2011 - 2016...implementation programme 2011 - 2016 grid25 implementation programme 2011 - 2016...

89
GRID25 Implementation Programme 2011 - 2016

Upload: others

Post on 01-Sep-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

GRID25Implementation Programme

2011 - 2016

Page 2: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

www.eirgrid.com

Page 3: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

GRID25Implementation Programme

2011 - 2016

Page 4: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

Section 1 - Introduction and Context

1.1 Context 2

1.2 TheVisionofGrid25 5

1.3 StrategicObjectivesofGrid25 5

1.4 TheStrategicPolicyContextforGrid25 6

1.5 TheChallenges 7

Section 2 - The Grid Development Strategy

2.1 Introduction 9

2.2 TheGrid 9

2.3 TransmissionSystemPlanning 9

2.3.1 ElectricityDemand

2.3.2 Generation

2.3.3 Potentialmajordemandcentres

2.3.4 Interconnection

2.3.5 Planning,environmentalandcommunityconsiderations

2.4 FutureGridRequirements 13

2.4.1 Onshoregrid

2.4.2 Offshoregrid

2.5 TheGridDevelopmentStrategy 15

2.5.1 ReinforcementofthetransmissionsystemintheBorderRegion

2.5.2 ReinforcementofthetransmissionsystemintheMidlandsRegion

2.5.3 ReinforcementofthetransmissionsystemintheSouth-EastRegion

2.5.4 ReinforcementofthetransmissionsystemintheWestRegion

2.5.5 ReinforcementofthetransmissionsystemintheMid-WestRegion

2.5.6 ReinforcementofthetransmissionsystemintheSouth-WestRegion

2.5.7 ReinforcementofthetransmissionsystemintheDublinandMid-EastRegions

Section 3 - Towards A Planning And Environmental-Led Approach To Electricity Transmission

Infrastructure Development

3.1 Context 29

3.2 GovernanceandProcess 29

3.3 EnvironmentalDataandGuidelines 31

3.4 ProceduresforTransmissionSystemPlanning 34

Section 4 - Planned Network Developments

4.1 Context 35

4.2 NetworkReinforcementDevelopments 39

4.3 DSOConnections 40

4.4 GeneratorConnections 41

Table of Contents

Page 5: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

Section 5 - Environmental Mitigation Measures

5.1 Introduction 43

5.2 EMM1FullIntegrationofPlanningandEnvironmentalConsiderationsinEirGrid’s

TransmissionSystemPlanning 45

5.3 EMM2PreparationofStrategicEnvironmentalConstraintsMapping 46

5.4 EMM3PreparationofEvidence-BasedEnvironmentalGuidelines 46

5.5 EMM4ConsiderationoftheBroadestPossibleRangeof

AlternativesinallFutureEnergyTransmissionStrategies 50

5.6 EMM5PreparationofTransmissionDevelopmentPlanEnvironmentalAppraisalReport 50

5.7 EMM6OngoingCo-operationinpreparationofRenewableEnergyGenerationGuidelines

andStrategies 50

5.8 EMM7IntegratingOffshoreGridconnectivityrequirementsandenvironmental

considerationsinEirGrid’sStrategicEnvironmentalFramework(SEF) 51

APPENDIX A – Network Reinforcement Projects, Demand Customer and DSO Connection

Projects, and Generator Connection Projects, identified in EirGrid’s Transmission

Development Plan 2010.

A1 NetworkReinforcementProjects 53

A2 DemandCustomerandDSOConnections 67

A3 GeneratorConnections 71

A4 ConnectionofInterconnectors 74

APPENDIX B – Mitigation Measures 75

Page 6: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

1

Page 7: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

2

1.1 ContextEirGridplc(“EirGrid”)istheNationalelectricityTransmissionSystemOperator(TSO).TheEuropeanCommunities(InternalMarketinElectricity)Regulations,2000(SINo.445of2000)setsouttheroleandresponsibilitiesoftheTSO;inparticular,Article8(1)(a)givesEirGrid,asTSO,theexclusivefunction:

“to operate and ensure the maintenance of and, if necessary, develop a safe, secure, reliable, economical, and efficient electricity transmission system, and to explore and develop opportunities for interconnection of its system with other systems, in all cases with a view to ensuring that all reasonable demands for electricity are met having due regard for the environment.”

“Develop”inthiscontextreferstoplanning,routing,obtainingconsentsetc,butnottoconstructingthetransmissionsystem(theGrid),whichiscarriedoutbyESBNetworksasTransmissionAssetOwner(TAO).NeitherdoesEirGrid’sroleincludethegeneration,distributionandsellingofelectricityinIreland.

Section 1 - Introduction and Context

Grid251isahigh-levelstrategyoutlininghowEirGridintendstoundertakethedevelopmentoftheelectricitytransmissiongridintheshort-,medium-andlonger-terms,tosupportalong-termsustainableandreliableelectricitysupply.TheGrid25strategyseekstoimplementtheprovisionsofthe2007GovernmentWhitePaperonEnergy-Delivering a Sustainable Energy Future for Ireland intermsofdevelopmentofelectricitytransmissioninfrastructure.

Gridplanninganddevelopmentarehighlydynamicprocessesthatareconstantlyrespondingtochangesindemandandtheemergingconditionsofthegrid2.Griddevelopmentisessentiallyareactiveprocess–reactingto,andfacilitating,identifieddemandforanenhancednetworkinanarea,forexamplenewgenerationsources,ornewdemandcentressuchasnewcentresofemploymentorpopulationgrowth.Assuch,griddevelopment,andGrid25inparticular,doesnotdictatewheresuchnewdemandistooccur;rather,gridplanninganddevelopmenthassignificantcognisanceofotherstrategiesforspatialandstrategicplanninganddevelopment.

ThisGrid25 Implementation Programme(IP)isapracticalstrategicoverviewofhowtheearlystagesofGrid25areintendedtobeimplemented.TheIPidentifiesthebestcurrentunderstandingofthosepartsofthetransmissionsystemthatareenvisagedaslikelytobedevelopedoverthenextfiveyears–thisisseparatelysetoutinEirGrid’sannualTransmissionDevelopmentPlan(theidentifiedprojectsofwhicharereproducedinSection4andAppendixAofthisIP)togiveeffecttocurrentGovernmentPolicy.TheIPidentifiestheissues,objectivesandassociatedprocessesthatwillneedtobeadoptedwhenmakingdecisionsabouthow

1Grid25–“AStrategyfortheDevelopmentofIreland’sElectricityGridforaSustainableandCompetitiveFuture”,publishedbyEirGridinOctober2008.

2ThisdynamismisreflectedintheStatutoryreportingprocessesoftheCommissionforEnergyRegulation(CER)whichrequirethepublicationofannualreviewsandupdateofaTransmissionDevelopmentPlan–preparedinaccordancewithArticle8(6)ofTheEuropeanCommunities(InternalMarketinElectricity)Regulations,2000(SINo.445of2000),andwhichissubmittedforapprovaltotheCommissionforEnergyRegulation(CER).

Page 8: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

3

andwheredevelopmentswilloccur.Inthiswayitestablishestheparametersandcriteriafortheprocessesbywhichsubsequentdecisionswillbemade.

ThisIPandaccompanyingStrategicEnvironmentalAssessment(SEA),incorporatesadviceandcommentsreceivedfromboththeEnvironmentalProtectionAgency(EPA)andtheNationalParksandWildlifeService(NPWS)oftheDepartmentofArts,HeritageandtheGaeltacht(DAHG),aswellasfromotherpartiesduringtheperiodofpublicconsultationinrespectoftheDraftIP.TheSEAwasundertakenfollowingascopingexercise,inlinewithcurrentbestpracticeforthecarryingoutofSEAsforNational-scaleprogrammes.Theseassociateddocumentshavealsobeenrevisedinresponsetosubmissionsmadeduringtheperiodofpublicconsultation.

Itisimportanttonotethat,whileotherSEAs,suchasinrespectofland-useplans,maymakeretrospectiverecommendations3abouthowtheplansorpoliciesshouldbealteredtoavoidimpactsontheenvironment,duetothehighlevelandstrategicnatureoftheSEAforthisIP,mostoftherecommendationshavebeenabouthowtochangedecision-makingprocesseswithintheIPitself.Assuch,therecommendedmitigationmeasuresinmanyinstanceshavealreadybeenincorporatedintotheIPinaniterativeprocess,someofwhichhavebroughtaboutchangesintheorganisationalandworkingpracticeswithinEirGrid.ThesehighlevelmitigationmeasuresareoutlinedinSection5ofthisdocument,whilelowertiermeasuresareincludedinAppendixB.

Itisintendedthatfollowingadoption,theIPandassociatedSEA4willhavea5–yearlifespan,withthereviewanddraftingprocessforthesubsequent

3Theseareusuallyincludedas‘mitigationmeasures’

4PresentedinanEnvironmentalReport(ER)withaccompanyingNaturaImpactStatement

Page 9: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

4

Figure 1.1 Structure for Grid25 strategy and associated Implementation Programme, SEA, Transmission Development Plan* and associated Environmental Appraisal Report.

TDP

TDP EAR

TDP EAR

TDP EAR

TDP EAR

TDP

IP5Year

IPReview5Year

Grid 25

SEA

SEA

EAR

*TheTDPisafiveyearplanwhichissubjecttoannualreview.

Allreferencesto‘TransmissionDevelopmentPlan(TDP)2010’intheIP,andassociatedSEAdocuments,refertothe‘DraftTDP2010’whichiscurrentlywiththeCommissionforEnergyRegulation(CER)forformalreviewandapproval.

Page 10: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

5

IPandSEAcommencingwithinthefinalyearofthatlifespan.However,thecontentofthesedocumentswillbesubjecttoongoingreviewandupdateovertheperiodofGrid25,inthecontextoftheEirGridTransmissionDevelopmentPlan,whichisupdatedannually.AnEnvironmentalAppraisalReport(EAR)willbeproducedtoaccompanyeachannualTDP,todemonstratehowtheTDPisinaccordancewiththeprovisionsoftheIPandSEA,ortoidentifyanyupdatestothesedocuments.OngoingmonitoringmeasuresassetoutintheSEAwillalsobeaddressedineachannualEAR.

ThisrelationshipissetoutgraphicallyatFigure1.1.

1.2 The Vision of Grid25Giventhatthedemandsfortransmissioninfrastructurearelikelytobefardifferentin2025,andbeyond,thancurrently,EirGridmustplanforthelonger-termfuturestrategictransmissiondevelopmentandreinforcementneedsoftheelectricitytransmissionnetwork.

TheVisionofGrid25“is of a grid developed to match future needs, so it can safely and reliably carry power all over the country to the major towns and cities, and onwards to every home, farm and business where the electricity is consumed and so it can meet the needs of consumers and generators in a sustainable way”(p.13).TheStrategytoachievethisvisionstates,interalia,:

“Grid25 will deliver an efficient transmission network for Ireland’s social and economic development. It will have the necessary capacity to reliably transport the future anticipated power levels from renewable and conventional generators and interconnectors to the cities and towns and the villages where the power is required.

We will follow international best practice and innovative methods to provide the necessary transmission capacity. The technology options

available to implement Grid25 will increase as research and development is carried out. We will be proactive in investigating and adopting new technologies taking due consideration of the cost and effectiveness of the technology”.(p.21)

Grid25notesEirGrid’sStatutoryobligationtobalancetheprovisionofreliabletransmissioninfrastructurewiththecoststothefinalcustomerandwiththeimpactofthatinfrastructureontheenvironment(p.21).

1.3 Strategic Objectives of Grid25IndevelopingtheGrid,theGrid25strategyenvisagesthedeploymentofstrategicalternativesdesignedforthelong-termdevelopmentofasafe,secure,reliable,economicandefficientgrid.Inthiscontext,theGridDevelopmentStrategyofGrid25(pp21-22)notesthat,inconsiderationofthecapacityofnewtransmissionlines,therewillbeapositivepresumptiontowardsbuildingnewlinesat400kVandat110kVwhereappropriate.Buildingat400kVratherthan220kVismoreefficientandprovidesgreaterpowercarryingcapability.Buildingone400kVcircuitavoidstheneedforbuildingamultiplicityof220kVand110kVlinesandsohaslesslong-termimpactontheenvironmentandonlocalcommunities.Inthelongerterm,itmaybeappropriatetoupgradethe220kVnetworkto400kV,forsimilarreasonsofefficiencyandcapacity.EirGridwillexamineeachcaseastheneedtoupgradearises.

TheStrategynotesEirGrid’scommitmenttoseektominimisethenetlengthofnewlinebuildinaregionthroughanumberofinitiatives(p.22):

• Byutilisingtheexistingnetworkwherepossibletoavoidbuildingnewoverheadcircuits.Re-utilisingtheexistingnetworkmaybemorecostlythanbuildingnewcircuits,butmayresultinalowerimpactontheenvironment;

Page 11: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

6

• Seekingtoup-rateexistinglinesbyusingahighercapacityconductor,whereappropriate,toavoidtheneedformajorstructuralchangesandsotominimisesecurityissues;

• Wheretherequiredincreaseincapacitycannotbeachievedthroughanewconductor,consideringupgradingthecircuittoahighervoltage;

• Whereappropriate,consideringreplacinganexistingsingle-circuitlinewithadoublecircuitlinetoprovidetherequiredadditionalcapacity;whilethisisamorecostlyoption,andlessreliablethanhavingtwoseparatelines,itavoidsbuildinganewlineonaseparateroute;

• Inlimitedcircumstances,puttingcertain110kVcircuitsundergroundtominimisetheimpactofnewbuildinaregion.Thismaybeconsidered,forexample,inareaswherethereiscongestionofurbandevelopment,amultiplicityofoverheadlines,arelativelywideexpanseofwater,oranareaofuniquenaturalbeauty;

• ExaminingthepotentialforusingHVDCtechnologyforcertainapplicationswhereappropriate,forexamplesuchastransportinghighvolumesofpoweroverlongdistances;

• ConsideringtheappropriatenessofnewtowerdesignsandothermitigatingmeasuresoutlinedintheGovernment-sponsoredreport,preparedbyEcofys,onThe Comparative Merits of Overhead Electricity Transmission Lines Versus Underground Cablesinordertominimisethelandscapeandvisualimpactofnecessaryinfrastructure,andtakingaccountoftheNationalLandscapeStrategywhenpublished.

1.4 The Strategic Policy Context for Grid25

IrishenergypolicyissetfirmlyinaglobalandEUcontextwhichhasputenergysecurityandclimatechangeamongthemosturgentinternationalchallenges.Inpursuitofthis,theEUhassetalegallybindingobligationforMemberStatesthatgreenhousegasesacrosstheEUmustbereducedby

Page 12: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

7

atleast20%by2020,comparedwith1990levels.

ThestrategiccontextforenergyinfrastructureissetoutinanumberofpolicydocumentscoveringNational,RegionalandLocallevels,andcomprisingbothspatialandnon-spatialplanningpolicy.Theseinclude:

-IrishGovernment’sEnergyWhitePaper Delivering a Sustainable Energy Future for Ireland(March,2007)

- NationalDevelopmentPlan2007–2013, NationalSpatialStrategy2002–2020,

- RegionalPlanningGuidelines2010–2022,

- CountyDevelopmentPlansandrelevant LocalAreaPlans.

The2007WhitePapersetsatargetof33%ofelectricityproducedfromrenewablegenerationby2020;thiswassubsequentlyincreasedto40%.

Some58%ofcurrentdemandforelectricityisingatewaycitiesandtowns,asidentifiedintheNationalSpatialStrategy(NSS).TheNSSdefinesgatewaysashavingastrategiclocation,nationallyandrelativetotheirsurroundingareasandprovidingnational-scalesocialandeconomicinfrastructureandsupportservices.TheGrid25strategywillcontributetoachievingtheNSSgoalofdevelopinggatewaysandachievingbalancedregionaldevelopment.Inthisstrategiccontext,theprovisionsandpoliciesofthevariousRegionalPlanningGuidelinesareofessentialimportance.

EirGridpublishesaTransmissionForecastStatementannuallywhichhighlightsopportunitiesfortheconnectionofdemandat31pointsonthegrid.ThedocumentpresentstheopportunitiesforgeneratorconnectionsidentifiedthroughtheGate3connectionprocessandoutlinesthegenerationopportunitiesarisingfromGrid25.

EachPlanningAuthorityisrequiredtoprovideanobjectivewithinitsDevelopmentPlanforthe

provision/facilitationofinfrastructureincludingenergy.Inaddition,Section10(1B)ofthePlanningandDevelopmentActs2000–2010requiresthatallplanningauthoritiesshall,withinoneyearaftermakingRegionalPlanningGuidelines,prepareaCoreStrategy.TheCoreStrategymustshowthatCountyDevelopmentPlanobjectivesareconsistentwithnationalandregionaldevelopmentobjectivesintheNationalSpatialStrategyandRegionalPlanningGuidelines.Thisensuresthatthestrategicvisionofthesehigher-levelplanningandpolicydocumentsareappropriatelyandadequatelyreflectedinlocalDevelopmentPlanpoliciesandobjectives.

Thecorestrategymust,amongotheraspects:

- Detailandtakeaccountofexistingandproposedtransmissioninfrastructureinacounty;

-Providetheframeworkfordecidingonthescale,phasingandlocationofnewdevelopment,havingregardtoexistingservicedandplannedinvestmentoverthecomingyears.

Consequently,keyelectricityprojectswhicharecriticaltothefuturedevelopmentofacountyandregioncanbeprioritised.

1.5 The ChallengesEnergy Potential

GivenIreland’ssignificantpotentialforgenerationofrenewableenergythroughbothonshoreandoffshorewindenergy,andothermarinerenewableenergygeneration,thepotentialexiststomakeuseofthesenaturalresourcestoprovideforIreland’sinternalenergyneeds,meetNationalcommitmentstoreduceCO2emissionlevelsundertheKyotoProtocol,andtomakeIrelandmoreenergysecure.EirGrididentifiesfurtherrenewablegenerationasanincreasinglyimportantpartoftheoverallgenerationmix,andiscommittedtosupportingandfacilitatinggovernmentpolicyforthecapturingofrenewableenergy,primarilybymeansofthe

Page 13: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

8

developmentofarobust,secureandreliableelectricitytransmissiongrid.TheGovernment’srenewablegenerationtargetfor2020istomeet40%ofelectricityconsumptionfromrenewableenergysources.EirGrid’sGrid Development Strategy,assetoutinGrid25,involvesplanninganddevelopingthetransmissionsystemtomeetanticipatedlonger-termgeneration/demandneeds,therebyprovidingforamorecosteffective,optimalandefficientsystemthanwouldbethecasewithamoreshort-termandpiecemealapproach.Inparticular,Grid25providesfortheoptimalconnectionofaverysignificantcapacityofrenewablegenerationinIrelandoverthecomingyears;suchconnectionwilloccurthroughalong-termstrategicprogrammeoftransmissiondevelopment.

Economic Development

Continuedcommitmenttoinvestmentinnationalstrategicinfrastructure,includingtransmissioninfrastructure,providesakeybasisforeconomicrecoveryandgrowth.Givencurrenteconomiccircumstances,thereisaneedtoprioritiseprojectsandexpenditurewiththemostimmediatepositiveimpactontheeconomyandemployment.InvestmentmustalsobedeliveredinacoherentandefficientmannerandbeconsistentwiththeGovernmentvisiontocreatea‘SmartEconomy’.Theprovisionofenergyinfrastructureisoneofthekeydriversforeconomicgrowthandregionalandnationalcompetitiveness.TheGovernmenthasendorsedEirGrid’sstrategyforNationalinfrastructuredevelopmentasperGrid25,andsupportssignificantinvestmentinthestrategicandlonger-termdevelopmentoftheelectricitytransmissionnetwork

Export of Energy

Inresponsetothe2007GovernmentWhitePaperonEnergy-Delivering a Sustainable Energy Future for Ireland,EirGridhascarriedoutanassessmentofthecostsandbenefitsofadditionalinterconnection

betweentheislandofIrelandandtheUKandFrance5(inadditiontotheexistingMoyleInterconnector 6andtheEast-WestInterconnector,currentlyunderconstructionbyEirGridbetweenIrelandandWales).Incarryingoutthisassessment,EirGridhasexaminedabroadrangeofscenariossuchasthelikelyrequirednumberofinterconnectors,differentfuelpricesanddifferentgenerationportfolios.Thereportconcludesthatenhancedinterconnectionbetweentheall-islandgridandothergridshasthepotentialtodeliversignificantbenefitstotheislandofIreland.

Balanced Regional Development

BecauseoftheimportanceoftheelectricitysystemtocustomersalloverIreland,EirGridisveryconsciousofgovernmentpoliciestosupportregionaldevelopment.Theinvestmentinthistransmissionstrategyisdistributedacrossallregions,andtherebywillsignificantlyimproveregionalelectricityinfrastructure,andwillprovidethebackboneforfurthereconomicdevelopmentintheregions.FurtherdevelopmentemergingfromGrid25willmaintainpriorityinsupplystandardsacrossallpartsofthenetwork,thusenablingeconomicdevelopmentinallregions.

Itisimportantthatnationalandregionalspatialplanninganddevelopmentpoliciesandstrategiesrecognisetheestablishedrelationshipbetweeneconomicgrowthandelectricityconsumption.Aspartoftheeconomicrecoveryofeachregion,andthecountryasawhole,itisimportantthateachregionhasamodernefficienttransmissionnetworkthatwillallowittocompetewithotherregionsinIrelandandEuropeinattractingpotentialinvestorsandemployers.Inthiscontext,itisimportantthatlocalauthorities,localandcountydevelopmentplans,andregionalplanningguidelinesensureadequatepriorityforkeyelectricitytransmissionprojectsthatarecriticaltothefuturedevelopmentofaregion.

5InterconnectionEconomicFeasibilityReport,EirGrid,November2009,availableatwww.eirgrid.com

6TheMoyleInterconnectorconnectstheelectricitygridsofNorthernIrelandandScotland

Page 14: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

9

2.1 IntroductionThehighvoltage(HV)electricitytransmissionnetwork(110kV,220kVand400kV)formsthebackboneoftheelectricitysupplysysteminIreland.High-qualityandreliableelectricitytransmissioninfrastructure,providingqualityperformance,isvitalforIreland’songoingsocio-economicdevelopment,andthusisofnationalstrategicimportance.

2.2 The Grid Thenationalelectricitytransmissiongridplaysavitalroleinthesupplyofelectricity,providingthemeanstotransportpoweracrossameshednetwork,linkinggeneratorlocationswithoftensignificantlyspatiallydistantdemandcentres.The400kVnetworkprovidesahighcapacitylinkbetweenMoneypointgenerationstationonthewestcoastandtheGreaterDublinAreaontheeast.The220kVnetworkformsanumberofsinglecircuitloopsaroundthecountry.The110kVnetwork,whichisthemostextensiveelementoftheoveralltransmissionsystem,extendsacrossthecountry(refertoFigure2.1).

TheIrishnetworkiscurrentlyconnectedtothetransmissionsystemofNorthernIrelandprimarilybymeansofasingle275kVdoublecircuitinterconnectionbetweenLouthandTandrageesubstations.Therearealsotwolower-capacity110kVconnectionswiththeNorthernIrelandnetwork,atLetterkennyinCo.DonegalandCorraclassyinCo.Cavan.

ThetransmissionsystemontheislandofIrelandisalmostentirelyconstructedasoverheadline(OHL),exceptinverylimitedcircumstances,suchascongestedorbuilt-upareas,whereundergroundcable(UGC)used.

2.3 Transmission System PlanningThemaindeterminantsintransmissionsystemplanningare:

• Thedemandforelectricityfromconsumers;

• Additionalgenerationfromnewgenerators,comprisingbothconventionalgenerationandrenewablegeneration;

• Potentialmajordemandcentres,i.e.NSSgatewaysandhubs;

• Interconnectionandpotentialimportandexportofenergy.

Theseareaddressedinthefollowingsub-sections.

2.3.1 Electricity demand

Inmanycases,growthindemandforelectricityresultsinhigherpowerflowsonthetransmissionnetwork.Awellestablishedrelationshipexistsbetweeneconomicgrowthandelectricityconsumption.WherepowerflowsexceedthecapabilityoftheGrid,reinforcementisnecessary.Grid25isastrategydesignedtomeetincreasinganticipateddemandforelectricity.

InthecontextoftheGovernmentcommitmentfor40%ofNationalelectricitysupplyfromrenewablesourcesby2020,andtheclearpotentialforlonger-termfutureexportofenergy,EirGridisadoptingamoreproactiveapproachtothestrategicplanningofthetransmissionnetwork,wherebytransmissioninfrastructureisplannedandprioritisedinanticipationofforecastedlonger-termfuturelevelsofimport,exportandgenerationdemand.Thisstrategicapproachiscrucial,giventherelativelylonglead-intimesforsuchinfrastructuredevelopment–includingprojectidentification,studyandassessment,planningandconsenting,constructionandenergisation.ThisiswhytheGrid25strategyisbeingactivelypursuedinthecontextofashort-termeconomicdecline.

Section 2 - The Grid Development Strategy

Page 15: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

10

Figure 2.1 Map of the Irish Transmission System as at December 2010 (extract from EirGrid Transmission Development Plan 2010)

Page 16: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

11

2.3.2 Generation

Asnotedabove,generationfromrenewableenergysourcesisakeyfactorinGrid25tomeetingtheGovernmenttargetof40%by2020,toreducingcarbonemissions,andtomaintainingasustainableenergysupply.Itisrecognisedinthe2007GovernmentEnergyWhitePaperthatwindenergywillplayapivotalcontributiontomeetingthatgoal.Marinetechnologiesandbiomassarealsoexpectedtocontribute.

Ingeneral,additionofgenerationoutputcreatesamuchgreaterandimmediateimpactonthegridthandemandincreases,duetothesizeofagenerator,orcumulativesizeofclusteredgenerators,relativetothemoregradualincreasesinlocaldemand.Thegridoftenhastobereinforcedtofacilitatetheflowofpowerfromthegeneratortotherestofthesystem.Thisisparticularlyapparentinrespectofnon-traditionalmodesofgeneration,suchasrenewables,wheremanyofthelocationssuitableforrenewableenergygenerationschemesareinareaswheretherehas,historically,beenlittleornogenerationdevelopmentandassociatedprovisionofsupportingtransmissioninfrastructure.

Theaggregateofrenewablegenerationcapacityinsomeareasisequivalenttothatofalargeconventionalgenerationstation.Inmanycases,theexistingtransmissionnetworkisofinsufficientcapacitytocarrythepowerfromthesegenerationsources.Significantreinforcementandnewbuildofthegridisthereforerequiredtocaterforthenewpowerflowsfromrenewablegeneration.

Inshort,itwillnotbepossibletoutiliseIreland’snaturalresourcesofrenewableenergywithouttheassociatedessentialupgradingandreinforcementoftheNationalelectricitytransmissionnetwork,asoutlinedinGrid25.

2.3.3 Potential major demand centres

Asnotedabove,some58%ofcurrentdemandforelectricityisingatewaycitiesandtowns,asidentifiedintheNationalSpatialStrategy(NSS).TheNSSdefinesgatewaysashavingastrategiclocation,nationallyandrelativetotheirsurroundingareasandprovidingnational-scalesocialandeconomicinfrastructureandsupportservices.TheGrid25strategyendorsestheNSSgoalofdevelopinggatewaysandachievingbalancedregionaldevelopment.

2.3.4 Interconnection

TheprimarybenefitsofInterconnectionare:

• Improvingcompetition–bylinkingtootherEuropeanmarkets;

• Supportingdevelopmentofrenewablepowergeneration–byenhancingtheflexibleexchangeofpowerflowsovertheislandofIreland.Thiswillenabletheconnectionandoperationoflargervolumesofrenewablegeneration(especiallywindpoweredgeneration)throughouttheisland;

• Improvingsecurityofsupply–byprovidingadependablehighcapacitylinkbetweenthetransmissionsystemsofIrelandandothercountries.

TheexistingMoyleInterconnectorconnectstheelectricitygridsofNorthernIrelandandScotland.Ithasacapacityof500MWandcurrentlyiscapableofimporting450MWinwinterand400MWinsummerfromScotland.However,thisInterconnectorislimitedbycontractualarrangementstoanexportcapacitytoScotlandof80MW.Thisrestrictionisbeingreviewedatthemoment,anditisthereforeassumedforthepurposesofthisImplementationProgrammethatexportcapabilityisincreasedto400MW.

Page 17: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

12

EirGridiscurrentlydevelopingthe500MWEastWestInterconnectorbetweenIrelandandWales.Thishasascheduledcompletiondateof2012.

ItisthereforeassumedthattheislandofIrelandwillhavesome900MWofinterconnectionwiththeUnitedKingdomwithinthenextnumberofyears.

EirGridandNorthernIrelandElectricity(NIE)arecurrentlyprogressingtheplanningofasecondmajorinterconnectorbetweentheRepublicofIrelandandNorthernIreland.These,andotherpotentiallonger-termfutureinterconnectors,couldplayasignificantroleininternationalisingtheIrishenergymarket,andinfacilitatingtheanticipatedhighlevelsofrenewablegenerationontheisland,byprovidingameanstoexportexcessgenerationwhenoutputfromrenewablegenerationishigh,andtoimportpowerwhenitislow.

2.3.5 Planning, environmental and community considerations

EirGridiscommittedtoensuringthattheplanninganddevelopmentofthetransmissionnetworkoccursinaccordancewithallrelevantlegislation

andinternationalbestpractice.Recentchangesinlegislation(especiallytheHabitatsDirective),coupledwiththeexperienceofpublicconcernregardingtheperceivedeffectsoftransmissiondevelopments,particularlyasarticulatedinthepublicplanningprocessthroughwhichstrategicinfrastructurenowproceeds,meansthatenergyplanningmustnowdemonstrateconsideration,fromtheoutset,ofhowtoavoidorreduceenvironmentalandcommunityimpacts.

EirGridtakestheviewthatitwillnotbepossibletodevelopthetransmissionnetwork–andtherebytorealisethepotentialofthecountry’snaturalresourcesofrenewableenergy–withoutputtingplanning,environmentalandcommunityconsiderationsattheheartofitsTransmissionSystemPlanning.Ignoringtheseissueswilldelayorpreventthefuturedevelopmentofthetransmissionnetwork–resultinginincreasedcostsandreducedefficiencies.AssetoutinmoredetailinChapter3ofthisIP,EirGridappliesabestpracticeapproachtotheplanninganddevelopmentofalltransmissionprojects.

Page 18: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

13

2.4 Future Grid Requirements2.4.1 Onshore grid

The220kVnetworkwasfirstintroducedintheearly1960sinIreland,andthe400kVnetworkwasbuiltinthemid-1980s.Sincethistime,thisbulkpowernetworkhaschangedlittlewhiledemandoverthesameperiodhasgrownbyover150%,therebyleavinglittlecapacityforfurthergrowthontheexistingnetwork.Anticipatedincreasingpowerflowsonthenetworkmeansthatbetweennowand2025,thecapacityofthebulktransmissionsystemwillneedtobesignificantlyincreased.Theassociated110kVnetwork,whichprimarilybringspowerfromthebulknetworkstobulksupplypointsservingpopulationcentres,alsoneedstobesubstantiallyupgraded.

Grid25seekstoachieveabalancebetweencostsandtheimpactofnewtransmissioninfrastructure,throughmaximisingthecapabilityoftheexistinggridand,wherenewhighcapacityinfrastructureisrequired,buildingitmainlyatthe400kVvoltage.Thefollowingestimateshavebeenmaderegardingtheprovisionofinfrastructurerequiredtostrengthen

theNationaltransmissionnetwork,inaccordancewithGrid25(refertoFigure2.1):

• Grid25statesthatinrespecttofuturegridrequirementsthatapproximately1,150kmofnewcircuitswillberequiredupto2025tomeettheneedsofconsumersandgenerators.Thisrepresentsanincreaseofabout20%onthetotallengthoftheexistingnetwork.Ofthis,800kmwillneedtobeat220kVorhigher;theremaining350kmwillbeat110kV.Inadditiontothesecircuits,othercircuitswillbeneededtoconnectmanyofthenewgeneratorstothegrid;

• Some2,300kmoftheexistingtransmissionnetworkwillneedtobeupgradedby2025toprovidegreatercapacity.Thiscomprises1,100km,or70%,oftheexisting220kVnetwork,and1,200kmofthe110kVnetwork.

ItshouldbenotedthatthesefiguresmaybesubjecttochangeovertheperiodofGrid25,inresponsetochangingdemandandothercircumstances.

Figure2.2,extractedfromEirGrid’sTransmissionDevelopmentPlan2010,identifiesareasofchange,drivingplannednetworkdevelopment.

TheEirGridNationalControlCentre,Dublin

Page 19: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

14

Figure 2.2 Network Map Showing Areas of Change Driving Network Development (extract from EirGrid Transmission Development Plan 2010)

Page 20: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

15

2.4.2 Offshore grid

AnumberofscenariosforfutureelectricalgenerationandtransmissioninIrelandinvolvethedevelopmentofoffshoregridinfrastructure.ThishasthepotentialtooccurinmanyareasofftheIrishcoast,onaccountofdevelopmentsincludingtheexploitationofoffshorerenewableresources(wind,waveandtidal),increasedinterconnectionwithotherEUMemberStates,andtheparticipationofIrelandinaPan-Europeanoffshoregrid.Thishaspotentiallysignificantimplicationsforgriddevelopmentandforinteractionswithterrestrialandinshoreenvironments.

2.5 The Grid Development StrategyGrid25isaimedatdeliveringanefficientandhigh-qualityNationalelectricitytransmissionnetwork.Itwillensurethenecessarycapacitytoreliablytransportfutureanticipatedpowerlevelsfromrenewableandconventionalgeneratorsandinterconnectorstothecities,towns,villages,homes,andotherkeymarketswherethepowerisrequired.

TheNationalelectricaltransmissionnetworkisadynamicandmeshedsystemthatisconstantlysubjecttochange,andwherethechangeofasinglevariablehasthepotentialtochangethesystematlarge.Thismakesfuturepredictionsacomplexanddynamicprocess,whicharelikelytochangeovertimeasdemand,generationflows,andgridcapacityfluctuateandchange.

Figure2.3,andsubsequentFigures2.4-2.10,havebeenextractedfromEirGrid’sTransmissionDevelopmentPlan2010,andprovideahigh-levelindicativeoverview,andregionalbreakdown,ofthegeneralstrategyforthefuturedevelopmentofthegrid,aspertheprovisionsofGrid25.Thearrowscolouredgreenonthesefiguresprovideanindicativerepresentationofthestrategyfortransmissionofthepotentialflowofelectricity(betweendemand/loadcentres,generatorsandthesystematlarge).

Itshouldbenotedthatthesefiguresderivefromanun-scaledmapwithindicativerepresentation.Assuch,thesearrowsrepresenttheoverallintendeddevelopmentstrategy,anddonotpurporttorepresentspecificprojects;norisitintendedtosuggestthattheeventualrealisationoftheseprojectswillbecontainedwithintheareaofthesearrows.

Mostoftheelectricitytransmissionnetworkiscurrentlyperformingwithinrequiredstandards.Someareashavebeenidentifiedaslikelytorequirenetworkreinforcement,asdemandincreasesand/ornewgenerationisconnected.ThenetworkreinforcementprojectswithinthisImplementationProgramme(andwithinEirGrid’sTransmissionDevelopmentPlan2010),havebeendesignedtodealwiththeseemergingchallenges.

Becauseofthemeshednatureofthenetwork,theidentifiedstrategicdevelopmentsarelikelytobenefitawiderareathantheactualscopeofaparticularreinforcementproject.

Detailedstudiesarebeingcarriedouttoidentifynetworksolutionswhichwillbebroughtforwardintheplanningprocessandultimatelytoconstruction.SuchsolutionsareultimatelyidentifiedasprojectsinEirGrid’sTransmissionDevelopmentPlan2010followingreceiptofinternalCapitalApproval.Thekeyareasforplanned,andlonger-term,strategicgridnetworkdevelopmentasoutlinedinGrid25arepresentedonaregionalbasisbelow.

Page 21: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

16

Figure 2.3 Map Indicating Future Network Development Requirements (extract from EirGrid Transmission Development Plan 2010)

Page 22: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

17

2.5.1 Reinforcement of the transmission system in the

BORDER REGION

ThereareanumberofissuesthatneedtobeaddressedforthestrategicdevelopmentoftheelectricitytransmissioninfrastructureintheBorderRegionoftheRepublicofIreland.Theseissuesarisedueto:

• Thesignificantextentofnewgeneration,inparticulargenerationfromrenewablesources,thatisexpectedtomaterialisethroughoutboththeBorderRegionitself,andtheWestRegion;

• TherequirementtooptimallyintegraterenewablegenerationintheBorderRegionandNorthernIreland;

• Securityofsupplyintheregion.

Figure2.4providesanindicativestrategicrepresentationofareasrequiringfuturenetworkdevelopmentwithintheBorderRegion.

AsubstantialnumberofnewelectricitygeneratorsareintendingtolocateintheBorderRegion,particularlyinCountiesDonegalandSligo,andinNorthernIreland,eachofwhichwillrequireconnectiontotheelectricitytransmissiongrid.Thesemainlycompriserenewablegenerationsourcessuchaswindfarms.Theelectricity

transmissioninfrastructurewillrequiretobesignificantlystrengthenedtofacilitatesuchconnection,whichwillresultintherequirementbothtoupgradeexistinginfrastructureandtoconstructnewhighvoltageelectricitytransmissioninfrastructure.Thiswillhavethebenefitofstrengtheningtheoverallmeshedgrid,thusprovidingamoresecureandreliablesystemforinwardinvestment,aswellasfacilitatingthetransmissionofenergygeneratedtoloadcentresthroughouttheregionandthecountry.

EirGridiscurrentlyworkingwiththeelectricitynetworkoperatorandownerinNorthernIrelandtoidentifytheoptimalsolutionforthenetworktocaterforrenewablegenerationintheNorth-Westoftheisland(i.e.DonegalandthewesternpartofNorthernIreland).

ThesubstantialnumberofnewgenerationconnectionsbeingsoughtintheWestRegion(Section2.5.4)mayalsohaveanimpactontheBorderRegion.Furtherinter-regionaltransmissionreinforcementwillberequiredtoensurethatthisgenerationisadequatelyconnectedtotheNationalnetwork.

TheplannedsecondmajorinterconnectorbetweentheRepublicandNorthernIrelandisrequiredtoimprovecompetitionbyreducingtransmissionconstraintsthatarecurrentlyrestrictingtheefficient

TheCOntrolRoomatSONI,Belfast

Page 23: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

18

performanceoftheall-islandSingleElectricityMarket,tosupportthedevelopmentofgenerationfromrenewableenergysources,andtoimprovesecurityofsupplyontheisland.

Longer-termforecastedgrowthindemandforelectricityintheBorderRegion,asoutlinedinGrid25,willplacepressureonthetransmissionnetwork,requiringitsupgradingtoensurecontinuedsecurityofsupplytolocalhomesandbusinesses

intheRegion.StrengtheningofcircuitsbetweentheNorth-WestandNorth-Eastregionswillberequiredinthelonger-termtofacilitatepowerflows,including:

• FurtherintegrationoftheDonegalandNorthernIrelandnetworks;

• UpgradednetworkssupplyingDundalk;

• Upgradingoftheexistingtransmissionnetwork.

Figure 2.4 Areas Requiring Future Network Development In The Border Region

Page 24: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

19

2.5.2 Reinforcement of the transmission system in the

MIDLANDS REGION

ThetransmissionreinforcementprojectsintheMidlandsregionare,intheshort-term,drivenbytheneedtoincreasethesecurityandqualityofsupplytokeypartsofthenetwork.Thisisthecasewiththeconstructionofnew110kVcircuitsbetweenThornsberryandCushaling,andthereinforcementoftransmissioninfrastructureintheMullingararea.

A400/110kVsubstationisrequiredintheLaoisareatosupportthe110kVnetworksandprovidetherequisitelevelofsecurityofsupplyinLaois,CarlowandKilkenny.

AshighlightedinGrid25,longer-termreinforcementsareassociatedwiththetransmissionofwindgenerationthatwillassistinmeetingthegovernmentcommitmentofproviding40%oftheRepublicofIreland’selectricitydemandfromrenewablesourcesby2020.Thisincludesupgradingthetransmissionnetworktofacilitatepowerflowsfrombothrenewableandconventionalsourcesandmaximisetheuseofexistingpowercorridors.

Figure 2.5 Areas Requiring Future Network Development In The Midlands Region

Page 25: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

20

Page 26: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

21

2.5.3 Reinforcement of the transmission system in the

SOUTH-EAST REGION

Thereareanumberofissuesthatneedtobeaddressedregardingthelong-termstrategicdevelopmentofthetransmissioninfrastructureintheSouth-EastregionoftheRepublicofIreland.Theseissuesarisedueto:

• Generaldemandgrowth,particularlyintheGreaterDublinArea;

• NewgenerationconnectionswithintheSouth-Eastregion;

• ThepotentialforadditionaltransmissioninterconnectionwithGreatBritainandmainlandEuropebasedintheregion;and

• Thesignificantamountofwindgenerationexpectedtomaterialisethroughoutthecountry,particularlyintheSouthofthecountry.

Theexistingtransmissioninfrastructureisexpectedtocomeunderstrainbothatalocalandataregionallevel:Atalocallevel,demandgrowth(despitecurrentreductionsinload)placespressureonthetransmissioninfrastructure,requiringlocalreinforcement.Thereisalsoaneedtointegrate

newgenerationthatisplannedtoconnecttothenetwork.Ataregionallevel,alargeamountofwindgenerationisplannedtoconnectintheSouthofthecountryandwouldresultinanincreaseintheamountofenergythatwouldrequiretotraversetheSouth-Eastregion.Inordertofacilitatethesepowerflows,transmissionreinforcementwillberequired,(seeFigure2.6)asoutlinedinGrid25.

ThereisapotentialforfurtherinterconnectiontobeconstructedbetweentheRepublicofIrelandandUnitedKingdomand/ormainlandEurope.Givenitsgeographicallocation,theSouth-Eastregionisconsideredtoconstitutealikelyareaforterminationofafutureinterconnector.

Longer-termreinforcementintheregionincludes:

• StrengtheningofthehighvoltagetransmissionlinkstobothDublinandCorktofacilitateincreasedpowerflows;

• StrengtheningofthenetworkssupplyingmajorcitiesandtownsintheSouth-Eastregion;

• Reinforcementofcurrentinfrastructurewhilemaximisingtheuseofexistingcorridorswherepossible,throughup-ratingtheexisting110kVand220kVcircuits.

Page 27: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

22

Figure 2.6 Areas Requiring Future Network Development In The South-East Region

Page 28: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

23

2.5.4 Reinforcement of the transmission system in the

WEST REGION

Theissuesthatneedtobeaddressedinthelong-termstrategicdevelopmentoftheelectricitytransmissioninfrastructureoftheWestRegionincludethefollowing:

• Thesignificantquantityofgeneration,inparticulargenerationfromrenewablesources,thatisexpectedtomaterialiseintheWestRegion;

• Generaldemandgrowthinthearea.

AsubstantialnumberofnewelectricitygeneratorsareproposingtolocateintheWestRegion,andeachrequirestobeconnectedtotheelectricitygrid.Thesegeneratorscomprisemainlyrenewablegenerationsourcessuchaswindfarms,biomassplantsandmarine-basedgenerationtechnologies.Thiswillresultintherequirementtobuildnewhighvoltageelectricitytransmissioninfrastructureintheregion,whichwillhavethebenefitofstrengtheningtheexistingtransmissioninfrastructure,thusprovidingamoresecureandreliablesystemforinwardinvestmentaswellasdistributingtheenergygeneratedtoloadcentresthroughouttheregionandthecountry.

ThemainnewcorridorsintheWestRegioncomprise:

• NewelectricityinfrastructurewhichwillberequiredfromtheNorthMayoarea,initiallytowardsexistinggridinfrastructurelocatedineithertheeastorsouthpartoftheWestRegion.Itislikelythatsuchinfrastructurewillthencontinuetothekeymarketsontheeasternsideofthecountry.

• NewelectricitytransmissioninfrastructurewhichwillalsoberequiredfromwestCo.GalwaytoGalwaycityandbeyond.

Theconnectionofthesenewgeneratorswillalsoresultinanassociatedrequirementtoupgrademanypartsoftheexistingtransmissionnetwork.

Grid25statesthatgenerallonger-termforecasteddemandgrowthintheregionwillalsoresultintherequirementtoupgradetheexistingnetwork,andtobuildnewtransmissionlines.Thisincludes:

• MajorinfrastructuraldevelopmentfromMayotothemainbulktransmissionsystemintheeasternpartoftheregion;

• Upgradingtheexistingtransmissionnetwork.

Figure 2.7 Areas Requiring Future Network Development In The West Region

Page 29: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

24

2.5.5 Reinforcement of the transmission system in the

MID-WEST REGION

ReinforcementofthetransmissionsystembetweenMoneypointandTarbert,includingtheprovisionofanewsubstationtothewestoftheexistingTarbertsubstation,andtheongoingdevelopmentofMoneypointasakeytransmissionhub,isrequiredtofacilitatepowerflowsinthemid-westandsouth-westofthecountry.Thisreinforcementisrequiredtoenablerenewableandconventionalgenerationto

betransmittedtotheloadcentres,thusprovidingincreasedsecurityandavailabilityforconsumers.

Suchreinforcementgivesflexibilityformeetingthepowerrequirementsoftheregion.

Longer-termdevelopmentincludes:

• StrengtheningthetransmissioncapacityacrosstheShannonEstuary;

• UpgradednetworkssupplyingtheurbancentresofEnnisandLimerick;

• Up-ratingexistingnetworkstofacilitatehighercapacitypowerflows,usingexistingcorridorswherepossible.

Figure 2.8 Areas Requiring Future Network Development In The Mid-West Region

Page 30: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

25

2.5.6 Reinforcement of the transmission system in the

SOUTH-WEST REGION

Thereareanumberofissueswhichneedtobetakenintoaccountwhenplanningforthelong-termstrategicdevelopmentoftheelectricitytransmissioninfrastructureoftheSouth-Westregion.Theseinclude:

• Thesignificantamountofgeneration,inparticulargenerationfromrenewablesources,thatisexpectedtomaterialisethroughouttheSouth-Westregion;

• Generaldemandgrowthinthearea.

TheSouth-Westregionhasseenahighlevelofrenewablegenerationandconventionalgenerationseekingtoconnecttotheelectricitynetwork,asoutlinedinGrid25.Thiswillresultintherequirementtobuildsignificantnewhighvoltageelectricitytransmissioninfrastructureintheregion,includingnewsubstationsconnectingtokeytransmission

hubsinMoneypointandCork.Thiswillhavethebenefitofstrengtheningtheexistingtransmissioninfrastructure,thusprovidingamoresecureandreliablesystemforinwardinvestment,aswellastransmittingtheenergygeneratedtoloadcentresthroughouttheregionandthecountry.

GrowthindemandforelectricityintheSouth-Westregionneedstobefacilitated,andthismayleadtotherequirementtoconstructnewelectricitytransmissioninfrastructure.Thiswillensurethattheregionhastheappropriatetransmissioninfrastructuretoenableittoattractnewindustryandallowexistingindustrytoexpand.

Longer-termforecasteddevelopmentintheRegionincludes:

• SignificantstrengtheningofcapacitybetweentheSouth-WestandSouth-Eastregionstoallowexcesspowertoflowfrombothrenewableandconventionalsourcestosupplydemandinotherpartsofthecountry;

• Upgradingoftransmissionnetwork.

Page 31: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

26

Figure 2.9 Areas Requiring Future Network Development In The South-West Region

Page 32: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

27

2.5.7 Reinforcement of the transmission system in the

DUBLIN AND MID-EAST REGIONS

Itisperhapsunsurprising,givenitsrelativelyhighdensityofresidentialandemploymentpopulations,thattheGreaterDublinArea(formedbytheDublinandMid-EastRegions)isthemostsignificantelectricitydemandcentreinthecountry.Assuch,alargeconcentrationoftransmissionlinesarelocatedintheareawhichincludes110kV,220kVand400kVlinesandstations.

TheDublin220kVsystemcurrentlyconsistsofaringoffourprimaryBulkSupplyPoints,comprisingthehubsofCarrickmines,Finglas,InchicoreandPoolbeg220/110kVstations.Planneddevelopmentincludesadditional220kVBulkSupplyPointsatFinnstown(nearAdamstown),andintheDublinNorthCityFringearea.OtherplanneddevelopmentincludesincreasedtransformercapacityatCarrickmines,FinglasandInchicorestations.EirGridandESBNetworks(theDistributionSystemOperator-DSO)areworkingtogethertoprovideadditionaltransformercapacityatCarrickminesandInchicore220kVstations.

InrelationtotheDublinnetworks,EirGridinconjunctionwithESBnetworkshasidentifiedtheneedforthetwonew220/110kVin-feedstationsinthenorthandwestofDublin.Newstationsareplannedinthenorthandwestcityareas,toaccommodatedemandgrowth,andtobettermanageexistingdemandlevelshighlightedinGrid25.

Itislikelythatsomereconfigurationand/orreinforcementofthe220kVandthe110kVnetworkswillberequiredinthelonger-termtomeetDSOdemands,andtoavoidnetworkconstraintsintheDublinarea.

The400kVnetworkprovidesahighcapacitylinkbetweenMoneypointgenerationstationandGalwayonthewestcoastandDublinontheeast.EirGridalsoisconsideringtheneedforandoptionstoexpandits400kVnetworkintheGreaterDublinArea.Thiscouldbebythealterationofexistingroutesorequipmentorwithentirelynewoverheadlineorundergroundcableroutes.Additionaltransformercapacityisplannedatthetwoexisting400kVstations–atWoodlandnearDunshaughlin,Co.Meath,andatDunstown,Co.Kildare.

Longer-termdevelopmentintheRegionincludes:

• StrengtheningofnetworkintoandoutoftheRegiontoallowthedemandtobemetbyrenewablegeneratorslocatedmainlyinthewestofthecountry;

• StrengtheningofnetworkservingDublincityload;

• Developmenttoallownorth-southflowstoby-passthenetworkservingtheDublinload;

• ReinforcementofthenetworktocaterforstronggrowthinKildareandnorthWicklow;

• Upgradingoftheexistingnetwork.

Page 33: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

28

Figure 2.10 Areas Requiring Future Network Development In The Dublin And Mid-East Region

Page 34: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

29

3.1 Context UndertheprovisionsofthePlanningandDevelopmentActs2000–2010,themajorelectricitytransmissioninfrastructuredevelopmentbeingcarriedoutbyEirGridnowgenerallycomprisesstrategicinfrastructuredevelopment,asdefinedundertheActs,requiringanapplicationforStatutoryApprovaltobemadedirectlytoAnBordPleanála.

Assuch,thesecomplexdevelopmentsnowoccurwithinthevehicleofthepublicplanningprocess,wherethefocusisonmattersofproperplanningandsustainabledevelopment,andwherepublicparticipationisakeypillaroftheprocess.

Combinedwiththis,thereisnowasignificantemphasisandfocusontheenvironmentalimpactofalldevelopmentprojects,primarilyinreferencetotheEUHabitatsDirective,whichgivesappropriateprotectiontositesandspeciesofdesignatedinternationalimportance.

EirGridhasrespondedproactivelytothisnewregimeintermsoftheplanninganddevelopmentofelectricitytransmissioninfrastructure.Thishasprimarilyoccurredbyshiftingthemanagementandstructureofprojectdevelopmenttowardsaplanningandenvironmentalcontext.

3.2 Governance and ProcessEirGridhasinstitutedanewinternalsectionforthegovernanceoftheGrid25Programme.Inadditiontocoveringmattersofadministrative,financialandcorporategovernance,theProgrammeManagementOffice(PMO)includesexperiencedexpertsintheareasofecology,publicplanning,wayleavingandlandownerengagement,andprojectcommunications.TheseexpertsareassignedtoallEirGridprojects,toadviseandassistprojectmanagersandtheirprojectteamswiththeplanninganddevelopmentofallEirGridprojects.

InordertoensurethattheplanninganddevelopmentofallEirGridprojectsoccursinaconsistentandtransparentmanner,andwithappropriateemphasisonplanning,environmental,andcommunityissues,thePMOhasdevelopedaprocess(knownasaProjectDevelopmentandConsultationRoadmap)whichisappliedtoalllargescaleprojects.Theprocessissetoutinaseriesofstageswhichprogressfromthebroadestearlystageofinformationgatheringtothedetailedpre-applicationstageofsiting,environmentalassessmentandpreparationoftheplanningapplication.TheRoadmapalsoincludesthepost-consentconstructionphase.

TheemphasisoftheRoadmapisthatplanning,environmentalandcommunityissuesareidentifiedfromtheearlieststageofaproject.Theearlyidentificationofsuchissuesmeansthatconsiderationisgivenattheoutsettotheavoidanceofconstraints,ratherthanlatermitigationofimpactsarising.Thus,inthefirststageofinformationgatheringinrespectofaproject,astudyareaisidentified,environmentalandotherconstraintswithinthatstudyareaareidentified,andtheprojectissitedorroutedwiththeemphasisonavoidingthoseidentifiedconstraints.Allissues,decisionsandsolutionsaresubjecttoastructuredproject-specificstrategyofpublicandstakeholderconsultation,withfeedbackincorporatedintotheongoingprogressandplanningoftheproject.

AsummarygraphicoftheProjectDevelopmentandConsultationRoadmapissetoutinFigure3.1.TheeventualprojectsubmittedforStatutoryApprovalwillthereforehavebeensubjecttodetailedenvironmentalandotherassessment,withaclearstatementofalternativesconsidered,andappropriatelycommunicatedtothepublic,landownersandotherstakeholders,includingAnBordPleanálaastheStatutoryCompetentAuthority.

Section 3 - Towards a Planning and Environmental-led Approach to Electricity Transmission Infrastructure Development

Page 35: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

30

Figure 3.1 EirGrid’s Project Development and Consultation Roadmap

Page 36: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

31

3.3 Environmental Data and GuidelinesEirGridhascommittedsignificantresourcestogatheringenvironmentaldataandinformationwhichwillinformdecisionsforprojectdevelopment.ResponsibilityforthedeliveryandinterpretationofthisinformationrestsgenerallywiththeConsultantEcologistofthePMO,andthereforecanbemostappropriatelyandeffectivelydisseminatedtotheprojectteamswithinEirGrid,aspartoftheProjectDevelopmentandConsultationRoadmapprocess.Suchdataandguidelinesincludesthefollowing:

• TheStrategicEnvironmentalAssessment(SEA)–comprisinganEnvironmentalReport&NaturaImpactStatement–whichhasinformedthisIP;

• StrategicEnvironmentalConstraintsMapping,whichusesaGISdatabasetomapdesignatedenvironmentalandothersensitivesitesandareas–thismappinghasbeenusedtoinformtheSEA;

• EirGridisinthefinalstagesofcompletingEcologyGuidelinestoinformthedevelopmentoftransmissioninfrastructure;

• ThePMOissuesinternalPracticeNotesforprojectmanagersrelatingtoplanningandenvironmentalissues,includingonthescreeningandscopingofEnvironmentalImpactStatements,andAppropriateAssessment;

• EirGridhascommencedthepreparationofEvidence-BasedEnvironmentalStudiestodeterminetheactualeffectoftheconstructionandexistenceoftransmissioninfrastructureprojectsontheirreceivingenvironment.ThesestudieswillbothinformEirGrid

andallstakeholdersastotheactualenvironmentalimpactoftransmissionprojects,butalsowillidentifynecessaryorappropriatemodificationstocurrentdesignandpracticewhichwillhavealowerenvironmentalimpact.ThisisaddressedinmoredetailinChapter5ofthisIP,andinSection9oftheaccompanyingSEAEnvironmentalReport.

Thesedataandguidelines,combinedwithEirGrid’sinternalgovernanceprocesses,andinparticularitsProjectDevelopmentandConsultationRoadmap,servetoplaceplanningandenvironmentalmattersattheheartofallEirGrid’sdecision-makingrelatingtotheplanninganddevelopmentoftransmissioninfrastructure,fromthestrategicpolicyleveltothemoredetailedproject-specificlevel.

ThisapproachissetoutgraphicallyinFigure3.2,whichsetsEirGrid’sprocessesintotheirwidercontextofinternalenvironmentalprocesses,aswellasexternalpolicycontext.Itshouldbenotedthat,whilsteachlevelofEirGrid’sprocessissetinaparticularpolicycontext,themoredetailedprocesslevelswillalwayshaveregardtothehigher-levelpolicycontextandprocesses.

Thus,forexample,anyproposeddevelopmentwillbesetintothegoverningcontextoflocal,county,regional,andNationalstrategicandstatutoryplansandstrategies,aswellastheover-ridingpolicyoftheEnergyWhitePaper.Equally,theprojectwillbesubjectbothtotheproject-specificstatutoryEIAandAAprocesses,aswellashavingregardtothehigher-levelSEA.

Constructiononthetransmissiongrid

Page 37: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

32

Figure 3.2 EirGrid’s Strategic Decision Making Process (illustrating integration of environmental consideration at each level)

Policy

Programme

Plan

Project

EirGrid Process

Grid25 Implementation Programme

Master Plan

Scheme Development

Scheme Design & Permitting

Grid25

Policy Context

White Paper

National Plans & Strategies

Regional Guidelines & Strategies

County Development Plans & Strategies

County/ Local Development Plans & Strategies

Environmental Process

Strategic Environmental Assessment & Appropriate

Assessment

Screening for SEA & AA

Strategic Environmental Framework & Technical

Guidance

Screening for EIA & AA

Page 38: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

33

Page 39: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

34

3.4 Procedures for Transmission System Planning

Inthecontextoftheseprocessesandgovernance,theproceduresforTransmissionSystemPlanningtotakeaccountofPlanningandEnvironmentalconsiderationsoccurateachstage,asfollows:

AtStrategic Level,(thisIP),procedures,processes,andresources(staffanddata)areputinplace.

AtTechnical Planning Level,arangeofalternativeapproachesareconsidered–theseincludegridconfigurationandmanagement,andre-useofexistingassets,technicalandroutingoptions.EirGridiscurrentlyconsideringthemeritsofcapturingthisintheformofregionalMasterplansforgriddevelopment.TheongoingpreparationoftheseMasterplanswillbesubjecttocontinualenvironmentalscrutinyandassessmentasappropriate,toensurecompliancewiththeSEA.

AtProject Level,oncetheneedandtechnicalconfigurationhasbeendetermined,moredetailedalternativesfortherealisationofthatprojectareconsidered,withaformalconsiderationofallalternatives–usingSEAandEIAtechniques

AtPermitting LeveltheapplicationforconsentissubjecttoformalEIAandthereisformalpublicandagencyconsultation,inreferencetotheProjectDevelopmentandConsultationRoadmapprocess.

Overall,withtheimplementationandongoinggovernanceoftheseprocessesandprocedures,strategicplanningandenvironmentalconsiderationsarenowattheheartofEirGrid’sprojectdevelopmentprocess.Thisisconsideredtobeappropriate,consistentwithbestpracticefortransmissioninfrastructureplanning,andinaccordancewiththeprinciplesofproperplanningandsustainabledevelopment.

Page 40: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

35

4.1 Context EirGrid’sTransmissionDevelopmentPlan(TDP)2010,availableonwww.eirgrid.compresentstheplannednetworkdevelopmentprojectsthatEirGridhasprogressedtothepointwheretheyarethepreferredschemetomeetthechangingsystemrequirementsinthecontextofthelong-termdevelopmentofthenetwork.Theseprojectshaveallbeensubjecttoinitialenvironmentalevaluation,primarilyinreferencetostrategicconstraintsmapping,aspertheprocesssetoutinFigure3.1and3.2;anumberoftheseprojectshaveprogressedtothestageatwhichtheirgeneralnature,locationandextentisconfirmed,suchthattheyarecurrentlysubjecttoproject-specificenvironmentalassessment(withAAasappropriate).Inaddition,theseprojectshavebeenconsideredagainsttheGrid25IPSEA.

TheTDP2010identifiesatotalof111projectsthatareinprogress,70ofwhichareinthedetaileddesignandconstructionphase–thesearereproducedintheirentiretyAppendixAofthisIP.AnumberoftransmissionprojectsarecurrentlyintheStatutoryplanningconsentsprocess,orpermittedandunderconstruction.ThesehavenotbeenspecificallyidentifiedinthisImplementationProgramme(althoughtheyareincludedintheprojectslistedinAppendixA),astheyare,orhavebeen,separatelysubjecttospecificenvironmentalandotherassessment,inaccordancewithEirGrid’sprocessesfortheplanninganddevelopmentofprojects,asperitsProjectDevelopmentandConsultationRoadmap,aswellasinaccordancewithStatutoryprocedureandbestpractice.

TheTDP2010presentstheanticipatedtotalsofnewequipmentcurrentlyplanned/atinternalCapitalApprovalstage–thisisreproducedinTable4.1.Theseareestimatesonly,becausethescopesoftransmissionprojects,particularlythoseinthepreliminarystagesofdesign,canchange.

Inaddition,theTDP2010anticipatesthatsome7.7kmof220kV,and575kmof110kVtransmissioncircuitswillhavetheirthermalratingsincreased.2no.220kVtransmissionlinesand2no.110kVtransmissionlineswillberefurbishedwithoutaffectingtheirratings.

Itisimportanttonotethatthevarioustransmissiondevelopmentprojectsareatdifferentphasesoftheirlifetime.ThisIPidentifies26no.networkdevelopmentprojectscontainedwithintheTDP2010thatareatdesignandenvironmentalassessmentstage,andwhichEirGridconsidersarerequiredtomeetchangingsystemrequirementsintheshorttomediumtermdevelopmentofthenetwork,asidentifiedatastrategiclevelinChapter2ofthisIP.

400kV 220kV 110kV

NumberofNewStations 1 9 7

NumberofNewStationBays 8 49 181

OverheadLine,(km) 140 56 313

Underground/UnderseaCable,(km) 0.5 33.5 0

400/ 400/ 220/ 220kV 110kV 110kV

NumberofNewTransformers 2 2 16

NewTransformers,TotalMVA 1,000 500 3,250

110kV

NumberofNewCapacitorBanks 7

CapacitorBanksTotalMvar 135

Table 4.1 Estimates of Identified New Transmission Assets (Table S-1 of EirGrid’s TDP 2010)

Section 4 - Planned Network Developments

Page 41: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

36

Page 42: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

37

Thetransmissioninfrastructureprojectsoutlinedbelowarecategorisedunderthreesubsectionsrelatingtothemaindriversfortransmissiondevelopment:

• NetworkReinforcements;

• GeneratorConnections;

• DSOConnections.

Becauseoftheuncertaintiesinherentinthepublicplanningprocess,thetimeframeandthescopeofprojectsnotyetintheconstructionphasemaybesubjecttochange.

Tables4.2,4.3,and4.4presentthefollowingprojectinformation:

• CapitalProjectnumber(CPNo.)–eachprojectisreferencedwithaCapitalProjectnumberforco-ordinationbetweenEirGridandtheTransmissionAssetsOwner(TAO-ESBNetworks);

• ProjectTitleandDescription–forprojectsinthePreliminaryDesignstage,theprojectdescriptionsareEirGrid’scurrentbestestimatesandmaybeliabletochange;

• ExpectedCompletionDate(E.C.D.)–theseestimatesaresubjecttotheplanningprocess,theconstructionprogress,availabilityoftransmissionoutages,andcommissioning,andmaybeliabletochange.

• Phase–relatingtothestageofprojectdevelopment.

LinelengthsareapproximateforNetworkReinforcementprojectsthatareinthepreliminarydesignphaseorinpublicplanningprocess.

EirGridandESBNetworks,asTSOandTAOrespectively,arealsoco-ordinatingothercapitalprojectsnotlistedherein,generallycomprisingminorcapitalworks,andlineuprating,diversionsandalterations.

Figures4.1and4.2,extractedfromEirGrid’sTransmissionDevelopmentPlan2010,provideanindicativeoverviewoftheplannednetworkdevelopmentsatOutlineDesignandEIA,orconsentandconstructionstages,asoutlinedintheDraftTDP2010.Thisprovidesanindicativerepresentationofplanneddevelopment,anddoesnotrepresentspecificalignmentsofproposals.

AsnotedinChapter3above,allEirGridprojectsinthepre-planningstagesofprojectdevelopment(notedas“outlinedesignandEIA”inthefollowingtables)aresubjecttotheEIAandAAprocesses;thisinitiallycomprisesascreeningprocess.Whereaprojectiscurrentlyintheplanningprocess,andhasbeenaccompaniedbyanEISandAppropriateAssessment,thisisindicatedinthemorecomprehensivetablesextractedfromEirGrid’sTDP2010,reproducedatAppendixAofthisIP.

Page 43: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

38

Figure 4.1 Map Indicating Planned Network Developments in the Detailed Design & Construction Phase (from EirGrid’s Transmission Development Plan 2010)

Page 44: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

39

4.2 Network Reinforcement DevelopmentsThisSectiondealswiththeidentifieddevelopmentprojectsthataredrivenbygenericdemandgrowthandreinforcementsresultingfromgeneratordemandandinterconnectorconnections.Table4.2liststhenetworkreinforcementprojectsrelevanttothisImplementationProgramme(asextractedfromEirGrid’sTransmissionDevelopmentPlan2010).

Ofnote,intheTDP2010,theNorth-South400kVInterconnectordevelopmentwasidentifiedasinthepublicplanningprocess.Theapplicationwassubsequentlywithdrawnfromthatplanningprocessandtheprojecthasrevertedtothestatusof‘OutlineDesignandEIA’.However,forconsistency,thestatushasnotbeenalteredinthisIP,whichreflectsthecontentoftheTDP2010.TheprojectislistedinTableA1ofAppendixA.

1 Note EMM = Environmental Mitigation Measure

CP No. Project Title & Description E.C.D Phase

CP0501 Clashavoon-Dunmanway 110 kV New LineConstructionofanew110kVlinefromClashavoontoDunmanwaystationandassociatedstationworks.

Mar-14 OutlineDesignorEIA

CP0580 Carrickmines 220 kV GIS Development Replacementofexistingair-insulatedswitchgearwithgas-insulatedswitchgear(GIS);Installationofanew4th220/110kVtransformer.

Dec-12 OutlineDesignorEIA

CP0585 Laois /Kilkenny ReinforcementNew Station & Associated Lines & Station WorksNew400/110kVtransmissionstationinCo.Laois.ThestationwillbeloopedintotheexistingDunstown-Moneypoint400kVlineandCarlow-Portlaoise110kVline.Anew110kVcircuitfromthenewstationtoKilkennyusingtheexistingBallyragget-Kilkenny38kVlinewhichisbuiltto110kVstandards.Anew110/38kVstationatBallyraggettocaterforlossoftheKilkenny-Ballyragget38kVline.[DetailstobefinalisedwithDSO].

Dec-14 OutlineDesignorEIA

CP0596 New 110kV Circuit To MullingarConstructionofanew110kVcircuittoMullingar110kVstationfromeitherKinnegadorDerryiron110kVstations.

Oct-14 OutlineDesignorEIA

CP0597 Reinforcement of the Ardnacrusha & Ennis AreaUpratingoftheMoneypoint-Tullabrack-Booltiagh-Ennis110kVcircuittoequivalentof430mm2ACSR@80oC.DependentonMoneypoint400/220/110kVGISDevelopment,seeCP0688

Dec-14 OutlineDesignorEIA

CP0674 Tralee 110 kV StationNewCoupler

Aug-12 OutlineDesignorEIA

CP0699 Cathaleen’s Fall - Srananagh 1 110kV Line UprateUpratelinetoequivalentof430mm2ACSR@80oC

Oct-12 OutlineDesignorEIA

CP0709 Dunmanway 110kV Station Upgrade Dec-14 OutlineDesignorEIA

CP0707 Barrymore 110kV station extension - Loop into Cahir - Knockraha 110kV line

Jun-13 OutlineDesignorEIA

CP0619 New Capacitors at ShankillInstallationof15Mvarand30Mvarre-deployablecapacitorunitsatShankill110kVstation

OnHold OutlineDesignorEIA

Table 4.2Network Reinforcement Projects

Page 45: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

40

4.3 DSO ConnectionsMostdemandconnectionstothetransmissionsystemaresoughtbyESBNetworks,theDistributionSystemOperator(DSO)whichappliesfornewstationconnections.Table4.3liststhedevelopmentprojectsthatrelatedirectlytotheconnectionofnewTSO/DSOinterfacestationstothegrid,ortochangesinexistingconnectionarrangements.

TheDSOhasfurtherdevelopmentplanswhichareatvariousstagesofpreparation,severalatanadvancedstage.EirGridisco-operatingwiththeDSOontheseexpansionplansinordertobringthemforwardtoprojectinitiationwhenrequired.EirGridwillinitiatethenecessarytransmissionconnectionswhenformalnotificationsfromtheDSOtoproceedarereceived.

CP No. Project Title & Description E.C.D Phase

CP0437a North Dublin 220kV Project - New 220kV Station Anew220kVstationintheNorthDublinWorksareaandassociatednetworks.ThedevelopmentispartofawiderTSO/DSOagreedreinforcementstrategytoenhancethenetworkinthenorthernfringeofDublincity.ThestationwillbetailfedfromFinglas220kVusingcableandconstructedwithGIS.Theprocessofacquisitionofanewsiteforthisprojectiscurrentlyunderway.

Dec-14 OutlineDesignorEIA

CP0506 Finnstown 220kV Project (Adamstown) - New 220kV Station Finnstown220kVstation,southofLucan,anew220kVstationloopedintotheInchicore-MaynoothNo.1andNo.2220kVlines.Thestationwillbeinitiallyasingletransformer220kVstation,butallowfinaldevelopmentforafourtransformerstation.DuetospacerestrictionsonpotentialsitesanentirelyGISstationisproposed.

Mar-14 OutlineDesignorEIA

CP0644 Bracklone 110 kV Station and Loop In New110kVstationtobeloopedintoPortlaoise-Newbridge110kVline.ReplacesexistingPortarlington38kVStation.

Dec-12 OutlineDesignorEIA

CP0649 Drumline 110 kV Station Works Two20MVATransformerssupplying12.2MWNewloadand11.4MWtransferedloadfromexistingDrumlinetransformers.

Jun-13 OutlineDesignorEIA

CP0627 Bandon 110 kV Station NewTransformerBay.

OnHold OutlineDesignorEIA

CP0075 Ballycummin 110 kV New Station NewstationloopedintotheLimerick-Moneteen110kVline.

OnHold OutlineDesignorEIA

Table 4.3DSO Connection Projects

Page 46: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

41

4.4 Generator ConnectionsThissectionoutlinesprojectsthatrelatedirectlytoconnectionofgenerationtothetransmissionsystemortochangesinexistinggenerationconnectionarrangements.Someoftheseconnectionsarecontestable,i.e.thegeneratorhasdecidedtobuildtheconnectionassetstoTSOspecifiedstandards.

TheEstimatedCompletionDate(E.C.D.)isEirGrid’scurrentbestestimateofwhenthegeneration

connectionwillbecompleted.ItshouldbenotedthatthisisdependentonprogressbytheapplicantandnotEirGrid.Thedateofcompletionfortheseprojectsisco-ordinatedwiththeIndependentPowerProducer(IPP)programmeofconnection.

Table4.4liststhegeneratorconnectionprojectsrelevanttothisImplementationProgramme(asextractedfromEirGrid’sTransmissionDevelopmentPlan2010).

Table 4.4Generator Connection Projects

CP No. Project Title & Description E.C.D Phase

CP0500 North Kerry Project Anew220kVstationloopedintotheexistingClashavoon-Tarbert220kVline.TheworkincludesconnectionworksforAthea,DromadaandCloghboolawindfarms

Apr-14 OutlineDesignorEIA

CP0603 IPP088 Mulreavy Connection Connectionofanew110kVstationforconnectionofnewwindfarm.

Jan-12 OutlineDesignorEIA

CP0608 IPP119 Cloghboola Wind Farm ConnectionofanewwindfarmintotheexistingTrien110kVstation.

Apr-14 OutlineDesignorEIA

CP0615 Glenree 110kV Station Connectionofanew110kVstation,loopedintotheexistingCunghill-Moy110kVline.ThisstationwillfacilitatetheconnectionofnewDSOwindfarms.

Sep-11 OutlineDesignorEIA

CP0648 Garrow 110 kV Station ExtensionWorksforanew110kVtransformerbayfortheprovisionofrenewableenergy.

Aug-11 OutlineDesignorEIA

CP0650 Millstreet 220/110 kV station New220/110kVstationloopedintotheexistingClashavoon-Tarbert220kVlinefortheconnectionofwindfarms.

Aug-14 OutlineDesignorEIA

CP0651 East Kerry & North West Cork 220 kV Station Anew220kVstationloopedintotheexistingClashavoon-Tarbert220kVlinefortheconnectionofwindfarms.Twonew110kVlineswillbeconstructed,onetoGlenlaraandtheothertotheplannedCordalstationinCo.Kerry.KnockacummerconnectionintoGlenlaraisalsopartofthisproject.

Jan-14 OutlineDesignorEIA

CP0602 IPP044 Keelderry Wind FarmConnectionofanewwindfarmtoanewstation,loopedintotheexistingAgannygal-Derrybrien110kVline.

OnHold OutlineDesignorEIA

CP0641 IPP118NorePowerStationExtensionworksintheexistingKilkennystationfortheconnectionofanewOCGT.

OnHold OutlineDesignorEIA

Page 47: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

42

Figure 4.2 Map Indicating Planned Network Developments in the Outline Design Phase and Public Planning Process. Note: All new developments on this map are subject to on-going EIA and AA processes

Page 48: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

43

5.1 Introduction Mitigationmeasuresaremeasuresenvisagedtoprevent,reduceand,asfullyaspossible,offsetanysignificantadverseimpactsontheenvironmentofimplementingtheIP.

Mitigationinvolvesamelioratingsignificantnegativeeffects.Wheretherearesignificantnegativeeffects,considerationisgiveninthefirstinstancetopreventingsucheffectsor,wherethisisnotpossibleforstatedreasons,tolesseningoroffsettingthoseeffects.Mitigationmeasurescanberoughlydividedintothosethat:avoideffects;reducethemagnitudeorextent,probabilityand/orseverityofeffects;repaireffectsaftertheyhaveoccurred,and;compensateforeffects,balancingoutnegativeimpactswithotherpositiveones.

Therearetwotypesofmitigationmeasures.Thefirstinvolveshigh-levelpreventativemitigationmeasuresthatwereincorporatedintothedraftingoftheIPdocumentorbybringingaboutchangesinorganisationalandworkingpracticeswithinEirGrid.Theseincludesevenmajorprocedures,identifiedbelowandoutlinedinthesubsequentsectionsofthischapter,whichwillbeemployedtoidentifyandavoidenvironmentaleffects:

EMM 1. FullIntegrationofPlanningand EnvironmentalConsiderationsin TransmissionSystemPlanning;

EMM 2. PreparationofStrategicEnvironmental ConstraintsMapping;

EMM 3. PreparationofEvidence-Based EnvironmentalGuidelines,consistingof:

a) EnvironmentalBenchmarking Studies;

b) Evidence-BasedEnvironmentalDesign Guidelines;and

c) GuidelinesonEIAforTransmission ProjectsinIreland;

EMM 4. ConsiderationoftheBroadestPossible RangeofAlternativesinallfutureEnergy TransmissionStrategies;

EMM 5. PreparationofTransmissionDevelopment PlanEnvironmentalAppraisalReport;

EMM 6. OngoingCo-operationinpreparation ofRenewableEnergyGeneration GuidelinesandStrategies;and,

EMM 7. IntegratingOffshoreGridconnectivity requirementsandenvironmental considerationsinEirGrid’sStrategic EnvironmentalFramework(SEF).

ThesecondtypeofmitigationmeasuresinvolvesthosethataddresstheimplementationoftheIP.TheseareidentifiedinAppendixBofthisreportandhavebeenfullyintegratedintotheIP.Projectteamsshouldrefertotheseinterimgeneralmitigationmeasures.ThesemeasureswillbeextendedandaugmentedbytheoutputfromtheEnvironmentalBenchmarkingStudiesandEvidence-BasedEnvironmentalDesignGuidelinesreferredtoaboveandoutlinedbelow.Itisnotedthattherearelinkagesbetweenvariousmitigationmeasuresandthatthemitigationofcertaineffectswillbecontributedtowardsbymultiplemeasures.

Additional,moredetailedmitigationmeasurestothoseidentifiedbelowwouldbelikelytoberequiredbylowertier,project-specific,environmentalassessmentsandwouldneedtobeintegratedintorelevantspecificplansandprojects.Itshouldbenotedthatmanyoftheidentifiedlowertiermitigationmeasuresareproceduresandprocessesthatwillneedtobeadopted.

ThemitigationmeasuressetoutunderSections5.2to5.8wererecommendedbytheSEAandAAprocessestobeintegratedintoanearlierdraftoftheIP.TheIPpreparationteamtookonboardthisrecommendationandfullyintegratedthemeasuresintoSection5intheIP.ThestatusofimplementingallmitigationmeasuresisdetailedinTable5.1.

Section 5 - Environmental Mitigation Measures

7NoteEMM=EnvironmentalMitigationMeasure

Page 49: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

44

Mitigation Measure Code

Mitigation Measure Title Status

EMM1 FullIntegrationofPlanningandEnvironmentalConsiderationsinEirGrid’sTransmissionSystemPlanning

Hasalreadyoccurred;changeswillcontinuetobeimplemented.

EMM2 PreparationofStrategicEnvironmentalConstraintsMapping

Hasalreadyoccurred;willbeupdatedonanongoingbasis,asappropriate,toincludemostup-to-date,relevantenvironmentaldata.

EMM3 PreparationofEvidence-basedEnvironmentalGuidelines

Hasbegun;Guidelinestobepublished.

EMM4 ConsiderationoftheBroadestPossibleRangeofAlternativesinallFutureEnergyTransmissionStrategies

MeasuretobeadheredtoasrelevantonadoptionofIP.

EMM5 PreparationofTransmissionDevelopmentPlanEnvironmentalAppraisalReport

MeasuretobeadheredtoasrelevantonadoptionofIP.

EMM6 OngoingCo-operationinpreparationofRenewableEnergyGenerationGuidelinesandStrategies

MeasuretobeadheredtoasrelevantonadoptionofIP.

EMM7 IntegratingOffshoreGridconnectivityrequirementsandenvironmentalconsiderationsinEirGrid’sStrategicEnvironmentalFramework(SEF)

MeasuretobeadheredtoasrelevantonadoptionofIP.

EMM8(AtoK) OthermeasuresintegratedintotheIP MeasurestobeadheredtofornewprojectsasrelevantandasappropriateonadoptionofIP.

MeasurestobeextendedandaugmentedbytheoutputfromtheEnvironmentalBenchmarkingStudiesandEvidence-BasedEnvironmentalDesignGuidelines

Table 5.1

Status of Implementing Mitigation Measures

Page 50: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

45

5.2 EMM1 Full Integration of Planning and Environmental Considerations in EirGrid’s Transmission System PlanningConsiderablechangesofproceduresandpersonnelhavebeenputinplacetoensurethatenvironmentalfactorsareconsideredattheearlieststageofEirGrid’sTransmissionPlanningSystem–asaresultoftheparallelSEAprocess.Thesearepreventativemeasuresaimedatanticipatingstrategicdecisionsthatwouldbelikelytoresultinavoidableadverseenvironmentaleffects.

ThisStrategicEnvironmentalFramework(SEF)hasresultedinfourmajortypesofinterventions:

1. TheEirGridTransmissionSystemplanning procedureshavebeenstrengthenedto incorporateenvironmentalconsiderationsas anearlydeterminant(refertoChapter3of thisIP)andasacriticalstageintheprocess ofdecisionmaking.Thesesystemsarenow operational.

2. EirGridhasestablishedaProgramme ManagementOffice(PMO)andnewpositions ofresponsibilitywithintheorganisationthat provideseniorplanningandecologicaladvice toprojectteams.Appointmentshavebeen madetothesepositions.

3. EirGridisimplementingStrategic EnvironmentalConstraintsMappingthat providesdecision-makersandsystemplanners withhigh-levelenvironmentaldatathatcan beusedfortheconceptualdevelopmentstage ofTransmissionPlanning.

4. Procedurestobefollowedonaproject-by- projectbasisforthedetailedconsideration, weightingandevaluationoflikely environmentaleffects–including cumulativeeffects–havingparticularregard totherequirementsoftheHabitatsDirective8.

Suchproceduresincludetheneedfor timelyconsultationwithrelevantplanning andenvironmentalauthoritiessuchasthe NPWS,theevaluationofup-to-datemapping, designationsanddevelopmentplans,policies, andaconsiderationofanyrelevantsectoral guidelines.

Inaddition,EirGridwillcontinuetoworkpro-activelywiththeDepartmentofArts,HeritageandtheGaeltacht(DAHG)andwithlocalplanningauthoritiesandregionalauthoritiestoidentifycriticalpolicies,objectivesandconstraints-e.g.criticalrivercrossingpoints–inDevelopmentPlansandRegionalPlanningGuidelines,toensurethattheplanninganddevelopmentofnationalstrategictransmissioninfrastructureoccursinthecontextofbestenvironmentalpractice,andinaccordancewiththeprinciplesofproperplanningandsustainabledevelopment.

EirGridwillalsocontinuetoworkalongsideESBNetworks,BordGais,theNationalTransportAuthority,theNationalRoadAuthoritiesandotherkeystrategicbodiesinordertoensurethatsustainabledevelopment,spatialplanningandtransportandgridinfrastructurearepromotedinanintegratedmanner.

8Referencedstatutoryobligation

Page 51: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

46

5.3 EMM2 Preparation of Strategic Environmental Constraints MappingTheScopingReportfortheSEAidentifiedtheneedtoputStrategicEnvironmentalConstraintsMappinginplaceinordertoensurethatenvironmentalconsiderationsareincludedattheearlieststageofprojectinceptionandintheconsiderationofalternatives.AstudywascommissionedandcompletedwhileconsultationswerebeingundertakenfortheSEAandtheinformationcontainedintheStudyinformednumeroussectionsofthisSEAEnvironmentalReport.

TheStrategicEnvironmentalConstraintsMappingcomprisesmappingoftheenvironmentalconsiderations–bothconstraintsandopportunities–thatneedtobeincorporatedintostrategicdecisionsaboutprojectsandotherdevelopmentslikelytogiverisetoenvironmentaleffects.Themappingisofsufficientdetailtoprovideanoverviewofthelikelihoodofencounteringenvironmentalchallengeswhenplanningroutesthoughparticularareas–ataregionallevel–andshouldassistinmoredetailedconsiderationofpotentialroutecorridorsandintheselectionofroutingalternatives.Themappingshouldformaframeworkformoredetailedmapping–onaprojectbyprojectbasis–ofsitespecificsensitivitiesforecologyandculturalheritageandforlocaldevelopmentplandesignationsofsceneryandvisualvulnerability.

TheconstraintsmappingwillbecomepartofEirGrid’sStandardOperationalProcedureaspartoftheoverallSEFtowhichdesignersarerequiredtohaveregard.ItishopedthattheconstraintsmappingcanultimatelybeupdatedtoincludeNorthernIrelandandwillbeupdatedperiodicallytoensuretheuseofthemostup-to-date,relevantenvironmentalbaselinedata.

5.4 EMM3 Preparation of Evidence-based Environmental GuidelinesThroughtheSEAscopingprocesstheideaofaseriesofauthoritativestudiesexaminingtheactualeffectsoftheconstructionandexistenceofpowertransmissionprojectsinIrelandwasrecommendedtobepreparedandtheseareintheprocessofbeingcommissioned.

Theseauthoritative,ex post9studieswillprovidebenchmarkstofacilitatethepreparation,presentationanddefenceofpowerprojectsthatwillberobustandwillrigorouslyassesstheimpactsoftransmissionprojectsinIreland.Detailsofthethreetypesofstudiesthatwillmitigateimpactsbyanticipationandavoidanceareasfollows:

1. Environmental Benchmarking Studies

StudieswillbecarriedouttodeterminetheactualeffectoftheconstructionandexistenceofpowerprojectsinarepresentativerangeoftypicalIrishenvironmentalconditions.Thestudieswillfocusontheprincipaltopicsofconcerninenvironmentalimpactassessments–includingecology,visualimpact,andimpactuponhumanbeings.

Thestudieswillexaminetheeffectonatypicalarea,habitatorcircumstancethatiscommonlyencountered–suchaspasturesinthelowlands,blanketbogsortheenvironsofavillage.Theywillexaminetheeffectsoftheconstructionandexistenceofarangeofpowertransmissionprojects–includingsubstationsandarangeofsizesoftransmissionlinesrangingfrom110–400kV.

Studieswilldescribetheeffectofpowerprojectsonspecifictopicsinspecificenvironments–thesewillbecomparedtounaffectedareas,ontheonehand,andtonon-standardand‘worstcase’conditionsontheother,inordertoestablishthefullrangeofconditionsthatcouldarise,asfollows.

9Ex postistheLatinfor“afterthefact”.Inmodelswherethereisuncertaintythatisresolvedduringthecourseofevents,theex postvalues(e.g.ofexpectedgain)arethosethatarecalculatedaftertheuncertaintyhasbeenresolved.

Page 52: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

47

Typical Conditions

Ineachcaseanareawillbeidentified–andagreedwithstakeholders–asbeingtypicalofthespecificconditionswherethetransmissionprojecthasinteractedwiththeenvironmentaltopic.Theareaofinteractionwillbescrutinisedandcomparedwithanunaffectedcontrolareatodescribethenature,magnitudeandsignificanceoftheeffectsthathaveoccurred.

InadditiontotheTypicalConditiontherewillalsobeanexaminationoftwootherconditions–Non-standardandWorstCaseconditions–thatcanbeusedtodeterminetheparameterswithinwhichthebenchmarkingoftheenvironmentaleffectscanbedeemedtobereliablypredicted.

Non-standard Conditions

Locationswillbeidentifiedandagreedwithkeystakeholderswhicharetypicalofalandscape,habitatorlandusebutwhichhaveobjectivecircumstancesorfactorsthatincreasethepotentialforenvironmentaleffect–suchassteeperslope,greaterage,differentmanagementregimes.ThesewillbescrutinisedandcomparedwithbothTypicalConditionsandunaffectedcontrolarea,inordertodescribethenature,magnitudeandsignificanceoftheeffectsthathaveoccurred.

Worst Case Condition

Locationswillbeidentifiedandagreedwithstakeholderswhicharetypicalofalandscape,habitatorlanduseinwhichthereisobjectiveevidenceofadverseenvironmentaleffectsduetotheexistence,constructionormaintenanceofthepowerproject.Thenature,magnitudeandsignificanceoftheeffectsthathaveoccurredwillbedescribedandevaluatedtodeterminehowsuchadverseeffectsoccurred,andhowtheymightbeavoidedinfuture.

Lessons Learned

Eachsectionwillincludeasummaryofwhatprojectdesignerscanlearnfromthisanalysisintermsofwhatpracticesappeartogiverisetotheleastandthegreatestenvironmentaleffect.Thisadvicewillbeclearlydifferentiatedintobestpracticetobringabout‘LegalCompliance’,aswellas‘BestPractice’.

Summary Study

AllstudiesforeachsectionofthecountrysidewillbesummarisedintoanoverallrouteselectionandprojectdesignguideforeachcomponentoftheIrishcountryside.Forinstance,therewillbeasectionentitled‘PowerProjectsinWetlands’.Thiswillprovideauthoritativedesignadviceonallaspectsofeachstepofapowerproject–fromrouteselectionthroughtoprojectdesignandcontractimplementation.Usingthis,designerswillbeabletoanticipate,avoidorameliorateadverseeffectsoncommunities,flora,fauna,water,landscapeorculturalheritage.ThisinformationwillbecompiledintoEvidence-Based Design Guidelines for Power Projects in Ireland[seebelow].

On-going Studies

Thestudiesareconceivedasanon-goingbodyofworkthatwillbecontinuouslyupdatedandamendedtotakeaccountofdevelopmentsinunderstanding–arisingfrompracticeorresearch.

Page 53: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

48

Page 54: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

49

2. Evidence-Based Environmental Design Guidelines

TheprimaryobjectiveisthattheseDesignGuidelineswillprovidepracticalguidanceforhowbesttoincorporateeachtypeofpowerprojectintoeachpartoftheIrishenvironmentinsuchawayastoanticipateandavoidadverseeffectstothegreatestextentpossible.

Thesecondaryobjectiveistoestablishanevidencebasedapproach–acceptedbystakeholders–thatcanbeusedtodemonstratethatanyresidualeffectsareconsistentwith‘bestpractice’.

TheEnvironmentalBenchmarkingStudieswillidentifyevidenceforthetypesofroutes,designs,constructionandmaintenancemethodsthatgiverisetotheleasteffectontheenvironment.ThisknowledgewillbetranslatedbyprojectdesignersintoGuidelinesforrouteplanners,projectdesigners,managersandthoseresponsibleforconstructionandmanagementofpowerassets.

TheDesignGuidelineswilladdresstheissuesthatariseateachofthreestagesofaprojectbeginningattheInitiationstagewhereaprojectisfirstconceived,throughthePlanningStage–whereroutesareselected–finishingwiththeDesignStagewheredetaileddecisionsaretakenabouthowtheprojectwillbebuilt.Theseissuesareconsideredasfollows:

• ProjectInitiationIssues

• PlanningIssues

• DesignIssues

ThereportsfromtheEnvironmental Benchmarking Studieswillbeexaminedtodeterminetherouting,designandconstructionmethodsthatproducethemostenvironmentallysuitableoutcomes.Thesereportswillalsodescribeanddetailevidenceofenvironmentaldegradationthathasoccurredashighlightedinthe‘worstcase’evaluations.TheadvicefromtheLessons Learnedandthe

Summary StudysectionsoftheEnvironmentalBenchmarkingStudieswillbeusedasabasisformostofthismaterial.

Theemphasisthroughoutwillbeonprovidingconcise,practicaladvicefrompractitionerstopractitionersthatwillmaketheoutcomeofmoredetailedstudiesbyspecialistsavailableinanimmediatelyapplicableway.

3. Guidelines on EIA for Transmission Projects in Ireland

TheEIA GuidelinesaremeanttoaccompanytheEvidence-Based Design GuidelinesandareintendedtoprovideanagreedandauthoritativeformatforthepreparationofEIAforpowerprojectsinIreland.

TheobjectiveistominimisechallengesanddisputesabouttheproceduresandcontentofthecoverageofEIAsforpowerprojects.Itwillachievethisbyidentifyingandagreeingappropriatescope,contentandstructureforpowerprojectEIAswithallrelevantstakeholders–inadvanceofanyspecificproject.

ItisproposedthatthestructureandcontentwillexactlymatchthatemployedintheEPA’sAdvice Notes on Current Practice in the Preparation of Environmental Impact Statements.Itwill,howeverprovideconsiderablymoredetailoneachsection.

TheseGuidelineswilldrawheavilyonboththeEnvironmental Benchmarking Studies and the Evidence-Based Design Guidelinestoprovidethedetailaboutthescopeofenvironmentalstudiesontheonehandandtodescribehowtheprojectsshouldbedescribedontheother.TheywillalsotakeintoaccountEirGrid’sEcologyGuidelinesforTransmissionPowerlineswhichwillbeupdatedasappropriatefollowingcompletionofthebenchmarkingstudies.OneofthemostimportantcomponentsoftheGuidelineswillbeastandardisedGlossaryofImpacts.Thiswillcollateastandardisedandauthoritativesetofdescriptionsoflevelsofimpactforpowerprojects.

Page 55: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

50

ThisisintendedtoremoveuncertaintyinthepreparationofEnvironmentalImpactStatementsbyfacilitatingrapidandconsistentscopingandscreening.Itwillalsomakekeydeterminationsmorerobustandprotecttheirdecisionsagainstanythreatsanddisputesaboutthesufficiencyofthedataortheappropriatenessofthemethodsemployed.

ThebenchmarkstudieswillprovidethefactualbasisforEvidence-BasedDesignGuidelinesforPowerTransmissionProjectsinIreland.Thebenchmarkstudiesandthedesignguidelines,inturnwillprovidethebasisforspecialistEIAGuidelinesforthissector.

ItisnotedthatprojectswillalsohavetobescreenedwithrespecttotheHabitatsDirectiveAssessment/AppropriateAssessmentasrequiredbyArticle6oftheHabitatsDirective10–availableDEHLGGuidance’AppropriateAssessmentofPlansandProjectsinIreland’(2009)shouldbeconsideredasappropriateinthisregard.

5.5 EMM4 Consideration of the Broadest Possible Range of Alternatives in all Future Energy Transmission StrategiesAlternativeroutesandregionalgriddevelopmentstrategieswillconsiderthebroadestrangepossibleofspatialandenvironmentalalternativesatthenextlevelofenvironmentalassessment–i.e.thatoflowertierplans,multipleorindividualprojects.Allprojectswillbesubjecttodetailedconstraintsandroutesstudy,inaccordancewithEirGrid’sProjectDevelopmentandConsultationRoadmap.

5.6 EMM5 Preparation of Transmission Development Plan Environmental Appraisal ReportEirGridproducesanannualrollingoperationaldocument,theTransmissionDevelopmentPlan(TDP),asrequiredbyregulation8(6)ofSI445/2000,andsubmittedforapprovaltotheCER(CommissionforEnergyRegulation).

IncompliancewithSI435of2004,TDPswillbescreenedfortheneedtoundertakeSEAandAA.Notwithstandingtheoutcomeofscreening,anEnvironmentalAppraisalReportwillbepreparedtoaccompanyeachannualTDPwhichwilldescribeanyeffectsarisingthatwillbesignificantlygreater,differentormoresignificantthanthoseanticipatedbytheSEAorAA.

TheEnvironmentalAppraisalReportwhichaccompaniesthenextTDPshalltakeintoaccountmaritimemappingandissuesemergingfromtheseparateSEAinrespectofthecurrentOffshoreRenewableEnergyDevelopmentPlan,asappropriate.

5.7 EMM6 Ongoing Co-operation in preparation of Renewable Energy Generation Guidelines and Strategies Somepartsofthecountryarebettersituatedforgenerationofrenewablesuppliesofenergythanothers.However,thereiscurrentlynogoverningterrestrialrenewableenergystrategydetailingwhererenewableenergygenerationshouldoccurinIreland.AnumberofpoliciesandobjectivesexistinvariousCountyDevelopmentPlansandCountyWindEnergyStrategieswhichpromotethedevelopmentofrenewableenergyatidentifiedlocationsintheirjurisdictions.

10Referencedstatutoryobligation

Page 56: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

51

ThereisclearmeritinthepreparationofRegionalRenewableEnergyGenerationGuidelines,asrenewableenergydevelopmentsmayoftentraversecountyandregionalboundaries.EirGridiskeentosupport,co-operateandparticipateinthepreparationofanysuchfutureRegionalRenewableEnergyGenerationGuidelines,RegionalRenewableEnergyStrategies,CountyWindEnergyStrategiesandCountyRenewableEnergyStrategies.Furthermore,EirGridwillcontinuetosupporttheimplementationofaspectsoftheNationalRenewableEnergyActionPlan2010whereapplicable.

5.8 EMM7 Integrating Offshore Grid connectivity requirements and environmental considerations in EirGrid’s Strategic Environmental Framework (SEF)ItisemergingthatanumberofscenariosforfutureelectricalgenerationanddistributionstrategiesinIrelandarelikelytoinvolvethedevelopmentofoffshoregridinfrastructure.ThishasthepotentialtooccurinareasoffmanypartsofIrelandonaccountofvariousdevelopmentsincludingtheexploitationofoffshorerenewableresources(windandwave),interconnectorswithotherEUMemberStatesandtheparticipationofIrelandinapan-Europeanoffshoregrid.Allofthesehavesignificantimplicationsforgriddevelopmentandpotentialforsignificantinteractionswithinshoreandterrestrialenvironments.

TheSEADirective11requirestheidentificationofarangeofenvironmentaleffectsincludingthosewhichareindirect.InterconnectionacrosswaterandrenewableenergygenerationinfrastructureenabledbytheIP,forexample,cancausepotentialindirectandcumulativeeffectsonboththeonshoreandoffshoreenvironments.Currentlyavailableoffshoreenvironmentaldataisnotsufficiently

completetofacilitateacomprehensiveevaluationoflikelyimpactstothetransitionzonebetweenterrestrialandmarineenvironments.TheOREDPwillbereviewedandupdated,andintegrationwillbecomemoreapparentwithtime.ItisanticipatedthatimprovedoffshoredatawillbecomeavailableintheperiodfollowingthisSEA,particularlyasaresultoftheSEAwhichiscurrentlybeingundertakenforoffshorerenewableresources.ThisdatawillbetakenintoaccountintheEnvironmentalAppraisalReportsforforthcomingannualTDPsandintheSEAsoffutureiterationsoftheIP.

Figure5.1illustratesaqualitativeindicationofgeneral,potentiallocationsforland/seaconnectionswheretherearelesssensitiveonshoreenvironmentsinthevicinityofcoasts.Thisqualitativeindicationwasdeterminedbythesensitivityofonshoreenvironmentsinthevicinityofcoasts,asillustratedbytheOverallDevelopmentPotentialRatingmappingforthevariousregionstowhichGrid25relates,aswellasrelevantcorrespondingdata–includingthatrelatingtolandscapeandecologicalconstraints–forNorthernIreland.Itwouldbeusefulifoffshoregridsgenerallyaimedtomakelandfallintheseareasanditwouldbedesirableforsuchdecisionstoconsidercomparable,equivalenton-shoreandoffshoredata.

Anyconsiderationofalternativeroutes/locationsforland/seaconnectionswillberequiredtoconsiderspatialandenvironmentalalternativesatthenextlevelofenvironmentalassessment–i.e.thatoflowertierplans,multipleorindividualprojects–asisrequiredbymitigationmeasureEMM4,whichhasbeenintegratedintotheIP.

11Referencedstatutoryobligation

Page 57: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

52

Figure 5.1 Less Sensitive12 Areas for Land/Sea Connections (identified in yellow)

12Presenceoflessenvironmentalsensitivities

 

Page 58: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

53

APPENDIX A - Network Reinforcement Projects, Demand Customer and DSO Connection Projects, and Generator Connection Projects, identified in EirGrid’s Transmission Development Plan 2010

CP No. Project Title & Description Major New Equipment

Project Justification ECD Phase

CP0217a Blake-Cushaling-Maynooth 110 kV Line - Loop into Newbridge 110 kV station

ExistingCushaling-Maynooth110kVcircuittobeloopedintoNewbridge110kVstationbetweenBlakeTandCushaling.

110kVbays:2110kVline:14km

Toimprovethequalityofsupplytothe110kVstationsinthisareabypreventinglowvoltagesandlineoverloadsundercertaincontingencies.

Jun-10 Complete

CP0241a Lodgewood 220kV Project - New 220kV Station

AnewLodgewood220/110kVstationinCo.Wexford,connectedintotheArklow-GreatIsland220kVlineandlinkedwithanewCrane-Lodgewood110kVline,througha250MVA220/110kVtransformer

220kVStation

220/110kV250MVATrafo:1

220kVbays:5

110kVbays:5

Inotherstations

110kVbays:1

New Line 220 kV line:1km

110kV:7km

Toprovidesupporttothe110kVnetworkinthisareaandbypreventinglowvoltagesandlineoverloadsundercertaincontingencies.

Dec-10 Complete

Table A1

Network Reinforcement Projects

A1 Network Reinforcement DevelopmentsThesecomprisedevelopmentprojectsthataredrivenbygenericdemandgrowthandthedeepreinforcementsresultingfromgeneratordemandandinterconnectorconnections.

Page 59: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

54

CP0264a Finglas 220kV Station:

5th 250MVA 220/110 kV Transformer (T2105)

Installationofafifth250MVA220/110kVtransformerandcoupler

220kVbays:2

110kVbays:2220/110kV250MVATrafo:1

TomaintainshortcircuitlevelswithinstandardsandtoalleviatepotentialoverloadingoftheMaynooth-Ryebrook110kVlineundercertainmaintenance-tripconditions.

Feb-10 Complete

CP0379 Carrigadrohid-Kilbarry 110 kV Line Uprate

Upratelineandbusbarstoequivalentof430mm2ACSR@80oC

Uprate110kVline

33.6km

Refurbishmentrequiredduetoconditionofline,uprateindicatednecessarybystudiesforGate2wind.

Dec-10 Complete

CP0451 Dungarvan-Knockraha 110kV Line Uprate

Upratelineto430mm2ACSR@80oC

Uprate110kVline:54km

Thisuprateisnecessarytoavoidunacceptableoverloadingofthe110kVduringcertaincontingenciesasaresultofnewgenerationinthesouthwest

Theupratingofthelinehasbeencompleted,workiscurrentlybeingcarriedouttoupratetheremoteendstoenablefulloperatingcapacityofthecircuit.

Dec-10 Complete

CP0512 New Capacitors at Kilkenny

Onenew30MvarcapacitoratKilkenny110kVstation

110kVstation.

110kVbays:1

Caps:1x30Mvar

ToensurethatvoltagesintheKilkennyareacontinuetocomplywithstandardsandtominimisetheriskofvoltagecollapsefollowingthetrippingoftheKilkenny-Kellis110kVline.

Mar-10 Complete

CP0515 New capacitor at Drumline:

One new 15 Mvar capacitor at Drumline 110 kV station.

110kVbays:1

Caps.:1x15MVar

ToensurethatvoltagesintheDrumlineareacontinuetocomplywithstandards.

Oct-10 Complete

CP0528 New capacitor at Kilteel

Onenew30MvarcapacitoratKilteel110kVstation

110kVbays:1

Caps.:1x30Mvar

ToensurethatvoltagesintheKildareareacontinuetocomplywithvoltagestandardsfollowingtheloopingofKilteelstationandtominimisetheriskofvoltagecollapse.

Nov-10 Complete

Page 60: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

55

CP0549a Shannonbridge-Dallow T-Portlaoise

110 kV Line Partial Uprate

Partiallineupratesothatallofthelineisequivalentto430mm2ACSR@80°C

Uprate110kVline:18.3kmof66.7km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Sep-10 Complete

CP0562 Great Island-Waterford 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80°C

Uprate110kVline

11.8km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Oct-10 Complete

CP0576 Cathaleen’s Fall-Corraclassy 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80°C

61.3km TheneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsofthelineintimesofhighwindoutputfromDonegal

Nov-10 Complete

CP0584 Shannonbridge-Ikerrin T 110 kV Line Uprate:

Upratelinetotheequivalentrating

of430mm2ACSR@80°Canduprateallstationequipmenttothisrating.

Uprate110kVline:

54km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Sep-10 Complete

CP0590 Raffeen-Trabeg No.2 110 kV Line Uprate:

Upratelinetotheequivalentof430mm2

ACSR@80°C.

Uprate110kVline:

9.23km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Dec-10 Complete

CP0592 Aghada-Raffeen 220 kV Cable

Thenew220kVcircuitconsistingofasectionofcableandasectionofoverheadline.Theoverheadlineportionofthecircuithasbeencompletedin2006

220kVbays:2

220kVcable:7km

220kVline:8km

TheincreasedgrowthinbothdemandandgenerationintheCorkareahasplacedalargestrainonthenetworksinthisarea.

Jun-10 Complete

Page 61: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

56

CP0626 Killonan-Knockraha 220 kV Line Uprate:

ReplacetheexistingconductorwithaHighTemperatureLowSag(GAP)conductortoachieveahigherrating.

Uprate220kVline:

82km

Conditionassessmentidentifiedtheneedforrefurbishment.Thelinewasreplacedwithoneofahigherratingwhichadherestocurrentstandards.

Dec-10 Complete

CP0175 Charleville-Killonan 110 kV Line Uprate

UprateLineto430mm2ACSR@80°C

Uprate110kVLine:

36.9km

Theneedforupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Theupratingofthelinehasbeencompletedandworkiscurrentlybeingcarriedouttoupratetheremoteendstoenablefulloperatingcapacityofthecircuit.

Jun-11 DetailedDesign&Construction

CP0197a Cushaling-Thornsberry 110kV New Line

ConstructionofanewCushaling-Thornsberry110kVlineasa2ndconnectiontoThornsberry110kVstation

110kVbays:2

110kVline:30km

Toimprovethequalityofsupplytothe110kVstationsinthisareabypreventinglowvoltagesandlineoverloadsundercertaincontingencies.

TheDSOhasrequestedasecond110kVlinetotheDSOstationatThornsberrytoimprovethesecurityofsupply.

Sep-11 DetailedDesign&Construction

CP0211 Srananagh 220 kV Station and Line:

AnewSrananagh220/110kVstationconnectedbyanew220kVlinetoFlagford

220kVstation;

110kVworknowcomplete

220 kV Station:

220/110kV250MVATrafo:1

220kVbays:3

New Lines:220kV:56km

ThisdevelopmentisneededtoreinforcethenetworkintheNorth-Westareabysupportingthevoltageandreducingtheriskoflossofsupplyduringthewinterpeaksandthesummermaintenanceoutages.

Itisalsorequiredtofacilitatetheexportofrenewablegenerationfromthenorthwest.

Dec-11 DetailedDesign&Construction

CP0218 Gorman-Navan No. 3 110 kV line:

AthirdlinefromGorman110kVstationto

Navan110kVstationwillbeconstructed.

110kVbays:2

110kVline:4km

ToalleviateunacceptableoverloadsofeitheroftheexistingGorman-Navan110kVlinesfrom2012undercertaincontingencies.

Sep-11 DetailedDesign&Construction

Page 62: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

57

CP0246a Tarbert-Tralee No.2 110 kV New Line

AsecondlinefromTarberttoTraleeconstructedat110kV

110kVbays:2110kVline:47km

Thisisneededtoovercome110kVlineoverloadsandvoltagecollapseintheTraleearea.

Nov-11 DetailedDesign&Construction

CP0254 Cashla loop-in of the Dalton-Galway 110 kV line:

LoopingoftheDalton–Galway110kVlineintotheCashlastation,creatingtheCashla–DaltonlineandtheCashla–GalwayNo.4110kVline.ThislinewillthenbeextendedouttothenewSalthill100kVstation,creatingaCashla-Salthill110kVline.RefCP0543inDSOsection.

110kVbays:2110kVline:22km

ToavoidoverloadingtheexistingCashla-Galway110kVlinesduringcertaincontingenciesbyremovingtheDaltonloadconnectionandprovidinganadditionalcircuitintoGalway.

Sep-11 DetailedDesign&Construction

CP0265 Cullenagh - Great Island 220 kV Line Uprate

Upratelinetoequivalentof600mm2HTLSACSR@80oC

Uprate220kVLine

23km

Theupratewillavoidunacceptableoverloadingofthelineduringcertaincontingencies.

Oct-12 DetailedDesign&Construction

CP0292a Gorman-Meath Hill 110 kV New Line

Anew110kVlinewillbeconstructedbetweenGormanandMeathHill110kVstations

110kVbays:2110kVline:30km

TheDSOhasrequestedasecondconnectiontoMeathHill110kVstation.

Dec-11 DetailedDesign&Construction

CP0374a Arva-Shankill No.2 110 kV New Line

Anew110kVlineconstructedbetweenArvaandShankill110kVstations.

110kVbays:2110kVline:20km

Toalleviateunacceptableoverloadsofanumberof110kVlinesintheareaforcertaincontingencyconditions.Thisreinforcementisassociatedwithgenerationconnection.

Dec-11 DetailedDesign&Construction

CP0371 Ballydine - Doon 110 kV Line Uprate (inc of Ballydine busbar) (11.4km)

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVline:11.4km

Theupratewillavoidunacceptableoverloadingofthelineduringcertaincontingencies.

Oct-12 DetailedDesign&Construction

Page 63: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

58

CP0406a Cashla-Cloon 110kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVline:23km

Theupratewillavoidunacceptableoverloadingofthelineduringcertaincontingencies.

Jun-11 DetailedDesign&Construction

CP0421 Binbane-Letterkenny 110 kV New Line (Donegal Reinforcement)

Anew110kVlinebetweentheexistingBinbaneandLetterkenny110kVstationsinCountyDonegal;thisnewlineisloopedintoanew110kVswitchingstation,Tievebrack,eastofGlentiestofacilitateDSOconnectiontoArdnagappary.

110kVbays:4110kVline:65km

TheDSOhasrequestedasecond110kVconnectiontoBinbane.TheBinbane-LetterkennylinemeetstheDSO’sneedswhilefacilitatinggenerationexportsfromDonegalduringlowdemandperiodsandmeetingtheincreasingelectricitydemandinthearea.

Oct-13 DetailedDesign&Construction

CP0467a Louth 220kV Station - Reactive Compensation

Installationofa30Mvarre-deployablecapacitorunitatthe110kVbusbarinLouthstation.

Louth 110 kV

Bays:1

Caps:1x30Mvar

Toresolvetemporaryandlongtermvoltageproblemsinthenortheast.

Jun-10 DetailedDesign&Construction

CP0511 Killonan 220kV Station

Installationofa4th220/110kVTransformer.Theunitwillhavearatingof250MVA.

220/110kV250MVATrafo:1

Requiredtoavoidoverloadingtheexisting63MVAtransformerswhenthe125MVAtransformerisoutofserviceandoneoftheremaining63MVAtransformerstrips.

Jun-11 DetailedDesign&Construction

CP0513 Carrickmines 220kV Station

Installationofa3rd250MVA220/110kVTransformer

220/110250MVATrafo:1

110kVbays:1

220kVbays:1

Necessarytoavoidunacceptablevoltagelevelsintheareawhenonetransformersisoutofserviceandthesubsequentlossofthesecondtransformer.

Oct-11 DetailedDesign&Construction

CP0514 Ardnacrusha 110 kV Station Reactive Compensation

Installationofanew30MvarcapacitoratArdnacrusha110kVStation.

110kVbays:1

Caps.:1x30Mvar

ToensurethatvoltagesintheArdnacrushaareacontinuetocomplywithstandards.

Jun-11 DetailedDesign&Construction

Page 64: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

59

CP0523 Inchicore 220kV Station - 4th 250MVA 220/110kV Transformer

Connectionofanew250MVA,220/110kVdoublewoundtransformer(T2103)inInchicore220kVstation;extensionoftheexistingGIS220kVbusbarandbuilding;installationofanew220kVtransformerbay,linebayandcoupler.

220kVbays:3

220/110250MVATrafo:1

Thiswillmaintainsecurityofsupplyandalleviateexisting220kVshortcircuitproblems.

Jun-11 DetailedDesign&Construction

CP0529 New Capacitor at Thurles

Onenew15MvarCapacitoratThurles110kVstation

110kVbays:1

Caps.:1x15Mvar

ToensurethatvoltagesintheThurlesareacontinuetocomplywiththeTPCandtominimisevoltagedropviolations

Oct-12 DetailedDesign&Construction

CP0537 Limerick-Moneteen 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVline

6.4km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Aug-11 DetailedDesign&Construction

CP0551 Cahir-Doon 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVline

6.4km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Aug-11 DetailedDesign&Construction

CP0552 Athlone-Shannonbridge 110 kV Line Uprate

Upratelinetoequivalentratingof430mm2ACSR@80oC

Uprate110kVline:21km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Oct-11 DetailedDesign&Construction

CP0575 Corraclassy-Gortawee 110 kV Line Uprate

RefurbishmentandfullupratingoftheCorraclassy-Gortawee110kVlinetoanequivalentof430mm2ACSR@80oC

Uprate110kVline

10.9km

AconditionassessmentoftheCorraclassy–Gortawee110kVlinewascarriedoutandshowedtherequirementtoreplacetheconductor.TheneedforupratinghasbeenidentifiedtoavoidpotentialoverloadsonthislineintimesofhighwindoutputfromDonegal

LineWorknowcomplete,Awaitingbayconductoruprate

Mar-11 DetailedDesign&Construction

Page 65: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

60

CP0586 Knockraha 220 kV Station

Installationofa3rd250MVA220/110kVtransformer

220/110kVtrafo:1

220kVbay:1

110kVbays:1

110kVcable:1

TwonewCCGTsinCorkdrivetheneedforadditionaltransformercapacityinKnockraha220kVstation.

Jun-11 DetailedDesign&Construction

CP0593 Aghada 220 kV AIS Station

Replacementandupgradingofexistingstation

220 kV Station

Theincreasedgrowthinbothdemandandgenerationisplacingalargestrainonthenetworksinthisarea.Theconditionoftheplantandapparatusduetoageisalsoafactor

Aug-11 DetailedDesign&Construction

CP0594 New Capacitors at Mullingar

Twonew15MvarcapacitorsatMullingar110kVstation

110kVbays:2

Caps:2x15Mvar

ToensurethatvoltagesintheMullingarareacontinuetocomplywiththeTPCandtocaterforincreasingdemand

Oct-12 DetailedDesign&Construction

CP0618 New Capacitors at Lisdrum

Installationoftwo15MvarfixedcapacitorunitsatLisdrum110kVstation

110kVbays:2

Caps:2x15Mvar

Toresolvethetemporaryandlongtermvoltageproblemsinthenortheast

Apr-11 DetailedDesign&Construction

CP0587 Glanagow-Raffeen 220 kV Underground Cable Circuit

Anew220kVcircuitconsistingofasectionofcableandasectionofoverheadline.

220 kV Cables

Underground:4km

Undersea:4.5km

220kVbays:2

ThisisnecessarytofacilitatetheexportofgenerationfromtheCorkharbourarea

Jul-11 DetailedDesign&Construction

CP0620 Arva-Gortawee 110 kV Line Uprate

RefurbishmentandfullupratingoftheArva-Gortawee110kVlinetoanequivalentof430mm2ACSR@80oC

Uprate110kVline:

30.6km

AconditionassessmentoftheArva-Gortawee110kVlinewascarriedoutin2008.Theneedforrefurbishmentwasidentifiedbythisassessmentwhilesystemstudiesindicatedtheneedtoupratetoavoidunacceptableoverloading.

Jun-11 DetailedDesign&Construction

Page 66: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

61

CP0517 Coolroe - Kilbarry 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

14.5km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Dec-12 DetailedDesign&Construction

CP0518 Coolroe - Inniscarra line uprate (inc Innicscarra busbar)

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

2.74km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Oct-11 DetailedDesign&Construction

CP0559 Butlerstown - Killoteran line uprate (inc of busbars)

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

2.7km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Oct-12 DetailedDesign&Construction

CP0560 Cullenagh - Waterford 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

12.5km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Oct-12 DetailedDesign&Construction

CP0637D Portlaoise busbar uprate-Athy Carlow Line Works

Busbars,sectionalisersanddisconnectorstobeuprated.

110kVStation:BBuprate:1

Theneedofupratinghasbeenidentifiedtoenabledevelopmentofthenetwork.

Oct-11 DetailedDesign&Construction

CP0656 Arklow - Crane 110 kV Line Uprate incl busbars in Arklow & Crane

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

41.8km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Aug-11 DetailedDesign&Construction

CP0659 Arva - Navan 110 kV Line Uprate & Line Works

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

65.5km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline.

Jul-11 DetailedDesign&Construction

Page 67: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

62

CP0667 Inchicore - Maynooth 1 & 2 220kV Line (double cct)- Uprate with HTLS

Uprate220kVLine

2x19km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Dec-12 DetailedDesign&Construction

CP0687 Dunmanway - Macroom 110kV Refurbishment

Newlineequivalentof430mm2ACSR@80oC

Uprate110kVLine

26.2km

ConditionAssessmentindicatesrequirementforlinerefurbishment.Existinglinetobeupgradedaccordingtocurrentpolicy

Oct-11 DetailedDesign&Construction

CP0689 Ennis 110kV station - Busbar Uprate

110kVStation:Busbaruprate:1

Theneedofupratinghasbeenidentifiedtoenabledevelopmentofthenetwork

Oct-12 DetailedDesign&Construction

CP0694 Athlone 110kV Busbar Uprate 110kVStation:Busbaruprate:1

Theneedofupratinghasbeenidentifiedtoenabledevelopmentofthenetwork

Dec-11 DetailedDesign&Construction

CP0696 Marina - Trabeg 1 110kV Cable Uprate

110kVCableuprate3.3km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Dec-12 DetailedDesign&Construction

CP0698 Prospect - Tarbert 220kV Line Uprate (7.7km)

Uprate220kVline

7.7km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Dec-12 DetailedDesign&Construction

CP0701 Cullenagh - Dungarvan 110 kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVline

34.32km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Oct-13 DetailedDesign&Construction

Page 68: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

63

CP0702 Butlerstown - Cullenagh 110kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

14.5km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Oct-13 DetailedDesign&Construction

CP0660 Cashla-Ennis 110 kV Line Uprate

UprateLinetoequivalentof430mm2@80oC

Uprate110kVLine

54.3km

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Jul-11 DetailedDesign&Construction

CP0466a&CP0469

North-South 400 kV Interconnection Development

Anew400kVlineconstructedbetweentheexistingWoodland400kVstation,insoutheastCo.MeathandTurleenaninCo.Tyrone

Woodland 400 kV

Bay:1

400kVline:140km

Toincreasetransfercapacitybetweenthetwosystemsinbothdirectionsandavoidsituationswhereasingleeventcouldleadtosystemseparation.Alsotoprovidenetworkreinforcementinthenortheast

Dec-14 PublicPlanningProcess1

CP0399 Moneypoint-Tarbert 220 kV New Cable

AnewsubmarinecableconstructedacrosstheShannonEstuaryfromMoneypointinCo.Claretoanew220kVstationwestofTarbertinnorthCo.Kerry;installationofanew400/220kVtransformerinMoneypoint

400kVbays:1

220kVbays:1

500MVATrafo:1

220kVcable:10km

Toprovideanalternativerouteforpowerintoandoutofthesouthwestaswellasanadditionallinkbetweenthe400kVand220kVnetworks.

Jul-13 PublicPlanningProcess2

CP0682 Woodland 400 kV Station - 2nd 400/220 500MVA Trafo

400kVStation:1

500MVATrafo:1

RequireddeepreinforcementforEast-WestInterconnector.

Jul-12 PublicPlanningProcess3

CP0683 Dunstown 400kV Station - 2nd 400/220 500MVA Trafo

400kVStation:1

500MVATrafo:1

RequireddeepreinforcementforEast-WestInterconnector.

Dec-12 PublicPlanningProcess4

1ThisprojectwasoriginallysubmittedasanapplicationforApprovaltoABP,butwaswithdrawnpriortoitsdetermination. TheprojectiscurrentlyatOutlineDesignorEIA2IncludingenvironmentalreportandAAscreening3Thisprojecthassubsequentlybeenapproved,andisnowatdetaileddesignandconstructionphase4Thisprojecthassubsequentlybeenapproved,andisnowatdetaileddesignandconstructionphase

Page 69: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

64

CP0647 Tarbert Redevelopment Project

New220/110kVstationtothewestoftheexistingTarbertStation.Allexisting110kVcircuitsconnectedintoTarbert220kVstationwillbedivertedtothisnewstation

220/110kVStation:1

220/110kVTrafos:3

220kVBays:12

110kVBays:12

RequiredtoaccommodateplannedgenerationinthesouthwestandtherefurbishmentoftheexistingTarbert220kVstation.Thenew110kVpartofthestationwillallowfortheexistingTarbert110kVequipmenttoberemovedforacleanupoflinesinthearea.AlsotherouteaccessintoTarbertisrestricted,thenewstationwillimprovethis

Jul-13 PublicPlanningProcess5

CP0501 Clashavoon-Dunmanway 110 kV New Line

Constructionofanew110kVlinefromClashavoontoDunmanwaystationandassociatedstationsworks

110kVline:35km

110kVbays:2

TheconstructionofaClashavoon-Dunmanway110kVlinewillimprovesecurityofsupplyforwestCorkandfacilitaterenewablegeneration

Mar-14 OutlineDesignorEIA

CP0580 Carrickmines 220 kV GIS Development

Replacementofexistingair-insulatedswitchgearwithgas-insulatedswitchgear(GIS);

Installationofanew4th220/110kVtransformer.

220kVsubstation:1

220kVbays:1

220/110kV250MVATrafo:1

Therequirementtochangetheswitchgearisduetotheassets’conditionandexpansionneeds.The4th220/110kV250MVAtransformerisnecessarytoavoidunacceptablelowvoltagelevelsintheareawhenonetransformerisoutformaintenanceandafaultoccursonasecondtransformer

Dec-12 OutlineDesignorEIA

CP0585 Laois /Kilkenny Reinforcement New Station & Associated Lines & Station Works

New400/110kVtransmissionstationinCo.Laois.ThestationwillbeloopedintotheexistingDunstown-Moneypoint400kVlineandCarlow-Portlaoise110kVline.

Anew110kVcircuitfromthenewstationtoKilkennyusingtheexistingBallyragget-Kilkenny38kVlinewhichisbuiltto110kVstandards.

Anew110/38kVstationatBallyraggettocaterforlossoftheKilkenny-Ballyragget38kVline.[DetailstobefinalisedwithDSO].

400kVStation

400kVbays:5

400kVbusbar

110kVStation:

110kVbays:7

110kVbusbar

Inother110kVstations

110kVbays:5

110kVOHL:30km

Thiswillprovideastronginjectionfromthe400kVnetworkintothe110kVnetworknearPortlaoise,andwillsignificantlyimprovethequalityandsecurityofsupplyincountiesLaois,CarlowandKilkennyandprovideforlongtermgrowththroughouttheregion.

Dec-14 OutlineDesignorEIA

5IncludingenvironmentalreportandAAscreening

Page 70: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

65

CP0596 New 110kV Circuit To Mullingar

Constructionofanew110kVcircuittoMullingar110kVstationfromeitherKinnegadorDerryiron110kVstations

110kVbays:2

110kVLine:30km

RequiredtoensurevoltagelevelsatMullingarremainwithinstandardsduringcertaincontingenciesandallowforeconomicgrowthinthearea

Oct-14 OutlineDesignorEIA

CP0597 Reinforcement of the Ardnacrusha & Ennis Area

UpratingoftheMoneypoint-Tullabrack-Booltiagh-Ennis110kVcircuittoequivalentof430mm2ACSR@80oC.DependentonMoneypoint400/220/110kVGISDevelopment,seeCP0688

Uprate110kVline:53.1km

ToalleviatelowvoltagelevelsintheArdnacrushaandEnnisareasduringthesummermaintenanceofcertainexistingoverheadlinesinthearea

Dec-14 OutlineDesignorEIA

CP0674 Tralee 110 kV Station

NewCoupler

110kVCoupler:1

RequiredtoimprovesecurityofsupplyinKerry

Aug-12 OutlineDesignorEIA

CP0688 Moneypoint - New 400/220/110kV GIS development

400,220,110kVstation

Requiredtocomplywithbusbarpolicyandsecurityofsupplystandards.Alsofacilitatedevelopmentoftransmissionnetwork

Oct-15 OutlineDesignorEIA

CP0699 Cathaleen’s Fall - Srananagh 1 110kV Line Uprate

Upratelinetoequivalentof430mm2ACSR@80oC

Uprate110kVLine

52.7km

110kVBay:1

Theneedofupratinghasbeenidentifiedtoavoidpotentialoverloadsoftheline

Oct-12 OutlineDesignorEIA

CP0709 Dunmanway 110kV Station Upgrade

100kVStation:

TrafoBay:1

BB/coupler:1

Requiredtocomplywithbusbarpolicyandsecurityofsupplystandards.Alsofacilitatedevelopmentoftransmissionnetwork

Dec-14 OutlineDesignorEIA

CP0707 Barrymore 110kV station extension - Loop into Cahir - Knockraha 110kV line

NewLines:110kV:

0.3km

DSOhasrequestedconnectionofof2nd110/38kVtransformer.Thisdrivesneedforfull4bayloopedinstationtocomplywithtransmissionstandards

Jun-13 OutlineDesignorEIA

CP0619 New Capacitors at Shankill

Installationof15Mvarand30Mvarre-deployablecapacitorunitsatShankill110kVstation

110kVbays:2

Caps:1x15Mvar

1x30Mvar

Toresolvethetemporaryandlongtermvoltageproblemsinthenortheast

OnHold

OutlineDesignorEIA

Page 71: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

66

Page 72: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

67

CP No. Project Title & Description Major New Equipment ECD Phase

CP0489 Castlebar 110 kV Station - New 110 kV Line bay for Carrowbeg

Carrowbegisthenameforanew110kVstationnearWestport,Co.Mayo,tailfedfromCastlebar.Installationof110kVequipmentinanexistinglinebayinCastlebar110kVstation.

Itisproposedthatthenewstationwillsupply1MVAofnewloadandaccommodatethetransferof22MWfromCastlebar

110kVbay:1 Jun-10 Complete

CP0535 College Park 110 kV Station - 3rd Transformer bay

Connect1X20MVA,110/10kVtransformer(T103)inCollegePark110kVstation.

ItisproposedthatthenewtransformerwillenableCollegePark110kVstationtoaccommodateanincreaseinMICof24MVA

110kVbay:1 Mar-10 Complete

CP0628 Doon 110 kV Station NewTransformerBay

110kVTrafobay:1 Dec-10 Complete

Table A2

DSO Connection Projects

A2 Demand Customer and DSO ConnectionsMostdemandconnectionstothetransmissionsystemaresoughtbytheDistributionSystemOperatorwhichappliesfornewstationconnections.TableA2liststhedevelopmentprojectsthatrelatedirectlytotheconnectionofnewTSO/DSOinterfacestationstothegrid,ortochangesinexistingconnectionarrangements.

Page 73: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

68

CP0631 Waterford 110 kV Station - Uprate 2 bays to 63 MVA

Replacetheexisting2x31.5MVATransformersatWaterford110kVstationwith2x63MVAunits.

110kVTrafobay:2 Sep-10 Complete

CP0173b Banoge 110 kV New Connection

TheexistingArklow-Crane110kVlineloopedintoBanoge110kVstation,creatingnewArklow-BanogeandBanoge-Crane110kVlines.Thisstationhasalreadybeenbuiltandisawaitingconnection

110 kV station

110kVbays:4

110kVline:6km

Jun-11 DetailedDesign&Construction

CP0201a Athy 110 kV Station

TheexistingCarlow-Portlaoise110kVlineloopedintoanewAthy110kVstation,creatingnewAthy-PortlaoiseandAthy-Carlow110kVlines.

Stationiscompleteandenergised,butistee’dontoCarlow-Portlaoise110kVline.

Afurtheroutageisrequiredin2010toloopthisnewstationintotheexistingcircuit.

110 kV station

110kVbays:5

110kVline:18km

Dec-11 DetailedDesign&Construction

CP0507 Arklow 220/110 kV Station –

New2x20MVADSOTransformers(T2101/T2102)tobeinstalledtoaccommodategrowingloadinthearea

110 kV bays: 2 Mar-11 DetailedDesign&Construction

CP0543 Salthill 110kV Station - New Station

Newlooped110kVstationwillbebuiltonsiteofexistingSalthill38kVstation.SalthillwillbeconnectedtoGalway110kVstationandtoCashlabyre-directingtheproposedCashla-Galway110kVNo.4linetoSalthill,whichwillbecomeCashla-Salthill110kV.ThisprojectalsoincorporatesabayinSalthillfortheDSOconnectiontoScreeb

110kVlinebays:5

110kVtrafobays:3

110kVcable:12km

Jul-11 DetailedDesign&Construction

CP0630 Carlow 110 kV Station - Uprate 2 bays to 63 MVA

Replacetheexisting2x31.5MVATransformersatCarlow110kVstationwith2x63MVAunits

110kVTrafoBay:2 Oct-11 DetailedDesign&Construction

CP0646 Finglas 110 kV Station

New 35 bay 110 kV GIS Station to replace existing 110 kV AIS.

110kVStation

Bays:35

Dec-14 PublicPlanningProcess6

6Thisprojecthassubsequentlybeenapproved,andisnowatdetaileddesignandconstructionphase

Page 74: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

69

CP0437a North Dublin 220kV Project - New 220kV Station

A new 220 kV station in the Balgriffin area and associated networks. The development is part of a wider TSO/DSO agreed reinforcement strategy to enhance the network in the northern fringe of Dublin city. The station will be tail fed from Finglas 220 kV using cable and constructed with GIS.

The process of acquisition of a new site for this project is currently underway.

220kVStation(GIS):1

220/110kV250MVATrafo:1

220kVbays:1

Inotherstations

220kVbays:1

220kVcable;15km

Dec-14 OutlineDesignorEIA

CP0506 Finnstown 220kV Project

(Adamstown) - New 220kV Station

Finnstown 220 kV station, south of Lucan, a new 220 kV station looped into the Inchicore-Maynooth No. 1 and No.2 220 kV lines. The station will be initially a single transformer 220 kV station, but allow final development for a four transformer station. Due to space restrictions on potential sites an entirely GIS station is proposed.

220kVGISstation

Trafobay:4

Line/cablebays:4

Couplerbay:3

220/110kV250MVATrafo:1

110kVGISStation

Doublebusbar:1

Trafobay:4

Line/cable/MVtrafobays:8

GIScouplerbay:3

Mar-14 OutlineDesignorEIA

CP0644 Bracklone 110 kV Station and Loop In

New 110 kV station to be looped into Portlaoise-Newbridge 110 kV line. Replaces existing Portarlington 38 kV Station.

110kVstation

linebays:2

TrafoBays:2

Mar-14 OutlineDesignorEIA

CP0649 Drumline 110 kV Station Works

Two 20 MVA Transformers supplying 12.2 MW New load and 11.4 MW transfered load from existing Drumline transformers.

110KVBays:2 Jun-13 OutlineDesignorEIA

CP0627 Bandon 110 kV Station

New Transformer Bay.

110kVTrafobay:1 OnHold

OutlineDesignorEIA

CP0075 Ballycummin 110 kV New Station

New station looped into the Limerick-Moneteen 110 kV line.

110kVlinebays:5

110kVline:0.2km

OnHold

OutlineDesignorEIA

CP0629 Monread 110 kV Station

New Transformer Bay

Cancelled – included in Minor Capital Works instead Jan 10)

110kVTrafoBay:1 Dec-10 Cancelled

Page 75: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

70

Page 76: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

71

CP No. Project Title & Description Major New Equipment ECD Phase

CP0563 IPP62 Garvagh Connection

Installation of Garvagh 110 kV bay in Corderry 110 kV station (IPP build)

Bays:1(locatedatCorderry110kV)

Line:7km

Apr-10 Complete

CP0599 IPP048E Coomagearlahy Wind Farm Extension

A new bay in the existing Coomagearlahy 110 kV station to facilitate an extension of the wind farm (IPP Build)

110kVBay:1 Feb-10 Complete

CP0614 IPP142 Edenderry Peaker Project

A new 110 kV bay at the existing Cushaling 110 kV station to connect a new 116 MW distillate generator

Bays:1(atCushaling110kV) Apr-10. Complete

CP0555 IPP111 Castledockrill Connection

A new 110 kV station connected to Lodgewood station, see CP241 in Table 4-2. This will facilitate connection of DSO windfarm. (IPP Build).

110kVstation

110kVbays:2

110kVCable:6.6km

Dec-10 Complete

Table A3

Generator Connection Projects

A3 Generator ConnectionsThissectionoutlinestheprojectsunderwaythatrelatedirectlytoconnectionofgenerationtothetransmissionsystemortochangesinexistinggenerationconnectionarrangements.Someoftheseconnectionsare“contestable”,i.e.thegeneratorhasdecidedtobuildtheconnectionassetstoTSOspecifiedstandards.Itshouldbenotedthatthisisdependentonprogressbytheapplicant.

Page 77: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

72

CP0479a IPP055 Athea Phase 1 Connection

A new Athea 110 kV station connected to the existing Trien 110 kV station for the connection of Athea Windfarm (IPP Build).

110kVGISStation

Bays:7(inc.1bayatTrien110kV)

Line:13km(toDromada)

Jul-11 DetailedDesign&Construction

CP0595 Glanagow 220 kV Station

A new 220 kV GIS station for the connection of a new CCGT plant. (Already generating, with temporary connection via AIS station)

New220kVStation:1 Jul-11 DetailedDesign&Construction

CP0500 North Kerry Project

A new 220 kV station looped into the existing Clashavoon-Tarbert 220 kV line. The work includes connection works for Athea, Dromada and Cloghboola windfarms

220kVStation:1

250MVATrafo:1

Bays:2

110kVStation:1

Bays:5

Line:15.2km

Apr-14 OutlineDesignorEIA

CP0603 IPP088 Mulreavy Connection

Connection of a new 110 kV station for connection of new windfarm.

110kVStation:1

110kVBays:5

110kVLine:7.7km

Jan-12 OutlineDesignorEIA

CP0608 IPP119 Cloghboola Wind Farm

Connection of a new windfarm into the existing Trien 110 kV station.

110kVStation

Bays:3

Line:13km

Trien110kV

Bays:1

Apr-14 OutlineDesignorEIA

CP0615 Glenree 110kV Station

Connection of a new 110 kV station, looped into the existing Cunghill-Moy 110 kV line. This station will facilitate the connection of new DSO windfarms.

110kVStation

Bays:3

Sectionaliser:1

Line:1.4km(2x0.7km)

Sep-11 OutlineDesignorEIA

CP0648 Garrow 110 kV Station

Extension Works for a new 110 kV transformer bay for the provision of renewable energy.

110kVstation

110kVLineBays:3

110kVTrafoBay:1

110kVCoupler1

110kVbusbarextension

Aug-11 OutlineDesignorEIA

CP0650 Millstreet 220/110 kV station

New 220/110 kV station looped into the existing Clashavoon-Tarbert 220 kV line for the connection of wind farms.

220/110kVStation

220/110kVTrafo:1

220kVBays:2

110kVBays:1

Aug-14 OutlineDesignorEIA

Page 78: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

73

CP0651 East Kerry & North West Cork 220 kV Station

A new 220 kV station looped into the existing Clashavoon-Tarbert 220 kV line for the connection of wind farms. Two new 110 kV lines will be constructed, one to Glenlaraand the other to the planned Cordal station in Co. Kerry. Knockacummer connection into Glenlara is also part of this project.

220/110kVStation

220/110kVTrafo:1

220kVBays:2

110kVBays:2

Jan-14 OutlineDesignorEIA

CP0602 IPP044 Keelderry Wind Farm

Connection of a new windfarm to a new station, looped into the existing Agannygal-Derrybrien 110 kV line.

110kVStation:1

Bays:3

OnHold OutlineDesignorEIA

CP0641 IPP118 Nore Power Station

Extension works in the existing Kilkenny station for the connection of a new OCGT.

110kVstation

110kVbusbarextension

110kVCableBay(atKilkenny)

OnHold OutlineDesignorEIA

CP0669 IPP159 Cuilleen Power Shallow Connection

Connection of a new OCGT into the existing Athlone 110 kV station

Athlone110kVstation

LineBay:1

110kVCoupler

OnHold OutlineDesignorEIA

CP0670 IPP112 Suir Power Shallow Connection

Connection of a new OCGT into the existing Cahir 110 kV station

110kVStation

110kVbusbarextension

110kVCableBay:1(atCahir)

OnHold OutlineDesignorEIA

Page 79: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

74

CP No. Project Title & Description Major New Equipment ECD Phase

CP0652 East-West Interconnector

Shallow connection of East-West Interconnector into Woodland

400 kV station from new HVDC/HVAC Converter Station at Portan, near Woodland in Co. Meath

400kVbays:1

400kVtailedconverterstation:1

400kVcable:500m

Sep-12 DetailedDesign&Construction

Table A4

Interconnector Connection Projects

A4 Connection of InterconnectorsThissectionoutlinestheprojectsthatrelatedirectlytotheconnectionofinterconnectorstothetransmissionsystem.ThesearelistedinTableA4.

TheCable-layingvessel‘Nostag’atworkonEastWestInterconnectorinWales

Page 80: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

75

AsextractedfromSection9oftheEnvironmentalReportoftheSEAaccompanyingthisIP.

EMM8 Other Measures Integrated into the IPMitigationmeasuresdescribedbelowhavebeenwordedtofacilitatedirecttranscriptionandincorporationintotheImplementationProgramme.

NotethatthefollowingmitigationmeasureswillbeextendedandaugmentedbytheoutputfromtheEnvironmentalBenchmarkingStudiesandEvidence-BasedDesignGuidelinesdescribedabove.

EMM8A Biodiversity and Flora and Fauna

EMM8A(i) Designated European and National Sites of Nature Conservation Interest

Everyeffortwillbemadetoavoiddesignatedsitesofconservationimportance.However,wherethisisnotpossible,routingwillbeselectedtoensurenosignificantimpactsontheintegrityofthesite.Restrictedworkingareaswillbeimposedtoensureminimaldisturbancetosensitivehabitats.

Sensitiveconstructiontechniqueswillbeusedsuchastheuseofbogmatsformachineryaccess,particularlyifundergroundcablesareproposedorinremoteboglandareas.Aerialaccesswillbeconsidered–forbothmaterialsandworkforce–inexceptionallysensitivesites.

Ecologicalmonitoringwillbeundertakenatsensitivesitesduringconstructionasappropriate.Suchsiteswillbeidentifiedonacasebycasebasis.

EMM8A(ii) General Habitat Loss and Disturbance

• Wherepossible,directhabitatlosswithindesignatedsiteswillbeavoided.

• Whenconstructionoccurswithinadesignatedsite,sensitiveconstructiontechniqueswillbeusedsuchastheuseofbogmatsformachinery

access,particularlyifundergroundcablesareproposedorinremoteboglandareas.Aerialaccesswillbeconsidered–forbothmaterialsandworkforce–inexceptionallysensitivesites.

• Useofbog-matstominimisetheimpactofheavymachineryonvegetationandsoils.

• Minimiseextentofworksareas.

• Re-distributevegetationandsoilstrippedfromtheconstructionareastoprovideaseedbankanddonotre-seedwithPerennialRyegrass.

• Landwithintheworkingareawillbereinstatedasnearaspracticaltoitsformercondition.

EMM8A(iii) Bogs and Peatland areas

• Areasofdeepandactivepeatshallbeavoided.

• Detailedpeatslipriskassessmentsshouldbecarriedoutforallproposeddevelopmentsinareaswherepeatsubstratesoccur.

• Constructionmachineryshouldberestrictedtositeroadsanddesignatedaccessroutes.Machineryshouldnotbeallowedtoaccess,parkortraveloverareasoutsidedevelopmentconstructionzones.

• Peatexcavatedduringconstructionactivityshouldnotbestored(temporarilyorotherwise)onareasofadjacentmirehabitatsornearflushesordrains.Temporarystorageofspoilmaterialexcavatedduringtheconstructionphasedevelopmentsshouldbestoredatsuitablelocationsawayfromsurfacewatercourses.

• Allspoilmaterialexcavatedduringtheconstructionphaseshouldbereinstatedfollowingthecompletionoftheconstructionphaseofaproposeddevelopment.

• Wheredisturbanceofpeatsoilscannotbeavoided,thereshouldbesomeconsiderationgiventopossiblere-seedingwithnativespeciestostabilisethepeatandacceleraterecoveryofthevegetation.

APPENDIX B - Environmental Mitigation Measures

Page 81: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

76

EMM8A(iv) Birds

• Wherefeasible,siteclearanceinvolvingthecuttingordestructionofvegetationandhedgerowsshallnottakeplaceinthebirdbreedingseasonbetweenMarch1standAugust31stinclusive.

• Intheeventthatsiteclearancedoestakeplaceduringthebirdnestingseason,theappropriatelicencewillbeappliedfor.

• Ontheadviceofrelevantornithologicalexpertsandagenciesbirdwarningdevicesshallbeputinplacewherecrossingsofsensitiveflightcorridorscannotbeavoided.

EMM8A(v) Bats

• Theremovalofbatcommutingandforaginghabitatshallbeavoidedwherepossibleduringtheconstructionandoperationphaseofinfrastructure.

• Wheretheremovalofcommutingorforaginghabitatcannotbeavoidedalternativehabitatshouldbeestablishedpriortosuchhabitatremoval.

• Treesscheduledforfellingaspartofsiteclearanceshallbecheckedbyabatspecialistforthepresenceofbats.

• Wherebatsarenotedtobewithinatreepriortofellingoperations,itwillbenecessarytopostponefellingtocreatetheopportunityforbatstoceaseusage.Ifbatsdonotleaveatreeorbuildingwithinareasonabletimeframe,itmaybepossibleforabatspecialisttoseektoexcludethebats(orotherwiseremovethemtosafety).ThisshallbecarriedoutbyaqualifiedbatspecialistwithwrittenpermissionfromtheNationalParksandWildlifeSectionoftheDepartmentofArts,HeritageandtheGaeltachtbywayofalicencetoderogatefromtheprotectionaffordedbatsbyIrishandEUlaw.Alllicencesshallbeinplacepriortofellingproceduresastodestroyaroostwithoutalicenceisanoffence.

EMM8A(vi) Otters

• Destructionofactiveotterholtsshallbeavoided

• Noworksshallbeundertakenwithin150mofanyholtsatwhichbreedingfemalesorcubsarepresent.

• Nowheeledortrackedvehicles(ofanykind)shouldbeusedwithin20mofactive,butnon-breeding,otterholts.Lightwork,suchasdiggingbyhandorscrubclearanceshouldalsonottakeplacewithin15mofsuchholts,exceptunderlicence.

EMM8A(vii) Other protected species

• Thebreedingandrestingsitesofprotectedspeciesshallbeavoidedduringtheappropriateseasons.

• Heavymachineryshallnotbeusedwithin30mofanoccupiedbadgersett.

• AderogationlicencefromtherespectiveWildlifeActs13shallbesought–andworksshallnotbecommencedwithoutsuchconsentwhereitappearsthatprotectedfloraandfaunaspeciesarelikelytobeunavoidablydisturbed.

EMM8A(viii) Protected Surface Water or Riparian Habitats

Inallcaseswhereworkshavethepotentialtoimpactonprotectedsurfacewaterorriparianhabitats,theInlandFisheriesIrelanddocumentRequirementsfortheProtectionofFisheries Habitat during Construction and Development Works at River Sitesshallbeadheredto.DevelopmentoftransmissioninfrastructureadjacenttodesignatedfisheriesshallbecarriedoutinconsultationwithInlandFisheriesIrelandtominimisethepotentialeffectsondesignatedsurfacewaters.

13Referencedstatutoryobligation

Page 82: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

77

EMM8A(ix) Freshwater Pearl Mussel Catchments

• ActionmeasuresasoutlinedintheSubBasinManagementPlansshallbetakenintoaccountwheredevelopmentisconsideredadjacenttoareasassociatedwithFreshwaterPearlMussels.

• InthevicinityofwatersthatsustainpopulationsofFreshwaterPearlMusselsthefollowingadditionalmitigationmeasuresshallbeemployed:

• Thereshallbenostreamcrossingbymachinery.

• Siltywaterwillbecollectedinsettlementponds priortodischargetowatercourse.

• Bufferingstripswillbeprovidednear watercourses.

EMM8A(x) Fisheries

• AllworksadjacenttodesignatedfisherieswaterswillbedoneinconsultationwithInlandFisheriesIreland.

• AllworksinvolvingopencutcrossingsshallbeconductedduringtheperiodMaytoSeptembertoavoidinterruptionofsalmonidspawningruns,spawning,incubationofeggsandtheearlydevelopmentalstages.

• Whereappropriateandpractical,bankvegetationandbedmaterialwhichhasbeenremovedshallbestoredtofacilitateitsreplacementwhenchannelworkshavebeencompleted.

• Worksinthevicinityofawatercourseshallbecarriedoutwithreferencetoawaterqualityprotectionplanforeachsitewhichshallensurethat:

• Allnecessarymeasuresshallbetakento minimisethegenerationandreleaseof sedimentsintoallwatercourses.

• Levelsofsuspendedsolidsintherivershallbe monitoredduringthecourseoftheworks.

• Precautionsshallbeputinplacetoavoid spillagesofdiesel,oilorotherpollutingsubstances.

EMM8A(xi) Mature Trees

Whereconstructionworkisrequiredclosetotrees,theNationalJointUtilitiesGroup‘GuidelinesforthePlanningInstallationandMaintenanceofUtilityServicesinProximitytoTrees’(NJUG10)willbefollowed.

EMM8A(xii) Hedgerows

Alldisturbedhedgerowswillbere-plantedassoonaspossibleafterconstruction,usingIrishnurserystockandindigenousspecies.Plantingwillbemaintaineduntilvigorousre-growthhasbeenestablished.Wherehedgesofparticularvalueareencounteredtheextentanddurationoftheworksshallbeminimised.Forspecies-richbanks,turfwillbestrippedandstoredseparatelyforreplacementorre-instatement.

EMM8B Water Resources

EMM8B(i) Accidental spillage of fuel chemicals or sewage causing pollution to water or ground

• Develop,implementandenforceaWaterPollutionPreventionandEnvironmentalEmergencyResponsePlanforallworksites.ThisshouldincludegoodsitepracticesasdescribedintheGoodPracticeGuidancenotesproposedbyEA/SEPA/EHS.

EMM8B(ii) Suspended solids & sediment deposition

• Precautionsshallbeputinplacetoavoidorminimisethegenerationandreleaseofsediments14intoallwatercourses.

EMM8B(iii) Physical Damage to watercourses

• Develop,implementandenforceacodeofbestpracticeforconstructionandreinstatementmethodstobeusedforunavoidableconstructionworksinthevicinityofwatercourses.

14Sedimentsinthisinstanceincludeallsoilsincludingpeat.

Page 83: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

78

EMM8B(iv) Flooding

• Withinknownfloodplains,measuresshallbetakentoavoidanypotentialimpactofconstructionorexistenceoftheworksonthecapacityforfloodwaterstorage.

• Damagetoanyflooddefenceembankmentsshallbeimmediatelyrepairedtoastandardequaltoorbetterthantheexistingembankments.

• EirGridshallcarefullyexaminedevelopmentproposalstoensureconsistencywiththerequirementsofThe Planning System and Flood Risk Management: Guidelines for Planning Authorities(DEHLG,2009)15.

• EirGridshallengagewithplanningauthoritiesatanearlystage,utilisingarrangementsforpre-planningapplicationconsultationwithregardtoanyfloodriskassessmentissuesthatmayarise.

• EirGridshallcarryoutasite-specificfloodriskassessment,asappropriate,andcomplywiththetermsandconditionsofanygrantofplanningpermissionwithregardtotheminimisationoffloodrisk.

EMM8C Soils and Geology

EMM8C(i) Geological Features

• Siteinvestigationsshallbeundertakenatintervalsandspecificlocationsalongthepowercircuitroute.Thisinformationshallbeusedtoplansiteworkoperationstoanticipate,avoidorminimiseconstructionimpactsarisingfromdisturbanceofsub-surfaceconditions.

• Cutandfilloperationsshouldbeavoidedunlessabsolutelynecessary.

• RouteselectionandlowertierassessmentsshouldconsultGeologicalSurveyofIrelandasappropriateinrelationtogeologicalheritagesiteseitherrecommendedforNHAorCountyGeologicalSitedesignation.

EMM8C(ii) Soil

• Heightofstockpilesshouldbelimitedtolessthat3mandstoragetimewillbeminimised.

• Materialhandlingandreinstatementoperationsshouldfollowgoodpracticetoavoidinadequateorovercompactionofthematerials.

• RouteselectionandlowertierassessmentsforpeatlandareasshouldconsiderrelevantgovernmentguidelinesondevelopmentintheseareasaswellasrelevantdatasetsincludingtheGeologicalSurveyofIreland’slandslidedatasetandTeagasc’ssubsoilsdataset.

EMM8C(iii) Mineral Resources

Thepowercircuitshallberoutedtoavoiddisturbancetoexistingorplannedoperationsofareasofextractionandlicensedmineralreserves.

EMM8C(iv) Contaminated Land

• Agroundinvestigationmaybeundertakentosurvey,analyseandassesstheareaswherethereisapotentialforthisrisktoarise.

• Followingthis,methodstatementsshallbepreparedtodealwithanyareaofcontaminatedground.

EMM8C(v) Bedrock

• RouteselectionandlowertierassessmentsshouldconsiderGeologicalSurveyofIreland’sbedrockdataasappropriateinordertoanticipateengineeringdifficulties.

• RouteselectionandlowertierassessmentsshouldconsiderIrishNationalSeabedSurveydataandINFOMARsurveydataasappropriatetoanticipatethenatureanddepthofstablesubstrateforoffshoreprojectsfoundationsandconnectiontoonshoregrid.

15Referencedstatutoryobligation

Page 84: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

79

EMM8D Cultural Heritage• Wheretheproposedrouteisincloseproximityto

archaeologicalsitestheworkingareashallbekepttoaminimum.

• Pre-constructionworksshallbecarriedoutinthoseunrecordedareasidentifiedashavingarchaeologicalpotential.

• TherewillbefullimplementationofanArchaeologicalPlanincluding,pre-constructionworks,watchingbriefandexcavation.

• Wherepreviouslyunrecordedfindsareuncoveredduringconstruction,adequatearchaeologicalinvestigationandrecordingwillbecarriedoutbeforeconstructionworksintheseareasarecontinued.

EMM8E Landscape and Visual

Routesshallbeselectedaccordingtothefollowingcriteria:

• Avoidanceofareasdesignatedasbeingofscenicsensitivityorsignificance.

• Avoidanceofareasthatwoulddisproportionatelyimpingeuponsensitivelandscapefeatures–suchasprominentskylineridges,shores,rivercrossings.

• Avoidareasthatwoulddisproportionatelyimpingeuponsensitiveareasorsitesofculturalorhistoricsignificance–includingmonuments,listedandprotectedstructuresandtheircontextsandsites.

• Routeselectionandlowertierassessmentsshouldconsider(asappropriate)datafromthelandscapecharacterassessmentscontainedinthedevelopmentplansoflocalauthorities.

EMM8F Noise

Inrelationtonoisesensitivereceptors,theconstraintsmappingidentifiedareasofhighbuildingdensityandthereforeanyroutecorridorsselectedshallattempttominimiseimpactsonbuiltupareas.

EMM8G Liquid Effluent and Spillages

Portabletoiletswillbeprovidedatthesiteoffices.Theywillbeemptiedregularlybyaspecialistcontractorasappropriate.

EMM8H Solid Wastes

WasteManagementPlanswillbepreparedaspartoftheoverallprojectdesign.Thiswillidentifylikelywastearisings,approximatequantitiesandappropriatehandlinganddisposalmethods.

EMM8I Construction of New Substations and Extension of Existing Substations

EMM8I(i) Theconstructionofnewsubstationscanhaveasignificantimpactparticularlywheretheareaisundeveloped.Siteselectionneedstoensuresensitivelandscapesandhabitatsareavoided.Opportunitiesfornaturalscreeningfromtopographyandvegetationshouldbemaximisedandusedwhereverpossibleasthiswillprovidethebestopportunityforintegratingthefacilityintotheexistinglandscape.

EMM8I(ii)Itwillbeimportanttoensurethatsubstationsarenotlocatedwithinthefloodplainofmajorwatercourses,whichcouldimpactontheaccessandfunctioningofthesubstation.Also,itwillalsobeimportanttoensurethatnewsubstationlocationsavoiddesignatedconservationsitesandsensitivehabitatswherepossible.

EMM8I(iii) Whereexistingsubstationsneedtobeextendeditwillbeimportanttoensuretheextensiondoesnotimpactonanynearbybuiltupareasandthattheextensionisappropriatelydesignedtoensureadequateintegrationwiththeexistingenvironment.Thescaleoftheextensionshouldbesuitedtothesurroundingareaandshouldnotbeinappropriategiventhesizeoftheexistingfacilityanditssurroundings.

Page 85: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

80

EMM8J Reinforcement of the Transmission System in the Regions16

EMM8J(i) Midlands Region TheMidlandsRegionistransectedbymanykilometresofmajorandminorgridinfrastructureaswellashavingasignificantconcentrationofjunctionsandsubstations–manyassociatedwithexistingorformerpowerstations.Theseroutesandsitesofferstrongprecedentthatshouldbere-usedwhereverpossible.Itshouldberecognisedthatlargeareasofcut-overpeatlandsmaynotbesuitablelow-resistanceroutingoptionsasmanyofthesesitesarenearingtheendofproductionandmostifnotallwillshortlybereinstatedaspeatlandsitesthatarelikelytobedeemedtobesensitive–ifnotprotected–habitats.

NewmajorgridprojectsinthisRegionwillbechallengedwhentryingtoidentifyoptimumcrossingpointsoverthesensitiveShannonsystem.Existingcrossingpointsshouldbere-usedorintensifiedwhereverpossible.Suchcrossingpointsshouldbeidentifiedandsecuredinregionalandcountydevelopmentplansasamatterofurgency–theyarenationallysignificanteconomicassets.

EMM8J(ii) South-East Region LargerscalegriddevelopmentsintheSouth-EastRegionshouldparallelcoastalplainsandmajorriversystems–ideallyoccupyingthetransitionalfoothills–withoutencroachingoneitherthemoresensitiveuplandsortheimmediateenvironsofriversandcoasts.

Mostmajorrouteswithinthisregionfollowthetransitionbetweenuplandsandlowlandsandcauselittleadverseenvironmentaleffect.Iffuturedevelopmentcontinuesthisgeneralpatternthereisalowpotentialforsignificanteffectstoarise.

EMM8J(iii) Mid-West Region MajorgriddevelopmentworksintheMid-WestRegionshouldre-useorcloselyfollowestablishedroutingsorareaswithestablishedprecedentoflarge-scaleinfrastructuralandindustrialdevelopment.Newworksshouldparallelthecoastsandrivers–whichcontaindensecorridorsofancientlyestablishedsettlement–whileavoidingmoresensitiveuplandinteriors.Highlevelsofruraldwellingsinsomeareasmayrequiresub-optimalproximitytosomeenvironmentalsensitivities,suchasculturalheritage.

EMM8J(iv) South-West Region IfnewgriddevelopmentcontinuespatternsoffollowingthestronglyEast-WesttrendingrivervalleysintheSouth-WestRegionthereisalowpotentialforsignificantadverseeffectsontheenvironment.Majorgriddevelopmentsshouldbeconfinedtothemoreenvironmentallyrobustcentreandeastofthisregion.

ThedevelopmentofnewtransmissionlinesbetweenMoneypointandCorkCitywouldneedtocarefullyconsiderecologicalandvisualimpactissues,especiallyinuplandareas.Alternativesshouldconsiderthereuseofexistingpowerandtransportlinks.

EMM8J(v) Dublin & Mid-East Region ItwouldbeusefultointegratewithDevelopmentplans–bothatRegionalandCountylevel-toidentifyinfrastructurecorridors–ideallyparallelingtheexistingandemergingmajorroadandrailcorridorsthatwilldevelopintheDublinandMid-EastRegionduringtheperiodto2025.Itwouldalsobeofmerit,forworkinginexistingandemergingurbanandperi-urbanareas,toclearlyidentifycriteriathatwouldleadtodeterminingwhenandwheretoundergroundelectricityinfrastructure.

16NotethatnospecificmeasurearestatedherefortheBorderandWestRegions;allothermitigationmeasuresapplyasrelevant.

Page 86: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

81

LandUsePlansforUrbanAreasshouldbeencouragedtospecificallyzonelandforsub-stationsandtoprotectexistingstrategiccorridorsfrominappropriatedevelopment.

EMM8K National and EU Legislation and Plans/Programmes

Wheregridrelateddevelopmentisproposed,EirGridwillseektocontributetowardstheprotectionofenvironmentalfeatures,asrelevantandappropriate

toEirGrid’sresponsibilitiesandobligationsundernationalandEUenvironmentallegislationandincludingthosewhichrelatestospecificregional/nationalplans/programmesforparticularaspectsoftheenvironmente.g.CatchmentFloodRiskAssessmentandManagementStudyPlans,RiverBasinDistrictManagementPlansandFreshWaterPearlMusselSubBasinManagementPlans.

Page 87: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic
Page 88: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic
Page 89: 2011 - 2016...Implementation Programme 2011 - 2016 GRID25 Implementation Programme 2011 - 2016 Section 1 - Introduction and Context 1.1 Context 2 1.2 The Vision of Grid25 5 1.3 Strategic

TheOval,160ShelbourneRoad,Ballsbridge,Dublin4.

Tel +353(0)1677 1700Fax +353(0)1661 5375

[email protected]

PRNA11/0158

TheOval,160BótharShíolBhroin,DroicheadnaDothra,BaileÁthaCliath4.

Tel +353(0)1677 1700Fax+353(0)1661 5375

Environmental Impact Services2ndFloor,TheCourtyard,25GreatStrandStreet,Dublin1.