20 foundation

33
Foundations Prof Schierle 1 Foundations Prof Schierle 1 FOUNDATIONS

Upload: limuel-espiritu

Post on 29-Sep-2015

6 views

Category:

Documents


0 download

DESCRIPTION

oooo

TRANSCRIPT

  • Foundations Prof Schierle 1Foundations Prof Schierle 1

    FOUNDATIONS

  • Foundations Prof Schierle 2Foundations Prof Schierle 2

    Liquefaction reduced the soil strength under these apartment buildings in Niigata (Japan) 1964.

    Liquefied soil exerts higher pressure on retaining walls, displace them and cause settlement of retained soil.

    LiquefactionLiquefaction reduces soil strength and stiffnessby earthquakes shaking. Liquefaction causedgreat damage in past earthquakes.

    Liquefaction occurs in sandy soil saturated withwater. Earthquakes increase the water pressureto make the soil liquid.

  • Foundations Prof Schierle 3Foundations Prof Schierle 3

    LandslideLandslides are movements of surfacematerial down a slope. Landslides may be caused by earthquakes.

    During a Northridge Earthquake aftershocklandslide dust blows eerily out of the SantaSusana Mountains into the Simi Valley

  • Foundations Prof Schierle 4

    To avoidexpensiveearthquakesettlementrepair ...

    Sustainable hill site design

  • Foundations Prof Schierle 5

    Buildings adapted to site to avoid differential grading settlement

    to reduces gradingand retaining wallsand avoid expensivesettlement repairs

    . adapt buildings to site instead of adapting site to buildings

  • Foundations Prof Schierle 6Foundations Prof Schierle 6

    Soil Capacity Soil type Soil capacity (approximate)Soft clay 2 ksf 100 kPaStiff clay 4 ksf 200 kPaSand, compacted 6 ksf 300 kPaGravel 15 ksf 700 kPaSedimentary rock 50 ksf 2400 kPaHard rock (granite) 200 ksf 9600 kPa

  • Foundations Prof Schierle 7Foundations Prof Schierle 7

    1 Shallow footing (in areas of no frost)2 Frost-free footing (depth per map below)A Slab on grade, 4 with welded wire mesh (8 edge resists shear)B Gravel bed and waterproof membraneC Base plate, pressure treated, min 6 above gradeD Plywood sheathingE Anchor bolts at max. 4 o. c. F Footing rebarsG CMU stem wall with dowel bars & waterproof membraneH Stem wall keyI Perforated drain pipe at base of footingJ Gravel bed

    F

    r

    o

    s

    t

    p

    e

    n

    e

    t

    r

    a

    t

    i

    o

    n

    m

    a

    p

  • Foundations Prof Schierle 8

    Footing types1 Column footing

    2 Grade beams

    3 Wall footing

    4 Mat footing

    5 Piles (joint by pile caps to distribute load)

    6 Grade beams join pile caps for lateral stability

  • Foundations Prof Schierle 9Foundations Prof Schierle 9

    Footing type use

  • Foundations Prof Schierle 10Foundations Prof Schierle 10

    Poor quality excavationcauses poor footings

    Stepped footingat sloping site

    Formwork providesbetter quality

    Footing construction

  • Foundations Prof Schierle 11Foundations Prof Schierle 11

    ReinforcingPost footings require 2-way reinforcing

    Wall footings require length reinforcing

    Wide wall footings require also width reinforcing

    Concrete and CMU walls require dowel bars(must overlap with wall bars 40 bar diameter)

  • Foundations Prof Schierle 12Foundations Prof Schierle 12

    Hold-down & post baseTo resist overturning, wood shear wallsrequire hold-downs at both sides

    Hold-down ties wall to footing

    Twin hold-downs tietop wall to wall below

    Post base ties post to footing

  • Foundations Prof Schierle 13Foundations Prof Schierle 13

    W

    a

    l

    l

    f

    o

    o

    t

    i

    n

    g

    W

    i

    t

    h

    s

    t

    e

    m

    w

    a

    l

    l

    a

    n

    d

    c

    r

    a

    w

    l

    s

    p

    a

    c

    e

    Wall footing designAssume: Soil capacity unknown, use code minimum f = 1500 psf2-story wood framingFloor load (incl. walls) DL = 25 psf

    LL = 40 psfRoof load (incl. walls) DL = 15 psf

    LL = 20 psfTotal load = 100 psf

    Tributary width supported by walle = 20/2 e = 10Wall load per footw = 100 psf x 10 w = 1000 plfFooting DL estimate(assume 8x4 stem wall+1.5x1 ftg.)w = 150 pcf (1.5x1+4x8/12) w = 625 plfTotal loadw = 1000+625 w = 1625 plfRequired footing widthb = w/f = 1625/1500 = 1.1 use b = 18

    b

  • Foundations Prof Schierle 14Foundations Prof Schierle 14

    B

    a

    s

    e

    m

    e

    n

    t

    w

    a

    l

    l

    C

    o

    n

    c

    r

    e

    t

    e

    o

    r

    C

    M

    U

    (

    c

    o

    s

    t

    l

    e

    s

    s

    )

    N

    o

    t

    e

    :

    i

    f

    g

    r

    e

    a

    t

    f

    r

    o

    s

    t

    d

    e

    p

    t

    h

    i

    s

    r

    e

    q

    u

    i

    r

    e

    d

    ,

    b

    a

    s

    e

    m

    e

    n

    t

    s

    a

    r

    e

    c

    o

    s

    t

    -

    e

    f

    f

    e

    c

    t

    i

    v

    e

  • Foundations Prof Schierle 15Foundations Prof Schierle 15

    Concrete wall footing designAssume: Soil capacity Soft clay f = 2000 psf2-story concreteFloor load (incl. walls) DL = 170 psf

    LL = 50 psfRoof load (incl. walls) DL = 120 psf

    LL = 20 psfTotal load = 360 psf

    Tributary width supported by walle = 20/2 e = 10Wall load per footw = 360 psf x 10 w = 3,600 plfFooting DL estimate(12 basement wall, 9 high)w = 150 pcf (3x1.5+1x9) w = 2,025 plfTotal loadw = 3,600+2,025 w = 5,625 plfRequired footing widthb = w/f = 5,625/2000 = 2.8 use b = 3

  • Foundations Prof Schierle 16Foundations Prof Schierle 16

    Post footing DesignAssume:2-story buildingSoil capacity (stiff clay) f = 4 ksfLoads: 150 psf DL + 50 psf LL = 200 psfTributary area A = 30x30 A = 900 ft2Post load P = 2x200x900/1000 P = 360 kFooting DL (estimate 10x10x18)P = 10x10x1.5x150 pcf/1000 P = 23 kRequired Footing areaAf = P/f =(360+23)/4 ksf Af = 96 ft2Footing sizeb = Af1/2 = 961/2 = 9.8 use 10x10x18

  • Foundations Prof Schierle 17Foundations Prof Schierle 17

    Post template with anchor bolts, furnished by steel fabricator, installed in concrete footing

    Post with base plate, replacing template, attached to anchor bolts

    Twin nuts to align postprior to grouting

    Grouting

    Steel column base

  • Foundations Prof Schierle 18Foundations Prof Schierle 18

    Steel erection

  • Foundations Prof Schierle 19Foundations Prof Schierle 19

    Construction steps:

    1 Excavate

  • Foundations Prof Schierle 20Foundations Prof Schierle 20

    Construction steps:

    2 Place reinforcingDowel bars must overlap post/wall bars minimum 40 bar diameters

  • Foundations Prof Schierle 21Foundations Prof Schierle 21

    Construction steps:

    3 Place concrete

  • Foundations Prof Schierle 22Foundations Prof Schierle 22

    Mat footingCrown Zellerbach building, San FranciscoArchitect: SOM with Hertzka and KnowlesEngineer: H J Brunnier

    The 19-story building has a mat footing that extends under the entirebuilding to resist ground water buoyancy during constructionBuilding height: 285Footing depth: 8

    69

  • Foundations Prof Schierle 23

    Pile and caissonPiles and caissons/piers are used in poor soil to increase bearing capacity

    Piles are driven into soil Caissons/piers are cast into shafts that areexcavated or drilled

    1 Steel H-pile2 Timber pile3 Concrete piles4 Piles

    Left: end-bearing pileRight: friction pile (100 -400 plf)

    5 Caissons/piersLeft: Caisson with bell to increase bearingRight: straight caisson

    6 Pile caps

  • Foundations Prof Schierle 24

    ROCK

    SOFT SOILPILES

    End Bearing PilesEnd bearing pile transmit load through soft soil to rest on firm soil or rock

    Friction PilesIf firm soil is too deep, friction piles resist load by friction between pile and soil

    SOFT SOILPILES

    Pile types

  • Foundations Prof Schierle 25

    Pile drivingCason/pier drilling

  • Foundations Prof Schierle 26

  • Foundations Prof Schierle 27

    0.87

    0.69

    0.46

    0.58

    0.40

    0.23

    Skin Friction(psi)

  • Foundations Prof Schierle 28Foundations Prof Schierle 28

    Retaining walls1-3 Mass retaining walls4 Concrete / CMU wall

    at property line with adjacent land lower5 Concrete / CMU wall6 Concrete / CMU wall

    at property line with adjacent land higher7 Concrete / CMU wall with shear key8 Concrete / CMU wall with shear key9 Concrete / CMU wall with shear keyNote: shear key adds lateral resistance

    Floor bracing

    Temporary bracing

  • Foundations Prof Schierle 29Foundations Prof Schierle 29

    H-shape steel piling

    Tiebacks anchor wall to soil

    Wood boards

    Bolts tie concrete wall to piling

    Dowel bars tie concrete to footing

    Footing

    Retaining wall with tiebacks

  • Foundations Prof Schierle 30

    Tie-back

    Installation

    Prestressingwith hydraulic jack

  • Foundations Prof Schierle 31Foundations Prof Schierle 31

    Slot cuttingUsed for retaining walls at property line

    Slot cutting steps:

    1 Cut slots in retaining slopes

    2 Build retaining wall segments

    3 Backfill retaining walls after about a week(backfill adds soil pressure)

    4 Cut soil between wall segments

    5 Construct infill retaining walls

  • Foundations Prof Schierle 32Foundations Prof Schierle 32

    Base isolators dampen seismic load, similar to theeffect of shock absorbers on cars

    Base Isolators

    Base isolators reduce differential building drift

    Base isolators consist of rubber and steel sheetstied together by a central bolt and lead cylinder

    Buildings with base isolators must be isolatedfrom surrounding ground to allow free movement

    Base isolators are effective for low-rise buildingsbut increase overturn tendency of tall buildings

    Base isolators are placed between footing andcolumns or walls

    Kerckhoff Hall UCLA, base isolator upgradeCourtesy WWCOT Architects

  • Foundations Prof Schierle 33Foundations Prof Schierle 33

    ENDEND