2 cm-ms-bld-012 - roof fan & natural ventilator

17
Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal CAI MEP INTERNATIONAL CONTAINER TERMINAL METHOD STATEMENT OF INSTALLATION ROOF FAN AND NATURAL VENTILATOR FOR BUILDING WORK Page 1

Upload: minh-bui-si

Post on 19-Jul-2015

88 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

CAI MEP INTERNATIONAL CONTAINER TERMINAL

METHOD STATEMENT OF INSTALLATION ROOF FAN AND NATURAL VENTILATOR FOR BUILDING WORK

Page 1

Page 2: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

TABLE OF CONTENS

1. Introduction Page 3

2. References Page 3

3. Work Flow Chart Page 4

4. Work Procedure Page 5

4.1 Preparation work Page 5

4.2 Survey fan location Page 5

4.3 Installation work Page 5

4.4 Manpower & Equipment Plan Page 9

4.5 QA/QC Procedures Page 10

4.6 Site supervision and Process control Page 10

5. Safety process Page 10

6. Environment Protection Page 11

7. Organization chart Page 12

8. Appendix Page 12

1. Work schedule

2. Inspection & Testing Plan (ITP)

3. Inspection form

4. Check list

5. Test report

Page 2

Page 3: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

1. INTRODUCTION:

This Method Statement is prepared to ensure that installation of Roof fan and Natural

ventilator for Mechanical work on this project shall comply on specifications, approved shop

drawing, and all relevant standard and code requirements in the execution of different work

activities to be performed in the installation of Roof fan and Natural ventilator. In addition,

this will serve as a tool to guide all technical personnel and layman execute proper installation

procedures complied with the quality and safety plans for the project.

2. REFERENCE TECHNICAL SPECIFICATION:

Page 3

Page 4: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

1. WORK FLOW CHART:

.

Not Approved Approved

Page 4

Submission of Shop drawing; get approval

Preparation work

Testing & Inspection with JPC-

NK

Survey work

Installation work

Rectificationof Work

Cleaning & Touch-up paint

Completion Work

Page 5: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

3. WORK PROCEDURE:

The work procedure is described as follows:

4.1 PREPARATION WORK:

Before carrying out any work, check the followings as listed below:

- Checks all approved shop drawings and confirm latest drawings are used.

- Confirm all materials procured against material approval list.

- Ensure that approved installation details methods are fully comprehended by the

workers.

- Clear area under installation location and install warning tape for forbidding non-

authorized person to enter.

- Support for fan shall be prepared prior to installation work.

- Check dimension of fan’s support to ensure enough space for installation fan.

- The coordinates and level shall be followed approved shop drawing and confirmed with

Engineer prior to the commencement of construction works.

- Roof fan , Natural ventilator shall be approved and accepted for using by Engineer.

4.2 SURVEY FAN LOCATION:

After determining the coordinates and elevation level, location and level of Fan shall be

determined following approved shop drawing with Engineer’s representative. The support of fan

shall be fabricated basing on approved shop drawing in accordance with instruction by the

Engineer (if any).

4.3 INSTALLATION WORK:

4.3.1. Support Installation:

- Support shall be fabricated to follow approved drawing of Engineer and installed on the

steel structure of building.

- Support shall be painted with approved color prior to installation work.

- The survey work shall be done to confirm the location of support and to be checked by

Engineer.

- Installation work shall be carried out carefully because of high level. Workers shall

observe safety patrol for working at high level.

- Supports shall be fixed to steel structure by bolt and nut with washers after that checking

its stable by visual and shaking by hand.

Page 5

Page 6: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

Page 6

Page 7: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

4.3.2 Fan installation:

Fan shall be installed on the steel support or concrete base. The dimension of both kind have to

follow the manufacture specification.

Fan shall be fixed to support by screws or bolts with quantity and size basing on approved shop

drawing and instruction of Engineer.

The rubber isolator with 10mm thickness shall also be installed between fan’s base and support.

Page 7

Page 8: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

The balance and level of fan shall be check carefully prior to fixing work.

Screw or bolt for fixed fan to support do not over-tighten to prevent distortion of fan base (in

case fan case made by GPR, fiberglass) and rubber isolator.

Water proof work shall be carried out carefully to ensure non-leakage when it rain. Every gap,

joint shall be sealed by suitable caulking material which is approved by Engineer.

4.3.3 Testing work:

Air flow rate of fan (except Natural ventilator) shall be tested basing on the specification.

Electrical power (voltage, ampere) shall be also check to ensure the operation of fan with

correctly condition.

4.3.4 Completion work:

At the end of Mechanical work, all equipment and redundant material shall be removed and

transported to another place. Clean up the working place for next work team to start.

Touch-up paint to damage position on support before finishing work.

4.3.5 Electrical work:

Electrical work(power supply) shall be executed to follow the approved drawing by skill

electrical worker after Mechanical work finished.

Page 8

Page 9: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

4.4 MANPOWER AND EQUIPMENT:

4.4.1 Manpower List :

No. Designation Unit Quantity1 M&E Manager (Japanese) Person 12 Chief Engineer (Japanese) Person 13 Site Engineer (Local) Person 24 QA/QC & Safety Engineer Person 15 Skilled worker Person 26 Unskilled labor Person 87 Foremen Person 18 Welder Person 1

TOTAL Persons 17

4.4.2 Equipment List :

No. Designation Unit Quantity1 Cutter Set 12 Drilling machine Set 13 Marking instrument Set 14 Scale Set 15 Bubble level Set 1

6

Hand tools(Screw driver, basin

wrench, pliers, adjustable wrench,

etc.)

lot 1

7 Extension Socket for power supply lot 18 Electric welding machine Set 1

4.5 QA/QC PROCEDURES:

4.5.1 General

The Contractor shall submit the name, shop drawing and appropriate details of any

independent testing organization to the Engineer for approval before any construction work

for fan installation commences.

Page 9

Page 10: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

4.5.2 Materials Testing

Materials testing are to be carried out before delivery of materials into the site and quality

certificate shall be submitted.

The Contractor should be submitted to the Engineer the related documents for approval

before delivery to site or start the construction.

The inspection report or specification of Fan shall be received before arrival of Fan on site.

Upon arrival on site, Fan shall be inspected as to dimensions, quantity, and physical

condition and reported to the Engineer.

4.6 SITE SUPERVISION AND PROCESS CONTROL:

Approved for materials shall be carried out prior to delivery to the project site. Constructions

shall be followed approved shop drawing by Engineer.

The Ventilation Fan, support, & accessories shall be checked and inspected for defects to

ensure that all material is good quality prior to install.

The work shall be supervised by qualified and experienced staff and executed by highly

skilled , experienced operators and workers.

5. SAFETY PROCESS:

The project Safety Plan is established for the Construction of CAI MEP INTERNATIONAL

CONTAINER TERMINAL in Vietnam based on Occupational Health and Safety and

Rehabilitation Management Manual of TTJV.

The safety control of works shall be maintained and ensure its compliance through-out the

completion period so that works can be executed smoothly without unnecessary interruption.

Importance shall be placed on the prevention of any accident such as personal injury ,

damage to structures and work itself.

In general, safety rules and regulations stipulated by the governing authorities of Vietnam as

well as by the client shall be observed.

6. ENVIROMENT PROTECTION:

The Project Environmental Management Plan (EMP) addresses the requirements for

Environmental Management, outlining how the scope, as described by the Conditions of

Contract , will be implemented to achieve the key objectives for CAI MEP

Page 10

Page 11: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

INTERNATIONAL CONTAINER TERMINAL PROJECT , and has been designed to

comply with the intent of OHSAS 18001 and ISO 14001.

Built into this operating system will be CAI MEP INTERNATIONAL CONTAINER

TERMINAL PROJECT Specification requirements ,as defined in the contract. This

Environmental Management Plan will incorporate work method statements, inspections, test

plans , and check sheets are developed to cover the particular requirements of this project.

This Plan is established based on the Environmental Management Manual of TTJV.

All materials will be stacked safely and with clear means of access. Scrap, rubbish and debris

frequently and regularly will be removed from the site.

Combustible waste materials and rubbish will not be allowed accumulating within the project

site or in its immediate vicinity. A waste bin will be placed.

Welding and cutting are prohibited near the places of combustible materials, or to the area

where flammable dust, gas or vapor, which are likely to be present or given off.

Regular disposal of rubbish will be maintained as soon as practicable.

Proper maintenance and operation of engines will be controlled emission from gas or diesel

engines.

No person will permit to drive a vehicle without an appropriate license to drive.

All workers must wear proper personal protective equipment.

All field staffs and workers including subcontractor are given a counseling and training to

apprise the HSE requirements.

All related tools and equipment should regularly maintain and check for safe working

condition.

An emergency contact network is a source to avoid negative events such as an accident.

Working area will regularly be inspected for cleanliness (Housekeeping) and safe working

environment.

Regular daily toolbox meeting will be held before start working.

7. ORGANIZATION CHART :

TOA-TOYO

(MAIN CONTRACTOR)

Page 11

Mr. Fukushima Project Manager

Page 12: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

YURTEC

(SUBCONTRACTOR)

8. APPENDIX :

1. Work schedule

2. Inspection & Testing plan (ITP)

3. Inspection form

4. Check list

5. Test Report

Page 12

TTJV Mechanical Engineer

TTJV Electrical Engineer

Surveyor

Mr. SatoM&E Deputy

Manager

Mr. Asai Building Manager

(TTJV)

Mr. RollyBldg QS/QC Chief

Engineer

Mr. Quan HSE Manager

Bldg M&E Chief Engineer

Mr. Bao Anh

Mr. ChauMechanical Engineer

Mr. QuangElectrical Engineer

Mr. SatohM&E Manager

Page 13: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

Appendix - 1

Work schedule

Page 13

Page 14: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

Appendix - 2

Inspection and Test Plan

Page 14

Page 15: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

Appendix - 3

Inspection form

Page 15

Page 16: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

Appendix - 4

Check list

Page 16

Page 17: 2   cm-ms-bld-012 - roof fan & natural ventilator

Doc. Title Method Statement of installation Roof Fan & Natural Ventilator TOA-TOYO JOINT VENTURE

Doc. No CM – MS – BLD - 013 Rev. No. 0 Date Mar. 31, 2011Construction of Port Facilities and Buildings for Cai Mep International Container Terminal

Appendix - 5

Test Report

Page 17