2. workplan and works completion programme 20-11-2013
TRANSCRIPT
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
1/26
WORKPLAN AND WORKS COMPLETION PROGRAMME
WORK PROGRAMDesign and Construction of a Leachate
Treatment Plant at Livade Landfill in
Podgorica, Montenegro
Description of the Work Program
2013
JOINT VENTURE: ERGASIS TECHNIKI S.A.
KARKANIAS S.A.21/10/2013
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
2/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 2
TABLE OF CONTENTS
1. DOCUMENTATION OF WORK IMPLEMENTATION PROGRAMME ..................4
1.1. INTRODUCTION..........................................................................................................4
1.2. NOTICE OF AWARD OF CONTRACTNOTICE TO COMMENCEFINAL
DESIGN .....................................................................................................................................5
1.3. ACCESS TO THE SITE.................................................................................................6
1.4. MOBILIZATION SCHEDULE........................................................................................6
1.5. PRELIMINARY WORKS ................................................................................................7
1.6. CIVIL WORKS ...............................................................................................................8
1.6.1. EQUALIZATION TANK - SBR FEED TANKS - ODOR ................................. 9
1.6.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK .......................... 10
1.6.3. SLUDGE THICKENER ........................................................................... 10
1.6.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASH TREATED
WATER......................................................................................................... 11
1.6.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION . 12
1.7. MECHANICAL WORKS............................................................................................... 13
1.7.1. EQUALIZATION TANK - SBR FEED TANKS - ODOR ............................... 13
1.7.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK - ODOR FACILITY 14
1.7.3. SLUDGE THICKENER ........................................................................... 15
1.7.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASH TREATED
WATER......................................................................................................... 15
1.7.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION . 16
1.8. ELECTRICAL WORKS................................................................................................ 16
1.8.1. EQUALIZATION TANK - SBR FEED TANKS - ODOR ............................... 17
1.8.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK .......................... 17
1.8.3. SLUDGE THICKENER ........................................................................... 18
1.8.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASH TREATED
WATER......................................................................................................... 18
1.8.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION . 19
1.8.6. PLCSCADA ...................................................................................... 19
1.9. GENERAL WORKS...................................................................................................... 20
1.9.1. PIPE WORKS BETWEEN UNITS ............................................................ 20
1.9.2. PAVEMENTS - WALKWAYS - LANDSCAPING .......................................... 21
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
3/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 3
1.9.3. ELECTRICAL INSTALLATIONS .............................................................. 21
1.9.4. ROAD WORKS .................................................................................... 21
1.10. TRIAL OPERATIONAL PERIOD............................................................................ 21
1.11. DEFECTS NOTIFICATION PERIOD..................................................................... 22
2. COMMENTS ..................................................................................................................... 23
PART : ACTIVITY SCHEDULEWORK PROGRAMME (GANNT DIAGRAM) ..... 24
PART C: MILESTONESRESOURCES ............................................................................. 25
PART D: CASH FLOW ............................................................................................................ 26
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
4/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 4
1. DOCUMENTATION OF WORK IMPLEMENTATION
PROGRAMME
In this chapter is described analytically, the Work Programme for the following
project: "Design and Construction of Leachate Treatment Plant at
Livade Landfill in Podgorica, Montenegro. This Work Programme it has
been done according to the Design and the Bidding Documents of the a.m.
project. The implementation and completion of the project within the time
limits, which are described in the documentation of the bid is main scope for
the construction schedule. Additional the construction schedule has a structure,
which it has its fundamental elements in realization of the Works that it has to
be done. After the analysis of all the factors, the weather conditions, the
compliance with all the environmental and construction laws and regulations of
the Montenegro, etc., the final form of the Work Programme it is have been
created in order to reduce the time, to reduce the financial costs, to reduce the
disturbance of the surround area and to achieve the best result for the
implementation of the individual working groups and for the whole project.
The resources that are necessary for the implementation of the project are
shown in the attached Milestones Report, where there is reference about the
exact resources for every individual unit for the different types of works, such
as civil, mechanical, electrical works etc.
Below it is described analytically the time for the implementation of every Work
group for all the individual Working Groups.
1.1. INTRODUCTIONThe construction of the project, according to the contractual terms, will be
completed within 15 months from the Notice of Commence including and the
trial operational period of 3 months. According to the Activity Schedule
Programme shall be considered and adhered to in the Work Programme, from
the commencement date that would be needed at least 9 weeks for the
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
5/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 5
submission of the Design and approval of it by the Employer and for the obtain
of the appropriate permits for the construction of the LTP facility.
The construction schedule satisfies the requirements the Tender Documentsand Contract as regards the overall completion date with the completion of
works being achieved within 15 months. The implementation program also
ensures the ability to monitor the achievement of required the staggered
deadlines required to complete the project. The implementation program also
ensures that the plant and personnel are utilized to full capacity also enabling
the realization and execution of parallel works, but also facilitating so as to be
able to work into the programme sufficient project slack for contingency of any
delays introduced by any factor.
The duration of the individual work tasks is considered adequate by the J/ V
ERGASIS TECHNIKI S.A. KARKANIAS S.A., which has great experience in
this field of expertise and consists of experienced crews with the correct
equipment for the implementation of works of this nature.
The individual works and their duration according to the Schedule are:
1.2. NOTICE OF AWARD OF CONTRACT NOTICE TO COMMENCE FINAL DESIGN
The project starts with the issuing of the notice of award of contract by the
Contracting Authority to the Contractor. Within 28 days the Contactor must
submit to the Authority the relative Performance Security. Within a short periodof time will be sent and the Notice to Commence. Within 42 days, after the
Commence Notice, the contractor must submit the Detail Design and in about
next 30 days will take the Approval for the Design. In parallel the contractor
will prepare and submit all the required documents in order to obtain the
required permits for the start of the Works within 30 days after the submission
of all required documents. The time for obtain of the permits is assumable but
it considered a reasonable period for obtaining the permits.
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
6/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 6
Within this time the contractor as it is shown in the GANNT Diagram will be
submit to the Engineer all the other documents that are necessary for the Final
Design, such the Environmental Management Plan, the Health and Safety Plan,
the Quality Assurance Plan etc.
1.3. ACCESS TO THE SITEWithin 7 days from commencement date the contractor will obtain access to
the site. After the provision of the access to the site it will start the geodetic
works of the area for the implementation of the Geotechnical Report of the
Final Design and will start all the procedures for the installation of the Engineer
and Contractor Facilities that will be last about 15 days.
1.4. MOBILIZATION SCHEDULEThe mobilization Schedule, which will lasts 15 days, will be done after the
obtaining of the permits. For the completion of the mobilization of machineries
and equipment will have be done a complete schedule before the beginning of
this activity, in order to ensure that everything will be done on time and
without any problems. The mobilization schedule includes the transportation in
situ all of equipment which is fundamental for the initial start of the works and
especially for the earthworks and civil works, which will start immediately after
the receipt of the construction permits.
All the equipment that will be installed in the plant, such as the pumps, the
blowers, the aerators etc., will be on the site at least ten days before their
mechanical installation, for safety reasons.
In parallel with the mobilization plan will start all the necessary works for the
construction of the facilities of the Contractor and the Engineer Supervisor.
These works will be done within 15 days with intensive rates in order
everything to be done within these time limits.
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
7/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 7
1.5. PRELIMINARY WORKSThese works will last about almost 25 days. These works include first of all the
geodetic works which will last about 7 days, geodetic works will be done in allthe period of the construction works but here are referred the general geodetic
works with the surveying of the general structures. For these works will be
used the following resources:
1 Engineer, 1 Surveyor, 3 Unskilled Workers
After that will be done all the appropriate clearance works for the removal of
the plants, trees etc. which will last about 6 days and referred to any work thatis have to be done before the start of the excavation works. For these works
will be used the following resources:
Plants: 2 Excavators, 2 Loaders, 1 backhoe loader, 3 Trucks, 1 Roller
Human: 4 Plant Operators, 3 Drivers, 3 Unskilled Workers, 1 Engineer
Then will take place the earthworks, which will last about 12 days. There will be
done so much little time, because the area is flat and the majority of thestructures are over the ground, only the equalization tank with the SBR feed
tanks are underground and of course all the foundation of the concrete
structures. For these works will be used the following resources:
Plants: 2 Excavators, 2 Loaders, 1 backhoe loader, 3 Trucks, 1 Roller
Human: 5 Plant Operators, 3 Drivers, 3 Unskilled Workers, 1 Engineer, 1Surveyor
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
8/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 8
1.6. CIVIL WORKSIn the following paragraphs will be described briefly all the Works for the
implementation of the different units which are consisting the LTP Facility. Firstof all will be analyzed the civil works, which are one of the main working
groups for the implementation of this project.
In this chapter will be described all the civil works within the Area of the
Leachate Treatment Plant (LTP) in Livade Landfill. The works will be done for
the completion of the following units:
Equalization Tank - SBR feed Tanks - Odor
Chemical Pre Treatment - Sedimentation Tank
Sludge Thickener
SBR Tanks - Treated Water Tanks - Filter Backwash Treated Water
Control Room - Dosing Station - Control PanelFiltration
The above works will be done in parallel due to the time limits for the
implementation of each unit. The only exception in this is the construction of
the metal units of chemical pre treatment and the sedimentation tank, whichare going to install in the top of the equalization tank, for functional reasons of
the whole facility. The works will be done in parallel and for another reason
because the units have small scale works and the working groups for both of
concrete and metal works will made parallel works in the different structures.
The resources that will be used are referred analytically in the following
paragraphs and they have been calculated in order to complete each on time.
In the calculation of these resources have been added and a safety factor forthe adverse conditions that may occur in the construction phase. When it is
applicable will be done all the appropriate earthworks, such as backfilling works
around the tanks, or for the formation of the ground for the installation of the
above structures. For the implementation of whole civil works will be needed
about 140 days. The activities program of the individual units for the
completion of the civil works is the following:
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
9/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 9
1.6.1. EQUALIZATION TANK - SBR FEED TANKS - ODORThe equalization is the biggest underground structure of the whole facility, it
will be constructed by concrete will be a circular structure with diameter of 10meters. Also will be constructed and a pumping station in the bottom of the
tank for the recirculation in case of emergency and for the supply of the
chemical pretreatment unit. Near to the tank will place a container of 10 which
is going to facilitate the odor unit with a place for the installation of the blower
for the air supply in the equalization tank. For the odor unit a concrete base
plate will be constructed. The total time for the completion of the works is
about 120 days or 4 months.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Excavation works 4d
Leveling works 4d
Compacting works 4d
Formworks 91dReinforcement placement 80d
Concrete placement 82d
Sealing works 7d
Water Tightness Testing 7d
Backfilling works 5d
For these works will be used the following resources:
1 Crane, 1 Excavator, 1 Loader, 1 Roller
2 Plant Operators, 1 Driver
Concrete Works: 3 Skilled Workers, 3 Unskilled Workers, 1 Engineer
Metal Works: 1 Skilled Workers, 1 Unskilled Workers, 1 Engineer
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
10/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 10
1.6.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANKThe works for the construction of the chemical pre treatment and the
sedimentation tank are mostly metal works. These tanks will be installed, alongwith the odor facility on the roof of the equalization tank, next to the
equalization tank for the better functionality of the whole facility and will start
immediately after the completion of the works in the equalization tank. These
works will last about 118 days or about 4 months.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Excavation works 6d
Leveling works 5d
Compacting works 3d
Formworks 18d
Reinforcement placement 5d
Concrete placement 5d
Metal - Steel works 60dSealing works 10d
Water Tightness Testing 14d
Backfilling works 4d
For these works will be used the following resources:
1 Crane, 1 Excavator, 1 Loader, 1 Roller
2 Plant Operators, 1 Driver
Concrete Works: 1 Skilled Worker, 2 Unskilled Workers, 1 Engineer
Metal Works: 3 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.6.3. SLUDGE THICKENERThe works are similar with the above, and includes the construction of a
concrete base plate for the placement of the two sludge thickeners and the
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
11/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 11
construction and installation of the two sludge thickeners in the site. These
works will last about 115days.
The works that will be done according to the attached GANNT Diagram withtheir implementation times are the following:
Excavation works 4d
Leveling works 4d
Compacting works 4d
Formworks 18d
Reinforcement placement 6d
Concrete placement 6d
Metal - Steel works 60d
Sealing works 11d
Water Tightness Testing 10d
Backfilling works 4d
For these works will be used the following resources:
1 Crane, 1 Excavator, 1 Loader, 1 Roller2 Plant Operators, 1 Driver
Concrete Works: 1 Skilled Workers, 1 Unskilled Workers, 1 Engineer
Metal Works: 2 Skilled Workers, 3 Unskilled Workers, 1 Engineer
1.6.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASHTREATED WATER
The construction of the SBR Tanks is the major structure that it will be
constructed in the site. The whole construction will be done from concrete, with
the additional foundation works. Also will take place formworks and
reinforcement works. The whole structure will over the ground, except the
foundations, so it has to be done some finishing works in the outside side of
the tank. Additional will be done and sealing and insulation works. All these
works will be last about 140 days.
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
12/26
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
13/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 13
Leveling works 4d
Compacting works 4d
Formworks 18d
Reinforcement placement 5d
Concrete placement 7d
Metal - Steel works 64d
Sealing works 11d
Backfilling works 4d
For these works will be used the following resources:
1 Crane, 1 Excavator, 1 Loader, 1 Roller
2 Plant Operators, 1 Driver
Concrete Works: 1 Skilled Worker, 2 Unskilled Workers, 1 Engineer
Metal Works: 2 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.7. MECHANICAL WORKSThe mechanical works that will take place, after the completion of the civil
works in the individual units in the site, are concerning different things. The
one is the supply of the equipment, which are going to take place mostly during
the period of the implementation of the civil works, the installation of the
equipment (pumps, aerators, mixers, valves etc.) and the works for the
connection of this equipment together in order to be functional. The whole
mechanical works will last about 130 days. The activities program of the
individual units for the completion of the mechanical works is the following:
1.7.1. EQUALIZATION TANK - SBR FEED TANKS - ODORThe mechanical works for the installation of the equipment and the connection
of it in the equalization tank and the odor facility will last about 94 days. These
works will be done simultaneously with the works in the other units and will
take place after the completion of the civil works.
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
14/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 14
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 59dDelivery on the site 65d
Installation of the equipment 75d
Testing and commissioning 25d
For these works will be used the following resources:
1 Crane
1 Plant Operator, 1 Driver2 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.7.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK - ODORFACILITY
The works for these units that it concerns all the works for the installation of
the equipment in flocculation, coagulation and sludge contact basin tanks and
the connections between them and the installation of the equipment in the
sedimentation tank will last about 75 days.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 50d
Delivery on the site 53d
Installation of the equipment 54dTesting and commissioning 25d
For these works will be used the following resources:
1 Crane
1 Plant Operator, 1 Driver
Mechanical works: 3 Skilled Workers, 3 Unskilled Workers, 1 Engineer
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
15/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 15
1.7.3. SLUDGE THICKENERThe works for the installation in the sludge thickener tanks and the connection
between them will last about 50 days.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 25d
Delivery on the site 27d
Installation of the equipment 30d
Testing and commissioning 25d
For these works will be used the following resources:
1 Crane
1 Plant Operator, 1 Driver
2 Skilled Workers, 2 Unskilled Workers, 1 Engineer
1.7.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASHTREATED WATER
The completion of the mechanical works, which are include the installation of
the surface aerators, the installation of the overflow weirs, the pumps, the
valves, the connection between the different tanks and all the other works is
going to be in 91 days.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 56d
Delivery on the site 64d
Installation of the equipment 71d
Testing and commissioning 25d
For these works will be used the following resources:
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
16/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 16
1 Crane
1 Plant Operator, 1 Driver
3 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.7.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION
The mechanical works that is going to be done in the title units, the installation
of the equipment, the connection between them, because they are going to
take place mainly inside the containers and the nature of the equipment will
last about 120 days from the finishing of the civil works.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 60d
Delivery on the site 70d
Installation of the equipment 89d
Testing and commissioning 30d
For these works will be used the following resources:
1 Crane
1 Plant Operator, 1 Driver
3 Skilled Workers, 6 Unskilled Workers, 1 Engineer
1.8. ELECTRICAL WORKSThe electrical works will be done almost in parallel with the mechanical works,
about 15 days after the start of the mechanical works in each unit. This is
happening because for the installation of the equipment and the functionality of
it, the electrical works which are include the electrical connections of the
installed equipment and the realization of the start up of this equipment but
also all the other necessary works, such us the lighting protection of the units,
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
17/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 17
the grounding, the electrical supply, the interior lighting etc. will be last about
132 days from the beginning of the works. In the following is given the times
for the electrical works for the individual units and also the installation of the
PLC and SCADA, which is the most important work for the proper operation of
the facility.
1.8.1. EQUALIZATION TANK - SBR FEED TANKS - ODORThe electrical works in the equalization tank and the odor facility will last about
89 days and will start 15 days after the start of the mechanical works and will
finish about 10 days after the completion of the mechanical works.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 44d
Delivery on the site 53d
Installation of the equipment 60d
Testing and commissioning 22d
For these works will be used the following resources:
2 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.8.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANKThe electrical works in the chemical pretreatment and the sedimentation tank
will last about 82 days and will start 15 days after the start of the mechanical
works and will finish about 20 days after the completion of the mechanical
works in the unit.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 50d
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
18/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 18
Delivery on the site 56d
Installation of the equipment 60d
Testing and commissioning 21d
For these works will be used the following resources:
2 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.8.3. SLUDGE THICKENERThe electrical works in the sludge thickener tanks will last about 50 days and
will start 15 days after the start of the mechanical works and will finish about
15 days after the completion of the mechanical works.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 25d
Delivery on the site 30d
Installation of the equipment 30d
Testing and commissioning 19d
For these works will be used the following resources:
2 Skilled Workers, 2 Unskilled Workers, 1 Engineer
1.8.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASHTREATED WATER
The electrical works in the SBR tanks will last about 85 days and will start 15
days after the start of the mechanical works and will finish about 10 days after
the completion of the mechanical works.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 45d
Delivery on the site 50d
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
19/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 19
Installation of the equipment 60d
Testing and commissioning 20d
For these works will be used the following resources:
2 Skilled Workers, 4 Unskilled Workers, 1 Engineer
1.8.5. CONTROL ROOM - DOSING STATION - CONTROL PANEL FILTRATION
The electrical works in the control room, the dosing station, the electrical
control panel room and the filtration unit will last about 102 days and will start
15 days after the start of the mechanical works and will finish about 25 days
after the completion of the mechanical works.
The works that will be done according to the attached GANNT Diagram with
their implementation times are the following:
Order and supply of the equipment 70d
Delivery on the site 76dInstallation of the equipment 80d
Testing and commissioning 22d
These works are include among the installation of the electrical connections of
the individual equipment, also the installation of the main electrical panel of the
LTP facility, the installation of the local electrical panel, the installation of the
emergency diesel generator, all these works are very important for the
operation of the facility, because are concerning the electrical connection of the
LTP with the rest of the Livade Sanitary Landfill. For these works will be used
the following resources:
3 Skilled Workers, 6 Unskilled Workers, 1 Engineer
1.8.6. PLCSCADAThe works for the installation of the PLC system and the SCADA are the most
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
20/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 20
important works in the site, because without the appropriate works for the
installation of the electrical connection of the different parts of the facility in
order to operate with automations, the facility will not be able to operate. The
installation of the automations in each different part of the equipment it will be
done after the electrical connection of the individual equipment but in parallel
with all the other electrical works. Also it includes the building of the network.
These works will be last about 132 days.
Order and supply of the equipment 90d
Delivery on the site 99d
Installation of the equipment 100d
Testing and commissioning 30d
For these works will be used the following resources:
3 Skilled Workers, 3 Unskilled Workers, 1 Engineer
1.9. GENERAL WORKSThese works includes all the works for the implantation of the project and will
take place in the last period of the time, before the start of the trial operational
period. These works will last about 144 days from its beginning. The works and
the times that are going to take place are:
1.9.1. PIPE WORKS BETWEEN UNITSThese works will last about 88 days and will occur after the completion of all
the civil works of the units and including all the works for the underground
networks with the installation of HDPE and PVC pipes in order to connect
hydraulically the different units. For these works will be used the following
resources:
Plants: 1 Excavator, 1 Loader, 1 backhoe loader, 2 Trucks, 1 Compactor
Human: 3 Plant Operators, 2 Drivers,2 Skilled Workers, 4 Unskilled
Workers, 1 Engineer
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
21/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 21
1.9.2. PAVEMENTS - WALKWAYS - LANDSCAPINGThese works are going to take place in the two last month of the work
program, before the start of the trial operational period, because for theimplantation of them it must be completed all the underground activities. They
will last 40 days. For these works will be used the following resources:
Plants: 1 Excavator, 1 Loader, 1 backhoe loader, 2 Trucks, 1 Roller
Human: 3 Plant Operators, 2 Drivers,3 Skilled Workers, 6 Unskilled
Workers, 1 Engineer, 1 Surveyor
1.9.3. ELECTRICAL INSTALLATIONSThese works includes the general electrical installation such the connection with
the main network, the installation of the Light in the LTP area etc. They will last
about 99 days. For these works will be used the following resources:
Plants: 1 Excavator, 1 Loader, 1 backhoe loader, 2 Trucks, 1 Compactor
Human: 3 Plant Operators, 2 Drivers,3 Skilled Workers, 3 Unskilled
Workers, 1 Engineer
1.9.4. ROAD WORKSLike the landscaping works will be done in the last period after the
implementation of all other works, and includes the internal roads of the LTP
facility and the connection with the existence roads of the rest of the Landfill
and all the works for these connections like the junctions, the signs etc. Will
last 39 days. For these works will be used the following resources:
Plants: 1 Excavator, 2 Loader, 1 backhoe loader, 3 Trucks, 1 Roller
Human: 4 Plant Operators, 3 Drivers,3 Skilled Workers, 6 Unskilled
Workers, 1 Engineer, 1 Surveyor
1.10.TRIAL OPERATIONAL PERIODThis is the period for the testing of the equipment of the facility, the operation
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
22/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 22
of the facility and the results from this operation, the identification of any
deficits, the cost for the operation of the site, the training of the personnel of
the Employer etc. This period is going to last 90 days or three months.
1.11. DEFECTS NOTIFICATION PERIODThe 24 month Liability Period will start after the completion of the whole works
and the three month trial operation period of the LTP facility.
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
23/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 23
2. COMMENTSThis schedule has taken into account:
a) The requirements of Tender Documents the project
b) The General Conditions set out by the Contract
c) The Special Conditions set out by the Contract (Appendix to Tender for a
Work Contract)
d) The size and volume of the construction works
e) The technical specifications of the project
f) The cost of the works
g) The weather conditions
h)All the adverse conditions which may affect the construction
During the construction of the project, the above schedule may be changed, to
adjust to the real time of works implementation, thus taking in account any
restrictions or commitments that will emerge from the weather.
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
24/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 24
PART : ACTIVITY SCHEDULE WORK PROGRAMME
(GANNT DIAGRAM)
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
25/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 25
PART C: MILESTONESRESOURCES
-
8/12/2019 2. Workplan and Works Completion Programme 20-11-2013
26/26
DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN
PODGORICA, MONTENEGRO
PART D: CASH FLOW