2011 08 proposed nuclear power development: hinkley point c, an update – nigel knee

15
(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved. 1 Proposed Nuclear Power Station Development: Hinkley Point C an update Nigel Knee Severn Estuary Forum 23 rd September 2011

Upload: severnestuary

Post on 12-Apr-2017

169 views

Category:

Engineering


3 download

TRANSCRIPT

Page 1: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.1

Proposed Nuclear Power Station

Development: Hinkley Point C

– an update

Nigel Knee

Severn Estuary Forum23rd September 2011

Page 2: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.2

About EDF Energy

• UK’s biggest electricity generator

• Operator of 8 nuclear power stations

• Continued operation of two coal-fired stations

• Development of new gas-fired power stations

• Renewables – onshore and offshore wind

• New nuclear power stations

- 4 EPR units in the UK

- Preferred sites are Hinkley Point & Sizewell

• Gas and electricity supplier to 5.5 million customers

• We employee 15,000 people across the UK

Page 3: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.3

Why nuclear?

Decarbonisation of electricity

…help keep the (low carbon) lights on

Diverse and secure energy mix

Page 4: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.4

Electricity supplied by fuel type 2010

Contribution of

low-carbon

electricity today

Gas 47%

Coal 28%

Oil 1%

Nuclear

16%

Wind - 3%

Hydro &

others - 4%

Imports - 1%

Source: UK Energy in Brief 2011

Page 5: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.5

Government’s view – National Policy Statements

(July 2011)

- urgency of the need for new electricity capacity

- At least 59GW of new capacity by 2025

- 33GW from renewable sources by 2025

- need for 18GW of new non-renewable capacity, plus 8GW

already under construction

- new nuclear power should be free to contribute as much as

possible

Source: Overarching National Policy Statement for Energy, DECC, June 2011

Page 6: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.6

UK nuclear power station sites

EDF Energy nuclear

power stations

Other nuclear power

stations

EDF Energy Site in draft

NPS

Other sites in draft NPS

Sizewell

Torness

Hartlepool

Dungeness

Hunterston

Heysham

Hinkley Point

Wylfa

OldburyBradwell

Sellafield

Note: The assessment process

for potential new build sites did

not apply in Scotland

Page 7: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.7

Hinkley

Point

Bridgwater

Burnham-on-Sea

Page 8: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.8

Special Area of Conservation

Special Protection Area

SSSI

AONB

Bridgwater

Hinkley

Point

Page 9: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.99

New Nuclear Vision

• Safety,

reliability, and

sustainability

• Maximise

Benefits

• Mitigate

Impacts

Page 10: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.1010

Hinkley Point C – Ongoing activities: land

remediation

Page 11: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.1111

Environmental mitigation (1) – bat house

Page 12: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.1212

Environmental mitigation (2) – artificial badger sett

Page 13: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.1313

Environmental mitigation (3) – temporary badger

sett

Page 14: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.14

Temporary jetty – view from Burnham-on-Sea

JettyHinkley Point B

Page 15: 2011 08 Proposed Nuclear Power Development: Hinkley Point C, An Update – Nigel Knee

(NOT PROTECTIVELY MARKED) Severn Estuary Forum 23 September 2011 Partnership © EDF Energy plc. All rights Reserved.15

Hinkley Point C - Next steps

• Commence site preparatory works (subject to clearance of conditions)

• Obtain consent for temporary jetty(Marine Management Organisation)

• Application for Development Consent Order(Infrastructure Planning Commission)

• Progress application for Nuclear Site Licence(Office for Nuclear Regulation)

• Consultation on environmental discharge authorisations (Environment Agency)