2. ed merrow presentation

42
1 ECI’s 23 rd Annual Conference 2012 The European Construction Industry Facing the Global Challenges 26 & 27 April 2012 Hilton Hotel, Dusseldorf

Upload: initiative1972

Post on 20-Oct-2015

63 views

Category:

Documents


5 download

TRANSCRIPT

  • 1ECIs 23rd Annual Conference 2012

    The European Construction Industry Facing the Global Challenges

    26 & 27 April 2012Hilton Hotel, Dusseldorf

  • 2Industrial Megaprojects Concepts, Strategies and

    Practices for Success

    Ed MerrowPresident & CEO

    Independent Project Analysis, Inc. (IPA)

  • 3Our Vantage Point on the Industry

    Independent Project Analysis evaluates industrial projects, large and small, around the world Are the projects ready to proceed to the next

    phase?

    Are the projects set up to succeed (or fail)

    At the end, did the projects accomplish their goals?

    In a typical year, 700-800 new projects are added to our databases

  • 4Our Vantage Point on the Industry

    About 10 percent of these projects fall into the very large categorywell over $1 billion in capital

    The number of these very large projects has increased dramatically over the last decade, controlling for escalation

    We are deeply concerned about their results

  • 5Some Key Questions

    Projects are getting larger and more complex everywhere in the world

    As we will see, large projects fail much more often than their smaller counterparts

    Do large projects fail more often simply because they are more difficultordo we alter our practices?

    As project leaders and professionals, what do we need to do differently?

  • 6Outline

    The Data

    The results of large industrial projects

    The proximate and root causes of failures

    Implications for project management

  • 7$3,250Project Cost (in millions 2011 US$)

    Megaprojects Database

    Number of Owners Represented

    Percent of Projects with Any New Technology

    Average Execution Duration (months)

    Average Authorization Year

    Number of Projects

    77

    36%

    43

    2005

    318

    Research Database Description

    Characteristics

  • 8Industries Represented

    Petroleum Processing Petroleum Processing 21%21%Chemicals Chemicals

    10%10%

    Mining, Mining, Minerals & Minerals &

    Metals Metals 15%15%

    LNG LNG 8%8%

    Power Power Generation Generation

    3%3%

    Distribution Distribution 2%2%

    Other Other 2%2%

    Oil & Gas Production Oil & Gas Production 41%41%

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS9

    United States 13%

    Europe15%

    Asia9%

    Australia9%

    Africa9%

    South America19%

    Geographical Distribution of Megaprojects

    Canada7%

    Central Asia 4%

    Middle East15%

  • 10

    Outline

    The Data

    The results of large industrial projectsThe results of large industrial projects The proximate and root causes of failures

    Implications for project management

  • 11

    Costs grew (real)

    Schedule Slipped

    Execution time (Absolute Measure)

    Severe and Continuing Operational Problems into Year 2 after startup

    Defining Success and Failure

    About two-thirds of large projects failed by these criteriatwice the rate of small projects

    Overspent (Absolute Measure)

    25% +

    25% +

    50% +

    Yes

    25% +

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Megaprojects

    Failure Rate

    Projects

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS12

    80%

    COST INDEX

    PRODUCTION

    EXECUTION SCHEDULE INDEX

    EXECUTIONSCHEDULE SLIP

    COST GROWTH

    1.3

    1.0

    1.2

    1.0

    1.3

    1.2

    1.1

    0%10%

    30%

    20%

    0%

    Failed Projects (65 percent)

    Successful Projects (35 percent)

    40%

    100%

    60%

    1.1

    10%

    20%30%

    Megaprojects Split Into Radically Different Groups

  • 13

    Is Failure Driven by Geography?

    The OECD countries success rate is indistinguishable from the overall average

    Europe is no better than average

    The Middle East fares a little better

    Australia and Central Asia have a lower than average success rate

  • 14

    Is Failure Driven by Industrial Sector?

    Petroleum development and minerals megaprojects fare worse than industry average

    Chemical industry does a little better

    However, these results are driven by differences in practices, not sector

  • 15

    Outline

    The Data

    The results of large industrial projects

    The proximate and root causes of failuresThe proximate and root causes of failures Implications for project management

  • 16

    The Proximate Causes: Weak Practices

    The effects of poor practices are much more devastating for large and very large projects because larger and more complex projects are inherently fragile

    Four critical practices set megaprojects up to succeed or fail: Clear objectives for the team

    All key owner functions involved in development

    Stability in project leadership

    Complete front-end loading (FEL) prior to sanction

  • 17

    The Project Objectives Problem

    Coherent project objectives are the foundation on which a strongproject team is built

    This requires that all of the objectives being articulated in a meaningful waynot just some empty nostrum such as make a lot of money

    It requires that the trade-offs amongst objectives are understood and that clear priorities are established

    So, how are we doing?

    Clear ObjectivesClear Objectives

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS18

    0

    10

    20

    30

    40

    50

    60

    70

    Very Fairly Somewhat Unclear

    Under $500MM Megaprojects

    P

    e

    r

    c

    e

    n

    t

    o

    f

    P

    r

    o

    j

    e

    c

    t

    s

    Only a Slight Difference in Clarity of Business Objectives Between Megas and Non-Megas

    Team Understanding of Project Business Objectives at Sanction

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS19

    0

    10

    20

    30

    40

    50

    60

    70

    80

    Very Fairly Somewhat Unclear

    Under $500MM Megaprojects

    P

    e

    r

    c

    e

    n

    t

    o

    f

    S

    u

    c

    c

    e

    s

    s

    f

    u

    l

    P

    r

    o

    j

    e

    c

    t

    s

    But Differences in Effects Are Huge

    Team Understanding of Project Business Objectives at Sanction

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS20

    Trade-offs Are Less Clear for Megas

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    Very Clear Fairly Somewhat Unclear

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS21

    Team Integration Is a Necessary Condition for Effective FEL

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    45%Projects Without Integrated TeamsProjects With Integrated Teams

    P

    e

    r

    c

    e

    n

    t

    o

    f

    P

    r

    o

    j

    e

    c

    t

    s

    MiserablePoorFairGoodBest

    FEL Index

    Missing critical functions during FEL damages quality and Missing critical functions during FEL damages quality and completeness of the frontcompleteness of the front--end workend work

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS22

    Turnover of the Project Leader HurtsBut It Destroys MegaprojectsBut It Destroys Megaprojects

    0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    $10MM -$25MM

    $25MM -$100MM

    $100MM -$250MM

    $250MM -$500MM

    Megaprojects

    E

    f

    f

    e

    c

    t

    o

    f

    P

    M

    T

    u

    r

    n

    o

    v

    e

    r

    o

    n

    P

    r

    o

    j

    e

    c

    t

    F

    a

    i

    l

    u

    r

    e

    R

    a

    t

    e

    Project Size

    Leadership TurnoverLeadership Turnover

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS23

    25%

    30%

    35%

    40%

    45%

    50%

    10 50 100 150 200 250 300 350 400 450 500

    Cost 2011$ (million)

    P

    e

    r

    c

    e

    n

    t

    o

    f

    P

    r

    o

    j

    e

    c

    t

    s

    t

    h

    a

    t

    E

    x

    p

    e

    r

    i

    e

    n

    c

    e

    P

    r

    o

    j

    e

    c

    t

    M

    a

    n

    a

    g

    e

    r

    T

    u

    r

    n

    o

    v

    e

    r

    Larger Projects Experience More Frequent Project Manager Turnovers Even After

    Controlling for Schedule

    Turnover rate in Megaprojects

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS24

    0%

    1.00

    10%

    COST INDEX

    PRODUCTION FAILURES

    SCHEDULE INDEX SCHEDULE SLIP

    No TurnoverTurnover

    COST GROWTH

    1.40

    0.90

    1.20

    1.00

    10%

    40%

    20%30%

    1.10

    40%30%

    20%

    60%

    30%

    20%

    10%

    0%

    40%

    1.20

    1.10

    0.90

    1.40

    Project Director Turnover Relates to All Outcome Metrics

    1.30

    1.30

    50%

  • 25

    Why is Turnover So High?

    Some suspect the turnover is high because owners are replacing failing project managers

    In fact, that is rarely the case; contractor PMs are the usual designated scapegoats

    Some turnovers are caused by irrational staffing and the shortage of project personnel

    But the principal cause of megaproject turnover appears to be simple burnoutsimple burnout

    Project director turnover is strongly related to the business sponsors setting highly aggressive schedules

  • 26

    Why Is Turnover So Damaging? Complex projects need to integrate a large number of

    owner functions into a coherent whole

    The project director and immediate reports form the glue that binds the project together

    When the project director leaves for whatever reason a significant unraveling of the project occurs All informal agreements disappear

    There is a period of indecision while learning occurs

    The turnovers provide an avenue for opportunistic behavior, especially with regard to changes

  • 27

    Front-End Loading is the Key Practice

    IPA measures the quality of pre-sanction work with an index that has been developed and improved over the past 35 years

    The FEL index is the single most reliable predictor of how any project will turn out

    The index measures the definition of the project in its context, the completeness of basic engineering, and the quality of the execution planning

    We convert intervals on the numerical index to descriptive words in presentation

    FrontFront--End LoadingEnd Loading

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS28

    0%

    10%

    20%

    30%

    40%

    Best Practical Good Fair Poor Screening

    FEL is Most Important for Megaprojects

    E

    f

    f

    e

    c

    t

    o

    f

    F

    E

    L

    o

    n

    t

    h

    e

    C

    o

    s

    t

    I

    n

    d

    e

    x

    FEL Index

    Megaprojects

    MISERABLEPOORFAIRGOODBEST

    250 - 500

    100 - 250

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS29

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    P

    e

    r

    c

    e

    n

    t

    a

    g

    e

    o

    f

    P

    r

    o

    j

    e

    c

    t

    s

    FEL Index

    MISERABLEPOORFAIRGOODBEST

    How Well Are Megaprojects Defined at Authorization?

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS30

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    Percent in Group Percent Successful in Group

    What Difference Does it Make?P

    e

    r

    c

    e

    n

    t

    a

    g

    e

    o

    f

    P

    r

    o

    j

    e

    c

    t

    s

    FEL Index

    MISERABLEPOORFAIRGOODBEST

  • CONFIDENTIAL INDEPENDENT PROJECT ANALYSIS31

    Objectives, Team Integration, and FEL

    Very Clear Fairly Clear SomewhatClear

    Not Very Clear Not Clear At All

    F

    E

    L

    I

    n

    d

    e

    x

    Clarity of the Objectives

    F

    a

    i

    r

    B

    e

    s

    t

    M

    i

    s

    e

    r

    a

    b

    l

    e

    G

    o

    o

    d

    P

    o

    o

    r

    Pr < 0.0001

    Pr < 0.91

    Source: Industrial Megaprojects

    Team Is Not IntegratedTeam Is Integrated

  • 32

    Practices that Drive Megaprojects Results

    1. Clear and fully articulated business objectives

    2. Full functional integration of the teams

    3. Continuity of team leadership

    4. Excellence in front-end definition and planning

  • 33

    Practices are more important for large projects

    The effects of poor practices are far more destructive for larger projects

    The fact that the practices we follow for large projects are not as good as those for smaller projects is the proximate cause of the high rate of failure

    But it merely raises a deeper question: why would we systematically follow poorer practices on our most important projects?

    Practices Drive But Do Not Really Explain

    Root CausesRoot Causes

  • 34

    A simple reason is that practices are more difficult and resource-consuming on larger projects Front-end loading costs will be in the many millions of dollars

    for megaprojects

    The sheer numbers of people required to properly staff teams are larger and often exhaust available resources

    It is difficult to recruit team members when remote sites are involved

    Difficulty contributes to poor practices, but is a secondary cause

    The primary cause is the drive for unachievable speed

    Why Do Practices Degrade on Large Projects?

  • 35

    In Megaprojects, Speed Kills!

    The drive for speed results in the projects outrunning: Basic (Technical) Data development

    Stakeholder alignment

    Permitting requirements

    Front-end loading development

    Even the business deal may be incomplete

    Large projects cannot recover from cut-corners

    There are too many business cowboys with weak accountability for results driving the projects too fast

  • 36

    Mamas, dont let your babiesgrow up to be cowboys!

    Willie Nelson

  • 37

    Outline

    The Data

    The results of large industrial projects

    The proximate and root causes of failures

    Implications for project managementImplications for project management

  • 38

    The Need for Change is Clear

    As a profession, our track record of failure on major industrial projects is not acceptable

    This is true even though project management professionals are rarely the actual source of the failures

    Most of the failures are caused by owner business professionals who too often do not understand the basics of the projects they put off the rails

    Just as every contractor knows that managing the client is essential, owner project professionals must learn to manage their business clientele

  • 39

    Redress and Rebalance

    Most of the teams on the failed megaprojects knew the projects were headed for disaster well sanction

    They also felt there was nothing they could do about it

    During the 1990s, project management was relegated to the backseat in many industrial companies

    We became progressively passive in the face of the new business model with its focus on immediate gain

    Although the market situation changed in 2004, we did not redress the imbalance that had emerged between the technical functions and the businesses

  • 40

    Redefining Project Management for Large Projects

    An essential project management skill is the ability to speak truth to power effectively

    We must see ourselves and then be seen as equal partners with the businesses in creating successful capital assets

    We need business education for project professionals

    We need capability to speak effectively to those who do not understand the havoc they are creating

    Unless we change, we must look forward to another decade of large project disasters

  • 41

    Thank you for Thank you for your Attention!your Attention!

  • 42

    European Construction Institute

    www.europeanconstruction.eu