1a 3 duncan wb rehabilitation in challenging environments
TRANSCRIPT
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
1/12
Hydropower rehabilitationin a challenging
institutional environment
Reynold DuncanWorld Bank Africa Energy Group
Workshop on Rehabilitation of
Hydropower
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
2/12
Outline
Lessons LearnedGhana Sixth Power Project ( Akosombo)
Zambia Power Rehabilitation Project
(Kafue Gorge and Kariba North)Uganda Second and Third PowerProjects (Owen Falls/ Nalubale)
Iraq Emergency (Dokan andDerbandikhan)
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
3/12
Lessons Learned
The urgency of rehabilitation usually results infinancing decisions taking place prior toadequate investigations and designs
Limited knowledge by the operators and lack of
proper monitoring and inspection duringoperation contribute to lack of preparedness oncommencement of rehabilitation
Cost overruns and implementation delays can
only be mitigated if the necessary preparatorywork is conducted ahead of investment
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
4/12
Lessons Learned ctd
Financiers should help advance technicalassistance for proper project preparation
Financiers and Borrowers should be flexibleto accepts changes in design along the way
Rehabilitation should consider the entirepower plant and with repowering possibilitiesLimited operator knowledge and lack of
proper monitoring during operationexacerbate poor preparation for rehabilitation
Consultants alone do not have the necessarycompetencies to conduct the necessaryinvestigations
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
5/12
Akosombo
First HPP: four of the units (588 MW, with15%overload capacity commissioned1965);additional two units (324MW, with15% overloadcapacity commissioned 1972)
Credit approved 1990 to retrofit the plantincluding the reconditioning of the six runners,rehabilitation of other turbine parts, new
governors, new stator core windings for first fourgenerators and rewinding of other two, newequipment for the overhaul of the electro-mechanical systems and the supply of spare
parts for the five year operation
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
6/12
Akosombo ctd
The proposed project was prepared by VRA withthe assistance of consultants
The condition of the Akosombo had beeninvestigated by several external experts
A manufacturer and consultant had carried outindependent studies to compare replacement andoverhaul of the turbine runners and concluded thatthe benefit of replacement would be marginal
Above confirmed by an operating utility
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
7/12
Akosombo ctd
Credit was expected to be fully utilized end-1995but work had just commenced
Original technical solution of refurbishing the
hydro turbine runners at Akosombo abandonedafter one refurbished unit-expected efficiencygains not obtained
Decided to replace the runners instead and IDA
financed the design of the runners and modeltesting
Credit closed with only 28% disbursed;implementation of the new design financed by
others
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
8/12
Kafue Gorge and Kariba North ctd
Approved February 1998; first WB project in 20 years Rehabilitation of Victoria Fall (108MW), Kariba North
Bank (4 x 150 MW) and Kafue Gorge (6 x 150 MW) Original project design replacement of parts Later realized capacity increases at Kariba North
(120 MW) and Kafue Gorge (90 MW) were possible Kafue consultants had decided not run tests to
determine most probable scope but decide duringimplementation when machines opened
Repowering was least cost option of increasing
capacity (at $200K compared to $1 m at the time) Credit was closed prior to the repowering works,
which were financed by others
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
9/12
Owen Falls
The plant had been in operation since 1954 Second Power Project Credit approved March 1985 Scope quite complete: underwater repairs, power
station repairs, re-waterproofing powerhouse, dam gateequipment, transformers and ancillary equipment, stator
windings upgrade, refurbishment or replacement of allmoving parts, modernization of I&C, upgrading the 10units from 15 to 18 MW
Original scope omitted dam rehabilitation The timetable too optimistic considering this was the
only power plant and UEB had not undertaken majorconstruction in several years Start-up delayed by 2.5 years due to country-wide strife Original completion date 1990, actual completion seven
years behind schedule
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
10/12
Owen Falls ctd
(the dam)
Dam suffered alkali-aggregate reaction,designed without proper drainage, and a risk toOwen Falls and all future hydro development,all of which would be downstream
Owen Fall Extension (Kiira Units 1 and 2)approved 1987 included dam rehabilitation butcost overruns caused further postponement
Supplemental loan approve 2000to rehabilitatethe dam
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
11/12
Dokan and Derbandikhan Emergency
Hydropower Project (ongoing)
Dokan: 400 MW, commissioned 1979
Derbandikhan 249 MW, commissioned 1986
Project design combined urgent repairs and technical
assistance for subsequent rehabilitation Urgent repairs due to years of neglect – financing and
knowledge shortfalls
Urgent repairs include the entire power plants, from the
dams to substations Technical assessment will comprise detailed
assessment of the plants’ condition, dam safety and
feasibility of repowering
-
8/20/2019 1A 3 Duncan WB Rehabilitation in Challenging Environments
12/12
Thank You