2 - robuste risikoanalyser - linda fløttum og tore andre svidal

Upload: nurhayati-muhamad-nor

Post on 16-Oct-2015

9 views

Category:

Documents


0 download

DESCRIPTION

oil and gas

TRANSCRIPT

  • Confidential 2013 Aker Solutions Preferred partner

    Preferred partner

    Robust Risk Analysis from a engineering

    point of view Stavanger 24th of October

    Linda Flttum & Tore Svidal

  • Confidential 2013 Aker Solutions Preferred partner

    What is overall important to a project?

    Critical decisions at the right time

    Maturity requirements per milestone

    Predictability in: Design development

    Deliverables

    Quality

    Cost

    Develop a project that meets National Regulations and Clients

    Requirements and which provides a good as possible working

    environment, is inherently safe with as low as possible risk for people

    and the environment

    25 October, 2013 Slide 2

  • Confidential 2013 Aker Solutions Preferred partner

    What is overall important to expect from a Risk Analyst

    Experienced and well qualified in general and with expertise also to: Qualitatively rank different design proposals in the feasibility, concept

    and FEED phases

    Propose alternatively design solutions

    Provide the project with DAL values at the end of the FEED phase

    which is likely to be valid when Final As Built deliverables are completed

    Flexibility to rapidly perform additional analysis and assessments as

    e.g. part of ALRP evaluations

    Willing to locate key risk analyst personnel in the same office as

    engineering is performed

    Have the right tools and methods

    Can provides the project with correct and sufficiently robust results

    25 October, 2013 Slide 3

  • Confidential 2013 Aker Solutions Preferred partner Slide 4

  • Confidential 2013 Aker Solutions Preferred partner

    FEED

    Fabrication

    Assy &

    Hook-up

    AFC

    Detail Engineering

    Procurement

    Align contract and Project Execution Model milestones

    Ready for

    Tow Start

    FEED

    Class II cost

    estimate Hull to

    Hook-up

    Yard/Mating

    PO Long Lead

    CA EP(C)

    Contract Milestones

    Milestones

    Modules to

    Hook-up

    Yard

    Hook-up &

    Completion

    1A 1B 1C 1D

    2A 2B 2C

    3A 3B 3C

    4A 4B 4C

    5A 5B 5C 5D

    Feasibility &

    Concept

    System

    Definition

    Detailing &

    Fabrication

    Assembly/

    Erection

    System

    Completion

    Slide 5

    2 6 10 14 14 5 8

    Freeze DALs As built IFC drawings

    Duration [months]

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    A new oil or gas discovery

    Slide 6

    Main project goal:

    The best alternative solutions for how to bring up the oil and

    gas from the reservoir on a safe and reliable manner to be

    developed.

    Different solutions will be evaluated.

    Concept to be developed to a ~ +/- 30% cost estimate.

    Robust Analysis:

    Qualitatively assist engineering to select the best alternative

    solution.

    Quantified risk analysis may be introduced for special

    challenging concept

    Rank different concepts.

    Propose alternative and better solutions.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 7

    Main project goal:

    Project matures the selected concept to ensure the correct

    size of the production unit.

    Concept to be developed to a ~ +/- 20% cost estimate.

    Provide the project with DAL values at the end of the FEED

    phase which is likely to be valid when Final As Built deliverables are completed

    Event Exposed

    Area

    Items to be Protected Design Load

    Heat Load

    (kW/m2)

    Duration

    (Minutes)

    Fire at

    Process area

    Main deck

    Process area

    from

    EL50.500

    and above

    - Main deck

    - Main loadbearing structure

    - Critical equipment/piping

    250/150

    250/150

    250/150

    20 + 40

    20 + 40

    20 + 40

    Robust Analysis:

    Quantified risk analysis is introduced

    Rank different design alternatives for the selected concept

    and assist engineering to select the best alternative

    solution

    Establish sectionalisation principles topside and need for

    sectionalisation on production import and export lines (e.g.

    SSIV)

    Establish Safety Strategy and Performance Standards

    Establish DAL for input to engineering design and

    procurement of long lead items

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 8

    Main project goal 2A:

    Project confirms the best concept

    All systems needed on the production units are defined

    Procurement of most important equipment ( priority1)

    where engineering information is needed, or with long

    delivery time

    Robust Analysis:

    Quantified risk analysis to be started early in the detail

    engineering phase.

    Confirm/verify and detail out DALs Assist in ALARP evaluations

    Rank different design alternatives for the selected concept

    and assist engineering to select the best alternative

    solution

    Confirm sectionalisation segments topside and need for

    sectionalisation on production import and export lines (e.g.

    SSIV)

    Start to perform and establish segment evaluation vs.

    volumes, blowdown duration, flare height and radiation

    levels.

    Continue to provide DALs for input to engineering design and procurement

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 9

    Main project goal 2B:

    The design of main steel structures are completed.

    All systems needed on the production units are defined.

    Procurement of priority 2 equipment where engineering

    information is needed.

    24VG001

    Vtgass

    Vskeutskiller

    HC: 12.3 tonn

    20VA001

    1.trinns separator

    HC: 94 tonn

    24PA001A/B

    HC:< 1 tonn

    24ESV1025

    24ESV1031

    24ESV1036

    24ESV1022

    Robust Analysis:

    Quantified risk analysis and emergency preparedness

    analysis continues.

    Confirm/verify and detail out DALs. Continue to provide DALs for input to engineering design

    and procurement .

    CFD evaluation related to fire and response analysis

    versus structures and hydrocarbon segments

    Continue to perform and establish segment evaluation vs.

    volumes, blowdown duration.

    Assist in ALARP evaluations.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 10

    Main project goal 2C:

    The P&IDs and global design are completed

    All supplier information with interfaces are frozen

    Procurement of priority 3 equipment

    Robust Analysis:

    Quantified risk analysis and emergency preparedness

    analysis continues.

    Confirm/verify and detail out DALs. Continue to provide DALs for input to engineering design

    and procurement .

    CFD evaluation related to fire analysis finalished.

    Response analysis versus structures and hydrocarbon

    segments finalised versus main structural structures

    Finalise hydrocarbon segment evaluation vs. volumes,

    blowdown duration for large bore lines.

    Assist in ALARP evaluations.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 11

    Main project goal 3A:

    Design of outfitting arrangements and small items

    Detail design completed

    Issue of all drawings for fabrication

    Robust Analysis:

    Quantified risk analysis and emergency

    preparedness analysis finalised for detail

    engineering phase.

    Confirm/verify and detail out DALs. Response analysis versus structures and

    hydrocarbon segments finalised versus secondary

    and outfitting structures

    Finalised hydrocarbon segment evaluation vs.

    volumes, blowdown duration for all lines.

    Assist in ALARP evaluations.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 12

    Main project goal 3B:

    The fabrication yard performs shop engineering

    and preparations for fabrication

    Engineering assists the fabrication yard

    Robust Analysis:

    Update analysis according to introduced changes

    No change.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 13

    Main project goal 3C & 3D:

    Pre-fabrication of steel sections

    Assembly of steel sections to modules

    Equipment and system installation

    Engineering assists the fabrication yard

    Robust Analysis:

    Update analysis according to introduced changes

    No change.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 14

    Main project goal 4A 4C: Assembly and hook-up of modules

    Hook-up installation of equipment and systems

    Engineering assists the fabrication yard

    Robust Analysis:

    Update analysis according to introduced changes

    No change.

  • Confidential 2013 Aker Solutions Preferred partner

    Project Execution

    Slide 15

    Main project goal 5A 5C: Onshore/at-shore Commissioning of equipment and

    systems

    Preparation for tow-out

    Tow-out

    Offshore installation and commissioning

    As-built documentation and contract close-out

    Robust Analysis:

    As Built

  • Confidential 2013 Aker Solutions Preferred partner

    To much optimisation can be introduced: Simulate a few fires and use the result in structural response analysis

    Structural response simulations concludes that PFP is not required

    But

    If explosion occurs during start-up of fire is the structural response

    analysis fully valid? Structure may have deflected rather much Is this robust or ALARP?

    Robustness

    25 October, 2013 Slide 16

    Loss of

    containment

    Explosion

    Fire

    Ignition

  • Confidential 2013 Aker Solutions Preferred partner

    PFP epoxy application cost

    Correct timing: Application cost for 1 m2 epoxy PFP with a thickness

    of 8 mm is in the order of NOK 4.500,- m2

    Incorrect timing: In the order of 2 to 3 times cost of as indiciated for

    correct timed PFP application

    Remove epoxy PFP: Takes from 30 minutes to cut off cutting machine to 3 hours with water

    jetting. Approximately 3 person required.

    25 October, 2013 Slide 17

  • Confidential 2013 Aker Solutions Preferred partner

    Project cost and resource timing

    Slide 18 Slide 18

    Ability to

    influence cost Project cost

    Time

    E P C I C Operation Front end

    studies FEED

  • Confidential 2013 Aker Solutions Preferred partner 25 October 2013 Slide 19

    Why is it challenging to make robust risk analysis?

    Some project examples..

  • Confidential 2013 Aker Solutions Preferred partner

    Example: Leak frequency

    The leak frequency is the one of the parameters in the risk analysis

    with largest influence on the risk picture (and hences DALs!)

    The leak frequency is estimated by counting the number of leak

    sources from P&IDs

    Further the DNV leak frequency model (industry practice) is used to estimate the leak frequency based on statistical failure rates for

    different leak sources (valves, flanges etc.)

    25 October 2013 Slide 20

    Challenge 1: How to ensure that the number of leak sources

    is estimated similarly independent of person/Company

    performing the calculations?

    Challenge 2: How to estimate the increase in number of leak

    sources from early stage to as built?

  • Confidential 2013 Aker Solutions Preferred partner

    Counting of leak sources

    Defined rules for performing the counting by each sub-

    contractor

    Time demanding calculations &

    manual work

    Relatively inexperienced

    personnel often responsible for

    the calculations

    Variation in results observed for

    the same basis

    Need for a industry practice?

    Possible to utilize engineering

    systems/PDMS better?

    25 October 2013 Slide 21

    Example of equipment count

  • Confidential 2013 Aker Solutions Preferred partner 25 October 2013 Slide 22

    Increase in the number of leak sources throughout

    the project

    P&ID gas export meeting, FEED phase

    P&ID gas export meeting, detail engineering

    Some challenges: Only large dimension piping

    modeled in early stage

    Many details/leak sources

    missing (e.g. instruments,

    valves, flanges)

    Vendor P&IDs not available

    before late detail eng.

    No common industry method

    to estimate increase in leak

    sources & limited with

    experience data

    Normally the risk analysis

    contractor makes the

    assumption

    Critical assumption for the

    project

  • Confidential 2013 Aker Solutions Preferred partner

    Relevance of leak frequency model

    Estimation of leak frequency requires a lot of resources and it is

    challenging to get it right

    And even if we get it right, is this the best estimate of the leak picture for the installation?

    Is the leak frequency proportional with the number of leak sources?

    Or is other factors also important for the leak frequency, e.g. Safety & operation philosophy and culture

    Variation in operation modes

    Quality of design & fabrication

    One advantage with the current leak frequency model is the focus on

    reducing the number of leak sources

    On long term basis: could a more simple and robust model be used? Predicable for the project

    Robust safety design

    25 October 2013 Slide 23

  • Confidential 2013 Aker Solutions Preferred partner

    Example: Congestion level in an explosion analysis

    The congestion level inside the process areas is very important for

    the resulting explosion pressure

    The congestion level in the 3D model will increase until as built

    Explosion analysis performed at an earlier stage in the project must

    assume an expected increase in congestion level until as built

    25 October 2013 Slide 24

    Challenge: the design explosion

    loads will be frozen at an early

    stage in the project

    This assumption is, hence, very

    critical for the project

  • Confidential 2013 Aker Solutions Preferred partner

    Increase in congestion level Project example

    A significant increase in congestion level from detail engineering to

    as built was reported

    The assumption in detail engineering appears not to have been be

    conservative enough

    The change resulted in a significant increase in explosion pressure

    Project was saved by a significant margin from dimensioning

    accidental load to design accidental load

    25 October 2013 Slide 25

  • Confidential 2013 Aker Solutions Preferred partner

    Example: Explosion analysis in concept/FEED phase

    The 3D model will be immature at this stage

    Important to use a representative and conservative congestion level

    It is desired to a have a significant margin to the acceptance criterion

    at this stage

    25 October 2013 Slide 26

    3D modell in early phase (concept) 3D modell as built

  • Confidential 2013 Aker Solutions Preferred partner

    How to add extra geometry to reflect as built?

    25 October 2013 Slide 27

    Different methods

    Normally, the risk analysis contractors have their database with as

    built platforms, and corresponding congestion levels

    Is the reported/read equipment density from FLACS cofile utility a

    real equipment density? Known limitations in FLACS utility (used for density reporting) should be

    accounted for

    E.g. cylinders inside enclosed boxes may lead to overestimation

    Example:

    compressor

    with 104 m

    piping inside

  • Confidential 2013 Aker Solutions Preferred partner

    Results from a concept/FEED explosion analysis

    Explosion load on firewall (4 x 4 m panel)

    25 October 2013 Slide 28

  • Confidential 2013 Aker Solutions Preferred partner

    Explosion analysis in concept/FEED phase

    Important with a good method to establish representative equipment

    density in the early phases of the project

    Overestimation of equipment density may lead to too high explosion

    pressures, and possible non-feasible concepts In particular this applies for large process areas

    Underestimation of equipment density may lead to significant

    challenges later in the project

    25 October 2013 Slide 29

  • Confidential 2013 Aker Solutions Preferred partner

    Reflections - Industry

    The fire and explosion analyses tend to be more and more complex Are we on the right track?

    Does this gives us increased safety level?

    Are we optimizing too much?

    What happens with the traceability of the analysis?

    Need for more industry specific standards? Calculation/estimation of number of leak sources

    Standardization of generic assumptions, e.g. equipment density Method for performing fire and explosion analysis

    Are enough recourses used on analysis in the early stages of the

    project?

    Changes in method/best practice over time: Challenge for a project when increase in risk level occur without any

    design change

    Openness about of causes of increase important

    25 October 2013 Slide 30

  • Confidential 2013 Aker Solutions Preferred partner

    Reflections Engineering

    Set more stringent requirements to the risk analysis sub-contractor

    Be more involved in the risk analysis execution Take more responsibility for the assumptions

    Get own experience data (e.g. equipment density and increase in

    number of leak sources over time)

    Increase risk analysis competency in-house

    Possibility of doing parts of risk analysis by in-house team.

    25 October 2013 Slide 31

  • Confidential 2013 Aker Solutions Preferred partner

    Reflections - Risk analysis sub-contractors

    Make robust assumptions in close cooperation with engineering / oil

    company

    Be willing to work integrated with the project

    Ensure experienced personnel and secure continuity

    Increase competency about project execution

    Be open about uncertainty in the analysis

    Communicate results clearly

    Make transparent and traceable analysis

    25 October 2013 Slide 32

  • Confidential 2013 Aker Solutions Preferred partner

    Copyright and disclaimer

    Copyright Copyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and

    third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor

    used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall

    be altered or removed from any reproduction.

    Disclaimer This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and

    uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations,

    estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major

    markets for Aker Solutions ASA and Aker Solutions ASAs (including subsidiaries and affiliates) lines of business. These expectations, estimates and projections are generally identifiable by statements containing words such as expects, believes, estimates or similar expressions. Important factors that could cause actual results to differ materially from those expectations include, among others,

    economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions businesses, oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency

    exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes

    that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will

    be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty,

    expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its

    directors, officers or employees will have any liability to you or any other persons resulting from your use.

    Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the

    common brand or trade mark for most of these entities. In this presentation we may sometimes use Aker Solutions, we or us when we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions

    company.

    Slide 33 25 October, 2013