2011 - 2016...implementation programme 2011 - 2016 grid25 implementation programme 2011 - 2016...
TRANSCRIPT
GRID25Implementation Programme
2011 - 2016
www.eirgrid.com
GRID25Implementation Programme
2011 - 2016
Section 1 - Introduction and Context
1.1 Context 2
1.2 TheVisionofGrid25 5
1.3 StrategicObjectivesofGrid25 5
1.4 TheStrategicPolicyContextforGrid25 6
1.5 TheChallenges 7
Section 2 - The Grid Development Strategy
2.1 Introduction 9
2.2 TheGrid 9
2.3 TransmissionSystemPlanning 9
2.3.1 ElectricityDemand
2.3.2 Generation
2.3.3 Potentialmajordemandcentres
2.3.4 Interconnection
2.3.5 Planning,environmentalandcommunityconsiderations
2.4 FutureGridRequirements 13
2.4.1 Onshoregrid
2.4.2 Offshoregrid
2.5 TheGridDevelopmentStrategy 15
2.5.1 ReinforcementofthetransmissionsystemintheBorderRegion
2.5.2 ReinforcementofthetransmissionsystemintheMidlandsRegion
2.5.3 ReinforcementofthetransmissionsystemintheSouth-EastRegion
2.5.4 ReinforcementofthetransmissionsystemintheWestRegion
2.5.5 ReinforcementofthetransmissionsystemintheMid-WestRegion
2.5.6 ReinforcementofthetransmissionsystemintheSouth-WestRegion
2.5.7 ReinforcementofthetransmissionsystemintheDublinandMid-EastRegions
Section 3 - Towards A Planning And Environmental-Led Approach To Electricity Transmission
Infrastructure Development
3.1 Context 29
3.2 GovernanceandProcess 29
3.3 EnvironmentalDataandGuidelines 31
3.4 ProceduresforTransmissionSystemPlanning 34
Section 4 - Planned Network Developments
4.1 Context 35
4.2 NetworkReinforcementDevelopments 39
4.3 DSOConnections 40
4.4 GeneratorConnections 41
Table of Contents
Section 5 - Environmental Mitigation Measures
5.1 Introduction 43
5.2 EMM1FullIntegrationofPlanningandEnvironmentalConsiderationsinEirGrid’s
TransmissionSystemPlanning 45
5.3 EMM2PreparationofStrategicEnvironmentalConstraintsMapping 46
5.4 EMM3PreparationofEvidence-BasedEnvironmentalGuidelines 46
5.5 EMM4ConsiderationoftheBroadestPossibleRangeof
AlternativesinallFutureEnergyTransmissionStrategies 50
5.6 EMM5PreparationofTransmissionDevelopmentPlanEnvironmentalAppraisalReport 50
5.7 EMM6OngoingCo-operationinpreparationofRenewableEnergyGenerationGuidelines
andStrategies 50
5.8 EMM7IntegratingOffshoreGridconnectivityrequirementsandenvironmental
considerationsinEirGrid’sStrategicEnvironmentalFramework(SEF) 51
APPENDIX A – Network Reinforcement Projects, Demand Customer and DSO Connection
Projects, and Generator Connection Projects, identified in EirGrid’s Transmission
Development Plan 2010.
A1 NetworkReinforcementProjects 53
A2 DemandCustomerandDSOConnections 67
A3 GeneratorConnections 71
A4 ConnectionofInterconnectors 74
APPENDIX B – Mitigation Measures 75
1
2
1.1 ContextEirGridplc(“EirGrid”)istheNationalelectricityTransmissionSystemOperator(TSO).TheEuropeanCommunities(InternalMarketinElectricity)Regulations,2000(SINo.445of2000)setsouttheroleandresponsibilitiesoftheTSO;inparticular,Article8(1)(a)givesEirGrid,asTSO,theexclusivefunction:
“to operate and ensure the maintenance of and, if necessary, develop a safe, secure, reliable, economical, and efficient electricity transmission system, and to explore and develop opportunities for interconnection of its system with other systems, in all cases with a view to ensuring that all reasonable demands for electricity are met having due regard for the environment.”
“Develop”inthiscontextreferstoplanning,routing,obtainingconsentsetc,butnottoconstructingthetransmissionsystem(theGrid),whichiscarriedoutbyESBNetworksasTransmissionAssetOwner(TAO).NeitherdoesEirGrid’sroleincludethegeneration,distributionandsellingofelectricityinIreland.
Section 1 - Introduction and Context
Grid251isahigh-levelstrategyoutlininghowEirGridintendstoundertakethedevelopmentoftheelectricitytransmissiongridintheshort-,medium-andlonger-terms,tosupportalong-termsustainableandreliableelectricitysupply.TheGrid25strategyseekstoimplementtheprovisionsofthe2007GovernmentWhitePaperonEnergy-Delivering a Sustainable Energy Future for Ireland intermsofdevelopmentofelectricitytransmissioninfrastructure.
Gridplanninganddevelopmentarehighlydynamicprocessesthatareconstantlyrespondingtochangesindemandandtheemergingconditionsofthegrid2.Griddevelopmentisessentiallyareactiveprocess–reactingto,andfacilitating,identifieddemandforanenhancednetworkinanarea,forexamplenewgenerationsources,ornewdemandcentressuchasnewcentresofemploymentorpopulationgrowth.Assuch,griddevelopment,andGrid25inparticular,doesnotdictatewheresuchnewdemandistooccur;rather,gridplanninganddevelopmenthassignificantcognisanceofotherstrategiesforspatialandstrategicplanninganddevelopment.
ThisGrid25 Implementation Programme(IP)isapracticalstrategicoverviewofhowtheearlystagesofGrid25areintendedtobeimplemented.TheIPidentifiesthebestcurrentunderstandingofthosepartsofthetransmissionsystemthatareenvisagedaslikelytobedevelopedoverthenextfiveyears–thisisseparatelysetoutinEirGrid’sannualTransmissionDevelopmentPlan(theidentifiedprojectsofwhicharereproducedinSection4andAppendixAofthisIP)togiveeffecttocurrentGovernmentPolicy.TheIPidentifiestheissues,objectivesandassociatedprocessesthatwillneedtobeadoptedwhenmakingdecisionsabouthow
1Grid25–“AStrategyfortheDevelopmentofIreland’sElectricityGridforaSustainableandCompetitiveFuture”,publishedbyEirGridinOctober2008.
2ThisdynamismisreflectedintheStatutoryreportingprocessesoftheCommissionforEnergyRegulation(CER)whichrequirethepublicationofannualreviewsandupdateofaTransmissionDevelopmentPlan–preparedinaccordancewithArticle8(6)ofTheEuropeanCommunities(InternalMarketinElectricity)Regulations,2000(SINo.445of2000),andwhichissubmittedforapprovaltotheCommissionforEnergyRegulation(CER).
3
andwheredevelopmentswilloccur.Inthiswayitestablishestheparametersandcriteriafortheprocessesbywhichsubsequentdecisionswillbemade.
ThisIPandaccompanyingStrategicEnvironmentalAssessment(SEA),incorporatesadviceandcommentsreceivedfromboththeEnvironmentalProtectionAgency(EPA)andtheNationalParksandWildlifeService(NPWS)oftheDepartmentofArts,HeritageandtheGaeltacht(DAHG),aswellasfromotherpartiesduringtheperiodofpublicconsultationinrespectoftheDraftIP.TheSEAwasundertakenfollowingascopingexercise,inlinewithcurrentbestpracticeforthecarryingoutofSEAsforNational-scaleprogrammes.Theseassociateddocumentshavealsobeenrevisedinresponsetosubmissionsmadeduringtheperiodofpublicconsultation.
Itisimportanttonotethat,whileotherSEAs,suchasinrespectofland-useplans,maymakeretrospectiverecommendations3abouthowtheplansorpoliciesshouldbealteredtoavoidimpactsontheenvironment,duetothehighlevelandstrategicnatureoftheSEAforthisIP,mostoftherecommendationshavebeenabouthowtochangedecision-makingprocesseswithintheIPitself.Assuch,therecommendedmitigationmeasuresinmanyinstanceshavealreadybeenincorporatedintotheIPinaniterativeprocess,someofwhichhavebroughtaboutchangesintheorganisationalandworkingpracticeswithinEirGrid.ThesehighlevelmitigationmeasuresareoutlinedinSection5ofthisdocument,whilelowertiermeasuresareincludedinAppendixB.
Itisintendedthatfollowingadoption,theIPandassociatedSEA4willhavea5–yearlifespan,withthereviewanddraftingprocessforthesubsequent
3Theseareusuallyincludedas‘mitigationmeasures’
4PresentedinanEnvironmentalReport(ER)withaccompanyingNaturaImpactStatement
4
Figure 1.1 Structure for Grid25 strategy and associated Implementation Programme, SEA, Transmission Development Plan* and associated Environmental Appraisal Report.
TDP
TDP EAR
TDP EAR
TDP EAR
TDP EAR
TDP
IP5Year
IPReview5Year
Grid 25
SEA
SEA
EAR
*TheTDPisafiveyearplanwhichissubjecttoannualreview.
Allreferencesto‘TransmissionDevelopmentPlan(TDP)2010’intheIP,andassociatedSEAdocuments,refertothe‘DraftTDP2010’whichiscurrentlywiththeCommissionforEnergyRegulation(CER)forformalreviewandapproval.
5
IPandSEAcommencingwithinthefinalyearofthatlifespan.However,thecontentofthesedocumentswillbesubjecttoongoingreviewandupdateovertheperiodofGrid25,inthecontextoftheEirGridTransmissionDevelopmentPlan,whichisupdatedannually.AnEnvironmentalAppraisalReport(EAR)willbeproducedtoaccompanyeachannualTDP,todemonstratehowtheTDPisinaccordancewiththeprovisionsoftheIPandSEA,ortoidentifyanyupdatestothesedocuments.OngoingmonitoringmeasuresassetoutintheSEAwillalsobeaddressedineachannualEAR.
ThisrelationshipissetoutgraphicallyatFigure1.1.
1.2 The Vision of Grid25Giventhatthedemandsfortransmissioninfrastructurearelikelytobefardifferentin2025,andbeyond,thancurrently,EirGridmustplanforthelonger-termfuturestrategictransmissiondevelopmentandreinforcementneedsoftheelectricitytransmissionnetwork.
TheVisionofGrid25“is of a grid developed to match future needs, so it can safely and reliably carry power all over the country to the major towns and cities, and onwards to every home, farm and business where the electricity is consumed and so it can meet the needs of consumers and generators in a sustainable way”(p.13).TheStrategytoachievethisvisionstates,interalia,:
“Grid25 will deliver an efficient transmission network for Ireland’s social and economic development. It will have the necessary capacity to reliably transport the future anticipated power levels from renewable and conventional generators and interconnectors to the cities and towns and the villages where the power is required.
We will follow international best practice and innovative methods to provide the necessary transmission capacity. The technology options
available to implement Grid25 will increase as research and development is carried out. We will be proactive in investigating and adopting new technologies taking due consideration of the cost and effectiveness of the technology”.(p.21)
Grid25notesEirGrid’sStatutoryobligationtobalancetheprovisionofreliabletransmissioninfrastructurewiththecoststothefinalcustomerandwiththeimpactofthatinfrastructureontheenvironment(p.21).
1.3 Strategic Objectives of Grid25IndevelopingtheGrid,theGrid25strategyenvisagesthedeploymentofstrategicalternativesdesignedforthelong-termdevelopmentofasafe,secure,reliable,economicandefficientgrid.Inthiscontext,theGridDevelopmentStrategyofGrid25(pp21-22)notesthat,inconsiderationofthecapacityofnewtransmissionlines,therewillbeapositivepresumptiontowardsbuildingnewlinesat400kVandat110kVwhereappropriate.Buildingat400kVratherthan220kVismoreefficientandprovidesgreaterpowercarryingcapability.Buildingone400kVcircuitavoidstheneedforbuildingamultiplicityof220kVand110kVlinesandsohaslesslong-termimpactontheenvironmentandonlocalcommunities.Inthelongerterm,itmaybeappropriatetoupgradethe220kVnetworkto400kV,forsimilarreasonsofefficiencyandcapacity.EirGridwillexamineeachcaseastheneedtoupgradearises.
TheStrategynotesEirGrid’scommitmenttoseektominimisethenetlengthofnewlinebuildinaregionthroughanumberofinitiatives(p.22):
• Byutilisingtheexistingnetworkwherepossibletoavoidbuildingnewoverheadcircuits.Re-utilisingtheexistingnetworkmaybemorecostlythanbuildingnewcircuits,butmayresultinalowerimpactontheenvironment;
6
• Seekingtoup-rateexistinglinesbyusingahighercapacityconductor,whereappropriate,toavoidtheneedformajorstructuralchangesandsotominimisesecurityissues;
• Wheretherequiredincreaseincapacitycannotbeachievedthroughanewconductor,consideringupgradingthecircuittoahighervoltage;
• Whereappropriate,consideringreplacinganexistingsingle-circuitlinewithadoublecircuitlinetoprovidetherequiredadditionalcapacity;whilethisisamorecostlyoption,andlessreliablethanhavingtwoseparatelines,itavoidsbuildinganewlineonaseparateroute;
• Inlimitedcircumstances,puttingcertain110kVcircuitsundergroundtominimisetheimpactofnewbuildinaregion.Thismaybeconsidered,forexample,inareaswherethereiscongestionofurbandevelopment,amultiplicityofoverheadlines,arelativelywideexpanseofwater,oranareaofuniquenaturalbeauty;
• ExaminingthepotentialforusingHVDCtechnologyforcertainapplicationswhereappropriate,forexamplesuchastransportinghighvolumesofpoweroverlongdistances;
• ConsideringtheappropriatenessofnewtowerdesignsandothermitigatingmeasuresoutlinedintheGovernment-sponsoredreport,preparedbyEcofys,onThe Comparative Merits of Overhead Electricity Transmission Lines Versus Underground Cablesinordertominimisethelandscapeandvisualimpactofnecessaryinfrastructure,andtakingaccountoftheNationalLandscapeStrategywhenpublished.
1.4 The Strategic Policy Context for Grid25
IrishenergypolicyissetfirmlyinaglobalandEUcontextwhichhasputenergysecurityandclimatechangeamongthemosturgentinternationalchallenges.Inpursuitofthis,theEUhassetalegallybindingobligationforMemberStatesthatgreenhousegasesacrosstheEUmustbereducedby
7
atleast20%by2020,comparedwith1990levels.
ThestrategiccontextforenergyinfrastructureissetoutinanumberofpolicydocumentscoveringNational,RegionalandLocallevels,andcomprisingbothspatialandnon-spatialplanningpolicy.Theseinclude:
-IrishGovernment’sEnergyWhitePaper Delivering a Sustainable Energy Future for Ireland(March,2007)
- NationalDevelopmentPlan2007–2013, NationalSpatialStrategy2002–2020,
- RegionalPlanningGuidelines2010–2022,
- CountyDevelopmentPlansandrelevant LocalAreaPlans.
The2007WhitePapersetsatargetof33%ofelectricityproducedfromrenewablegenerationby2020;thiswassubsequentlyincreasedto40%.
Some58%ofcurrentdemandforelectricityisingatewaycitiesandtowns,asidentifiedintheNationalSpatialStrategy(NSS).TheNSSdefinesgatewaysashavingastrategiclocation,nationallyandrelativetotheirsurroundingareasandprovidingnational-scalesocialandeconomicinfrastructureandsupportservices.TheGrid25strategywillcontributetoachievingtheNSSgoalofdevelopinggatewaysandachievingbalancedregionaldevelopment.Inthisstrategiccontext,theprovisionsandpoliciesofthevariousRegionalPlanningGuidelinesareofessentialimportance.
EirGridpublishesaTransmissionForecastStatementannuallywhichhighlightsopportunitiesfortheconnectionofdemandat31pointsonthegrid.ThedocumentpresentstheopportunitiesforgeneratorconnectionsidentifiedthroughtheGate3connectionprocessandoutlinesthegenerationopportunitiesarisingfromGrid25.
EachPlanningAuthorityisrequiredtoprovideanobjectivewithinitsDevelopmentPlanforthe
provision/facilitationofinfrastructureincludingenergy.Inaddition,Section10(1B)ofthePlanningandDevelopmentActs2000–2010requiresthatallplanningauthoritiesshall,withinoneyearaftermakingRegionalPlanningGuidelines,prepareaCoreStrategy.TheCoreStrategymustshowthatCountyDevelopmentPlanobjectivesareconsistentwithnationalandregionaldevelopmentobjectivesintheNationalSpatialStrategyandRegionalPlanningGuidelines.Thisensuresthatthestrategicvisionofthesehigher-levelplanningandpolicydocumentsareappropriatelyandadequatelyreflectedinlocalDevelopmentPlanpoliciesandobjectives.
Thecorestrategymust,amongotheraspects:
- Detailandtakeaccountofexistingandproposedtransmissioninfrastructureinacounty;
-Providetheframeworkfordecidingonthescale,phasingandlocationofnewdevelopment,havingregardtoexistingservicedandplannedinvestmentoverthecomingyears.
Consequently,keyelectricityprojectswhicharecriticaltothefuturedevelopmentofacountyandregioncanbeprioritised.
1.5 The ChallengesEnergy Potential
GivenIreland’ssignificantpotentialforgenerationofrenewableenergythroughbothonshoreandoffshorewindenergy,andothermarinerenewableenergygeneration,thepotentialexiststomakeuseofthesenaturalresourcestoprovideforIreland’sinternalenergyneeds,meetNationalcommitmentstoreduceCO2emissionlevelsundertheKyotoProtocol,andtomakeIrelandmoreenergysecure.EirGrididentifiesfurtherrenewablegenerationasanincreasinglyimportantpartoftheoverallgenerationmix,andiscommittedtosupportingandfacilitatinggovernmentpolicyforthecapturingofrenewableenergy,primarilybymeansofthe
8
developmentofarobust,secureandreliableelectricitytransmissiongrid.TheGovernment’srenewablegenerationtargetfor2020istomeet40%ofelectricityconsumptionfromrenewableenergysources.EirGrid’sGrid Development Strategy,assetoutinGrid25,involvesplanninganddevelopingthetransmissionsystemtomeetanticipatedlonger-termgeneration/demandneeds,therebyprovidingforamorecosteffective,optimalandefficientsystemthanwouldbethecasewithamoreshort-termandpiecemealapproach.Inparticular,Grid25providesfortheoptimalconnectionofaverysignificantcapacityofrenewablegenerationinIrelandoverthecomingyears;suchconnectionwilloccurthroughalong-termstrategicprogrammeoftransmissiondevelopment.
Economic Development
Continuedcommitmenttoinvestmentinnationalstrategicinfrastructure,includingtransmissioninfrastructure,providesakeybasisforeconomicrecoveryandgrowth.Givencurrenteconomiccircumstances,thereisaneedtoprioritiseprojectsandexpenditurewiththemostimmediatepositiveimpactontheeconomyandemployment.InvestmentmustalsobedeliveredinacoherentandefficientmannerandbeconsistentwiththeGovernmentvisiontocreatea‘SmartEconomy’.Theprovisionofenergyinfrastructureisoneofthekeydriversforeconomicgrowthandregionalandnationalcompetitiveness.TheGovernmenthasendorsedEirGrid’sstrategyforNationalinfrastructuredevelopmentasperGrid25,andsupportssignificantinvestmentinthestrategicandlonger-termdevelopmentoftheelectricitytransmissionnetwork
Export of Energy
Inresponsetothe2007GovernmentWhitePaperonEnergy-Delivering a Sustainable Energy Future for Ireland,EirGridhascarriedoutanassessmentofthecostsandbenefitsofadditionalinterconnection
betweentheislandofIrelandandtheUKandFrance5(inadditiontotheexistingMoyleInterconnector 6andtheEast-WestInterconnector,currentlyunderconstructionbyEirGridbetweenIrelandandWales).Incarryingoutthisassessment,EirGridhasexaminedabroadrangeofscenariossuchasthelikelyrequirednumberofinterconnectors,differentfuelpricesanddifferentgenerationportfolios.Thereportconcludesthatenhancedinterconnectionbetweentheall-islandgridandothergridshasthepotentialtodeliversignificantbenefitstotheislandofIreland.
Balanced Regional Development
BecauseoftheimportanceoftheelectricitysystemtocustomersalloverIreland,EirGridisveryconsciousofgovernmentpoliciestosupportregionaldevelopment.Theinvestmentinthistransmissionstrategyisdistributedacrossallregions,andtherebywillsignificantlyimproveregionalelectricityinfrastructure,andwillprovidethebackboneforfurthereconomicdevelopmentintheregions.FurtherdevelopmentemergingfromGrid25willmaintainpriorityinsupplystandardsacrossallpartsofthenetwork,thusenablingeconomicdevelopmentinallregions.
Itisimportantthatnationalandregionalspatialplanninganddevelopmentpoliciesandstrategiesrecognisetheestablishedrelationshipbetweeneconomicgrowthandelectricityconsumption.Aspartoftheeconomicrecoveryofeachregion,andthecountryasawhole,itisimportantthateachregionhasamodernefficienttransmissionnetworkthatwillallowittocompetewithotherregionsinIrelandandEuropeinattractingpotentialinvestorsandemployers.Inthiscontext,itisimportantthatlocalauthorities,localandcountydevelopmentplans,andregionalplanningguidelinesensureadequatepriorityforkeyelectricitytransmissionprojectsthatarecriticaltothefuturedevelopmentofaregion.
5InterconnectionEconomicFeasibilityReport,EirGrid,November2009,availableatwww.eirgrid.com
6TheMoyleInterconnectorconnectstheelectricitygridsofNorthernIrelandandScotland
9
2.1 IntroductionThehighvoltage(HV)electricitytransmissionnetwork(110kV,220kVand400kV)formsthebackboneoftheelectricitysupplysysteminIreland.High-qualityandreliableelectricitytransmissioninfrastructure,providingqualityperformance,isvitalforIreland’songoingsocio-economicdevelopment,andthusisofnationalstrategicimportance.
2.2 The Grid Thenationalelectricitytransmissiongridplaysavitalroleinthesupplyofelectricity,providingthemeanstotransportpoweracrossameshednetwork,linkinggeneratorlocationswithoftensignificantlyspatiallydistantdemandcentres.The400kVnetworkprovidesahighcapacitylinkbetweenMoneypointgenerationstationonthewestcoastandtheGreaterDublinAreaontheeast.The220kVnetworkformsanumberofsinglecircuitloopsaroundthecountry.The110kVnetwork,whichisthemostextensiveelementoftheoveralltransmissionsystem,extendsacrossthecountry(refertoFigure2.1).
TheIrishnetworkiscurrentlyconnectedtothetransmissionsystemofNorthernIrelandprimarilybymeansofasingle275kVdoublecircuitinterconnectionbetweenLouthandTandrageesubstations.Therearealsotwolower-capacity110kVconnectionswiththeNorthernIrelandnetwork,atLetterkennyinCo.DonegalandCorraclassyinCo.Cavan.
ThetransmissionsystemontheislandofIrelandisalmostentirelyconstructedasoverheadline(OHL),exceptinverylimitedcircumstances,suchascongestedorbuilt-upareas,whereundergroundcable(UGC)used.
2.3 Transmission System PlanningThemaindeterminantsintransmissionsystemplanningare:
• Thedemandforelectricityfromconsumers;
• Additionalgenerationfromnewgenerators,comprisingbothconventionalgenerationandrenewablegeneration;
• Potentialmajordemandcentres,i.e.NSSgatewaysandhubs;
• Interconnectionandpotentialimportandexportofenergy.
Theseareaddressedinthefollowingsub-sections.
2.3.1 Electricity demand
Inmanycases,growthindemandforelectricityresultsinhigherpowerflowsonthetransmissionnetwork.Awellestablishedrelationshipexistsbetweeneconomicgrowthandelectricityconsumption.WherepowerflowsexceedthecapabilityoftheGrid,reinforcementisnecessary.Grid25isastrategydesignedtomeetincreasinganticipateddemandforelectricity.
InthecontextoftheGovernmentcommitmentfor40%ofNationalelectricitysupplyfromrenewablesourcesby2020,andtheclearpotentialforlonger-termfutureexportofenergy,EirGridisadoptingamoreproactiveapproachtothestrategicplanningofthetransmissionnetwork,wherebytransmissioninfrastructureisplannedandprioritisedinanticipationofforecastedlonger-termfuturelevelsofimport,exportandgenerationdemand.Thisstrategicapproachiscrucial,giventherelativelylonglead-intimesforsuchinfrastructuredevelopment–includingprojectidentification,studyandassessment,planningandconsenting,constructionandenergisation.ThisiswhytheGrid25strategyisbeingactivelypursuedinthecontextofashort-termeconomicdecline.
Section 2 - The Grid Development Strategy
10
Figure 2.1 Map of the Irish Transmission System as at December 2010 (extract from EirGrid Transmission Development Plan 2010)
11
2.3.2 Generation
Asnotedabove,generationfromrenewableenergysourcesisakeyfactorinGrid25tomeetingtheGovernmenttargetof40%by2020,toreducingcarbonemissions,andtomaintainingasustainableenergysupply.Itisrecognisedinthe2007GovernmentEnergyWhitePaperthatwindenergywillplayapivotalcontributiontomeetingthatgoal.Marinetechnologiesandbiomassarealsoexpectedtocontribute.
Ingeneral,additionofgenerationoutputcreatesamuchgreaterandimmediateimpactonthegridthandemandincreases,duetothesizeofagenerator,orcumulativesizeofclusteredgenerators,relativetothemoregradualincreasesinlocaldemand.Thegridoftenhastobereinforcedtofacilitatetheflowofpowerfromthegeneratortotherestofthesystem.Thisisparticularlyapparentinrespectofnon-traditionalmodesofgeneration,suchasrenewables,wheremanyofthelocationssuitableforrenewableenergygenerationschemesareinareaswheretherehas,historically,beenlittleornogenerationdevelopmentandassociatedprovisionofsupportingtransmissioninfrastructure.
Theaggregateofrenewablegenerationcapacityinsomeareasisequivalenttothatofalargeconventionalgenerationstation.Inmanycases,theexistingtransmissionnetworkisofinsufficientcapacitytocarrythepowerfromthesegenerationsources.Significantreinforcementandnewbuildofthegridisthereforerequiredtocaterforthenewpowerflowsfromrenewablegeneration.
Inshort,itwillnotbepossibletoutiliseIreland’snaturalresourcesofrenewableenergywithouttheassociatedessentialupgradingandreinforcementoftheNationalelectricitytransmissionnetwork,asoutlinedinGrid25.
2.3.3 Potential major demand centres
Asnotedabove,some58%ofcurrentdemandforelectricityisingatewaycitiesandtowns,asidentifiedintheNationalSpatialStrategy(NSS).TheNSSdefinesgatewaysashavingastrategiclocation,nationallyandrelativetotheirsurroundingareasandprovidingnational-scalesocialandeconomicinfrastructureandsupportservices.TheGrid25strategyendorsestheNSSgoalofdevelopinggatewaysandachievingbalancedregionaldevelopment.
2.3.4 Interconnection
TheprimarybenefitsofInterconnectionare:
• Improvingcompetition–bylinkingtootherEuropeanmarkets;
• Supportingdevelopmentofrenewablepowergeneration–byenhancingtheflexibleexchangeofpowerflowsovertheislandofIreland.Thiswillenabletheconnectionandoperationoflargervolumesofrenewablegeneration(especiallywindpoweredgeneration)throughouttheisland;
• Improvingsecurityofsupply–byprovidingadependablehighcapacitylinkbetweenthetransmissionsystemsofIrelandandothercountries.
TheexistingMoyleInterconnectorconnectstheelectricitygridsofNorthernIrelandandScotland.Ithasacapacityof500MWandcurrentlyiscapableofimporting450MWinwinterand400MWinsummerfromScotland.However,thisInterconnectorislimitedbycontractualarrangementstoanexportcapacitytoScotlandof80MW.Thisrestrictionisbeingreviewedatthemoment,anditisthereforeassumedforthepurposesofthisImplementationProgrammethatexportcapabilityisincreasedto400MW.
12
EirGridiscurrentlydevelopingthe500MWEastWestInterconnectorbetweenIrelandandWales.Thishasascheduledcompletiondateof2012.
ItisthereforeassumedthattheislandofIrelandwillhavesome900MWofinterconnectionwiththeUnitedKingdomwithinthenextnumberofyears.
EirGridandNorthernIrelandElectricity(NIE)arecurrentlyprogressingtheplanningofasecondmajorinterconnectorbetweentheRepublicofIrelandandNorthernIreland.These,andotherpotentiallonger-termfutureinterconnectors,couldplayasignificantroleininternationalisingtheIrishenergymarket,andinfacilitatingtheanticipatedhighlevelsofrenewablegenerationontheisland,byprovidingameanstoexportexcessgenerationwhenoutputfromrenewablegenerationishigh,andtoimportpowerwhenitislow.
2.3.5 Planning, environmental and community considerations
EirGridiscommittedtoensuringthattheplanninganddevelopmentofthetransmissionnetworkoccursinaccordancewithallrelevantlegislation
andinternationalbestpractice.Recentchangesinlegislation(especiallytheHabitatsDirective),coupledwiththeexperienceofpublicconcernregardingtheperceivedeffectsoftransmissiondevelopments,particularlyasarticulatedinthepublicplanningprocessthroughwhichstrategicinfrastructurenowproceeds,meansthatenergyplanningmustnowdemonstrateconsideration,fromtheoutset,ofhowtoavoidorreduceenvironmentalandcommunityimpacts.
EirGridtakestheviewthatitwillnotbepossibletodevelopthetransmissionnetwork–andtherebytorealisethepotentialofthecountry’snaturalresourcesofrenewableenergy–withoutputtingplanning,environmentalandcommunityconsiderationsattheheartofitsTransmissionSystemPlanning.Ignoringtheseissueswilldelayorpreventthefuturedevelopmentofthetransmissionnetwork–resultinginincreasedcostsandreducedefficiencies.AssetoutinmoredetailinChapter3ofthisIP,EirGridappliesabestpracticeapproachtotheplanninganddevelopmentofalltransmissionprojects.
13
2.4 Future Grid Requirements2.4.1 Onshore grid
The220kVnetworkwasfirstintroducedintheearly1960sinIreland,andthe400kVnetworkwasbuiltinthemid-1980s.Sincethistime,thisbulkpowernetworkhaschangedlittlewhiledemandoverthesameperiodhasgrownbyover150%,therebyleavinglittlecapacityforfurthergrowthontheexistingnetwork.Anticipatedincreasingpowerflowsonthenetworkmeansthatbetweennowand2025,thecapacityofthebulktransmissionsystemwillneedtobesignificantlyincreased.Theassociated110kVnetwork,whichprimarilybringspowerfromthebulknetworkstobulksupplypointsservingpopulationcentres,alsoneedstobesubstantiallyupgraded.
Grid25seekstoachieveabalancebetweencostsandtheimpactofnewtransmissioninfrastructure,throughmaximisingthecapabilityoftheexistinggridand,wherenewhighcapacityinfrastructureisrequired,buildingitmainlyatthe400kVvoltage.Thefollowingestimateshavebeenmaderegardingtheprovisionofinfrastructurerequiredtostrengthen
theNationaltransmissionnetwork,inaccordancewithGrid25(refertoFigure2.1):
• Grid25statesthatinrespecttofuturegridrequirementsthatapproximately1,150kmofnewcircuitswillberequiredupto2025tomeettheneedsofconsumersandgenerators.Thisrepresentsanincreaseofabout20%onthetotallengthoftheexistingnetwork.Ofthis,800kmwillneedtobeat220kVorhigher;theremaining350kmwillbeat110kV.Inadditiontothesecircuits,othercircuitswillbeneededtoconnectmanyofthenewgeneratorstothegrid;
• Some2,300kmoftheexistingtransmissionnetworkwillneedtobeupgradedby2025toprovidegreatercapacity.Thiscomprises1,100km,or70%,oftheexisting220kVnetwork,and1,200kmofthe110kVnetwork.
ItshouldbenotedthatthesefiguresmaybesubjecttochangeovertheperiodofGrid25,inresponsetochangingdemandandothercircumstances.
Figure2.2,extractedfromEirGrid’sTransmissionDevelopmentPlan2010,identifiesareasofchange,drivingplannednetworkdevelopment.
TheEirGridNationalControlCentre,Dublin
14
Figure 2.2 Network Map Showing Areas of Change Driving Network Development (extract from EirGrid Transmission Development Plan 2010)
15
2.4.2 Offshore grid
AnumberofscenariosforfutureelectricalgenerationandtransmissioninIrelandinvolvethedevelopmentofoffshoregridinfrastructure.ThishasthepotentialtooccurinmanyareasofftheIrishcoast,onaccountofdevelopmentsincludingtheexploitationofoffshorerenewableresources(wind,waveandtidal),increasedinterconnectionwithotherEUMemberStates,andtheparticipationofIrelandinaPan-Europeanoffshoregrid.Thishaspotentiallysignificantimplicationsforgriddevelopmentandforinteractionswithterrestrialandinshoreenvironments.
2.5 The Grid Development StrategyGrid25isaimedatdeliveringanefficientandhigh-qualityNationalelectricitytransmissionnetwork.Itwillensurethenecessarycapacitytoreliablytransportfutureanticipatedpowerlevelsfromrenewableandconventionalgeneratorsandinterconnectorstothecities,towns,villages,homes,andotherkeymarketswherethepowerisrequired.
TheNationalelectricaltransmissionnetworkisadynamicandmeshedsystemthatisconstantlysubjecttochange,andwherethechangeofasinglevariablehasthepotentialtochangethesystematlarge.Thismakesfuturepredictionsacomplexanddynamicprocess,whicharelikelytochangeovertimeasdemand,generationflows,andgridcapacityfluctuateandchange.
Figure2.3,andsubsequentFigures2.4-2.10,havebeenextractedfromEirGrid’sTransmissionDevelopmentPlan2010,andprovideahigh-levelindicativeoverview,andregionalbreakdown,ofthegeneralstrategyforthefuturedevelopmentofthegrid,aspertheprovisionsofGrid25.Thearrowscolouredgreenonthesefiguresprovideanindicativerepresentationofthestrategyfortransmissionofthepotentialflowofelectricity(betweendemand/loadcentres,generatorsandthesystematlarge).
Itshouldbenotedthatthesefiguresderivefromanun-scaledmapwithindicativerepresentation.Assuch,thesearrowsrepresenttheoverallintendeddevelopmentstrategy,anddonotpurporttorepresentspecificprojects;norisitintendedtosuggestthattheeventualrealisationoftheseprojectswillbecontainedwithintheareaofthesearrows.
Mostoftheelectricitytransmissionnetworkiscurrentlyperformingwithinrequiredstandards.Someareashavebeenidentifiedaslikelytorequirenetworkreinforcement,asdemandincreasesand/ornewgenerationisconnected.ThenetworkreinforcementprojectswithinthisImplementationProgramme(andwithinEirGrid’sTransmissionDevelopmentPlan2010),havebeendesignedtodealwiththeseemergingchallenges.
Becauseofthemeshednatureofthenetwork,theidentifiedstrategicdevelopmentsarelikelytobenefitawiderareathantheactualscopeofaparticularreinforcementproject.
Detailedstudiesarebeingcarriedouttoidentifynetworksolutionswhichwillbebroughtforwardintheplanningprocessandultimatelytoconstruction.SuchsolutionsareultimatelyidentifiedasprojectsinEirGrid’sTransmissionDevelopmentPlan2010followingreceiptofinternalCapitalApproval.Thekeyareasforplanned,andlonger-term,strategicgridnetworkdevelopmentasoutlinedinGrid25arepresentedonaregionalbasisbelow.
16
Figure 2.3 Map Indicating Future Network Development Requirements (extract from EirGrid Transmission Development Plan 2010)
17
2.5.1 Reinforcement of the transmission system in the
BORDER REGION
ThereareanumberofissuesthatneedtobeaddressedforthestrategicdevelopmentoftheelectricitytransmissioninfrastructureintheBorderRegionoftheRepublicofIreland.Theseissuesarisedueto:
• Thesignificantextentofnewgeneration,inparticulargenerationfromrenewablesources,thatisexpectedtomaterialisethroughoutboththeBorderRegionitself,andtheWestRegion;
• TherequirementtooptimallyintegraterenewablegenerationintheBorderRegionandNorthernIreland;
• Securityofsupplyintheregion.
Figure2.4providesanindicativestrategicrepresentationofareasrequiringfuturenetworkdevelopmentwithintheBorderRegion.
AsubstantialnumberofnewelectricitygeneratorsareintendingtolocateintheBorderRegion,particularlyinCountiesDonegalandSligo,andinNorthernIreland,eachofwhichwillrequireconnectiontotheelectricitytransmissiongrid.Thesemainlycompriserenewablegenerationsourcessuchaswindfarms.Theelectricity
transmissioninfrastructurewillrequiretobesignificantlystrengthenedtofacilitatesuchconnection,whichwillresultintherequirementbothtoupgradeexistinginfrastructureandtoconstructnewhighvoltageelectricitytransmissioninfrastructure.Thiswillhavethebenefitofstrengtheningtheoverallmeshedgrid,thusprovidingamoresecureandreliablesystemforinwardinvestment,aswellasfacilitatingthetransmissionofenergygeneratedtoloadcentresthroughouttheregionandthecountry.
EirGridiscurrentlyworkingwiththeelectricitynetworkoperatorandownerinNorthernIrelandtoidentifytheoptimalsolutionforthenetworktocaterforrenewablegenerationintheNorth-Westoftheisland(i.e.DonegalandthewesternpartofNorthernIreland).
ThesubstantialnumberofnewgenerationconnectionsbeingsoughtintheWestRegion(Section2.5.4)mayalsohaveanimpactontheBorderRegion.Furtherinter-regionaltransmissionreinforcementwillberequiredtoensurethatthisgenerationisadequatelyconnectedtotheNationalnetwork.
TheplannedsecondmajorinterconnectorbetweentheRepublicandNorthernIrelandisrequiredtoimprovecompetitionbyreducingtransmissionconstraintsthatarecurrentlyrestrictingtheefficient
TheCOntrolRoomatSONI,Belfast
18
performanceoftheall-islandSingleElectricityMarket,tosupportthedevelopmentofgenerationfromrenewableenergysources,andtoimprovesecurityofsupplyontheisland.
Longer-termforecastedgrowthindemandforelectricityintheBorderRegion,asoutlinedinGrid25,willplacepressureonthetransmissionnetwork,requiringitsupgradingtoensurecontinuedsecurityofsupplytolocalhomesandbusinesses
intheRegion.StrengtheningofcircuitsbetweentheNorth-WestandNorth-Eastregionswillberequiredinthelonger-termtofacilitatepowerflows,including:
• FurtherintegrationoftheDonegalandNorthernIrelandnetworks;
• UpgradednetworkssupplyingDundalk;
• Upgradingoftheexistingtransmissionnetwork.
Figure 2.4 Areas Requiring Future Network Development In The Border Region
19
2.5.2 Reinforcement of the transmission system in the
MIDLANDS REGION
ThetransmissionreinforcementprojectsintheMidlandsregionare,intheshort-term,drivenbytheneedtoincreasethesecurityandqualityofsupplytokeypartsofthenetwork.Thisisthecasewiththeconstructionofnew110kVcircuitsbetweenThornsberryandCushaling,andthereinforcementoftransmissioninfrastructureintheMullingararea.
A400/110kVsubstationisrequiredintheLaoisareatosupportthe110kVnetworksandprovidetherequisitelevelofsecurityofsupplyinLaois,CarlowandKilkenny.
AshighlightedinGrid25,longer-termreinforcementsareassociatedwiththetransmissionofwindgenerationthatwillassistinmeetingthegovernmentcommitmentofproviding40%oftheRepublicofIreland’selectricitydemandfromrenewablesourcesby2020.Thisincludesupgradingthetransmissionnetworktofacilitatepowerflowsfrombothrenewableandconventionalsourcesandmaximisetheuseofexistingpowercorridors.
Figure 2.5 Areas Requiring Future Network Development In The Midlands Region
20
21
2.5.3 Reinforcement of the transmission system in the
SOUTH-EAST REGION
Thereareanumberofissuesthatneedtobeaddressedregardingthelong-termstrategicdevelopmentofthetransmissioninfrastructureintheSouth-EastregionoftheRepublicofIreland.Theseissuesarisedueto:
• Generaldemandgrowth,particularlyintheGreaterDublinArea;
• NewgenerationconnectionswithintheSouth-Eastregion;
• ThepotentialforadditionaltransmissioninterconnectionwithGreatBritainandmainlandEuropebasedintheregion;and
• Thesignificantamountofwindgenerationexpectedtomaterialisethroughoutthecountry,particularlyintheSouthofthecountry.
Theexistingtransmissioninfrastructureisexpectedtocomeunderstrainbothatalocalandataregionallevel:Atalocallevel,demandgrowth(despitecurrentreductionsinload)placespressureonthetransmissioninfrastructure,requiringlocalreinforcement.Thereisalsoaneedtointegrate
newgenerationthatisplannedtoconnecttothenetwork.Ataregionallevel,alargeamountofwindgenerationisplannedtoconnectintheSouthofthecountryandwouldresultinanincreaseintheamountofenergythatwouldrequiretotraversetheSouth-Eastregion.Inordertofacilitatethesepowerflows,transmissionreinforcementwillberequired,(seeFigure2.6)asoutlinedinGrid25.
ThereisapotentialforfurtherinterconnectiontobeconstructedbetweentheRepublicofIrelandandUnitedKingdomand/ormainlandEurope.Givenitsgeographicallocation,theSouth-Eastregionisconsideredtoconstitutealikelyareaforterminationofafutureinterconnector.
Longer-termreinforcementintheregionincludes:
• StrengtheningofthehighvoltagetransmissionlinkstobothDublinandCorktofacilitateincreasedpowerflows;
• StrengtheningofthenetworkssupplyingmajorcitiesandtownsintheSouth-Eastregion;
• Reinforcementofcurrentinfrastructurewhilemaximisingtheuseofexistingcorridorswherepossible,throughup-ratingtheexisting110kVand220kVcircuits.
22
Figure 2.6 Areas Requiring Future Network Development In The South-East Region
23
2.5.4 Reinforcement of the transmission system in the
WEST REGION
Theissuesthatneedtobeaddressedinthelong-termstrategicdevelopmentoftheelectricitytransmissioninfrastructureoftheWestRegionincludethefollowing:
• Thesignificantquantityofgeneration,inparticulargenerationfromrenewablesources,thatisexpectedtomaterialiseintheWestRegion;
• Generaldemandgrowthinthearea.
AsubstantialnumberofnewelectricitygeneratorsareproposingtolocateintheWestRegion,andeachrequirestobeconnectedtotheelectricitygrid.Thesegeneratorscomprisemainlyrenewablegenerationsourcessuchaswindfarms,biomassplantsandmarine-basedgenerationtechnologies.Thiswillresultintherequirementtobuildnewhighvoltageelectricitytransmissioninfrastructureintheregion,whichwillhavethebenefitofstrengtheningtheexistingtransmissioninfrastructure,thusprovidingamoresecureandreliablesystemforinwardinvestmentaswellasdistributingtheenergygeneratedtoloadcentresthroughouttheregionandthecountry.
ThemainnewcorridorsintheWestRegioncomprise:
• NewelectricityinfrastructurewhichwillberequiredfromtheNorthMayoarea,initiallytowardsexistinggridinfrastructurelocatedineithertheeastorsouthpartoftheWestRegion.Itislikelythatsuchinfrastructurewillthencontinuetothekeymarketsontheeasternsideofthecountry.
• NewelectricitytransmissioninfrastructurewhichwillalsoberequiredfromwestCo.GalwaytoGalwaycityandbeyond.
Theconnectionofthesenewgeneratorswillalsoresultinanassociatedrequirementtoupgrademanypartsoftheexistingtransmissionnetwork.
Grid25statesthatgenerallonger-termforecasteddemandgrowthintheregionwillalsoresultintherequirementtoupgradetheexistingnetwork,andtobuildnewtransmissionlines.Thisincludes:
• MajorinfrastructuraldevelopmentfromMayotothemainbulktransmissionsystemintheeasternpartoftheregion;
• Upgradingtheexistingtransmissionnetwork.
Figure 2.7 Areas Requiring Future Network Development In The West Region
24
2.5.5 Reinforcement of the transmission system in the
MID-WEST REGION
ReinforcementofthetransmissionsystembetweenMoneypointandTarbert,includingtheprovisionofanewsubstationtothewestoftheexistingTarbertsubstation,andtheongoingdevelopmentofMoneypointasakeytransmissionhub,isrequiredtofacilitatepowerflowsinthemid-westandsouth-westofthecountry.Thisreinforcementisrequiredtoenablerenewableandconventionalgenerationto
betransmittedtotheloadcentres,thusprovidingincreasedsecurityandavailabilityforconsumers.
Suchreinforcementgivesflexibilityformeetingthepowerrequirementsoftheregion.
Longer-termdevelopmentincludes:
• StrengtheningthetransmissioncapacityacrosstheShannonEstuary;
• UpgradednetworkssupplyingtheurbancentresofEnnisandLimerick;
• Up-ratingexistingnetworkstofacilitatehighercapacitypowerflows,usingexistingcorridorswherepossible.
Figure 2.8 Areas Requiring Future Network Development In The Mid-West Region
25
2.5.6 Reinforcement of the transmission system in the
SOUTH-WEST REGION
Thereareanumberofissueswhichneedtobetakenintoaccountwhenplanningforthelong-termstrategicdevelopmentoftheelectricitytransmissioninfrastructureoftheSouth-Westregion.Theseinclude:
• Thesignificantamountofgeneration,inparticulargenerationfromrenewablesources,thatisexpectedtomaterialisethroughouttheSouth-Westregion;
• Generaldemandgrowthinthearea.
TheSouth-Westregionhasseenahighlevelofrenewablegenerationandconventionalgenerationseekingtoconnecttotheelectricitynetwork,asoutlinedinGrid25.Thiswillresultintherequirementtobuildsignificantnewhighvoltageelectricitytransmissioninfrastructureintheregion,includingnewsubstationsconnectingtokeytransmission
hubsinMoneypointandCork.Thiswillhavethebenefitofstrengtheningtheexistingtransmissioninfrastructure,thusprovidingamoresecureandreliablesystemforinwardinvestment,aswellastransmittingtheenergygeneratedtoloadcentresthroughouttheregionandthecountry.
GrowthindemandforelectricityintheSouth-Westregionneedstobefacilitated,andthismayleadtotherequirementtoconstructnewelectricitytransmissioninfrastructure.Thiswillensurethattheregionhastheappropriatetransmissioninfrastructuretoenableittoattractnewindustryandallowexistingindustrytoexpand.
Longer-termforecasteddevelopmentintheRegionincludes:
• SignificantstrengtheningofcapacitybetweentheSouth-WestandSouth-Eastregionstoallowexcesspowertoflowfrombothrenewableandconventionalsourcestosupplydemandinotherpartsofthecountry;
• Upgradingoftransmissionnetwork.
26
Figure 2.9 Areas Requiring Future Network Development In The South-West Region
27
2.5.7 Reinforcement of the transmission system in the
DUBLIN AND MID-EAST REGIONS
Itisperhapsunsurprising,givenitsrelativelyhighdensityofresidentialandemploymentpopulations,thattheGreaterDublinArea(formedbytheDublinandMid-EastRegions)isthemostsignificantelectricitydemandcentreinthecountry.Assuch,alargeconcentrationoftransmissionlinesarelocatedintheareawhichincludes110kV,220kVand400kVlinesandstations.
TheDublin220kVsystemcurrentlyconsistsofaringoffourprimaryBulkSupplyPoints,comprisingthehubsofCarrickmines,Finglas,InchicoreandPoolbeg220/110kVstations.Planneddevelopmentincludesadditional220kVBulkSupplyPointsatFinnstown(nearAdamstown),andintheDublinNorthCityFringearea.OtherplanneddevelopmentincludesincreasedtransformercapacityatCarrickmines,FinglasandInchicorestations.EirGridandESBNetworks(theDistributionSystemOperator-DSO)areworkingtogethertoprovideadditionaltransformercapacityatCarrickminesandInchicore220kVstations.
InrelationtotheDublinnetworks,EirGridinconjunctionwithESBnetworkshasidentifiedtheneedforthetwonew220/110kVin-feedstationsinthenorthandwestofDublin.Newstationsareplannedinthenorthandwestcityareas,toaccommodatedemandgrowth,andtobettermanageexistingdemandlevelshighlightedinGrid25.
Itislikelythatsomereconfigurationand/orreinforcementofthe220kVandthe110kVnetworkswillberequiredinthelonger-termtomeetDSOdemands,andtoavoidnetworkconstraintsintheDublinarea.
The400kVnetworkprovidesahighcapacitylinkbetweenMoneypointgenerationstationandGalwayonthewestcoastandDublinontheeast.EirGridalsoisconsideringtheneedforandoptionstoexpandits400kVnetworkintheGreaterDublinArea.Thiscouldbebythealterationofexistingroutesorequipmentorwithentirelynewoverheadlineorundergroundcableroutes.Additionaltransformercapacityisplannedatthetwoexisting400kVstations–atWoodlandnearDunshaughlin,Co.Meath,andatDunstown,Co.Kildare.
Longer-termdevelopmentintheRegionincludes:
• StrengtheningofnetworkintoandoutoftheRegiontoallowthedemandtobemetbyrenewablegeneratorslocatedmainlyinthewestofthecountry;
• StrengtheningofnetworkservingDublincityload;
• Developmenttoallownorth-southflowstoby-passthenetworkservingtheDublinload;
• ReinforcementofthenetworktocaterforstronggrowthinKildareandnorthWicklow;
• Upgradingoftheexistingnetwork.
28
Figure 2.10 Areas Requiring Future Network Development In The Dublin And Mid-East Region
29
3.1 Context UndertheprovisionsofthePlanningandDevelopmentActs2000–2010,themajorelectricitytransmissioninfrastructuredevelopmentbeingcarriedoutbyEirGridnowgenerallycomprisesstrategicinfrastructuredevelopment,asdefinedundertheActs,requiringanapplicationforStatutoryApprovaltobemadedirectlytoAnBordPleanála.
Assuch,thesecomplexdevelopmentsnowoccurwithinthevehicleofthepublicplanningprocess,wherethefocusisonmattersofproperplanningandsustainabledevelopment,andwherepublicparticipationisakeypillaroftheprocess.
Combinedwiththis,thereisnowasignificantemphasisandfocusontheenvironmentalimpactofalldevelopmentprojects,primarilyinreferencetotheEUHabitatsDirective,whichgivesappropriateprotectiontositesandspeciesofdesignatedinternationalimportance.
EirGridhasrespondedproactivelytothisnewregimeintermsoftheplanninganddevelopmentofelectricitytransmissioninfrastructure.Thishasprimarilyoccurredbyshiftingthemanagementandstructureofprojectdevelopmenttowardsaplanningandenvironmentalcontext.
3.2 Governance and ProcessEirGridhasinstitutedanewinternalsectionforthegovernanceoftheGrid25Programme.Inadditiontocoveringmattersofadministrative,financialandcorporategovernance,theProgrammeManagementOffice(PMO)includesexperiencedexpertsintheareasofecology,publicplanning,wayleavingandlandownerengagement,andprojectcommunications.TheseexpertsareassignedtoallEirGridprojects,toadviseandassistprojectmanagersandtheirprojectteamswiththeplanninganddevelopmentofallEirGridprojects.
InordertoensurethattheplanninganddevelopmentofallEirGridprojectsoccursinaconsistentandtransparentmanner,andwithappropriateemphasisonplanning,environmental,andcommunityissues,thePMOhasdevelopedaprocess(knownasaProjectDevelopmentandConsultationRoadmap)whichisappliedtoalllargescaleprojects.Theprocessissetoutinaseriesofstageswhichprogressfromthebroadestearlystageofinformationgatheringtothedetailedpre-applicationstageofsiting,environmentalassessmentandpreparationoftheplanningapplication.TheRoadmapalsoincludesthepost-consentconstructionphase.
TheemphasisoftheRoadmapisthatplanning,environmentalandcommunityissuesareidentifiedfromtheearlieststageofaproject.Theearlyidentificationofsuchissuesmeansthatconsiderationisgivenattheoutsettotheavoidanceofconstraints,ratherthanlatermitigationofimpactsarising.Thus,inthefirststageofinformationgatheringinrespectofaproject,astudyareaisidentified,environmentalandotherconstraintswithinthatstudyareaareidentified,andtheprojectissitedorroutedwiththeemphasisonavoidingthoseidentifiedconstraints.Allissues,decisionsandsolutionsaresubjecttoastructuredproject-specificstrategyofpublicandstakeholderconsultation,withfeedbackincorporatedintotheongoingprogressandplanningoftheproject.
AsummarygraphicoftheProjectDevelopmentandConsultationRoadmapissetoutinFigure3.1.TheeventualprojectsubmittedforStatutoryApprovalwillthereforehavebeensubjecttodetailedenvironmentalandotherassessment,withaclearstatementofalternativesconsidered,andappropriatelycommunicatedtothepublic,landownersandotherstakeholders,includingAnBordPleanálaastheStatutoryCompetentAuthority.
Section 3 - Towards a Planning and Environmental-led Approach to Electricity Transmission Infrastructure Development
30
Figure 3.1 EirGrid’s Project Development and Consultation Roadmap
31
3.3 Environmental Data and GuidelinesEirGridhascommittedsignificantresourcestogatheringenvironmentaldataandinformationwhichwillinformdecisionsforprojectdevelopment.ResponsibilityforthedeliveryandinterpretationofthisinformationrestsgenerallywiththeConsultantEcologistofthePMO,andthereforecanbemostappropriatelyandeffectivelydisseminatedtotheprojectteamswithinEirGrid,aspartoftheProjectDevelopmentandConsultationRoadmapprocess.Suchdataandguidelinesincludesthefollowing:
• TheStrategicEnvironmentalAssessment(SEA)–comprisinganEnvironmentalReport&NaturaImpactStatement–whichhasinformedthisIP;
• StrategicEnvironmentalConstraintsMapping,whichusesaGISdatabasetomapdesignatedenvironmentalandothersensitivesitesandareas–thismappinghasbeenusedtoinformtheSEA;
• EirGridisinthefinalstagesofcompletingEcologyGuidelinestoinformthedevelopmentoftransmissioninfrastructure;
• ThePMOissuesinternalPracticeNotesforprojectmanagersrelatingtoplanningandenvironmentalissues,includingonthescreeningandscopingofEnvironmentalImpactStatements,andAppropriateAssessment;
• EirGridhascommencedthepreparationofEvidence-BasedEnvironmentalStudiestodeterminetheactualeffectoftheconstructionandexistenceoftransmissioninfrastructureprojectsontheirreceivingenvironment.ThesestudieswillbothinformEirGrid
andallstakeholdersastotheactualenvironmentalimpactoftransmissionprojects,butalsowillidentifynecessaryorappropriatemodificationstocurrentdesignandpracticewhichwillhavealowerenvironmentalimpact.ThisisaddressedinmoredetailinChapter5ofthisIP,andinSection9oftheaccompanyingSEAEnvironmentalReport.
Thesedataandguidelines,combinedwithEirGrid’sinternalgovernanceprocesses,andinparticularitsProjectDevelopmentandConsultationRoadmap,servetoplaceplanningandenvironmentalmattersattheheartofallEirGrid’sdecision-makingrelatingtotheplanninganddevelopmentoftransmissioninfrastructure,fromthestrategicpolicyleveltothemoredetailedproject-specificlevel.
ThisapproachissetoutgraphicallyinFigure3.2,whichsetsEirGrid’sprocessesintotheirwidercontextofinternalenvironmentalprocesses,aswellasexternalpolicycontext.Itshouldbenotedthat,whilsteachlevelofEirGrid’sprocessissetinaparticularpolicycontext,themoredetailedprocesslevelswillalwayshaveregardtothehigher-levelpolicycontextandprocesses.
Thus,forexample,anyproposeddevelopmentwillbesetintothegoverningcontextoflocal,county,regional,andNationalstrategicandstatutoryplansandstrategies,aswellastheover-ridingpolicyoftheEnergyWhitePaper.Equally,theprojectwillbesubjectbothtotheproject-specificstatutoryEIAandAAprocesses,aswellashavingregardtothehigher-levelSEA.
Constructiononthetransmissiongrid
32
Figure 3.2 EirGrid’s Strategic Decision Making Process (illustrating integration of environmental consideration at each level)
Policy
Programme
Plan
Project
EirGrid Process
Grid25 Implementation Programme
Master Plan
Scheme Development
Scheme Design & Permitting
Grid25
Policy Context
White Paper
National Plans & Strategies
Regional Guidelines & Strategies
County Development Plans & Strategies
County/ Local Development Plans & Strategies
Environmental Process
Strategic Environmental Assessment & Appropriate
Assessment
Screening for SEA & AA
Strategic Environmental Framework & Technical
Guidance
Screening for EIA & AA
33
34
3.4 Procedures for Transmission System Planning
Inthecontextoftheseprocessesandgovernance,theproceduresforTransmissionSystemPlanningtotakeaccountofPlanningandEnvironmentalconsiderationsoccurateachstage,asfollows:
AtStrategic Level,(thisIP),procedures,processes,andresources(staffanddata)areputinplace.
AtTechnical Planning Level,arangeofalternativeapproachesareconsidered–theseincludegridconfigurationandmanagement,andre-useofexistingassets,technicalandroutingoptions.EirGridiscurrentlyconsideringthemeritsofcapturingthisintheformofregionalMasterplansforgriddevelopment.TheongoingpreparationoftheseMasterplanswillbesubjecttocontinualenvironmentalscrutinyandassessmentasappropriate,toensurecompliancewiththeSEA.
AtProject Level,oncetheneedandtechnicalconfigurationhasbeendetermined,moredetailedalternativesfortherealisationofthatprojectareconsidered,withaformalconsiderationofallalternatives–usingSEAandEIAtechniques
AtPermitting LeveltheapplicationforconsentissubjecttoformalEIAandthereisformalpublicandagencyconsultation,inreferencetotheProjectDevelopmentandConsultationRoadmapprocess.
Overall,withtheimplementationandongoinggovernanceoftheseprocessesandprocedures,strategicplanningandenvironmentalconsiderationsarenowattheheartofEirGrid’sprojectdevelopmentprocess.Thisisconsideredtobeappropriate,consistentwithbestpracticefortransmissioninfrastructureplanning,andinaccordancewiththeprinciplesofproperplanningandsustainabledevelopment.
35
4.1 Context EirGrid’sTransmissionDevelopmentPlan(TDP)2010,availableonwww.eirgrid.compresentstheplannednetworkdevelopmentprojectsthatEirGridhasprogressedtothepointwheretheyarethepreferredschemetomeetthechangingsystemrequirementsinthecontextofthelong-termdevelopmentofthenetwork.Theseprojectshaveallbeensubjecttoinitialenvironmentalevaluation,primarilyinreferencetostrategicconstraintsmapping,aspertheprocesssetoutinFigure3.1and3.2;anumberoftheseprojectshaveprogressedtothestageatwhichtheirgeneralnature,locationandextentisconfirmed,suchthattheyarecurrentlysubjecttoproject-specificenvironmentalassessment(withAAasappropriate).Inaddition,theseprojectshavebeenconsideredagainsttheGrid25IPSEA.
TheTDP2010identifiesatotalof111projectsthatareinprogress,70ofwhichareinthedetaileddesignandconstructionphase–thesearereproducedintheirentiretyAppendixAofthisIP.AnumberoftransmissionprojectsarecurrentlyintheStatutoryplanningconsentsprocess,orpermittedandunderconstruction.ThesehavenotbeenspecificallyidentifiedinthisImplementationProgramme(althoughtheyareincludedintheprojectslistedinAppendixA),astheyare,orhavebeen,separatelysubjecttospecificenvironmentalandotherassessment,inaccordancewithEirGrid’sprocessesfortheplanninganddevelopmentofprojects,asperitsProjectDevelopmentandConsultationRoadmap,aswellasinaccordancewithStatutoryprocedureandbestpractice.
TheTDP2010presentstheanticipatedtotalsofnewequipmentcurrentlyplanned/atinternalCapitalApprovalstage–thisisreproducedinTable4.1.Theseareestimatesonly,becausethescopesoftransmissionprojects,particularlythoseinthepreliminarystagesofdesign,canchange.
Inaddition,theTDP2010anticipatesthatsome7.7kmof220kV,and575kmof110kVtransmissioncircuitswillhavetheirthermalratingsincreased.2no.220kVtransmissionlinesand2no.110kVtransmissionlineswillberefurbishedwithoutaffectingtheirratings.
Itisimportanttonotethatthevarioustransmissiondevelopmentprojectsareatdifferentphasesoftheirlifetime.ThisIPidentifies26no.networkdevelopmentprojectscontainedwithintheTDP2010thatareatdesignandenvironmentalassessmentstage,andwhichEirGridconsidersarerequiredtomeetchangingsystemrequirementsintheshorttomediumtermdevelopmentofthenetwork,asidentifiedatastrategiclevelinChapter2ofthisIP.
400kV 220kV 110kV
NumberofNewStations 1 9 7
NumberofNewStationBays 8 49 181
OverheadLine,(km) 140 56 313
Underground/UnderseaCable,(km) 0.5 33.5 0
400/ 400/ 220/ 220kV 110kV 110kV
NumberofNewTransformers 2 2 16
NewTransformers,TotalMVA 1,000 500 3,250
110kV
NumberofNewCapacitorBanks 7
CapacitorBanksTotalMvar 135
Table 4.1 Estimates of Identified New Transmission Assets (Table S-1 of EirGrid’s TDP 2010)
Section 4 - Planned Network Developments
36
37
Thetransmissioninfrastructureprojectsoutlinedbelowarecategorisedunderthreesubsectionsrelatingtothemaindriversfortransmissiondevelopment:
• NetworkReinforcements;
• GeneratorConnections;
• DSOConnections.
Becauseoftheuncertaintiesinherentinthepublicplanningprocess,thetimeframeandthescopeofprojectsnotyetintheconstructionphasemaybesubjecttochange.
Tables4.2,4.3,and4.4presentthefollowingprojectinformation:
• CapitalProjectnumber(CPNo.)–eachprojectisreferencedwithaCapitalProjectnumberforco-ordinationbetweenEirGridandtheTransmissionAssetsOwner(TAO-ESBNetworks);
• ProjectTitleandDescription–forprojectsinthePreliminaryDesignstage,theprojectdescriptionsareEirGrid’scurrentbestestimatesandmaybeliabletochange;
• ExpectedCompletionDate(E.C.D.)–theseestimatesaresubjecttotheplanningprocess,theconstructionprogress,availabilityoftransmissionoutages,andcommissioning,andmaybeliabletochange.
• Phase–relatingtothestageofprojectdevelopment.
LinelengthsareapproximateforNetworkReinforcementprojectsthatareinthepreliminarydesignphaseorinpublicplanningprocess.
EirGridandESBNetworks,asTSOandTAOrespectively,arealsoco-ordinatingothercapitalprojectsnotlistedherein,generallycomprisingminorcapitalworks,andlineuprating,diversionsandalterations.
Figures4.1and4.2,extractedfromEirGrid’sTransmissionDevelopmentPlan2010,provideanindicativeoverviewoftheplannednetworkdevelopmentsatOutlineDesignandEIA,orconsentandconstructionstages,asoutlinedintheDraftTDP2010.Thisprovidesanindicativerepresentationofplanneddevelopment,anddoesnotrepresentspecificalignmentsofproposals.
AsnotedinChapter3above,allEirGridprojectsinthepre-planningstagesofprojectdevelopment(notedas“outlinedesignandEIA”inthefollowingtables)aresubjecttotheEIAandAAprocesses;thisinitiallycomprisesascreeningprocess.Whereaprojectiscurrentlyintheplanningprocess,andhasbeenaccompaniedbyanEISandAppropriateAssessment,thisisindicatedinthemorecomprehensivetablesextractedfromEirGrid’sTDP2010,reproducedatAppendixAofthisIP.
38
Figure 4.1 Map Indicating Planned Network Developments in the Detailed Design & Construction Phase (from EirGrid’s Transmission Development Plan 2010)
39
4.2 Network Reinforcement DevelopmentsThisSectiondealswiththeidentifieddevelopmentprojectsthataredrivenbygenericdemandgrowthandreinforcementsresultingfromgeneratordemandandinterconnectorconnections.Table4.2liststhenetworkreinforcementprojectsrelevanttothisImplementationProgramme(asextractedfromEirGrid’sTransmissionDevelopmentPlan2010).
Ofnote,intheTDP2010,theNorth-South400kVInterconnectordevelopmentwasidentifiedasinthepublicplanningprocess.Theapplicationwassubsequentlywithdrawnfromthatplanningprocessandtheprojecthasrevertedtothestatusof‘OutlineDesignandEIA’.However,forconsistency,thestatushasnotbeenalteredinthisIP,whichreflectsthecontentoftheTDP2010.TheprojectislistedinTableA1ofAppendixA.
1 Note EMM = Environmental Mitigation Measure
CP No. Project Title & Description E.C.D Phase
CP0501 Clashavoon-Dunmanway 110 kV New LineConstructionofanew110kVlinefromClashavoontoDunmanwaystationandassociatedstationworks.
Mar-14 OutlineDesignorEIA
CP0580 Carrickmines 220 kV GIS Development Replacementofexistingair-insulatedswitchgearwithgas-insulatedswitchgear(GIS);Installationofanew4th220/110kVtransformer.
Dec-12 OutlineDesignorEIA
CP0585 Laois /Kilkenny ReinforcementNew Station & Associated Lines & Station WorksNew400/110kVtransmissionstationinCo.Laois.ThestationwillbeloopedintotheexistingDunstown-Moneypoint400kVlineandCarlow-Portlaoise110kVline.Anew110kVcircuitfromthenewstationtoKilkennyusingtheexistingBallyragget-Kilkenny38kVlinewhichisbuiltto110kVstandards.Anew110/38kVstationatBallyraggettocaterforlossoftheKilkenny-Ballyragget38kVline.[DetailstobefinalisedwithDSO].
Dec-14 OutlineDesignorEIA
CP0596 New 110kV Circuit To MullingarConstructionofanew110kVcircuittoMullingar110kVstationfromeitherKinnegadorDerryiron110kVstations.
Oct-14 OutlineDesignorEIA
CP0597 Reinforcement of the Ardnacrusha & Ennis AreaUpratingoftheMoneypoint-Tullabrack-Booltiagh-Ennis110kVcircuittoequivalentof430mm2ACSR@80oC.DependentonMoneypoint400/220/110kVGISDevelopment,seeCP0688
Dec-14 OutlineDesignorEIA
CP0674 Tralee 110 kV StationNewCoupler
Aug-12 OutlineDesignorEIA
CP0699 Cathaleen’s Fall - Srananagh 1 110kV Line UprateUpratelinetoequivalentof430mm2ACSR@80oC
Oct-12 OutlineDesignorEIA
CP0709 Dunmanway 110kV Station Upgrade Dec-14 OutlineDesignorEIA
CP0707 Barrymore 110kV station extension - Loop into Cahir - Knockraha 110kV line
Jun-13 OutlineDesignorEIA
CP0619 New Capacitors at ShankillInstallationof15Mvarand30Mvarre-deployablecapacitorunitsatShankill110kVstation
OnHold OutlineDesignorEIA
Table 4.2Network Reinforcement Projects
40
4.3 DSO ConnectionsMostdemandconnectionstothetransmissionsystemaresoughtbyESBNetworks,theDistributionSystemOperator(DSO)whichappliesfornewstationconnections.Table4.3liststhedevelopmentprojectsthatrelatedirectlytotheconnectionofnewTSO/DSOinterfacestationstothegrid,ortochangesinexistingconnectionarrangements.
TheDSOhasfurtherdevelopmentplanswhichareatvariousstagesofpreparation,severalatanadvancedstage.EirGridisco-operatingwiththeDSOontheseexpansionplansinordertobringthemforwardtoprojectinitiationwhenrequired.EirGridwillinitiatethenecessarytransmissionconnectionswhenformalnotificationsfromtheDSOtoproceedarereceived.
CP No. Project Title & Description E.C.D Phase
CP0437a North Dublin 220kV Project - New 220kV Station Anew220kVstationintheNorthDublinWorksareaandassociatednetworks.ThedevelopmentispartofawiderTSO/DSOagreedreinforcementstrategytoenhancethenetworkinthenorthernfringeofDublincity.ThestationwillbetailfedfromFinglas220kVusingcableandconstructedwithGIS.Theprocessofacquisitionofanewsiteforthisprojectiscurrentlyunderway.
Dec-14 OutlineDesignorEIA
CP0506 Finnstown 220kV Project (Adamstown) - New 220kV Station Finnstown220kVstation,southofLucan,anew220kVstationloopedintotheInchicore-MaynoothNo.1andNo.2220kVlines.Thestationwillbeinitiallyasingletransformer220kVstation,butallowfinaldevelopmentforafourtransformerstation.DuetospacerestrictionsonpotentialsitesanentirelyGISstationisproposed.
Mar-14 OutlineDesignorEIA
CP0644 Bracklone 110 kV Station and Loop In New110kVstationtobeloopedintoPortlaoise-Newbridge110kVline.ReplacesexistingPortarlington38kVStation.
Dec-12 OutlineDesignorEIA
CP0649 Drumline 110 kV Station Works Two20MVATransformerssupplying12.2MWNewloadand11.4MWtransferedloadfromexistingDrumlinetransformers.
Jun-13 OutlineDesignorEIA
CP0627 Bandon 110 kV Station NewTransformerBay.
OnHold OutlineDesignorEIA
CP0075 Ballycummin 110 kV New Station NewstationloopedintotheLimerick-Moneteen110kVline.
OnHold OutlineDesignorEIA
Table 4.3DSO Connection Projects
41
4.4 Generator ConnectionsThissectionoutlinesprojectsthatrelatedirectlytoconnectionofgenerationtothetransmissionsystemortochangesinexistinggenerationconnectionarrangements.Someoftheseconnectionsarecontestable,i.e.thegeneratorhasdecidedtobuildtheconnectionassetstoTSOspecifiedstandards.
TheEstimatedCompletionDate(E.C.D.)isEirGrid’scurrentbestestimateofwhenthegeneration
connectionwillbecompleted.ItshouldbenotedthatthisisdependentonprogressbytheapplicantandnotEirGrid.Thedateofcompletionfortheseprojectsisco-ordinatedwiththeIndependentPowerProducer(IPP)programmeofconnection.
Table4.4liststhegeneratorconnectionprojectsrelevanttothisImplementationProgramme(asextractedfromEirGrid’sTransmissionDevelopmentPlan2010).
Table 4.4Generator Connection Projects
CP No. Project Title & Description E.C.D Phase
CP0500 North Kerry Project Anew220kVstationloopedintotheexistingClashavoon-Tarbert220kVline.TheworkincludesconnectionworksforAthea,DromadaandCloghboolawindfarms
Apr-14 OutlineDesignorEIA
CP0603 IPP088 Mulreavy Connection Connectionofanew110kVstationforconnectionofnewwindfarm.
Jan-12 OutlineDesignorEIA
CP0608 IPP119 Cloghboola Wind Farm ConnectionofanewwindfarmintotheexistingTrien110kVstation.
Apr-14 OutlineDesignorEIA
CP0615 Glenree 110kV Station Connectionofanew110kVstation,loopedintotheexistingCunghill-Moy110kVline.ThisstationwillfacilitatetheconnectionofnewDSOwindfarms.
Sep-11 OutlineDesignorEIA
CP0648 Garrow 110 kV Station ExtensionWorksforanew110kVtransformerbayfortheprovisionofrenewableenergy.
Aug-11 OutlineDesignorEIA
CP0650 Millstreet 220/110 kV station New220/110kVstationloopedintotheexistingClashavoon-Tarbert220kVlinefortheconnectionofwindfarms.
Aug-14 OutlineDesignorEIA
CP0651 East Kerry & North West Cork 220 kV Station Anew220kVstationloopedintotheexistingClashavoon-Tarbert220kVlinefortheconnectionofwindfarms.Twonew110kVlineswillbeconstructed,onetoGlenlaraandtheothertotheplannedCordalstationinCo.Kerry.KnockacummerconnectionintoGlenlaraisalsopartofthisproject.
Jan-14 OutlineDesignorEIA
CP0602 IPP044 Keelderry Wind FarmConnectionofanewwindfarmtoanewstation,loopedintotheexistingAgannygal-Derrybrien110kVline.
OnHold OutlineDesignorEIA
CP0641 IPP118NorePowerStationExtensionworksintheexistingKilkennystationfortheconnectionofanewOCGT.
OnHold OutlineDesignorEIA
42
Figure 4.2 Map Indicating Planned Network Developments in the Outline Design Phase and Public Planning Process. Note: All new developments on this map are subject to on-going EIA and AA processes
43
5.1 Introduction Mitigationmeasuresaremeasuresenvisagedtoprevent,reduceand,asfullyaspossible,offsetanysignificantadverseimpactsontheenvironmentofimplementingtheIP.
Mitigationinvolvesamelioratingsignificantnegativeeffects.Wheretherearesignificantnegativeeffects,considerationisgiveninthefirstinstancetopreventingsucheffectsor,wherethisisnotpossibleforstatedreasons,tolesseningoroffsettingthoseeffects.Mitigationmeasurescanberoughlydividedintothosethat:avoideffects;reducethemagnitudeorextent,probabilityand/orseverityofeffects;repaireffectsaftertheyhaveoccurred,and;compensateforeffects,balancingoutnegativeimpactswithotherpositiveones.
Therearetwotypesofmitigationmeasures.Thefirstinvolveshigh-levelpreventativemitigationmeasuresthatwereincorporatedintothedraftingoftheIPdocumentorbybringingaboutchangesinorganisationalandworkingpracticeswithinEirGrid.Theseincludesevenmajorprocedures,identifiedbelowandoutlinedinthesubsequentsectionsofthischapter,whichwillbeemployedtoidentifyandavoidenvironmentaleffects:
EMM 1. FullIntegrationofPlanningand EnvironmentalConsiderationsin TransmissionSystemPlanning;
EMM 2. PreparationofStrategicEnvironmental ConstraintsMapping;
EMM 3. PreparationofEvidence-Based EnvironmentalGuidelines,consistingof:
a) EnvironmentalBenchmarking Studies;
b) Evidence-BasedEnvironmentalDesign Guidelines;and
c) GuidelinesonEIAforTransmission ProjectsinIreland;
EMM 4. ConsiderationoftheBroadestPossible RangeofAlternativesinallfutureEnergy TransmissionStrategies;
EMM 5. PreparationofTransmissionDevelopment PlanEnvironmentalAppraisalReport;
EMM 6. OngoingCo-operationinpreparation ofRenewableEnergyGeneration GuidelinesandStrategies;and,
EMM 7. IntegratingOffshoreGridconnectivity requirementsandenvironmental considerationsinEirGrid’sStrategic EnvironmentalFramework(SEF).
ThesecondtypeofmitigationmeasuresinvolvesthosethataddresstheimplementationoftheIP.TheseareidentifiedinAppendixBofthisreportandhavebeenfullyintegratedintotheIP.Projectteamsshouldrefertotheseinterimgeneralmitigationmeasures.ThesemeasureswillbeextendedandaugmentedbytheoutputfromtheEnvironmentalBenchmarkingStudiesandEvidence-BasedEnvironmentalDesignGuidelinesreferredtoaboveandoutlinedbelow.Itisnotedthattherearelinkagesbetweenvariousmitigationmeasuresandthatthemitigationofcertaineffectswillbecontributedtowardsbymultiplemeasures.
Additional,moredetailedmitigationmeasurestothoseidentifiedbelowwouldbelikelytoberequiredbylowertier,project-specific,environmentalassessmentsandwouldneedtobeintegratedintorelevantspecificplansandprojects.Itshouldbenotedthatmanyoftheidentifiedlowertiermitigationmeasuresareproceduresandprocessesthatwillneedtobeadopted.
ThemitigationmeasuressetoutunderSections5.2to5.8wererecommendedbytheSEAandAAprocessestobeintegratedintoanearlierdraftoftheIP.TheIPpreparationteamtookonboardthisrecommendationandfullyintegratedthemeasuresintoSection5intheIP.ThestatusofimplementingallmitigationmeasuresisdetailedinTable5.1.
Section 5 - Environmental Mitigation Measures
7NoteEMM=EnvironmentalMitigationMeasure
44
Mitigation Measure Code
Mitigation Measure Title Status
EMM1 FullIntegrationofPlanningandEnvironmentalConsiderationsinEirGrid’sTransmissionSystemPlanning
Hasalreadyoccurred;changeswillcontinuetobeimplemented.
EMM2 PreparationofStrategicEnvironmentalConstraintsMapping
Hasalreadyoccurred;willbeupdatedonanongoingbasis,asappropriate,toincludemostup-to-date,relevantenvironmentaldata.
EMM3 PreparationofEvidence-basedEnvironmentalGuidelines
Hasbegun;Guidelinestobepublished.
EMM4 ConsiderationoftheBroadestPossibleRangeofAlternativesinallFutureEnergyTransmissionStrategies
MeasuretobeadheredtoasrelevantonadoptionofIP.
EMM5 PreparationofTransmissionDevelopmentPlanEnvironmentalAppraisalReport
MeasuretobeadheredtoasrelevantonadoptionofIP.
EMM6 OngoingCo-operationinpreparationofRenewableEnergyGenerationGuidelinesandStrategies
MeasuretobeadheredtoasrelevantonadoptionofIP.
EMM7 IntegratingOffshoreGridconnectivityrequirementsandenvironmentalconsiderationsinEirGrid’sStrategicEnvironmentalFramework(SEF)
MeasuretobeadheredtoasrelevantonadoptionofIP.
EMM8(AtoK) OthermeasuresintegratedintotheIP MeasurestobeadheredtofornewprojectsasrelevantandasappropriateonadoptionofIP.
MeasurestobeextendedandaugmentedbytheoutputfromtheEnvironmentalBenchmarkingStudiesandEvidence-BasedEnvironmentalDesignGuidelines
Table 5.1
Status of Implementing Mitigation Measures
45
5.2 EMM1 Full Integration of Planning and Environmental Considerations in EirGrid’s Transmission System PlanningConsiderablechangesofproceduresandpersonnelhavebeenputinplacetoensurethatenvironmentalfactorsareconsideredattheearlieststageofEirGrid’sTransmissionPlanningSystem–asaresultoftheparallelSEAprocess.Thesearepreventativemeasuresaimedatanticipatingstrategicdecisionsthatwouldbelikelytoresultinavoidableadverseenvironmentaleffects.
ThisStrategicEnvironmentalFramework(SEF)hasresultedinfourmajortypesofinterventions:
1. TheEirGridTransmissionSystemplanning procedureshavebeenstrengthenedto incorporateenvironmentalconsiderationsas anearlydeterminant(refertoChapter3of thisIP)andasacriticalstageintheprocess ofdecisionmaking.Thesesystemsarenow operational.
2. EirGridhasestablishedaProgramme ManagementOffice(PMO)andnewpositions ofresponsibilitywithintheorganisationthat provideseniorplanningandecologicaladvice toprojectteams.Appointmentshavebeen madetothesepositions.
3. EirGridisimplementingStrategic EnvironmentalConstraintsMappingthat providesdecision-makersandsystemplanners withhigh-levelenvironmentaldatathatcan beusedfortheconceptualdevelopmentstage ofTransmissionPlanning.
4. Procedurestobefollowedonaproject-by- projectbasisforthedetailedconsideration, weightingandevaluationoflikely environmentaleffects–including cumulativeeffects–havingparticularregard totherequirementsoftheHabitatsDirective8.
Suchproceduresincludetheneedfor timelyconsultationwithrelevantplanning andenvironmentalauthoritiessuchasthe NPWS,theevaluationofup-to-datemapping, designationsanddevelopmentplans,policies, andaconsiderationofanyrelevantsectoral guidelines.
Inaddition,EirGridwillcontinuetoworkpro-activelywiththeDepartmentofArts,HeritageandtheGaeltacht(DAHG)andwithlocalplanningauthoritiesandregionalauthoritiestoidentifycriticalpolicies,objectivesandconstraints-e.g.criticalrivercrossingpoints–inDevelopmentPlansandRegionalPlanningGuidelines,toensurethattheplanninganddevelopmentofnationalstrategictransmissioninfrastructureoccursinthecontextofbestenvironmentalpractice,andinaccordancewiththeprinciplesofproperplanningandsustainabledevelopment.
EirGridwillalsocontinuetoworkalongsideESBNetworks,BordGais,theNationalTransportAuthority,theNationalRoadAuthoritiesandotherkeystrategicbodiesinordertoensurethatsustainabledevelopment,spatialplanningandtransportandgridinfrastructurearepromotedinanintegratedmanner.
8Referencedstatutoryobligation
46
5.3 EMM2 Preparation of Strategic Environmental Constraints MappingTheScopingReportfortheSEAidentifiedtheneedtoputStrategicEnvironmentalConstraintsMappinginplaceinordertoensurethatenvironmentalconsiderationsareincludedattheearlieststageofprojectinceptionandintheconsiderationofalternatives.AstudywascommissionedandcompletedwhileconsultationswerebeingundertakenfortheSEAandtheinformationcontainedintheStudyinformednumeroussectionsofthisSEAEnvironmentalReport.
TheStrategicEnvironmentalConstraintsMappingcomprisesmappingoftheenvironmentalconsiderations–bothconstraintsandopportunities–thatneedtobeincorporatedintostrategicdecisionsaboutprojectsandotherdevelopmentslikelytogiverisetoenvironmentaleffects.Themappingisofsufficientdetailtoprovideanoverviewofthelikelihoodofencounteringenvironmentalchallengeswhenplanningroutesthoughparticularareas–ataregionallevel–andshouldassistinmoredetailedconsiderationofpotentialroutecorridorsandintheselectionofroutingalternatives.Themappingshouldformaframeworkformoredetailedmapping–onaprojectbyprojectbasis–ofsitespecificsensitivitiesforecologyandculturalheritageandforlocaldevelopmentplandesignationsofsceneryandvisualvulnerability.
TheconstraintsmappingwillbecomepartofEirGrid’sStandardOperationalProcedureaspartoftheoverallSEFtowhichdesignersarerequiredtohaveregard.ItishopedthattheconstraintsmappingcanultimatelybeupdatedtoincludeNorthernIrelandandwillbeupdatedperiodicallytoensuretheuseofthemostup-to-date,relevantenvironmentalbaselinedata.
5.4 EMM3 Preparation of Evidence-based Environmental GuidelinesThroughtheSEAscopingprocesstheideaofaseriesofauthoritativestudiesexaminingtheactualeffectsoftheconstructionandexistenceofpowertransmissionprojectsinIrelandwasrecommendedtobepreparedandtheseareintheprocessofbeingcommissioned.
Theseauthoritative,ex post9studieswillprovidebenchmarkstofacilitatethepreparation,presentationanddefenceofpowerprojectsthatwillberobustandwillrigorouslyassesstheimpactsoftransmissionprojectsinIreland.Detailsofthethreetypesofstudiesthatwillmitigateimpactsbyanticipationandavoidanceareasfollows:
1. Environmental Benchmarking Studies
StudieswillbecarriedouttodeterminetheactualeffectoftheconstructionandexistenceofpowerprojectsinarepresentativerangeoftypicalIrishenvironmentalconditions.Thestudieswillfocusontheprincipaltopicsofconcerninenvironmentalimpactassessments–includingecology,visualimpact,andimpactuponhumanbeings.
Thestudieswillexaminetheeffectonatypicalarea,habitatorcircumstancethatiscommonlyencountered–suchaspasturesinthelowlands,blanketbogsortheenvironsofavillage.Theywillexaminetheeffectsoftheconstructionandexistenceofarangeofpowertransmissionprojects–includingsubstationsandarangeofsizesoftransmissionlinesrangingfrom110–400kV.
Studieswilldescribetheeffectofpowerprojectsonspecifictopicsinspecificenvironments–thesewillbecomparedtounaffectedareas,ontheonehand,andtonon-standardand‘worstcase’conditionsontheother,inordertoestablishthefullrangeofconditionsthatcouldarise,asfollows.
9Ex postistheLatinfor“afterthefact”.Inmodelswherethereisuncertaintythatisresolvedduringthecourseofevents,theex postvalues(e.g.ofexpectedgain)arethosethatarecalculatedaftertheuncertaintyhasbeenresolved.
47
Typical Conditions
Ineachcaseanareawillbeidentified–andagreedwithstakeholders–asbeingtypicalofthespecificconditionswherethetransmissionprojecthasinteractedwiththeenvironmentaltopic.Theareaofinteractionwillbescrutinisedandcomparedwithanunaffectedcontrolareatodescribethenature,magnitudeandsignificanceoftheeffectsthathaveoccurred.
InadditiontotheTypicalConditiontherewillalsobeanexaminationoftwootherconditions–Non-standardandWorstCaseconditions–thatcanbeusedtodeterminetheparameterswithinwhichthebenchmarkingoftheenvironmentaleffectscanbedeemedtobereliablypredicted.
Non-standard Conditions
Locationswillbeidentifiedandagreedwithkeystakeholderswhicharetypicalofalandscape,habitatorlandusebutwhichhaveobjectivecircumstancesorfactorsthatincreasethepotentialforenvironmentaleffect–suchassteeperslope,greaterage,differentmanagementregimes.ThesewillbescrutinisedandcomparedwithbothTypicalConditionsandunaffectedcontrolarea,inordertodescribethenature,magnitudeandsignificanceoftheeffectsthathaveoccurred.
Worst Case Condition
Locationswillbeidentifiedandagreedwithstakeholderswhicharetypicalofalandscape,habitatorlanduseinwhichthereisobjectiveevidenceofadverseenvironmentaleffectsduetotheexistence,constructionormaintenanceofthepowerproject.Thenature,magnitudeandsignificanceoftheeffectsthathaveoccurredwillbedescribedandevaluatedtodeterminehowsuchadverseeffectsoccurred,andhowtheymightbeavoidedinfuture.
Lessons Learned
Eachsectionwillincludeasummaryofwhatprojectdesignerscanlearnfromthisanalysisintermsofwhatpracticesappeartogiverisetotheleastandthegreatestenvironmentaleffect.Thisadvicewillbeclearlydifferentiatedintobestpracticetobringabout‘LegalCompliance’,aswellas‘BestPractice’.
Summary Study
AllstudiesforeachsectionofthecountrysidewillbesummarisedintoanoverallrouteselectionandprojectdesignguideforeachcomponentoftheIrishcountryside.Forinstance,therewillbeasectionentitled‘PowerProjectsinWetlands’.Thiswillprovideauthoritativedesignadviceonallaspectsofeachstepofapowerproject–fromrouteselectionthroughtoprojectdesignandcontractimplementation.Usingthis,designerswillbeabletoanticipate,avoidorameliorateadverseeffectsoncommunities,flora,fauna,water,landscapeorculturalheritage.ThisinformationwillbecompiledintoEvidence-Based Design Guidelines for Power Projects in Ireland[seebelow].
On-going Studies
Thestudiesareconceivedasanon-goingbodyofworkthatwillbecontinuouslyupdatedandamendedtotakeaccountofdevelopmentsinunderstanding–arisingfrompracticeorresearch.
48
49
2. Evidence-Based Environmental Design Guidelines
TheprimaryobjectiveisthattheseDesignGuidelineswillprovidepracticalguidanceforhowbesttoincorporateeachtypeofpowerprojectintoeachpartoftheIrishenvironmentinsuchawayastoanticipateandavoidadverseeffectstothegreatestextentpossible.
Thesecondaryobjectiveistoestablishanevidencebasedapproach–acceptedbystakeholders–thatcanbeusedtodemonstratethatanyresidualeffectsareconsistentwith‘bestpractice’.
TheEnvironmentalBenchmarkingStudieswillidentifyevidenceforthetypesofroutes,designs,constructionandmaintenancemethodsthatgiverisetotheleasteffectontheenvironment.ThisknowledgewillbetranslatedbyprojectdesignersintoGuidelinesforrouteplanners,projectdesigners,managersandthoseresponsibleforconstructionandmanagementofpowerassets.
TheDesignGuidelineswilladdresstheissuesthatariseateachofthreestagesofaprojectbeginningattheInitiationstagewhereaprojectisfirstconceived,throughthePlanningStage–whereroutesareselected–finishingwiththeDesignStagewheredetaileddecisionsaretakenabouthowtheprojectwillbebuilt.Theseissuesareconsideredasfollows:
• ProjectInitiationIssues
• PlanningIssues
• DesignIssues
ThereportsfromtheEnvironmental Benchmarking Studieswillbeexaminedtodeterminetherouting,designandconstructionmethodsthatproducethemostenvironmentallysuitableoutcomes.Thesereportswillalsodescribeanddetailevidenceofenvironmentaldegradationthathasoccurredashighlightedinthe‘worstcase’evaluations.TheadvicefromtheLessons Learnedandthe
Summary StudysectionsoftheEnvironmentalBenchmarkingStudieswillbeusedasabasisformostofthismaterial.
Theemphasisthroughoutwillbeonprovidingconcise,practicaladvicefrompractitionerstopractitionersthatwillmaketheoutcomeofmoredetailedstudiesbyspecialistsavailableinanimmediatelyapplicableway.
3. Guidelines on EIA for Transmission Projects in Ireland
TheEIA GuidelinesaremeanttoaccompanytheEvidence-Based Design GuidelinesandareintendedtoprovideanagreedandauthoritativeformatforthepreparationofEIAforpowerprojectsinIreland.
TheobjectiveistominimisechallengesanddisputesabouttheproceduresandcontentofthecoverageofEIAsforpowerprojects.Itwillachievethisbyidentifyingandagreeingappropriatescope,contentandstructureforpowerprojectEIAswithallrelevantstakeholders–inadvanceofanyspecificproject.
ItisproposedthatthestructureandcontentwillexactlymatchthatemployedintheEPA’sAdvice Notes on Current Practice in the Preparation of Environmental Impact Statements.Itwill,howeverprovideconsiderablymoredetailoneachsection.
TheseGuidelineswilldrawheavilyonboththeEnvironmental Benchmarking Studies and the Evidence-Based Design Guidelinestoprovidethedetailaboutthescopeofenvironmentalstudiesontheonehandandtodescribehowtheprojectsshouldbedescribedontheother.TheywillalsotakeintoaccountEirGrid’sEcologyGuidelinesforTransmissionPowerlineswhichwillbeupdatedasappropriatefollowingcompletionofthebenchmarkingstudies.OneofthemostimportantcomponentsoftheGuidelineswillbeastandardisedGlossaryofImpacts.Thiswillcollateastandardisedandauthoritativesetofdescriptionsoflevelsofimpactforpowerprojects.
50
ThisisintendedtoremoveuncertaintyinthepreparationofEnvironmentalImpactStatementsbyfacilitatingrapidandconsistentscopingandscreening.Itwillalsomakekeydeterminationsmorerobustandprotecttheirdecisionsagainstanythreatsanddisputesaboutthesufficiencyofthedataortheappropriatenessofthemethodsemployed.
ThebenchmarkstudieswillprovidethefactualbasisforEvidence-BasedDesignGuidelinesforPowerTransmissionProjectsinIreland.Thebenchmarkstudiesandthedesignguidelines,inturnwillprovidethebasisforspecialistEIAGuidelinesforthissector.
ItisnotedthatprojectswillalsohavetobescreenedwithrespecttotheHabitatsDirectiveAssessment/AppropriateAssessmentasrequiredbyArticle6oftheHabitatsDirective10–availableDEHLGGuidance’AppropriateAssessmentofPlansandProjectsinIreland’(2009)shouldbeconsideredasappropriateinthisregard.
5.5 EMM4 Consideration of the Broadest Possible Range of Alternatives in all Future Energy Transmission StrategiesAlternativeroutesandregionalgriddevelopmentstrategieswillconsiderthebroadestrangepossibleofspatialandenvironmentalalternativesatthenextlevelofenvironmentalassessment–i.e.thatoflowertierplans,multipleorindividualprojects.Allprojectswillbesubjecttodetailedconstraintsandroutesstudy,inaccordancewithEirGrid’sProjectDevelopmentandConsultationRoadmap.
5.6 EMM5 Preparation of Transmission Development Plan Environmental Appraisal ReportEirGridproducesanannualrollingoperationaldocument,theTransmissionDevelopmentPlan(TDP),asrequiredbyregulation8(6)ofSI445/2000,andsubmittedforapprovaltotheCER(CommissionforEnergyRegulation).
IncompliancewithSI435of2004,TDPswillbescreenedfortheneedtoundertakeSEAandAA.Notwithstandingtheoutcomeofscreening,anEnvironmentalAppraisalReportwillbepreparedtoaccompanyeachannualTDPwhichwilldescribeanyeffectsarisingthatwillbesignificantlygreater,differentormoresignificantthanthoseanticipatedbytheSEAorAA.
TheEnvironmentalAppraisalReportwhichaccompaniesthenextTDPshalltakeintoaccountmaritimemappingandissuesemergingfromtheseparateSEAinrespectofthecurrentOffshoreRenewableEnergyDevelopmentPlan,asappropriate.
5.7 EMM6 Ongoing Co-operation in preparation of Renewable Energy Generation Guidelines and Strategies Somepartsofthecountryarebettersituatedforgenerationofrenewablesuppliesofenergythanothers.However,thereiscurrentlynogoverningterrestrialrenewableenergystrategydetailingwhererenewableenergygenerationshouldoccurinIreland.AnumberofpoliciesandobjectivesexistinvariousCountyDevelopmentPlansandCountyWindEnergyStrategieswhichpromotethedevelopmentofrenewableenergyatidentifiedlocationsintheirjurisdictions.
10Referencedstatutoryobligation
51
ThereisclearmeritinthepreparationofRegionalRenewableEnergyGenerationGuidelines,asrenewableenergydevelopmentsmayoftentraversecountyandregionalboundaries.EirGridiskeentosupport,co-operateandparticipateinthepreparationofanysuchfutureRegionalRenewableEnergyGenerationGuidelines,RegionalRenewableEnergyStrategies,CountyWindEnergyStrategiesandCountyRenewableEnergyStrategies.Furthermore,EirGridwillcontinuetosupporttheimplementationofaspectsoftheNationalRenewableEnergyActionPlan2010whereapplicable.
5.8 EMM7 Integrating Offshore Grid connectivity requirements and environmental considerations in EirGrid’s Strategic Environmental Framework (SEF)ItisemergingthatanumberofscenariosforfutureelectricalgenerationanddistributionstrategiesinIrelandarelikelytoinvolvethedevelopmentofoffshoregridinfrastructure.ThishasthepotentialtooccurinareasoffmanypartsofIrelandonaccountofvariousdevelopmentsincludingtheexploitationofoffshorerenewableresources(windandwave),interconnectorswithotherEUMemberStatesandtheparticipationofIrelandinapan-Europeanoffshoregrid.Allofthesehavesignificantimplicationsforgriddevelopmentandpotentialforsignificantinteractionswithinshoreandterrestrialenvironments.
TheSEADirective11requirestheidentificationofarangeofenvironmentaleffectsincludingthosewhichareindirect.InterconnectionacrosswaterandrenewableenergygenerationinfrastructureenabledbytheIP,forexample,cancausepotentialindirectandcumulativeeffectsonboththeonshoreandoffshoreenvironments.Currentlyavailableoffshoreenvironmentaldataisnotsufficiently
completetofacilitateacomprehensiveevaluationoflikelyimpactstothetransitionzonebetweenterrestrialandmarineenvironments.TheOREDPwillbereviewedandupdated,andintegrationwillbecomemoreapparentwithtime.ItisanticipatedthatimprovedoffshoredatawillbecomeavailableintheperiodfollowingthisSEA,particularlyasaresultoftheSEAwhichiscurrentlybeingundertakenforoffshorerenewableresources.ThisdatawillbetakenintoaccountintheEnvironmentalAppraisalReportsforforthcomingannualTDPsandintheSEAsoffutureiterationsoftheIP.
Figure5.1illustratesaqualitativeindicationofgeneral,potentiallocationsforland/seaconnectionswheretherearelesssensitiveonshoreenvironmentsinthevicinityofcoasts.Thisqualitativeindicationwasdeterminedbythesensitivityofonshoreenvironmentsinthevicinityofcoasts,asillustratedbytheOverallDevelopmentPotentialRatingmappingforthevariousregionstowhichGrid25relates,aswellasrelevantcorrespondingdata–includingthatrelatingtolandscapeandecologicalconstraints–forNorthernIreland.Itwouldbeusefulifoffshoregridsgenerallyaimedtomakelandfallintheseareasanditwouldbedesirableforsuchdecisionstoconsidercomparable,equivalenton-shoreandoffshoredata.
Anyconsiderationofalternativeroutes/locationsforland/seaconnectionswillberequiredtoconsiderspatialandenvironmentalalternativesatthenextlevelofenvironmentalassessment–i.e.thatoflowertierplans,multipleorindividualprojects–asisrequiredbymitigationmeasureEMM4,whichhasbeenintegratedintotheIP.
11Referencedstatutoryobligation
52
Figure 5.1 Less Sensitive12 Areas for Land/Sea Connections (identified in yellow)
12Presenceoflessenvironmentalsensitivities
53
APPENDIX A - Network Reinforcement Projects, Demand Customer and DSO Connection Projects, and Generator Connection Projects, identified in EirGrid’s Transmission Development Plan 2010
CP No. Project Title & Description Major New Equipment
Project Justification ECD Phase
CP0217a Blake-Cushaling-Maynooth 110 kV Line - Loop into Newbridge 110 kV station
ExistingCushaling-Maynooth110kVcircuittobeloopedintoNewbridge110kVstationbetweenBlakeTandCushaling.
110kVbays:2110kVline:14km
Toimprovethequalityofsupplytothe110kVstationsinthisareabypreventinglowvoltagesandlineoverloadsundercertaincontingencies.
Jun-10 Complete
CP0241a Lodgewood 220kV Project - New 220kV Station
AnewLodgewood220/110kVstationinCo.Wexford,connectedintotheArklow-GreatIsland220kVlineandlinkedwithanewCrane-Lodgewood110kVline,througha250MVA220/110kVtransformer
220kVStation
220/110kV250MVATrafo:1
220kVbays:5
110kVbays:5
Inotherstations
110kVbays:1
New Line 220 kV line:1km
110kV:7km
Toprovidesupporttothe110kVnetworkinthisareaandbypreventinglowvoltagesandlineoverloadsundercertaincontingencies.
Dec-10 Complete
Table A1
Network Reinforcement Projects
A1 Network Reinforcement DevelopmentsThesecomprisedevelopmentprojectsthataredrivenbygenericdemandgrowthandthedeepreinforcementsresultingfromgeneratordemandandinterconnectorconnections.
54
CP0264a Finglas 220kV Station:
5th 250MVA 220/110 kV Transformer (T2105)
Installationofafifth250MVA220/110kVtransformerandcoupler
220kVbays:2
110kVbays:2220/110kV250MVATrafo:1
TomaintainshortcircuitlevelswithinstandardsandtoalleviatepotentialoverloadingoftheMaynooth-Ryebrook110kVlineundercertainmaintenance-tripconditions.
Feb-10 Complete
CP0379 Carrigadrohid-Kilbarry 110 kV Line Uprate
Upratelineandbusbarstoequivalentof430mm2ACSR@80oC
Uprate110kVline
33.6km
Refurbishmentrequiredduetoconditionofline,uprateindicatednecessarybystudiesforGate2wind.
Dec-10 Complete
CP0451 Dungarvan-Knockraha 110kV Line Uprate
Upratelineto430mm2ACSR@80oC
Uprate110kVline:54km
Thisuprateisnecessarytoavoidunacceptableoverloadingofthe110kVduringcertaincontingenciesasaresultofnewgenerationinthesouthwest
Theupratingofthelinehasbeencompleted,workiscurrentlybeingcarriedouttoupratetheremoteendstoenablefulloperatingcapacityofthecircuit.
Dec-10 Complete
CP0512 New Capacitors at Kilkenny
Onenew30MvarcapacitoratKilkenny110kVstation
110kVstation.
110kVbays:1
Caps:1x30Mvar
ToensurethatvoltagesintheKilkennyareacontinuetocomplywithstandardsandtominimisetheriskofvoltagecollapsefollowingthetrippingoftheKilkenny-Kellis110kVline.
Mar-10 Complete
CP0515 New capacitor at Drumline:
One new 15 Mvar capacitor at Drumline 110 kV station.
110kVbays:1
Caps.:1x15MVar
ToensurethatvoltagesintheDrumlineareacontinuetocomplywithstandards.
Oct-10 Complete
CP0528 New capacitor at Kilteel
Onenew30MvarcapacitoratKilteel110kVstation
110kVbays:1
Caps.:1x30Mvar
ToensurethatvoltagesintheKildareareacontinuetocomplywithvoltagestandardsfollowingtheloopingofKilteelstationandtominimisetheriskofvoltagecollapse.
Nov-10 Complete
55
CP0549a Shannonbridge-Dallow T-Portlaoise
110 kV Line Partial Uprate
Partiallineupratesothatallofthelineisequivalentto430mm2ACSR@80°C
Uprate110kVline:18.3kmof66.7km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Sep-10 Complete
CP0562 Great Island-Waterford 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80°C
Uprate110kVline
11.8km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Oct-10 Complete
CP0576 Cathaleen’s Fall-Corraclassy 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80°C
61.3km TheneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsofthelineintimesofhighwindoutputfromDonegal
Nov-10 Complete
CP0584 Shannonbridge-Ikerrin T 110 kV Line Uprate:
Upratelinetotheequivalentrating
of430mm2ACSR@80°Canduprateallstationequipmenttothisrating.
Uprate110kVline:
54km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Sep-10 Complete
CP0590 Raffeen-Trabeg No.2 110 kV Line Uprate:
Upratelinetotheequivalentof430mm2
ACSR@80°C.
Uprate110kVline:
9.23km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Dec-10 Complete
CP0592 Aghada-Raffeen 220 kV Cable
Thenew220kVcircuitconsistingofasectionofcableandasectionofoverheadline.Theoverheadlineportionofthecircuithasbeencompletedin2006
220kVbays:2
220kVcable:7km
220kVline:8km
TheincreasedgrowthinbothdemandandgenerationintheCorkareahasplacedalargestrainonthenetworksinthisarea.
Jun-10 Complete
56
CP0626 Killonan-Knockraha 220 kV Line Uprate:
ReplacetheexistingconductorwithaHighTemperatureLowSag(GAP)conductortoachieveahigherrating.
Uprate220kVline:
82km
Conditionassessmentidentifiedtheneedforrefurbishment.Thelinewasreplacedwithoneofahigherratingwhichadherestocurrentstandards.
Dec-10 Complete
CP0175 Charleville-Killonan 110 kV Line Uprate
UprateLineto430mm2ACSR@80°C
Uprate110kVLine:
36.9km
Theneedforupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Theupratingofthelinehasbeencompletedandworkiscurrentlybeingcarriedouttoupratetheremoteendstoenablefulloperatingcapacityofthecircuit.
Jun-11 DetailedDesign&Construction
CP0197a Cushaling-Thornsberry 110kV New Line
ConstructionofanewCushaling-Thornsberry110kVlineasa2ndconnectiontoThornsberry110kVstation
110kVbays:2
110kVline:30km
Toimprovethequalityofsupplytothe110kVstationsinthisareabypreventinglowvoltagesandlineoverloadsundercertaincontingencies.
TheDSOhasrequestedasecond110kVlinetotheDSOstationatThornsberrytoimprovethesecurityofsupply.
Sep-11 DetailedDesign&Construction
CP0211 Srananagh 220 kV Station and Line:
AnewSrananagh220/110kVstationconnectedbyanew220kVlinetoFlagford
220kVstation;
110kVworknowcomplete
220 kV Station:
220/110kV250MVATrafo:1
220kVbays:3
New Lines:220kV:56km
ThisdevelopmentisneededtoreinforcethenetworkintheNorth-Westareabysupportingthevoltageandreducingtheriskoflossofsupplyduringthewinterpeaksandthesummermaintenanceoutages.
Itisalsorequiredtofacilitatetheexportofrenewablegenerationfromthenorthwest.
Dec-11 DetailedDesign&Construction
CP0218 Gorman-Navan No. 3 110 kV line:
AthirdlinefromGorman110kVstationto
Navan110kVstationwillbeconstructed.
110kVbays:2
110kVline:4km
ToalleviateunacceptableoverloadsofeitheroftheexistingGorman-Navan110kVlinesfrom2012undercertaincontingencies.
Sep-11 DetailedDesign&Construction
57
CP0246a Tarbert-Tralee No.2 110 kV New Line
AsecondlinefromTarberttoTraleeconstructedat110kV
110kVbays:2110kVline:47km
Thisisneededtoovercome110kVlineoverloadsandvoltagecollapseintheTraleearea.
Nov-11 DetailedDesign&Construction
CP0254 Cashla loop-in of the Dalton-Galway 110 kV line:
LoopingoftheDalton–Galway110kVlineintotheCashlastation,creatingtheCashla–DaltonlineandtheCashla–GalwayNo.4110kVline.ThislinewillthenbeextendedouttothenewSalthill100kVstation,creatingaCashla-Salthill110kVline.RefCP0543inDSOsection.
110kVbays:2110kVline:22km
ToavoidoverloadingtheexistingCashla-Galway110kVlinesduringcertaincontingenciesbyremovingtheDaltonloadconnectionandprovidinganadditionalcircuitintoGalway.
Sep-11 DetailedDesign&Construction
CP0265 Cullenagh - Great Island 220 kV Line Uprate
Upratelinetoequivalentof600mm2HTLSACSR@80oC
Uprate220kVLine
23km
Theupratewillavoidunacceptableoverloadingofthelineduringcertaincontingencies.
Oct-12 DetailedDesign&Construction
CP0292a Gorman-Meath Hill 110 kV New Line
Anew110kVlinewillbeconstructedbetweenGormanandMeathHill110kVstations
110kVbays:2110kVline:30km
TheDSOhasrequestedasecondconnectiontoMeathHill110kVstation.
Dec-11 DetailedDesign&Construction
CP0374a Arva-Shankill No.2 110 kV New Line
Anew110kVlineconstructedbetweenArvaandShankill110kVstations.
110kVbays:2110kVline:20km
Toalleviateunacceptableoverloadsofanumberof110kVlinesintheareaforcertaincontingencyconditions.Thisreinforcementisassociatedwithgenerationconnection.
Dec-11 DetailedDesign&Construction
CP0371 Ballydine - Doon 110 kV Line Uprate (inc of Ballydine busbar) (11.4km)
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVline:11.4km
Theupratewillavoidunacceptableoverloadingofthelineduringcertaincontingencies.
Oct-12 DetailedDesign&Construction
58
CP0406a Cashla-Cloon 110kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVline:23km
Theupratewillavoidunacceptableoverloadingofthelineduringcertaincontingencies.
Jun-11 DetailedDesign&Construction
CP0421 Binbane-Letterkenny 110 kV New Line (Donegal Reinforcement)
Anew110kVlinebetweentheexistingBinbaneandLetterkenny110kVstationsinCountyDonegal;thisnewlineisloopedintoanew110kVswitchingstation,Tievebrack,eastofGlentiestofacilitateDSOconnectiontoArdnagappary.
110kVbays:4110kVline:65km
TheDSOhasrequestedasecond110kVconnectiontoBinbane.TheBinbane-LetterkennylinemeetstheDSO’sneedswhilefacilitatinggenerationexportsfromDonegalduringlowdemandperiodsandmeetingtheincreasingelectricitydemandinthearea.
Oct-13 DetailedDesign&Construction
CP0467a Louth 220kV Station - Reactive Compensation
Installationofa30Mvarre-deployablecapacitorunitatthe110kVbusbarinLouthstation.
Louth 110 kV
Bays:1
Caps:1x30Mvar
Toresolvetemporaryandlongtermvoltageproblemsinthenortheast.
Jun-10 DetailedDesign&Construction
CP0511 Killonan 220kV Station
Installationofa4th220/110kVTransformer.Theunitwillhavearatingof250MVA.
220/110kV250MVATrafo:1
Requiredtoavoidoverloadingtheexisting63MVAtransformerswhenthe125MVAtransformerisoutofserviceandoneoftheremaining63MVAtransformerstrips.
Jun-11 DetailedDesign&Construction
CP0513 Carrickmines 220kV Station
Installationofa3rd250MVA220/110kVTransformer
220/110250MVATrafo:1
110kVbays:1
220kVbays:1
Necessarytoavoidunacceptablevoltagelevelsintheareawhenonetransformersisoutofserviceandthesubsequentlossofthesecondtransformer.
Oct-11 DetailedDesign&Construction
CP0514 Ardnacrusha 110 kV Station Reactive Compensation
Installationofanew30MvarcapacitoratArdnacrusha110kVStation.
110kVbays:1
Caps.:1x30Mvar
ToensurethatvoltagesintheArdnacrushaareacontinuetocomplywithstandards.
Jun-11 DetailedDesign&Construction
59
CP0523 Inchicore 220kV Station - 4th 250MVA 220/110kV Transformer
Connectionofanew250MVA,220/110kVdoublewoundtransformer(T2103)inInchicore220kVstation;extensionoftheexistingGIS220kVbusbarandbuilding;installationofanew220kVtransformerbay,linebayandcoupler.
220kVbays:3
220/110250MVATrafo:1
Thiswillmaintainsecurityofsupplyandalleviateexisting220kVshortcircuitproblems.
Jun-11 DetailedDesign&Construction
CP0529 New Capacitor at Thurles
Onenew15MvarCapacitoratThurles110kVstation
110kVbays:1
Caps.:1x15Mvar
ToensurethatvoltagesintheThurlesareacontinuetocomplywiththeTPCandtominimisevoltagedropviolations
Oct-12 DetailedDesign&Construction
CP0537 Limerick-Moneteen 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVline
6.4km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Aug-11 DetailedDesign&Construction
CP0551 Cahir-Doon 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVline
6.4km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Aug-11 DetailedDesign&Construction
CP0552 Athlone-Shannonbridge 110 kV Line Uprate
Upratelinetoequivalentratingof430mm2ACSR@80oC
Uprate110kVline:21km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Oct-11 DetailedDesign&Construction
CP0575 Corraclassy-Gortawee 110 kV Line Uprate
RefurbishmentandfullupratingoftheCorraclassy-Gortawee110kVlinetoanequivalentof430mm2ACSR@80oC
Uprate110kVline
10.9km
AconditionassessmentoftheCorraclassy–Gortawee110kVlinewascarriedoutandshowedtherequirementtoreplacetheconductor.TheneedforupratinghasbeenidentifiedtoavoidpotentialoverloadsonthislineintimesofhighwindoutputfromDonegal
LineWorknowcomplete,Awaitingbayconductoruprate
Mar-11 DetailedDesign&Construction
60
CP0586 Knockraha 220 kV Station
Installationofa3rd250MVA220/110kVtransformer
220/110kVtrafo:1
220kVbay:1
110kVbays:1
110kVcable:1
TwonewCCGTsinCorkdrivetheneedforadditionaltransformercapacityinKnockraha220kVstation.
Jun-11 DetailedDesign&Construction
CP0593 Aghada 220 kV AIS Station
Replacementandupgradingofexistingstation
220 kV Station
Theincreasedgrowthinbothdemandandgenerationisplacingalargestrainonthenetworksinthisarea.Theconditionoftheplantandapparatusduetoageisalsoafactor
Aug-11 DetailedDesign&Construction
CP0594 New Capacitors at Mullingar
Twonew15MvarcapacitorsatMullingar110kVstation
110kVbays:2
Caps:2x15Mvar
ToensurethatvoltagesintheMullingarareacontinuetocomplywiththeTPCandtocaterforincreasingdemand
Oct-12 DetailedDesign&Construction
CP0618 New Capacitors at Lisdrum
Installationoftwo15MvarfixedcapacitorunitsatLisdrum110kVstation
110kVbays:2
Caps:2x15Mvar
Toresolvethetemporaryandlongtermvoltageproblemsinthenortheast
Apr-11 DetailedDesign&Construction
CP0587 Glanagow-Raffeen 220 kV Underground Cable Circuit
Anew220kVcircuitconsistingofasectionofcableandasectionofoverheadline.
220 kV Cables
Underground:4km
Undersea:4.5km
220kVbays:2
ThisisnecessarytofacilitatetheexportofgenerationfromtheCorkharbourarea
Jul-11 DetailedDesign&Construction
CP0620 Arva-Gortawee 110 kV Line Uprate
RefurbishmentandfullupratingoftheArva-Gortawee110kVlinetoanequivalentof430mm2ACSR@80oC
Uprate110kVline:
30.6km
AconditionassessmentoftheArva-Gortawee110kVlinewascarriedoutin2008.Theneedforrefurbishmentwasidentifiedbythisassessmentwhilesystemstudiesindicatedtheneedtoupratetoavoidunacceptableoverloading.
Jun-11 DetailedDesign&Construction
61
CP0517 Coolroe - Kilbarry 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
14.5km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Dec-12 DetailedDesign&Construction
CP0518 Coolroe - Inniscarra line uprate (inc Innicscarra busbar)
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
2.74km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Oct-11 DetailedDesign&Construction
CP0559 Butlerstown - Killoteran line uprate (inc of busbars)
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
2.7km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Oct-12 DetailedDesign&Construction
CP0560 Cullenagh - Waterford 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
12.5km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Oct-12 DetailedDesign&Construction
CP0637D Portlaoise busbar uprate-Athy Carlow Line Works
Busbars,sectionalisersanddisconnectorstobeuprated.
110kVStation:BBuprate:1
Theneedofupratinghasbeenidentifiedtoenabledevelopmentofthenetwork.
Oct-11 DetailedDesign&Construction
CP0656 Arklow - Crane 110 kV Line Uprate incl busbars in Arklow & Crane
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
41.8km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Aug-11 DetailedDesign&Construction
CP0659 Arva - Navan 110 kV Line Uprate & Line Works
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
65.5km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.
Jul-11 DetailedDesign&Construction
62
CP0667 Inchicore - Maynooth 1 & 2 220kV Line (double cct)- Uprate with HTLS
Uprate220kVLine
2x19km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Dec-12 DetailedDesign&Construction
CP0687 Dunmanway - Macroom 110kV Refurbishment
Newlineequivalentof430mm2ACSR@80oC
Uprate110kVLine
26.2km
ConditionAssessmentindicatesrequirementforlinerefurbishment.Existinglinetobeupgradedaccordingtocurrentpolicy
Oct-11 DetailedDesign&Construction
CP0689 Ennis 110kV station - Busbar Uprate
110kVStation:Busbaruprate:1
Theneedofupratinghasbeenidentifiedtoenabledevelopmentofthenetwork
Oct-12 DetailedDesign&Construction
CP0694 Athlone 110kV Busbar Uprate 110kVStation:Busbaruprate:1
Theneedofupratinghasbeenidentifiedtoenabledevelopmentofthenetwork
Dec-11 DetailedDesign&Construction
CP0696 Marina - Trabeg 1 110kV Cable Uprate
110kVCableuprate3.3km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Dec-12 DetailedDesign&Construction
CP0698 Prospect - Tarbert 220kV Line Uprate (7.7km)
Uprate220kVline
7.7km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Dec-12 DetailedDesign&Construction
CP0701 Cullenagh - Dungarvan 110 kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVline
34.32km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Oct-13 DetailedDesign&Construction
63
CP0702 Butlerstown - Cullenagh 110kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
14.5km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Oct-13 DetailedDesign&Construction
CP0660 Cashla-Ennis 110 kV Line Uprate
UprateLinetoequivalentof430mm2@80oC
Uprate110kVLine
54.3km
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Jul-11 DetailedDesign&Construction
CP0466a&CP0469
North-South 400 kV Interconnection Development
Anew400kVlineconstructedbetweentheexistingWoodland400kVstation,insoutheastCo.MeathandTurleenaninCo.Tyrone
Woodland 400 kV
Bay:1
400kVline:140km
Toincreasetransfercapacitybetweenthetwosystemsinbothdirectionsandavoidsituationswhereasingleeventcouldleadtosystemseparation.Alsotoprovidenetworkreinforcementinthenortheast
Dec-14 PublicPlanningProcess1
CP0399 Moneypoint-Tarbert 220 kV New Cable
AnewsubmarinecableconstructedacrosstheShannonEstuaryfromMoneypointinCo.Claretoanew220kVstationwestofTarbertinnorthCo.Kerry;installationofanew400/220kVtransformerinMoneypoint
400kVbays:1
220kVbays:1
500MVATrafo:1
220kVcable:10km
Toprovideanalternativerouteforpowerintoandoutofthesouthwestaswellasanadditionallinkbetweenthe400kVand220kVnetworks.
Jul-13 PublicPlanningProcess2
CP0682 Woodland 400 kV Station - 2nd 400/220 500MVA Trafo
400kVStation:1
500MVATrafo:1
RequireddeepreinforcementforEast-WestInterconnector.
Jul-12 PublicPlanningProcess3
CP0683 Dunstown 400kV Station - 2nd 400/220 500MVA Trafo
400kVStation:1
500MVATrafo:1
RequireddeepreinforcementforEast-WestInterconnector.
Dec-12 PublicPlanningProcess4
1ThisprojectwasoriginallysubmittedasanapplicationforApprovaltoABP,butwaswithdrawnpriortoitsdetermination. TheprojectiscurrentlyatOutlineDesignorEIA2IncludingenvironmentalreportandAAscreening3Thisprojecthassubsequentlybeenapproved,andisnowatdetaileddesignandconstructionphase4Thisprojecthassubsequentlybeenapproved,andisnowatdetaileddesignandconstructionphase
64
CP0647 Tarbert Redevelopment Project
New220/110kVstationtothewestoftheexistingTarbertStation.Allexisting110kVcircuitsconnectedintoTarbert220kVstationwillbedivertedtothisnewstation
220/110kVStation:1
220/110kVTrafos:3
220kVBays:12
110kVBays:12
RequiredtoaccommodateplannedgenerationinthesouthwestandtherefurbishmentoftheexistingTarbert220kVstation.Thenew110kVpartofthestationwillallowfortheexistingTarbert110kVequipmenttoberemovedforacleanupoflinesinthearea.AlsotherouteaccessintoTarbertisrestricted,thenewstationwillimprovethis
Jul-13 PublicPlanningProcess5
CP0501 Clashavoon-Dunmanway 110 kV New Line
Constructionofanew110kVlinefromClashavoontoDunmanwaystationandassociatedstationsworks
110kVline:35km
110kVbays:2
TheconstructionofaClashavoon-Dunmanway110kVlinewillimprovesecurityofsupplyforwestCorkandfacilitaterenewablegeneration
Mar-14 OutlineDesignorEIA
CP0580 Carrickmines 220 kV GIS Development
Replacementofexistingair-insulatedswitchgearwithgas-insulatedswitchgear(GIS);
Installationofanew4th220/110kVtransformer.
220kVsubstation:1
220kVbays:1
220/110kV250MVATrafo:1
Therequirementtochangetheswitchgearisduetotheassets’conditionandexpansionneeds.The4th220/110kV250MVAtransformerisnecessarytoavoidunacceptablelowvoltagelevelsintheareawhenonetransformerisoutformaintenanceandafaultoccursonasecondtransformer
Dec-12 OutlineDesignorEIA
CP0585 Laois /Kilkenny Reinforcement New Station & Associated Lines & Station Works
New400/110kVtransmissionstationinCo.Laois.ThestationwillbeloopedintotheexistingDunstown-Moneypoint400kVlineandCarlow-Portlaoise110kVline.
Anew110kVcircuitfromthenewstationtoKilkennyusingtheexistingBallyragget-Kilkenny38kVlinewhichisbuiltto110kVstandards.
Anew110/38kVstationatBallyraggettocaterforlossoftheKilkenny-Ballyragget38kVline.[DetailstobefinalisedwithDSO].
400kVStation
400kVbays:5
400kVbusbar
110kVStation:
110kVbays:7
110kVbusbar
Inother110kVstations
110kVbays:5
110kVOHL:30km
Thiswillprovideastronginjectionfromthe400kVnetworkintothe110kVnetworknearPortlaoise,andwillsignificantlyimprovethequalityandsecurityofsupplyincountiesLaois,CarlowandKilkennyandprovideforlongtermgrowththroughouttheregion.
Dec-14 OutlineDesignorEIA
5IncludingenvironmentalreportandAAscreening
65
CP0596 New 110kV Circuit To Mullingar
Constructionofanew110kVcircuittoMullingar110kVstationfromeitherKinnegadorDerryiron110kVstations
110kVbays:2
110kVLine:30km
RequiredtoensurevoltagelevelsatMullingarremainwithinstandardsduringcertaincontingenciesandallowforeconomicgrowthinthearea
Oct-14 OutlineDesignorEIA
CP0597 Reinforcement of the Ardnacrusha & Ennis Area
UpratingoftheMoneypoint-Tullabrack-Booltiagh-Ennis110kVcircuittoequivalentof430mm2ACSR@80oC.DependentonMoneypoint400/220/110kVGISDevelopment,seeCP0688
Uprate110kVline:53.1km
ToalleviatelowvoltagelevelsintheArdnacrushaandEnnisareasduringthesummermaintenanceofcertainexistingoverheadlinesinthearea
Dec-14 OutlineDesignorEIA
CP0674 Tralee 110 kV Station
NewCoupler
110kVCoupler:1
RequiredtoimprovesecurityofsupplyinKerry
Aug-12 OutlineDesignorEIA
CP0688 Moneypoint - New 400/220/110kV GIS development
400,220,110kVstation
Requiredtocomplywithbusbarpolicyandsecurityofsupplystandards.Alsofacilitatedevelopmentoftransmissionnetwork
Oct-15 OutlineDesignorEIA
CP0699 Cathaleen’s Fall - Srananagh 1 110kV Line Uprate
Upratelinetoequivalentof430mm2ACSR@80oC
Uprate110kVLine
52.7km
110kVBay:1
Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline
Oct-12 OutlineDesignorEIA
CP0709 Dunmanway 110kV Station Upgrade
100kVStation:
TrafoBay:1
BB/coupler:1
Requiredtocomplywithbusbarpolicyandsecurityofsupplystandards.Alsofacilitatedevelopmentoftransmissionnetwork
Dec-14 OutlineDesignorEIA
CP0707 Barrymore 110kV station extension - Loop into Cahir - Knockraha 110kV line
NewLines:110kV:
0.3km
DSOhasrequestedconnectionofof2nd110/38kVtransformer.Thisdrivesneedforfull4bayloopedinstationtocomplywithtransmissionstandards
Jun-13 OutlineDesignorEIA
CP0619 New Capacitors at Shankill
Installationof15Mvarand30Mvarre-deployablecapacitorunitsatShankill110kVstation
110kVbays:2
Caps:1x15Mvar
1x30Mvar
Toresolvethetemporaryandlongtermvoltageproblemsinthenortheast
OnHold
OutlineDesignorEIA
66
67
CP No. Project Title & Description Major New Equipment ECD Phase
CP0489 Castlebar 110 kV Station - New 110 kV Line bay for Carrowbeg
Carrowbegisthenameforanew110kVstationnearWestport,Co.Mayo,tailfedfromCastlebar.Installationof110kVequipmentinanexistinglinebayinCastlebar110kVstation.
Itisproposedthatthenewstationwillsupply1MVAofnewloadandaccommodatethetransferof22MWfromCastlebar
110kVbay:1 Jun-10 Complete
CP0535 College Park 110 kV Station - 3rd Transformer bay
Connect1X20MVA,110/10kVtransformer(T103)inCollegePark110kVstation.
ItisproposedthatthenewtransformerwillenableCollegePark110kVstationtoaccommodateanincreaseinMICof24MVA
110kVbay:1 Mar-10 Complete
CP0628 Doon 110 kV Station NewTransformerBay
110kVTrafobay:1 Dec-10 Complete
Table A2
DSO Connection Projects
A2 Demand Customer and DSO ConnectionsMostdemandconnectionstothetransmissionsystemaresoughtbytheDistributionSystemOperatorwhichappliesfornewstationconnections.TableA2liststhedevelopmentprojectsthatrelatedirectlytotheconnectionofnewTSO/DSOinterfacestationstothegrid,ortochangesinexistingconnectionarrangements.
68
CP0631 Waterford 110 kV Station - Uprate 2 bays to 63 MVA
Replacetheexisting2x31.5MVATransformersatWaterford110kVstationwith2x63MVAunits.
110kVTrafobay:2 Sep-10 Complete
CP0173b Banoge 110 kV New Connection
TheexistingArklow-Crane110kVlineloopedintoBanoge110kVstation,creatingnewArklow-BanogeandBanoge-Crane110kVlines.Thisstationhasalreadybeenbuiltandisawaitingconnection
110 kV station
110kVbays:4
110kVline:6km
Jun-11 DetailedDesign&Construction
CP0201a Athy 110 kV Station
TheexistingCarlow-Portlaoise110kVlineloopedintoanewAthy110kVstation,creatingnewAthy-PortlaoiseandAthy-Carlow110kVlines.
Stationiscompleteandenergised,butistee’dontoCarlow-Portlaoise110kVline.
Afurtheroutageisrequiredin2010toloopthisnewstationintotheexistingcircuit.
110 kV station
110kVbays:5
110kVline:18km
Dec-11 DetailedDesign&Construction
CP0507 Arklow 220/110 kV Station –
New2x20MVADSOTransformers(T2101/T2102)tobeinstalledtoaccommodategrowingloadinthearea
110 kV bays: 2 Mar-11 DetailedDesign&Construction
CP0543 Salthill 110kV Station - New Station
Newlooped110kVstationwillbebuiltonsiteofexistingSalthill38kVstation.SalthillwillbeconnectedtoGalway110kVstationandtoCashlabyre-directingtheproposedCashla-Galway110kVNo.4linetoSalthill,whichwillbecomeCashla-Salthill110kV.ThisprojectalsoincorporatesabayinSalthillfortheDSOconnectiontoScreeb
110kVlinebays:5
110kVtrafobays:3
110kVcable:12km
Jul-11 DetailedDesign&Construction
CP0630 Carlow 110 kV Station - Uprate 2 bays to 63 MVA
Replacetheexisting2x31.5MVATransformersatCarlow110kVstationwith2x63MVAunits
110kVTrafoBay:2 Oct-11 DetailedDesign&Construction
CP0646 Finglas 110 kV Station
New 35 bay 110 kV GIS Station to replace existing 110 kV AIS.
110kVStation
Bays:35
Dec-14 PublicPlanningProcess6
6Thisprojecthassubsequentlybeenapproved,andisnowatdetaileddesignandconstructionphase
69
CP0437a North Dublin 220kV Project - New 220kV Station
A new 220 kV station in the Balgriffin area and associated networks. The development is part of a wider TSO/DSO agreed reinforcement strategy to enhance the network in the northern fringe of Dublin city. The station will be tail fed from Finglas 220 kV using cable and constructed with GIS.
The process of acquisition of a new site for this project is currently underway.
220kVStation(GIS):1
220/110kV250MVATrafo:1
220kVbays:1
Inotherstations
220kVbays:1
220kVcable;15km
Dec-14 OutlineDesignorEIA
CP0506 Finnstown 220kV Project
(Adamstown) - New 220kV Station
Finnstown 220 kV station, south of Lucan, a new 220 kV station looped into the Inchicore-Maynooth No. 1 and No.2 220 kV lines. The station will be initially a single transformer 220 kV station, but allow final development for a four transformer station. Due to space restrictions on potential sites an entirely GIS station is proposed.
220kVGISstation
Trafobay:4
Line/cablebays:4
Couplerbay:3
220/110kV250MVATrafo:1
110kVGISStation
Doublebusbar:1
Trafobay:4
Line/cable/MVtrafobays:8
GIScouplerbay:3
Mar-14 OutlineDesignorEIA
CP0644 Bracklone 110 kV Station and Loop In
New 110 kV station to be looped into Portlaoise-Newbridge 110 kV line. Replaces existing Portarlington 38 kV Station.
110kVstation
linebays:2
TrafoBays:2
Mar-14 OutlineDesignorEIA
CP0649 Drumline 110 kV Station Works
Two 20 MVA Transformers supplying 12.2 MW New load and 11.4 MW transfered load from existing Drumline transformers.
110KVBays:2 Jun-13 OutlineDesignorEIA
CP0627 Bandon 110 kV Station
New Transformer Bay.
110kVTrafobay:1 OnHold
OutlineDesignorEIA
CP0075 Ballycummin 110 kV New Station
New station looped into the Limerick-Moneteen 110 kV line.
110kVlinebays:5
110kVline:0.2km
OnHold
OutlineDesignorEIA
CP0629 Monread 110 kV Station
New Transformer Bay
Cancelled – included in Minor Capital Works instead Jan 10)
110kVTrafoBay:1 Dec-10 Cancelled
70
71
CP No. Project Title & Description Major New Equipment ECD Phase
CP0563 IPP62 Garvagh Connection
Installation of Garvagh 110 kV bay in Corderry 110 kV station (IPP build)
Bays:1(locatedatCorderry110kV)
Line:7km
Apr-10 Complete
CP0599 IPP048E Coomagearlahy Wind Farm Extension
A new bay in the existing Coomagearlahy 110 kV station to facilitate an extension of the wind farm (IPP Build)
110kVBay:1 Feb-10 Complete
CP0614 IPP142 Edenderry Peaker Project
A new 110 kV bay at the existing Cushaling 110 kV station to connect a new 116 MW distillate generator
Bays:1(atCushaling110kV) Apr-10. Complete
CP0555 IPP111 Castledockrill Connection
A new 110 kV station connected to Lodgewood station, see CP241 in Table 4-2. This will facilitate connection of DSO windfarm. (IPP Build).
110kVstation
110kVbays:2
110kVCable:6.6km
Dec-10 Complete
Table A3
Generator Connection Projects
A3 Generator ConnectionsThissectionoutlinestheprojectsunderwaythatrelatedirectlytoconnectionofgenerationtothetransmissionsystemortochangesinexistinggenerationconnectionarrangements.Someoftheseconnectionsare“contestable”,i.e.thegeneratorhasdecidedtobuildtheconnectionassetstoTSOspecifiedstandards.Itshouldbenotedthatthisisdependentonprogressbytheapplicant.
72
CP0479a IPP055 Athea Phase 1 Connection
A new Athea 110 kV station connected to the existing Trien 110 kV station for the connection of Athea Windfarm (IPP Build).
110kVGISStation
Bays:7(inc.1bayatTrien110kV)
Line:13km(toDromada)
Jul-11 DetailedDesign&Construction
CP0595 Glanagow 220 kV Station
A new 220 kV GIS station for the connection of a new CCGT plant. (Already generating, with temporary connection via AIS station)
New220kVStation:1 Jul-11 DetailedDesign&Construction
CP0500 North Kerry Project
A new 220 kV station looped into the existing Clashavoon-Tarbert 220 kV line. The work includes connection works for Athea, Dromada and Cloghboola windfarms
220kVStation:1
250MVATrafo:1
Bays:2
110kVStation:1
Bays:5
Line:15.2km
Apr-14 OutlineDesignorEIA
CP0603 IPP088 Mulreavy Connection
Connection of a new 110 kV station for connection of new windfarm.
110kVStation:1
110kVBays:5
110kVLine:7.7km
Jan-12 OutlineDesignorEIA
CP0608 IPP119 Cloghboola Wind Farm
Connection of a new windfarm into the existing Trien 110 kV station.
110kVStation
Bays:3
Line:13km
Trien110kV
Bays:1
Apr-14 OutlineDesignorEIA
CP0615 Glenree 110kV Station
Connection of a new 110 kV station, looped into the existing Cunghill-Moy 110 kV line. This station will facilitate the connection of new DSO windfarms.
110kVStation
Bays:3
Sectionaliser:1
Line:1.4km(2x0.7km)
Sep-11 OutlineDesignorEIA
CP0648 Garrow 110 kV Station
Extension Works for a new 110 kV transformer bay for the provision of renewable energy.
110kVstation
110kVLineBays:3
110kVTrafoBay:1
110kVCoupler1
110kVbusbarextension
Aug-11 OutlineDesignorEIA
CP0650 Millstreet 220/110 kV station
New 220/110 kV station looped into the existing Clashavoon-Tarbert 220 kV line for the connection of wind farms.
220/110kVStation
220/110kVTrafo:1
220kVBays:2
110kVBays:1
Aug-14 OutlineDesignorEIA
73
CP0651 East Kerry & North West Cork 220 kV Station
A new 220 kV station looped into the existing Clashavoon-Tarbert 220 kV line for the connection of wind farms. Two new 110 kV lines will be constructed, one to Glenlaraand the other to the planned Cordal station in Co. Kerry. Knockacummer connection into Glenlara is also part of this project.
220/110kVStation
220/110kVTrafo:1
220kVBays:2
110kVBays:2
Jan-14 OutlineDesignorEIA
CP0602 IPP044 Keelderry Wind Farm
Connection of a new windfarm to a new station, looped into the existing Agannygal-Derrybrien 110 kV line.
110kVStation:1
Bays:3
OnHold OutlineDesignorEIA
CP0641 IPP118 Nore Power Station
Extension works in the existing Kilkenny station for the connection of a new OCGT.
110kVstation
110kVbusbarextension
110kVCableBay(atKilkenny)
OnHold OutlineDesignorEIA
CP0669 IPP159 Cuilleen Power Shallow Connection
Connection of a new OCGT into the existing Athlone 110 kV station
Athlone110kVstation
LineBay:1
110kVCoupler
OnHold OutlineDesignorEIA
CP0670 IPP112 Suir Power Shallow Connection
Connection of a new OCGT into the existing Cahir 110 kV station
110kVStation
110kVbusbarextension
110kVCableBay:1(atCahir)
OnHold OutlineDesignorEIA
74
CP No. Project Title & Description Major New Equipment ECD Phase
CP0652 East-West Interconnector
Shallow connection of East-West Interconnector into Woodland
400 kV station from new HVDC/HVAC Converter Station at Portan, near Woodland in Co. Meath
400kVbays:1
400kVtailedconverterstation:1
400kVcable:500m
Sep-12 DetailedDesign&Construction
Table A4
Interconnector Connection Projects
A4 Connection of InterconnectorsThissectionoutlinestheprojectsthatrelatedirectlytotheconnectionofinterconnectorstothetransmissionsystem.ThesearelistedinTableA4.
TheCable-layingvessel‘Nostag’atworkonEastWestInterconnectorinWales
75
AsextractedfromSection9oftheEnvironmentalReportoftheSEAaccompanyingthisIP.
EMM8 Other Measures Integrated into the IPMitigationmeasuresdescribedbelowhavebeenwordedtofacilitatedirecttranscriptionandincorporationintotheImplementationProgramme.
NotethatthefollowingmitigationmeasureswillbeextendedandaugmentedbytheoutputfromtheEnvironmentalBenchmarkingStudiesandEvidence-BasedDesignGuidelinesdescribedabove.
EMM8A Biodiversity and Flora and Fauna
EMM8A(i) Designated European and National Sites of Nature Conservation Interest
Everyeffortwillbemadetoavoiddesignatedsitesofconservationimportance.However,wherethisisnotpossible,routingwillbeselectedtoensurenosignificantimpactsontheintegrityofthesite.Restrictedworkingareaswillbeimposedtoensureminimaldisturbancetosensitivehabitats.
Sensitiveconstructiontechniqueswillbeusedsuchastheuseofbogmatsformachineryaccess,particularlyifundergroundcablesareproposedorinremoteboglandareas.Aerialaccesswillbeconsidered–forbothmaterialsandworkforce–inexceptionallysensitivesites.
Ecologicalmonitoringwillbeundertakenatsensitivesitesduringconstructionasappropriate.Suchsiteswillbeidentifiedonacasebycasebasis.
EMM8A(ii) General Habitat Loss and Disturbance
• Wherepossible,directhabitatlosswithindesignatedsiteswillbeavoided.
• Whenconstructionoccurswithinadesignatedsite,sensitiveconstructiontechniqueswillbeusedsuchastheuseofbogmatsformachinery
access,particularlyifundergroundcablesareproposedorinremoteboglandareas.Aerialaccesswillbeconsidered–forbothmaterialsandworkforce–inexceptionallysensitivesites.
• Useofbog-matstominimisetheimpactofheavymachineryonvegetationandsoils.
• Minimiseextentofworksareas.
• Re-distributevegetationandsoilstrippedfromtheconstructionareastoprovideaseedbankanddonotre-seedwithPerennialRyegrass.
• Landwithintheworkingareawillbereinstatedasnearaspracticaltoitsformercondition.
EMM8A(iii) Bogs and Peatland areas
• Areasofdeepandactivepeatshallbeavoided.
• Detailedpeatslipriskassessmentsshouldbecarriedoutforallproposeddevelopmentsinareaswherepeatsubstratesoccur.
• Constructionmachineryshouldberestrictedtositeroadsanddesignatedaccessroutes.Machineryshouldnotbeallowedtoaccess,parkortraveloverareasoutsidedevelopmentconstructionzones.
• Peatexcavatedduringconstructionactivityshouldnotbestored(temporarilyorotherwise)onareasofadjacentmirehabitatsornearflushesordrains.Temporarystorageofspoilmaterialexcavatedduringtheconstructionphasedevelopmentsshouldbestoredatsuitablelocationsawayfromsurfacewatercourses.
• Allspoilmaterialexcavatedduringtheconstructionphaseshouldbereinstatedfollowingthecompletionoftheconstructionphaseofaproposeddevelopment.
• Wheredisturbanceofpeatsoilscannotbeavoided,thereshouldbesomeconsiderationgiventopossiblere-seedingwithnativespeciestostabilisethepeatandacceleraterecoveryofthevegetation.
APPENDIX B - Environmental Mitigation Measures
76
EMM8A(iv) Birds
• Wherefeasible,siteclearanceinvolvingthecuttingordestructionofvegetationandhedgerowsshallnottakeplaceinthebirdbreedingseasonbetweenMarch1standAugust31stinclusive.
• Intheeventthatsiteclearancedoestakeplaceduringthebirdnestingseason,theappropriatelicencewillbeappliedfor.
• Ontheadviceofrelevantornithologicalexpertsandagenciesbirdwarningdevicesshallbeputinplacewherecrossingsofsensitiveflightcorridorscannotbeavoided.
EMM8A(v) Bats
• Theremovalofbatcommutingandforaginghabitatshallbeavoidedwherepossibleduringtheconstructionandoperationphaseofinfrastructure.
• Wheretheremovalofcommutingorforaginghabitatcannotbeavoidedalternativehabitatshouldbeestablishedpriortosuchhabitatremoval.
• Treesscheduledforfellingaspartofsiteclearanceshallbecheckedbyabatspecialistforthepresenceofbats.
• Wherebatsarenotedtobewithinatreepriortofellingoperations,itwillbenecessarytopostponefellingtocreatetheopportunityforbatstoceaseusage.Ifbatsdonotleaveatreeorbuildingwithinareasonabletimeframe,itmaybepossibleforabatspecialisttoseektoexcludethebats(orotherwiseremovethemtosafety).ThisshallbecarriedoutbyaqualifiedbatspecialistwithwrittenpermissionfromtheNationalParksandWildlifeSectionoftheDepartmentofArts,HeritageandtheGaeltachtbywayofalicencetoderogatefromtheprotectionaffordedbatsbyIrishandEUlaw.Alllicencesshallbeinplacepriortofellingproceduresastodestroyaroostwithoutalicenceisanoffence.
EMM8A(vi) Otters
• Destructionofactiveotterholtsshallbeavoided
• Noworksshallbeundertakenwithin150mofanyholtsatwhichbreedingfemalesorcubsarepresent.
• Nowheeledortrackedvehicles(ofanykind)shouldbeusedwithin20mofactive,butnon-breeding,otterholts.Lightwork,suchasdiggingbyhandorscrubclearanceshouldalsonottakeplacewithin15mofsuchholts,exceptunderlicence.
EMM8A(vii) Other protected species
• Thebreedingandrestingsitesofprotectedspeciesshallbeavoidedduringtheappropriateseasons.
• Heavymachineryshallnotbeusedwithin30mofanoccupiedbadgersett.
• AderogationlicencefromtherespectiveWildlifeActs13shallbesought–andworksshallnotbecommencedwithoutsuchconsentwhereitappearsthatprotectedfloraandfaunaspeciesarelikelytobeunavoidablydisturbed.
EMM8A(viii) Protected Surface Water or Riparian Habitats
Inallcaseswhereworkshavethepotentialtoimpactonprotectedsurfacewaterorriparianhabitats,theInlandFisheriesIrelanddocumentRequirementsfortheProtectionofFisheries Habitat during Construction and Development Works at River Sitesshallbeadheredto.DevelopmentoftransmissioninfrastructureadjacenttodesignatedfisheriesshallbecarriedoutinconsultationwithInlandFisheriesIrelandtominimisethepotentialeffectsondesignatedsurfacewaters.
13Referencedstatutoryobligation
77
EMM8A(ix) Freshwater Pearl Mussel Catchments
• ActionmeasuresasoutlinedintheSubBasinManagementPlansshallbetakenintoaccountwheredevelopmentisconsideredadjacenttoareasassociatedwithFreshwaterPearlMussels.
• InthevicinityofwatersthatsustainpopulationsofFreshwaterPearlMusselsthefollowingadditionalmitigationmeasuresshallbeemployed:
• Thereshallbenostreamcrossingbymachinery.
• Siltywaterwillbecollectedinsettlementponds priortodischargetowatercourse.
• Bufferingstripswillbeprovidednear watercourses.
EMM8A(x) Fisheries
• AllworksadjacenttodesignatedfisherieswaterswillbedoneinconsultationwithInlandFisheriesIreland.
• AllworksinvolvingopencutcrossingsshallbeconductedduringtheperiodMaytoSeptembertoavoidinterruptionofsalmonidspawningruns,spawning,incubationofeggsandtheearlydevelopmentalstages.
• Whereappropriateandpractical,bankvegetationandbedmaterialwhichhasbeenremovedshallbestoredtofacilitateitsreplacementwhenchannelworkshavebeencompleted.
• Worksinthevicinityofawatercourseshallbecarriedoutwithreferencetoawaterqualityprotectionplanforeachsitewhichshallensurethat:
• Allnecessarymeasuresshallbetakento minimisethegenerationandreleaseof sedimentsintoallwatercourses.
• Levelsofsuspendedsolidsintherivershallbe monitoredduringthecourseoftheworks.
• Precautionsshallbeputinplacetoavoid spillagesofdiesel,oilorotherpollutingsubstances.
EMM8A(xi) Mature Trees
Whereconstructionworkisrequiredclosetotrees,theNationalJointUtilitiesGroup‘GuidelinesforthePlanningInstallationandMaintenanceofUtilityServicesinProximitytoTrees’(NJUG10)willbefollowed.
EMM8A(xii) Hedgerows
Alldisturbedhedgerowswillbere-plantedassoonaspossibleafterconstruction,usingIrishnurserystockandindigenousspecies.Plantingwillbemaintaineduntilvigorousre-growthhasbeenestablished.Wherehedgesofparticularvalueareencounteredtheextentanddurationoftheworksshallbeminimised.Forspecies-richbanks,turfwillbestrippedandstoredseparatelyforreplacementorre-instatement.
EMM8B Water Resources
EMM8B(i) Accidental spillage of fuel chemicals or sewage causing pollution to water or ground
• Develop,implementandenforceaWaterPollutionPreventionandEnvironmentalEmergencyResponsePlanforallworksites.ThisshouldincludegoodsitepracticesasdescribedintheGoodPracticeGuidancenotesproposedbyEA/SEPA/EHS.
EMM8B(ii) Suspended solids & sediment deposition
• Precautionsshallbeputinplacetoavoidorminimisethegenerationandreleaseofsediments14intoallwatercourses.
EMM8B(iii) Physical Damage to watercourses
• Develop,implementandenforceacodeofbestpracticeforconstructionandreinstatementmethodstobeusedforunavoidableconstructionworksinthevicinityofwatercourses.
14Sedimentsinthisinstanceincludeallsoilsincludingpeat.
78
EMM8B(iv) Flooding
• Withinknownfloodplains,measuresshallbetakentoavoidanypotentialimpactofconstructionorexistenceoftheworksonthecapacityforfloodwaterstorage.
• Damagetoanyflooddefenceembankmentsshallbeimmediatelyrepairedtoastandardequaltoorbetterthantheexistingembankments.
• EirGridshallcarefullyexaminedevelopmentproposalstoensureconsistencywiththerequirementsofThe Planning System and Flood Risk Management: Guidelines for Planning Authorities(DEHLG,2009)15.
• EirGridshallengagewithplanningauthoritiesatanearlystage,utilisingarrangementsforpre-planningapplicationconsultationwithregardtoanyfloodriskassessmentissuesthatmayarise.
• EirGridshallcarryoutasite-specificfloodriskassessment,asappropriate,andcomplywiththetermsandconditionsofanygrantofplanningpermissionwithregardtotheminimisationoffloodrisk.
EMM8C Soils and Geology
EMM8C(i) Geological Features
• Siteinvestigationsshallbeundertakenatintervalsandspecificlocationsalongthepowercircuitroute.Thisinformationshallbeusedtoplansiteworkoperationstoanticipate,avoidorminimiseconstructionimpactsarisingfromdisturbanceofsub-surfaceconditions.
• Cutandfilloperationsshouldbeavoidedunlessabsolutelynecessary.
• RouteselectionandlowertierassessmentsshouldconsultGeologicalSurveyofIrelandasappropriateinrelationtogeologicalheritagesiteseitherrecommendedforNHAorCountyGeologicalSitedesignation.
EMM8C(ii) Soil
• Heightofstockpilesshouldbelimitedtolessthat3mandstoragetimewillbeminimised.
• Materialhandlingandreinstatementoperationsshouldfollowgoodpracticetoavoidinadequateorovercompactionofthematerials.
• RouteselectionandlowertierassessmentsforpeatlandareasshouldconsiderrelevantgovernmentguidelinesondevelopmentintheseareasaswellasrelevantdatasetsincludingtheGeologicalSurveyofIreland’slandslidedatasetandTeagasc’ssubsoilsdataset.
EMM8C(iii) Mineral Resources
Thepowercircuitshallberoutedtoavoiddisturbancetoexistingorplannedoperationsofareasofextractionandlicensedmineralreserves.
EMM8C(iv) Contaminated Land
• Agroundinvestigationmaybeundertakentosurvey,analyseandassesstheareaswherethereisapotentialforthisrisktoarise.
• Followingthis,methodstatementsshallbepreparedtodealwithanyareaofcontaminatedground.
EMM8C(v) Bedrock
• RouteselectionandlowertierassessmentsshouldconsiderGeologicalSurveyofIreland’sbedrockdataasappropriateinordertoanticipateengineeringdifficulties.
• RouteselectionandlowertierassessmentsshouldconsiderIrishNationalSeabedSurveydataandINFOMARsurveydataasappropriatetoanticipatethenatureanddepthofstablesubstrateforoffshoreprojectsfoundationsandconnectiontoonshoregrid.
15Referencedstatutoryobligation
79
EMM8D Cultural Heritage• Wheretheproposedrouteisincloseproximityto
archaeologicalsitestheworkingareashallbekepttoaminimum.
• Pre-constructionworksshallbecarriedoutinthoseunrecordedareasidentifiedashavingarchaeologicalpotential.
• TherewillbefullimplementationofanArchaeologicalPlanincluding,pre-constructionworks,watchingbriefandexcavation.
• Wherepreviouslyunrecordedfindsareuncoveredduringconstruction,adequatearchaeologicalinvestigationandrecordingwillbecarriedoutbeforeconstructionworksintheseareasarecontinued.
EMM8E Landscape and Visual
Routesshallbeselectedaccordingtothefollowingcriteria:
• Avoidanceofareasdesignatedasbeingofscenicsensitivityorsignificance.
• Avoidanceofareasthatwoulddisproportionatelyimpingeuponsensitivelandscapefeatures–suchasprominentskylineridges,shores,rivercrossings.
• Avoidareasthatwoulddisproportionatelyimpingeuponsensitiveareasorsitesofculturalorhistoricsignificance–includingmonuments,listedandprotectedstructuresandtheircontextsandsites.
• Routeselectionandlowertierassessmentsshouldconsider(asappropriate)datafromthelandscapecharacterassessmentscontainedinthedevelopmentplansoflocalauthorities.
EMM8F Noise
Inrelationtonoisesensitivereceptors,theconstraintsmappingidentifiedareasofhighbuildingdensityandthereforeanyroutecorridorsselectedshallattempttominimiseimpactsonbuiltupareas.
EMM8G Liquid Effluent and Spillages
Portabletoiletswillbeprovidedatthesiteoffices.Theywillbeemptiedregularlybyaspecialistcontractorasappropriate.
EMM8H Solid Wastes
WasteManagementPlanswillbepreparedaspartoftheoverallprojectdesign.Thiswillidentifylikelywastearisings,approximatequantitiesandappropriatehandlinganddisposalmethods.
EMM8I Construction of New Substations and Extension of Existing Substations
EMM8I(i) Theconstructionofnewsubstationscanhaveasignificantimpactparticularlywheretheareaisundeveloped.Siteselectionneedstoensuresensitivelandscapesandhabitatsareavoided.Opportunitiesfornaturalscreeningfromtopographyandvegetationshouldbemaximisedandusedwhereverpossibleasthiswillprovidethebestopportunityforintegratingthefacilityintotheexistinglandscape.
EMM8I(ii)Itwillbeimportanttoensurethatsubstationsarenotlocatedwithinthefloodplainofmajorwatercourses,whichcouldimpactontheaccessandfunctioningofthesubstation.Also,itwillalsobeimportanttoensurethatnewsubstationlocationsavoiddesignatedconservationsitesandsensitivehabitatswherepossible.
EMM8I(iii) Whereexistingsubstationsneedtobeextendeditwillbeimportanttoensuretheextensiondoesnotimpactonanynearbybuiltupareasandthattheextensionisappropriatelydesignedtoensureadequateintegrationwiththeexistingenvironment.Thescaleoftheextensionshouldbesuitedtothesurroundingareaandshouldnotbeinappropriategiventhesizeoftheexistingfacilityanditssurroundings.
80
EMM8J Reinforcement of the Transmission System in the Regions16
EMM8J(i) Midlands Region TheMidlandsRegionistransectedbymanykilometresofmajorandminorgridinfrastructureaswellashavingasignificantconcentrationofjunctionsandsubstations–manyassociatedwithexistingorformerpowerstations.Theseroutesandsitesofferstrongprecedentthatshouldbere-usedwhereverpossible.Itshouldberecognisedthatlargeareasofcut-overpeatlandsmaynotbesuitablelow-resistanceroutingoptionsasmanyofthesesitesarenearingtheendofproductionandmostifnotallwillshortlybereinstatedaspeatlandsitesthatarelikelytobedeemedtobesensitive–ifnotprotected–habitats.
NewmajorgridprojectsinthisRegionwillbechallengedwhentryingtoidentifyoptimumcrossingpointsoverthesensitiveShannonsystem.Existingcrossingpointsshouldbere-usedorintensifiedwhereverpossible.Suchcrossingpointsshouldbeidentifiedandsecuredinregionalandcountydevelopmentplansasamatterofurgency–theyarenationallysignificanteconomicassets.
EMM8J(ii) South-East Region LargerscalegriddevelopmentsintheSouth-EastRegionshouldparallelcoastalplainsandmajorriversystems–ideallyoccupyingthetransitionalfoothills–withoutencroachingoneitherthemoresensitiveuplandsortheimmediateenvironsofriversandcoasts.
Mostmajorrouteswithinthisregionfollowthetransitionbetweenuplandsandlowlandsandcauselittleadverseenvironmentaleffect.Iffuturedevelopmentcontinuesthisgeneralpatternthereisalowpotentialforsignificanteffectstoarise.
EMM8J(iii) Mid-West Region MajorgriddevelopmentworksintheMid-WestRegionshouldre-useorcloselyfollowestablishedroutingsorareaswithestablishedprecedentoflarge-scaleinfrastructuralandindustrialdevelopment.Newworksshouldparallelthecoastsandrivers–whichcontaindensecorridorsofancientlyestablishedsettlement–whileavoidingmoresensitiveuplandinteriors.Highlevelsofruraldwellingsinsomeareasmayrequiresub-optimalproximitytosomeenvironmentalsensitivities,suchasculturalheritage.
EMM8J(iv) South-West Region IfnewgriddevelopmentcontinuespatternsoffollowingthestronglyEast-WesttrendingrivervalleysintheSouth-WestRegionthereisalowpotentialforsignificantadverseeffectsontheenvironment.Majorgriddevelopmentsshouldbeconfinedtothemoreenvironmentallyrobustcentreandeastofthisregion.
ThedevelopmentofnewtransmissionlinesbetweenMoneypointandCorkCitywouldneedtocarefullyconsiderecologicalandvisualimpactissues,especiallyinuplandareas.Alternativesshouldconsiderthereuseofexistingpowerandtransportlinks.
EMM8J(v) Dublin & Mid-East Region ItwouldbeusefultointegratewithDevelopmentplans–bothatRegionalandCountylevel-toidentifyinfrastructurecorridors–ideallyparallelingtheexistingandemergingmajorroadandrailcorridorsthatwilldevelopintheDublinandMid-EastRegionduringtheperiodto2025.Itwouldalsobeofmerit,forworkinginexistingandemergingurbanandperi-urbanareas,toclearlyidentifycriteriathatwouldleadtodeterminingwhenandwheretoundergroundelectricityinfrastructure.
16NotethatnospecificmeasurearestatedherefortheBorderandWestRegions;allothermitigationmeasuresapplyasrelevant.
81
LandUsePlansforUrbanAreasshouldbeencouragedtospecificallyzonelandforsub-stationsandtoprotectexistingstrategiccorridorsfrominappropriatedevelopment.
EMM8K National and EU Legislation and Plans/Programmes
Wheregridrelateddevelopmentisproposed,EirGridwillseektocontributetowardstheprotectionofenvironmentalfeatures,asrelevantandappropriate
toEirGrid’sresponsibilitiesandobligationsundernationalandEUenvironmentallegislationandincludingthosewhichrelatestospecificregional/nationalplans/programmesforparticularaspectsoftheenvironmente.g.CatchmentFloodRiskAssessmentandManagementStudyPlans,RiverBasinDistrictManagementPlansandFreshWaterPearlMusselSubBasinManagementPlans.
TheOval,160ShelbourneRoad,Ballsbridge,Dublin4.
Tel +353(0)1677 1700Fax +353(0)1661 5375
PRNA11/0158
TheOval,160BótharShíolBhroin,DroicheadnaDothra,BaileÁthaCliath4.
Tel +353(0)1677 1700Fax+353(0)1661 5375
Environmental Impact Services2ndFloor,TheCourtyard,25GreatStrandStreet,Dublin1.