173704485 merc time and action calender
TRANSCRIPT
-
8/13/2019 173704485 Merc Time and Action Calender
1/10
Time and Action
Calender
-
8/13/2019 173704485 Merc Time and Action Calender
2/10
Usually the delivery of goods closed between a
buyer and an export house is :
Ex-country, or
AC At consolidator , FOB seaor
AC-at consolidator , FOB air
So Backward calculations need to be done to work
out the complete planning of the garment/ goodsdelivery
-
8/13/2019 173704485 Merc Time and Action Calender
3/10
Ex country- date when goods need to exit
the country
AC date- at consolidator date..this can be:
FOB sea or FOB air
PCD- Planned cut date
-
8/13/2019 173704485 Merc Time and Action Calender
4/10
Types of samples :
Proto sample / PD sample, mockup.
Salesman samples/ internet / marketing/photo
samples 1stfit sample
2ndand 3rdfits incorporating the comments/changes and corrections
PP /sealer sample TOP sample
-
8/13/2019 173704485 Merc Time and Action Calender
5/10
Approval terminologies
Strikeoffs s/o
Labdips l/d
Desklooms
Hyde policy
-
8/13/2019 173704485 Merc Time and Action Calender
6/10
T n a Example
Style- Suede skirt with polyester dtm lining,
invisible zipper and metal hook and eye
AC- 10/10 sea port chennai Order qty- 2500 pcs
Leather- italian goat suede color beige
Lining and trims
local sourced Factory located in- Delhi
-
8/13/2019 173704485 Merc Time and Action Calender
7/10
Order and inhouse dates for smpl and bulk
Trims
Leather, fabric, packing materials
Minimums n leadtimes
FIS SHEETS Testing dates- FPT, GPT
-
8/13/2019 173704485 Merc Time and Action Calender
8/10
Inspection dates
Pilot
Midlines/ inlines
Final
Documentation
-
8/13/2019 173704485 Merc Time and Action Calender
9/10
T& AAC sea 10-Oct
ex fty 5-Oct ex country-5
final inspection 30-Sep ex fty-5
midline inspection 18-Sep final insp-12
TOP 10-Sep pilot inspn+1
pilot inspection 9-Sep pcd+4
PCD planned cut date 5-Sep final inspection -25
size set approval 31-Aug pcd-5
fit approval 26-Aug pcd-10
leather inhouse 26-Aug pcd-10
-
8/13/2019 173704485 Merc Time and Action Calender
10/10
leather shade lot approval 2-Sep pcd-3
trim inhouse 26-Aug pcd-10
trim approval 2-Sep pcd-3
leather ordering (includes
transit also) 22-Jul leather inhouse -35
leather color approval to
order 17-Jul leather ordering-5
trim ordering 27-Jul trim inh -30
trim approval from buyer
to order 22-Jul trim order-5
order confirmation on
style, qty, color 17-Jul exfty-80
first proto sending 7-Jul first /p recd+10
first tech pack receipt 27-Jun