2 notes from the risk management workshop

Upload: mohammed-khatib

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 2 Notes From the Risk Management Workshop

    1/31

    Risk Management Workshop, Blackwater, 21 September 2010 1

    The Challenge..

  • 7/28/2019 2 Notes From the Risk Management Workshop

    2/31

    Risk Management Workshop, Blackwater, 21 September 2010 2

    Applicable Reference Material

  • 7/28/2019 2 Notes From the Risk Management Workshop

    3/31

    Risk Management Workshop, Blackwater, 21 September 2010 3

    Applicable Reference Material

  • 7/28/2019 2 Notes From the Risk Management Workshop

    4/31

    Risk Management Workshop, Blackwater, 21 September 2010 4

    Applicable Reference Material

  • 7/28/2019 2 Notes From the Risk Management Workshop

    5/31

    Risk Management Workshop, Blackwater, 21 September 2010 5

    Workshop pictures Page 1

    Jim Knowles and the Panel (Andrew Morrell, Gavin Taylor, Tim Whyte,

    John Sleigh, Jane Moss, Richard Mills, Adam Garde).

  • 7/28/2019 2 Notes From the Risk Management Workshop

    6/31

    Risk Management Workshop, Blackwater, 21 September 2010 6

    Workshop pictures Page 2

    Andrew Morrell

    Jane Moss

  • 7/28/2019 2 Notes From the Risk Management Workshop

    7/31

    Risk Management Workshop, Blackwater, 21 September 2010 7

    Workshop pictures Page 3

    Adam Garde

    Grant Cook

  • 7/28/2019 2 Notes From the Risk Management Workshop

    8/31

    Risk Management Workshop, Blackwater, 21 September 2010 8

    Key Points (John Sleigh) .

    When to use a JSA

    1. Most tasks will start out either as a part of a plan or as a response to anunexpected event.

    2. If the job is planned, then a procedure should be part of the plan. Considerthe task of adding another trailing cable in line either to a shovel (surface) or

    Continuous Miner (underground).

    3. The procedure should include a number of controls checking that the cable issuitable, isolating power, testing before restoring power.

    4. In the case where a plan is in place, the JSA is to make sure that the controlsare in place or followed and to see if any additional controls are required

    because of local conditions. E.g. Weather (surface) or accumulated water

    (underground)5. If the job is not planned, for example machine breakdown, strata failure then

    the JSA should look for what parts are covered by procedures and what parts

    are not. The controls in the relevant prepared procedures should be in place or

    equally robust alternatives adopted. The parts for which there are no

    procedures require additional job steps in the JSA.

    6. Unplanned jobs certainly require change management what additionalhazards or process steps were introduced by the unexpected event?

    7. Planned jobs may also require change management how does this job differfrom the standard envisaged when the procedure was developed?

    Environmental conditions? Personnel? Tools?

    8. Assessing the risk is about identifying the controls that are required. Managingthe risk is about putting the controls in place and monitoring their

    effectiveness.

    The hierarchy of controls

    There is an order of preference for controls those higher in the list are most

    effective. The terms vary between lists, but this is the list in the Queensland Mining

    and Quarrying Safety and Health regulation, 2001.

    (a) elimination of the hazard;

    (b) substitution with a lesser hazard;

    (c) separation of persons from the hazard;

    (d) engineering controls;Examples of engineering controls

    1 using fans and ducting to remove dust

    2 using guards on conveyors

    (e) administrative controls;Examples of administrative controls

    1 a restriction on the time a worker is exposed to a hazard

    2 a procedure or standard work instruction

    (f) personal protective equipment.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    9/31

    Risk Management Workshop, Blackwater, 21 September 2010 9

    This is how the NSW Coal Mine Health and Safety Regulation, 2006 lists them:

    (a) firstly, substituting the hazard giving rise to the risk with a hazard that gives rise to

    a lesser risk,

    (b) secondly, isolating the hazard from the person put at risk,

    (c) thirdly, minimising the risk by engineering means,

    (d) fourthly, minimising the risk by administrative means (for example, by adopting

    safe working practices or providing appropriate training, instruction or information),

    (e) fifthly, using personal protective equipment.

    In todays mining practices, there is another level below PPE and that isMaking people aware of the hazard.

    This is where barrier tape, signs and pre shift briefings belong. The objective is to control the risk as high up the list as is reasonably

    achievable.

    The control will usually only affect the likelihood, or frequency of an incident.It will rarely affect the consequences.

    It doesnt matter whether you support the roof with timber, roof bolts ortendons, if a piece falls out hits a mineworker, the consequences are the same.

    It doesnt matter whether a railway level crossing is protected by signs, boomgates or an overbridge. If the car finds its way onto the tracks as the train

    approaches, the consequences are the same.

    Using a matrix to assess risk requires people who have a strong knowledge ofpast incidents, their causes and controls which were not in place or which were

    not adequate.

    It is unlikely that a work team will have that expertise. So it is not an accuratetool for use in a JSA.

    It is even less likely that a mineworker will have that knowledge, so it is lessuseful in a SLAM or Take 5.

    The value of the matrix is in deciding a priority in which controls are appliedat the planning stage.

    If a mineworker assesses that a job is unsafe, the first step is to make it safe ifpossible, and if not to withdraw and report it.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    10/31

    Risk Management Workshop, Blackwater, 21 September 2010 10

    Key Points (Jim Knowles).

    The main points that I considered were,

    The interest show by the number of participants tells me that there is a greatneed for more of these types of forums

    There appears to be a need for better consistency in the risk managementprocess between organisations/ regulators/ unions/ consultants

    Improved education for Risk Managers More clarity on the residual risk ranking, re; acceptable level of risk

    particularly in Qld

    Possibility of the major players getting together to try for a consistentapproach to RA i.e.: Rio, Anglo, BMA and Xstrata

  • 7/28/2019 2 Notes From the Risk Management Workshop

    11/31

    Risk Management Workshop, Blackwater, 21 September 2010 11

    Key Points (Tim Whyte).

    The key points as I see them could be encapsulated in the following;

    The legislation requires individual mines to develop PHMPs and SOPs, whythen are we performing multiple JSEA (or whatever) for a task that hasalready been assessed and work instructions drawn up? If, as conveyed at the

    seminar, that S&HMS are a monster, then this is our own making. If the mines

    S&HMS is accessible and clear to read, then it should be robust enough to

    instruct those performing the task to understand the process and assist in

    identifying the hazards. Tools such as Take 5, SLAMs etc. are for the

    individual - not to change the S&HMS to suit the daily condition. If not then a

    review of the procedure is required.

    I have attached an Audit tool for all to use that relies on the person performingthe task to map against the procedure and what they are actually being

    requested to perform. This tool, if used, not only gives the mine a free auditbut also gets buy in by the mine workers. (You would have seen something

    similar at MNC)

    S&HMS have grown out of control, this sometime being due to multipleaccess to add or change the mines current S&HMS. I believe all mines must

    have a dedicated S&MS Document controller to ensure that there is only but

    one of each required procedure available to all coal mine workers. In addition,

    all mines need to halt the practice on performing risk assessments to come up

    with another procedure to allow a task to continue, when a procedure already

    exists. As stated in my presentation, a procedure, once developed and signedoff as part of the S&HMS is a statute of law. A dedicated Document controller

    would alleviate this debacle by ensuring only access to the mines S&HMS for

    change is performed by an authorised person.

    Restriction, if not prescribed removal of Corporate bullying to push theirbarrow on how they see the world. The SSE has the obligation to develop and

    implement the S&HMS not the associated Corporation.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    12/31

    Risk Management Workshop, Blackwater, 21 September 2010 12

    Key Points (Jane Moss)

    Please find below key points as a result of the workshop in Blackwater;

    Simplicity is the key to effective risk management - back to basicsA JSA is a part of the complete risk management framework, however it is nota risk assessment. A wide variety of tools exist within a sound risk

    management framework, it is important we educate (training and coaching)

    our workforce to effectively use the risk management tools most relevant to

    them

    Residual risk scores provide clarity around priority setting, they do notindicate a level of risk acceptance

    Critical control effectiveness should be the key driver of risk tolerability. We

    must challenge ourselves to devise ways to continually monitor critical control

    effectiveness so that it becomes a common understanding and a part of the

    way we operate.

    Risk management is the key foundation to Safety and Health management,however it is an area that has been somewhat neglected and misguided over

    the past 5 - 10 years. It was encouraging to see so much interest in this topic

    and to discover such commonality in thinking. To achieve

    the greatest improvement in risk management, within the mining industry, we

    need to strive to achieve a more consistent approach, if there is anything that I

    may be able to do to further assist in achieving this, please let me know.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    13/31

    Risk Management Workshop, Blackwater, 21 September 2010 13

    Key Points (Adam Garde)

    The few points I feel are truly important to making a positive difference with regard

    to improving risk management in the workplace are as follows;

    Current legislation places obligations on all mineworkers, and for a person todischarge those obligations then all possible action must be taken to reduce the

    level of risk that personnel are exposed to within our operations to an ALARA

    level. Ignorance, short cuts, poor planning, training or available resources,

    under no circumstances makes it allowable not to do everything that is

    possible to protect the health and safety of all concerned. With this point in

    mind, no matter the risk identification or management tool utilised by an

    operation, the key purpose remains the same, hazard identification and

    acceptable control are the outputs required from the process.

    Nearly all mines have a documented SHMS that on paper meets therequirements of legislation in regard to having prescribed PHMPs and

    SOPs etc. The key to improving the safety of the mine environment and the

    workforce is for the workforce to have an active understanding and

    involvement with their sites SHMS. The most perfectly written procedures

    are useless without an understanding of how to implement and apply them into

    every task within the mine. A safe mine and mine culture does not happen by

    accident, it takes planning, effort, team participation and continual review.

    Whilst it is the operators and tradesmen that normally perform the tasks on aday to day basis, it is critical that the people in supervisory and senior

    supervisory roles have a real understanding of exactly what is involved in the

    tasks they plan for completion. It is very easy to get bogged down and spend

    the whole day glued to the computer, but if you really want to be a part of your

    work groups and improve the performance in all areas, you need to spend real

    time in the workplace and see the day to day struggles and then action the

    issues to make a change. When planning tasks, ALL the required

    documentation should support the daily plan. Auditing your procedures

    against the actual way the tasks are done underground is the only way to

    ensure your systems and documents are adequate.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    14/31

    Risk Management Workshop, Blackwater, 21 September 2010 14

    Key Messages (Andrew Morrell) ..

    1 - Things go-wrong because of poor decision-making

    All 'Mishaps'; be they, injuries, fatal injuries, damage or failures to deliver on critical

    business objectives, are the result of one or more defective decision-makingsequences used within the organisation.

    2 - Good quality Risk assessments support good quality decision-making

    Timely, well-designed and completed Risk assessments are the best practice tool

    that helps the organisation to maximise the effectiveness of its decision-making. It

    does this by generating thorough understanding of what needs to be done, by when

    and the methods to be used that ensure that required outcomes are achieved, despite

    the presence of threatening, and often uncertain, energies/hazards.

    3 - The quality of risk assessments is entirely dependent on the process used

    The value of a risk assessment is dependent on the integrity of the processes used and

    how it is implemented so that it accurately:

    3.1 Identifies the steps that will be taken to achieve the required outcomes;

    3.2 Prioritizes the issues that threaten the required outcomes;

    3.3 Uses sound principles of Hazard (energy) Control that ensure the

    adequacy of control over the life of the assets being considered (including the

    potential for failure-on-demand);

    3.4 Harnessing the strengths of group analysis (e.g. synergy) without

    suffering from the inherent weaknesses of Group Think, Bias or Capture by

    individuals; and3.5 Reveals those things that the organisational decision-makers didnt know

    that they didnt know.

    4 - To be duly-diligent Hazard Control must be founded on sustainable &

    justifiable logic

    It is important to understand that most risk management concepts are based on

    models of the real world. If these models are pushed too hard, they can fail to yield

    helpful answers (or worse still they can give the wrong answer).

    Some examples are: the use of the 5 x 5 matrix to estimate controlled risks, a task for

    which, this simple and useful tool, was not designed. It is important to

    understand that it is a tool designed to logically allocate limited

    organisational resources with some capability to drive referral to other

    managerial or expertise levels; it is not a useful tool to measure hazard

    control effectiveness.

    Use of matrix risk ranking can inadvertently encourage personnel torank risks off-the-page as a method of avoiding effort (particularly in

    JSAs or WRAC exercises)

    Quoting residual risks, using a 5 x 5 matrix, often results indocumented evidence of risks being accepted that are indefensible inlaw. The chosen risk rating is not an acceptable risk because the

  • 7/28/2019 2 Notes From the Risk Management Workshop

    15/31

    Risk Management Workshop, Blackwater, 21 September 2010 15

    matrix was only intended for use as measure of raw risk and unless

    consequences can be significantly reduced the matrix will always

    prioritise the risk as unacceptable (too high). Good practice does not

    require qualitative residual risks, instead it needs evidence of adequate

    hazard control!

    Relying on arbitrary judgements on residual (controlled) risk using arisk matrix without a full explanation of how the reduction is to be

    achieved through the use of chosen layers of protection over the life of

    the asset.

    5 - Beware of ill-considered delegation in risk decision-making

    The tools of risk assessment (JSA, WRAC, HAZOP, FMECA, FTA, Bowtie etc.)

    can usefully be employed, together or individually, at any organisational level in an

    organisation. However, it is important to recognise that for each level, the specific

    needs for sound risk assessment are different. The competence set of those taking part

    in the risk assessment must be sufficiently wide and deep, to provide the rightanswers. It is vital that each managerial level of risk assessment process is tuned to

    reflect the authorities and accountabilities of those charged with providing guidance to

    decision-makers. In every type of risk assessment, someone in the risk assessment

    exercise has to be held accountable for ensuring the integrity of the assessment

    process, irrespective of other organisational priorities.

    6 Managements job is to find the right balance between thoroughness and

    efficiency.

    The real challenge for organisational management is to ensure that there is adequate

    and effective effort put into risk assessment and hazard control implementation in

    order to deliver on the organisationss aspirations for an adequate return for all

    stakeholders. This requires the organisation to embed an in-depth understanding of

    capable risk assessment processes and the will to adopt it, even in the face of the

    relentless imperative to be efficient.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    16/31

    Risk Management Workshop, Blackwater, 21 September 2010 16

    Key Messages (Richard Mills)

    In general mine personnel are not developing a risk assessment scope to thelevel of detail required so the outcome is a risk assessment that does not

    adequately address the issue when it is completed

    Risk assessment documents at various sites have a similar basic WRAC layouthowever not all encompass the required information input to prompt /

    encourage the necessary prework

    JSA formats are not suitable for all risk assessment tasks and limited personnelhave the confidence and skills to complete a comprehensive WRAC FMEA or

    HAZOP etc or know when they should be used and help of a skilled facilitator

    is required

    Separating or explanation of hazards in the correct terms (task, what could gowrong, why could that go wrong) to promote the use of targeted control

    methods rather than generalisations (encourages the correct use of the

    hierarchy of controls)

    Personnel are being educated in basic JSA and modified JSA methods andsome times WRAC through S1, S2,S3 and G2A process but in the field my

    experience has shown there still exists a considerable lack of knowledge in

    risk management by front line supervisors

    There is a tendency to rush the process which misses the necessary detail ordoes not adequately address the task, hazard and controls effectively.

    Commitment is required to provide the right people not just anybody Suggestion of some site risk management professionals that would be charged

    with vetting the scope prior to completing the risk assessment may improve

    the quality (typically some sites have the UMM or MM approve the scope

    prior to commencing the RA)

    A common matrix approach across industry Removal of any use of a matrix from the simple JSA approach An industry understanding that Risk Management is not just a WRAC or JSA

    but a bag of tools that requires knowledge of what tool is best used where

    when completing a risk management exercise.

  • 7/28/2019 2 Notes From the Risk Management Workshop

    17/31

    Risk Management Workshop, Blackwater, 21 September 2010 17

    Guidance Point #1

    Selecting the most appropriate risk assessment tool

    Context

    There is a general lack of understanding as to what risk-assessment tool needs to be

    applied in what circumstance. There is not enough effort in establishing the context,

    purpose and scope. These are critical steps and assist in selecting the most appropriate

    risk assessment tool.

    Potential Action Plan

    Recognised Standard 2 (or the equivalent document to be aligned withthe harmonised legislation in 2012) to be amended so that it becomes

    more effective in assisting people to select the most appropriate risk

    assessment tool

    To include checks on process performance To include strategies and guidance on how to avoid traps that lead to

    ineffective risk management processes (refer to National Minerals

    Industry Safety and Health Risk Assessment Guideline)

    To include guidance on how mines are to comply with s 62 Safety andHealth Management System (1) A safety and health management

    system for a coal mine is a system that incorporates risk management

    elements and practices that ensure safety and health of persons who

    may be affected by coal mining operations the Mine Site Risk

    Management Standard.

    The Mine Site Risk Management System (s62) forms a part of theSHMS- it should explain how the mine implements and applies

    Recognised Standard 2. It should include for example authorisation

    process and checks for scoping and facilitation via the most

    appropriate risk assessment tool eg. WRAC vs JSA.

    Relevance to existing processes

    S62 Safety and Health Management System Recognised Standard 2 Control of Risk Management Practices The Coal Mining Safety and Health Advisory Council In fulfilling its

    mandate is to Periodically review the effectiveness of the Act,

    regulations and recognised standards, and the effectiveness of the

    control of risk to any person from coal mining operations.

    Recognised Standard 9 Guidance Note on Reviewing the Effectivenessof the Safety and Health Management System

  • 7/28/2019 2 Notes From the Risk Management Workshop

    18/31

    Risk Management Workshop, Blackwater, 21 September 2010 18

    Notes related to Guidance Point #1

    Selecting the most appropriate risk assessment tool

    What Jim Joy said about that..

  • 7/28/2019 2 Notes From the Risk Management Workshop

    19/31

    Risk Management Workshop, Blackwater, 21 September 2010 19

  • 7/28/2019 2 Notes From the Risk Management Workshop

    20/31

    Risk Management Workshop, Blackwater, 21 September 2010 20

  • 7/28/2019 2 Notes From the Risk Management Workshop

    21/31

    Risk Management Workshop, Blackwater, 21 September 2010 21

  • 7/28/2019 2 Notes From the Risk Management Workshop

    22/31

    Risk Management Workshop, Blackwater, 21 September 2010 22

    Guidance Point #2

    Training and Educating people to make effective decisions when applying and

    implementing risk management practices

    Context

    There is a need to re-educate people who apply and implement risk management

    processes. There is inconsistency in establishing the context, purpose and scope, and

    in selecting and applying the most appropriate risk assessment tool.

    People without the necessary technical competencies and knowledge of the Safety Health

    Management System are appointed to supervisory positions. G2 and G3 training alone

    may not have been sufficient in effectively implementing effective risk management

    practices. Understanding what, why and how may have gone unchecked.

    Potential Action Plan Ensure that people on site are appropriately trained in the mine site

    system on how to implement the Risk Management System. Consider

    relevance of the site Training Needs Analysis (Regulation 84).

    This can also be addressed in the review of Recognised Standard 2 (orthe equivalent document to be aligned with the harmonised legislation

    in 2012).

    Consider if it justifies being a Prescribed tasko Set expectations with RTOs. Raise implementation issues associated

    with risk management practices on mine sites. RTOs to make

    adjustments to training material and verify same.

    Relevance to existing processes

    This extract immediately below is from the ANNUAL REPORT of the COALMINING SAFETY AND HEALTH ADVISORY COUNCIL July 2008 - June

    2009

    Quality of Competency Training

    Discussion on the quality of competency training, and the performance of

    Registered Training Organisations (RTOs), concluded that delivery ofcompetencies and testing is often substandard.

    The Council has begun to investigate options raised, including the possibility of

    training providers to be recognised by the Board of Examiners or the Council, or

    whether it is possible for the Department of Employment, Economic

    Development and Innovation to have a list of preferred or authorised RTOs. It

    was decided to make RTO training a permanent item on the Councils agenda.

    82 Training scheme 84 Refresher training 85 Coal mine worker not to carry out task unless competent Schedule 7 Prescribed tasks for section 76(3)(a) of the Act

  • 7/28/2019 2 Notes From the Risk Management Workshop

    23/31

    Risk Management Workshop, Blackwater, 21 September 2010 23

    Notes related to Guidance Point #2

    Training and Educating people to make effective decisions when applying and

    implementing risk management processes

    What Jim Joy said about that..

  • 7/28/2019 2 Notes From the Risk Management Workshop

    24/31

    Risk Management Workshop, Blackwater, 21 September 2010 24

  • 7/28/2019 2 Notes From the Risk Management Workshop

    25/31

    Risk Management Workshop, Blackwater, 21 September 2010 25

  • 7/28/2019 2 Notes From the Risk Management Workshop

    26/31

    Risk Management Workshop, Blackwater, 21 September 2010 26

    Guidance Point #3

    Inconsistent application and use of Job Safety Analysis (JSA)

    Context

    JSA forms a healthy part of on-site risk management practices. There are however

    inconsistencies in;

    Deciding if JSA should be risk scored. Deciding if a JSA should be converted into a documented procedure, in

    which case it can be re-used, and reviewed.

    Deciding if a procedure developed from JSA is an SOP. If it is, then; Recognised Standard 2 requires it to be risk scored, and Regulation 10

    requires it to be developed in consultation with other affected

    mineworkers.

    Subject to a plan to regularly review if the practice is at an acceptablelevel of risk (s62(1)(f)).

    Potential Action Plan;

    Recognised Standard 2 (or the equivalent document to be aligned withthe harmonised legislation in 2012) to be amended so that it becomesmore effective in assisting mines to apply JSA. Tri-partite to decide the

    above issues, in consultation with Jim Joy.

    Potential review and update of National Minerals Industry Safety andHealth Risk Assessment Guideline (v6, 2007).

    Relevance to existing processes

    Recognised Standard 2 Control of Risk Management Practices s10 Standard Operating Procedures s11 Accessing standard operating procedures

  • 7/28/2019 2 Notes From the Risk Management Workshop

    27/31

    Risk Management Workshop, Blackwater, 21 September 2010 27

    Notes related to Guidance Point #3

    Inconsistent application and use of Job Safety Analysis (JSA)

    What Jim Joy said about that..

  • 7/28/2019 2 Notes From the Risk Management Workshop

    28/31

    Risk Management Workshop, Blackwater, 21 September 2010 28

    Guidance Point #4

    Hierarchy of controls, and control effectiveness

    Context

    In the absence of specific expectations, too much onus is placed on administrative

    controls. This maybe influenced negatively by corporate pressure. Sometimes there is

    a lack of commitment to engineering/hard controls. Ineffective decision making can

    lead to;

    Inappropriate controls being identified Critical controls not effectively identified or implemented

    Review processes often fail to validate control effectiveness.

    Qld Coal Mining Safety and Health legislation does not reference effectiveness of

    control hierarchy, other than in Guidance Note 9.

    Potential Action Plan

    Recognised Standard 2 (or the equivalent document to be aligned with theharmonised legislation in 2012) to be amended to include strategies and

    guidance on the identification of appropriate control strategies including

    reference to the hierarchy of controls, the identification of critical controls, and

    measuring the effectiveness of controls.

    Relevance to existing processes

    S62 Safety and Health Management System Recognised Standard 2 Control of Risk Management Practices Recognised Standard 9 Guidance Note on Reviewing the Effectiveness

    of the Safety and Health Management System (Part 9 causal Analysis).

  • 7/28/2019 2 Notes From the Risk Management Workshop

    29/31

    Risk Management Workshop, Blackwater, 21 September 2010 29

    Notes on Guidance Point #4

    Hierarchy of controls, and control effectiveness

    What Jim Joy said about that..

  • 7/28/2019 2 Notes From the Risk Management Workshop

    30/31

    Risk Management Workshop, Blackwater, 21 September 2010 30

    Guidance Point # 5

    There may be a need for some mines to improve the effectiveness of their SHMS

    in respect to risk management processes. In particular the implementation of

    consistent risk management practices, review, and document control.

    Context

    Section 62 Safety and health management system states(1) A safety and health management system for a coal mine is a system that

    incorporates risk management elements and practices that ensure safety and health of

    persons who may be affected by coal mining operations.

    Notes from the Workshop Flyer

    We spend days reviewing SOPs that have not materially changed in yearsbecause the procedures are not fully integrated into the way of working of the

    mine. Management are not aware of their responsibilities under or

    responsibility for the maintenance of the Safety Health Management System

    and therefore there is no ownership.

    Senior Management may profess to making safety their number one priorityyet fail to maintain the systems that manage it. Coal mine workers may use

    the Safety Health Management System for purposes other than intended. In

    the search for clarity and brevity accusations are made of watering down the

    system. Most companies now employ electronic risk management systems

    and process such as First Priority Enterprise, SAP and Hummingbird but theSafety Health Management System has not necessarily been fully integrated

    into these.

    Potential Action Plan

    Recognised Standard 2 (or the equivalent document to be aligned with theharmonised legislation in 2012) to be amended to include strategies and

    guidance on how to measure and improve the effectiveness of risk

    management processes, including document control.

    To incorporate the need for investigation processes to evaluate theeffectiveness of controls identified in previous risk assessments.

    Relevance to existing processes

    s15 Investigating accidents and incidents Section 62 Safety and health management system Recognised Standard 9 Guidance Note on Reviewing the Effectiveness

    of the Safety and Health Management System

  • 7/28/2019 2 Notes From the Risk Management Workshop

    31/31

    Notes on Guidance Point # 5

    There may be a need for some mines to improve the effectiveness of their SHMS

    in respect to risk management processes. In particular the implementation of

    consistent risk management practices, review processes, and document control.

    What Jim Joy said about that..