    MM2100 Industrial Estate

    Block NN8-1, West Cikarang,

    Bekasi 17520, Indonesia

    Total Associate : 650 persons

    Cycle Time Down in Door Mirror Line By

    Process Balancing.

    PT. ABC

  • 7/28/2019 1st Winner 2009-1

    2/49

    We are produce and delivered above

    products to PT. HPM

    Product Introduction

  • 7/28/2019 1st Winner 2009-1

    3/49

    ThemeCycle Time Down in Door Mirror Line By

    Process Balancing.

    Circle NamePT. ABC

    Company

    Name

    Introductionof members

    MEMBER :

    Dewi AnggrainiKartika .AY

    Siti Maria

    Oden RudiyanaRiana Melasari

    Introduction of Circle

    Section : Assy 4R Members 4 persons Age Avg 23 years With high professionalism,good performance would have

    created a high productivity

    Circle Introduction

  • 7/28/2019 1st Winner 2009-1

    4/49

    step

    .

    .

    .

    .

    .

    .

    .

    .

    5 8 7

    STANDARDIZATION

    NEXT THEME

    A C T I V I T Y

    CURRENT CONDITION

    ANALYZE & SET A

    TARGET

    ANALYSIS OF KEY

    FACTORS

    IMPROVEMENT PLAN

    IMPROVEMENT

    ACTION

    DECIDE A THEME

    2 3 4

    IMPROVEMENTEVALUATION

    2009 QCC Activity Schedule

  • 7/28/2019 1st Winner 2009-1

    5/49

    Step 1 : Decide the Theme

  • 7/28/2019 1st Winner 2009-1

    6/49

    ONE YEAR POLICY

    To Be No. 1 QCD in All Honda Lock Group Area in 2010.

    To Build High Income Institution by Reduce Inefficient Process.

    CIRCLE THEME

    Cycle Time Down in Door Mirror

    Line By Process Balancing

    DEPARTMENT ACTIVITY PLAN Development & Reduce Inefficient Process

    - Target Value : 15 % Up

    Step 1 : Decide the Theme

  • 7/28/2019 1st Winner 2009-1

    7/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    Total Cycle Time :

    339.94 sec

    Nut

    Insert

    Packing

    & Stopper

    Assy

    Visual

    Check

    & Setting

    Handle

    Pin &

    Spring

    Insrting

    Pin

    Caulking

    Weight

    Counter

    Caulking

    Final

    Inspect

    Total Cycle Time :

    105.76 sec

    Flow Process Assembly Door Mirror

    Flow Process Assembly Out Handle

    RAW

    MATERIAL

    PAINTING

    PROCESS

    ASSEMBLY

    PROCESS

    WARE HOUSE

    FINISH GOODS

    Step 1 : Decide the Theme

  • 7/28/2019 1st Winner 2009-1

    8/49

    Our Team Product are Door Mirror and Out Handle and

    Cycle Time Performance for Both Products is Shown below:

    Product

    Cycle Time

    Current StandardCurrent vs

    Standard%

    DOOR MIRROR

    339.34 273.65 + 65.69 24.01%

    OUT HANDLE

    105.76 96.5 + 9.26 9.6%

    Note: Cycle Time is time needs to make one Finished Goods

    Step 1 : Decide the Theme

    THE VARIANCE OF DOOR MIRROR CYCLE TIME

    STANDARD IS HIGHER THAN OUT HANDLE

  • 7/28/2019 1st Winner 2009-1

    9/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    DOOR MIRROR Line Graphic CYCLE TIME

    0

    10

    20

    30

    40

    50

    60

    CycleTime(Second

    )

    Current 31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.6 37.58 27.4 33.97

    Standard 22.9 25.4 24.9 24.0 23.9 21.6 24.9 30.0 25.5 25.9 24.6

    Bracket

    Tightening

    Turn Light

    Tightening

    Inner Base

    Ass y

    Base Comp

    Ass y

    Seat Base

    Comp Assy

    Mirror

    Group Ass y

    Function

    Check

    Mirror

    Perform

    Check

    Tapping &

    Cord Dim

    Scull Cap

    Assy

    FI &

    Packing

    Step 1 : Decide the Theme

    From Graphic above Shown That Cycle Time Process are not Balance yet

  • 7/28/2019 1st Winner 2009-1

    10/49

    Step 2 : Current ConditionAnalyze & Set a Target

  • 7/28/2019 1st Winner 2009-1

    11/49

    Door Mirror Line Graphic Cycle Time

    56.6

    0

    10

    20

    30

    40

    50

    60

    C/T 31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.6 37.58 27.4 33.97

    Bracket

    Tightening

    Turn Light

    Tightening

    Inner Base

    Assy

    Base

    Comp

    Assy

    Seat Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Perform

    Check

    Tapping &

    Cord Dim

    Scull Cap

    Assy

    FI &

    Packing

    Man Power (MP) 11

    Capacity/Man (Cap/Man) 5.78

    Production/day 457 pcs/Day

    Effective Time 7.2 Hours

    Rate Operation (RO) 90 %

    Sec

    Month : Februari 2009

    Tact

    Time

    Inefficient Cycle Time

    Step 2 : Current Condition Analyze &Set a Target

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Bracket

    Tighten

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Function

    Check

    Mirror

    Check

    Preform

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.9731.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Cycle Time Analyze

  • 7/28/2019 1st Winner 2009-1

    12/49

    Man Power Understanding AnalyzeItem Review Analyze Evaluation

    Evaluator: Mr Andi (Section Head)

    1. Production Quality

    Control (PQC)

    Understanding

    2. NG Part Sample Limit

    Understanding

    3. Process Flow of Part

    to Finished Good

    Understanding 0

    1

    2

    3

    4

    Dewi

    Mela

    Icha

    Kartika

    Oden

    TrisnoTri

    Vivih

    Ema

    Ani

    Sri

    STANDARD

    ACTUAL

    Analyze Skill Map Poin:

    1. Understood Process

    2. Identify Abnormal Process Ability

    3. Able to Teach New Operator

    4. Able to Make Improvement

    1

    23

    4

    There are no man power factor which can affected to

    inefficient cycle time.

    Step 2 : Current Condition Analyze &Set a Target

  • 7/28/2019 1st Winner 2009-1

    13/49

    Part NameDrawing

    Number

    Qty/

    Bucket

    Plastic

    Cover

    Weight

    > 7 kgLoss Time Effect

    TF0-000 SCREW TAPPING INSIDE HANDLE (2AP TF0-E0003-0000 500 NO NO

    TF0-000 SEAT R,BASE TF0-E0401-0000 200 NO NO

    SNB-000 SCREW TAPPING TRUSS 4X14 (2AP) SNB-E0509-0000-D 500 NO NO

    TF0-020 COVER R,BASE TF0-E042F-0200 250 NO NO

    TF0-000 SEAL B TF0-E040A-0000 1000 NO NO

    TF0-000 BASE R,INNER TF0-E0421-0000 30 NO NO

    SFA-000 SCREW WASH M5X12 (2AP) SFA-E0503-0000 30 NO NO

    TF0-020 HOUSING R TF0-E0311-0200 10 YES NOLoss Time 3.55 Sec to

    Remove Plastic

    TF0-000 BOLT STUD M6 TF0-E0109-0000 1000 NO NO

    TF0-000 MIRROR GROUP R,R1400 (D/M) TF0-E0100-0000 80 YES YESLoss Time 2,58 Sec to

    Remove Plastic

    SFA-000 SEAL A (2AP) SFA-E0408-0000 1000 NO NO

    90106-003 SCREW TAPPING TRUSS 4X12 (2AP) 90106-S70-0030 500 NO NO

    TF0-020 BASE R,OUTER TF0-E0423-0200 40 YES NOLoss Time 3.48 Sec to

    Remove Plastic

    TF0-000 BRACKET SUB ASSY RH-R,A/T S/T TF0-E2300-0000 10 NO NO

    90109-003 SCREW TAPPING TRUSS 4X16 (2AP) 90109-S70-0030 500 NO NO

    There are 3 Materials that affect to cycle time Directly.

    Material AnalyzeStep 2 : Current Condition Analyze &Set a Target

  • 7/28/2019 1st Winner 2009-1

    14/49

    All Parts are Received

    by Warehouse

    QC check 100% Parts

    withremove plastic

    cover one by one

    After Checked the Part re-

    cover again and put in to

    bucket.

    WHP QC INCOMING WHP AF

    PLASTIC HOUSING

    30 x 25 CMPLASTIC MIROR

    20 x 25 CM

    PLASTIC OUTER BASE

    12 x 25 CM

    Plastic after used in assembly:

    waste

    Lost time occured while after checked QC Covering the part again

    Door Mirror Parts Flow (Housing, Outer Base, Mirror) AnalyzeStep 2 : Current Condition Analyze &Set a Target

  • 7/28/2019 1st Winner 2009-1

    15/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    SeatBase

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Bracket Tigtening Process 31.87

    1. Take a Housing 1.47

    2. Open Housing Cover 3.55

    3. Put into Jig 1.25

    4. Assy Bracket to Housing 6.45

    5. Hand Togle Down 1.39

    6. Bottom screw tightening 6.21

    7. Re-set hand togle position 1.10

    8. Inside screw tightening 8.52

    9. Take and transfer 1.93

    Base Inner Tightening 24.33

    1. Put into Jig 1.74

    2. Take a Base Outer 1.49

    3. Open Base Outer Cover 2.58

    4. Put Base Outer to Jig 3.97

    5. Base Inner Assy 3.25

    6. Screw Tightening 8.36

    7. Take and Transfer 2.94

    Mirror Group Assy 19.09

    1. Put into Jig 1.60

    2. Date Stamp 4.84

    3. Take a Mirror 1.32

    4. Open Mirror Cover 3.48

    5. Setting a Mirror 2.97

    6. Curve Check 1.91

    7. Take and Transfer 2.97

    Process of removing plastic cover are in process no: 1, 3 and 6

    Line Process which affected by plastic cover AnalyzeStep 2 : Current Condition Analyze &Set a Target

  • 7/28/2019 1st Winner 2009-1

    16/49

    4M+1E

    ANALYZEITEM VERIFICATION GEMBA JUDGE

    MAN

    Understanding of

    Production Quality Control

    ( PQC ) is Weak

    Operator understood PQC

    Step1 April 2009

    Understanding of Part NG

    Sample Limit is Weak

    Operator understood about

    Part NG Sample Limit1 April 2009

    Understanding of process

    flow part to goods is weak

    Operator understood about

    Part Process Flow to Goods1 April 2009

    MACHINE Line Lay out is long There are 11 Process 2 April 2009 X

    MATERIALPacking standart is not

    good2 April 2009 X

    METHODEThere are idle time in some

    process

    Cycle Time Graphic is not

    Balance Yet2 April 2009 X

    ENVIRONTMENT - - -

    Part Covered by plastic andStandar Packing is heavy

    = OK (is Not Problem Factor) X = Problem Factor

    4M + 1E AnalyzeStep 2 : Current Condition Analyze &Set a Target

  • 7/28/2019 1st Winner 2009-1

    17/49

    DOOR MIRROR Line Graphic CYCLE TIME

    0

    10

    20

    30

    40

    50

    60

    CycleTime(Seco

    nd)

    Current 31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.6 37.58 27.4 33.97

    Standard & Target 22.9 25.4 24.9 24.0 23.9 21.6 24.9 30.0 25.5 25.9 24.6

    Bracket

    Tightening

    Turn Light

    Tightening

    Inner Base

    Assy

    Base

    Comp

    Assy

    Seat Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Perform

    Check

    Tapping &

    Cord Dim

    Scull Cap

    Assy

    FI &

    Packing

    Current

    C/T :339.34

    Standard &

    Target

    C/T :

    273.65

    CYCLE TIME DOWN TARGET

    339.34273.65

    0

    50

    100

    150

    200

    250

    300

    350400

    Before Target

    Second

    Step 2 : Current Condition Analyze &Set a Target

    TargetDown 19.35%

  • 7/28/2019 1st Winner 2009-1

    18/49

    POINT OF REVIEW PARAMETER BEFORE TARGET

    Q Keep Zero Claim ZERO CLAIM Zero Claim Zero Claim

    C Reduce Loss Cost ProcessReduce Cycle

    Time339,34 second 273,65 Second

    D Level up in Support Deliveryto Customer.

    Production

    Capacity is

    Stabil

    10.075Pcs/Month

    10.075Pcs/Month

    SReduce risk of accident by

    reducing packing standard.

    Reduce Weight

    of Packing

    Standard

    Weight =

    19,26Kg

    63.6% of

    Weight Down

    => 7 Kg*)

    M Optimize Job DescriptionOperator

    Reduce quantityMP

    11 Man 7 Man

    EReduce Waste of Production

    Process

    Re-Use of

    Plastic Cover

    Material

    Become Waste

    Re-Use in

    Another

    Process

    *) Female Operator Canno t Lift Up Buc ket Over Than 7 Kg

    Step 2 : Current Condition Analyze &Set a Target

  • 7/28/2019 1st Winner 2009-1

    19/49

    Step 3 : Analysis of Key Factors

  • 7/28/2019 1st Winner 2009-1

    20/49

    Need 11

    manpower

    Unbalance

    d

    Process

    MACHINE MATERIAL

    ENVIRONMENT METHODE MAN

    D/M Line is

    Not yet

    Efficient.

    Ineficient

    Process

    There are

    Some idle

    time

    packingStandard are

    not good

    Packing

    heavy

    Part

    Covered by

    plastic

    No packing

    standartLine Setting

    Not Good

    No Problem

    Factor

    No Problem

    Factor

    Cycle

    Time

    is

    High

    Step 3 : Analysis of Key Factors

  • 7/28/2019 1st Winner 2009-1

    21/49

    Step 4 : Improvement Plan

  • 7/28/2019 1st Winner 2009-1

    22/49

    FACTOR PROBLEMIMPROVEMENT

    PLANHOW PIC SCHEDULE

    MATERIAL

    PART COVERED

    WITH PLASTIC

    PLASTIC COVER

    CHANGE TO

    PARTITION CHANGESTANDARD

    PACKING

    DM ASSY-

    QC-PE

    MEI JUN

    2009

    STANDART

    PACKING

    HEAVY

    REDUCE WEIGHT

    STANDARD

    DM ASSY-

    QC-PC

    MEI JUN

    2009

    METHODUNBALANCED

    PROCESS

    REDUCE LOSS TIME

    PROCESS PROCESS

    BALANCING

    DM ASSY-

    PE

    JUN AUG

    2009

    MACHINE

    DOOR MIRROR

    LINE PROCESSNEED 11 MAN

    POWER

    MODIFICATION LINELAYOUT

    DM ASSY-PE

    JUN AUG2009

    Step 4 : Improvement Plan

    St 4 I t Pl (St d d P ki Ch )

  • 7/28/2019 1st Winner 2009-1

    23/49

    PART

    NAMEBEFORE

    PACKING CHANGE

    PLANDIMENTION Reason

    HOUSING

    (4,24 Kg)

    10 Pcs

    Partision Size :

    = 200 mm X 110 mm X 300mmPartision Material : Sponge

    Bucket Capacity : 10 Pcs

    Weight: 4,8 Kg

    Construction : 1 Level (5 Row 2 Column) 1. Partition is

    Strong and

    easy to

    Construct

    2. More

    Effective to

    Prevent

    Scratch

    3. Caneliminate loss

    time of plastic

    removal

    BASE

    OUTER

    (6,56 Kg)

    40 Pcs

    Partision Size := 200 mm X 55 mm x 150 mm

    Partision Material : Sponge

    Bucket Capacity : 20 Pcs

    Weight: 3,28 Kg

    Construction : 1 Level (10 Row 2

    Column)

    MIRROR

    (19,26 Kg)

    80 Pcs

    Partision Size :

    = 15 mm X 225 mm x 150mm

    Partision Material : Sponge

    Bucket Capacity : 30 Pcs

    Weight: 6,76 Kg

    Construction : 1 Level (15 Row 2Column)

    580

    mm

    400 mm

    580

    mm

    400 mm

    300

    mm

    450 mm

    Step 4 : Improvement Plan (Standard Packing Change)

  • 7/28/2019 1st Winner 2009-1

    24/49

    0

    10

    20

    30

    40

    50

    60

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    1 2 3 4

    Process Merger Plan is Based on Low cycle time process

    Step 4 : Improvement Plan (Process Balancing)

  • 7/28/2019 1st Winner 2009-1

    25/49

    Step 5 : Improvement Action

    St 5 I t A ti (P ki Ch )

  • 7/28/2019 1st Winner 2009-1

    26/49

    PART NAME BEFORE AFTER STANDARD PACKINGIMPROVEMENT

    REVIEW

    HOUSING

    Before:

    Cover PlastickQuantity 10 pcs (4.24 Kg)

    After :

    Cover PartitionQuantity 10 pcs (4.8 Kg)

    QC JUDGE:Packing can

    prevent scratch

    NG

    Cost:

    Rp 7,600,000.-

    BASE

    OUTER

    Before :Cover Plastic

    Quantity 40 pcs (6.56 Kg)

    After :

    Cover PartitionQuantity 20 pcs (3.28Kg)

    MIRROR

    Before :

    Cover Plastic

    Quantity 80 pcs (19.26 Kg)

    After :

    Cover PartitionQuantity 30 pcs (6.76Kg)

    Step 5 : Improvement Action (Packing Change)

    St 5 I t A ti (P ki Ch Eff t)

  • 7/28/2019 1st Winner 2009-1

    27/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Bracket Tigtening Process Before After

    1. Take a Housing 1.47 1.47

    2. Open Housing Cover 3.55 -

    3. Put into Jig 1.25 1.25

    4. Assy Bracket to Housing 6.45 6.45

    5. Hand Togle Down 1.39 1.39

    6. Bottom screw tightening 6.21 6.21

    7. Re-set hand togle position 1.10 1.10

    8. Inside screw tightening 8.52 8.52

    9. Take and transfer 1.93 1.93

    TOTAL 31.87 28.32

    Base Inner Tightening Before After

    1. Put into Jig 1.74 1.74

    2. Take a Base Outer 1.49 1.49

    3. Open Base Outer Cover 2.58 -

    4. Put Base Outer to Jig 3.97 3.97

    5. Base Inner Assy 3.25 3.25

    6. Screw Tightening 8.36 8.36

    7. Take and Transfer 2.94 2.94

    TOTAL 24.33 21.75

    Mirror Group Assy Before After

    1. Put into Jig 1.60 1.60

    2. Date Stamp 4.84 4.84

    3. Take a Mirror 1.32 1.32

    4. Open Mirror Cover 3.48 -

    5. Setting a Mirror 2.97 2.97

    6. Curve Check 1.91 1.91

    7. Take and Transfer 2.97 2.97

    TOTAL 19.09 16.61

    Process of removing plastic cover are in process no: 1, 3 and 6

    Down 11.14%

    Down 10.6% Down 18.23%

    Step 5 : Improvement Action (Packing Change Effect)

    Step 5 : Improvement Action (Packing Change Effect)

  • 7/28/2019 1st Winner 2009-1

    28/49

    PLASTIC HOUSING

    30 x 25 CM

    PLASTIC MIROR

    20 x 25 CM

    PLASTIC OUTER BASE

    12 x 25 CM

    Plastic after used :

    Re-use Plastic to Cover

    J09 Key Set (2R)

    Product : Motorcycle Part

    Type : J09 Key Set Customer : Honda Thailand Packing Condition : Covered by Plastic

    to Prevent Scratch

    Plastic Source : Supplier

    Step 5 : Improvement Action (Packing Change Effect)

    Visibilities Studies to Re-Use Plastic Cover

    St 5 I t A ti (B l i P )

  • 7/28/2019 1st Winner 2009-1

    29/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Turn Light Tightening 25.811. Light Assy 10.21

    2. Screw & Marking 11.47

    3. Take and Transfer 4.13

    Base Inner Tightening 24.331. Put into Jig 1.74

    2. Take a Base Outer 1.49

    3. Open Base Outer Cover 2.58

    4. Put Base Outer to Jig 3.97

    5. Base Inner Assy 3.25

    6. Screw Tightening 8.36

    7. Take and Transfer 2.94

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    25.81 24.33

    Before merger

    Turn Light & Inner Base Tightening 41.69

    1. Light Assy 10.21

    2. Screw & Marking 11.47

    3. Take and Transfer eliminated

    4. Put into Jig eliminated

    5. Take a Base Outer 1.49

    6. Open Base Outer Cover eliminated

    7. Put Base Outer to Jig 3.97

    8. Base Inner Assy 3.25

    9. Screw Tightening 8.36

    10. Take and Transfer 2.94

    After merger process and

    Step 5 : Improvement Action (Balancing Process)

    St 5 I t A ti (P M difi ti )

  • 7/28/2019 1st Winner 2009-1

    30/49

    Step 5 : Improvement Action (Process Modification)

    1. Modify Jig Light & Inner Tightening 2. Relay out Working Table

    Base Inner Tightening Jig Turn Light Tightening Jig

    Light Inner Tightening Jig

    There are 2 jigs in Turn Ligh & Base Inner Tightening

    (A/T & R/C) Process:

    Special for A/T Type

    Turn Ligh Tightening Jig added with Base Inner &

    Base Outer Tightening Jig

    For R/C Type, Base Inner Tigh Jig is not modified

    Set Turn Ligh and Bases Inner Driver Move:

    Driver(Turn Ligh) Cannt reach ScrewFeeder 4x12 and Base Inner Location

    Driver(Base Inner) Cannt Reach Screw

    Feeder 4x14 & Turn Ligh Location

    St 5 I t A ti (P M difi ti )

  • 7/28/2019 1st Winner 2009-1

    31/49

    Step 5 : Improvement Action (Process Modification)

    Eliminate Idle Working Table

    Turn Light

    Tightening

    Process Table is

    disposed,andnext process

    move a head.

    So

    The Linebecome Shortly.

    St 5 I t A ti (B l i P )

  • 7/28/2019 1st Winner 2009-1

    32/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Base Comp Assy 58.591. Put into Jig 3.43

    2. Base Comp Join 5.84

    3. Screw Tightening 16.68

    4. Cover Base Assy 5.83

    5. Take and Transfer 3.97

    Seat Base Comp Assy 12.561. Put into Jig 2.5

    2. Seat Base Assy 7.78

    3. Take and Transfer 2.28

    Before merger

    Base Comp & Seat BaseAssy 41.69

    1. Put into Jig 3.43

    2. Base Comp Join 5.84

    3. Screw Tightening 16.68

    4. Cover Base Assy 5.83

    5. Take a Base Outer -

    6. Put into Jig -

    7. Seat Base Assy 7.78

    8. Take and Transfer 2.28

    After merger process and

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    35.75 12.56

    Seat Base Assy Process move into Base Comb Tightening Proess

    to Stabilize Cycle Time.

    To joining Seat

    Base Assy

    Process into Base

    Comb Tightening

    Process needs &

    Seat Base Assy

    needs to re-lay out

    working table anddispose Seat Base

    Comp Assy Table.

    Step 5 : Improvement Action (Balancing Process)

    St 5 I t A ti (P M difi ti )

  • 7/28/2019 1st Winner 2009-1

    33/49

    Base Comp Tight &

    Seat Base Comp

    Assy

    Step 5 : Improvement Action (Process Modification)

    Re-Layout Seat Base Assy Process

    1. Seat Base Comp Assy Table is Eliminated

    2. Base Comp Tightening Process Move to Seat Base

    Position.

    3. Buffer Table is Added in Base Comp Tightening Table .

    St 5 I t A ti (B l i P )

  • 7/28/2019 1st Winner 2009-1

    34/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Mirror Group Assy 10.771. Put into Jig 1.60

    2. Date Stamp -

    3. Take a Mirror 1.32

    4. Open Mirror Cover -

    5. Setting a Mirror 2.97

    6. Curve Check 1.91

    7. Take and Transfer 2.97

    Before merger

    Bracket Tightening 40.811. Take a Housing 1.47

    2. Open Housing Cover eliminated

    3. Put into Jig 1.25

    4. Assy Bracket to Housing 6.45

    5. Hand Togle Down 1.39

    6. Bottom screw tightening 6.21

    7. Re-set hand togle position 1.10

    8. Inside screw tightening 8.52

    9. Date Stamp 7.84

    10. Take and Transfer 1.93

    11. Stamp & Caulking Check 4.65

    After (movement process)

    To Stabilize Process, Stamp Date Process is moved toBracket Tightening Process.

    Mirror

    Group

    Assy

    19.09

    Moved to

    Bracket

    Tightening

    Process

    Step 5 : Improvement Action (Balancing Process)

    Step 5 : Improvement Action (Balancing Process)

  • 7/28/2019 1st Winner 2009-1

    35/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Mirror Group Assy 10.771. Put into Jig 1.60

    2. Date Stamp

    3. Take a Mirror 1.32

    4. Open Mirror Cover -

    5. Setting a Mirror 2.97

    6. Curve Check 1.91

    7. Take and Transfer 2.97

    Function Check 34.381. Put into Jig 3.73

    2. Cord Assy 6.11

    3. Push Button 19.64

    4. Take, Mark & Transfer 4.90

    Before merger

    Function Check 45.151. Put into Jig 1.60

    2. Date Stamp

    3. Take a Mirror 1.32

    4. Open Mirror Cover eliminated

    5. Setting a Mirror 2.97

    6. Curve Check 1.91

    7. Take and Transfer 2.97

    8. Put into Jig 3.73

    9. Cord Assy 6.11

    10. Push Button 19.64

    11. Take, Mark & Transfer 4.90

    After merger process andJoin to No1 process

    Mirror

    Group

    Assy

    Function

    Check

    19.09 34.38

    Join to No1 process CheckFunction

    Process

    is Joined

    to Mirror

    Group

    Assy

    Process

    Step 5 : Improvement Action (Balancing Process)

    Step 5 : Improvement Action (Balancing Process)

  • 7/28/2019 1st Winner 2009-1

    36/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Mirror Check Preform 56.601. Put into Jig 3.5

    2. Cord Assy 4.15

    3. Push Button 3.64

    4. Check M/C Preform 39.67

    5. Take, Mark & Transfer 5.64

    Tapping & Cord Dim 37.581. Put into Jig 2.3

    2. Test Cord Length 5.25

    3. Seal A Assy 4.65

    4. Tapping 13.32

    5. Gap Check 4.17

    6. Bending Check 4.2

    7. Take & Tansfer 3.69

    Before merger

    Mirror Assy andCheck Preform

    54.75

    1. Put into Jig 3.5

    2. Cord Assy eliminated

    3. Push Button 3.64

    4. Check M/C Preform 39.67

    5. Take, Mark & Transfer 5.64

    6. Put into Jig 2.3

    7. Test Cord Length eliminated

    8. Seal A Assy eliminated

    9. Tapping eliminated

    10. Gap Check eliminated

    11. Bending Check eliminated

    12. Take & Tansfer eliminated

    After merger process and

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    56.60 37.58

    Move Seal AJig,

    Tapping

    In This Joining

    Process, Checker

    Machine iddle Time

    is Used to do Next

    Process.

    Step 5 : Improvement Action (Balancing Process)

    Step 5 : Improvement Action (Balancing Process)

  • 7/28/2019 1st Winner 2009-1

    37/49

    Bracket

    Tighten

    Turn

    Light

    Tighten

    Inner

    Base

    Assy

    Base

    Comp

    Assy

    Seat

    Base

    Comp

    Assy

    Mirror

    Group

    Assy

    Function

    Check

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    31.87 25.81 24.33 35.75 12.56 19.09 34.38 56.60 37.58 27.40 33.97

    Skull Cap Assy 27.401. Put into Jig 3.13

    2. Take a Skull & Visual Check 8.98

    3. Skull Assy 7.56

    4. Gap Check 3.86

    5. Take & Transfer 3.87

    Tapping & Cord Dim 33.971. Part Completeness Check 5.21

    2. Apperance Check 3.56

    3. Mirror Check & Wash 4.23

    4. Visual Check 9.47

    5. Mirror Assy Shake 2.21

    6. Take a miramat Bag 2.01

    7. Put in 2.94

    8. Bag Close 1.38

    9. Place to Bucket 2.96

    Before merger

    Tapping & Cord Dim 48.031. Put into Jig 3.13

    2. Take a Skull & Visual Check 8.98

    3. Skull Assy 7.56

    4. Gap Check 3.86

    5. Take & Transfer eliminated

    6. Part Completeness Check 5.21

    7. Apperance Check 3.56

    8. Mirror Check & Wash 4.23

    9. Visual Check eliminated

    10. Mirror Assy Shake 2.21

    11. Take a miramat Bag 2.01

    12. Put in 2.94

    13. Bag Close 1.38

    14. Place to Bucket 2.96

    After merger process and

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    27.40 33.97

    Skull CapAssy is

    Joined in to

    FI & Packing

    Process.

    Step 5 : Improvement Action (Balancing Process)

    Step 5 : Improvement Action (Merger Process Effect)

  • 7/28/2019 1st Winner 2009-1

    38/49

    PROCESSBEFOREMERGER

    (in second)

    AFTERMERGER

    (in second)

    CYCLE TIME

    VARIANCEREMARKS REVIEW

    Bracket Tightening 31.87 40.81 Up 8.94 Additional ProcessFrom No

    Cost =

    Rp 16,073,400Turn Light Tightening 25.81

    41.69 Down 8.45

    Inner Base Assy 24.33 Base Comp Assy 35.75

    43.53 Down 4.78Cycle Time

    Before

    = 339.34 Second

    Seat BaseComp Assy

    12.56

    Mirror Group Assy 19.0945.15 Down 8.32 Function Check 34.38

    Cycle Time After= 273.96 Second

    Mirror Check Preform 56.6054.75 Down 39.43 Tapping & Cord

    Dimention37.58

    Skull Cap Assy 27.448.03 Down 13.34Final Inspect &

    Packing33.97

    T O T A L 339.34 273.96 Down 65.38 (19.26%)

    Step 5 : Improvement Action (Merger Process Effect)

    Step 5 : Improvement Action (Visual Check)

  • 7/28/2019 1st Winner 2009-1

    39/49

    Gomi

    Benang

    Spit/Gumpalan Cat

    Sagging

    Orange Peel

    Cat Tipis

    Fading/Un matching colour pada posisi tertentu

    Matching NG/beda warna

    Gelombang Scrath

    Bari

    Gelombang

    Weld

    Shape/berubah bentuk, tumpul

    PAINTING

    MATERIAL

    Before NG Material, Painting and NG Process Items is re-check inFinal Inspection Assembly (D/M & O/H)

    After Final Inspection Check only For Assy Process NG Item ,

    ex: Scrath

    Step 5 : Improvement Action (Visual Check)

    Visual Check Item Determination

  • 7/28/2019 1st Winner 2009-1

    40/49

    Step 6 : Improvement Evaluation

    Step 6 : Improvement Evaluation

  • 7/28/2019 1st Winner 2009-1

    41/49

    Part after check is Packed

    in to Bucket with PartitionAll Parts are Received

    by Warehouse

    QC check 100% Parts

    and Remove Plastic

    Cover

    Part Processed in

    Assembly.

    All Parts are Received

    by Warehouse

    QC check 100% Parts

    withremove plastic

    cover one by one

    After Checked the Part re-

    cover again and put in to

    bucket.

    Operator remove cover

    again in line before

    process

    WHP QC INCOMINGWHP AF

    WHP QC INCOMING WHP AF

    After

    Before

    Lost Time of Remove Plastic Cover in Assembly is eliminated.

    Step 6 : Improvement Evaluation

    New Flow Material Receiving

    Step 6 : Improvement Evaluation

  • 7/28/2019 1st Winner 2009-1

    42/49

    PLASTIC HOUSING

    30 x 25 CM

    PLASTIC MIROR

    20 x 25 CM

    PLASTIC OUTER BASE

    12 x 25 CM

    Plastic after used :

    waste

    After

    Before

    PLASTIC HOUSING

    30 x 25 CM

    PLASTIC MIROR

    20 x 25 CM

    PLASTIC OUTER BASE

    12 x 25 CM

    Plastic after used :

    J09 Key Set

    Step 6 : Improvement Evaluation

    Step 6 : Improvement Evaluation

  • 7/28/2019 1st Winner 2009-1

    43/49

    Step 6 : Improvement Evaluation

    Item Before After Before vs After

    MP Quantity 11 persons 6 persons 5 personsLabour Cost Rp. 13.200.000 Rp. 7.200.000 Rp. 6.000.000

    Invest

    ment

    Partion - Rp. 7.600.000Rp. 23.673.400

    Re-Layout - Rp. 16.073.400BEP

    = 4 month

    C/T (sec)TactTime

    (sec)MP RO

    Cap/Man

    (hr)

    Cap/Day

    (7.2hrs)

    Cap/

    Month

    Before 339.34 56.60 11 90% 5.78 458 10.075

    After 273.96 54.75 6 90% 10.78 473 10.415

    Before vs

    After

    Down

    19.2%

    Down

    3.26%

    Down 5

    persons-

    Up

    86.6%Up 3.2% Up 3.2%

    Break Event Point Analyze

    Production Capacity Analyze

    Total Investment for This Improvement is Rp. 23.673.400. And It Will

    Reach BEP for 4 Months with Cost Down/Month is Rp. 6.000.000.

    Step 6 : Improvement Evaluation

  • 7/28/2019 1st Winner 2009-1

    44/49

    POINT OF REVIEW PARAMETER BEFORE TARGET RESULTEVALUA

    TION

    Q Keep Zero Claim NGPROCESS

    Zero Claim Zero Claim Zero Claim C

    Reduce Loss Cost

    Process Cycle Time

    339,34

    second

    273,65

    Second

    273,96

    Second D Level up inSupport Delivery

    to Customer.

    ProductionCapacity is

    Stabil

    10.075Pcs/Month

    10.075Pcs/Month

    10.415Pcs/Month

    (Up 3.37%)

    S

    Reduce risk of

    accident by

    reducing packing

    standard.

    Weight of

    Packing

    Standard

    Weight =

    19,26Kg

    63.6% of

    Weight

    Down => 7

    Kg

    30 Pcs =

    6,76 Kg M

    Optimize Job

    Description

    Operator

    MP 11 Man 7 Man 6 Man E

    Reduce Waste of

    Production

    Process

    Re-Use of

    Plastic Cover

    Material

    Become

    Waste

    Re-Use in

    Another

    Process

    J09 Key

    Set

    Packing

    Step 6 : Improvement Evaluation

  • 7/28/2019 1st Winner 2009-1

    45/49

    Step 7 : Standardization

    Step 7 : Standardization

  • 7/28/2019 1st Winner 2009-1

    46/49

    Step 7 : Standardization

    MP TACT TIME CAP/MAN CAP/DAY RO

    6 54.75 10.95 pcs 473 pcs 90%

    Bracket

    Tighten

    Turn

    Light

    & BaseTighten

    Base

    Comp &

    Seat BaseAssy

    Mirror

    Assy &

    FunctionCheck

    Mirror

    Check

    Preform

    Tapping

    & Cord

    Dimention

    Skull

    Cap

    Assy

    Final

    Inspect

    & Packing

    1. New Line Door Mirror Process is Set for 6 Man Power

    Part after check is Packed

    in to Bucket with Partition

    All Parts are Received

    by Warehouse

    QC check 100% Parts and

    Remove Plastic Cover

    Part Processed in

    Assembly.

    WHP QC INCOMING WHP AF

    2. Part Plastic Cover removed at QC Incoming.

    Re-use Plastic to

    Export Packing J09 Key

    Set (2R)

  • 7/28/2019 1st Winner 2009-1

    47/49

    Step 8 : Next Theme

    Step 8 : Next Theme

  • 7/28/2019 1st Winner 2009-1

    48/49

    Cycle Time Down in Out Handle Line.

    Our Team Next Theme is:

    PRODUCTCYCLE TIME (Second)

    CURRENT STANDARD VARIANCE %

    Door Mirror

    273.96 273.65 0.31 0.11%

    Outer Handle105.76 96.5 9.26 9.6%

    Step 8 : Next Theme

    Note : Door Mirror Cycle Time Process is Successfully Down in This Year QCC

  • 7/28/2019 1st Winner 2009-1

    49/49

    Thank youfor your attention