173 feasibility study of micro hydro power in nepal

49
RESEARCH REPORT ON “FEASIBILITY STUDY OF MICRO HYDROPOWER IN NEPAL BY VAIBHAV PANDEY Under graduating student, Research coordinator Nepal Engineering College, nec 6/20/2011

Upload: anil-kunwor

Post on 29-Nov-2014

465 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: 173 Feasibility Study of Micro Hydro Power in Nepal

RESEARCH REPORT ON “FEASIBILITY STUDY OF MICRO HYDROPOWER IN NEPAL

BY VAIBHAV PANDEY Under graduating student, Research coordinator Nepal Engineering College, nec 6/20/2011

Page 2: 173 Feasibility Study of Micro Hydro Power in Nepal

The research was strongly

supported by Nepal

Engineering College

And

It was an initiative of Centre

for Advanced Research and

Obligatory Learning,

CAROL

Page 3: 173 Feasibility Study of Micro Hydro Power in Nepal

This page is intentionally left

blank

Page 4: 173 Feasibility Study of Micro Hydro Power in Nepal

SALIENT FEATURE

Gross Head : 30 m

Measured Flow & Date : 204 lps, May-11, 2009

Least Flow : 201.34 lps

Design discharge : 154 lps

Name of the River : Lower Puwa Khola

Power Output : 25 kW

Beneficiary Households (Nos) : 259 HH

Length of Power Canal (m) : 1071 m

1015 Stone masonry (1:4) C/S

56 m RCC Canal

Power House : Internal dimension (5x 7.95 x 2.7, m)

Stone masonry with mud mortar

Type of Turbine : Cross flow 38 kW Shaft Output

Type of Generator : 50 kVA, 3 Phases, Synchronous, Brushless

Type of Load Controller : ELC 25 kW with Ballast tank 30 kW

Penstock Type & Length : M.S 280 mm ID, 3 mm thickness – 66.0 m

Length of T & D Lines (m) : 24.008 km (single length)

H.T line 5.834 km

L.T 3 phase 7.824 km

L.T 1 phase 10.6 km

Composite Line 4.734 km

Transformer : 25 kVA -2 nos, Setp up, Setup down

Road head Name : Nepaltar, Puwa khola bazaar (Ilaam)

Distance (km) : 45

Productive End uses : Agro-processing, Rural Carpentry, Computer

Bakery and High vision hall

Proposed Tariff : Rs. 2/Watt/month for HH lighting

Rs.8/kWh for end uses

Average Subscribed Power : 96 Watt per HH

Page 5: 173 Feasibility Study of Micro Hydro Power in Nepal

Project Costs

Total Project Cost (Rs.) : 9, 048, 745.00

Cost per kW (Rs.) : 361, 950.00

Total Non Local Cost (Rs.) : 7, 604, 702.00

Non Local Cost per kW (Rs.) : 305, 950.00

Source of Finance (Rs.)

Subsidy : 3,562,500.00

Community Investment (Loan) : 1,160,853.00

DDC Investment : 452, 437.00 (5% of TPC)

VDC Investment : 904, 875.00 (10% of TPC)

Community Equity (Local costs) : 1,414, 081.00

Community Equity (Cash) : 1,554,000.00

Nepal Engineering College : 50,000.00

CAROL : 80,000.00

Financial Analysis

IRR : 15%

NPV (Rs.) : 1,120,955.00 (Rate of 10%, 15 yrs)

B/C Ratio : 1.07

Payback Period : 6.8 yrs.

Economical Analysis

EIRR : 11%

NPV (Rs.) : 453,222.00, (Rate of 10 %, 15yrs)

Payback Period : 7.5 yrs.

Page 6: 173 Feasibility Study of Micro Hydro Power in Nepal

TABLE OF CONTENT

SAILENT FEATURE ..................................................................................................... - 0 -

TABLE OF CONTENT .................................................................................................. - 5 -

EXECUTIVE SUMMARY ............................................................................................. - 8 -

ACKNOWLEDGEMENT ............................................................................................... - 9 -

ACRONYMS AND ABBREVIATIONS ...................................................................... - 10 -

Chapter 1 ........................................................................................................................... 12

INTRODUCTION ............................................................................................................. 12

1.1 Back ground ............................................................................................................ 12

1.2 Objective of the Study ............................................................................................ 13

1.3 Methodology ........................................................................................................... 13

1.3.1 Field Work ....................................................................................................... 13

1.3.2 Office Work ..................................................................................................... 14

Chapter 2 ........................................................................................................................... 15

GENERAL PROJECT DESCRIPTION ............................................................................ 15

2.1 Locations and Accessibility .................................................................................... 15

2.2 Topography and Geography ................................................................................... 15

2.3 Climate and Vegetation. ......................................................................................... 16

2.4 Project Area and Facilities ...................................................................................... 16

2.5 Hydrology and Water Right Issues ......................................................................... 16

2.6 Energy Consumption Pattern .................................................................................. 17

2.6.1 Present Situation .............................................................................................. 17

2.6.2 Domestic Demand of Electricity ..................................................................... 17

2.6.3 Potential End Uses ........................................................................................... 18

I Agro-processing ............................................................................................... 18

II Rural Carpentry ............................................................................................... 18

III Computer ......................................................................................................... 19

IV Bakery .............................................................................................................. 19

V High Vision Hall .............................................................................................. 19

2.6.4 Expected Load Demand Pattern ...................................................................... 20

2.7 Socioeconomic Condition and Affordability .......................................................... 20

2.8 Status of DEES Community Mobilization Process ................................................ 21

2.9 Plant Size and Power Requirements ....................................................................... 21

Chapter 3 ........................................................................................................................... 23

Page 7: 173 Feasibility Study of Micro Hydro Power in Nepal

TECHNICAL ASPECTS OF THE MHS .......................................................................... 23

3.1 Civil Components ................................................................................................... 23

3.1.1 I ntake Structure and Diversion ....................................................................... 23

3.1.2 Headrace Conveyance ..................................................................................... 23

3.1.3 Crossing ........................................................................................................... 23

3.1.4 Desilting Basin ................................................................................................ 23

3.1.3 Forebay Cum Settling Basin ............................................................................ 24

3.1.5 Anchor Block & Support Piers ........................................................................ 24

3.1.6 Powerhouse, Machine Foundation & Tailrace ............................................... 24

3.2 Electro-mechanical Works: ..................................................................................... 25

3.2.1 Trash rack ........................................................................................................ 25

3.2.2 Penstock layout & Expansion Joints .............................................................. 25

3.2.3 Turbine ............................................................................................................ 26

3.2.4 Generator ......................................................................................................... 26

3.2.5 Drive System ................................................................................................... 27

3.2.6 Control System ................................................................................................ 27

3.2.7 Powerhouse Cabling ........................................................................................ 28

3.2.8 Transmission / Distribution Network .............................................................. 28

3.2.9 Earthings & Lightening Arrestors ................................................................... 29

3.2.10 Consumer Protection & Service Wire ............................................................. 30

Chapter 4 ........................................................................................................................... 31

FINANCIAL AND ECONOMICAL ASPECTS OF THE MHS...................................... 31

4.1 Quantity Estimate and Rate Analysis ..................................................................... 31

4.2 Detailed Cost Estimate ............................................................................................ 31

4.2.2 Cost of Electro Mechanical Components ........................................................ 32

4.2.3 Other Costs ...................................................................................................... 33

4.3 Summary of Cost .................................................................................................... 33

4.4 Financial Mix .......................................................................................................... 34

4.5 Annual Expenses ..................................................................................................... 35

4.6 Annual Incomes ..................................................................................................... 35

4.7 Financial Analysis ................................................................................................... 36

4.8 Economic Analysis ................................................................................................. 37

4.8.1 Investment Cost ............................................................................................... 37

4.8.2 Operation and Maintenance Cost .................................................................... 37

4.8.3 Economic Benefit ............................................................................................ 37

4.8.4 Economical Indicators ..................................................................................... 39

Chapter 5 ........................................................................................................................... 40

OPERATION AND MANAGEMENT ASPECTS OF THE MHS .................................. 40

5.1 Institutions .............................................................................................................. 40

5.2 Skilled Manpower ................................................................................................... 41

Page 8: 173 Feasibility Study of Micro Hydro Power in Nepal

5.3 Follow-up, Supervision and Reporting ................................................................... 41

Chapter 6 ........................................................................................................................... 42

ENVIRONMENTAL ANALYSIS .................................................................................... 42

Chapter 7 ........................................................................................................................... 45

SOCIAL (VULNERABLE COMMUNITY) ASPECTS OF THE MHS.......................... 45

Chapter 8 ........................................................................................................................... 47

CONCLUSIONS AND RECOMMENDATIONS ............................................................ 47

REFERENCES .................................................................................................................. 48

ANNEXES: ....................................................................... Error! Bookmark not defined.

ANNEX I ........................................................................... Error! Bookmark not defined.

QUANTITY ESTIMATE .................................................. Error! Bookmark not defined.

ANNEX II (A) ................................................................... Error! Bookmark not defined.

UNIT RATE OF MATERIALS AND LABOUR ............. Error! Bookmark not defined.

ANNEX II (B) ................................................................... Error! Bookmark not defined.

RATE ANALYSIS ............................................................ Error! Bookmark not defined.

ANNEX III ........................................................................ Error! Bookmark not defined.

COST ESTIMATE ............................................................ Error! Bookmark not defined.

ANNEX IV (A) ................................................................. Error! Bookmark not defined.

INVESTMENT & SOURCES OF FUNDING ................. Error! Bookmark not defined.

ANNEX IV (B) .................................................................. Error! Bookmark not defined.

ANNUAL EXPENDITURES & INCOME ....................... Error! Bookmark not defined.

ANNEX V (A) ................................................................... Error! Bookmark not defined.

FINANCIAL ANALYSIS SPREADSHEET .................... Error! Bookmark not defined.

ANNEX V (B) ................................................................... Error! Bookmark not defined.

ECONOMICAL ANALYSIS ............................................ Error! Bookmark not defined.

ANNEX VI ........................................................................ Error! Bookmark not defined.

T & D VOLTAGE DROP CALACULATION ................. Error! Bookmark not defined.

ANNEX VII ....................................................................... Error! Bookmark not defined.

DATA COLLECTION FORM .......................................... Error! Bookmark not defined.

ANNEX VIII ..................................................................... Error! Bookmark not defined.

HYDROLOGY CALCULATIONS .................................. Error! Bookmark not defined.

ANNEX IX ........................................................................ Error! Bookmark not defined.

PHOTOGRAPHS .............................................................. Error! Bookmark not defined.

ANNEX X ......................................................................... Error! Bookmark not defined.

DRAWINGS ...................................................................... Error! Bookmark not defined.

Page 9: 173 Feasibility Study of Micro Hydro Power in Nepal

EXECUTIVE SUMMARY

Lower Puwa Khola MHS Project is located on the left bank of Lower Puwa Khola in Ilaam

VDC-6 of Ilaam District.

After a thorough research conducted by students of civil engineering (07 batch) at nec and

CAROL, the Lower Puwa Khola MHS is found to be feasible, technically, economically

and socially as well. The site for the scheme is in stable region and hence the components of

the scheme do not need any major protection measures.

Lower Puwa Khola MHS is a runoff river type with the source as Puwa Khola. Analysis

shows that the source is perennial and has sufficient discharge even in dry season. The

survey team from Himal Dolakha Hydropower Company (HDHC) measured the discharge

of 204 lps on 11th

May 2009. The lowest flow in the Lower Puwa Khola based on

hydrological calculations for un-gauged MHP River is 201.34 lps. The design discharge is

taken as 154 lps after considering 15% of the lowest flow for downstream water release due

to environmental reasons and 10% of discharge diverted for water losses due to evaporation

/flushing/ seepage.

The gross head and design discharge of the scheme is 30 m and 154 lps respectively

resulting the total power generation of 25 kW with overall efficiency of 55 %. The scheme

will provide electricity to the residents of ward no 4, 5, 6 and 7 of Puwa Khola VDC. The

electricity generated will be utilized mostly for household uses along with some end uses.

Altogether 259 households from the settlement will be benefited from the scheme with

possibility of addition of few more household during implementation. The detailed survey

data shows that there will be end use diversification with the implementation of the project

in years to come. Amongst the different end use possibilities, agro processing mill

consisting of grinder can be installed. Local carpentry is also potentially installed after the

project implementation. Similarly computer, bakery and high vision hall can be run.

The total cost of the project is Rs. 9, 048, 745.00. And the cost per kW is Rs 361, 950.00.

The program would provide Rs 3,562,500.00 as subsidy to the MHS through the District

Energy Fund. The DDC would invest Rs 452, 437.00 at the rate of 5% of the total project

cost and VDC would also invest Rs 904, 875.00 at the rate of 10% of the total project cost.

The community people would mobilize Rs.1, 414,081 through voluntary labor and local

material contribution and Rs. 1, 554, 00.00 as cash contribution. And remaining amount of

Rs 1,160,853.00 will be mobilized from nec, CAROL and HDHC.

Page 10: 173 Feasibility Study of Micro Hydro Power in Nepal

ACKNOWLEDGEMENT

The Detailed-feasibility study of Lower Puwa Khola MHS was brought to effect after

awarding the assignment to HDHC, CAROL and civil engineering Students (07

batch) of nec. For the purpose of fulfilling the above task, a well managed survey

team with sufficient equipment was mobilized.

We would like to express our sincerity acknowledgement to District Development

Committee: District Energy & Environment Section (DDC: DEES) Ilaam. Required

drawing, design & cost estimate is prepared according to the information and

guidelines provided by DDC: DEES and present market rate.

The research was a strong initiative of CAROL and civil engineering Students (07

batch) of nec which was supervised by the technical experts of HDHC and

department of civil engineering at nec.

We are deeply grateful to Mr. Bishnu Shakya, REA/REDP Central Region, Prof. Dr.

Hari Krishna Shrestha, Prof. Dr. Deepak Bhttarai, Students of civil engineering (07

batch) from nec, technical experts of Himal Dolakha Hydropower company and Mr

Anil Shrestha (Energy Development Officer, DEES) for their valuable suggestions

and technical support during the preparation and edition of this report. Similarly, we

would like to thank Mrs Kamal Danuwar Community Mobilizer for their tireless

effort, contribution and support in conducting the survey during the field visit.

We would also like to express our sincerity to National Programme Manager and

Senior Rural Energy Development System Advisor for their support and concern to

our effort.

And at last but not the least, we would like to express our acknowledgement to the

local villagers for their support and for delivering valuable information, co-operation

during the site visit and as well as for their hospitality during that period.

We hope that the study will truthfully reflect the villagers lighting problem and their

desire to implement the proposed MHS scheme.

Page 11: 173 Feasibility Study of Micro Hydro Power in Nepal

………………………………………..

Project Manager

CAROL

ACRONYMS AND ABBREVIATIONS

ACSR - Aluminum Conductor Steel Reinforced

AEPC - Alternative Energy Promotion Centre

Amp - Ampere

BOQ - Bill of Quantity

CAROL - Centre for Advanced Research and Obligatory Learning

CM - Community Mobilizer

Cu.m - Cubic Meter

DDC - District Development Committee

DDC: DEES - District Development Committee: District Energy &

Environment Section

EIA - Environment Impact Assessment

E/M - Electromechanical

HDHC - Himal Dolakha Hydropower Company

kg - Kilogram

km - Kilometer

kV - Kilovolt

kVA - Kilo Volt Ampere

kW - Kilo Watt

kWh - Kilo Watt Hour

LA - Lightning Arrestor

LPS - Liter per second

LT - Low Tension

MCB - Miniature Circuit Breaker

m - Meter

MHDS - Micro Hydro Demonstration Scheme

MHFG - Micro Hydro Functional Group

MHP - Micro Hydro Project

MHS - Micro Hydropower System

MIP - Medium Irrigation Project

nec - Nepal Engineering College

PCC - Plain Cement Concrete

PCD - Pitch Circle Diameter

PDP - Power Development Project

RCC - Reinforced Cement Concrete

RPM - Revolution per Minute

Rs. - Rupees

Sq. m. - Square Meter

Page 12: 173 Feasibility Study of Micro Hydro Power in Nepal

UNDP - United Nations Development Program

VCDP - Vulnerable Community Development Plan

VDC - Village Development Committee

WB - The World Bank

Page 13: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 1

INTRODUCTION

1.1 Back ground

Renewable energy technologies are being presently promoted in Nepal through several

organizations. Among various organizations Rural Energy Development Programme (REDP) is

one of the major organizations which have been working for the promotion of rural energy

technologies with community mobilization approach. To address the aspects of the decentralized

energy planning and management in Nepal, REDP was initiated in 1996 with the joint effort of

Nepal Government and United Nations Development Program (UNDP). It was initiated with

covering 5 hilly districts in 1996, 10 districts in the 1998 and 15 districts in 2000 of its operation

under the REDP-1 phase. Then REDP-II was functional in 25 districts since 2003 to 2007. Since

2007, the program is in 40 districts with the joint effort of GoN, UNDP and the WB. The

program aims to support the community managed and community-oriented development

initiatives, the implementation of CM process with its six basic principles viz. Organization

development: capital formation: skill enhancement: technology promotion: environment

management and Vulnerable Community’s empowerment.

The Lower Puwa Khola Micro Hydropower System was reported as feasible for detail study,

preliminarily surveyed by DDC: DEES, Ilaam. For detail feasibility study of the Lower Puwa

Khola MHS, a contract was signed between HImal Dolakha Hydropower Company Students of

civil engineering (07 batch) and CAROL on behalf of Lower Puwa Khola MHFG. In accordance

to that contract, this report is the final outcome of the technical and socio economic aspects of

the field survey and interaction during meeting with Lower Puwa Khola MHS functional group

and villagers.

The site was surveyed by Civil Engineers from the contractors from 10th

May to 13th

May 2009.

Professionals as enlisted below visited the site:

Table 1: Manpower

Designation Name of candidate

Project manager: Vaibhav Pandey

Program coordinator: Dinesh Shrestha

Administrator: Kalyan Bikram Neupane

Chief development officer: Baibhav Ojha

Chief technical officer: Ganesh Aryal

Technical officer: Ashish Gautam, Prakriti Pradhan and Ganesh Niraula

Development officer: Bal KrishnaThapa, Sushma Chaudhary

Page 14: 173 Feasibility Study of Micro Hydro Power in Nepal

Research analyst: Lokendra Pun

Researchers: Usha Dhami and Paras Mani Bhatta

Finance controller: Shakti Pandey and Ritu Mishra

Public relationship officer: Ranjan Bhatta

Surveyors: Anil Bhatta, Dipak Basnet, Rajeev Shrestha, Nirajan

K.C, Mandeep Shrestha and Nirmal Shrestha

1.2 Objective of the Study

Energy is the basic tool for development activities in any village. From analyzing various

projects, the study shows that most of the project fails due to the improper analysis of the

hydrology, failure in civil structure and also in selection of the appropriate and sufficient electro-

mechanical components. Considering all the issues following objectives have been noted to carry

out the feasibility study of the project.

Hydrological study and flow measurement

Carry out survey for appropriate civil structures, their location and design

Design appropriate and suitable electro-mechanical equipment

Design transmission / distribution lines

Identification of potential load and load center / demand of power

Identification of environment and issues related to water right

Identify any other suitable measures for the futures sustainability

Discuss about the technical and socio- economic aspects of the proposed scheme

1.3 Methodology

The entire work of the Detailed Feasibility Study was carried out in two stage viz fieldwork and

desk (office) work.

1.3.1 Field Work

To start with, the team made a comprehensive reconnaissance survey around the village and

stream bank with the villagers. Consultations were made with the former VDC Chairman, local

teachers, social workers and senior citizens of the locality, who were present in the village during

the time. With the thorough analysis of the situation, detailed measurements were carried out to

locate the best suitable intake, proper canal alignment, stable forebay location and powerhouse.

Page 15: 173 Feasibility Study of Micro Hydro Power in Nepal

The detail survey was done with the help of an Anbey Level, GPS, 50 and 5 m tapes. The detail

survey was done within the principles of leveling. The flow measurement was done by salt

dilution method using conductivity meter.

The team carried out detailed engineering survey of intake area, alignment of the headrace

conveyance, forebay and powerhouse locations and exit of the water (tailrace and spillway) with

the help of the members of the Functional Groups. The transmission / distribution line was also

measured with due considerations of having least adverse impact on environment and aesthetics.

The team tried to make the T/D lines shortest possible and the alignment in the stable place. Due

attention was given to have multipurpose use of water, both for irrigation and power generation.

A meeting with the MHS users, the Micro Hydro Functional Group (MHFG) with the help of

Community Mobilizers (CM) was done. Participatory approach was adopted with the direct and

active involvement of the beneficiary community members during the survey of the MHS. Focus

Group Discussions (FGD) were also organized in order to acquire the necessary information,

especially about the socio-economic situation of the area.

1.3.2 Office Work

After the completion of the fieldwork, the team proceeded to analyze the data and work out

designs of various components. All the data and information were carefully analyzed to come to

the final and detailed designs of all the necessary components. The views and suggestions were

duly taken into consideration while carrying out the detail designs of the scheme. The design of

all civil as well as electro-mechanical components was carried out following AEPC/REDP guide

lines and design spread sheets and necessary drawings were prepared. This detailed feasibility

study report is the outcome of the survey conducted.

Page 16: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 2

GENERAL PROJECT DESCRIPTION

2.1 Locations and Accessibility

The proposed micro-hydro project is in Puwakola VDC; ward no - 6 of Ilaam district. Ilaam

district lies in the Mechi zone, Eastern Development Region of Nepal. It is one of the

mountainous regions with full of slope terrain and cultivated land. The proposed site is situated

at about 1300 m above msl.

The proposed project site lies north of the district head quarter. It takes about 1.5 day walk for

normal and about 3 days for loaded porter to reach the site. The nearest road head is Magar gau

VDC of Ilaam which is about 45 km away from the project site.

2.2 Topography and Geography

The topography and geography condition of the proposed site is found to be fairly stable enough.

The topography of the proposed site lies in the Mahabharat range. Most of the proposed project

area lies in moderate sloppy area with full of slope terrain. No any sign of major landslide and

other instability were found during the site visit.

Geologically the proposed site is predominated by sedimentary and metamorphic rock consisting

of shale, mudstone and limestone. All the structure of the proposed MHS lies on the left bank of

the Banakhu Khola.

The proposed intake and diversion location is at the left bank of Banakhu Khola, and lies in

stable place and possibility of bed scouring is also less. The bank of the Khola is also strong and

stable enough with provision of large boulders for diverting water safely to the canal. The

alignment of the headrace runs through left bank of the Khola. The total length of the headrace

canal is about 1071 meter.

Page 17: 173 Feasibility Study of Micro Hydro Power in Nepal

2.3 Climate and Vegetation.

The District lies in the MIP region 5, which is categorized as mountainous catchments. The two

seasons of the year are well marked with typical variations. Due to the moderate altitude the

climate is suitable for growing different types of plant and vegetation. The natural vegetation in

this project area changes with the variation in elevation, soil regime and slope. Agriculture is the

most predominant occupation of the people of that area.

Major land use category of the VDC includes agriculture land, forest and bushes, hard rock and

mountain, rivers and stream banks. The natural vegetation around the project area

consists of bushes, soft wood trees and hard wood trees. Sal wood is also available in the area.

Major agricultural products are rice, maize, wheat, millet, potato etc.

2.4 Project Area and Facilities

The target area covers ward no 4, 5, 6 and 7 of Puwa khola gau VDC. The number of household

in beneficiary area is 259 with the population about 1922. There are four primary schools as well

as one high school. Other facility in the area includes VDC office and Post office.

2.5 Hydrology and Water Right Issues

The source of flow is Puwa Khola, which is a perennial stream. The flow in the stream was

measured by salt dilution method using conductivity meter. And the discharge is found to 204.0

lps. The calculation sheet is given in the annex VIII. The flow was measured on 11th

of May

2009.

The hydrological calculation is based on MIP method. The site lies on the MIP region 5. The

design discharge is taken as 154 lps after considering 15% of the lowest flow for downstream

water release due to environmental reasons and 10% of discharge diverted for water losses due to

evaporation /flushing/ seepage.

Table 2: Mean Monthly Flow, Banakhu Khola (source:HDHC)

Month Flow at River, lps

January 535.44

February 402.69

March 300.91

April 221.26

May 201.34

Page 18: 173 Feasibility Study of Micro Hydro Power in Nepal

June 604.03

July 2480.30

August 3084.34

September 2212.58

October 1442.60

November 1006.72

December 736.79

Annual Average 1102.42

(Note: The Hydrological Data was measured by the technical experts of HDHC)

There are no water right conflicts in the area for power generation. The water needed for the

plant can be diverted without any conflicts. There is sufficient discharge in the stream even in the

driest month. The matter of water use was thoroughly discussed amongst the community people.

The MHFG is in the process of registering the MHS in the District Water Resource Committee

for obtaining the water use right legally.

2.6 Energy Consumption Pattern

2.6.1 Present Situation

Firewood is being used extensively as the major source of energy and it is being largely

consumed for residential purposes. Consequently, massive encroachment of forests has taken

place due to fuel wood collection. Kerosene is mainly used for lighting. The general energy use

pattern of this settlement (community) has been summarized in the following table.

Table 3: Energy Source and Use (source: HDHC)

Description Unit Rate/

Unit

Qty. (per HH

per month)

Average Monthly Use Remarks

Cooking % Lighting %

Fuel Wood

Per HH Bhari 50

~5-6 Bhari

(280 kg) - 100 - -

Free of cost normally,

pressure on forest is

maximum

Kerosene Litre 100 3.5 - - 3 86

Dry Cell

Batteries Pair 50 3 - - 1.0 33

67 % for radio,

cassette.

2.6.2 Domestic Demand of Electricity

Page 19: 173 Feasibility Study of Micro Hydro Power in Nepal

The study shows that almost the entire village has minimum 2 to maximum 4 rooms. That means

an average demand of electricity is between 2 to 4 bulbs, which will be enough. Considering the

average demand and the production of electricity about 96 watt per household is proposed for the

electricity, which is just sufficient to illuminate three to four incandescent bulbs of 25 watt.

Furthermore, the technological advancement in the area of

efficient lighting (CFLs) would solve the future demand of peak hour lighting. Study shows that

the peak demand of electricity has been coming from household lighting in morning and in the

evening. In addition to household lighting, for the use of daytime energy there is possibility to

promote different kinds of end-uses by providing technical training and other kinds of supports.

2.6.3 Potential End Uses

Electrical energy is one of the least cost options for income generating activities in the remote

rural area. The proposed MHS is designed to produce 25 kW, which can only meet

the peak demand for lighting, so the end-use application will be done mostly during daytime.

I Agro-processing

Based on the survey on agriculture production and the assessment of quantities that could be

processed in the beneficiary area it has been found that there is the potentiality for the

establishment of an agro-processing mill. At present most of the local people are using the

traditional way of agro-processing which is time consuming and also needs more strength. As

per the survey and discussion with the local people and MHFG members, the MHFG seems

interested to operate the agro-processing mill itself. Based on the survey, there seems a good

potentiality for an agro-processing mill. An agro-processing of 8 kW power is proposed running

for 10 hours a day during day time.

II Rural Carpentry

The area has very good vegetation of forest with different types of trees. So it is very much

possible to run a rural carpentry for wood works. There are skilled carpenters in the project area,

who make furniture by using manual tools to meet local demand. With the establishment of the

industry, the quality of the products would be enhanced, thus would also increase their demand.

As per discussion with the community people, at least one such workshop would be established

in the community. The proposed rural carpentry will consume 3 kW power for 10 hours a day

during day time.

Page 20: 173 Feasibility Study of Micro Hydro Power in Nepal

III Computer

The micro hydro power system covered the primary schools as well as high school, So the power

to be utilized in school and for computer and other works in school which would be consume 2

kW running for 8 hours a day during day time.

IV Bakery

According to the local people of surveyed area bakery will be a good endues in this project and

the micro hydropower system covers the local bazaar of the VDC. So there is a possibility of

bakery which would consume 5 kW for 6 hours a day during night time.

V High Vision Hall

According to the young people of the surveyed area, high vision hall will be a best endues and

they want the high vision with them. The high vision hall consumes 3 kW running for 6 hours

per a day during morning time.

Table 4: Possible End Uses (source: HDHC)

S.N. Type of Business Location

Ward no.

Power

(kW)

Operating

Hours

Operating

Days

/Month

Operating

Months

/Year

Total

Energy

Consump

(kwh)

Tariff/kWh Remarks

1 Agro-processing Village 8 10 26 12 24960 8 One

unit at a

time 2 Rural Carpentry Village 3 10 26 12 9360 8

3 Computer

Centre Village 2 8 26 12 4992 8

4 Bakery Village 5 6 25 12 9000 8

5 High vison Hall Village 3 6 24 12 5184 8

Total: 21 53496

Above mentioned end uses could be established with DEES’s support for end use promotions.

The DEES Support Rs 250, 000.00 (Rs. 10,000 per kW of installed capacity of the MHS, Rs.

250,000 maximum) for end-use promotions that will be provided to the concerned MHFG as

grant and the respective MHFG will provide the support to interested entrepreneur in the form of

soft loans. The MHFG will provide only 50% (maximum) of total investment cost for the

establishment of the enterprises to the respective entrepreneurs. The entrepreneurs themselves

Page 21: 173 Feasibility Study of Micro Hydro Power in Nepal

will mobilize additional amount required. The DDC: DEES helps the community people for

identification of the potential end-uses.

2.6.4 Expected Load Demand Pattern

The expected load demand pattern (Watt) over 24 hours period has been provided in the

following table.

Table 5: Expected Load Demand Pattern (source: HDHC)

Load 4.00 am –

7.00 am

7.00 am –

10.00 am

10.00 am –

12.00 pm

12.00 pm

–4.00 pm

4.00 pm –

6.00 pm

6.00 pm –

11.00 pm

11.00 pm

– 4.00 am Remarks

HH lightening 25 25 9 hrs/day

Agro-

processing 8 kW 8 kW

10 hrs/day, 312

days/year operation

Rural carpentry 3 kW 3 kW

10 hrs/day, 312

days/year operation

Computer 2 kW 8 hrs/day, 312 days/year

operation

Bakery 5 kW 5 hrs/day, 300 days/year

operation

High Vision

Hall 3 kW

6 hrs/day, 288 days/year

operation

Total 25 kW 18kW 10kW 11 kW 11 kW 25 kW 5 kW

Note: The agro-processing units and other end use should be run at different times during the day without

overloading the plant.

2.7 Socioeconomic Condition and Affordability

The detail socio-economic status of the project area will be discussed in the Volume III of the

Detail Project Report as Vulnerable Community Development Study Report (VCDSR) to be

prepared by the DDC: DEES, however some relevant information about the socio-economic

condition of the proposed project area has been discussed herein.

Page 22: 173 Feasibility Study of Micro Hydro Power in Nepal

There are 259 households with about 1922 households’ members to be benefited from this

project. The main occupation of the people of the village is agriculture and livestock. The

average landholding per household in the village is about 15 ropanis. Main agricultural products

are rice, maize and millet, oilseeds and potatoes. The economic status of the villagers is

considerably fair.

There is at least a literate in each household. There are facilities of schools at a distance of 2 km

from powerhouse. The status and interest of the women in the area is good and having high

levels of enthusiasm for the development of project, the MHS is highly viable for the area.

The socio-economic survey of the impact area indicates that about almost all the beneficiaries

HHs are capable to pay for the electricity. The main source of income of the local people is

agriculture-products, livestock.

2.8 Status of DEES Community Mobilization Process

District Development Committee: District Energy and Environment (DDC: DEES), Ilaam has

been established for the development programme of the local villagers. The main activities of

this mobilization are to make the local people aware of the capacity building , natural resource

management, Skill enhancement, Vulnerable community development, Capital formation and

their application with the local technology with the participation of the local people.

The DDC: DEES has started the CM process in the area since Jan 2010. DDC: DEES is

conducting the community mobilization as per the six principles of community mobilization. All

together 28 Cos are formed which include 14 male and 14 female Cos. These COs will be

carrying out various socio-economic activities in the community, especially through the

mobilization of local resources as well as resources from different agencies. The MHFG is

registered at the District Water Resources Committee.

2.9 Plant Size and Power Requirements

Before effective design of hydropower project, one must consider the coordinated use of the

stream water for power generation as well as other local purposes. The site for the powerhouse is

selected in such a way that the water from the tailrace can safely be discharge to the parent

stream. No serious water right issues have been observed during the survey.

Power (P) = x Qmin x Hg x g

Page 23: 173 Feasibility Study of Micro Hydro Power in Nepal

= 0.55*0.154*30*9.81

= 25 kW

Where,

Q = Discharge in lps- 0.154 m3/sec

H = Gross Head in m- 30 m

= Overall Efficiency of System (55%)

g = Acceleration due to gravity, 9.81 m3/sec

All the project structures are proposed to be constructed on the left bank of Puwa Khola. The tail

water will be safely discharged to river. The length of the tailrace canal is 20 m.

Page 24: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 3

TECHNICAL ASPECTS OF THE MHS

3.1 Civil Components

3.1.1 Intake Structure and Diversion

The intake structure is proposed at left bank of Lower Puwa Khola and is located at Puwa Khola

VDC, ward no 6. In consideration of the flow of the river, temporary type diversion structure of

gabion weir of approximate height of 1 m and 10 meter long is proposed to be built across the

river. The proposed temporary weir is of low cost and can be easily maintained if it is damaged

by the flood during rainy seasons. The respective position of weirs and other fundamental

components of Lower Puwa Khola MHS are shown in drawing no 1 and 2.

The geological condition of the intake site is appropriate for diverting water into the canal. An

orifice type of side intake is proposed. The orifice is designed to drag 171 lps of discharge and

the size of orifice is 0.2 x 0.6 m. A coarse trash rack is also proposed. Details of the head works

are given in drawing no 2.

3.1.2 Headrace Conveyance

Due to geology and topography of the site, stone masonry canal in 1:4 cement mortars with 1:4

cement plasters is proposed. The headrace pipe passes through left bank of the river. The details

of the headrace profile and section are shown in the annex, drawing no 3.

Stone masonry canal, W-0.5 m, H-0.3 m, FB-0.15 m, Length- 1015 m

3.1.3 Crossing

There is crossing in the alignment of headrace. So a crossing structure of RCC in 1:2:4 is

proposed and the typical details of crossing structure is given in the drawing no 5.

Crossing structure : CH-0+567.0 to CH-0+601.0 m & CH-0+602.5 to CH-0+624.5 m

: W-0.5 m, H-0.3 m, B-0.1 m, Length-56 m

3.1.4 Desilting Basin

Considering the flow and geological condition a desilting basin is proposed at 35 m from the

intake. The desilting basin is designed considering 2 kg/m3 sediment concentration in order to

Page 25: 173 Feasibility Study of Micro Hydro Power in Nepal

settle particles larger than 3 mm. The internal size of the basin is proposed of 8 x 1.75 x 1.1m

length, breadth and depth (avg) respectively. The basin is designed to flush at every 12 hours

manually. A spillway of 2.5 m and flushing gate of M.S is proposed. The flushing canal is about

10 m long. The structure is proposed to be made of stone masonry with 1:4 c/m with inner

surface plaster with 1:4 c/s. The detail of the desilting basin is given in the drawing no 4.

3.1.3 Forebay cum Settling Basin

Considering the flow and geological condition a forebay cum settling basin type of structure is

proposed. It is located at the end of headrace canal. The basin is designed for settling particles as

well as for forebay purpose. The settling basin is designed considering 1 kg/cm3 sediment

concentration in order to settle particles larger than 0.3 mm. The internal size of the basin is

proposed of 8.0 x 1.75 x 1.1(avg) m. The basin is designed to flush at every 12 hours and

manually. A flushing gate and about 43 meter of canal is proposed for flushing sediments as well

as over flow is proposed for flushing sediments as well as over flow. A fine trash rack is

provided in order to prevent any debris

entering in the turbine through penstock.

The second part is the forebay with 1.75x1.5x1.6 m with internal size. The structure is proposed

to be made of stone masonry with 1:4 c/m with inner surface plaster with 1:4 c/s. A fine trash

rack is provided in order to prevent any debris entering in the turbine through penstock. The

details of the basin structure are given in the annex, drawing no 6.

3.1.5 Anchor Block & Support Piers

The anchor blocks and the support piers are designed to support the penstock pipe. Anchor

blocks are proposed to be designed at every vertical bend and at 30 meter spacing at the straight

section. Altogether 4 numbers of anchor blocks are required along the penstock pipe. Each

anchor block is constructed of 1:3:6 PCC with 40% plum concrete. Support piers are designed at

about 3.5 to 4 meter spacing. Altogether 14 nos. of supports piers are designed. Support piers are

constructed of stone masonry in 1:4 c/s mortars. These blocks are designed considering the

stability, bearing capacity of soil, thrust pressure and water pressure. The details of the blocks are

given in the annex X, drawing no 9 & 10.

3.1.6 Powerhouse, Machine Foundation & Tailrace

The powerhouse is proposed to be located on the uncultivated forest land. It is located in flatter

portion of land having sufficient space for building the house. The powerhouse is sufficiently

above the flood level. The powerhouse consists of internal dimensions of 5 m lengths, 4 m

Page 26: 173 Feasibility Study of Micro Hydro Power in Nepal

widths and 2.7m heights. Similarly operator room of internal dimension 3m lengths, 2.5 m

widths and 2.7 m heights. The building is to be built of locally available stone masonry walls

with mud mortar. The roof is to be covered with CGI sheets with wooden rafters and purlins. The

details of the power house are given in the drawing no 11.

Machine foundation has been designed as required to be in safer side against over turning,

bearing pressure and sliding considering the forces due to maximum expected surge head, weight

of turbine and weight of generator. A minimum of 20 mm diameter, 700 mm long anchor bars

are to be used to fix base frame to the machine foundation. 10 mm dia Tor steel bars are to be

used for reinforcement. Maximum spacing to be provided is 150 mm in turbine pit and 300 mm

on other faces. Lap length will be 400 mm on other faces. Lap length shall be 400 mm min.

Minimum reinforcement cover shall be 50 mm. Structural concrete shall be 1:2:4 mix. 10 mm

width of sand and gravel has been placed at periphery of machine foundation down to depth of

powerhouse floor.

A stone masonry tailrace canal is proposed from the powerhouse after the turbine to discharge

the water back into the stream. The length of the tailrace canal is about 20 m. It will be of about

50 cm width and 30 cm depth in dimensions. The details of the machine foundation and tailrace

canal are given in the annex X, drawing 12.

3.2 Electro-mechanical Works:

Most of the electromechanical components would be manufactured / fabricated in Nepal. The

topic gives a brief description about design and selection of the components proposed for the

project.

3.2.1 Trash rack

A coarse trash rack is proposed at the intake. The proposed size of the coarse trash rack is 0.6 m

x 0.6 m. The trash rack is proposed of 5 x 40 mm steel plate with 50 mm c/c spacing of the bars

and inclined at 1:3.

Similarly a fine trash rack is proposed at the forebay. The proposed size of the fine trash rack is

0.9 m x 1.75 m. The trash rack is proposed of 5 x 40 mm steel plates with 25 mm c/c spacing of

the bars. The details of the trash racks are given in the drawing no 8.

3.2.2 Penstock layout & Expansion Joints

Page 27: 173 Feasibility Study of Micro Hydro Power in Nepal

According to the available head, a mild steel pipe of 280 mm MS ID is proposed. The overall

length of the penstock is 66 meter and 3 mm thickness.

The M.S pipes are proposed of about 2.5 meters in length, rolled/ welded having flange at each

end connected together. Flange should have 12 mm thickness and properly welded together with

the pipe. The details of penstock profile are given in the drawing no 7.

Expansion joints are also designed for the movement of the pipes during the temperature

variation. The thickness and size of the joints are decided on the basis of the temperature

variation of the scheme. The maximum temperature of the site is considered 30 degree and

minimum as 1 degree. Altogether 4 nos of expansions joints are enough. An air vent pipe of 50

mm diameter is proposed at the starting point of the penstock pipe.

3.2.3 Turbine

For the available gross head of 30 meter and the design discharge 154 lps, a Cross flow turbine has

been proposed. Though the each manufacturer has their own design and product specification, we

have recommended the following major specifications of the turbine. Detail design will be as per

the manufacturer at the time of manufacturing with required output. Specification of the

proposed turbine is presented below.

Type Cross flow turbine (T15)

Valve Butterfly (Gear Operated)

RPM 750

Rated capacity 38 kW

Efficiency 70%

Discharge 154 lps

The turbine is proposed to be equipped with manually operated flow regulating valve. The bearings

are rated to withstand runway speed of the turbine. The bearings are recommended such that they

take into account the static load exerted on it due to the drive system.

3.2.4 Generator

(Note: all the electrical works is implemented by the technical team of HDHPC)

To convert the mechanical power available at the turbine shaft, synchronous, 3-phase brushless

generator is proposed for the scheme. The generator size and type is compatible with the electronic

regulation system. The specification of the generator is as follow.

Type and rating 3 Phase, brush less synchronous Generator

Page 28: 173 Feasibility Study of Micro Hydro Power in Nepal

Synchronous, 50 kVA

Frequency 50 Hz

Voltage 400 Volts, 3- phase

Pole 4 pole

Efficiency 86%

Power Factor 0.8 lagging

Speed 1500 rpm

Over speed 180 % continuously

Connection Star

AVR Mounted internally, voltage regulation + or – 5%

With under/over voltage and under/over frequency

protection

3.2.5 Drive System

The drive system transfers the mechanical energy from the Turbine shaft to the generator rotor at

required speed. Here, the speed of the turbine is 750 rpm and the generator rated speed is 1500

rpm. So, the gear ratio should be 1:2. For this, habasit belt is recommended. The belt could get

loose after some period of operation. A sliding mechanism should be incorporated in the

generator base to tight the belt.

3.2.6 Control System

For matching variable behavior of the load an Electric Load Controller (ELC) is to be used to

safe guard in the system. 25 kW capacity ELC is proposed to be used along with the ballast

heater of 30 kW capacities. Incorporation of the Load controller with generator helps to maintain

the generator speed at constant level. The ELC diverts the excess power generated to the ballast

heater in the ballast tank. The box enclosing ELC also contains meter showing current, voltage

and frequency output of the generator, kW meter and one energy meter (kWh meter).

Similarly, the protection system should also include adequately sized MCCBs to protect against

overload as well as short circuits without damaging the generator and other control equipment.

Table 6: MCCB

MCCB on the generator side MCCB after ELC

No. of poles 4 pole with switched neutral 34pole with switched neutral

Operating voltage 400 V 400 V

Rated Current at 415V 80 A 63 A

Page 29: 173 Feasibility Study of Micro Hydro Power in Nepal

Breaking Capacity 10kA 10kA

Frame Size GS GS

Similarly for the protection in the transformer following MCCB are proposed

MCCB for step up transformer: 32 Amp

MCCB for step down transformer: 32 Amp

3.2.7 Powerhouse Cabling

Armored copper 35 mm² power cables are proposed to connect generator, panel and dummy load

inside the powerhouse. Similarly, 50 mm2, 4- core armored aluminum cable is proposed for the

connection between the main switch and the first pole. Cable ratings are proposed such that they

can carry at least 150 percent of the required maximum current. At least 3 light points with

incandescent lamps and one power point with necessary switches and fuses are proposed for the

powerhouse use. The details of power single line diagram are given in the annex X, drawing no

13.

3.2.8 Transmission / Distribution Network

(Note: T/D network would be completely managed by HDHC)

Since the transmission line is long, so a 25 kVA setup transformer (star/delta) is proposed at power

house and 25 kVA set down transformer (delta/star) is proposed at different cluster. The

transmission and distribution network consists of poles, transformers, conductors and insulators.

The generated power is proposed to be transmitted and distributed to the load centers via 3 phases,

11 kV High-Tension (H. T.), 0.4 kV Low-Tension (L. T.) overhead lines and single phase 230V

overhead lines. The design and construction has been simplified with an overview to reducing the

project cost by using locally available resources as much as possible. The transmission and

distribution lines are designed considering 10% voltage drop. The total single line length is 19.52

kilometer.

ACSR Conductor for transmission and Distribution purpose

1. ACSR Squirrel 60326 m

2. ACSR Weasel 11950 m

3. ACSR Rabbit 4721 m

Poles

9 meter Tubular Swage Poles has been proposed for the H.T line and 7 meter 8 m wooden poles

are proposed for the L. T for single phase and three phase lines respectively. The average pole-

to-pole distance is kept at 35 m in case of wooden poles and 50 m in case of steel poles.

Page 30: 173 Feasibility Study of Micro Hydro Power in Nepal

Table 7: Specification of Wooden poles:

Specifications Wooden poles for 3

phase L.T.

Wooden Poles for 1

phase l.T

Tubular poles for

H.T. (Steel)

No. of Poles 116 260 125 Spacing 35 m 35 m 50 m Pole Height 8 m 7 m 9 m Min. ground

clearance 5 m 4.5 m 5.5 m

Conductor spacing 30 cm (vertical) 30 cm (vertical) *See note below Min. top diameter 140 mm 125 mm 5 inch

* NOTE: L.T. lines are placed vertically. The details of diagram are given in the drawing.

For L.T. lines, the conductor spacing is 30 cm vertically.

Stay set

Stay sets are required at every bends, first pole and last pole of the transmission and distribution

and in steep slope upward. Generally, for safety, every 5th pole is to be stayed on both sides even

if the poles are in straight line, so as to provide protection from storms according to the standard

of REDP. The stay set consists of MS rod, stay bow, stay insulator, turn buckle and anchor plate

of 3 mm. About 101 stay wires are used for support of the poles depending upon the

geographical condition of the site.

Insulators, D-iron Clamp

To lay the wire in poles insulators are used. Shackle type insulators are used for the L.T. lines of

both 3 phase and 1 phase. Total 1430 numbers of shackle insulators are proposed. Details of

transmission and distribution are also given in the drawing no 14.

Table 8: Insulators Type:

S.N. Size Dimension Numbers

1 Small 55 mm*55 mm 1070 units

2 Medium 75mm*90mm 360 units

*Each set of Shackle type insulators is provided with D clamp, nuts and bolts.

Similarly for H T lines

Pin Type Insulators: 383 units.

Disc Type Insulators: 30 units.

D.O. fuses with operating rod are proposed for the protection of transformers.

3.2.9 Earthings & Lightening Arrestors

All exposed metal parts of the generating equipments and generator neutral terminal are

proposed to be earthed separately in a proper manner. Similarly, each lighting arrestors installed

Page 31: 173 Feasibility Study of Micro Hydro Power in Nepal

should be separately earthed. Apart from earth continuity from the powerhouse through the cable

armored up to the main distribution board, each distribution box is proposed to be properly

connected to earth. It is proposed to do the earthing work with the same conductor and plate.

Three different earth pits at the Power House for

One for neutral earthling.

Equipment Ear thing.

Lighting Arrester Ear thing.

The positioning of the Farthing system is shown in details in the transmission/Distribution

diagram in the Annex

Specifications:

600mm*600mm*3mm copper plate. Numbers: 47

Ear thing wire: 8 SWG copper wires

GI pipe for the protection of Earth wire is also recommended. The copper earthing plate should

be buried in a trench of minimum depth 2.5 m.

Similarly lightening arrestors of 11 kV and 0.5 kV is proposed. 21 and 68 nos respectively of

L.As are proposed. The details location of the LAs and earthing are shown in the drawing no 14.

3.2.10 Consumer Protection & Service Wire

All consumer connections should be protected through MCBs of appropriate rating to suit

consumer’s peak wattage subscription. These are to be installed in enamel painted, lockable

metal enclosures. Adequate wiring and terminal connections will be provided for neat and

efficient service cable connection. Total 259 no. of 0.5A MCB are proposed for the scheme but

the costs is not included in the estimate as it is assume to be bought by the consumers

themselves. Similarly service wire of 6 sq.cm is proposed at the rate of 20 m per H/H.

Page 32: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 4

FINANCIAL AND ECONOMICAL ASPECTS OF THE MHS

4.1 Quantity Estimate and Rate Analysis

Rate analysis for the construction activities of the MHS has been done using Nepal Government

norms. A district rate, published by DDC at Ilaam has been also considered while analyzing the

rates. Since the project is in far remote place and will be constructed by the local people using

available local materials, so the local available materials rates and local labor rates are also

consider in the rate analysis.

After the detailed engineering designed was complete than the quantity and volume of work were

worked. All necessary drawing has been prepared, which are enclosed in the annex X. Item wise

breakdown of the work has been made keeping the importance and needs. The details of rate

analysis and quantities of work are presented in the annex of this report.

4.2 Detailed Cost Estimate

The total cost estimation of the project has been carried out from the costing of mechanical

works, electrical works, civil works, tools, spare parts, transportation cost, and installation,

testing commissioning and contingency. The total project cost is Rs. 9,048,746.00. The cost per

kW is Rs. 361, 950.00.

Page 33: 173 Feasibility Study of Micro Hydro Power in Nepal

4.2.1 Cost of Civil Components

The cost of civil components of the project is Rs 2, 051, 942.0. It is 22.68% of the total project cost.

The Cost of estimation for civil structures include cost of intake structure, power canal, forebay,

civil work for penstock, anchor block, saddle support (pier), power house, tail race etc.

Table 9: Cost Estimate of Civil Works

S.N. Description of works Amount

(NRs.) Local

(NRS.) Non Local (NRs.)

1 Intake and Diversion 52166 14242 37924

2 Desilting basin 70773 34783 35990

3 Headrace Conveyance 1524498 686351 838147

4 Forebay cum desilting basin &

Spillway 152851 66759 86091

5 Penstock Support & Anchor Blocks 59908 23850 36058

6 Power House 141522 88365 53157

7 Machine Foundation & Tailrace canal 50224 19284 30940

Total 2051942 933634 1118308

4.2.2 Cost of Electro Mechanical Components (source: HDHC)

The Electro mechanical component cost of the project is Rs 5, 183, 102.0. It is 57.28% of the total

project cost. The costs are based upon quotation from the suppliers.

Table 10: Cost Estimate of E/M Works

S.N. Description of works Amount

(NRs.) Local

(NRS.) Non Local (NRs.)

1 Trash rack and flushing 38475 0 38475

2 Turbine, Drive System & Accessories 340700 0 340700

3 Penstock and Accessories 333500 0 333500

Page 34: 173 Feasibility Study of Micro Hydro Power in Nepal

4 Generator & Accessories 195000 0 195000

5

Load Controller, Ballast & 759200 0 759200

Main Switch ( Protection System)

6 Transmission/Distribution Line 2083427 0 2083427

7 Poles 1112800 112800 1000000

8 Transformer 320000 0 320000

Grand Total 5183102 112800 5070302

4.2.3 Other Costs

Apart from the civil and electromechanical costs, costs of various other components are costs of

tools and spare parts, transportation costs and installation and testing/commissioning costs. These

costs add up to Rs. 613, 647.00. Whereas, 5% contingencies of TPC is Rs. 363, 665.00

Table 11: Cost of Others

S.N Particular Amount(Rs.) Local (Rs.) Non-Local (Rs.)

1 Tools 16000 0 16000

2 Spare parts 20000 0 20000

3 Transportation and Packing 427647 367647 60000

4 Installation & Commissioning 150000 0 150000

4.3 Summary of Cost

The total cost of project consists of civil costs, electro mechanical costs, transportation costs,

installation costs, and testing/commissioning costs, costs of tools and spare parts and contingencies.

The summary of costs of the MHS is presented below;

Table 12: Summary of Projects Costs

S.N. Description of works Amount

(NRs.) Local

(NRS.) Non Local

(NRs.) % of Total

cost

Page 35: 173 Feasibility Study of Micro Hydro Power in Nepal

1 Civil works 2,051,942 933,634 1,118,308 22.68

2 Mechanical works 712,675 0 712,675 7.88

3 Electrical works 4,470,427 112,800 4,357,627 49.40

4 Tools 16,000 0 16,000 0.18

5 Spare parts 20,000 0 20,000 0.22

6 Transportation 427,647 367,647 60,000 4.73

7 Installation &

Commissioning 150,000 0 150,000 1.66

Sub Total 7848691 1414081 6434610 86.74

Vat (13% of non local costs) 836,499 0 836,499 9.24

Sub Total 8,685,190 1,414,081 7,271,109 95.98

Contingencies 5% of TPC 0 0 363,555 4.02

Total Project Cost Rs. 9,048,746 1,414,081 7,634,665 100.00

Power output kW 25

Cost per kW Rs. 361,950

Total Beneficial HH 259

Cost per HH 34,937

Non Local Cost per kW 305,387

4.4 Financial Mix

For the implementation of this MHS, major source of finance will be provided by REDP/AEPC

as a subsidy. The source of financial will be mobilized from as shown below.

Table 13: Mobilization of Resources

S.N. Sources Amount (Rs) Share (%) Remarks

1 GoN / Subsidy 3562500 39.85 (@125,000 per kW+ 500 x 35 x per

kW)

2 DDC Investment 452437 5.0 5 % of TPC

3 VDC Investment 904875 10.0 10 % of TPC

4 nec, CAROL and

individual students

investment 513353 5.67

5 Cash Collection

from community 2201500 24.33 @ Rs.8500/HH (Total 259 HH)

6 Community Equity 1414081 15.63 Local Costs

Total Source of Finance 9048746 100.00

Page 36: 173 Feasibility Study of Micro Hydro Power in Nepal

4.5 Annual Expenses

The total annual expenses are tabulated below.

4.6 Annual Incomes

The MHS FG will have to determine the tariff rate for the MHS, facilitated by the DDC: DEES.

Based on the investment required, annual expenses and other necessary provisions, tariff rate has

been proposed herewith but this might have to be revised regularly to incorporate the changes in

price and other relevant factors over time. Considering these, fixed tariff rate of Rs. 2 per watt

per month for domestic lighting and Rs. 8 per kWh for end-use activities have been proposed for

this scheme.

Table 16: Annual Income

Probable Business:

S.N. Type of Business Power

(kW)

Operating

Hours

Operating

Days

/Month

Operating

Months

/Year

Total

Energy

Consump

(kwh)

Tariff/kWh Total

Income Remarks

1 Agro-processing 8 10 26 12 24960 8 199680 One unit at

a time 2 Rural Carpentry 3 10 26 12 9360 8 74880

3 Computer Centre 2 8 26 12 4992 8 39936

4 Bakery 5 6 25 12 9000 8 72000

5 High vison Hall 3 6 24 12 5184 8 41472

Total: 21 53496 427968

427968

Household Lighting:

Page 37: 173 Feasibility Study of Micro Hydro Power in Nepal

S.N. No of Households Power

(kW)

Operating

Hours

Operating

Days

/Month

Operating

Months

/Year

Total

Energy

Consump

(kWh)

Tariff Total

Income Remarks

1 259 25 9 28 12 75600 2 600000

Total Electrical Income from Household Lighting(Ilit) =

600000

Total Electrical Income (Annual) Ie : (Iind+Ilit) =

1027968

Annual Energy Production Potential (kWh) =

201600

(336 days operation / year)

Productive End-uses (%) =

27

4.7 Financial Analysis

This section of the report presents the brief cost analysis of the proposed scheme. The cost

evaluation is undertaken to assess the economic viability (soundness) of the project. This will be

useful to judge the project from the developer's and financial institution's perspective. The

following parameters are considered for the cost analysis of the project.

- Capital Investment

- Construction Period

- Economic Life of the Project

- Running Cost Involved

- Revenues from the Project

The financial analysis of the scheme focuses on the source of funding for the project, annual

income, annual loss, and financial indicator of the project such as Net Present Value, Benefit

Cost Ratio, and Internal Rate of Return etc. The Financial Analysis Sheet has been attached in

Annex V (A). Main financial indicators are presented below.

NPV at 10% Rate = Rs. 1,120,955.00

IRR = 15 %

Pay Back Period = 6.06

Benefit Cost Ratio = 1.17

The depreciation of the scheme is calculated by straight-line depreciation method with subsidy

deducted (for project life of 15 years) will be Rs. 365, 750.00. The analysis has been done

considering total project cost deducting the subsidy amount to be the total investment amount.

Table 17: Annuity Payment Schedule

S.No. Description Amount, Rs Remarks

1 Annuity Payment (Rs) 322032 12 % annual Interest & loan maturity period is 5 years

Page 38: 173 Feasibility Study of Micro Hydro Power in Nepal

2 Depreciation (Rs) 365750 Straight line Calculation, (Total project cost - Subsidy) / 15

3 Recuring Annual Cost (Rs) 327862

4 Total Annual Cost (Rs) 1015644

5 Net Annual Profit (Rs) 12324 Total income - Total annual cost

6 Dividend to DDC (Rs) 616 5 % dividend as % of investment

7 Dividend to VDC (Rs) 1232 10 % dividend as % of investment

4.8 Economic Analysis

The economic analysis is carried out to assess the economic efficiency of the resources invested

in a project. As the scope of the economic benefit encompasses the welfare effect of all the

members of the society, the definition of cost and benefit is a bit different from the financial

analysis. The assessment of the efficiency can be done through the changes in the welfare of the

society, on the basis of costs and benefits brought about by the systems (MHS) to the society.

The present analysis is being carried out in that tune to assess the efficiency of the investment

made in the Lower Puwa Khola MHS.

4.8.1 Investment Cost

The total investment cost has been calculated after deducting all the applicable taxes from the

total project cost. In our case, no any taxes are charged so the total investment cost is calculated

as shown below.

Investment Cost = Total Project Cost - taxes/Duties

= Rs. 9, 048, 746.00 – 836, 499.00

= Rs. 8, 212, 247.00

4.8.2 Operation and Maintenance Cost

In terms of the cost for repair and maintenance, the usual practice is to take 3 % of the total

project cost.

Operation and Maintenance Cost = Repair and Maintenance Cost

= Rs. 271,462. 00

4.8.3 Economic Benefit

Page 39: 173 Feasibility Study of Micro Hydro Power in Nepal

The net benefit to all the individuals in the community brought about by a Micro Hydro scheme

is the economic benefit of the system. The net benefit to an individual can be accessed through

the aggregation of all the benefits and other costs incurred, apart from the cost of the system. As

the scope of economic benefit is broad, some assumptions have been made and only quantifiable

benefits are considered in order to make the assessment of the economic benefits of the proposed

MHS simple and precise. The economic benefits have been assessed based on the avoided cost of

diesel in case of supply for productive end uses, and the avoided cost of kerosene uses in case of

supply to households for lighting. Furthermore, the avoided cost of the dry cell battery use for

household purposes has also been taken into account.

Annual Saving from Kerosene Replacement

With the operation of the MH scheme, it is assumed that the electricity would replace nearly

86% of the kerosene being consumed. In this way average monthly kerosene consumption for

lighting would reduce from 3.5 lit/HH to 0.5 lit/HH, i.e. saving 3 lit/HH/month. Annual saving

from kerosene replacement

= Rs. 100/lit x 3 lit/HH x 259 HHs x 12 months

= Rs 932, 400.00

Annual Saving from Diesel Replacement

If it were assumed that a 10 HP diesel agro-processing mill will promoted in absence of the MHS

which would consume 1 lit/hr diesel, then amount of diesel that would be replaced by the

electrically driven agro-processing mill after promotion of the MHS would be around 1 lit/hr x 5

hrs/day x 330 days/year i.e. 1,200 liters/year. Thus annual saving due to diesel replacement

would be Rs. 110 x 2, 400 (at prevailing diesel rate of Rs. 110/lit) i.e. Rs. 1815, 000.00.

Annual Saving from Dry Cell Battery Replacement

Average battery consumption of the MHS area is 3.0 pair/HH/month (1.0 pair for lighting and 2

pair for radio, cassette etc.), the total battery replaced by the electricity would be 2.5

pair/HH/month. Annual saving from Cell replacement

= Rs. 50 x 2.5 pair/HH/month x 259 HHs x 12 months

= Rs. 388, 500.00

Therefore, total annual saving from kerosene, diesel and battery replacements

Page 40: 173 Feasibility Study of Micro Hydro Power in Nepal

= Rs. 1, 502, 400.00

4.8.4 Economical Indicators

With the calculation and assumptions mentioned in preceding topics, the economic analysis has

been carried out. The economic analysis spreadsheet is given in Annex VI (B).

NPV at 10% Rate = Rs. 453222.00

IRR = 11 %

Pay Back Period = 7.16

Page 41: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 5

OPERATION AND MANAGEMENT ASPECTS OF THE MHS

The success of a project depends on its operation and management. As the project itself is the

property of the local people, so it is the responsibility of the local people to look after the project.

Considerable benefits can be reaped from MHS if it is operated and managed properly. Neither

the entrepreneurs nor the consumers will gain from the MHS that is not operated and managed

properly. Prospective MHS entrepreneurs should bear in mind the aspects of operation and

management i.e. management of daily operations, availability of operators and resource

management.

5.1 Institutions

The ownership type of the MHS is community owned. Community Mobilization works is being

carried out by DDC: DEES, Ilaam based on the Community mobilization’s fundamental

principles.

The MHFG will be fully responsible for the operation and management of the MHS with

guidance from DDC: DEES. It is mandatory for the MHFG to create a Community Energy Fund

(CEF) for the mobilization of the resource from different partner organizations. The DDC: DEES

will release funds from the District Energy Fund (DEF) as grants to the CEF. And the CEF will

release funds to pay the electro-mechanical equipment and for materials for civil works and

others on approval of the MHFG and DDC: DEES. The management structure of the MHS will

be is as follows.

Lower Puwa Khola Micro Hydro Functional

Group

Micro Hydro Plant Manager Micro Hydro Plant Operator

Lower Puwa Khola Micro Hydro Management

Committee

Page 42: 173 Feasibility Study of Micro Hydro Power in Nepal

5.2 Skilled Manpower

Selection of the micro hydro operator and manager will be undertaken by the MHFG based on

technical aptitude and commitment to the community. The selected persons will make written

commitments to the community, that they will provide their services on along-term basis. The

manger and operators will assist the community mobilization works, scheme operation and

management after the training. Training will be provided to them by DEES. The manager and

operator will be responsible for the daily operation and management of the MHS.

Similarly local man power like unskilled labour, mason and carpenter are easily available at the

project area. Mostly they are within the MHS community.

5.3 Follow-up, Supervision and Reporting

The monitoring will be carried out regularly based on information collection, decision making

from follow-up and reports. The periodic reports and information received at different places and

different intervals will be reviewed and evaluated. The regular weekly, monthly and mass

meeting of COs, MHWC and MHFG ensure the transparency and consensus decisions among the

community members in participatory manner.

The MHFG will be responsible for procurement and construction of the system. It is mandatory

to hire a civil overseer to set out and supervise the construction of the work. Construction

progress records (including volunteer labor provided by each household) will be maintained by

the overseer, and release of fund for payment of the suppliers will be made only after DDC:

DEES have verified that quantities are correct, and construction quality is to acceptable standard.

And the completion of the project construction, generally auditing by registered auditor and

public audit among the community in the presence of representative of DDC, VDC and DDC:

DEES and other partner organizations will be conducted by the respective MHFG with in the

process of the DEES community mobilization procedure.

Similarly, the micro hydro operator and manger will report MHFG regularly on the status of the

MHS operation and management. And operational rules administered by the MHFG will provide

for connection condition, collection of tariffs, fines for late fee and disconnection for

nonpayment. The manger will be responsible for ensuring timely payment of electricity bills by

consumers and for dealing with tampering, theft, etc. Lists of defaulting consumers will be

announced at monthly MHFG meeting.

Page 43: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 6

ENVIRONMENTAL ANALYSIS

Generally, environmental problems in Nepal are the result of mismanagement of natural

resources evolved from the lack of integration of environmental considerations in the

development process. Integration of environmental assessment in the development of MH from

the planning stage helps identify possible adverse impacts and their mitigation measures to avoid

or minimize the adverse consequences in the micro level, which in the long run helps to make the

MH scheme cost effective as well sustainable. Realizing this, a separate EIA study of the project

has been conducted by DDC: DEES Ilaam and the report are presented as Vol. II of the DPR of

the Lower Puwa Khola MHS.

After implementation of the MHS, the social situations, community facilities, employment

opportunities, land price and markets for local produce will increase considerably. There will not be

considerable biological impacts such as effects on vegetation and forest resources, wild life, crops,

aquatic life etc. The implementation of the project will not cause significant physical impacts such

as floods, landslides, and deterioration of water and soil qualities. However, minor impacts such as

loss of some agriculture lands, cutting of some trees etc. will occur in the project area. Preventive

measures such as awareness creation and tree plantation are suggested to reduce potential adverse

impacts. Especially, micro watershed development and tree plantation are recommended in the

peripheral areas of the canal, intake, penstock alignment, overflow canal, tailrace canal etc.

In general, the MHS under consideration is small in magnitude and does not require a huge and

costly mitigation measures. The intake does not need huge excavation and cutting of trees. More

than 15% of the flow will be in the stream even in the driest season, which will help in preserving

the flora and aquatic life in the downstream areas. Similarly, the headrace canal is existing irrigation

canal and there is no any possibility of environmental imbalance even the same canal is used for

MHS.

As forebay area is located in the uncultivated land, the spill water from the forebay tank is proposed

to be diverted through spillway to the source stream. The spill water can also be used for irrigating

lands near the forebay area. Based on the site condition, there is no risk of erosion. The powerhouse

is located at the left bank of the Banakhu Khola. The tailrace canal section is constructed from

powerhouse to Puwa Khola, which follows the natural contour so that erosion due to constant

flow is less.

Page 44: 173 Feasibility Study of Micro Hydro Power in Nepal

There will not be heavy excavations and tree cuttings for civil constructions. Hence, there will not

be risk of flooding and erosion. The proposed powerhouse site is high enough than highest flood

level and hence there is no flood risk. The project needs about 376 wooden poles that are being

planned to be obtained from community forest of the areas. The MHFG is planning get the poles by

cutting old, unnecessary and fallen trees of the community forest. The cutting of trees will be as per

the approved work plan of the community forest and as per the District Forest Office regulations. In

this way, environmental implications of poles preparation will be minimized. Also to balance the

cutting of the trees, plantation will be carried out with support from the DEES and the DFO.

Thus, the project does not hamper any household in the project area and does not disturb significant

cultivated lands. As there is minimum of bushes and few trees in the project alignment, there will

not be cutting of trees in a massive scale. Since the excavations for the project is minimum, there is

no possibility of natural disturbances such as landslide, erosion and flooding. Furthermore, as per

the mitigation measures, DEES supports the Environment and Natural Resource Management

(ENRM) activities like nursery establishment, bioengineering works, tree, fruit and fodder

plantations, training to nursery naike, environment campaigns etc. in the project area. The DEES's

support for such activities for the project will be compensated by environmental benefits due to

replacements of kerosene and diesel, and other direct and indirect environmental and social benefits

in the project area.

Establishment of the MHS will certainly change the energy consumption pattern of the area.

Kerosene for lighting and diesel for running mills will be replaced and these will have additional

environmental advantages in terms of equivalent carbon replacement, which otherwise would

have polluted the atmosphere. As per the United Nations Frameworks on Convention of Climate

Change (UNFCCC) guidelines, environmental benefits due to replacement of kerosene by micro

hydro electricity are around 0.9 kg of carbon/kWh electricity consumed. Considering about only

35% plant factor, annual electricity consumption of the project area will be about 0.9 x 0.35 x 25

x 8,760 kg of carbon, i.e. about 68.99 ton of carbon annually. Similarly, if it is assumed that at

least a 10 HP diesel motor is required in the village in case of no electricity. Then economic

analysis show that about 1,200 lit. (1 x 5 hours/day x 330 days) of diesel will be replaced after

implementation of the MHS due to replacement of the diesel mill by the electric mill. With

carbon content of diesel at about 3216 kg per litre, total carbon avoided due to replacement of the

diesel mill by electric mill would be around 6.4 tons of carbon annually. These elaborations

clearly justify the environmental benefits of the proposed MHS.

Page 45: 173 Feasibility Study of Micro Hydro Power in Nepal
Page 46: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 7

SOCIAL (VULNERABLE COMMUNITY) ASPECTS OF THE MHS

Micro-hydro is generally a clean source of energy without adverse impact on the environment.

However, the sustainability of micro-hydro schemes depends much not only on technical,

management and financial aspects but on social aspects also. The past experience on

development suggests that people's access to public goods (such as water and other natural

resources) differs significantly depending on their social identity, in terms of caste, ethnicity and

gender and on their economic status and location (urban/rural/remote rural). Because policies

have been insensitive to the social realities of Nepal, certain groups have been excluded from the

mainstream of the development process. Therefore, it is essential to undertake social assessment

of proposed Micro Hydro power system (MHS) in order to assess existing social considerations

of the locality, determine possible impacts, plan mitigation measures and implement various

social development activities. The social assessment of the proposed MHS area revealed some

degree of social exclusion based on caste and ethnicity. It is recommended that serious attention

should be given their effective participation in the programme to include a specific focus on

social inclusion. In this regard, Vulnerable Community Development Study Report (VCDSR) of

the project has been conducted by DDC: DEES, Ilaam and the report are prepared as Vol. III of

the DPR of the Lower Puwa Khola MHS.

In line with the World Bank's Operational Directives (OD 4.2) that instructs Bank supported

operations to avoid or mitigate potentially adverse effects on VCs, the survey team met with a

number of VC groups and focus groups of the MHS beneficiaries to document any adverse

impacts experienced during community mobilization process and consulted with these groups on

their concerns about possible adverse impacts. During these consultations, focus group

discussions and individual interviews were carried out. Based on these discussions, the survey

team learned that the adverse impacts experienced about the MHS was mainly indirect and had

mostly to do with lack of cultural sensitivity. The team was also concerned that VC groups might

have less access to project benefits than local dominant caste groups.

The lands needed for canal construction and for constructing other civil structures are already

acquired by the concerned MHFG by consulting the landowners and through bilateral

negotiations and consensus mass decisions. All the concerned landowners are well off and not

many lands to be used for MH construction at present. And they have agreed to provide the lands

free of cost. The canal alignment, forebay structure and power house area lies in private land and

the owner is willing to provide the land on the name of the MHFG. Thus there is no issue related

to water right conflict and land acquisition at present and it's unlikely that any issue will arise in

future related to these. Moreover, the MHFG has been already initiated to register at the District

Page 47: 173 Feasibility Study of Micro Hydro Power in Nepal

Water Resource Committee, Ilaam in order to avoid the possible conflict regarding the use of

water in future, even though there is not any sign of conflict on water sharing practice at present.

The required collateral for bank loan process i.e. land certificate will be collected from elite

households in consensus decision and there is not any problem for other vulnerable communities

regarding this. The project requires cash contribution of about Rs. 1, 554, 000.00 @ 6,000 per

HH and ready to collect from the beneficiary household. The community will be strongly

encouraged to develop mechanisms to subsidize the contribution from the poor groups.

The provision of end use development with the MHS and internal saving and credit facilities in

the COs will help for economical upliftment of the community. Similarly, the programme will

have positive impacts on health and sanitation through environment awareness programme. All

including the VCs will encouraged to make, ICS, latrines and waste disposal site and the

provision of additional DEES subsidy for toilet attached biogas will be supportive for the

promotion of biogas in the MHS area.

It is observed that the VCs may need additional support to find creative ways to reduce the

dominance of the elite and encourage more democratic behavior in the MHFG/WC. The

successful implementation of VCs concerns activities will be performed by respective

community organizations with the help of support organization and the technical input of DDC:

DEES.

Page 48: 173 Feasibility Study of Micro Hydro Power in Nepal

Chapter 8

CONCLUSIONS AND RECOMMENDATIONS

From the preceding analyses and discussions, it is found out that the project is technically and

financially feasible. The implementation of the project will provide high quality lighting for

household purpose as well as reliable and environmentally safe power for end-use applications.

The MHS will help in saving of about 75.4 tons of carbon annually due to the replacement of

kerosene and diesel by micro hydro electricity.

As seen through the financial analysis, the NPV of the project is positive (10% rate, 15 years)

with Payback period of 6.06 years, B/C ratio of 1.17 and IRR being 15%. Similarly, economic

analyses of the project show that a positive NPV at 10% rate with payback Period of 7.16 years

and the EIRR 11%. Thus the project should be considered beneficial from all aspects viz.

financially, environmentally, socially and economically. The cost/kW of the proposed project is

about 361, 950.00.

The local people are very much positive towards the project and are ready to contribute from

their side. During installation, it is highly recommended to involve only experienced parties or

technicians. As DEES has rich institutional experiences in the field MH development, it is hoped

that they will also carry out the monitoring the site conditions and other probable implications of

the project implementation. The project is believed to be very successful with the assistance and

supervision of reputed organizations like DEES and the DDC: DEES.

Obviously, the socio-economical status of the village will be improved with the implementation

of the project. Presently used resources to mitigate the lighting energy demand will be replaced

by converting the water potential to electrical energy as discussed above. It will definitely reduce

forest product consumption. After implementation of the scheme, there will several end uses like

agro-processing mill, rural carpentry, bakery, computer and high vision hall etc and many more

installations, which will automatically make life easier.

Thus the project is feasible and recommended for its construction.

Page 49: 173 Feasibility Study of Micro Hydro Power in Nepal

REFERENCES

Micro Hydro Design Manual – Addm Harvey, 1983

Micro Hydro Sources Book – NRECS, 1986

National Environmental Impact Assessment Guidelines, NPC/IUCN, – 1992

Environmental Management Guidelines – REDP, 1997

Financial Guide Line – REDP, Nepal

For more details please contact

Mr. Vaibhav Pandey

Email: [email protected]

Contact no: +977-9849525011

Research coordinator

Centre for Advanced Research and Obligatory Learning, CAROL