2. workplan and works completion programme 20-11-2013

Upload: vampireknight

Post on 03-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    1/26

    WORKPLAN AND WORKS COMPLETION PROGRAMME

    WORK PROGRAMDesign and Construction of a Leachate

    Treatment Plant at Livade Landfill in

    Podgorica, Montenegro

    Description of the Work Program

    2013

    JOINT VENTURE: ERGASIS TECHNIKI S.A.

    KARKANIAS S.A.21/10/2013

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    2/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 2

    TABLE OF CONTENTS

    1. DOCUMENTATION OF WORK IMPLEMENTATION PROGRAMME ..................4

    1.1. INTRODUCTION..........................................................................................................4

    1.2. NOTICE OF AWARD OF CONTRACTNOTICE TO COMMENCEFINAL

    DESIGN .....................................................................................................................................5

    1.3. ACCESS TO THE SITE.................................................................................................6

    1.4. MOBILIZATION SCHEDULE........................................................................................6

    1.5. PRELIMINARY WORKS ................................................................................................7

    1.6. CIVIL WORKS ...............................................................................................................8

    1.6.1. EQUALIZATION TANK - SBR FEED TANKS - ODOR ................................. 9

    1.6.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK .......................... 10

    1.6.3. SLUDGE THICKENER ........................................................................... 10

    1.6.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASH TREATED

    WATER......................................................................................................... 11

    1.6.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION . 12

    1.7. MECHANICAL WORKS............................................................................................... 13

    1.7.1. EQUALIZATION TANK - SBR FEED TANKS - ODOR ............................... 13

    1.7.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK - ODOR FACILITY 14

    1.7.3. SLUDGE THICKENER ........................................................................... 15

    1.7.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASH TREATED

    WATER......................................................................................................... 15

    1.7.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION . 16

    1.8. ELECTRICAL WORKS................................................................................................ 16

    1.8.1. EQUALIZATION TANK - SBR FEED TANKS - ODOR ............................... 17

    1.8.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK .......................... 17

    1.8.3. SLUDGE THICKENER ........................................................................... 18

    1.8.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASH TREATED

    WATER......................................................................................................... 18

    1.8.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION . 19

    1.8.6. PLCSCADA ...................................................................................... 19

    1.9. GENERAL WORKS...................................................................................................... 20

    1.9.1. PIPE WORKS BETWEEN UNITS ............................................................ 20

    1.9.2. PAVEMENTS - WALKWAYS - LANDSCAPING .......................................... 21

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    3/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 3

    1.9.3. ELECTRICAL INSTALLATIONS .............................................................. 21

    1.9.4. ROAD WORKS .................................................................................... 21

    1.10. TRIAL OPERATIONAL PERIOD............................................................................ 21

    1.11. DEFECTS NOTIFICATION PERIOD..................................................................... 22

    2. COMMENTS ..................................................................................................................... 23

    PART : ACTIVITY SCHEDULEWORK PROGRAMME (GANNT DIAGRAM) ..... 24

    PART C: MILESTONESRESOURCES ............................................................................. 25

    PART D: CASH FLOW ............................................................................................................ 26

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    4/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 4

    1. DOCUMENTATION OF WORK IMPLEMENTATION

    PROGRAMME

    In this chapter is described analytically, the Work Programme for the following

    project: "Design and Construction of Leachate Treatment Plant at

    Livade Landfill in Podgorica, Montenegro. This Work Programme it has

    been done according to the Design and the Bidding Documents of the a.m.

    project. The implementation and completion of the project within the time

    limits, which are described in the documentation of the bid is main scope for

    the construction schedule. Additional the construction schedule has a structure,

    which it has its fundamental elements in realization of the Works that it has to

    be done. After the analysis of all the factors, the weather conditions, the

    compliance with all the environmental and construction laws and regulations of

    the Montenegro, etc., the final form of the Work Programme it is have been

    created in order to reduce the time, to reduce the financial costs, to reduce the

    disturbance of the surround area and to achieve the best result for the

    implementation of the individual working groups and for the whole project.

    The resources that are necessary for the implementation of the project are

    shown in the attached Milestones Report, where there is reference about the

    exact resources for every individual unit for the different types of works, such

    as civil, mechanical, electrical works etc.

    Below it is described analytically the time for the implementation of every Work

    group for all the individual Working Groups.

    1.1. INTRODUCTIONThe construction of the project, according to the contractual terms, will be

    completed within 15 months from the Notice of Commence including and the

    trial operational period of 3 months. According to the Activity Schedule

    Programme shall be considered and adhered to in the Work Programme, from

    the commencement date that would be needed at least 9 weeks for the

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    5/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 5

    submission of the Design and approval of it by the Employer and for the obtain

    of the appropriate permits for the construction of the LTP facility.

    The construction schedule satisfies the requirements the Tender Documentsand Contract as regards the overall completion date with the completion of

    works being achieved within 15 months. The implementation program also

    ensures the ability to monitor the achievement of required the staggered

    deadlines required to complete the project. The implementation program also

    ensures that the plant and personnel are utilized to full capacity also enabling

    the realization and execution of parallel works, but also facilitating so as to be

    able to work into the programme sufficient project slack for contingency of any

    delays introduced by any factor.

    The duration of the individual work tasks is considered adequate by the J/ V

    ERGASIS TECHNIKI S.A. KARKANIAS S.A., which has great experience in

    this field of expertise and consists of experienced crews with the correct

    equipment for the implementation of works of this nature.

    The individual works and their duration according to the Schedule are:

    1.2. NOTICE OF AWARD OF CONTRACT NOTICE TO COMMENCE FINAL DESIGN

    The project starts with the issuing of the notice of award of contract by the

    Contracting Authority to the Contractor. Within 28 days the Contactor must

    submit to the Authority the relative Performance Security. Within a short periodof time will be sent and the Notice to Commence. Within 42 days, after the

    Commence Notice, the contractor must submit the Detail Design and in about

    next 30 days will take the Approval for the Design. In parallel the contractor

    will prepare and submit all the required documents in order to obtain the

    required permits for the start of the Works within 30 days after the submission

    of all required documents. The time for obtain of the permits is assumable but

    it considered a reasonable period for obtaining the permits.

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    6/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 6

    Within this time the contractor as it is shown in the GANNT Diagram will be

    submit to the Engineer all the other documents that are necessary for the Final

    Design, such the Environmental Management Plan, the Health and Safety Plan,

    the Quality Assurance Plan etc.

    1.3. ACCESS TO THE SITEWithin 7 days from commencement date the contractor will obtain access to

    the site. After the provision of the access to the site it will start the geodetic

    works of the area for the implementation of the Geotechnical Report of the

    Final Design and will start all the procedures for the installation of the Engineer

    and Contractor Facilities that will be last about 15 days.

    1.4. MOBILIZATION SCHEDULEThe mobilization Schedule, which will lasts 15 days, will be done after the

    obtaining of the permits. For the completion of the mobilization of machineries

    and equipment will have be done a complete schedule before the beginning of

    this activity, in order to ensure that everything will be done on time and

    without any problems. The mobilization schedule includes the transportation in

    situ all of equipment which is fundamental for the initial start of the works and

    especially for the earthworks and civil works, which will start immediately after

    the receipt of the construction permits.

    All the equipment that will be installed in the plant, such as the pumps, the

    blowers, the aerators etc., will be on the site at least ten days before their

    mechanical installation, for safety reasons.

    In parallel with the mobilization plan will start all the necessary works for the

    construction of the facilities of the Contractor and the Engineer Supervisor.

    These works will be done within 15 days with intensive rates in order

    everything to be done within these time limits.

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    7/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 7

    1.5. PRELIMINARY WORKSThese works will last about almost 25 days. These works include first of all the

    geodetic works which will last about 7 days, geodetic works will be done in allthe period of the construction works but here are referred the general geodetic

    works with the surveying of the general structures. For these works will be

    used the following resources:

    1 Engineer, 1 Surveyor, 3 Unskilled Workers

    After that will be done all the appropriate clearance works for the removal of

    the plants, trees etc. which will last about 6 days and referred to any work thatis have to be done before the start of the excavation works. For these works

    will be used the following resources:

    Plants: 2 Excavators, 2 Loaders, 1 backhoe loader, 3 Trucks, 1 Roller

    Human: 4 Plant Operators, 3 Drivers, 3 Unskilled Workers, 1 Engineer

    Then will take place the earthworks, which will last about 12 days. There will be

    done so much little time, because the area is flat and the majority of thestructures are over the ground, only the equalization tank with the SBR feed

    tanks are underground and of course all the foundation of the concrete

    structures. For these works will be used the following resources:

    Plants: 2 Excavators, 2 Loaders, 1 backhoe loader, 3 Trucks, 1 Roller

    Human: 5 Plant Operators, 3 Drivers, 3 Unskilled Workers, 1 Engineer, 1Surveyor

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    8/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 8

    1.6. CIVIL WORKSIn the following paragraphs will be described briefly all the Works for the

    implementation of the different units which are consisting the LTP Facility. Firstof all will be analyzed the civil works, which are one of the main working

    groups for the implementation of this project.

    In this chapter will be described all the civil works within the Area of the

    Leachate Treatment Plant (LTP) in Livade Landfill. The works will be done for

    the completion of the following units:

    Equalization Tank - SBR feed Tanks - Odor

    Chemical Pre Treatment - Sedimentation Tank

    Sludge Thickener

    SBR Tanks - Treated Water Tanks - Filter Backwash Treated Water

    Control Room - Dosing Station - Control PanelFiltration

    The above works will be done in parallel due to the time limits for the

    implementation of each unit. The only exception in this is the construction of

    the metal units of chemical pre treatment and the sedimentation tank, whichare going to install in the top of the equalization tank, for functional reasons of

    the whole facility. The works will be done in parallel and for another reason

    because the units have small scale works and the working groups for both of

    concrete and metal works will made parallel works in the different structures.

    The resources that will be used are referred analytically in the following

    paragraphs and they have been calculated in order to complete each on time.

    In the calculation of these resources have been added and a safety factor forthe adverse conditions that may occur in the construction phase. When it is

    applicable will be done all the appropriate earthworks, such as backfilling works

    around the tanks, or for the formation of the ground for the installation of the

    above structures. For the implementation of whole civil works will be needed

    about 140 days. The activities program of the individual units for the

    completion of the civil works is the following:

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    9/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 9

    1.6.1. EQUALIZATION TANK - SBR FEED TANKS - ODORThe equalization is the biggest underground structure of the whole facility, it

    will be constructed by concrete will be a circular structure with diameter of 10meters. Also will be constructed and a pumping station in the bottom of the

    tank for the recirculation in case of emergency and for the supply of the

    chemical pretreatment unit. Near to the tank will place a container of 10 which

    is going to facilitate the odor unit with a place for the installation of the blower

    for the air supply in the equalization tank. For the odor unit a concrete base

    plate will be constructed. The total time for the completion of the works is

    about 120 days or 4 months.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Excavation works 4d

    Leveling works 4d

    Compacting works 4d

    Formworks 91dReinforcement placement 80d

    Concrete placement 82d

    Sealing works 7d

    Water Tightness Testing 7d

    Backfilling works 5d

    For these works will be used the following resources:

    1 Crane, 1 Excavator, 1 Loader, 1 Roller

    2 Plant Operators, 1 Driver

    Concrete Works: 3 Skilled Workers, 3 Unskilled Workers, 1 Engineer

    Metal Works: 1 Skilled Workers, 1 Unskilled Workers, 1 Engineer

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    10/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 10

    1.6.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANKThe works for the construction of the chemical pre treatment and the

    sedimentation tank are mostly metal works. These tanks will be installed, alongwith the odor facility on the roof of the equalization tank, next to the

    equalization tank for the better functionality of the whole facility and will start

    immediately after the completion of the works in the equalization tank. These

    works will last about 118 days or about 4 months.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Excavation works 6d

    Leveling works 5d

    Compacting works 3d

    Formworks 18d

    Reinforcement placement 5d

    Concrete placement 5d

    Metal - Steel works 60dSealing works 10d

    Water Tightness Testing 14d

    Backfilling works 4d

    For these works will be used the following resources:

    1 Crane, 1 Excavator, 1 Loader, 1 Roller

    2 Plant Operators, 1 Driver

    Concrete Works: 1 Skilled Worker, 2 Unskilled Workers, 1 Engineer

    Metal Works: 3 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.6.3. SLUDGE THICKENERThe works are similar with the above, and includes the construction of a

    concrete base plate for the placement of the two sludge thickeners and the

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    11/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 11

    construction and installation of the two sludge thickeners in the site. These

    works will last about 115days.

    The works that will be done according to the attached GANNT Diagram withtheir implementation times are the following:

    Excavation works 4d

    Leveling works 4d

    Compacting works 4d

    Formworks 18d

    Reinforcement placement 6d

    Concrete placement 6d

    Metal - Steel works 60d

    Sealing works 11d

    Water Tightness Testing 10d

    Backfilling works 4d

    For these works will be used the following resources:

    1 Crane, 1 Excavator, 1 Loader, 1 Roller2 Plant Operators, 1 Driver

    Concrete Works: 1 Skilled Workers, 1 Unskilled Workers, 1 Engineer

    Metal Works: 2 Skilled Workers, 3 Unskilled Workers, 1 Engineer

    1.6.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASHTREATED WATER

    The construction of the SBR Tanks is the major structure that it will be

    constructed in the site. The whole construction will be done from concrete, with

    the additional foundation works. Also will take place formworks and

    reinforcement works. The whole structure will over the ground, except the

    foundations, so it has to be done some finishing works in the outside side of

    the tank. Additional will be done and sealing and insulation works. All these

    works will be last about 140 days.

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    12/26

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    13/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 13

    Leveling works 4d

    Compacting works 4d

    Formworks 18d

    Reinforcement placement 5d

    Concrete placement 7d

    Metal - Steel works 64d

    Sealing works 11d

    Backfilling works 4d

    For these works will be used the following resources:

    1 Crane, 1 Excavator, 1 Loader, 1 Roller

    2 Plant Operators, 1 Driver

    Concrete Works: 1 Skilled Worker, 2 Unskilled Workers, 1 Engineer

    Metal Works: 2 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.7. MECHANICAL WORKSThe mechanical works that will take place, after the completion of the civil

    works in the individual units in the site, are concerning different things. The

    one is the supply of the equipment, which are going to take place mostly during

    the period of the implementation of the civil works, the installation of the

    equipment (pumps, aerators, mixers, valves etc.) and the works for the

    connection of this equipment together in order to be functional. The whole

    mechanical works will last about 130 days. The activities program of the

    individual units for the completion of the mechanical works is the following:

    1.7.1. EQUALIZATION TANK - SBR FEED TANKS - ODORThe mechanical works for the installation of the equipment and the connection

    of it in the equalization tank and the odor facility will last about 94 days. These

    works will be done simultaneously with the works in the other units and will

    take place after the completion of the civil works.

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    14/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 14

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 59dDelivery on the site 65d

    Installation of the equipment 75d

    Testing and commissioning 25d

    For these works will be used the following resources:

    1 Crane

    1 Plant Operator, 1 Driver2 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.7.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANK - ODORFACILITY

    The works for these units that it concerns all the works for the installation of

    the equipment in flocculation, coagulation and sludge contact basin tanks and

    the connections between them and the installation of the equipment in the

    sedimentation tank will last about 75 days.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 50d

    Delivery on the site 53d

    Installation of the equipment 54dTesting and commissioning 25d

    For these works will be used the following resources:

    1 Crane

    1 Plant Operator, 1 Driver

    Mechanical works: 3 Skilled Workers, 3 Unskilled Workers, 1 Engineer

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    15/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 15

    1.7.3. SLUDGE THICKENERThe works for the installation in the sludge thickener tanks and the connection

    between them will last about 50 days.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 25d

    Delivery on the site 27d

    Installation of the equipment 30d

    Testing and commissioning 25d

    For these works will be used the following resources:

    1 Crane

    1 Plant Operator, 1 Driver

    2 Skilled Workers, 2 Unskilled Workers, 1 Engineer

    1.7.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASHTREATED WATER

    The completion of the mechanical works, which are include the installation of

    the surface aerators, the installation of the overflow weirs, the pumps, the

    valves, the connection between the different tanks and all the other works is

    going to be in 91 days.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 56d

    Delivery on the site 64d

    Installation of the equipment 71d

    Testing and commissioning 25d

    For these works will be used the following resources:

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    16/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 16

    1 Crane

    1 Plant Operator, 1 Driver

    3 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.7.5. CONTROL ROOM - DOSING STATION - CONTROL PANELFILTRATION

    The mechanical works that is going to be done in the title units, the installation

    of the equipment, the connection between them, because they are going to

    take place mainly inside the containers and the nature of the equipment will

    last about 120 days from the finishing of the civil works.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 60d

    Delivery on the site 70d

    Installation of the equipment 89d

    Testing and commissioning 30d

    For these works will be used the following resources:

    1 Crane

    1 Plant Operator, 1 Driver

    3 Skilled Workers, 6 Unskilled Workers, 1 Engineer

    1.8. ELECTRICAL WORKSThe electrical works will be done almost in parallel with the mechanical works,

    about 15 days after the start of the mechanical works in each unit. This is

    happening because for the installation of the equipment and the functionality of

    it, the electrical works which are include the electrical connections of the

    installed equipment and the realization of the start up of this equipment but

    also all the other necessary works, such us the lighting protection of the units,

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    17/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 17

    the grounding, the electrical supply, the interior lighting etc. will be last about

    132 days from the beginning of the works. In the following is given the times

    for the electrical works for the individual units and also the installation of the

    PLC and SCADA, which is the most important work for the proper operation of

    the facility.

    1.8.1. EQUALIZATION TANK - SBR FEED TANKS - ODORThe electrical works in the equalization tank and the odor facility will last about

    89 days and will start 15 days after the start of the mechanical works and will

    finish about 10 days after the completion of the mechanical works.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 44d

    Delivery on the site 53d

    Installation of the equipment 60d

    Testing and commissioning 22d

    For these works will be used the following resources:

    2 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.8.2. CHEMICAL PRE TREATMENT - SEDIMENTATION TANKThe electrical works in the chemical pretreatment and the sedimentation tank

    will last about 82 days and will start 15 days after the start of the mechanical

    works and will finish about 20 days after the completion of the mechanical

    works in the unit.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 50d

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    18/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 18

    Delivery on the site 56d

    Installation of the equipment 60d

    Testing and commissioning 21d

    For these works will be used the following resources:

    2 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.8.3. SLUDGE THICKENERThe electrical works in the sludge thickener tanks will last about 50 days and

    will start 15 days after the start of the mechanical works and will finish about

    15 days after the completion of the mechanical works.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 25d

    Delivery on the site 30d

    Installation of the equipment 30d

    Testing and commissioning 19d

    For these works will be used the following resources:

    2 Skilled Workers, 2 Unskilled Workers, 1 Engineer

    1.8.4. SBR TANKS - TREATED WATER TANKS - FILTER BACKWASHTREATED WATER

    The electrical works in the SBR tanks will last about 85 days and will start 15

    days after the start of the mechanical works and will finish about 10 days after

    the completion of the mechanical works.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 45d

    Delivery on the site 50d

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    19/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 19

    Installation of the equipment 60d

    Testing and commissioning 20d

    For these works will be used the following resources:

    2 Skilled Workers, 4 Unskilled Workers, 1 Engineer

    1.8.5. CONTROL ROOM - DOSING STATION - CONTROL PANEL FILTRATION

    The electrical works in the control room, the dosing station, the electrical

    control panel room and the filtration unit will last about 102 days and will start

    15 days after the start of the mechanical works and will finish about 25 days

    after the completion of the mechanical works.

    The works that will be done according to the attached GANNT Diagram with

    their implementation times are the following:

    Order and supply of the equipment 70d

    Delivery on the site 76dInstallation of the equipment 80d

    Testing and commissioning 22d

    These works are include among the installation of the electrical connections of

    the individual equipment, also the installation of the main electrical panel of the

    LTP facility, the installation of the local electrical panel, the installation of the

    emergency diesel generator, all these works are very important for the

    operation of the facility, because are concerning the electrical connection of the

    LTP with the rest of the Livade Sanitary Landfill. For these works will be used

    the following resources:

    3 Skilled Workers, 6 Unskilled Workers, 1 Engineer

    1.8.6. PLCSCADAThe works for the installation of the PLC system and the SCADA are the most

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    20/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 20

    important works in the site, because without the appropriate works for the

    installation of the electrical connection of the different parts of the facility in

    order to operate with automations, the facility will not be able to operate. The

    installation of the automations in each different part of the equipment it will be

    done after the electrical connection of the individual equipment but in parallel

    with all the other electrical works. Also it includes the building of the network.

    These works will be last about 132 days.

    Order and supply of the equipment 90d

    Delivery on the site 99d

    Installation of the equipment 100d

    Testing and commissioning 30d

    For these works will be used the following resources:

    3 Skilled Workers, 3 Unskilled Workers, 1 Engineer

    1.9. GENERAL WORKSThese works includes all the works for the implantation of the project and will

    take place in the last period of the time, before the start of the trial operational

    period. These works will last about 144 days from its beginning. The works and

    the times that are going to take place are:

    1.9.1. PIPE WORKS BETWEEN UNITSThese works will last about 88 days and will occur after the completion of all

    the civil works of the units and including all the works for the underground

    networks with the installation of HDPE and PVC pipes in order to connect

    hydraulically the different units. For these works will be used the following

    resources:

    Plants: 1 Excavator, 1 Loader, 1 backhoe loader, 2 Trucks, 1 Compactor

    Human: 3 Plant Operators, 2 Drivers,2 Skilled Workers, 4 Unskilled

    Workers, 1 Engineer

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    21/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 21

    1.9.2. PAVEMENTS - WALKWAYS - LANDSCAPINGThese works are going to take place in the two last month of the work

    program, before the start of the trial operational period, because for theimplantation of them it must be completed all the underground activities. They

    will last 40 days. For these works will be used the following resources:

    Plants: 1 Excavator, 1 Loader, 1 backhoe loader, 2 Trucks, 1 Roller

    Human: 3 Plant Operators, 2 Drivers,3 Skilled Workers, 6 Unskilled

    Workers, 1 Engineer, 1 Surveyor

    1.9.3. ELECTRICAL INSTALLATIONSThese works includes the general electrical installation such the connection with

    the main network, the installation of the Light in the LTP area etc. They will last

    about 99 days. For these works will be used the following resources:

    Plants: 1 Excavator, 1 Loader, 1 backhoe loader, 2 Trucks, 1 Compactor

    Human: 3 Plant Operators, 2 Drivers,3 Skilled Workers, 3 Unskilled

    Workers, 1 Engineer

    1.9.4. ROAD WORKSLike the landscaping works will be done in the last period after the

    implementation of all other works, and includes the internal roads of the LTP

    facility and the connection with the existence roads of the rest of the Landfill

    and all the works for these connections like the junctions, the signs etc. Will

    last 39 days. For these works will be used the following resources:

    Plants: 1 Excavator, 2 Loader, 1 backhoe loader, 3 Trucks, 1 Roller

    Human: 4 Plant Operators, 3 Drivers,3 Skilled Workers, 6 Unskilled

    Workers, 1 Engineer, 1 Surveyor

    1.10.TRIAL OPERATIONAL PERIODThis is the period for the testing of the equipment of the facility, the operation

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    22/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 22

    of the facility and the results from this operation, the identification of any

    deficits, the cost for the operation of the site, the training of the personnel of

    the Employer etc. This period is going to last 90 days or three months.

    1.11. DEFECTS NOTIFICATION PERIODThe 24 month Liability Period will start after the completion of the whole works

    and the three month trial operation period of the LTP facility.

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    23/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 23

    2. COMMENTSThis schedule has taken into account:

    a) The requirements of Tender Documents the project

    b) The General Conditions set out by the Contract

    c) The Special Conditions set out by the Contract (Appendix to Tender for a

    Work Contract)

    d) The size and volume of the construction works

    e) The technical specifications of the project

    f) The cost of the works

    g) The weather conditions

    h)All the adverse conditions which may affect the construction

    During the construction of the project, the above schedule may be changed, to

    adjust to the real time of works implementation, thus taking in account any

    restrictions or commitments that will emerge from the weather.

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    24/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 24

    PART : ACTIVITY SCHEDULE WORK PROGRAMME

    (GANNT DIAGRAM)

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    25/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    JOINT VENTURE: ERGASIS TECHNIKI S.A.KARKANIAS S.A. | WORKS PROGRAM 25

    PART C: MILESTONESRESOURCES

  • 8/12/2019 2. Workplan and Works Completion Programme 20-11-2013

    26/26

    DESIGN AND CONSTRUCTION OF A LEACHATE TREATMENT PLANT AT LIVADE LANDFILL IN

    PODGORICA, MONTENEGRO

    PART D: CASH FLOW