuits are fed from a transformerlocated

    in anelectrical substation, where the voltage is reduced from the high values used for power

    transmission. Conductors for distribution may be carried on overhead

    pole lines, or in densely-populated areas where they are buried underground. Urban and

    suburban distribution is done with three-phase systems to serve both residential , commercial,

    and industrial loads. Distribution in rural areas may be only single-phase if it is not economical

    to install three-phase power for relatively few and small customers.

    Only large consumers are fed directly from distribution voltages; most utility customers are

    connected to a transformer, which reduces the distribution voltage to the relatively low voltage

    used by lighting and interior wiring systems. The transformer may be pole-mounted or set on the

    ground in a protective enclosure. In rural areas a pole-mount transformer may serve only one

    customer, but in more built-up areas multiple customers may be connected. In very dense city

    areas, a secondary network may be formed with many transformers feeding into a common bus

    at the utilization voltage. Each customer has an "electrical service" or "service drop" connection

    and a meter for billing. (Some very small loads, such as yard lights, may be too small to meter

    and so are charged only a monthly rate.)

    http://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Three-phase_electric_powerhttp://en.wikipedia.org/wiki/Transformerhttp://en.wikipedia.org/wiki/Electrical_substationhttp://en.wikipedia.org/wiki/Three-phase_electric_power
  • 7/28/2019 2012 Project

    12/66

    CHAPTER-3

    AP TNANSCO PLANNING CRITERIA

    3.1 INTRODUCTION

    We all know electrical energy cannot be stored, it is getting utilized

    simultaneously while generated. Also load is very dynamic which poses challenge to the

    system operators. To balance generation and demand, the system operator shall be

    facilitated with sufficient data bank of past trends of load and expected load in future over a

    stipulated period. This knowledge of old data and predicted future is system planning. Also

    power system planning is to provide an orderly and economic expansion to meet the utility

    future electric demand and acceptable reliability. Correct planning requires a proper forecast.

    The quality and accuracy of this forecast is crucial to electric utility since it dictates the

    planning of generation, transmission and distribution facilities. If the forecast is understated

    it results in shortage in generation capacity and in adequacy of transmission and distribution

    facilities. Similarly if it is over stated the result is excessive financial investments in facilities

    in advance of actual needs and there by blocking of scarce capital which could have been

    otherwise utilized in a more profitable way.

    Planning of system involves determining

    The correct sizes

    Location

    Interconnection

    Timing future additions to this equipment

  • 7/28/2019 2012 Project

    13/66

    Such planning is a difficult task, compounded by resent trends in tightening the

    design margins. Correct planning of capacity of equipment requires a forecast of future

    geographical distribution of electric demand.

    During last decade a number of practical and efficient automated computerized

    methods have been developed as an aid to system planning and design and determine minimum

    cost plan. These automatic produces produce substantial saving over traditional methods, but

    require high resolution projection future loads. Therefore to gain maximum benefit from these

    produces, development of accurate forecast methods have been subject of increasing attention

    during last few years.

    3.2 TRANSMISSION PLANNING REQUIREMENTS:

    Basic requirements for carrying a transmission planning study are:

    Information on the existing transmission facilities.

    Load forecast

    Generation planning

    Information on the existing transmission facilities:

    Collection of all the available information on the existing system forms the first stage in the

    planning process. Data required is as given below. Data is usually available in the records

    maintained at the substations. Basic parameters required are,

    Transmission line data line voltage, number of conductors per phase, size and type of

    conductor and shield wire.

    Line resistance, resistance and susceptance (positive and zero sequence)

    Thermal capacity

    Size and location of line connected shunt reactors

    Size and location of series capacitive compensation

    3.3 SUBSTATION DATA

    Data required for transmission planning purposes, at the substation level and for each year

    consists of

    Real and reactive demand (MW and MVAR)

  • 7/28/2019 2012 Project

    14/66

    Peak and minimum demand

    Seasonal variation of demand

    Single line diagram and layout plan

    Transformer rating, impedance, tap changer ranges and type

    Transformer winding arrangement

    Transformer grounding arrangement

    Circuit breaker continues and interrupting current ratings

    Shunt reactor/capacitor ratings

    3.4DISTRIBUTION LOAD FORECAST CAN BE CLASSIFIED INTO:

    3.4.1System load forecast :viz. , forecast of the load for entire study area.

    Spatial or small area load forecast: viz. , divide the utility area in to sufficiently large

    number of small areas and forecast for each small area. There are number of different approaches

    small areas and forecasting generally falling into two categories viz., trending and simulation

    methods.

    I. Trending method: Trending methods produces the future electric demand by extrapolation

    the past trends, or pattern of load growth in small areas.

    II .Multivariate method: This method builds relationship with one set of data viz. customer

    demand data, and another class of data set such as controlled data that is pattern of land use,

    number of customers in each class etc. the demand variables are forecasted given historical and

    future set of control variables.

    III. Land used based simulation method: in this methoda mathematical relationship has

    been developed between.

    a. Changes in electric usage on per customer basis,

    b. Changes in the number and location of customers which drives the geographic spread ofelectricity demand.

    Trend methods requires historical demand data for last 4-5 years, whereas

    multivariate and land use simulation, methods requires historical land use data and customer

    number in each class and also future land use and customer spread in small area.

  • 7/28/2019 2012 Project

    15/66

    Global load forecast:Evaluates the energy and demand of the study area globally on

    Long term basis using, time series different trend curves, regression techniques linking energy

    and demand to various demographic and economic factors and end use method.

    3.5 PRESPECTIVE PLANNING:

    APTRANSCO adopts trends method for conducting feasibility studies for the

    planning of 132/33 KV substations in AP.

    A Case load flow study is done on 33kv feeders from 132/33kv-

    mustyal,Raghunathpally, Jangaon, Ghanapur substations was presented in this thesis.

  • 7/28/2019 2012 Project

    16/66

    CHAPTER-4

    LOAD FLOW STUDIES ON SUBSTATION

    4.1 INTRODUCTIONThe primary objective of system voltage control is to provide power to each user at

    specified voltage that is directed by regulator.Ideally, the output of most power supplies should be a constant voltage. Unfortunately,

    this is difficult to achieve. Voltage drop exists in each part of the power system from the source

    to the consumer service drop. It also occurs in interior wiring. System voltage regulation is

    essentially no more than maintaining the voltage at the consumer service entrance with in

    permissible limits by the use of voltage control equipment.

    In general the voltage drop is the difference between the voltage at the transmitting and

    receiving ends of a feeder, main or service. There are two factors that can cause the output

    voltage to change. First, the ac line voltage is not constant. The second factor that can change the

    dc output voltage is a change in the load resistance. Many circuits are designed to operate with a

    particular supply voltage. When the supply voltage changes, the operation of the circuit may be

    adversely affected. Consequently, some types of equipment must have power supplies that

    produce the same output voltage regardless of changes in the load resistance or changes in the ac

    line voltage.

    4.2 VOLTAGE SPREAD:

    It is the difference between maximum and minimum voltage at a particular point in the

    distribution system. It will vary in magnitude depending upon the particular location within the

    system where the spread is measured. An illustration of the voltage spreads occurring at the

    utilization point is shown in the figure below.

  • 7/28/2019 2012 Project

    17/66

    FIG:4.1

    Consumer A, which is the first consumer served by the feeder, has a voltage spread of

    just 1 volt when going from light load (230v) to heavy load (229v) conditions. Consumer B

    which is the last consumer served by the feeder has a voltage spread of seven volts i.e: 218v at

    heavy load conditions to 225v at light load conditions. The utilization voltage at consumers A or

    B for load conditions between the maximum and minimum values of the respective voltage

    spreads.

    The voltage spread at the utilization point of any other consumer on the same feeder

    would have a voltage spread with somewhere between one and seven volts, depending upon the

    location.

  • 7/28/2019 2012 Project

    18/66

    Similar voltage spreads are found at the utilization points of every consumer on the

    system. The average voltage spread at the utilization points are generally wider for rural

    distribution feeders than residential feeders or urban feeders. Consumers on urban feeders

    generally have smallest average voltage spread because the feeders are shorter in length and the

    conductor sizes are larger.

    FIG:4.2

    4.3 EFFECT OF VOLTAGE SPREAD ON UTILIZATION EQUIPMENT:

    Whenever the voltage applied to the terminals of utilization device varies from the

    rated or nameplate voltage of the device, performance characteristics and equipment life will also

    change. The extent of the change may be minor or serious depending upon the device, how it is

    applied, and how much the terminal voltage deviates from the nameplate rating.

  • 7/28/2019 2012 Project

    19/66

    Voltage drop will result in huge losses in network.

    4.3.1 SOME MORE EFFECTS DUE TO VARIATION OF VOLTAGE ARE AS

    FOLLOWS:

    Lamps: a 10% reduction in lamp voltage results in a 30% reduction in light output it

    means 30% of the investment is lost.

    Fluorescent lamps will operate satisfactorily over a wide range of voltage spread and

    their life is less affected. In general 1% variation in line voltage will change the

    lumen output only by about 1%

    Electronic equipment: the emission of all electron tubes is affected seriously by voltage

    variation. The cathode life is curve indicates that the life is reduced by half for each 5%

    increase in cathode voltage.

    Capacitors: the kilowatt output of capacitors varies with the square of the impressed

    voltage . a drop 10% in the supply voltage reduces the kilowatts by almost 20% .

    4.4 INDUCTION MOTORS:

    as voltage fails below rated rated voltage the starting torque reduces substantially,

    because starting torque varies as the square of the applied voltage.

    For an applied voltage 10% below rated voltage, the starting torque decreases to

    81% of normal.

    The reduction in the starting torque with low voltage may be significant and costly

    in motor applications., driving high inertia equipment.

    The table lists the general effects of voltage variation on induction motor.

    Voltage variation

    90% voltage Function of

    voltage

    110% voltage 120% voltage

    Starting and

    maximum

  • 7/28/2019 2012 Project

    20/66

    1)Running

    torque

    2)Synchronous

    speed

    3)% slip

    4)Full load

    speed

    Decreases

    19%

    No change

    Increases 23%

    Decreases 11/2

    (voltage)2

    Constant

    1/(voltage)2

    (syn. Speed-

    slip)

    Increases 21%

    No change

    Decreases

    17%

    Increases 1%

    Increases 44%

    No change

    Decreases

    30%

    Increases1.5%

    Efficiency

    1)full load

    2)3/4 load

    3)1/2 load

    Decrease 2 pt

    Practically no

    change

    Increases 1 to

    2 pts

    -------

    -------

    -------

    Increases to

    1 pt

    Practically no

    change

    Decreases 1 to

    2 pts

    Small increase

    Decreases to

    to 2 pts

    Decreases 7 to

    2 pts

    Power factor

    1)full load

    2)3/4 load

    3)1/2 load

    4)Full load

    current

    Increases 1 pt

    Increases 2 to

    3 pts

    Increases 4 to

    5 pts

    Increases 11%

    -------

    -------

    -------

    -------

    Decreases 3

    pts

    Decreases 4

    pts

    Decreases 5 to

    6 pts

    Decreases 7%

    Decreases 5 to

    15 pts

    Decreases 10

    to 30 pts

    Decreases 15

    to 40 pts

    Decreases

    11%

    Starting

    current

    Decrease 10

    to 12%

    voltage Increases 10

    to 12%

    Increase 25%

    Temp rise ,full

    load

    Increase 6-7

    degree

    centigrade

    --------

    Decraeses 3-4

    degree

    centigrade

    Decreases 5-6

    degree

    centigrade

    Maximum

    overload

    capacity

    Decreases

    19%

    (voltage)2 Increases 21% Increases 44%

    Mag.noise- no Decreases Increases Noticeable

  • 7/28/2019 2012 Project

    21/66

  • 7/28/2019 2012 Project

    22/66

    4.6 UTILIZTION EQUIPMENT VOLTAGE RATINGS:

    The design (nameplate) voltage of utilization equipment is generally matched to the

    utilization voltage that occurs during the time when it is most frequently used. Appliances which

    are used for long duration and during any load conditions, light or heavy have design voltages the

    same as nominal system voltage. Appliances of shorter time usage and relatively high demands

    have a design voltage slightly less than nominal also the voltage spread used s a basis of design

    for utilization equipment will vary depending upon the time usage and demand. For eg: the small

    household cooking appliances have design voltage spread of 100 to 120 volts, while the large

    household cooking appliances have design voltage spread of 107 to 122 volts.

    4.7 VOLTAGE DROP IN SYSTEM COMPONENTS:

    The system component voltage drop will be discussed only for the various types of

    feeders from the location on the feeder of the first consumer served to the last.

    4.7.1 RESIDENTIAL FEEDERS:

    The voltage at the point of utilization when keeping with in the favorable zone can be 217

    to 230 volts. The logical primary feeder designed to permit maximum loading and area coverage

    is to permit the first consumer electrically nearest to the source to have maximum voltage of 230

    volts during maximum load conditions. The most remote consumer electrically from the source to

    have the minimum permissible voltage of 217 volts. The average voltage drop for residential

    interior wiring during maximum load conditions is approximately three volts; hence, to have the

    utilization voltage no lower than 217volts, the voltage at the consumers service entrance or meter

    socket must be 220volts or above.

    The feeder components of a residential feeder are shown in one-line diagram below.

    Studies of residential feeder design have shown that at a definite amount of voltage drop can be

    allocated to each component for maximum economy.

  • 7/28/2019 2012 Project

    23/66

    FIG:4.7.1 Residential Feeder

    4.7.1(A) SERVICE DROP:

    The voltage drop most generally found for service drops during heavy load conditions

    is 1 volt.

  • 7/28/2019 2012 Project

    24/66

    4.7.1(B) SECONDARY LINE:

    Secondary conductors when installed generally have a voltage drop of approximately two

    to two and half volts, and as load increases the voltage drop is permitted to increase to three or

    three and half volts. When the voltage drop reaches the upper limit another

    distribution transformer is added between the existing, and the secondary line is split between the

    new and existing units. Such a procedure reduces the secondary voltage drop to less than 1 volt.

    4.7.2 DISTRIBUTION TRANSFORMER:

    At the time of installation in a developed residential area, the transformer

    loading during peak periods is generally 80 to 100 percent. For the average distribution

    transformer rating this represents a voltage drop of 1.75 to 2.5 volts the transformer remains in

    service until the peak load increases to about 140 to 160 percent. This represents a voltage drop

    of 3.25 to 4 volts. The amount of voltage drop allocated to the distribution transformer out of the

    permissible 12 volts spread is generally 3 volts.

    4.7.3 PRIMARY FEEDERS INCLUDING LATEARLS:

    The voltage drop allocated to the primary portion of the residential feeder is 3 volts, on a

    120-volt base, and is as measured from the primary terminals of the first distribution transformer

    on the feeder to the last or most remote transformer electrically. Where single phase laterals are

    tapped off the three phase main, they generally have a voltage drop from one to three volts, with

    the last lateral having about one volt drop, and the lateral tapped off near the first distribution

    transformer on the feeder three volts.

    4.7.4 RURAL FEEDERS:

    Rural feeders are also similar to residential feeders. Length of the feeders is more i.e 5 to

    10 times longer in rural feeder. Age loads play predominant role in rural feeders which contribute

    poor power factor thus more voltage drops.

  • 7/28/2019 2012 Project

    25/66

    FIG: 4.7.4 Rural Feeder

    Below table shows typical voltage drop allocations for rural feeder components. The table

    values keep the service voltage within the favorable zone. Even with the increased primary line

  • 7/28/2019 2012 Project

    26/66

    drop as compared to the residential feeder, it is often necessary to add some supplementary

    voltage boost out on the feeder.

    FEEDER

    COMPONENTS

    RESIDENTIAL

    FEEDER

    RURAL

    FEEDERMAXIMUM

    LOAD

    CONDITION

    MINIMUM

    LOAD

    CONDITION

    MAXIMUM

    LOAD

    CONDITION

    MINIMUM

    LOAD

    CONDITION

    Primary feeder From

    first distribution

    transformer to

    Last

    Distribution

    Transformer

    3.5

    1.0 6 2.0

    Distribution

    transformer3

    1.0 3 1.0

    Secondary line

    3.5

    1.0

    Total

    11.0 volts 3.3 volts 11.0volts 4.0 volts

  • 7/28/2019 2012 Project

    27/66

    4.7.5 INDUSTRIAL FEEDERS:

    Industrial feeders are relatively short feeders and serve any where from one to several

    consumers. They are similar to rural feeders, in that there are generally no secondaries, as each

    consumer has his own transformer. Many industrial consumers purchase energy directly at the

    primary voltage level and own the step-down transformer.

    There are no recommended allocations of voltage drop for industrial feeder

    components. Each industrial consumer on a feeder should have the supply voltage to the

    transformer or transformers which serve the plant fall within the zone shown in columns 2 and 3

    in the below table .The voltage spread for the primary supply should be four percent and should

    fall within the recommended voltage zone.

    NOMINAL

    SYSTEM

    VOLTAGE

    ZONE OF VOLTAGES OF

    PRIMARY ON

    TRANSFORMERS

    PRIMARY VOLTAGE

    SPREAD

    COLUMN 1

    VOLTS

    COLUMN 2

    MINIMUM

    VOLTS

    COLUMN 3

    MAXIMUM

    VOLTS

    COLUMN 4

    % OF

    COLUMN 1

    COLUMN 5

    VOLTS

    2400

    4160

    4800

    6900

    11500

    13300

    2130

    3680

    4260

    6100

    10200

    12200

    2520

    4360

    5040

    7250

    12100

    14500

    4%

    4%

    4%

    4%

    4%

    4%

    100

    170

    190

    280

    460

    550

  • 7/28/2019 2012 Project

    28/66

    TABLE: 4.7.5 Industrial Feeders

    4.8 VOLTAGE REGULATION BASED ON POWER FACTOR ANDDIVERSITY FACTOR:

    As we know that voltage regulation is the difference between the maximum and

    minimum voltage at a point in the distribution system, it can be based on the following

    Power factor

    Diversity factor

    4.8.1 POWER FACTOR :Poor power factor of load results in bad or very high voltage regulation. Power factor of some

    of the common types of loads are given below:

    LOAD

    POWER FACTOR

    Incandescent lamp

    Arc lamps used in for advertisements

    Florescent lamps

    Fans

    Electric drills

    Resistance heaters

    Induction heaters

    Arc furnaces

    Arc welders

    Resistance welders

    Induction motors

    1.0

    0.3 to 0.7

    0.4 to 0.5

    0.6 to 0.8

    0.5 to 0.8

    0.9

    1.0

    0.85

    0.85

    0.3 to 0.4

    0.65

    0.4 to 0.8

  • 7/28/2019 2012 Project

    29/66

    With the increasing trend to use more motorized gadgets by the domestic consumers, the power

    factor of the system will further decrease. It is not practicable to impose power restrictions on the

    small individual consumers.

    4.8.2 DIVERSITY FACTOR:

    There is general tendency to assume high diversity factor at the designed stage of feeders in

    order to reduce the cost f the scheme and thus make the same remunerative as per the

    departmental standards. Reasonable diversity factors for 11 kv and LT feeders are 3 and 1.5

    respectively. While these serve as general guide the diversity factors can be different provided

    they can substantiated with actual diversity factors obtainable in a particular area of feeder. The

    departmental practice at present is to design the 11 kv feeders for 10% regulation with DF of 2.5

    or 3 and LT FEEDERS FOR 5% regulation may be adopted for LT feeders when the distribution

    transformer LT voltage in 433 volts as this would still satisfy the IE rules.

    4.9 METHODS OF IMPROVING VOLTAGE REGULATION:

    There are several methods of improving voltage regulation throughout the distribution system.

    The various methods of improving voltage regulation through a distribution system are listed

    below. Each method has its own characteristics concerning amount of voltage improvement, cost-

    per-volt improvement, and flexibility.

    1. Use of generator voltage regulators.

    2. Application of voltage regulation equipment in the distribution substations.

    3. Application of capacitors in the distribution substation.

    4. Balancing of the loads on the primary feeder.

    5. Increasing of feeder conductor size.

    6. Changing of feeder sections from single-phase to multi-phase.

    7. Transferring of loads to new feeders.

    8. Installing of new substations and primary feeders.

    9. Increasing of primary voltage level.

    In order to evaluate the performance of a power distribution network and to examine

    the effectiveness of proposed alterations to a system in the planning stage, it is essential that a

  • 7/28/2019 2012 Project

    30/66

    load flow analysis of the network is carried out. The load flow studies are normally carried out to

    determine:

    The flow of active and reactive power in network branches.

    No circuits are overloaded, and the bus bar voltages are within acceptable limits.

    Effect of additions or alterations on a system such as voltage regulators, shunt & series

    capacitors.

    Effect of loss of circuits under emergency conditions.

    Optimum system loading conditions.

    Optimum system losses.

    The load flow in distribution networks is carried out for simple radial networks in

    this project, which is largely self evident.

  • 7/28/2019 2012 Project

    31/66

    CHAPTER-5

    SOFTWARE DESCRIPTION

    The code DISBUT developed by A.P.S.E. Board aims to meet the requirements of the

    distribution system planning and design. It is a complete integrated code for Computer Aided

    Distribution System analysis optimization.

    5.1 OPEN SYSTEMS:

    DISBUT is based on open systems concept using UNIX operating system conforming

    to IEEE POSIX standards, X-windows and X lib. The software is capable of working in

    networking environment on DEC, SUN, HP, SG, IBM workstations and one can choose the

    workstation platform of their choice.

    5.2 CUSTOMISED GUI:

    DISBUT is totally user friendly and interactive with Customized Graphical User

    Interface (GUI) with features like pop up menus to select options, dialogue boxes to enter data

    interactively and with scroll bar frames to display results.

    5.3 FULL GRAPHICS:

    Implements full graphics interface, providing zooming & panning and de cluttering functions.

    Zoom & pan allows user to view a particular area in detail. De cluttering allows user to define the

    level of details to be displayed.

    5.4 DIGITISATION

    5.4.1NETWORK:

  • 7/28/2019 2012 Project

    32/66

    DISBUT provides a powerful tool to digitize the electrical distribution network with

    all its entities like substations, transformers, capacitors, regulators, branches, and links including

    graphic points and their connectivity and also creates spatial and network connectivity data bases.

    Facility to edit network like add, modify and delete any entity is provided. Facility to input

    transformer capacity at each bus while digitizing the network and calculate length of line

    segments based on scale map are provided.

    5.4.2 GEOGRAPHICAL INFORMATION:

    The geographical features of area like administrative boundaries, roads, rivers, tanks

    etc.., can be digitized creating a true life image of field conditions.

    5.4.3 SINGLE LINE DIAGRAM:

    Creates a single line diagram of each feeder to display network parameters or study

    5.5 SYSTEM ANALYSIS:

    5.5.1 LOAD FLOW ANALYSIS:

    Load flow analysis is made to identify pockets of low voltage and high power

    losses, using a special iterative radial load flow algorithm, which guarantee convergence in 2 or 3

    iterations, even for the ill conditioned feeder with 20% or 30% voltage drops, with accurateresults. Facility to conduct load flow analysis of multi voltage networks and 3phase load flow

    analysis for unbalanced and unsymmetrical networks is also provided.

    5.5.2 SHORT CIRCUIT STUDY:

    Computes the fault current and fault MVA at each bus for single phase to ground and

    three phase faults with fault impedances.

    5.5.3PROTECTIVE COORDINATION: Provides protective coordination of relay and fuses in the network.

    5.5.4 LOAD MODEL:

    Evaluates annual load factor, loss factor and load duration curve of a feeder or substation.

    5.6 SYSTEM PLANNING

  • 7/28/2019 2012 Project

    33/66

    5.6.1TRENDS OF GROWTH:

    Evaluates the trend parameters of load development for different tariff categories

    from historical load data and displays trend curves.

    5.6.2 GLOBAL LOAD FORECAST:

    Evaluates the energy and demand of the study area globally on Long term basis

    using, time series different trend curves, regression techniques linking energy and demand to

    various demographic and economic factors and end use method.

    5.6.3SPATIAL LOAD FORECAST:

    Distribution planning requires quantum, location and timing of load growth, for each

    small area. The module determines the demand of each small area using time series of different

    trend curves and Land use based simulation techniques, considering development plans of the

    state and local authorities.

    5.6.4LOCATION & SIZING OF SUBSTATION:The module determines the number, location and size of Distribution substations for

    least cost system expansion plan over long term period by minimizing fixed charges of

    substations and cost of network losses.

    User has to give the potential substation sites and the feasible capacity options at

    each location. The program generates optimal and sub-optimal solutions determining the number,

    location and capacity of substations and the total cost of plan, in three steps. First step creates

    node loss table indicating the incremental losses in the network, when each node is fed from a

    given substation using principle of shortest path of algorithm and modeling losses as quadratic

    function. Second step creates minimal power loss tree, considering the constraints of substation

    size, voltage drop and load transfer using Zero one voltage drop and load transfer using Zero One

    programming. Third step generates optimal and sub-optimal feasible solutions using Branch and

    Bound techniques.

  • 7/28/2019 2012 Project

    34/66

    Another algorithm based on growth rate of KVAOHM of feeder is provided to

    choose optimal substation locations from potential sites. KVAOHM of a feeder is defined as the

    sum of products of power flows and resistance of line segments constituting the feeder. This

    algorithm gives good results in the absence of Spatial load forecast as it considers load growth

    and its location and is useful to utilities in developing countries where spatial load forecast may

    not be available.

    5.6.5 PERSPECTIVE PLANS:

    Develops Perspective Plans for Distribution system expansion for a given period,

    giving Physical and Financial Estimates.

    The above package is used in APTRANSCO, for conducting load flow studies for

    future plans, optimal utilization of existing network and minimize losses due to over loading etc.

    As a case study load flow of 33kv feeders from 132/33kv mustyal,

    Raghunathpally, Janagon, Ghanapur, substations was presented in this thesis

  • 7/28/2019 2012 Project

    35/66

    CHAPTER 6

    CASE STUDY

    The load flow was carried out on the following 7nos 33 kV feeders in Warangal districtwith actual data. Individual single line diagrams are given below with actual distances and

    connected load are self explanatory:

    6.1 FEEDER DIAGRAMS:

    (i) FEEDER 1:MUSTYAL THARIGOPPULA ANKSHAPUR2095KVA

    REBARTHY3325KVA

    MUSTYAL 3.7 KM 3.16 KM

    6.25 KM 13.24 KM

    6.98KM THARIGOPPULA5050KVA

    VELDANDA

    3067KVA

  • 7/28/2019 2012 Project

    36/66

    (ii)FEEDER 2: RAGUNATHAPALLY-QUILASHPUR

    RAGHUNATHPALLY NARMETTA5.33KM 5.92KM 5.53KM 0.83KM

    4477KVA

    QUILASHAPUR 0.67KM 4KM

    3991KVA

    MEKALAGUTA

    1400KVA

    ADDABATA

    1714KVA

    (iii)FEEDER 3: JANGAON-GANDIRAMARAM

    JANGAON BOMMAKUR15.27 KM 7500KVA

    8.53 KM

  • 7/28/2019 2012 Project

    37/66

    GANDIRAMARAM

    7500KVA

    (iv) FEEDER 4: JANGAON-ADAVIKESHAPUR

    JANGAON ADAVIKESHAPUR

    14.55 KM 5000KVA

    2.

    72 KM

    HANU MANTHAPUR

    5000KVA

    (v) FEEDER 5: GHANPUR- TADIKONDA

    GHANAPUR THATIKONDA

    8.02KM 5000KV

    4.66KM

  • 7/28/2019 2012 Project

    38/66

    5000KVA

    FATEHPURAM

    (vi) FEEDER 6: GHANAPUR MALKAPUR

    RAHAVARAM

    5000KVA

    GHANAPUR

    5.3KM 1.45KM 1.11KM 9.63KM 3.95KM

    2.56 KM PICHARA

    MALKAPUR 5000KVA10000KVA

    PEDDAPENDIAL

    8150KVA

  • 7/28/2019 2012 Project

    39/66

    (vii) FEEDER 7: MUSTYAL-DHOOLMITTA

    MUSTYAL MUSTYAL DHOOLMITTA

    10000KVA0.9 KM 7.09 KM 5.84 KM

    2.66 KM

    AKUNUR5000KVA

    BEKKAL

    5000KVA

    3.64 KM

    KUTTIGAL

    3100KVA

    The study was carried out assuming the load is balanced and pf was constant i.e., 0.8

    Two types of studies are conducted one with optimization techniques like add feeder,

    section or shunt capacitor etc presented as case I. Second study by proposing a new 132/33 kV

    SS in the scheme area that is at Narmetta with 5nos new 33 kV feeders as case-II. In both the

  • 7/28/2019 2012 Project

    40/66

    cases projection of load growth for 5 years at the rate of 9.7% is also calculated as per the

    planning criteria of APTRANSCO

    According to load flow studies the voltage regulations are as follows:

    Sl.

    No.

    Name of the 33 kV feeder No. of

    33/11

    kV SS

    Name of the

    33/11 kV SS

    % Voltage Regulations

    BaseYear

    Horizonyear

    1. Mustyal - Tharigoppula 4 Rebathy,Veldanada,

    Tharigoppula,Ankshapur(P)

    8.46 13.44

    2. Ragunathpalli- Quilashapur 4 Quilashapur,Mekalagattu

    Narmetta,

    Addabata

    5.97 9.48

    3. Jangoan - Gandiramaram 2 Gandiramaram (LI),Bommakur (LI)

    14.20 14.20

    4. Jangoan - Adavikeshapur 2 Hanmathapur,Adavikeshapur

    3.78 6.01

    5. Ghanpur -Tadikonda 2 Tadikonda,Fatehpuram

    1.87 2.97

    6. Ghanpur - Malkapur 4 Peddapendial,Malkapur,

    Rajavarm,Peechara

    10.01 15.90

    7. Mustyal - Dhoolmitta 5 Mustyal,Aknuru,Dhoolmitta,

    Bekkal,

    Kutigal

    8.70 13.82

    TABLE 6.1: Voltage regulations at base year

    As per the above results, the voltage regulation on feeders 3&6 are beyond permissible limits in

    base year. Voltage regulations on feeders at Sl No. 1,2,&7 is beyond permissible limits at the

    horizon year . Jangoan Gandiramaram (Sl No. 3) is independent feeder feeding a constant

    load, hence projection of load for horizon year is not allowed.

  • 7/28/2019 2012 Project

    41/66

    6.2 CASE-I

    1. 2 MVAR capacitor banks proposed at Tharigoppula to improve voltage regulation onfeeder at Sl no: (1).

    2. 2 MVAR capacitor banks is proposed at 33/11 kV SS Addabata SS to improve

    voltage regulation on feeder at Sl no (2).

    3. A new 33 kV feeder is proposed from Raghunathpalli SS to Gandiramaram toimprove voltage regulation on feeder at Sl n: (3)

    4. A new 33 kV feeder is proposed from Ghanapur SS to improve voltage regulation on

    feeder at Sl no (6) and also 2MVAR capacitor banks at 33/11 Pechara SS.5. A new 33 kV feeder is proposed from Mustyal SS to kutigal to improve voltage

    regulation on feederat Sl no: (7).

    The voltage regulations are given below table.

    Sl.

    No.

    Name of the 33 kV feeder No. of

    33/11kV SS

    Name of the

    33/11 kV SS

    % Voltage Regulations

    Base

    Year

    Horizon

    year

    1. Mustyal - Tharigoppula 3 Rebathy,

    Veldanada,

    Tharigoppula,

    4.91 7.81

    2. Ragunathpalli- Quilashapur 4 Quilashapur,

    MekalagattuNarmetta,

    Addabata

    4.79 7.56

    3. Jangoan - Gandiramaram 1 Bommakur (LI)

    5.08 5.08

    4. Jangoan - Adavikeshapur 2 Hanmathapur,Adavikeshapur

    3.78 6.01

    5. Ghanpur -Tadikonda 2 Tadikonda,Fatehpuram

    1.87 2.97

    6. Ghanpur - Malkapur 2 Peddapendial,Rajavarm,

    2.05 3.25

    7. Mustyal - Dhoolmitta 3 Mustyal,Aknuru,

    Dhoolmitta,

    4.81 7.65

  • 7/28/2019 2012 Project

    42/66

    8 MUSTYAL-KUTIGAL 3 KUTIGAL,Bekkal,Ankushapur

    4.63 7.35

    9 Ragunathpalli-Gandiramaram

    1 Gandiramaram 5.63 5.63

    10 Ghanpur - Peechara 2 Peechara, Malkapur 4.99 7.92

    6.3 Case II:Studies were also conducted by proposing new 132/33 kV SS in the scheme area is at Narmettawith 5 nos new feeders as the listed below:

    Sl.No Name of 33 kV feeder

    Length of

    new

    33kV

    line(Km)

    Name of 33/11 kV

    SS to be transferred

    No. of

    SS s to betransferred

    to new SS

    1 Narmetta Narmetta 1Narmetta,

    Addabata

    2

    2.Narmetta - Gandiramaram

    5Gandiramaram 1

    3.Narmetta Tharigoppula

    6Tharigoppula,

    Ankushapur

    2

    4. Narmetta Kutigal 10 Kutigal,Bekkal

    2

    5.Narmetta Malkapur

    15Malkapur 1

    The voltage regulations new 132/33 kV SS are given below table.

    Sl.No.

    Name of the 33 kV feeder No. of33/11

    kV SS

    Name of the33/11 kV SS

    % Voltage Regulations

    BaseYear

    Horizonyear

    1. Mustyal - Tharigoppula 2 Rebathy,Veldanada,

    2.65 4.21

    2. Ragunathpalli- Quilashapur 2 Quilashapur,

    Mekalagattu

    1.47 2.34

  • 7/28/2019 2012 Project

    43/66

    3. Jangoan - Gandiramaram 1

    Bommakur (LI)

    5.08 5.08

    4. Jangoan - Adavikeshapur 2 Hanmathapur,

    Adavikeshapur

    3.78 6.01

    5. Ghanpur -Tadikonda 2 Tadikonda,Fatehpuram 1.87 2.97

    6. Ghanpur - Malkapur 3 Peddapendial,

    Rajavarm,Peechara

    3.79 6.03

    7. Mustyal - Dhoolmitta 3 Mustyal,

    Aknuru,Dhoolmitta,

    4.81 7.65

    8 Narmetta-narmetta 2 Narmetta,

    Addabata

    0.60 0.95

    9 Narmetta- Gandiramaram 1 Gandiramaram 1.39 1.39

    10 Narmetta- Tharigoppula 2 Tharigoppula,Ankushapur

    2.01 3.19

    11 Narmetta-kutigal 2Kutigal,

    Bekkal

    1.99 3.16

    12 Narmetta-- Malkapur 1 Malkapur 5.06 8.03

    TABLE 6.3.2: Details of the voltage regulations after erection of substation.

    Any of the two cases may be implemented duly considering other criteria like financial

    viability and field conditions.

    6.4. CALCULATION OF VOLTAGE REGULATION BY

    CONVENTIONAL METHOD:

  • 7/28/2019 2012 Project

    44/66

    Voltage regulation on sub transmission or on distribution feederswhich are radial feeders are also calculated through conventional method byassuming regulation constants per 100kva per km.

    The regulation constants for commonly used conductors are

    given bellow:

    DETAILS OF THE

    CONDUCTOR

    % REGULATION PER 100KVA PER KM

    415 KV 11KV 33KV

    7/2.00 (SQUIRREL) 20sq.mm

    7/2.00 (WEASEL) 30sq.mm

    7/3.15 (RABBIT) 50sq.mm

    7/4.26 (DOG)

    100sq.mm

    83.75

    59.4

    40.09

    -

    0.1211

    0.08062

    0.05853

    0.03294

    -

    -

    0.0064

    0.00394

    TABLE 6.4: Details of the conductors.

    FORMULA:

    Total KVA KM x regulation constant per 100 KVAper KMPercentage regulation =-------------------------------------------------------------------------------

    100x Diversity Factor

    Here diversity factor is taken as constant 1.

    CONVENTIONAL CALCULATION

    FEEDER 1: MUSTYAL - THARIGOPPULA

  • 7/28/2019 2012 Project

    45/66

    REBARTHY ANKSHAPUR

    3.7 KM3.16KM

    MUSTYAL

    6.25KM 13.24KM

    6.98KMTHARIGOPPULA

    VELDANDA

    = 98424.5

    CALCULATION OF % REGULATION ON EACH FEEDER

    CALCULATIONS:

    KVA at ANKSHAPUR = load on the feeder x the distance from the feeder to the substation.

    = 2095 x (13.24+6.25+3.16)

    = 2095 x 22.65

    = 47451.75

    KVA at THARIGOPPULA= 5050 x (13.24+6.25)

    = 5050 x 19.49

    = 98424.5

    KVA at VELDANDA = 3067 x (6.98+6.25)= 3067 x 13.23

    .= 40576.41

    KVA at REBARTHY = 3325 x (3.7+6.25)

    = 3325 x 9.25

  • 7/28/2019 2012 Project

    46/66

    = 30 756.25

    Total KVA KM = 47451.75+98424.5+40576.41+30 756.25= 217208.91

    % regulation = total KVA KM x constant factor /100

    = 217208.91 x 0.00394/100

    =855.80311/100= 8.55%

    FEEDER 2: RAGUNATHAPALLY-QUILASHPUR

    RAGHUNATHPALLY NARMETTA

  • 7/28/2019 2012 Project

    47/66

    5.33KM 5.92KM 5.53KM 0.83KM

    QUILASHAPUR 0.67KM 4KM

    MEKALAGUTA

    ADDABATA

    CALCULATION:

    KVA at NARMETTA= 4477 x (0.83+05.53+5.92+5.33)

    = 4477 x 17.61

    = 78839.97

    KVA at ADDABATA= 1714 x (4+5.53+5.92+5.33)

    = 1714 x 20.78

    = 35616.92

    KVA at MEKALGUTTA = 1400 x (0.67+5.92+5.33)

    = 1400 x 11.92

    = 16688

    KVA at QUILASHAPUR = 3991 x 5.33

  • 7/28/2019 2012 Project

    48/66

  • 7/28/2019 2012 Project

    49/66

  • 7/28/2019 2012 Project

    50/66

    JANGAON ADAVIKESHAPUR 14.55 KM

    2.72 KM

    2286KVA

    HANUMANTHAPUR

    CALCULATION:

    KVA at HANUMANTHPUR = 2286 x (2.72+14.55)

    = 2286 x 17.27

    = 39479.22

    50

    KVA at ADAVIKESHAVPUR = 3239 x 14.55

    = 47127.45

    Total KVA KM = 39479.22+47127.45

    = 86606.67

  • 7/28/2019 2012 Project

    51/66

  • 7/28/2019 2012 Project

    52/66

    GHANAPUR THATIKONDA

    8.02KM 3070KVA

    4.66KM

    1500KVA

    FATEHPURAM

    CALCULATION:

    KVA at FATEHPURAM = 1500 x (4.66+8.02)

    = 1500 x 12.88

    = 19320

    KVA at THATIKONDA = 3070 x 8.02

    = 24621.4

    Total KVA km = 19320+24621.4

    = 43941.4

    % Regulation at FATEHPURAM = 43941.4 x 0.00394/100

    = 1.73%

    FEEDER 6: GHANAPUR MALKAPUR

  • 7/28/2019 2012 Project

    53/66

    RAHAVARAM

    GHANAPUR

    5.3KM 1.45KM 1.11KM 9.63KM 3.95KM

    MALKAPUR PICHARA

    2.56 KM

    4001KVA

    PEDDAPENDIAL

    CALCULATION:

    KVA at PICHARA = 2744 x (3.95+9.63+1.45+5.3)

    = 2744 x 20.33

    = 55785.52

    KVA at MALKAPUR = 9297 x (9.63+1.45+5.3)

    = 9297 x 16.38

    = 152284.86

    KVA at RAJAVARAM = 4573 x (1.45+5.3+1.11)

    = 4573 x 7.86

  • 7/28/2019 2012 Project

    54/66

    = 35943.78

    KVA at PEDDAPENDIYALA = 4001 x (2.56+5.3)

    = 4001 x 3.09

    = 12363.09

    Total KVA km = 55785.52+152284.86+35943.78+12363.09

    = 256377.25

    % Regulation at PICHARA = 256377.25 x 0.00394/100

    = 10.10%

    FEEDER 7: MUSTYAL-DHOOLMITTA

  • 7/28/2019 2012 Project

    55/66

    MUSTYAL 5000 KVA

    MUSTYAL DHOOLMITTA

    0.9 KM 7.09 KM 5.84 KM

    8955 KVA

    2.66 KM

    3.43 KM

    AKUNUR

    BEKKAL

    5000 KVA

    3.64 KM

    KUTIGAL

    3100 KVA

    CALCULATION:

    KVA at KUTIGAL = 3100 x (3.64+3.43+5.84+7.09+0.9)

    = 3100 x 20.09

    = 62279

    KVA at BEKKAL =2854 x (3.43+5.84+7.09+0.9)

  • 7/28/2019 2012 Project

    56/66

    = 2854 x 17.26

    = 49260.04

    KVA at DHOOLMITTA = 8955 x (5.84+7.09+0.9)

    = 8955 x 13.83

    = 123847.65

    KVA at AKUNUR = 2705 x (2.66+7.09+0.9)

    = 2705 x 10.65

    = 28808.25

    KVA at MUSTYAL = 8478 x 0.9

    = 7630.2

    Total KVA km = 62279+49260.04+123847.65+28808.25+7630.2

    = 271825.14

    % Regulation at MUSTYAL = 271825.14 x 0.00394/100

    = 10.70%

    6.5 OBSERVATIONS:

    1. MUSTYAL-THARIGOPPULA

    We can observe here that when we calculate voltage regulation through hand, the voltage

    regulation at this feeder is 8.55 and system analysis gives the result as 8.46.

    2. RAGUNATHPALLY- GANDIRAMARAM

  • 7/28/2019 2012 Project

    57/66

    We can observe here that when we calculate voltage regulation through hand, the voltage

    regulation at this feeder is 6.005 and system analysis gives the result as 5.97.

    3.JANGAON- GANDIRAMARAM

    We can observe here that when we calculate voltage regulation through hand, the voltage

    regulation at this feeder is 11.43 and system analysis gives the result as 14.20.

    4.JANGAON- ADAVIKESHAPUR

    We can observe here that when we calculate voltage regulation through hand, the voltage

    regulation at this feeder is 3.41 and system analysis gives the result as 3.78.

    5. GHANPUR- TADIKONDA

    We can observe here that when we calculate voltage regulation through hand, the voltage

    regulation at this feeder is 1.73 and system analysis gives the result as 1.87.

    6. GHANPUR- MALKAPUR

    We can observe here that when we calculate voltage regulation through hand, the

    voltage regulation at this feeder is 10.10 and system analysis gives the result as 10.01.

    7. MUSTYAL-DHOOLMITTA

    We can observe here that when we calculate voltage regulation through hand, the voltage

    regulation at this feeder is 10.70 and system analysis gives the result as 8.70.

    From the above all results and analysis we can observe that the voltage regulations

    obtained through conventional method are more than the results of voltage regulation obtained

    from system analysis.

    Therefore we can concludes that system analysis for load flow studies is the most

    appropriate method.

  • 7/28/2019 2012 Project

    58/66

    CHAPTER 7

    RESULTS

    7.1 BASE STUDY

    TABLE: FEEDER DATA

    Feeder

    no.

    Name of the

    feeder

    no. of

    substation

    Transformer

    s capacitykva

    Load

    factor

    Length

    km

    Starting

    voltagekv

    12

    3

    4

    56

    7

    Mstl-tgplRgpl-qspr

    Jgn-grvm

    Jgn-akpr

    Gpr-tkdGpr-mkpr

    Mstl-dmt

    44

    2

    2

    24

    5

    2500020000

    15000

    10000

    1000028150

    35000

    0.500.50

    0.50

    0.50

    0.500.50

    0.50

    33.3322.28

    23.80

    17.27

    12.6824.20

    23.56

    33.0033.00

    33.00

    33.00

    33.0033.00

    33.00

    total 23 143150 157.12

    TABLE: FEEDER ANALYSIS

    Feederno.

    Name ofthe feeder

    Activeload kw

    Reactiveload

    kvar

    Energyloss l.u

    Powerlosskw

    % reg %energy

    loss

    1

    2

    34

    5

    67

    Mstl-tgpl

    Rgpl-qspr

    Jgn-grvmJgn-akpr

    Gpr-tkd

    Gpr-mkprMstl-dmt

    11464.

    8759.

    13451.4559.

    3708.

    14712.15629.

    8850.

    6703.

    10664.3475.

    2802.

    11419.12008.

    16.69

    8.84

    38.273.66

    1.37

    25.5218.95

    635.

    336.

    1456.139.

    52.

    971.721.

    8.46

    5.97

    14.203.78

    1.87

    10.018.70

    3.32

    2.30

    6.501.84

    0.84

    3.962.77

    total 72283. 55919. 113.29 4311. 14.20

    maximum

    3.58

  • 7/28/2019 2012 Project

    59/66

  • 7/28/2019 2012 Project

    60/66

    7.1 CASE-1: AFTER ADDING FEEDERS AND CAPACITOR BANKS.

    BASE YEAR:TABLE

    S.No Name of

    the feeder

    no. of

    substation

    Transformer

    s capacitykva

    Load

    factor

    Length

    km

    Starting

    voltage kv

    1

    2

    34

    5

    6

    78

    9

    10

    Mstl-tgpl

    Rgpl-qspr

    Jgn-grvmJgn-akpr

    Gpr-tkd

    Gpr-mkpr

    Mstl-dmtMstl-ktl

    Rgpl-grvm

    Gpr-pcr

    3

    4

    12

    2

    2

    33

    1

    2

    20000

    20000

    750010000

    10000

    13150

    2500015000

    7500

    15000

    0.50

    0.50

    0.500.50

    0.50

    0.50

    0.500.50

    0.50

    0.50

    31.82

    22.28

    20.9217.27

    12.68

    12.63

    18.1223.20

    16.83

    16.54

    33.00

    33.00

    33.0033.00

    33.00

    33.00

    33.0033.00

    33.00

    33.00total 23 143150 192.29

    FEEDER ANALYSIS:

    Feederno.

    Name of thefeeder

    Activeload in

    kw

    Reactiveload in

    kvar

    Powerloss kw

    Energyloss l.u

    % reg %energy

    loss

    1

    234

    5

    6

    78

    9

    10

    Mstl-tgpl

    Rgpl-qsprJgn-grvmJgn-akpr

    Gpr-tkd

    Gpr-mkpr

    Mstl-dmtMstl-ktl

    Rgpl-grvm

    Gpr-pcr

    9470.

    8684.6269.4559.

    3708.

    5816.

    11793.5277.

    6300.

    8355.

    5419.

    4797.4809.3475.

    2802.

    4401.

    8958.4037.

    4844.

    4590.

    316.

    261.269.139.

    52.

    100.

    286.199.

    300.

    328.

    8.31

    6.857.083.66

    1.37

    2.62

    7.515.22

    7.89

    8.61

    4.91

    4.765.083.78

    1.87

    2.05

    4.814.63

    5.63

    4.99

    2.00

    1.802.581.84

    0.84

    1.03

    1.452.26

    2.86

    2.35

    total 70231. 48132. 2250. 59.12 5.63 1.92

  • 7/28/2019 2012 Project

    61/66

    HORIZON YEAR:

    Feeder

    no.

    Name of the

    feeder

    Source

    load kw

    Power loss

    kw

    Energy

    loss l.u

    % reg % energy

    loss

    123

    4

    5

    67

    8

    910

    Mstl-tgplRgpl-qsprJgn-grvm

    Jgn-akpr

    Gpr-tkd

    Gpr-mkprMstl-dmt

    Mstl-ktl

    Rgpl-grvmGpr-pcr

    15044.13796.6269.

    7243.

    5891.

    9239.18735.

    8383.

    6300.13273.

    798.658.269.

    352.

    131.

    251.721.

    501.

    300.827.

    20.9817.307.08

    9.25

    3.45

    6.6118.94

    13.18

    7.8921.73

    7.817.565.08

    6.01

    2.97

    3.257.65

    7.35

    5.637.92

    3.182.862.58

    2.92

    1.34

    1.632.31

    3.59

    2.863.74

    Total 104174. 4810. 126.41

  • 7/28/2019 2012 Project

    62/66

  • 7/28/2019 2012 Project

    63/66

    TABLE: FEEDER ANALYSIS AT HORIZON YEARHORIZON YEAR:2015

    Feederno. Name of thefeeder Source loadkw Powerloss kw Energyloss l.u % reg % energyloss

    1

    2

    3

    45

    6

    78

    9

    1011

    12

    Mstl-tgpl

    Rgpl-qspr

    Jgn-grvm

    Jgn-akprGpr-tkd

    Gpr-mkpr

    Mstl-dmtNrmt-nrmt

    Nrmt-grm

    Nrmt-trgNrmt-ktg

    Nrmt-mlk

    8295.

    6292.

    6269.

    7243.5891.

    12291.

    18735.7175.

    6071.

    9221.5489.

    10287.

    271.

    101.

    269.

    352.131.

    483.

    721.35.

    71.

    223.134.

    699.

    7.13

    2.66

    7.08

    9.253.45

    12.70

    18.940.92

    1.86

    5.873.52

    18.37

    4.21

    2.34

    5.08

    6.012.97

    6.03

    7.650.95

    1.39

    3.193.16

    8.03

    1.96

    0.97

    2.53

    2.921.34

    2.36

    2.310.29

    0.70

    1.451.46

    4.08

    total 103260 3491. 91.75

    TABLE: SUBSTATION DEMAND AND CAPACITY.

    S.No.

    Name of the

    substation

    Before improvements After improvements proposed

    capacity

    mva

    Transformer

    capacity

    Demand

    kva

    Demand

    existingkva

    demand at

    horizonyear kva

    12

    3

    45

    mustyalr pally

    janagoan

    ghanpurNARMETTA

    6347.5

    32

    47.5

    59300.46850.

    27180.

    45700.

    46470.40781.

    17916.

    36793.33023.

    59045.43701.

    21291.

    45248.47986.

    Total demand 174983. 217271.

    .

  • 7/28/2019 2012 Project

    64/66

    CHAPTER 8

    CONCLUSION

    As discussed in earlier chapters load flow is most efficient and useful tool in Power

    System planning and operation. Load flow on actual sub-transmission network in Warangal

    district was studies necessary improvements were also suggested to improve the voltage

    wherever they are beyond permissible limits in this project work.

    The load flow can also be carried out for arriving network losses and remedial measures

    for reducing losses may also be studied in future. Reduction of network losses is very important

    in the prospect of any utility.

    63

  • 7/28/2019 2012 Project

    65/66

  • 7/28/2019 2012 Project

    66/66