8th, december 2006 1 TPL Dismantling Project – [email protected] TORE SUPRA Association EURATOM-CEA PFC Thermal test program: TPL sector dismantling (Q6A)

Upload: sebastian-alexander

Post on 27-Mar-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 1TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

PFC Thermal test program:

TPL sector dismantling (Q6A)

Page 2: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 2TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

PFC program consists of 2 phases :

Phase A- selection of the spared TPL elements• technique • test process• manpower, cost

Phase B- Cartography of TPL sector• technique• test process• manpower, cost

TPL sector dismantling project

Page 3: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 3TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

- Phase A - Select the best spared PFC by means of the SATIR

test bed upgraded

Output:Selection of spared TPL elements (best-adapted

component)

Manpower : 2 pers.

Experimental : 5 days

Exp. criteria definition : 3 d

Analyse/report : 3 d

Page 4: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 4TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

(SATIR : French acronym for Infra Red Acquisition and Data Processing device)

SATIR facility principle

Its principle is based on the comparison of the surface temperature evolution of the inspected component with that of a “defect-free” reference one. The armour surface temperature is observed by means of a digital infrared camera.

Low heat transfer capability is detected by a slower temperature surface response

Output of the SATIR NDE : Cartography of quantitative criteria DTref is obtained

heat flux

Heatpath

control

Thermal transient method

time (sec.)

0

2

4

6

8

10

0 2 4 6 8 10

Difference (Ref. – Contr. Zone)

Criteria DT_ref_max (°C)

0

20

40

60

80

100

0 2 4 6 8 10

Evol. Tsurf. (°C)

Reference

Controlled (TCR)

Transient monitoring

time (sec.)

Reference.

Controlled zone

Page 5: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 5TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA SATIR control (spared elements)

PFC Program A1) Analyse the former SATIR control results (v.2001)

2) Infrared thermography tests of 23 spared elements 3) Selection of the TPL elements versus flux deposition pattern4) Inspection report

Page 6: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 6TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

- Phase B- Confirm the cartography of TPL sector by means of the LOCKIN Thermography

Output:1) Erosion / Deposition areas definition

2) Location of damaged tile

Manpower : 2 pers.Experimental : 0.5 day

Analyse : 5 daysSupplying : lamps (1KE)

Page 7: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 7TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

LOCKIN technique and the in situ device

The LOCKIN is a method based on propagation in the CFC tiles of modulated thermal waves imposed at the surface of element.

Cartography of Q6A TPL sector

Magnitude and phase-shift of surface temperature vary in case of

thermal properties variation

Time (s)

Sinusoidalthermal

stimulation

CopperCFCFlux (W)

Time (s)Flaw

IR detectorHalogen lamps

Mechanical device

Page 8: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 8TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA Cartography of Q6A TPL sector

phase-shift (TCR)

20° periodicity

Magnitude ()

Dotted lines = max deposit areas, dashed lines = erosion areaResults realised during the last campaign: feb. 2006

PFC Program B

(Use of the same device)

1- Confirm the damaged element (phase-shift) and the erosion / deposit zone (magnitude) by means of LOCKIN

2- SATIR test on damaged element (protect the test zone)

3- Validation : Cutting and metallurgical analyse

Damaged tile ?

Page 9: 1TPL Dismantling Project – alain.durocher@cea.fr TORE SUPRA Association EURATOM-CEA 8th, december 2006 PFC Thermal test program: TPL sector dismantling

8th, december 2006 9TPL Dismantling Project – [email protected]

TORE SUPRAAssociationEURATOM-CEA

Added remarks for phase B:

TPL elements

• Plansee can repair 4 tiles (max) per element = possibility to repair the removed elements (used for analysis of D content).

• Observation of the chemical state of the channel (oxidation layer?) = protection against oxidation after the dismantling of sector (under Ar, N2)

Cartography of Q6A TPL sector