20-jan-09 madrid, spain global design effort 1 barry barish madrid, spain 20-jan-09 designing the...
TRANSCRIPT
20-Jan-09 Madrid, Spain Global Design Effort 1
Barry BarishMadrid, Spain
20-Jan-09
Designing the ILC
ATF-2 Final Doublet System
20-Jan-09 Madrid, Spain Global Design Effort 2Global Design Effort 2
• Introduction to the ILC Global Design Effort• The motivation: science potential• Status and plans• Key elements of the accelertor R&D and
design effort • Detectors• Final Remarks
Outline
20-Jan-09 Madrid, Spain Global Design Effort 3
Why e+e- Collisions ?
• elementary particles
• well-defined
– energy,
– angular momentum
• uses full COM energy
• produces particles democratically
• can mostly fully reconstruct events
20-Jan-09 Madrid, Spain Global Design Effort 4
LHC: Low mass Higgs: H ggMH < 150 GeV/c2
Rare decay channel: BR ~ 10-3
Requires excellent electromagnetic calorimeter performance
acceptance, energy and angle resolution,
g/jet and g/p0 separation Motivation for LAr/PbWO4 calorimeters
for CMS
Resolution at 100 GeV: 1 GeV
Background large: S/B 1:20, but can estimate from non signal areas CMS
20-Jan-09 Madrid, Spain Global Design Effort 5
ILC: Precision Higgs physics
Model-independent Studies
• mass
• absolute branching ratios
• total width
• spin
• top Yukawa coupling
• self coupling
Precision MeasurementsGarcia-Abia et al
20-Jan-09 Madrid, Spain Global Design Effort 6
The linear collider will measure the spin of any Higgs it can produce by measuring the energy dependence from threshold
How do you know you have discovered the Higgs ?
Measure the quantum numbers. The Higgs must have spin zero !
20-Jan-09 Madrid, Spain Global Design Effort 7
Precision measurements of the Higgs?
Precision measurements of Higgs coupling
Higgs Coupling strength is proportional to Mass
20-Jan-09 Madrid, Spain Global Design Effort 8
Studying the Higgs
SM 2HDM/MSSM
Yamashita et al Zivkovic et al
Determine the underlying model
20-Jan-09 Madrid, Spain Global Design Effort 9
How the physics defines the ILC
20-Jan-09 Madrid, Spain Global Design Effort 10
Parameters for the ILC
• Ecm adjustable from 200 – 500 GeV
• Luminosity ∫Ldt = 500 fb-1 in 4 years
• Ability to scan between 200 and 500 GeV
• Energy stability and precision below 0.1%
• Electron polarization of at least 80%
• The machine must be upgradeable to 1 TeV
20-Jan-09 Madrid, Spain Global Design Effort 11
ILC – Underlying Technology
• Room temperature copper structures
OR
• Superconducting RF cavities
20-Jan-09 Madrid, Spain Global Design Effort 12
SCRF Technology Recommendation
• The recommendation of ITRP was presented to ILCSC & ICFA on August 19, 2004 in a joint meeting in Beijing.
• ICFA unanimously endorsed the ITRP’s recommendation on August 20, 2004
20-Jan-09 Madrid, Spain Global Design Effort 13
Superconducting RF Technology
• Forward looking technology for the next generation of particle accelerators: particle physics; nuclear physics; materials; medicine
• The ILC R&D is leading the way Superconducting RF technology– high gradients; low noise; precision optics
20-Jan-09 Madrid, Spain Global Design Effort 14
main linacbunchcompressor
dampingring
source
pre-accelerator
collimation
final focus
IP
extraction& dump
KeV
few GeV
few GeVfew GeV
250-500 GeV
Designing a Linear Collider
Superconducting RF Main Linac
20-Jan-09 Madrid, Spain Global Design Effort 15
Luminosity & Beam Size
• frep * nb tends to be low in a linear collider
• Achieve luminosity with spot size and bunch charge
Dyx
repb HfNn
L2
2
L frep [Hz] nb N [1010] x [mm] y [mm]
ILC 2x1034 5 3000 2 0.5 0.005
SLC 2x1030 120 1 4 1.5 0.5
LEP2 5x1031 10,000 8 30 240 4
PEP-II 1x1034 140,000 1700 6 155 4
20-Jan-09 Madrid, Spain Global Design Effort 16
• Low emittance machine optics• Contain emittance growth• Squeeze the beam as small as possible
Achieving High Luminosity
~ 5 nmInteraction Point (IP)
e- e+
20-Jan-09 Madrid, Spain Global Design Effort 17
– 11km SC linacs operating at 31.5 MV/m for 500 GeV– Centralized injector
• Circular damping rings for electrons and positrons• Undulator-based positron source
– Single IR with 14 mrad crossing angle– Dual tunnel configuration for safety and availability
ILC Reference Design
Reference Design – Feb 2007
Documented in Reference Design Report
20-Jan-09 Madrid, Spain Global Design Effort 18
RDR Design Parameters
Max. Center-of-mass energy 500 GeV
Peak Luminosity ~2x1034 1/cm2s
Beam Current 9.0 mA
Repetition rate 5 Hz
Average accelerating gradient 31.5 MV/m
Beam pulse length 0.95 ms
Total Site Length 31 km
Total AC Power Consumption ~230 MW
20-Jan-09 Madrid, Spain Global Design Effort 19
ILC RDR – A Complete Concept
• Reference Design Report (4 volumes)
ExecutiveSummary
Physicsat theILC
AcceleratorDetectors
20-Jan-09 Madrid, Spain Global Design Effort 20Global Design Effort 20
RDR Design Parameters
Max. Center-of-mass energy 500 GeV
Peak Luminosity ~2x1034 1/cm2s
Beam Current 9.0 mA
Repetition rate 5 Hz
Average accelerating gradient 31.5 MV/m
Beam pulse length 0.95 ms
Total Site Length 31 km
Total AC Power Consumption ~230 MW
20-Jan-09 Madrid, Spain Global Design Effort 21
Next: Build a Solid Technical Design
• Complete crucial R&D to reduce technical risk– SCRF gradient; final focus; electron cloud
• Optimize the ILC design for coherence, simplicity and cost / performance– Minimum Machine
• Develop capability to industrialize, construct ILC worldwide and develop international model for governance– Project Implementation Plan
20-Jan-09 Madrid, Spain Global Design Effort 22
ILC-GDE Organization Chart
SCRF-ML G-CFS AS
EU
AM
AS
ILCSC FALC
ILC-GDE Director
Regional Directors
Project Managers
AAP
PAC FALC-RG
Director’s Office= ~ Central Team
= ~ EC
Experts
Project. M. Office- EDMS- Cost & Schedule- Machine Detector Interface- ILC, XFEL, Project X liaison- ILC Communications
20-Jan-09 Madrid, Spain Global Design Effort 23Global Design Effort 23
TD Phase 1
• Timescale: Interim report mid 2010• Major theme: High-priority risk-mitigating
R&D and studies of cost reduction ideas– R&D demonstrations of critical items
– Minimum design -- top down cost/performance optimizaton to develop a new baseline by 2010
– Studies of governance models for a global project– Development of a site selection plan with ILCSC– Or how do we reduce the time to construction start and
therefore to physics results?
20-Jan-09 Madrid, Spain Global Design Effort 24Global Design Effort 24
• Timescale: Produce report by mid-2012• First goal: New baseline design
– SCRF – S1 Test of one RF unit
– Detailed technical design studies–
– Updated VALUE estimate and schedule
– Remaining critical R&D and technology demonstration
• Second Goal: Project Implementation Plan.
TD Phase 2
20-Jan-09 Madrid, Spain Global Design Effort 25Global Design Effort 25
R&D Plan - Technical Design Phase
• First Official Release June 08
• A 50 page document with details of all programs and schedules
• New: Release 3
Global Design Effort
20-Jan-09 Madrid, Spain Global Design Effort 26
Detector Concepts Report
20-Jan-09 Madrid, Spain Global Design Effort 27
detectorB
may be accessible during run
accessible during run Platform for electronic and
services (~10*8*8m). Shielded (~0.5m of concrete) from five sides. Moves with detector. Also provide vibration isolation.
Push-Pull Concept for two detectors
The concept is evolving and details being worked out
detectorA
20-Jan-09 Madrid, Spain Global Design Effort 28
Detector Performance Goals• ILC detector performance requirements and
comparison to the LHC detectors:○ Inner vertex layer ~ 3-6 times closer to IP
○ Vertex pixel size ~ 30 times smaller
○ Vertex detector layer ~ 30 times thinner
Impact param resolution Δd = 5 [μm] + 10 [μm] / (p[GeV] sin 3/2θ)
○ Material in the tracker ~ 30 times less
○ Track momentum resolution ~ 10 times better
Momentum resolution Δp / p2 = 5 x 10-5 [GeV-1] central region
Δp / p2 = 3 x 10-5 [GeV-1] forward region
○ Granularity of EM calorimeter ~ 200 times better
Jet energy resolution ΔEjet / Ejet = 0.3 /√Ejet
Forward Hermeticity down to θ = 5-10 [mrad]
20-Jan-09 Madrid, Spain Global Design Effort 29
Detector Performance Goals
20-Jan-09 Madrid, Spain Global Design Effort 30
Detector Performance Goals
20-Jan-09 Madrid, Spain Global Design Effort 31
Detector Plans
20-Jan-09 Madrid, Spain Global Design Effort 32
Detector Plans
20-Jan-09 Madrid, Spain Global Design Effort 33
Final Remarks
• The accelerator design is now in the technical design phase, which will culminate in 2012 with completion of crucial R&D and optimized cost / performance / risk design (see M Ross – next talk)
• The physics simulations and detector development are equally challenging. There are opportunities in fundamental detector R&D, in detector design, simulations, etc
• The science motivation for a lepton collider is very strong. We await LHC for validation, and then we should be ready to make a strong proposal.
20-Jan-09 Madrid, Spain Global Design Effort 34
Final Comment
• Over the next few years we must put together an irresistible case to achieve our dream of building a new major global particle accelerator
• You may ask whether we have the will, motivation and strength to succeed??
• Borrowing from hope, success and inspiration of our new U.S. president (by 6pm tonite).
YES WE CAN!!