Page 1: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

2009 Sales Tax ExtensionProject Status Update

Page 2: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

2

Background

• Sales Tax was extended via August 26, 2008 referendum.

• Sales Tax was extended for an additional six (6) years, beginning January 2009, through December 2014.

• Proceeds from Sales Tax are received from the State quarterly. Receipt of funds will begin March 2009.

• Estimated revenue to Charlotte County is $108 million.

Page 3: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

3

Financial Issues

• Revenue projections still keep collections at $108 Million – over 6 year period.

• “Pay as you go strategy” – traditionally works well with road projects.

• If cash flow issues arise, we can first look to borrow internally or if necessary utilize short term external borrowing.

Page 4: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

4

The Projects

• Edgewater Drive – Phase II• Midway Boulevard• Placida Road• Burnt Store Road – Phase III• Sidewalks

Page 5: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

5

Edgewater Drive - Phase IIMidway Boulevard to Harbor Boulevard

Page 6: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

6

Edgewater Drive

Page 7: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

7

Edgewater Drive

Page 8: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

8

Edgewater Drive – Phase IIOverview

• Estimated total project costs = $28.9 million.• $20 million allocated via 2009 Sales Tax Extension.• Remaining funding via Transportation Impact Fees and Gas Tax.• Widen existing 2-lane roadway to a 4-lane divided roadway

between Harbor Boulevard and Midway Boulevard.• Project length is approximately 2 miles.• Replace Sunrise Waterway bridge.• Replace East Spring Lake bridge.• Replace West Spring Lake bridge.• Modify geometrics and signalization at Harbor Boulevard

intersection.• Widen and signalize Midway Boulevard intersection.

(Signalization subject to meeting Florida Department of Transportation warrants).

Page 9: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

9

Edgewater Drive - Phase IIProject Schedule

• Initiate engineering design and permitting FY09• Initiate right-of-way acquisition FY10• Construction start FY12• Construction completion within 3 years.

Page 10: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

10

Midway BoulevardElkcam Boulevard to Kings Highway

Page 11: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

11

Midway Boulevard at Kings Highway

Page 12: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

12

US 41 Pipe Crossings

Page 13: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

13

Midway BoulevardOverview

• Estimated total project cost = $51.5 million.• $30 million allocated via 2009 Sales Tax Extension.• Remaining funding via Transportation Impact Fees and Gas Tax.• Widen existing 2-lane roadway to a 4-lane divided roadway between

Elkcam Boulevard and Kings Highway.• Replace and upgrade existing water control structures (weir and box

culvert) at the Elkcam Waterway, Yale Waterway, Fordham Waterway and Niagara Waterway.

• Directional bore twin 84” pipes under US 41 in the Elkcam Waterway.• Directional bore twin 84” pipes under US 41 in the Fordham Waterway.• Replace/upsize existing weir structure in the Elkcam Waterway north of

the US 41 Access Road.• Replace/upsize existing weir structure in the Fordham Waterway north

of the US 41 Access Road.• Project is in 3 phases.

Page 14: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

14

Midway Boulevard – Phase IProject Schedule

• Road widening from Elkcam Boulevard to Harbor Boulevard.• Replace/upsize water control structures at the Elkcam Waterway, Yale

Waterway, Fordham Waterway and Niagara Waterway.• Improvements to the Harbor Boulevard intersection.• The water control structures have already been designed and permitted. • Roadway plans are approximately 90% complete.• Public Works is processing a design contract change order for

signalization design at the Harbor Boulevard intersection.• Charlotte County Utilities is processing a design contract change order

for utility relocates.• Phase I remains on track for a construction start by mid to late 2009.• Estimated construction duration 18 months.• Roadway plans have been submitted to SWFWMD for permitting.

Page 15: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

15

Midway Boulevard – Phase IIProject Schedule

• Design, permit and construct US 41 pipe crossings at the Fordham Waterway, Niagara Waterway and Pompano Waterway.

• Design, permit and construct (replace/upsize) existing weir structure in the Fordham Waterway north of the north US 41 Access Road.

• Design, permit and construct (replace/upsize) existing weir structure in the Elkcam Waterway north of the north US 41 Access Road.

• Design and permitting efforts for all components of Phase II are underway.

• Permitting by Florida Department of Transportation and Southwest Florida Water Management District is required.

• Construction permit application for the US 41 pipe crossings has been submitted to the Florida Department of Transportation.

• A conceptual SWFWMD permit application has been submitted.

Page 16: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

16

Midway Boulevard – Phase IIIProject Schedule

• Complete widening of Midway Boulevard from Harbor Boulevard to Kings Highway.

• Phase II will have to be substantially complete before Phase III can begin.

• Construction plans are more than 30% complete.• Due to the dependence on completion of Phase II and the

complexity of Phase II, Phase III construction may not start until mid 2010 or later.

• A design change order will be forth-coming to complete the roadway design per roadway elevations as approved by

SWFWMD during Phase II permitting.

Page 17: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

17

Placida RoadRotonda Boulevard West to Cape Haze Drive

Page 18: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

18

Placida Road

Page 19: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

19

Placida RoadOverview

• Estimated total project costs = $41.3 million.• $28 million allocated via 2009 Sales Tax Extension.• Remaining funding via Gas Tax.• Widen existing 2-lane road to 4-lane divided roadway

between West Rotonda Boulevard and Cape Haze Drive.

• Project length is approximately 3 miles.

Page 20: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

20

Placida RoadProject Schedule

• Initiate engineering design and permitting FY09.• Initiate right-of-way acquisition FY10.• Construction start FY12.• Construction duration 2 years.

Page 21: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

21

Burnt Store Road - Phase IIIZemel Road to Lee County Line

Page 22: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

22

Burnt Store Road – Phase IIIOverview

• Estimated total project costs = $25.5 million.• $20 million allocated via 2009 Sales Tax Extension.• Remaining funding via Gas Tax.• Widen existing 2-lane roadway to a 4-lane divided

roadway.• Project length is approximately 2 miles.• Phase III is the roadway segment between Zemel

Road and the Lee County line.

Page 23: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

23

Burnt Store – Phase IIIProject Schedule

• Initiate engineering design and permitting FY10.• Initiate right-of-way acquisition FY11.• Construction start FY13.• Construction duration 2 years.

Page 24: 2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional

24

Sidewalks

• FY09 Sales Tax allocation is $10 million.• Estimated FY09 proceeds $2,160,000.• Design and construction will be balanced to start

construction in FY09.• Projects will be distributed among West County, Mid-

County and South County.